JP2004151984A - Construction work management device - Google Patents

Construction work management device Download PDF

Info

Publication number
JP2004151984A
JP2004151984A JP2002316137A JP2002316137A JP2004151984A JP 2004151984 A JP2004151984 A JP 2004151984A JP 2002316137 A JP2002316137 A JP 2002316137A JP 2002316137 A JP2002316137 A JP 2002316137A JP 2004151984 A JP2004151984 A JP 2004151984A
Authority
JP
Japan
Prior art keywords
construction
model data
schedule
dimensional model
user
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2002316137A
Other languages
Japanese (ja)
Inventor
Takeshi Iwasaki
剛 岩崎
Takamaru Ishikawa
貴丸 石川
Kazuhide Momose
和英 百瀬
Shigenori Goto
慈徳 後藤
Yoichi Kayama
陽一 嘉山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JGC Corp
Original Assignee
JGC Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JGC Corp filed Critical JGC Corp
Priority to JP2002316137A priority Critical patent/JP2004151984A/en
Publication of JP2004151984A publication Critical patent/JP2004151984A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction work management device capable of carrying out visually graspable schedule management or progress condition management by using graphics. <P>SOLUTION: Schedule are stored in a project database 11, and the three-dimensional model data of a construction job site are stored so as to be connected to the respective items of the schedule. Also, the three-dimensional of a construction machine are stored in a construction machine database 12. When a user inputs a start date and an end date from a keyboard, the schedule from the inputted start date to end date and the three-dimensional model data of the construction job site connected to the schedule are read and displayed from the project database 11. Also, the three-dimensional model data of the construction machine designated by the user are read from the database 12, and simulation for carrying in or installing the construction machine in the construction job site is carried out. <P>COPYRIGHT: (C)2004,JPO

Description

【0001】
【発明の属する技術分野】
この発明は、建設工事のスケジュール管理、進捗状況管理または機器搬入、据え付けのシミュレーションを行う際に用いられる建設工事管理装置に関する。
【0002】
【従来の技術】
従来、建設工事のスケジュール管理や進捗状況管理は、紙に文字および数字によって書かれたスケジュール表や、テキストによってメモリ内に記憶されたスケジュール表をコンピュータ画面に表示することによって行われていた。しかし、このような従来の管理方法は、スケジュール等を一目見ただけで視覚的に把握するということが難しい欠点があった。また、工事に必要な仮設物や建設機械の図形を紙に表示することもできなくはなかったが、非常に手間がかかる問題があった。
【0003】
他方、従来の建設工事を管理する装置として、特許文献1および2に記載される装置が知られている。特許文献1に記載される装置は建設現場の所定の位置に機器を搬入または据え付ける建設計画のシミュレーションを行う装置である。しかし、この装置は、時間の概念を有していないため、スケジュール管理や進捗状況管理ができない欠点があった。また、特許文献2に記載される装置は、プラント等の大規模な建造物の建設工程管理を支援するシステムであり、工事シーケンスに基づき時間軸に沿った表示が可能である。しかし、この特許文献2の装置は建設工事のシミュレーションを行うことはできない。
【0004】
【特許文献1】
特開平10−280685号公報
【特許文献2】
特許第2721231号公報
【0005】
【発明が解決しようとする課題】
この発明は、このような事情を考慮してなされたもので、その目的は、図形を用いて視覚的に把握可能なスケジュール管理や進捗状況管理を行うことができる建設工事管理装置を提供することにある。また、この発明の他の目的は、スケジュールに合わせて機器搬入、据え付けのシミュレーションを行うことができる建設工事管理装置を提供することにある。
【0006】
【課題を解決するための手段】
この発明は上記の課題を解決するためになされたもので、請求項1に記載の発明は、図1に示すように、スケジュールが記憶されると共に、前記スケジュールの各項目に結合させて工事現場の3次元モデルデータが記憶された記憶部101と、ユーザが開始日および終了日を入力する入力手段102と、前記入力手段によって入力された開始日から終了日までのスケジュールおよびそのスケジュールに結合された工事現場の3次元モデルデータを前記記憶部から読み出し、表示部103へ出力する第1の制御手段104とを具備することを特徴とする建設工事管理装置である。
【0007】
請求項2に記載の発明は、請求項1に記載の建設工事管理装置において、ユーザによって入力された実際の工事日に関するデータを前記記憶部に書き込む書込手段と、ユーザが指定した日付けにおける実際の工事状況とスケジュールとを前記記憶手段から読み出し、表示部へ出力する第2の制御手段とを設けたことを特徴とする。
【0008】
請求項3に記載の発明は、図2に示すように、スケジュールが記憶されると共に、前記スケジュールの各項目に結合させて工事現場の3次元モデルデータが記憶され、さらに、建設機械の3次元モデルデータおよび搬入または据え付け対象機器の3次元モデルデータが記憶された記憶部111と、ユーザが各種のデータを入力する入力手段112と、ユーザによって指定された建設機械の3次元モデルデータおよびユーザによって指定された日付けにおける工事現場の3次元モデルデータを前記記憶部111から読み出し、表示部113に表示する制御手段114と、ユーザによって入力された搬入または据え付け対象機器の3次元モデルデータを前記工事現場のモデルデータ内に配置する配置手段115と、前記建設機械によって前記対象機器を前記工事現場に搬入または据え付けるシミュレーションを行うシミュレーション手段116とを具備することを特徴とする建設工事管理装置である。
【0009】
請求項4に記載の発明は、請求項3に記載の建設工事管理装置において、前記シミュレーション手段のよるシミュレーションの過程を記録するアニメーション手段を設けたことを特徴とする。
請求項5に記載の発明は、請求項1〜4のいずれかの項に記載の建設工事管理装置において、工事現場の設計図、建設機械の仕様書、搬入または据え付け対象機器の形状を示す機器図に基づいて、工事現場、建設機械、対象機器それぞれの3次元モデルデータを形成し、前記記憶部に記憶させるモデルデータ形成手段をさらに設けたことを特徴とする。
【0010】
請求項6に記載の発明は、コンピュータに、開始日および終了日を入力する入力手順と、前記入力手順によって入力された開始日から終了日までのスケジュールおよびそのスケジュールに結合された工事現場の3次元モデルデータを記憶部から読み出す読出手順と、読み出されたスケジュールおよび工事現場の3次元モデルデータを表示部に表示する表示手順とを実行させるためのプログラムを記録したコンピュータ読み取り可能な記憶媒体である。
【0011】
請求項7に記載の発明は、請求項1に記載のコンピュータ読み取り可能な記憶媒体に、ユーザによって入力された実際の工事日に関するデータを前記記憶部に書き込む書込手順と、ユーザが指定した日付けにおける実際の工事状況とスケジュールとを前記記憶手段から読み出し、表示部に表示する手順とをさらに設けたことを特徴とする。
【0012】
請求項8に記載の発明は、コンピュータに、ユーザが各種のデータを入力する入力手順と、ユーザによって指定された建設機械の3次元モデルデータおよびユーザによって指定された日付けにおける工事現場の3次元モデルデータを記憶部から読み出し、表示する表示手順と、ユーザによって入力された搬入または据え付け対象機器の3次元モデルデータを前記工事現場のモデルデータ内に配置する配置手順と、前記建設機械によって前記対象機器を前記工事現場に搬入または据え付けるシミュレーションを行うシミュレーション手順とを実行させるためのプログラムを記録したコンピュータ読み取り可能な記憶媒体である。
【0013】
請求項9に記載の発明は、請求項8に記載のコンピュータ読み取り可能な記憶媒体に、前記シミュレーション手順によるシミュレーションの過程を記録するアニメーション手順をさらに設けたことを特徴とする。
請求項10に記載の発明は、請求項6〜9のいずれかの項に記載のコンピュータ読み取り可能な記憶媒体に、工事現場の設計図、建設機械の仕様書、搬入または据え付け対象機器の形状を示す機器図に基づいて、工事現場、建設機械、対象機器それぞれの3次元モデルデータを形成し、前記記憶部に記憶させるモデルデータ形成手順をさらに設けたことを特徴とする。
【0014】
【発明の実施の形態】
以下、図面を参照し、この発明の一実施の形態について説明する。図3は同実施の形態による建設工事管理装置の機能構成を示す機能ブロック図である。この図において、PC−CAD(Personal Computer−Computer Aided Design)1は、工事現場等の2次元のCADデータが記憶されたプロットプラン記憶部2と、PDS(Plant Design System)モデルデータ記憶部3とからデータを読み込み、読み込んだデータに所定の加工を行って3次元モデルデータを形成し、プロジェクトデータベース11へ書き込む。また、工事において搬入および据え付け対象となる対象機器の形状等を示す機器図4、足場/仮設物設計図5および建設機械仕様書6からデータを読み込み、これらのデータに基づいて3次元シミュレーションに対応する3次元モデルデータを作成し、プロジェクトデータベース11および建設機械データベース12へ書き込む。これにより、搬入、据え付けの対象となる対象機器の形状の3次元モデルデータおよび既存施設や架構の形状等の建設現場に関する3次元モデルデータがプロジェクトデータベース11に書き込まれ、また、クレーン等の建設機械の形状の3次元モデルデータが建設機械データベース12に書き込まれる。
【0015】
符号8はスケジュールデータベースであり、これによって作成された建設工事のスケジュールがテキストデータによって記憶されている。
符号10は工事管理ユニットであり、上述したデータベース11、12と、プログラム記憶部14と、アニメーション録画ファイル15と、プログラム記憶部内のプログラムに従って処理を行うCPU(中央処理装置;図示略)と、入力用キーボード、ディスプレイ装置(共に図示略)から構成されている。この場合、プログラム記憶部14には、スケジュールデータベース8と、プロジェクトデータベース11および建設機械データベース12内の3次元モデルデータとをつなぎ合わせるプログラムと、それをFWBS(Functional Work Breakdown Structure:機能別作業分類)の定義を使用して分類するプログラムとが記憶されている。
【0016】
次に、上述した建設工事管理装置の動作を図4〜図7に示すフローチャートを参照して説明する。
(1)管理データベースの作成
管理データベースとは、スケジュール管理のためのデータベースであり、プロジェクトデータベース11の一部として作成される。プロジェクトデータベース11には、この管理データベースの他に3次元モデルデータのデータベースも含まれている。
図4は管理データベースの作成過程を示すフローチャートである。まず、スケジュールデータベース8にスケジュールデータが既に入力されているか否かを判断する(ステップSa1)。そして、入力されていない場合は、スケジュールデータをキーボードから直接入力する(ステップSa2)。入力されたデータはプロジェクトデータベース11に書き込まれる。また、スケジュールデータベース8にスケジュールデータが既に入力されていた場合は、そのスケジュールデータをプロジェクトデータベース11に取り込む(ステップSa3)。
【0017】
次に、PDSモデルデータ記憶部3に3次元モデルデータが用意されているか否かをチェックする(ステップSa4)。そして、用意されていた場合はそのモデルデータの加工を行い(ステップSa5)、次いで、3次元モデルデータをプロジェクトデータベース11に取り込む(ステップSa6)。また、モデルデータが用意されていなかった場合は、足場/仮設物設計図5、建設機械仕様書6および機器図4を取得し(ステップSa7)、取得した設計図および仕様書にに基づいて3次元モデルデータを作成し(ステップSa8)、作成したモデルデータをプロジェクトデータベース11に取り込む(ステップSa6)。
【0018】
次に、プロジェクトデータベース11内のスケジュールデータの各スケジュール項目とモデルデータとを結合させる。これは、FWBS毎にルール付けをする情報を持っており、そのルールをスケジュールの項目毎に指定することによって行う。
【0019】
(2)建設工事シミュレーション
図5は建設工事シミュレーションの過程を示すフローチャートである。ユーザがシミュレーションを行う日付けを入力すると、プロジェクトデータベース11からその日付けの現場状況が呼び出され、表示される(ステップSb1)。次に、ユーザが搬入、据え付けの対象となる対象機器を選択し、重量、重心の位置およびLiftng Lug(リフト用突起)の位置を設定する(ステップSb2)。次に、対象機器を現場状況の中に配置する(ステップSb3)。次に、作業半径を入力し、建設機械データベース12から建設機械を選定する(ステップSb4)。ここで、選定した建設機械がデータベース12内に設定されていなかった場合は(ステップSb5)、3次元モデルデータを作成し(ステップSb6)、建設機械データベース12に登録する(ステップSb7)。
【0020】
上記のステップSb4において選定した建設機械がデータベース12内に設定されていた場合は、その建設機械のモデルデータがデータベース12から読み出され、そのモデルデータおよび現場状況を示すモデルデータに基づいてシミュレーションが行われる。このシミュレーションにおいて、ステップSb4で入力された作業半径が確認されると共に、オーバーロード(過負荷)が確認される。そして、シミュレーションの結果、問題があった場合は建設機械の選定を再度行った後、再び、シミュレーションを行う。また、シミュレーションの結果、問題がなかった場合は、シミュレーションの過程をアニメーション録画ファイルに記録する(ステップSb9)。次に、作成されたアニメーションファイルをプロジェクトデータベース11に保存する(ステップSb10)。
【0021】
(3)スケジュールシミュレーション
図6はスケジュールシミュレーションの過程を示すフローチャートである。まず、ユーザは、表示画面にスケジュールシミュレーションの開始日および終了日を入力する(ステップSc1)。次に、ユーザは何日毎の間隔で表示させるかを指定する(ステップSc2)。この指定が行われると、静止画シミュレーションが行われる。すなわち、プロジェクトデータベース11から上記開始日〜終了日の間のスケジュールおよび各スケジュール項目に対応する工事現場の3次元モデルデータが読み出され、順次、文字および静止画によって表示される(ステップSc3)。ここで、表示されたスケジュールに問題があった場合は、ユーザがスケジュール調整を行う(ステップSc4)。そして、再び、ステップSc1〜Sc3の過程を繰り返し、シミュレーションを行う。この場合、スケジュール項目と工事現場の結合の状態やスケジュールの情報を変更することで、様々なケースをシミュレーションすることができる。
【0022】
また、スケジュールに問題がなかった場合は、そのまま終了してもよく、あるいは、動画シミュレーションを行ってもよい。動画シミュレーションを行う場合は、ユーザがキーボードおよびマウスによって動画シミュレーションを指示するキー操作を行うと、建設工事シミュレーションにおいて録画されたアニメーションがスケジュール上に並べられて時系列に沿って表示される(ステップSc5)。次に、ユーザがアニメーションファイルとスケジュール項目をつなぎ合わせる(ステップSc6)。次に、ユーザがアニメーションを表示する期間(最大2週間)を指定する。
【0023】
ユーザによって上記の指定が行われると、指定された終了日の現場状況がプロジェクトデータベース11から読み出され、表示される。また同時に、指定された期間に含まれるアニメーションファイルの一覧が表示される(ステップSc8)。次に、ユーザが、表示されたアニメーションを再生する長さと順序を決定する(ステップSc9)。以後、アニメーションファイルが再生され、動画シミュレーションが表示される(ステップSc10)。また、表示に問題がある場合は、再び、ユーザが、表示されたアニメーションを再生する長さと順序の決定を行う(ステップSc9)。
【0024】
(4)進捗状況管理
図7は進捗状況管理の過程を示すフローチャートである。ユーザは、実際に完了した工事日を各スケジュール項目に入力する(ステップSd1)。入力された工事日はプロジェクトデータベース11内に、スケジュール項目に対応して書き込まれる。次に、ユーザが比較したい時点の日付けを指定し(ステップSd2)、そして、実行ボタンを押す(ステップSd3)。実行ボタンが押されると、プロジェクトデータベース11から、指定した日付けにおけるスケジュールと実際の工事状況が読み出されて表示され、スケジュールと実際の工事状況との進捗差がハイライトされる(ステップSd4)。
【0025】
以上説明したように、この実施形態による建設工事管理装置によれば、工事計画におけるConstructability(施工性)の検討やスケジュールの検証のために3次元CADで作成された3次元モデルデータと簡易的に作成する3次元モデルデータを用いることによって、従来、紙の上で行ってきたこれらの検討をより効率的に、また、詳細に行うことができる。そして、このことが、施工計画の時間短縮、計画ミスに起因する追加コストに対するリスクの軽減という効果を得ることができる。
【0026】
また、これらのプロダクトは、電子データであるため、社内プロジェクト関係者との情報の共有が容易になり、従来に比較し工事シーケンスや工法に対する認識の統一に割く時間を短縮することができる。
また、このシステムを現場事務所にて運用し、これをサブコントラクタへの施工計画の説明に利用できることで、上記と同様に、サブコントラクタに対しても意志統一を迅速に行うことができ、ここでも時間短縮が期待できる。
また、客先への施工計画の説明やプレゼンテーションに利用することによって会社のプレゼンスを高め、他社との差別化を行うことができる。
【0027】
【発明の効果】
この発明によれば、図形によって視覚的にスケジュールや進捗状況を一目で把握することができる効果が得られる。また、この発明によれば、スケジュールの進行状況に合わせて機器搬入、据え付けのシミュレーションを行うことができる効果が得られる。
【図面の簡単な説明】
【図1】請求項1の発明の機能ブロック図である。
【図2】請求項3の発明の機能ブロック図である。
【図3】この発明の一実施形態による建設工事管理装置の構成を示す機能ブロック図である。
【図4】同実施形態における管理データベースの作成過程を示すフローチャートである。
【図5】同実施形態における建設工事シミュレーションの過程を示すフローチャートである。
【図6】同実施形態における進捗状況管理の過程を示すフローチャートである。
【図7】同実施形態における進捗状況管理の過程を示すフローチャートである。
【符号の説明】
1…PC−CAD
2…プロットプラン記憶部
3…PDSモデルデータ記憶部
4…機器図
5…足場/仮設物設計図
6…建設機械仕様書
8…スケジュールデータベース
10…工事管理ユニット
11…プロジェクトデータベース
12…建設機械データベース
14…プログラム記憶部
15…アニメーション録画ファイル
[0001]
TECHNICAL FIELD OF THE INVENTION
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction work management device used for performing a schedule management, a progress status management of a construction work, or a simulation of carrying in and installing a device.
[0002]
[Prior art]
2. Description of the Related Art Conventionally, schedule management and progress management of construction work have been performed by displaying a schedule table written in characters and numbers on paper or a schedule table stored in a memory in text on a computer screen. However, such a conventional management method has a disadvantage that it is difficult to visually grasp a schedule or the like at a glance. In addition, it was not impossible to display on a piece of paper the shapes of temporary works and construction machines required for the construction, but there was a problem that it was very troublesome.
[0003]
On the other hand, as devices for managing conventional construction work, devices described in Patent Documents 1 and 2 are known. The device described in Patent Literature 1 is a device that simulates a construction plan for carrying or installing equipment at a predetermined position on a construction site. However, since this device does not have the concept of time, there is a disadvantage that schedule management and progress status management cannot be performed. Further, the device described in Patent Document 2 is a system that supports construction process management of a large-scale building such as a plant, and can display along a time axis based on a construction sequence. However, the device of Patent Document 2 cannot simulate construction work.
[0004]
[Patent Document 1]
Japanese Patent Application Laid-Open No. 10-280687 [Patent Document 2]
Japanese Patent No. 27212231 [0005]
[Problems to be solved by the invention]
The present invention has been made in view of such circumstances, and an object thereof is to provide a construction work management device capable of performing schedule management and progress management that can be visually grasped using a graphic. It is in. It is another object of the present invention to provide a construction work management device capable of simulating loading and installation of equipment in accordance with a schedule.
[0006]
[Means for Solving the Problems]
SUMMARY OF THE INVENTION The present invention has been made to solve the above problems, and the invention according to claim 1 stores a schedule as shown in FIG. 1 and combines the schedule with each item of the schedule to construct a construction site. The storage unit 101 stores the three-dimensional model data, an input unit 102 for the user to input a start date and an end date, and a schedule from the start date to the end date input by the input unit and the schedule. A first control means for reading out the three-dimensional model data of the construction site from the storage unit and outputting the data to the display unit.
[0007]
According to a second aspect of the present invention, in the construction work management apparatus according to the first aspect, a writing unit that writes data on an actual construction date input by a user into the storage unit, Second control means for reading out the actual construction status and schedule from the storage means and outputting the readout data to the display unit is provided.
[0008]
According to a third aspect of the present invention, as shown in FIG. 2, a schedule is stored, and three-dimensional model data of a construction site is stored in association with each item of the schedule. A storage unit 111 in which model data and three-dimensional model data of equipment to be carried in or installed are stored, input means 112 for the user to input various data, and three-dimensional model data of the construction machine specified by the user and the user The control unit 114 reads out the three-dimensional model data of the construction site on the designated date from the storage unit 111 and displays the data on the display unit 113. The three-dimensional model data of the equipment to be carried in or installed, which is input by the user, is stored in the construction unit. Arranging means 115 for arranging the object in the model data of the site; A construction management apparatus characterized by comprising a simulation unit 116 for performing loading or installing a simulation on the construction site the vessel.
[0009]
According to a fourth aspect of the present invention, in the construction management apparatus according to the third aspect, animation means for recording a process of the simulation by the simulation means is provided.
According to a fifth aspect of the present invention, there is provided the construction management apparatus according to any one of the first to fourth aspects, wherein a device includes a design drawing of a construction site, a specification of a construction machine, and a shape of a device to be carried or installed. Model data forming means for forming three-dimensional model data for each of a construction site, a construction machine, and a target device based on the drawing and storing the model data in the storage unit is further provided.
[0010]
According to a sixth aspect of the present invention, there is provided an input procedure for inputting a start date and an end date to a computer, a schedule from the start date to the end date input by the input procedure, and a construction site combined with the schedule. A computer-readable storage medium storing a program for executing a reading procedure for reading the three-dimensional model data from the storage unit and a reading procedure for displaying the read schedule and the three-dimensional model data of the construction site on the display unit; is there.
[0011]
According to a seventh aspect of the present invention, there is provided a computer-readable storage medium according to the first aspect, further comprising a step of writing data relating to an actual construction date input by a user to the storage unit; The method further comprises a step of reading out the actual construction status and schedule in the attachment from the storage means and displaying the schedule on the display unit.
[0012]
According to an eighth aspect of the present invention, there is provided an input procedure in which a user inputs various data to a computer, three-dimensional model data of a construction machine specified by the user, and three-dimensional data of a construction site on a date specified by the user. A display procedure for reading and displaying the model data from the storage unit, an arrangement procedure for arranging the three-dimensional model data of the equipment to be carried in or installed, which is input by the user, in the model data of the construction site, And a computer-readable storage medium storing a program for executing a simulation procedure for carrying out or installing a device on the construction site.
[0013]
According to a ninth aspect of the present invention, the computer-readable storage medium according to the eighth aspect further includes an animation procedure for recording a simulation process according to the simulation procedure.
According to a tenth aspect of the present invention, a computer readable storage medium according to any one of the sixth to ninth aspects stores a design drawing of a construction site, a specification of a construction machine, and a shape of a device to be carried or installed. A three-dimensional model data for each of a construction site, a construction machine, and a target device is formed based on the device diagram shown, and a model data forming procedure for storing the model data in the storage unit is further provided.
[0014]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, an embodiment of the present invention will be described with reference to the drawings. FIG. 3 is a functional block diagram showing a functional configuration of the construction work management device according to the embodiment. In this figure, a PC-CAD (Personal Computer-Computer Aided Design) 1 includes a plot plan storage unit 2 in which two-dimensional CAD data such as a construction site is stored, a PDS (Plant Design System) model data storage unit 3 Then, data is read from the device, a predetermined process is performed on the read data to form three-dimensional model data, and the data is written to the project database 11. In addition, data is read from the equipment figure 4 showing the shape of the target equipment to be carried in and installed in the construction, the scaffold / temporary object design drawing 5, and the construction machine specification 6, and a 3D simulation is performed based on these data. 3D model data to be created is written to the project database 11 and the construction machine database 12. As a result, the three-dimensional model data of the shape of the target equipment to be carried in and installed and the three-dimensional model data of the construction site such as the shape of the existing facility and the frame are written in the project database 11 and the construction machine such as a crane Is written into the construction machine database 12.
[0015]
Reference numeral 8 denotes a schedule database in which the schedule of the construction work created by this is stored as text data.
Reference numeral 10 denotes a construction management unit, which includes the above-mentioned databases 11, 12, a program storage unit 14, an animation recording file 15, a CPU (Central Processing Unit; not shown) that performs processing according to a program in the program storage unit, and an input. And a display device (both not shown). In this case, the program storage unit 14 stores a program for connecting the schedule database 8 with the three-dimensional model data in the project database 11 and the construction machine database 12, and stores the program in FWBS (Functional Work Breakdown Structure: work classification by function). And a program that classifies using the definition.
[0016]
Next, the operation of the construction work management device described above will be described with reference to the flowcharts shown in FIGS.
(1) Creation of Management Database The management database is a database for schedule management, and is created as a part of the project database 11. The project database 11 includes a database of three-dimensional model data in addition to the management database.
FIG. 4 is a flowchart showing the process of creating the management database. First, it is determined whether schedule data has already been input to the schedule database 8 (step Sa1). If the schedule data has not been input, the schedule data is directly input from the keyboard (step Sa2). The input data is written to the project database 11. If the schedule data has already been input to the schedule database 8, the schedule data is loaded into the project database 11 (step Sa3).
[0017]
Next, it is checked whether three-dimensional model data is prepared in the PDS model data storage unit 3 (step Sa4). If the model data has been prepared, the model data is processed (step Sa5), and the three-dimensional model data is loaded into the project database 11 (step Sa6). If the model data has not been prepared, the scaffold / temporary object design drawing 5, the construction machine specification 6 and the equipment drawing 4 are acquired (step Sa7), and 3 based on the acquired design drawing and specification. The dimensional model data is created (step Sa8), and the created model data is loaded into the project database 11 (step Sa6).
[0018]
Next, each schedule item of the schedule data in the project database 11 is combined with the model data. This is done by having information for assigning a rule for each FWBS and designating the rule for each schedule item.
[0019]
(2) Construction Work Simulation FIG. 5 is a flowchart showing a process of the construction work simulation. When the user inputs a date for performing the simulation, the site situation for that date is called from the project database 11 and displayed (step Sb1). Next, the user selects a target device to be loaded and installed, and sets the weight, the position of the center of gravity, and the position of Liftng Lug (projection for lift) (step Sb2). Next, the target device is placed in the site situation (step Sb3). Next, a work radius is input, and a construction machine is selected from the construction machine database 12 (step Sb4). If the selected construction machine has not been set in the database 12 (step Sb5), three-dimensional model data is created (step Sb6) and registered in the construction machine database 12 (step Sb7).
[0020]
If the construction machine selected in step Sb4 is set in the database 12, the model data of the construction machine is read from the database 12, and a simulation is performed based on the model data and the model data indicating the site situation. Done. In this simulation, the work radius input in step Sb4 is confirmed, and an overload (overload) is confirmed. If there is a problem as a result of the simulation, the construction machine is selected again, and then the simulation is performed again. If there is no problem as a result of the simulation, the process of the simulation is recorded in the animation recording file (step Sb9). Next, the created animation file is stored in the project database 11 (step Sb10).
[0021]
(3) Schedule Simulation FIG. 6 is a flowchart showing the process of the schedule simulation. First, the user inputs a start date and an end date of the schedule simulation on the display screen (step Sc1). Next, the user specifies how many days should be displayed (step Sc2). When this designation is made, a still image simulation is performed. That is, the schedule between the start date and the end date and the three-dimensional model data of the construction site corresponding to each schedule item are read from the project database 11 and sequentially displayed as characters and still images (step Sc3). Here, if there is a problem with the displayed schedule, the user adjusts the schedule (step Sc4). Then, the process of steps Sc1 to Sc3 is repeated again to perform a simulation. In this case, various cases can be simulated by changing the state of the connection between the schedule item and the construction site and the information on the schedule.
[0022]
If there is no problem in the schedule, the process may be terminated as it is, or a moving image simulation may be performed. In the case of performing a moving image simulation, when a user performs a key operation for instructing a moving image simulation using a keyboard and a mouse, animations recorded in the construction work simulation are arranged on a schedule and displayed in chronological order (step Sc5). ). Next, the user connects the animation file and the schedule item (step Sc6). Next, the user specifies a period (up to two weeks) for displaying the animation.
[0023]
When the above specification is performed by the user, the site situation of the specified end date is read from the project database 11 and displayed. At the same time, a list of animation files included in the specified period is displayed (step Sc8). Next, the user determines the length and order in which the displayed animation is reproduced (step Sc9). Thereafter, the animation file is reproduced, and the moving image simulation is displayed (Step Sc10). If there is a problem with the display, the user again determines the length and order in which the displayed animation is reproduced (step Sc9).
[0024]
(4) Progress Status Management FIG. 7 is a flowchart showing the progress status management process. The user inputs the actually completed construction date into each schedule item (step Sd1). The input construction date is written in the project database 11 corresponding to the schedule item. Next, the user designates a date when comparison is desired (step Sd2), and then presses an execution button (step Sd3). When the execution button is pressed, the schedule and the actual construction status at the designated date are read from the project database 11 and displayed, and the progress difference between the schedule and the actual construction status is highlighted (step Sd4). .
[0025]
As described above, according to the construction work management apparatus according to the present embodiment, three-dimensional model data created by three-dimensional CAD for examining the constructability (workability) in the work plan and verifying the schedule can be simplified. By using the created three-dimensional model data, these studies that have been conventionally performed on paper can be performed more efficiently and in detail. This can provide the effect of shortening the time of the construction plan and reducing the risk for additional cost due to a planning mistake.
[0026]
In addition, since these products are electronic data, it is easy to share information with in-house project stakeholders, and it is possible to reduce the time required for unifying the recognition of the construction sequence and the construction method as compared with the related art.
In addition, since this system is operated at the site office and can be used to explain the construction plan for the sub-contractor, the will can be unified quickly for the sub-contractor, as described above. But you can expect to save time.
In addition, by using the information for explanation and presentation of the construction plan to the customer, the presence of the company can be enhanced and the company can be differentiated from other companies.
[0027]
【The invention's effect】
According to the present invention, it is possible to obtain the effect that the schedule and the progress can be visually grasped at a glance by the graphic. Further, according to the present invention, there is obtained an effect that a simulation of carrying in and installation of a device can be performed in accordance with the progress of a schedule.
[Brief description of the drawings]
FIG. 1 is a functional block diagram according to the first embodiment of the present invention;
FIG. 2 is a functional block diagram according to the invention of claim 3;
FIG. 3 is a functional block diagram showing a configuration of a construction work management device according to an embodiment of the present invention.
FIG. 4 is a flowchart showing a process of creating a management database in the embodiment.
FIG. 5 is a flowchart showing a process of a construction work simulation in the embodiment.
FIG. 6 is a flowchart showing a process of managing the progress in the embodiment.
FIG. 7 is a flowchart showing a progress management process in the embodiment.
[Explanation of symbols]
1: PC-CAD
2 Plot plan storage unit 3 PDS model data storage unit 4 Equipment diagram 5 Scaffold / temporary object design drawing 6 Construction machine specifications 8 Schedule database 10 Construction management unit 11 Project database 12 Construction machine database 14 … Program storage unit 15… Animation recording file

Claims (10)

スケジュールが記憶されると共に、前記スケジュールの各項目に結合させて工事現場の3次元モデルデータが記憶された記憶部と、
ユーザが開始日および終了日を入力する入力手段と、
前記入力手段によって入力された開始日から終了日までのスケジュールおよびそのスケジュールに結合された工事現場の3次元モデルデータを前記記憶部から読み出し、表示部へ出力する第1の制御手段と、
を具備することを特徴とする建設工事管理装置。
A storage unit in which a schedule is stored, and in which three-dimensional model data of the construction site is stored in association with each item of the schedule;
An input means for a user to input a start date and an end date;
First control means for reading the schedule from the start date to the end date input by the input means and the three-dimensional model data of the construction site combined with the schedule from the storage unit, and outputting the read data to the display unit;
A construction work management device, comprising:
ユーザによって入力された実際の工事日に関するデータを前記記憶部に書き込む書込手段と、
ユーザが指定した日付けにおける実際の工事状況とスケジュールとを前記記憶手段から読み出し、表示部へ出力する第2の制御手段と、
を設けたことを特徴とする請求項1に記載の建設工事管理装置。
Writing means for writing data on the actual construction date input by the user into the storage unit;
Second control means for reading out the actual construction status and schedule at the date designated by the user from the storage means and outputting the readout to the display unit;
The construction work management device according to claim 1, further comprising:
スケジュールが記憶されると共に、前記スケジュールの各項目に結合させて工事現場の3次元モデルデータが記憶され、さらに、建設機械の3次元モデルデータおよび搬入または据え付け対象機器の3次元モデルデータが記憶された記憶部と、
ユーザが各種のデータを入力する入力手段と、
ユーザによって指定された建設機械の3次元モデルデータおよびユーザによって指定された日付けにおける工事現場の3次元モデルデータを前記記憶部から読み出し、表示部に表示する制御手段と、
ユーザによって入力された搬入または据え付け対象機器の3次元モデルデータを前記工事現場のモデルデータ内に配置する配置手段と、
前記建設機械によって前記対象機器を前記工事現場に搬入または据え付けるシミュレーションを行うシミュレーション手段と、
を具備することを特徴とする建設工事管理装置。
A schedule is stored, three-dimensional model data of a construction site is stored in association with each item of the schedule, and three-dimensional model data of a construction machine and three-dimensional model data of a device to be carried in or installed are stored. Storage unit,
Input means for the user to input various data;
Control means for reading out the three-dimensional model data of the construction machine specified by the user and the three-dimensional model data of the construction site on the date specified by the user from the storage unit and displaying the data on the display unit;
Arranging means for arranging the three-dimensional model data of the equipment to be carried in or installed inputted by the user in the model data of the construction site;
Simulation means for performing a simulation of loading or installing the target device on the construction site by the construction machine,
A construction work management device, comprising:
前記シミュレーション手段のよるシミュレーションの過程を記録するアニメーション手段を設けたことを特徴とする請求項3に記載の建設工事管理装置。The construction work management apparatus according to claim 3, further comprising animation means for recording a process of the simulation by said simulation means. 工事現場の設計図、建設機械の仕様書、搬入または据え付け対象機器の形状を示す機器図に基づいて、工事現場、建設機械、対象機器それぞれの3次元モデルデータを形成し、前記記憶部に記憶させるモデルデータ形成手段をさらに設けたことを特徴とする請求項1〜4のいずれかの項に記載の建設工事管理装置。3D model data of the construction site, the construction machine, and the target device are formed based on the design drawing of the construction site, the specification of the construction machine, and the device drawing showing the shape of the device to be carried or installed, and stored in the storage unit. The construction work management device according to claim 1, further comprising a model data forming unit that causes the model data to be created. コンピュータに、
開始日および終了日を入力する入力手順と、
前記入力手順によって入力された開始日から終了日までのスケジュールおよびそのスケジュールに結合された工事現場の3次元モデルデータを記憶部から読み出す読出手順と、
読み出されたスケジュールおよび工事現場の3次元モデルデータを表示部に表示する表示手順と、
を実行させるためのプログラムを記録したコンピュータ読み取り可能な記憶媒体。
On the computer,
Input procedure for inputting start date and end date,
A readout procedure for reading out a schedule from the start date to the end date input by the input procedure and the three-dimensional model data of the construction site combined with the schedule from the storage unit;
A display procedure for displaying the read schedule and the three-dimensional model data of the construction site on a display unit;
Computer-readable storage medium storing a program for executing the program.
ユーザによって入力された実際の工事日に関するデータを前記記憶部に書き込む書込手順と、
ユーザが指定した日付けにおける実際の工事状況とスケジュールとを前記記憶手段から読み出し、表示部に表示する手順と、
をさらに設けたことを特徴とする請求項1に記載のコンピュータ読み取り可能な記憶媒体。
A writing procedure for writing data regarding the actual construction date input by the user into the storage unit;
Reading the actual construction status and schedule at the date specified by the user from the storage means, and displaying the schedule on the display unit;
The computer-readable storage medium according to claim 1, further comprising:
コンピュータに、
ユーザが各種のデータを入力する入力手順と、
ユーザによって指定された建設機械の3次元モデルデータおよびユーザによって指定された日付けにおける工事現場の3次元モデルデータを記憶部から読み出し、表示する表示手順と、
ユーザによって入力された搬入または据え付け対象機器の3次元モデルデータを前記工事現場のモデルデータ内に配置する配置手順と、
前記建設機械によって前記対象機器を前記工事現場に搬入または据え付けるシミュレーションを行うシミュレーション手順と、
を実行させるためのプログラムを記録したコンピュータ読み取り可能な記憶媒体。
On the computer,
An input procedure in which the user inputs various data;
A display procedure for reading and displaying the three-dimensional model data of the construction machine specified by the user and the three-dimensional model data of the construction site on the date specified by the user from the storage unit;
An arrangement procedure for arranging the three-dimensional model data of the equipment to be carried in or installed, which is input by the user, in the model data of the construction site;
A simulation procedure of performing a simulation of loading or installing the target device on the construction site by the construction machine,
Computer-readable storage medium storing a program for executing the program.
前記シミュレーション手順によるシミュレーションの過程を記録するアニメーション手順をさらに設けたことを特徴とする請求項8に記載のコンピュータ読み取り可能な記憶媒体。The computer-readable storage medium according to claim 8, further comprising an animation procedure for recording a simulation process according to the simulation procedure. 工事現場の設計図、建設機械の仕様書、搬入または据え付け対象機器の形状を示す機器図に基づいて、工事現場、建設機械、対象機器それぞれの3次元モデルデータを形成し、前記記憶部に記憶させるモデルデータ形成手順をさらに設けたことを特徴とする請求項6〜9のいずれかの項に記載のコンピュータ読み取り可能な記憶媒体。3D model data of the construction site, the construction machine, and the target device are formed based on the design drawing of the construction site, the specification of the construction machine, and the device drawing showing the shape of the device to be carried or installed, and stored in the storage unit. The computer-readable storage medium according to any one of claims 6 to 9, further comprising a model data forming procedure for causing the computer-readable storage medium.
JP2002316137A 2002-10-30 2002-10-30 Construction work management device Pending JP2004151984A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002316137A JP2004151984A (en) 2002-10-30 2002-10-30 Construction work management device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002316137A JP2004151984A (en) 2002-10-30 2002-10-30 Construction work management device

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2008325623A Division JP5000630B2 (en) 2008-12-22 2008-12-22 Construction management method

Publications (1)

Publication Number Publication Date
JP2004151984A true JP2004151984A (en) 2004-05-27

Family

ID=32459928

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002316137A Pending JP2004151984A (en) 2002-10-30 2002-10-30 Construction work management device

Country Status (1)

Country Link
JP (1) JP2004151984A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006024073A (en) * 2004-07-09 2006-01-26 Hitachi Plant Eng & Constr Co Ltd Construction plan expression method, construction plan expression system, and method for displaying object involving shape change
JP2009169777A (en) * 2008-01-18 2009-07-30 Hitachi-Ge Nuclear Energy Ltd Operation-simulating system for plant construction
JP2010108321A (en) * 2008-10-31 2010-05-13 Hitachi-Ge Nuclear Energy Ltd Construction progress visualization system
KR101062211B1 (en) 2008-08-07 2011-09-05 에스케이건설 주식회사 Tunnel and underground space construction simulation system and method considering geological conditions

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04264583A (en) * 1991-02-20 1992-09-21 Amada Metrecs Co Ltd Plant simulation showroom
JPH09268760A (en) * 1996-03-28 1997-10-14 Shimizu Corp Schedule control support system
JPH10140832A (en) * 1996-11-15 1998-05-26 Ohbayashi Corp Installation plan preparing device of precast concrete long structure
JP2001249985A (en) * 1999-12-27 2001-09-14 Ohbayashi Corp Execution plan supporting system, execution plan supporting method, and recording medium recorded with computer program for realizing execution plan supporting system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04264583A (en) * 1991-02-20 1992-09-21 Amada Metrecs Co Ltd Plant simulation showroom
JPH09268760A (en) * 1996-03-28 1997-10-14 Shimizu Corp Schedule control support system
JPH10140832A (en) * 1996-11-15 1998-05-26 Ohbayashi Corp Installation plan preparing device of precast concrete long structure
JP2001249985A (en) * 1999-12-27 2001-09-14 Ohbayashi Corp Execution plan supporting system, execution plan supporting method, and recording medium recorded with computer program for realizing execution plan supporting system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006024073A (en) * 2004-07-09 2006-01-26 Hitachi Plant Eng & Constr Co Ltd Construction plan expression method, construction plan expression system, and method for displaying object involving shape change
JP2009169777A (en) * 2008-01-18 2009-07-30 Hitachi-Ge Nuclear Energy Ltd Operation-simulating system for plant construction
JP4672028B2 (en) * 2008-01-18 2011-04-20 日立Geニュークリア・エナジー株式会社 Work simulation system for plant construction
US8095346B2 (en) 2008-01-18 2012-01-10 Hitachi-Ge Nuclear Energy, Ltd. Operation simulation system for plant construction
KR101062211B1 (en) 2008-08-07 2011-09-05 에스케이건설 주식회사 Tunnel and underground space construction simulation system and method considering geological conditions
JP2010108321A (en) * 2008-10-31 2010-05-13 Hitachi-Ge Nuclear Energy Ltd Construction progress visualization system

Similar Documents

Publication Publication Date Title
JP5734902B2 (en) Construction process management system and management method thereof
JP2008046703A (en) Data cooperation system, and method and program for controlling the same
JP3056297B2 (en) Drawing information processing system, design support method
JP2013120396A (en) Manufacturing line simulation device, data input support device and data input support method
EP1930827A1 (en) CAD apparatus, method of editing graphic data, and computer product
EP2083393A2 (en) Image processing apparatus, image processing method, and storage medium storing a program for causing an image processing apparatus to execute an image processing method
JP5000630B2 (en) Construction management method
JP2004151984A (en) Construction work management device
JP5667911B2 (en) Material information management system
US7055141B2 (en) Humanity interface development system of testing program of circuit board
JP5386237B2 (en) Material information management system
JP2002163003A (en) Device and method for preparing control program, and recording medium
JPH06187396A (en) Network constitution design aid system
JP2012103804A (en) Location planning device and location planning method
JP6979274B2 (en) Work schedule range visualization device and work schedule range visualization method
Pascarelli et al. CAD-VR integration as a tool for industrial assembly processes validation: a practical application
JP2002117100A (en) Support method for planning and managing work progress
JP4411585B2 (en) Analysis device
JP2004005275A (en) Manufacturing supporting program
JP2009175936A (en) Drawing support device, drawing support program and drawing support method
JP2006146369A (en) Parameter setting support device, its control method and program
JP3737646B2 (en) Two-dimensional figure arrangement device and recording medium
JPH03100407A (en) Measuring network system
JPH10187771A (en) Device and method for analytic model generation
JP2004280271A (en) Graphic processor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050812

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080206

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080219

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080421

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20081021

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20090120