JP2004072891A - Method and apparatus for periodical inspection on generator or motor - Google Patents

Method and apparatus for periodical inspection on generator or motor Download PDF

Info

Publication number
JP2004072891A
JP2004072891A JP2002228478A JP2002228478A JP2004072891A JP 2004072891 A JP2004072891 A JP 2004072891A JP 2002228478 A JP2002228478 A JP 2002228478A JP 2002228478 A JP2002228478 A JP 2002228478A JP 2004072891 A JP2004072891 A JP 2004072891A
Authority
JP
Japan
Prior art keywords
generator
rotor
inspection
motor
gas turbine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2002228478A
Other languages
Japanese (ja)
Other versions
JP4039165B2 (en
Inventor
Satoru Ogino
荻野 哲
Yoshio Tada
多田 吉男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
JFE Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Steel Corp filed Critical JFE Steel Corp
Priority to JP2002228478A priority Critical patent/JP4039165B2/en
Publication of JP2004072891A publication Critical patent/JP2004072891A/en
Application granted granted Critical
Publication of JP4039165B2 publication Critical patent/JP4039165B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02KDYNAMO-ELECTRIC MACHINES
    • H02K15/00Methods or apparatus specially adapted for manufacturing, assembling, maintaining or repairing of dynamo-electric machines
    • H02K15/0006Disassembling, repairing or modifying dynamo-electric machines
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02KDYNAMO-ELECTRIC MACHINES
    • H02K15/00Methods or apparatus specially adapted for manufacturing, assembling, maintaining or repairing of dynamo-electric machines

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Power Engineering (AREA)
  • Manufacture Of Motors, Generators (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To solve such a problem associated with conventional methods for periodical inspection on generators in a bus turbine-combined power plant that a gas turbine is dismantled and then a rotor is pulled out before inspection is started, therefore, a schedule for inspection on the entire power plant is prolonged. <P>SOLUTION: A temporary working floor 10 is built above one equipment (steam turbine 120) of a generator 100. Then, the generator 100 is lifted up and its rotor 102 is pulled out to the working floor to inspect the rotor and the stator. For the lift 20, a gantry crane is used. Thus, the rotor and the stator can be inspected in parallel with the overhaul of the gas turbine, and the overall inspection schedule is shortened. <P>COPYRIGHT: (C)2004,JPO

Description

【0001】
【発明の属する技術分野】
本発明は、両端に機器を連結された発電機又は電動機の定期点検方法及び装置に関する。より詳細には、例えばガスタービン及び蒸気タービンを前後に連結された一軸型ガスタービンコンバインド発電所等における発電機等の定期点検方法及び装置に関する。
【0002】
【従来の技術】
一般に、発電機又は電動機の運用においては、経年的に内部コイル(固定子)の絶縁劣化、及び固定子を鉄心に保持するための固定治具(くさび)の劣化が生じる。このため、発電機又は電動機は安定運転維持を目的として、4〜10年を周期として定期的に内部コイル及びくさびの内部点検が実施されている。発電機又は電動機の固定子を点検するには、発電機又は電動機の片端を開放し内部の回転体(回転子)を抜き出すことが必要である。
【0003】
通常の場合、発電機又は電動機は、蒸気タービンなどの回転電気装置を回転させる駆動機器、又はファンなどの回転電気装置が駆動する被駆動機器が片側のみに連結されており、発電機又は電動機の回転子はこれらの機器の反対側に抜き出すことができる。従って、連結されている機器に干渉を与えることなく、容易に内部点検を行うことができる。発電機又は電動機の内部点検頻度は一般的に連結されている機器類の開放点検頻度に比べ少ないため、一般的には連結されている機器の点検・保守と同時期に点検・保守を行うことができた。
【0004】
発電機の両側に駆動機器あるいは負荷装置を有するいわゆるタンデム配列の装置においては、駆動機器又は負荷装置はケーシングを上下に分割可能であり、各部品の質量はせいぜい数十トン程度であり、また2年毎などに定期点検を行うので天井クレーン等の吊装置が設けられている。しかし、発電機又は電動機は上下分割等ができず一体で質量が数百トン例えば200〜300トンであり、10年に1回程度の点検頻度であるから、これを吊り上げる過大な天井クレーン等を設けるのは経済的ではない。このような発電機又は電動機の回転子を抜き出すためには、まず連結されている機器を分解し、この分解した機器の跡に、発電機又は電動機の回転子を抜き出すようにしていた。一例として、発電機の両端にガスタービンと蒸気タービンが連結されたガスタービンコンバインド発電所では、まず接続されている機器のうち例えばガスタービンを分解し、ガスタービンの上半車室、ロータ、静翼環をすべて取り除いた後、残っている下半車室上に発電機の回転子を抜き出していた。
【0005】
なお、ガスタービンコンバインド発電所の定期点検は次のように行われる。
【0006】
ガスタービンの点検周期:2年毎(電気事業法、法定)
蒸気夕一ビンの点検周期:4年毎(電気事業法、法定)
発電機の点検周期:10年程度(法定ではなく、各事業者の判断による)
【0007】
【発明が解決しようとする課題】
上記のように、両端に機器を連結された発電機又は電動機の従来の定期点検において、例えばガスタービン発電所では、ガスタービンの分解がすべて完了してから、その分解跡に発電機の回転子を抜き出して点検に着手するので、ガスタービンの分解点検と発電機の分解点検とは直列の作業工程となる。すなわち、ガスタービンの分解が完了するまで発電機の分解点検に着手することができず、一方、発電機の点検補修が完了するまでガスタービンの復旧作業を行うことができない。このため、発電所全体の定期点検日程が長期化するという問題点があった。
【0008】
また、発電機の回転子を引き出すための支持部をガスタービンの下部ケーシング内に配置し、ガスタービン車室上に引き出した回転子を仮置きするための敷き板を設ける必要があった。これらの作業はガスタービンの分解、組立工程と同時に行うことができないばかりでなく、タービン車室上に重量物(回転子)を仮置きするため、タービン構造物の破損、変形の恐れがあった。
【0009】
このような問題点を回避することを目的として、連結されている機器と同時並行的に発電機又は電動機の開放点検を行うことができるようにするために、発電機又は電動機を2つに分けて駆動機器又は負荷装置ごとに設け、発電機又は電動機の定期点検を単独に行うことができるように配置することも行われている。しかしながら、このような対策は、設備費の増嵩、設置面積の増大を招き経済的に不利となるという欠点があった。
【0010】
【課題を解決するための手段】
本発明は、上記実情に鑑み開発されたもので、その技術手段は、両端に機器を連結された発電機又は電動機の定期点検を行うに当たり、前記発電機又は電動機の両端の機器の何れかの上方に仮設作業床を構築し、同作業床上へ発電機又は電動機の回転子を抜き出し、回転子及び固定子の点検を行うことを特徴とする発電機又は電動機の定期点検方法である。両端に機器を連結された発電機又は電動機としては、両端の機器がタービン又は送風機であってもよく、また前記発電機又は電動機が発電機の場合、前記両端の機器がガスタービン及び蒸気タービンであってもよい。またガスタービン、蒸気タービンの他、送風機、ポンプを例とする被駆動機器であってもよい。
【0011】
例えば、ガスタービンコンバインド発電所の場合、ガスタービンの定期点検は2年毎であり、蒸気タービンの定期点検は4年ごとであり、発電機の定期点検は4年〜10年毎であるから、蒸気タービンの定期点検を行わないときに、蒸気タービンの上方に仮設作業床を構築することとすれば、発電機の定期点検をガスタービンの定期点検と同時並行的に行うことができる。
【0012】
本発明の定期点検方法を好適に実施することができる本発明の装置は、両端に機器を連結された発電機又は電動機の両端の機器の何れかの上方に構築した仮設作業床と、発電機又は電動機をリフトアップするリフトアップ装置とからなることを特徴とする発電機又は電動機の定期点検装置である。このとき前記リフトアップ装置は、発電機又は電動機をリフトアップする門形クレーンとすれば基礎上に反力を支持させて油圧ジャッキ等を用いて容易にリフトアップをすることができる。
【0013】
また、前記門形クレーンは複数台の油圧ジャッキ装置をビームで連結して門型としたものであってもよい。
【0014】
【発明の実施の形態】
以下図面を参照して本発明の実施の形態を説明する。
【0015】
まず本発明の適用される発電機又は電動機及びその両端に連結される機器の全体構成例を説明する。図8はガスタービン・蒸気タービンコンバインド発電所の機器構成の例を示す平面図である。発電機100には一方にガスタービン110が連結され、他方には蒸気タービン120が連結されている。蒸気タービン120によって駆動されるガス圧縮機で圧縮されたガスは、空気圧縮機115で圧縮された高圧空気により図示しない燃焼室で燃焼して燃焼ガスとなり、ガスタービン110内に入り、ガスタービンを回転させる。廃ガスは排気筒113から排出される。排出されたガスは図示しないボイラに導入され、ボイラは蒸気を発生し、発生した蒸気は蒸気タービン120に供給される。ガスタービン110及び蒸気タービン120は駆動源として発電機100を回転させ、発電機100は電力を発生する。
【0016】
2年毎の定期点検時には、ガスタービン110の上側ケーシング112、ローター、排気ケーシング、空気圧縮機115のケーシング、ローター、ガス圧縮機130のケーシング、ローター等が分解されて発電所内の床上に配置され、それぞれ分解点検、補修を行う。4年毎の蒸気タービンの定期点検時には、さらに蒸気タービン120のケーシング、ローター等が上記に加わり、適宜位置に配置されてそれぞれ分解、点検、補修を行う。さらに4年〜10年の間隔で発電機100の定期点検を行う。
【0017】
従来は、ガスタービン110を分解した後のガスタービン下部ケーシング上に発電機100の回転子102を抜き出し、発電機100の定期点検、補修を行っていた。
【0018】
この従来の発電機100の定期点検の工程を図9〜図12に示した。図9はガスタービン分解後、発電機100をリフト装置でリフトアップする状態を示す側面図、図10はその正面図である。リフト装置200は発電機100の両側に床養生したレール204上に載置された4台の装置から成っている。左右の2台のリフト装置202にそれぞれ発電機100上を横切るビーム203を載設し、この2本のビーム203からワイヤロープ211を吊下して発電機100のトラニオン101に接続する。次いで、図11に示すように、発電機100をリフトアップし、発電機100の下にはアルミ製尺角からなる棒材を積み重ねて受け養生103を行う。このリフトアップ高さは、ガスタービンの下ケーシング114上に発電機100の回転子を抜き出すことができる高さである。
【0019】
次いで図12に示すように、発電機100の回転子102を側方に抜き出し、これを天井走行クレーン220で吊り上げ、点検作業場所へ搬送する。発電機100の固定子側及び回転子側をそれぞれ点検、補修する。
【0020】
発電機100を組立てるときは以上の逆手順で行えばよい。このような発電機100の分解点検はガスタービン110を分解した後でなければ作業に着手できない。また、発電機100の組立完了後でなければ、ガスタービン110の組立作業を行うことはできなかった。
【0021】
本発明は、ガスタービン110の分解、組立とは無関係に発電機100の定期点検を並行的に行うことができるようにし、上記直列作業を廃止して定期点検工程全体の短縮を図るものである。
【0022】
次に本発明における発電機100の定期点検の工程を説明する。
【0023】
蒸気タービン、ガスタービンの回転を停止した後、図1に示すように、蒸気タービン120の上方に仮設作業床10を組立てる。仮設作業床10は点検作業開始前に設置しておくことが可能である。仮設作業床10は足場の転倒に対し充分な強度を持つ構造とする。仮設作業床10は回転電気装置100の懸架に対して障害となる部分や回転電気装置を懸架する際に干渉する機器(例えば励磁機等)の分解作業の障害となる部分は取外し可能にするなど適切な形状、構造としておく。この仮設作業床10は蒸気タービン120の頂端より僅か高い位置に仮設作業床上面を形成し、発電機100の回転子102を抜き出してこの仮設作業床10上に置き、点検、補修を行う。仮設作業床10のガス圧縮機130の上方の部分11はガス圧縮機を撤去した後に組立てる。また発電機100のトラオニオン101の手入、取付を行っておく。
【0024】
発電機100をリフトアップするリフトアップ装置(油圧門形クレーン)20を発電機100の横に設置する。リフトアップ装置20はベース21上に設けたジャッキ22と左右のジャッキの上方に掛け渡したビーム23とから成り、ビーム23から吊ロープを吊下して発電機100のトラニオン101に結束する。
【0025】
発電機100と各タービンのカップリングを外す。カップリングはインロー(相互はまり込み構造)となっているため、そのままでは発電機100をリフトアップすることはできない。タービンの軸の一部(中間軸)を取り外し、発電機100の回転子102を軸方向に移動させ、インローを外す。
【0026】
門形クレーン20は、発電機100の回転子102を仮設作業床10上に抜き出すことができる高さまで発電機100をリフトアップする。図9〜図10に示す従来の1m未満程度のリフトアップ量に比し、4m以上のリフトアップ量を必要とする。天井クレーンとの干渉を避けるため、門形クレーン20の吊ビーム23は低背丈で十分な曲げ剛性を有する形式とする。または発電機100のトラニオン101等に結束する吊ロープは湾曲半径を小さくすることができるナイロン等の材質のロープとし、ロープ長が極力短くなるような構成とした。この目的のため吊りロープに代えて、輪状にする必要のないシャックルと吊鋼棒との組合せとしてもよい。
【0027】
図2に示すように発電機の回転子の両端のエキサイタ、上側ブラケット、軸受、ファンブレード、エンドベル等を分解する。
【0028】
次いで図3に示すように発電機100をリフトアップし、発電機100の下に仮受架構27を挿入し、リフトアップされた発電機100の上下動を拘束する。仮受架構27は発電機100をリフトアップしてから短時間で発電機100の下に挿入する必要がある。回転子102の引き出し時には発電機100の固定子を仮設作業床10と結束することにより仮受架構27の転倒を防止するので、発電機100を支承する仮受架構27は転倒に対し特段の配慮を施した強固なものとする必要はない。
【0029】
次に、図4に示すように、回転子102の下側軸受104を分解し、回転子102を支持ブラケット105で吊下し、回転子の敷金106、回転子受け107、滑り金108等を回転子102の下方に挿入する。
【0030】
次いで、図5に示すように、回転子引抜具30を仮設作業床10上に設置し、回転子102の端部に連結する。回転子引抜具30は牽引装置31、ワイヤロープ32、シーブ33等から構成され、シーブ33は反力フレーム12に結合される。天井クレーンの吊ワイヤ41により回転子102を吊上げながら回転子102を102aの位置から矢印35の方向に引抜く。回転子102の引き抜き工程では発電機100を支持する仮受架構27に大きな転倒モーメントが掛かるが、仮設作業床10は、この転倒モーメントに十分耐える強度をもつ構造としてあり、発電機の牽引反力を支持するようにした。
【0031】
図6に示すように、回転子102が抜け出すに従い、回転子受け107等を移動しながら、天井クレーンの吊ロープ42の吊位置を変更しつつ、抜き出し作業を続行する。
【0032】
図7に示すように、回転子102の抜き出しが完了したら、回転子102は天井クレーンの吊ロープ42によって矢印43に示すように吊上げ、点検、補修可能な状態に保つ。あるいは、別の作業位置に回転子102を搬送して点検することとしてもよい。回転子の点検は主として外観チェック、清掃及び絶縁抵抗試験である。
【0033】
回転子102を抜き出した発電機100は仮受架構27を取外し、矢印26で示すように基礎上にリフトダウンして点検、補修を行う。なお、回転子102を抜き出した後、発電機100の固定子は、上方にリフトアップしたままで絶縁診断等の内部点検を行ってもよいし、リフトダウンして基礎上に戻してから点検を行ってもよい。固定子の点検はスロット中に保持されている固定子コイルを押しつけるウエッジの押付力の検査、取替等である。回転子及び固定子の点検、補修が完了したら発電機100を組立て、元の位置に戻してセンタリングを行う。発電機100の組立ては上記手順と逆工程で行う。
【0034】
以上の実施例によれば発電機100の点検、補修はガスタービン110の分解組立工程となんら干渉することなく両者を並行的に同時に実施できるようになった。従って、ガスタービンコンバインド発電所の定期点検の全体工程を大幅に短縮することが可能となった。
【0035】
【実施例】
ガスタービン及び蒸気タービンから構成された発電出力150MW級の規模を持つ一軸型ガスタービンコンバインド発電所の定期点検に本発明を適用した。従来、ガスタービン110単体の定期点検工程30日に加え、発電機100の定期点検作業工程10日が追加され、全体定期点検期間は40日を要していた。本発明では発電機100の点検をガスタービン110の分解、組立と同時並行工程とすることが可能となり、発電機100の内部点検を行わない場合と同等の30日間で全体の定期点検を完了させることができた。また、ガスタービン110上に発電機100の回転子102を抜出すことによる機器の破損・変形の可能性も排除することができた。
【0036】
また、発電機100の内部点検時に行われる絶縁診断を行う際、通電部分とガスタービン点検作業員との待避距離を十分に離すことができ、安全に作業を進めることができるという効果もある。
【0037】
なお、以上の実施例では両端にガスタービンと蒸気タービンを接続したガスタービンコンバインド発電所について述べたが、本発明はこれに限られるものではなく、例えば、電動機の両端に蒸気タービンや送風機などを接続した機器(蒸気タービンを補助駆動力とした電動送風機)などの電動機の定期点検にも同様に適用することが可能である。
【0038】
【発明の効果】
本発明によれば、両端に機器を連結した回転電気装置の定期点検に当り、その両端に接続された機器の点検工程と干渉することなく、回転電気装置の定期点検を実施することができ、プラント全体の定期点検工程の簡素化・短縮化を実現することが可能となった。また、回転電気装置の回転子を抜き出す際の機器類破損等の可能性を排除することができる。
【図面の簡単な説明】
【図1】実施例の作業工程を示す側面図である。
【図2】実施例の作業工程を示す側面図である。
【図3】実施例の作業工程を示す側面図である。
【図4】実施例の作業工程を示す側面図である。
【図5】実施例の作業工程を示す側面図である。
【図6】実施例の作業工程を示す側面図である。
【図7】実施例の作業工程を示す側面図である。
【図8】ガスタービンコンバインド発電所の機器構成、配列を示す平面図である。
【図9】従来の作業工程を示す側面図である。
【図10】従来の作業工程を示す側面図である。
【図11】従来の作業工程を示す側面図である。
【図12】従来の作業工程を示す側面図である。
【符号の説明】
10  仮設作業床
11  (仮設作業床の)部分
12  反力フレーム
20  リフトアップ装置(門形クレーン)
21  ベース
22  ジャッキ
23  ビーム
25、26  矢印
27  仮受架構
30  抜き出し装置
31  牽引装置
32  ワイヤロープ
33  シーブ
35  矢印
41  吊ワイヤ
42  吊ロープ
43  矢印
100  発電機
101  トラニオン
102  回転子
103  受け養生
104  軸受
105  支持ブラケット
110  ガスタービン
112  ケーシング
113  排出路
114  下部ケーシング
115  空気圧縮機
120  蒸気タービン
130  ガス圧縮機
200  リフトアップ装置
201  ベースフレーム
202  ジャッキ
203  ビーム
204  レール
211  吊ワイヤ
212  シャックル
213  吊具
220  天井走行クレーン
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method and a device for periodic inspection of a generator or a motor having devices connected to both ends. More specifically, the present invention relates to a method and an apparatus for periodic inspection of a generator or the like in a single-shaft gas turbine combined power plant or the like in which, for example, a gas turbine and a steam turbine are connected back and forth.
[0002]
[Prior art]
Generally, in operation of a generator or a motor, deterioration of insulation of an internal coil (stator) and deterioration of a fixing jig (wedge) for holding the stator to an iron core occur over time. For this reason, for the purpose of maintaining stable operation of the generator or the electric motor, the internal inspection of the internal coil and the wedge is periodically performed every 4 to 10 years. In order to check the stator of the generator or the electric motor, it is necessary to open one end of the generator or the electric motor and take out the rotating body (rotor) inside.
[0003]
In a normal case, a generator or a motor has a driving device that rotates a rotary electric device such as a steam turbine or a driven device that is driven by a rotary electric device such as a fan connected to only one side. The rotor can be withdrawn on the other side of these devices. Therefore, the internal inspection can be easily performed without causing interference to the connected devices. Since the frequency of internal inspections of generators or motors is generally lower than the frequency of open inspections of connected equipment, inspection and maintenance should be performed at the same time as inspection and maintenance of connected equipment. Was completed.
[0004]
In a device of a so-called tandem arrangement having a driving device or a load device on both sides of a generator, the driving device or the load device can divide a casing into upper and lower parts, each component has a mass of at most several tens tons, and 2 Suspension devices such as overhead cranes are provided for periodic inspections every year. However, the generator or electric motor cannot be divided into upper and lower parts or the like, and has a mass of several hundred tons, for example, 200 to 300 tons, and the inspection frequency is about once every ten years. It is not economical to provide. In order to extract the rotor of the generator or the motor, the connected device is first disassembled, and the rotor of the generator or the motor is extracted in the trace of the disassembled device. As an example, in a gas turbine combined power plant in which a gas turbine and a steam turbine are connected to both ends of a generator, first, for example, the gas turbine is disassembled among the connected devices, and the upper half compartment of the gas turbine, the rotor, and the static After removing all the wing rings, the generator rotor was pulled out onto the remaining lower half cabin.
[0005]
The periodic inspection of the gas turbine combined power station is performed as follows.
[0006]
Gas turbine inspection cycle: Every two years (Electrical Utility Law, statutory)
Steam bin inspection cycle: Every 4 years (Electrical Utility Law, statutory)
Generator inspection cycle: about 10 years (not legally determined, but by each company's judgment)
[0007]
[Problems to be solved by the invention]
As described above, in the conventional periodic inspection of a generator or an electric motor having devices connected to both ends, for example, in a gas turbine power plant, after all the gas turbines are completely disassembled, the generator trace is placed on the trace of the disassembly. And the inspection is started, so that the disassembly and inspection of the gas turbine and the disassembly and inspection of the generator are a series of operation steps. That is, the generator cannot be disassembled and inspected until the disassembly of the gas turbine is completed. On the other hand, the restoration work of the gas turbine cannot be performed until the inspection and repair of the generator are completed. For this reason, there has been a problem that the regular inspection schedule of the entire power plant is prolonged.
[0008]
In addition, it is necessary to arrange a support portion for extracting the rotor of the generator in the lower casing of the gas turbine, and to provide a laying plate for temporarily placing the extracted rotor on the gas turbine compartment. Not only can these operations be performed simultaneously with the disassembly and assembly steps of the gas turbine, but also because the heavy load (rotor) is temporarily placed on the turbine casing, there is a risk of damage and deformation of the turbine structure. .
[0009]
For the purpose of avoiding such problems, the generator or the motor is divided into two parts so that the open inspection of the generator or the motor can be performed simultaneously with the connected equipment. It is also provided for each driving device or load device so that the generator or the electric motor can be independently checked periodically. However, such measures have a disadvantage that the equipment cost increases and the installation area increases, which is disadvantageous economically.
[0010]
[Means for Solving the Problems]
The present invention has been developed in view of the above-mentioned circumstances, and its technical means is to perform a periodic inspection of a generator or a motor having devices connected to both ends, and to perform periodic inspection of the generator or the motor at either end of the generator or the motor. This is a periodic inspection method for a generator or a motor, comprising constructing a temporary work floor above, extracting a rotor of the generator or the motor onto the work floor, and checking the rotor and the stator. As the generator or motor with the equipment connected at both ends, the equipment at both ends may be a turbine or a blower, and when the generator or motor is a generator, the equipment at both ends may be a gas turbine and a steam turbine. There may be. Further, in addition to the gas turbine and the steam turbine, driven equipment such as a blower and a pump may be used.
[0011]
For example, in the case of a gas turbine combined power plant, the periodic inspection of the gas turbine is every two years, the periodic inspection of the steam turbine is every four years, and the periodic inspection of the generator is every four to ten years. If a temporary work floor is constructed above the steam turbine when the periodic inspection of the steam turbine is not performed, the periodic inspection of the generator can be performed concurrently with the periodic inspection of the gas turbine.
[0012]
The apparatus of the present invention, which can suitably carry out the periodic inspection method of the present invention, comprises: a temporary work floor constructed above any of a generator having equipment connected to both ends or equipment at both ends of the motor; Alternatively, there is provided a periodic inspection device for a generator or a motor, comprising a lift-up device for lifting up the motor. At this time, if the lift-up device is a portal crane that lifts up a generator or an electric motor, the lift-up device can easily lift up using a hydraulic jack or the like while supporting a reaction force on a foundation.
[0013]
Further, the portal crane may be a portal crane in which a plurality of hydraulic jack devices are connected by beams.
[0014]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0015]
First, a general configuration example of a generator or a motor to which the present invention is applied and devices connected to both ends thereof will be described. FIG. 8 is a plan view showing an example of a device configuration of the gas turbine / steam turbine combined power plant. A gas turbine 110 is connected to one side of the generator 100, and a steam turbine 120 is connected to the other side. The gas compressed by the gas compressor driven by the steam turbine 120 is burned in a combustion chamber (not shown) by the high-pressure air compressed by the air compressor 115 to become a combustion gas, and enters the gas turbine 110 and passes through the gas turbine. Rotate. The waste gas is discharged from the exhaust stack 113. The discharged gas is introduced into a boiler (not shown), and the boiler generates steam, and the generated steam is supplied to a steam turbine 120. The gas turbine 110 and the steam turbine 120 rotate the generator 100 as a drive source, and the generator 100 generates electric power.
[0016]
At the time of periodic inspection every two years, the upper casing 112, the rotor, the exhaust casing, the casing of the air compressor 115, the rotor, the casing of the gas compressor 130, the rotor, and the like of the gas turbine 110 are disassembled and placed on the floor in the power plant. , Perform overhaul and repair. At the time of periodic inspection of the steam turbine every four years, the casing, the rotor, and the like of the steam turbine 120 are added to the above, and are disposed at appropriate positions to perform disassembly, inspection, and repair. Further, the generator 100 is regularly inspected every 4 to 10 years.
[0017]
Conventionally, the rotor 102 of the generator 100 was extracted on the gas turbine lower casing after the gas turbine 110 was disassembled, and the generator 100 was regularly inspected and repaired.
[0018]
FIGS. 9 to 12 show the steps of the periodic inspection of the conventional generator 100. FIG. FIG. 9 is a side view showing a state in which the generator 100 is lifted up by a lift device after disassembly of the gas turbine, and FIG. 10 is a front view thereof. The lift device 200 is composed of four devices mounted on rails 204 cured on both sides of the generator 100. A beam 203 crossing over the generator 100 is mounted on each of the two lift devices 202 on the left and right sides, and a wire rope 211 is suspended from the two beams 203 and connected to the trunnion 101 of the generator 100. Next, as shown in FIG. 11, the generator 100 is lifted up, and a bar made of an aluminum square is stacked under the generator 100 to perform receiving curing 103. The lift-up height is a height at which the rotor of the generator 100 can be pulled out onto the lower casing 114 of the gas turbine.
[0019]
Next, as shown in FIG. 12, the rotor 102 of the generator 100 is extracted to the side, lifted by the overhead traveling crane 220, and transported to the inspection work place. Inspect and repair the stator side and rotor side of the generator 100 respectively.
[0020]
When assembling the generator 100, the above procedure may be followed. Such an overhaul of the generator 100 cannot be started until after the gas turbine 110 is disassembled. Also, the assembly work of the gas turbine 110 could not be performed unless the assembly of the generator 100 was completed.
[0021]
The present invention enables the periodic inspection of the generator 100 to be performed in parallel irrespective of the disassembly and assembly of the gas turbine 110, and eliminates the series work to shorten the entire periodic inspection process. .
[0022]
Next, a process of the periodic inspection of the generator 100 according to the present invention will be described.
[0023]
After stopping the rotation of the steam turbine and the gas turbine, the temporary work floor 10 is assembled above the steam turbine 120 as shown in FIG. The temporary work floor 10 can be installed before starting the inspection work. The temporary work floor 10 has a structure having sufficient strength against falling of the scaffold. The temporary work floor 10 is configured such that a portion that hinders the suspension of the rotary electric device 100 and a portion that hinders disassembly of devices (eg, an exciter) that interfere with the suspension of the rotary electric device can be removed. Have an appropriate shape and structure. The temporary work floor 10 forms an upper surface of the temporary work floor at a position slightly higher than the top end of the steam turbine 120, and the rotor 102 of the generator 100 is extracted and placed on the temporary work floor 10 for inspection and repair. The part 11 above the gas compressor 130 of the temporary work floor 10 is assembled after removing the gas compressor. Also, the trunnion 101 of the generator 100 is maintained and mounted.
[0024]
A lift-up device (hydraulic portal crane) 20 for lifting up the generator 100 is installed beside the generator 100. The lift-up device 20 is composed of a jack 22 provided on a base 21 and a beam 23 extending above the left and right jacks, and suspends a suspension rope from the beam 23 and binds it to the trunnion 101 of the generator 100.
[0025]
Remove the coupling between the generator 100 and each turbine. Since the coupling has a spigot (interlocking structure), the generator 100 cannot be lifted as it is. A part (intermediate shaft) of the turbine shaft is removed, the rotor 102 of the generator 100 is moved in the axial direction, and the spigot is removed.
[0026]
The portal crane 20 lifts the generator 100 up to a height where the rotor 102 of the generator 100 can be pulled out onto the temporary work floor 10. A lift-up amount of 4 m or more is required as compared with the conventional lift-up amount of less than about 1 m shown in FIGS. In order to avoid interference with the overhead crane, the suspension beam 23 of the portal crane 20 has a low height and a sufficient bending rigidity. Alternatively, the suspension rope bound to the trunnion 101 or the like of the generator 100 is a rope made of a material such as nylon capable of reducing a bending radius, and has a configuration in which the rope length is as short as possible. For this purpose, instead of the hanging rope, a combination of a shackle and a hanging steel bar which does not need to be formed in a ring shape may be used.
[0027]
As shown in FIG. 2, the exciters, upper brackets, bearings, fan blades, end bells and the like at both ends of the rotor of the generator are disassembled.
[0028]
Next, as shown in FIG. 3, the generator 100 is lifted up, the temporary receiving frame 27 is inserted under the generator 100, and the vertical movement of the generator 100 that has been lifted is restrained. The temporary receiving frame 27 needs to be inserted under the generator 100 in a short time after the generator 100 is lifted up. When pulling out the rotor 102, the stator of the generator 100 is bound to the temporary work floor 10 to prevent the temporary receiving frame 27 from overturning. It is not necessary to be strong with the above.
[0029]
Next, as shown in FIG. 4, the lower bearing 104 of the rotor 102 is disassembled, the rotor 102 is hung by the support bracket 105, and the rotor deposit 106, the rotor receiver 107, the slide metal 108 and the like are removed. It is inserted below the rotor 102.
[0030]
Next, as shown in FIG. 5, the rotor extraction tool 30 is installed on the temporary work floor 10 and connected to the end of the rotor 102. The rotor extraction tool 30 includes a traction device 31, a wire rope 32, a sheave 33, and the like. The sheave 33 is coupled to the reaction frame 12. The rotor 102 is pulled out from the position of 102a in the direction of the arrow 35 while lifting the rotor 102 by the hanging wire 41 of the overhead crane. In the process of pulling out the rotor 102, a large overturning moment is applied to the temporary receiving frame 27 supporting the generator 100. However, the temporary work floor 10 is structured to have a strength enough to withstand this overturning moment, and the traction reaction force of the generator Was supported.
[0031]
As shown in FIG. 6, as the rotor 102 comes out, the extraction operation is continued while changing the hanging position of the hanging rope 42 of the overhead crane while moving the rotor receiver 107 and the like.
[0032]
As shown in FIG. 7, when the extraction of the rotor 102 is completed, the rotor 102 is lifted by the hanging rope 42 of the overhead crane as shown by the arrow 43, and is maintained in a state where it can be inspected and repaired. Alternatively, the rotor 102 may be transported to another work position for inspection. Inspection of the rotor is mainly appearance check, cleaning and insulation resistance test.
[0033]
The generator 100 from which the rotor 102 has been removed removes the temporary receiving frame 27 and lifts down on the foundation as shown by the arrow 26 to perform inspection and repair. After the rotor 102 is extracted, the stator of the generator 100 may be subjected to internal inspection such as insulation diagnosis while being lifted up, or may be lifted down and returned to the foundation before inspection. May go. Inspection of the stator includes inspection and replacement of the pressing force of the wedge pressing the stator coil held in the slot. When the inspection and repair of the rotor and the stator are completed, the generator 100 is assembled, returned to its original position, and centered. The assembling of the generator 100 is performed in a process reverse to the above procedure.
[0034]
According to the above embodiment, the inspection and repair of the generator 100 can be performed simultaneously in parallel without any interference with the disassembly and assembly process of the gas turbine 110. Accordingly, it has become possible to greatly reduce the entire process of the periodic inspection of the gas turbine combined power plant.
[0035]
【Example】
The present invention is applied to a periodic inspection of a single-shaft gas turbine combined power plant having a power generation output of 150 MW class composed of a gas turbine and a steam turbine. Conventionally, in addition to the 30-day regular inspection process of the gas turbine 110 alone, a 10-day regular inspection work process for the generator 100 has been added, and the entire regular inspection period required 40 days. In the present invention, the inspection of the generator 100 can be performed simultaneously with the disassembly and assembly of the gas turbine 110, and the entire periodic inspection can be completed in 30 days equivalent to the case where the internal inspection of the generator 100 is not performed. I was able to. In addition, the possibility of damage or deformation of the device caused by extracting the rotor 102 of the generator 100 onto the gas turbine 110 could be eliminated.
[0036]
In addition, when performing insulation diagnosis performed at the time of internal inspection of the generator 100, there is an effect that the evacuation distance between the energized portion and the gas turbine inspection operator can be sufficiently separated, and the operation can be performed safely.
[0037]
In the above embodiment, a gas turbine combined power plant in which a gas turbine and a steam turbine are connected at both ends has been described.However, the present invention is not limited to this.For example, a steam turbine, a blower, or the like may be provided at both ends of an electric motor. The present invention can be similarly applied to periodic inspection of an electric motor such as a connected device (an electric blower using a steam turbine as an auxiliary driving force).
[0038]
【The invention's effect】
According to the present invention, the periodic inspection of the rotary electric device can be performed without interfering with the inspection process of the device connected to the both ends in the periodic inspection of the rotary electric device having the device connected to both ends, It has become possible to simplify and shorten the periodic inspection process of the entire plant. Further, it is possible to eliminate the possibility of breakage of equipment when extracting the rotor of the rotary electric device.
[Brief description of the drawings]
FIG. 1 is a side view showing a working process of an embodiment.
FIG. 2 is a side view showing a working process of the embodiment.
FIG. 3 is a side view showing a working process of the embodiment.
FIG. 4 is a side view showing working steps of the embodiment.
FIG. 5 is a side view showing the working process of the embodiment.
FIG. 6 is a side view showing the working steps of the embodiment.
FIG. 7 is a side view showing the working process of the embodiment.
FIG. 8 is a plan view showing a device configuration and an arrangement of a gas turbine combined power plant.
FIG. 9 is a side view showing a conventional working process.
FIG. 10 is a side view showing a conventional working process.
FIG. 11 is a side view showing a conventional working process.
FIG. 12 is a side view showing a conventional working process.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 10 Temporary work floor 11 Part (of temporary work floor) 12 Reaction frame 20 Lift-up device (portable crane)
21 Base 22 Jack 23 Beam 25, 26 Arrow 27 Temporary receiving frame 30 Extraction device 31 Traction device 32 Wire rope 33 Sheave 35 Arrow 41 Suspension wire 42 Suspension rope 43 Arrow 100 Generator 101 Trunnion 102 Rotor 103 Receiving curing 104 Bearing 105 Support Bracket 110 Gas turbine 112 Casing 113 Discharge path 114 Lower casing 115 Air compressor 120 Steam turbine 130 Gas compressor 200 Lift-up device 201 Base frame 202 Jack 203 Beam 204 Rail 211 Hanging wire 212 Shackle 213 Hanging tool 220 Overhead traveling crane

Claims (6)

両端に機器を連結した発電機又は電動機の定期点検を行うに当たり、前記発電機又は電動機の両端の機器の何れかの上方に仮設作業床を構築し、同作業床上へ前記発電機又は電動機の回転子を抜き出し、回転子及び固定子の点検を行うことを特徴とする発電機又は電動機の定期点検方法。In performing a periodic inspection of a generator or a motor having equipment connected to both ends, a temporary work floor is constructed above any of the equipment at both ends of the generator or the motor, and the generator or the motor is rotated on the work floor. A periodic inspection method for a generator or a motor, wherein a child is extracted and a rotor and a stator are inspected. 前記両端の機器がタービン又は送風機であることを特徴とする請求項1記載の発電機又は電動機の定期点検方法。The method of claim 1, wherein the equipment at both ends is a turbine or a blower. 前記発電機又は電動機が発電機であって前記両端の機器がガスタービン及び蒸気タービンであり、蒸気タービンの上方に仮設作業床を構築することを特徴とする請求項1記載の発電機又は電動機の定期点検方法。The generator or the electric motor according to claim 1, wherein the generator or the electric motor is a generator, the devices at both ends are a gas turbine and a steam turbine, and a temporary work floor is constructed above the steam turbine. Periodic inspection method. 両端に機器を連結された発電機又は電動機の両端の機器の何れかの上方に構築した仮設作業床と、前記発電機又は電動機をリフトアップするリフトアップ装置とからなることを特徴とする発電機又は電動機の定期点検装置。A generator comprising: a temporary work floor constructed above any one of a generator or a motor at both ends of which is connected to a device or a device at both ends of the motor; and a lift-up device for lifting up the generator or the motor. Or periodic inspection equipment for electric motors. 前記リフトアップ装置は、発電機又は電動機を吊上げる門形クレーンとしたことを特徴とする請求項4記載の発電機又は電動機の定期点検装置。5. The periodic inspection device for a generator or a motor according to claim 4, wherein the lift-up device is a portal crane that lifts the generator or the motor. 前記門形クレーンが複数台の油圧ジャッキ装置をビームで連結して門型としたものであることを特徴とする請求項5記載の発電機又は電動機の定期点検装置。The generator or electric motor periodic inspection device according to claim 5, wherein the portal crane has a plurality of hydraulic jack devices connected by beams to form a portal.
JP2002228478A 2002-08-06 2002-08-06 Method and apparatus for checking generator or motor Expired - Fee Related JP4039165B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002228478A JP4039165B2 (en) 2002-08-06 2002-08-06 Method and apparatus for checking generator or motor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002228478A JP4039165B2 (en) 2002-08-06 2002-08-06 Method and apparatus for checking generator or motor

Publications (2)

Publication Number Publication Date
JP2004072891A true JP2004072891A (en) 2004-03-04
JP4039165B2 JP4039165B2 (en) 2008-01-30

Family

ID=32015151

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002228478A Expired - Fee Related JP4039165B2 (en) 2002-08-06 2002-08-06 Method and apparatus for checking generator or motor

Country Status (1)

Country Link
JP (1) JP4039165B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006329025A (en) * 2005-05-25 2006-12-07 Chugoku Electric Power Co Inc:The Combined power plant
GB2459021A (en) * 2008-04-10 2009-10-14 Gen Electric Generator and rotor removal operation from a single shaft combined cycle machine
WO2013051348A1 (en) 2011-10-07 2013-04-11 川崎重工業株式会社 Maintenance inspection information management method and management system
WO2015064208A1 (en) * 2013-10-30 2015-05-07 三菱日立パワーシステムズ株式会社 Generator inspection method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20240141799A1 (en) * 2022-11-02 2024-05-02 Siemens Energy Global GmbH & Co. KG Disassembly and reassembly of a generator rotor in a plant

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006329025A (en) * 2005-05-25 2006-12-07 Chugoku Electric Power Co Inc:The Combined power plant
GB2459021A (en) * 2008-04-10 2009-10-14 Gen Electric Generator and rotor removal operation from a single shaft combined cycle machine
WO2013051348A1 (en) 2011-10-07 2013-04-11 川崎重工業株式会社 Maintenance inspection information management method and management system
CN103843233A (en) * 2011-10-07 2014-06-04 川崎重工业株式会社 Maintenance inspection information management method and management system
WO2015064208A1 (en) * 2013-10-30 2015-05-07 三菱日立パワーシステムズ株式会社 Generator inspection method
JP2015089225A (en) * 2013-10-30 2015-05-07 三菱日立パワーシステムズ株式会社 Method for checking electric generator
KR20160027060A (en) 2013-10-30 2016-03-09 미츠비시 히타치 파워 시스템즈 가부시키가이샤 Generator inspection method
CN105432004A (en) * 2013-10-30 2016-03-23 三菱日立电力系统株式会社 Generator inspection method
US9780628B2 (en) 2013-10-30 2017-10-03 Mitsubishi Hitachi Power Systems, Ltd. Generator inspection method
KR101785880B1 (en) 2013-10-30 2017-10-16 미츠비시 히타치 파워 시스템즈 가부시키가이샤 Generator inspection method

Also Published As

Publication number Publication date
JP4039165B2 (en) 2008-01-30

Similar Documents

Publication Publication Date Title
JP5349411B2 (en) Maintenance method for wind turbine blades of wind power generation equipment
JP4159933B2 (en) Repair methods and equipment for wind power towers, etc.
KR20170101786A (en) Generator, generator base, and generator repair method
JP2016508020A (en) Method and apparatus for separating the stator core of a generator
US7281308B2 (en) Methods of generator rotor removal in a combined-cycle stag application
JP4039165B2 (en) Method and apparatus for checking generator or motor
US20090255104A1 (en) Simplified generator removal operation for rotor removal of center generator in a single shaft combined cycle machine
JP6145026B2 (en) How to check the generator
CN112510930A (en) Method for moving generator rotor out of generator base in ship engine room
CN203933291U (en) A kind of Large Rotor is extracted out, charging apparatus
JP2011047287A (en) Steam turbine for nuclear power plant and replacing construction method thereof
CN202405962U (en) Motor overhauling system
CN208684271U (en) A kind of large-sized water turbine generator stator bar hanging apparatus
JP2017125411A (en) Turbine casing rotating device
CN207727534U (en) Hydraulic turbine maintenance structure
CN107359749A (en) A kind of device and method that rotor is taken out for auxiliary generator
JP4101411B2 (en) Power plant installation method
CN215201797U (en) Motor overhauls composite set
JPH0823283B2 (en) Portable Turbin Diaphragm Suspended Transporter
JP2005054593A (en) Runner disassembling method of vertical shaft bulb turbine generator
CN212245977U (en) Remove rotatory hoist and mount construction equipment
CN211867727U (en) Engine maintenance frock
JPH0940127A (en) Carrying-out/in device for gas turbine
JP4636446B2 (en) Inspection method for pumps and pump motors
CN114394533A (en) Gas turbine inlet cylinder overhauling and transferring system and overhauling and transferring method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050526

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070417

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070424

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070625

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070724

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070914

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071016

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071029

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101116

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4039165

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111116

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111116

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121116

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131116

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees