JP2004131923A - Extracting method for existing underground structure - Google Patents
Extracting method for existing underground structure Download PDFInfo
- Publication number
- JP2004131923A JP2004131923A JP2002262284A JP2002262284A JP2004131923A JP 2004131923 A JP2004131923 A JP 2004131923A JP 2002262284 A JP2002262284 A JP 2002262284A JP 2002262284 A JP2002262284 A JP 2002262284A JP 2004131923 A JP2004131923 A JP 2004131923A
- Authority
- JP
- Japan
- Prior art keywords
- existing structure
- casing
- lowermost end
- ground
- existing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
この発明は、地中の埋設された既設構造物を地盤から引き抜く引抜工法に関するものである。
【0002】
【従来の技術】
各種建造物の建築、構築を行う場合には地盤整備を行う必要がある。その一環として、コンクリート杭などのコンクリート構造物、鋼製杭などの鋼製構造物、木製杭などの木製構造物、その他の地中深く埋設されたまた残存している構造物(以下、これらの構造物を総称して「既設構造物」という)を引き抜く引抜作業が実行される。従来、この引抜作業は次のようにして行っていた。まず、既設構造物を包むようにケーシング(鋼管)を差し込み、ケーシングと既設構造物との間の土砂を除去する。そして、既設構造物をクレーン等の重機機械で吊上げて既設構造物の引き抜きを実行していた。
【0003】
【発明が解決しようとする課題】
しかしながら、従来工法では、重機機械の吊上げ力のみを利用して既設構造物の引抜を実行しているため、既設構造物の大型化に伴い、重機機械に要求される吊上能力も高くなり、大型の重機機械が必要となる。その結果、施工効率や施工コストの面で改善の余地が大きく残されていた。
【0004】
この発明は上記課題に鑑みなされたものであり、優れた施工効率で、しかも低コストで地盤から既設構造物を引き抜く引抜工法を提供することを目的とする。
【0005】
【課題を解決するための手段】
この発明は、地中の埋設された既設構造物を引き抜く引抜工法であって、上記目的を達成するため、既設構造物の最下端に繋がる削孔を既設構造物に形成する第1工程と、削孔を介して既設構造物の最下端に向けて水を送給して既設構造物に対して浮力を与える第2工程と、既設構造物に対して浮力を与えた状態のまま既設構造物を吊り上げる第3工程とを備えている。
【0006】
このように構成された発明では、既設構造物の最下端に繋がる削孔を既設構造物に形成した後、その削孔を介して既設構造物の最下端に向けて水を送給する。これによって、既設構造物の最下端から吐出される水の一部が既設構造物の外周側面に沿って地盤表面側に流れ、その水の存在により既設構造物に対して浮力が作用する。そして、この浮力が作用する状態で既設構造物を吊り上げて地盤から既設構造物を引き抜く。このように浮力を利用することで既設構造物の引抜に必要な吊上げ力を低減することが可能となる。
【0007】
ここで、既設構造物の最下端に向けて水を送給する前に、予め既設構造物を囲むようにケーシングを地盤に回転推進してケーシングの先端部を既設構造物の最下端以上の深さに到達させるように構成してもよい。この場合、既設構造物の最下端に向けて水を送給すると、既設構造物の最下端の下方に位置する地盤(土砂など)が給水により押し流されるとともに、ケーシング内が水で満たされる。つまり、既設構造物が貯水されたケーシング内に存在することとなり、既設構造物に対して浮力が作用する。このように、既設構造物の最下端から吐出される水が効率良くケーシング内を流れ、少ない水量で既設構造物の対して浮力を確実に与えることができる。
【0008】
また、第2工程前に、複数の鋼片を既設構造物の最下端の下方に位置させると、既設構造物の最下端から吐出される水が地盤に浸み込むのを効果的に防止し、水の利用効率をさらに高めることができる。また、複数の鋼片を用いることなく、施工効率を高めるために給水時の水圧を高めた場合、既設構造物の最下端の下方に位置する地盤をさらに深く掘り下げてしまうが、上記のように複数の鋼片を設けることで圧送されてきた水による地盤の掘り下げを防止することができる。
【0009】
さらに、地盤表面の上方位置で既設構造物に補助部材を取り付け、既設構造物の引抜の際(第3工程)に、既設構造物の引抜方向とほぼ平行な方向に補助部材を押し上げるように構成すれば、その押上力が既設構造物の引抜力となり、吊上げ力をさらに低減することができる。
【0010】
【発明の実施の形態】
図1および図2は、この発明にかかる地中既設構造物の引抜工法の一実施形態を示す図である。この引抜工法では、図1(a)に示すように、大径管の下端円周に削孔用チップ1を備えたケーシング2が既設構造物3の周面を取り囲むようにケーシング2を地盤表面に設置した後、駆動機構4を作動させることでケーシング2を地盤5に対して回転推進してその全長に亙り削孔して、既設構造物3と地盤5の縁を切っていく。なお、この実施形態では、内面チップ(図示省略)をケーシング2の内面の該ケーシング2の内径よりも設定寸法小径の想定円周線上に設けることでケーシング2内周面と既設構造物3との間に設定寸法のギャップ6を形成している。
【0011】
そして、同図(b)に示すように、ケーシング2の最下端、つまり削孔用チップ1が既設構造物3の最下端以上の深さに到達すると、ケーシング2の回転推進を停止する。そして、既設構造物3の中心軸を通過するように既設構造物3の最上端から最下端に繋がる削孔7を既設構造物3に形成する。なお、ここでは、削孔7を中心軸に沿って形成しているが、その中心軸からずれて削孔7を形成してもよく、また既設構造物3の側面から最下端に繋がるように削孔7を形成するようにしてもよい。この点に関しては、後の実施形態においても全く同様である。なお、同図中の符号8はワイヤであり、既設構造物3の上部に取り付けられ、クレーン等の重機機械により既設構造物3を吊上げ可能となっている。
【0012】
次に、図2(a)に示すように、ジェットポンプ9および一時回収タンク10をそれぞれ削孔7およびケーシング2に配管接続する。すなわち、上記のようにして形成された削孔7の最上端に対して給水用配管の一方端を接続するとともに、その給水用配管の他方端をジェットポンプ9の吐出口と接続する。また、ケーシング2の上端側でケーシング2の中空空間に排水用配管の一方端を連通接続するとともに、その排水用配管の他方端を一時回収タンク10に接続する。
【0013】
各配管接続が完了すると、ジェットポンプ9を作動させてジェットポンプ9から高圧水を削孔7に向けて給水する。すると、この高圧水は削孔7を介して既設構造物3の最下端に向けて圧送され、この最下端から吐出された水は、その最下端と接する地盤の土砂5a(図1(b))をギャップ6側に押し流す。そして、水を連続的に給水し続けると、該ギャップ6にも給水されてケーシング2の内部に水が溜まるとともに、オーバーフローする水については排水用配管を介して一時回収タンク10に回収される。なお、回収された土砂を含む水については、そのまま放流したり、土砂を分離した後で放流することができる。もちろん、水については必要に応じて循環的に利用するようにしてもよい。
【0014】
このようにケーシング2内に水を供給することでケーシング2内で既設構造物3が浸水状態で吊持された状態となり、その既設構造物3に対して浮力が作用する。そして、図2(b)に示すように、この浮力を受けた状態のままクレーンなどの重機機械をオペレータが操作してワイヤ8により既設構造物3を上方向(引抜方向)に吊上げ、地盤5から引き抜く。このとき、ジェットポンプ9から水を連続的に供給し続けるのが望ましいが、引抜途中で給水を停止するようにしてもよい。
【0015】
そして、引抜が完了すると、ジェットポンプ9を完全に停止させた後、既設構造物3を引き抜いた跡孔を貧配合モルタル、土、砂などで埋め戻した後、ケーシングをクレーンやワイヤ等で地上に引き抜き、工事を完了する。
【0016】
以上のように、この実施形態では、既設構造物3の最下端に繋がる削孔7を既設構造物3に形成した後、その削孔7を介して既設構造物3の最下端に向けて水を送給してケーシング2内を水で満たす。これによって、既設構造物は地盤5から完全に切り離され、しかもケーシング2内で浸水状態で存在している。したがって、既設構造物3に対して浮力が作用することとなり、既設構造物3を吊り上げて地盤から既設構造物3を引き抜く際に、その浮力分だけ既設構造物3の引抜に必要な吊上げ力を低減させることが可能となる。その結果、従来工法で使用していた重機機械に比べて吊上能力の低い重機機械を用いて既設構造物を引き抜くことができるようになり、施工効率を向上させるとともに、施工コストを抑制することができる。
【0017】
また、既設構造物3はその側面だけではなく、その最下端面も地盤5と縁が切れた状態で引き抜かれるため、効率的な引抜作業を行うことができる。
【0018】
また、既設構造物3の最下端から吐出される水はケーシング2内に導かれ、ギャップ6に沿って地盤表面側に流れるため、既設構造物の最下端から吐出される水が効率良くケーシング内に流れ、既設構造物3の対して浮力を確実に与えることができる。
【0019】
なお、本発明は上記した実施形態に限定されるものではなく、その趣旨を逸脱しない限りにおいて上述したもの以外に種々の変更を行うことが可能である。例えば、上記実施形態では、浮力と吊上げ力とを用いて既設構造物3を引き抜いているが、さらに図3に示すように、油圧シリンダなどのアクチュエータによる押上力を付加させることで吊上げ力をさらに低減させることができる。
【0020】
図3は、この発明にかかる地中既設構造物の引抜工法の他の実施形態を示す図である。この引抜工法では、既設構造物3の上端部に鋼管11の下端部を連結する。例えば既設構造物3がコンクリート製である場合には既設構造物3中に杭補強筋が設けられているため、その杭補強筋と鋼管11とを溶接により連結する。また、既設構造物3が鋼製杭である場合には杭本体を鋼管11と直接溶接して連結する。そして、鋼管11の上端部に引抜方向(同図の上下方向)とほぼ直交する方向に鋼製梁部材12を溶接などの連結方法により連結する。これにより、地盤表面の上方位置で鋼管11および鋼製梁部材12よりなる補助部材が既設構造物3に取り付けられる。
【0021】
そして、ケーシング2の上端部と梁部材12との間に油圧ジャッキなどのアクチュエータ13が複数本配置されており、それらのアクチュエータ13を作動させることで既設構造物の引抜方向(上方向)とほぼ平行な方向に補助部材(鋼管11および鋼製梁部材12)を押し上げ、その結果、既設構造物3に対して引抜方向への押上力を加えることが可能となっている。したがって、クレーンなどの重機機械を操作してワイヤ8により既設構造物3を吊上げ、地盤5から引き抜く際、それと同時にアクチュエータ13のロッド13aを伸張させることで、その押上力分だけ既設構造物3の引抜に必要な吊上げ力を低減させることが可能となる。したがって、さらに一段と低い吊上げ能力の重機機械を用いて既設構造物の引抜が可能となり、施工効率を向上させるとともに、施工コストを抑制することができる。なお、油圧シリンダなどのアクチュエータ13の本数や配設位置については特に限定されるものではない。
【0022】
また、上記実施形態では、ケーシング2を所定深さまで回転推進させた後、そのままの状態で削孔7を介して水を給水して既設構造物3の最下端から水を吐出しているが、図4に示すように、複数の鋼片21を既設構造物3の最下端の下方に位置させるようにしてもよく、こうすることで次のような作用効果が得られる。
【0023】
図4は、この発明にかかる地中既設構造物の引抜工法の別の実施形態を示す図である。この実施形態では、同図に示すように、ケーシング2内周面と既設構造物3との間のギャップ6に2つの鋼片21が回動軸22回りに回動自在に軸支されている。各鋼片21は略スコップ形状を有しており、ケーシング2の下端近傍に配置された状態で油圧シリンダのロッド23を伸張させると、回動軸22回りにそれぞれ相反する方向に回動して既設構造物3の最下端の下方に位置し、既設構造物3の最下端面を覆うこととなる(同図(b))。この状態でジェットポンプ9を作動させてジェットポンプ9から高圧水を削孔7に向けて給水すると、既設構造物3の最下端から高圧水が吐出されるが、その高圧水の大部分は複数の鋼片21によりギャップ6側に導かれる。このため、給水が地盤5に浸み込むのを効果的に防止し、水の効率的な利用を図ることができる。
【0024】
また、上記実施形態ではジェットポンプ9から高圧水を給水する、つまり施工効率を高めるために給水時の水圧を高めているが、図1ないし図3に示すように削孔7から高圧水を地盤の土砂5a(図1(b))に向けて吐出すると、単に土砂5aを押し流すのみならず、さらに地盤5をさらに深く掘り下げてしまうが、上記のように複数の鋼片21を設けることで圧送されてきた水による地盤5の掘り下げを防止することができる。したがって、作業効率の面でも有利なものとなる。
【0025】
また、上記実施形態では、既設構造物3を一度に地盤5から引き抜いているが、引抜方向(各図の上下方向)における既設構造物3の大きさによっては一度に地盤5から引き抜くのが困難な場合がある。その場合には、図5に示すように適当な位置まで引き抜いた後、既設構造物3を例えば仮想切断線(図5(a)中の1点鎖線)に沿って切断し、さらに上記実施形態と同様の引抜作業を繰り返すようにすればよい。このとき、切断された既設構造物3のうち上方部分についてはクレーンなどの重機機械で吊持されているが、切断とともに下方部分については吊持が解除されてケーシング2内に落下してしまう。そこで、このような問題に対応すべく、図5に示す実施形態では、たとえクレーンなどの重機機械により吊持されていなくとも既設構造物3がケーシング2内に落下するのを防止する落下防止機構を設けている。
【0026】
図5は、この発明にかかる地中既設構造物の引抜工法のさらに別の実施形態を示す図である。この実施形態では、ケーシング2の内壁面2aには、落下防止機構30が4個、しかも同図(b)に示すように平面視において等角度間隔で設けられている。なお、落下防止機構30の配設数については、これに限定されず、3個以上設けることで後述するようにして既設構造物3の落下を確実に防止することができる。
【0027】
各落下防止機構30は、同図(c)に示すように、ケーシング2の内周面に取り付けられる本体部31と、その本体部31に対して回動軸32回りに回動自在に軸支された可動部33と、可動部33が所定角度以上移動するのを阻止するストッパー34とを備えている。すなわち、各落下防止機構30では、可動部33の後端部がケーシング2の内壁面2aに対して回動軸32回りに0゜から約60゜の範囲で回動可能であり、その先端部は既設構造物3の側面3aと当接している。このため、ケーシング2が既設構造物3に対して相対的に下方移動する際には可動部33はフリーに回動自在となっており、上記相対移動は自由となっている。逆に既設構造物3がケーシング2に対して相対的に下方移動する際には可動部33が約60゜まで回動する間については上記相対移動が可能となるが、それ以上移動しようとすると、可動部33の後端部がストッパー34に係止され、可動部33によりケーシング2に対する既設構造物3の下方移動が阻止される。こうして既設構造物3の落下を効果的に防止することができ、既設構造物3を複数回に分けて引き抜くことが可能となる。したがって、この実施形態によれば、引抜方向における既設構造物3の大きさに制限されず、既設構造物3を確実に引き抜くことが可能となる。
【0028】
また、上記実施形態では、ケーシング2の回転推進後に削孔7を形成しているが、削孔形成後にケーシングの回転推進を実行したり、ケーシングの回転推進と同時に削孔7を形成するようにしてもよいことはいうまでもない。
【0029】
さらに、上記実施形態では、ケーシング2を所定深さまで回転推進させた後、削孔7を介して水を給水して既設構造物3の最下端から水を吐出しているが、図6に示すようにケーシング2を用いず、削孔7を介して既設構造物3の最下端から水を吐出させるようにしてもよい。
【0030】
図6は、この発明にかかる地中既設構造物の引抜工法のさらに他の実施形態を示す図である。この実施形態では、同図(a)に示すように、既設構造物3の中心軸を通過するように既設構造物3の最上端から最下端に繋がる削孔7を既設構造物3に形成する。そして、ジェットポンプ9を削孔7に配管接続した後、ジェットポンプ9を作動させてジェットポンプ9から高圧水を削孔7に向けて給水する。すると、この高圧水は削孔7を介して既設構造物3の最下端に向けて圧送され、この最下端から吐出された水の一部は、同図中の矢印に示すように、既設構造物3の外周側面に沿って地盤表面に流れ、その水によって既設構造物3に対して浮力が作用する。
【0031】
次に、同図(b)に示すように、この浮力を受けた状態のままクレーンなどの重機機械をオペレータが操作してワイヤ8により既設構造物3を上方向(引抜方向)に吊上げ、地盤5から引き抜く。このとき、ジェットポンプ9から水を連続的に供給し続けるのが望ましいが、引抜途中で給水を停止するようにしてもよい。
【0032】
そして、引抜が完了すると、ジェットポンプ9を完全に停止させた後、既設構造物3を引き抜いた跡孔を貧配合モルタル、土、砂などで埋め戻す。
【0033】
以上のように、この実施形態においても、既設構造物3に対して浮力を作用ささせた状態で既設構造物3を吊り上げて地盤5から既設構造物3を引き抜くように構成しているので、その浮力分だけ既設構造物3の引抜に必要な吊上げ力を低減させることが可能となる。その結果、従来工法で使用していた重機機械に比べて吊上げ能力の低い重機機械を用いて既設構造物を引き抜くことができるようになり、施工効率を向上させるとともに、施工コストを抑制することができる。また、ケーシング2を用いていないので、作業工程を簡素化することができ、施工効率および施工コストの面でさらに有利なものとなる。
【0034】
【発明の効果】
以上のように、この発明によれば、既設構造物の最下端に繋がる削孔を既設構造物に形成した後、その削孔を介して既設構造物の最下端に向けて水を送給して既設構造物に対して浮力を作用させているので、従来工法よりも小さな吊上げ力で既設構造物の引抜が可能となる、つまり、より吊上げ能力の重機機械を用いて既設構造物の引抜が可能となり、施工効率を向上させるとともに、施工コストを抑制することができる。
【図面の簡単な説明】
【図1】この発明にかかる地中既設構造物の引抜工法の一実施形態を示す図である。
【図2】この発明にかかる地中既設構造物の引抜工法の一実施形態を示す図である。
【図3】この発明にかかる地中既設構造物の引抜工法の他の実施形態を示す図である。
【図4】この発明にかかる地中既設構造物の引抜工法の別の実施形態を示す図である。
【図5】この発明にかかる地中既設構造物の引抜工法のさらに別の実施形態を示す図である。
【図6】この発明にかかる地中既設構造物の引抜工法のさらに他の実施形態を示す図である。
【符号の説明】
2…ケーシング
3…既設構造物
5…地盤
7…削孔
11…鋼管(補助部材)
12…鋼製梁部材(補助部材)
21…鋼片[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a drawing method for pulling an existing structure buried underground from the ground.
[0002]
[Prior art]
When building and constructing various structures, it is necessary to improve the ground. As part of this, concrete structures such as concrete piles, steel structures such as steel piles, wooden structures such as wooden piles, and other structures buried or remaining deep underground (hereinafter, these A pull-out operation is performed to pull out the structures (collectively, “existing structures”). Conventionally, this drawing operation has been performed as follows. First, a casing (steel pipe) is inserted so as to surround the existing structure, and soil and sand between the casing and the existing structure are removed. Then, the existing structure is lifted by a heavy machine such as a crane to pull out the existing structure.
[0003]
[Problems to be solved by the invention]
However, in the conventional method, since the existing structure is pulled out using only the lifting force of the heavy machinery, the lifting capacity required for the heavy machinery also increases with the enlargement of the existing structure, Large heavy machinery is required. As a result, there is much room for improvement in terms of construction efficiency and construction cost.
[0004]
The present invention has been made in view of the above problems, and has as its object to provide a drawing method for pulling out an existing structure from the ground with excellent construction efficiency and at low cost.
[0005]
[Means for Solving the Problems]
The present invention is a drawing method for pulling out an existing structure buried underground, in order to achieve the above object, a first step of forming a hole in the existing structure that is connected to the lowermost end of the existing structure, A second step of supplying water to the lowermost end of the existing structure through a borehole to give buoyancy to the existing structure, and a step of providing buoyancy to the existing structure while maintaining the existing structure with buoyancy And a third step of lifting
[0006]
In the invention configured as described above, after a drilling hole connected to the lowermost end of the existing structure is formed in the existing structure, water is supplied to the lowermost end of the existing structure through the drilling. As a result, part of the water discharged from the lowermost end of the existing structure flows to the ground surface side along the outer peripheral side surface of the existing structure, and buoyancy acts on the existing structure due to the presence of the water. Then, the existing structure is lifted in a state where the buoyancy acts, and the existing structure is pulled out from the ground. By using the buoyancy in this way, it is possible to reduce the lifting force required for pulling out the existing structure.
[0007]
Here, before water is supplied toward the lowermost end of the existing structure, the casing is previously rotationally propelled to the ground so as to surround the existing structure, and the front end of the casing is set to a depth equal to or more than the lowermost end of the existing structure. It may be configured to reach the height. In this case, when water is supplied toward the lowermost end of the existing structure, the ground (such as earth and sand) located below the lowermost end of the existing structure is flushed by the water supply, and the inside of the casing is filled with water. That is, the existing structure exists in the casing in which the water is stored, and buoyancy acts on the existing structure. In this way, water discharged from the lowermost end of the existing structure efficiently flows through the casing, and buoyancy can be reliably given to the existing structure with a small amount of water.
[0008]
Further, when the plurality of steel pieces are positioned below the lowermost end of the existing structure before the second step, water discharged from the lowermost end of the existing structure is effectively prevented from permeating into the ground. In addition, the water use efficiency can be further improved. Also, without using a plurality of steel slabs, if the water pressure at the time of water supply is increased in order to increase construction efficiency, the ground located below the lowermost end of the existing structure will be dug deeper, as described above. By providing a plurality of steel slabs, it is possible to prevent the ground from being dug down by the water that has been pumped.
[0009]
Further, an auxiliary member is attached to the existing structure at a position above the ground surface, and when the existing structure is pulled out (third step), the auxiliary member is pushed up in a direction substantially parallel to the drawing direction of the existing structure. Then, the lifting force becomes the pulling force of the existing structure, and the lifting force can be further reduced.
[0010]
BEST MODE FOR CARRYING OUT THE INVENTION
FIG. 1 and FIG. 2 are views showing one embodiment of a method of drawing an existing underground structure according to the present invention. In this drawing method, as shown in FIG. 1A, the
[0011]
Then, as shown in FIG. 4B, when the
[0012]
Next, as shown in FIG. 2A, the jet pump 9 and the
[0013]
When each pipe connection is completed, the jet pump 9 is operated to supply high-pressure water from the jet pump 9 toward the drilled
[0014]
By supplying water into the
[0015]
When the drawing is completed, the jet pump 9 is completely stopped, and the trace holes from which the existing
[0016]
As described above, in this embodiment, after the
[0017]
In addition, since the existing
[0018]
In addition, the water discharged from the lowermost end of the existing
[0019]
The present invention is not limited to the above-described embodiment, and various changes other than those described above can be made without departing from the gist of the present invention. For example, in the above embodiment, the existing
[0020]
FIG. 3 is a view showing another embodiment of the method of drawing an underground existing structure according to the present invention. In this drawing method, the lower end of the steel pipe 11 is connected to the upper end of the existing
[0021]
A plurality of
[0022]
Further, in the above embodiment, after the
[0023]
FIG. 4 is a diagram showing another embodiment of the method of drawing an underground existing structure according to the present invention. In this embodiment, as shown in the figure, two
[0024]
Further, in the above embodiment, high-pressure water is supplied from the jet pump 9, that is, the water pressure at the time of water supply is increased in order to increase construction efficiency. However, as shown in FIGS. When it is discharged toward the earth and sand 5a (FIG. 1 (b)), not only does the earth and sand 5a flow away, but also the
[0025]
Further, in the above embodiment, the existing
[0026]
FIG. 5 is a view showing still another embodiment of the underground existing structure drawing method according to the present invention. In this embodiment, four
[0027]
As shown in FIG. 1C, each of the
[0028]
Further, in the above-described embodiment, the drilled
[0029]
Furthermore, in the above embodiment, after the
[0030]
FIG. 6 is a view showing still another embodiment of the underground existing structure drawing method according to the present invention. In this embodiment, as shown in FIG. 1A, a
[0031]
Next, as shown in FIG. 2B, an operator operates a heavy equipment such as a crane while receiving the buoyancy to lift the existing
[0032]
Then, when the drawing is completed, the jet pump 9 is completely stopped, and then the trace holes from which the existing
[0033]
As described above, also in this embodiment, since the existing
[0034]
【The invention's effect】
As described above, according to the present invention, after forming a drilled hole connected to the lowermost end of the existing structure in the existing structure, water is supplied to the lowermost end of the existing structure through the drilled hole. As the buoyancy acts on the existing structure, it is possible to pull out the existing structure with a smaller lifting force than the conventional method.In other words, it is possible to pull out the existing structure using a heavy machinery machine with a higher lifting capacity. This makes it possible to improve construction efficiency and reduce construction costs.
[Brief description of the drawings]
FIG. 1 is a view showing an embodiment of a method for drawing an underground existing structure according to the present invention.
FIG. 2 is a view showing an embodiment of a method for drawing an underground existing structure according to the present invention.
FIG. 3 is a view showing another embodiment of a method for drawing an underground existing structure according to the present invention.
FIG. 4 is a view showing another embodiment of a method for drawing an underground existing structure according to the present invention.
FIG. 5 is a view showing still another embodiment of the drawing method of the existing underground structure according to the present invention.
FIG. 6 is a view showing still another embodiment of the method for extracting an underground existing structure according to the present invention.
[Explanation of symbols]
2 ... casing 3 ... existing
12 ... Steel beam member (auxiliary member)
21 ... Slab
Claims (4)
前記削孔を介して前記既設構造物の最下端に向けて水を送給して前記既設構造物に対して浮力を与える第2工程と、
前記既設構造物に対して浮力を与えた状態のまま前記既設構造物を吊り上げる第3工程と
を備えたことを特徴とする地中既設構造物の引抜工法。In a drawing method for pulling out an existing structure buried underground, a first step of forming a hole in the existing structure that is connected to the lowermost end of the existing structure,
A second step of supplying water toward the lowermost end of the existing structure through the hole to give buoyancy to the existing structure;
And a third step of lifting the existing structure while applying buoyancy to the existing structure.
前記第3工程とともに、前記既設構造物の引抜方向とほぼ平行な方向に前記補助部材を押し上げる第7工程と
をさらに備えた請求項1ないし3のいずれかに記載の地中既設構造物の引抜工法。A sixth step of attaching an auxiliary member to the existing structure at a position above the ground surface before the third step;
4. The underground existing structure withdrawal according to claim 1, further comprising a seventh step of pushing up the auxiliary member in a direction substantially parallel to the withdrawal direction of the existing structure together with the third step. Construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002262284A JP3500387B1 (en) | 2002-08-16 | 2002-09-09 | Underground existing structure extraction method |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002-237561 | 2002-08-16 | ||
JP2002237561 | 2002-08-16 | ||
JP2002262284A JP3500387B1 (en) | 2002-08-16 | 2002-09-09 | Underground existing structure extraction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP3500387B1 JP3500387B1 (en) | 2004-02-23 |
JP2004131923A true JP2004131923A (en) | 2004-04-30 |
Family
ID=31949535
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002262284A Expired - Lifetime JP3500387B1 (en) | 2002-08-16 | 2002-09-09 | Underground existing structure extraction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3500387B1 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102493454A (en) * | 2011-11-24 | 2012-06-13 | 上海八洲建设工程有限公司 | Ultrahigh-pressure aerodynamic force water-flushing pile extracting method of vibration-free flexible sleeve |
JP2015021230A (en) * | 2013-07-16 | 2015-02-02 | 株式会社コプロス | Removal method of existing manhole |
JP2015048665A (en) * | 2013-09-03 | 2015-03-16 | 大成建設株式会社 | Removal method of existing pile |
CN108797588A (en) * | 2018-05-30 | 2018-11-13 | 江苏海上龙源风力发电有限公司 | A kind of weak soil sea bed offshore wind turbine single-pile foundation overall pulling down auxiliary mould and remove technique |
CN109610454A (en) * | 2018-12-20 | 2019-04-12 | 上海勇创建设发展有限公司 | A kind of underground obstacle barrier clearing device and its construction method |
JP2020193534A (en) * | 2019-05-30 | 2020-12-03 | 株式会社設計室ソイル | Removal method of steel pipe pile |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113513022B (en) * | 2021-05-06 | 2022-08-30 | 湖北远大建设集团有限公司 | Bored concrete pile head concrete stripping chiseling device |
CN113199639B (en) * | 2021-05-06 | 2022-11-01 | 湖北远大建设集团有限公司 | Automatic butt joint positioning and cutting structure for concrete pile head |
-
2002
- 2002-09-09 JP JP2002262284A patent/JP3500387B1/en not_active Expired - Lifetime
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102493454A (en) * | 2011-11-24 | 2012-06-13 | 上海八洲建设工程有限公司 | Ultrahigh-pressure aerodynamic force water-flushing pile extracting method of vibration-free flexible sleeve |
JP2015021230A (en) * | 2013-07-16 | 2015-02-02 | 株式会社コプロス | Removal method of existing manhole |
JP2015048665A (en) * | 2013-09-03 | 2015-03-16 | 大成建設株式会社 | Removal method of existing pile |
CN108797588A (en) * | 2018-05-30 | 2018-11-13 | 江苏海上龙源风力发电有限公司 | A kind of weak soil sea bed offshore wind turbine single-pile foundation overall pulling down auxiliary mould and remove technique |
CN109610454A (en) * | 2018-12-20 | 2019-04-12 | 上海勇创建设发展有限公司 | A kind of underground obstacle barrier clearing device and its construction method |
JP2020193534A (en) * | 2019-05-30 | 2020-12-03 | 株式会社設計室ソイル | Removal method of steel pipe pile |
Also Published As
Publication number | Publication date |
---|---|
JP3500387B1 (en) | 2004-02-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109653682B (en) | Drill bit with adjustable drill diameter and hole digging machine | |
WO2009049470A1 (en) | A bored pile drilling machine | |
RO134509A1 (en) | Process and device for on-spot making a pile of variable diameter, decreasing in depth | |
JP3500387B1 (en) | Underground existing structure extraction method | |
CN111005381A (en) | Bottom-pocket type vibration hammer profile steel pile extractor and pile extracting method thereof | |
JPS6319328A (en) | Method and apparatus for constructing turning-penetrating type large-diameter steel tube | |
JP2007332559A (en) | Removal method for existing underground pile | |
CN108560551A (en) | A kind of pile pulling sleeve and its application method | |
KR102178354B1 (en) | Pile pullout apparatus | |
KR101139708B1 (en) | Ground excavating guied casing for concrete file construction and ground excavating method using the same | |
JP4635725B2 (en) | Pile construction system | |
CN106759377A (en) | The construction method of recyclable building enclosure | |
JP3663155B2 (en) | Widening excavation apparatus and widening excavation method | |
JP4400700B2 (en) | Cutting and drawing method and equipment for existing piles | |
JP6077986B2 (en) | Obstacle ground pile placing device and method of placing a steel pipe pile on the obstacle ground | |
JPH0868287A (en) | Multi-spindle diameter widening drill method and device thereof | |
JP3224008B2 (en) | Underwater ground improvement method | |
KR20130027763A (en) | Hammer bit structure for air circulation | |
KR100478234B1 (en) | Pile excution machine using screw hammer | |
JP3839819B2 (en) | Reverse circulation drill | |
JP2001303570A (en) | Method for drawing out pile | |
JP7235255B2 (en) | Equipment for extracting existing piles | |
JP6634251B2 (en) | Pile foundation structure, ready-made pile burying device, method of constructing pile foundation structure using said ready-made pile burying device | |
JP2715275B2 (en) | Excavation method | |
CN217651789U (en) | Sliding pin type old pile pulling device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20030819 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3500387 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081212 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091212 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091212 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101212 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111212 Year of fee payment: 8 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111212 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121212 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131212 Year of fee payment: 10 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |