JP2003331164A - Maintenance expense estimation system for water treatment equipment - Google Patents

Maintenance expense estimation system for water treatment equipment

Info

Publication number
JP2003331164A
JP2003331164A JP2002141549A JP2002141549A JP2003331164A JP 2003331164 A JP2003331164 A JP 2003331164A JP 2002141549 A JP2002141549 A JP 2002141549A JP 2002141549 A JP2002141549 A JP 2002141549A JP 2003331164 A JP2003331164 A JP 2003331164A
Authority
JP
Japan
Prior art keywords
maintenance
water treatment
equipment
treatment facility
plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2002141549A
Other languages
Japanese (ja)
Inventor
Masayuki Kobayashi
雅之 小林
Akio Kasahara
昭夫 笠原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kurita Water Industries Ltd
Original Assignee
Kurita Water Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kurita Water Industries Ltd filed Critical Kurita Water Industries Ltd
Priority to JP2002141549A priority Critical patent/JP2003331164A/en
Publication of JP2003331164A publication Critical patent/JP2003331164A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/20Controlling water pollution; Waste water treatment

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a maintenance expense estimation system for water treatment equipment capable of easily estimating maintenance expenses for the water treatment equipment and preventing an increase in a financial burden of a large amount of maintenance costs in the operation process of the water treatment equipment. <P>SOLUTION: This maintenance expense estimation system is provided with an equipment database storing information of the water treatment equipment constructed by a plurality of types of equipment, a device database storing the life time and/or maintenance frequency of each of the equipment and an expenses database storing unit costs of objects and work expenses about replacement or maintenance of each equipment. The equipment database and the equipment database are referred to, to find required maintenance items for the water treatment equipment over a prescribed term, a maintenance plan for the water treatment equipment is drawn up according to the required maintenance items (maintenance plan preparation means), and an expense storing means is referred to according to the maintenance plan to calculate maintenance expenses for the water treatment equipment (maintenance expense calculation means). <P>COPYRIGHT: (C)2004,JPO

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、例えば水処理設備
の運用に必要な保守経費を容易に見積もることができ、
また長期間に亘る保守経費の支払い計画を、支払額の急
激な増大を招来することなく作成するに好適な水処理設
備の保守経費見積システムに関する。
TECHNICAL FIELD The present invention makes it possible to easily estimate the maintenance cost necessary for operating a water treatment facility, for example.
The present invention also relates to a maintenance cost estimation system for a water treatment facility, which is suitable for preparing a maintenance cost payment plan for a long period of time without causing a sudden increase in payment amount.

【0002】[0002]

【関連する背景技術】下水や工業排水等を浄化する水処
理設備や河川水等から浄水を生成する水処理設備、更に
はボイラ設備等に組み込まれる水処理設備においては、
その運用状況を定期的に点検して薬液等の消耗品を補充
したり、耐用期間を過ぎたイオン交換樹脂やフィルタ等
を交換する等の保守が必要である。また長期間の運用に
伴って生じる不具合箇所(機器)を修理する等の保守も
必要である。
[Related Background Art] In water treatment equipment for purifying sewage, industrial wastewater, etc., water treatment equipment for producing purified water from river water, etc., and for water treatment equipment incorporated in boiler equipment, etc.,
It is necessary to perform maintenance such as periodically checking the operation status and replenishing consumables such as chemicals, and replacing the ion exchange resin and filters that have reached their end of life. In addition, maintenance such as repair of defective parts (equipment) caused by long-term operation is also necessary.

【0003】このような設備の保守・運用に伴う経費
(運用コスト)は、一般的にはその都度、保守契約会社
等に対して支払われる。
Expenses (operation costs) associated with the maintenance and operation of such equipment are generally paid to the maintenance contract company and the like each time.

【0004】[0004]

【発明が解決しようとする課題】ところでこの種の経費
(保守・運用コスト)は、設備の運用を開始した初期時
においては比較的低いが、通常、その運用期間が長くな
るに従って次第に増大する。特に設備の老朽化が進むに
従って不具合が発生し易くなる傾向にあり、これに伴っ
てその修理費等が次第に嵩んで行くことが否めない。し
かしながら設備の運用者側にとっては、その設備を長期
間に亘って運用して所定の成果を上げてきたにも拘わら
ず、その保守経費が急に高くなったような感じを覚える
ことが多々あり、またその高額な保守経費を捻出するこ
とが負担となることもある。
By the way, this kind of cost (maintenance / operation cost) is relatively low at the initial stage when the operation of the equipment is started, but usually it gradually increases as the operation period becomes longer. In particular, there is a tendency for problems to occur more easily as the equipment deteriorates, and it is undeniable that repair costs will increase accordingly. However, the operator of the equipment often feels that the maintenance cost has suddenly increased, despite the fact that the equipment has been operating for a long period of time and has achieved the desired results. Moreover, it may be a burden to generate the expensive maintenance cost.

【0005】本発明はこのような事情を考慮してなされ
たもので、その目的は、所定期間に亘る設備の保守計画
を立案し、その保守計画に応じて上記所定期間に亘る保
守経費を見積もることで、その運用過程において生じる
高額な保守経費の発生に伴う金銭的な負担の増大を防ぐ
ことのできる水処理設備の保守経費見積システムを提供
することにある。
The present invention has been made in consideration of such circumstances, and an object thereof is to formulate a maintenance plan for equipment over a predetermined period and estimate the maintenance cost over the predetermined period according to the maintenance plan. Therefore, it is to provide a maintenance cost estimation system for a water treatment facility that can prevent an increase in financial burden due to the occurrence of a large maintenance cost in the operation process.

【0006】[0006]

【課題を解決するための手段】上述した目的を達成する
べく本発明に係る水処理設備の保守経費見積システム
は、複数種の設備機器により構築された水処理設備の情
報を記憶した設備情報記憶手段と、前記各設備機器の耐
用期間および/または保守頻度を記憶した機器情報記憶
手段と、前記各設備機器の交換または保守に関わる物品
単価および/または工事費用を記憶した費用記憶手段と
を備え、前記設備情報記憶手段と機器情報記憶手段とを
参照して所定期間に亘る前記水処理設備の、例えば必要
保守項目を求め、この必要保守項目に従って該水処理設
備の保守計画を立案し(保守計画作成手段)、立案した
保守計画に従って前記費用記憶手段を参照して前記水処
理設備に対する保守経費を算出する(保守経費算出手
段)ことを特徴としている。
In order to achieve the above-mentioned object, a maintenance cost estimation system for a water treatment facility according to the present invention is a facility information storage storing information of a water treatment facility constructed by a plurality of types of facility equipment. Means, equipment information storage means for storing the service life and / or maintenance frequency of each equipment, and cost storage means for storing the unit price of goods and / or construction cost relating to the replacement or maintenance of each equipment. , A required maintenance item of the water treatment facility for a predetermined period of time is obtained by referring to the facility information storage means and the device information storage means, and a maintenance plan of the water treatment facility is prepared according to the required maintenance item (maintenance Plan creating means), referring to the cost storage means according to a planned maintenance plan, and calculating the maintenance cost for the water treatment facility (maintenance cost calculating means) That.

【0007】好ましくは前記保守費用算出手段は、前記
水処理設備の所定期間に亘る保守費用の総額を求める手
段を備える。更に前記水処理設備の保守経費見積システ
ムは、例えば予め設定された複数種のパターンの中から
選択指定された分割支払いパターンに応じて、前記所定
期間に亘る保守経費の総額を分配することで、前記水処
理設備の所定期間に亘る保守費用の分割支払い計画を作
成する支払計画作成手段を備えることを特徴としてい
る。
[0007] Preferably, the maintenance cost calculation means comprises means for determining the total maintenance cost of the water treatment facility over a predetermined period. Further, the maintenance cost estimation system for the water treatment equipment, for example, by distributing the total maintenance cost over the predetermined period in accordance with the divided payment pattern selected and designated from a plurality of preset patterns, It is characterized in that it comprises a payment plan preparation means for preparing an installment payment plan for the maintenance cost of the water treatment facility over a predetermined period.

【0008】[0008]

【発明の実施の形態】以下、図面を参照して本発明の一
実施形態に係る水処理設備の保守経費見積システムにつ
いて説明する。ちなみに水処理設備は、下水や工業排水
等を浄化する水処理設備や、河川や湖沼水等から浄水を
生成する水処理設備、更には空調設備やボイラ設備等に
組み込まれる水処理設備、更には工業用の高純水を生成
する水処理設備等からなる。
BEST MODE FOR CARRYING OUT THE INVENTION A maintenance cost estimation system for a water treatment facility according to an embodiment of the present invention will be described below with reference to the drawings. By the way, water treatment facilities are water treatment facilities that purify sewage, industrial wastewater, etc., water treatment facilities that generate purified water from rivers and lake water, and water treatment facilities that are built into air conditioning equipment, boiler equipment, etc. It consists of water treatment equipment that produces high-purity industrial water.

【0009】図1はこの実施形態に係る見積システムの
概略構成を示している。この見積システムは、複数種の
設備機器を用いて構築される各種水処理設備の構成(設
備仕様)を記憶する設備データベース(設備情報記憶手
段)1と、この設備データベース1に付随して設けられ
て上記各水処理設備の保守日やその保守項目、更にはそ
の故障履歴等を記憶する履歴データベース2を備える。
上記設備データベース1には、複数の客先にそれぞれ設
置されている既存の水処理設備の構成(設備仕様)が、
例えば管理IDを付してそれぞれ記憶されることは勿論
のこと、後述するように客先仕様に応じて新たに設計さ
れる水処理設備の構成(設備仕様)も記憶される。
FIG. 1 shows a schematic configuration of an estimation system according to this embodiment. This estimation system is provided in association with an equipment database (equipment information storage means) 1 that stores the configurations (equipment specifications) of various water treatment equipment constructed using a plurality of types of equipment, and the equipment database 1. A history database 2 for storing the maintenance date and maintenance items of each water treatment facility, and its failure history and the like.
In the equipment database 1, the configuration (equipment specifications) of the existing water treatment equipment installed at each of a plurality of customers,
For example, it is needless to say that the management ID is added to each and stored, and as will be described later, the configuration (equipment specifications) of the water treatment equipment newly designed according to the customer specifications is also stored.

【0010】またこの見積システムには、各種の水処理
設備を構築する為の複数種の設備機器(濾過フィルタや
ボイラ、熱交換器等)の仕様や耐用期間、その保守頻度
の情報をそれぞれ記憶した機器データベース(機器情報
記憶手段)3と、これらの各設備機器の交換または保守
に関わる物品単価(設備機器の価格)およびその工事費
用を記憶した費用データベース(費用記憶手段)4とが
設けられている。
Further, the estimation system stores the specifications, service life, and maintenance frequency information of a plurality of types of equipments (filtration filters, boilers, heat exchangers, etc.) for constructing various water treatment equipments. The equipment database (equipment information storage means) 3 and the cost database (expense storage means) 4 that stores the unit price of the equipment (price of equipment) related to replacement or maintenance of each equipment and the construction cost thereof are provided. ing.

【0011】さてコンピュータシステムからなる見積処
理部10は、情報入力部5から与えられる見積・設備情
報に従って前記各データベース1,2,3,4をそれぞれ
検索し、基本的には指定された水処理設備の保守項目を
抽出し、その保守項目に従って所定期間に亘る保守計画
を立案する機能(保守計画作成手段)、およびこの保守
計画に基づいて、例えば前記費用データベース4を参照
して各保守項目に係わる費用を積算する等して該水処理
設備の保守費用を算出する機能(保守経費算出手段)を
備える。更に見積処理部10は、後述するように所定期
間に亘る保守経費の支払計画を立案する機能(支払計画
作成手段)を備える。
The estimation processing unit 10 composed of a computer system searches each of the databases 1, 2, 3 and 4 in accordance with the estimation / facility information given from the information input unit 5, and basically specifies the designated water treatment. A function (maintenance plan creating means) of extracting a maintenance item of equipment and formulating a maintenance plan for a predetermined period according to the maintenance item, and based on this maintenance plan, for example, referring to the cost database 4 A function (maintenance cost calculation means) for calculating the maintenance cost of the water treatment facility by accumulating the costs involved is provided. Further, the quotation processing unit 10 has a function (payment plan creating means) for formulating a payment plan for maintenance expenses over a predetermined period as described later.

【0012】具体的には上記見積処理部10は、情報入
力部5を介して指定された水処理設備を構成している複
数の設備機器の情報を前記設備データベース1を検索し
て求め、これらの各設備機器の耐用期間等を前記機器デ
ータベース3を検索して調べることで、所定の保守期間
において保守が必要となる設備機器とその保守時期等を
保守項目として求める保守項目抽出手段11を備える。
この保守項目の抽出は、例えば水処理設備の運用開始日
を基準として、或いは前記履歴データベース2から取得
し得るメンテナンスを行った日を基準として定められる
所定の保守対象期間(見積期間)内に保守が必要となる
設備機器であるか否か判定することによってなされる。
また見積処理部10は、上記保守項目抽出手段11にて
求められた各保守項目について前記費用データベース4
を参照し、その保守項目(設備機器)を保守(修理・交
換等のメンテナンス)するに要する物品単価や工事費用
等からなる保守経費を求める保守経費算出手段12を備
える。
More specifically, the estimation processing unit 10 searches the facility database 1 for information on a plurality of facility devices that constitute the water treatment facility designated via the information input unit 5, and obtains these information. A maintenance item extracting means 11 is provided for searching the equipment database 3 for the service life of each equipment and the like, and ascertaining equipment and equipment requiring maintenance in a predetermined maintenance period and their maintenance times as maintenance items. .
This maintenance item is extracted within a predetermined maintenance target period (estimated period) determined based on, for example, the operation start date of the water treatment facility or the date of maintenance that can be acquired from the history database 2. This is done by determining whether or not the equipment is a required equipment.
Further, the estimation processing unit 10 uses the cost database 4 for each maintenance item obtained by the maintenance item extracting means 11.
And a maintenance cost calculating means 12 for determining a maintenance cost including an item unit price and a construction cost required for maintenance (maintenance such as repair / replacement) of the maintenance item (facility equipment).

【0013】このようにして求められる保守経費は、そ
の保守項目の情報と共に見積作成手段13に与えられ、
該見積作成手段13において上記保守項目により特定さ
れる設備機器を保守するに必要な経費の見積書(個別見
積書)が作成される。この見積書は、見積提示部6を介
して前記水処理設備を運用するユーザ(設備管理者)に
対して提示される。
The maintenance cost thus obtained is given to the estimate creating means 13 together with the information on the maintenance item,
The estimate creation means 13 creates an estimate (individual estimate) of the cost required to maintain the equipment specified by the maintenance item. This quotation is presented to the user (equipment manager) who operates the water treatment facility through the quotation presenting unit 6.

【0014】尚、水処理設備において処理する原水の量
(例えばm3/日)や水質データ等の、前記情報入力部
5から書き換え可能な運転条件記憶手段7を備えると共
に、この運転条件記憶手段7に記憶されたデータに基づ
いて前記機器データベース3内のデータ、即ち、保守頻
度等を演算して、該機器データベース3のデータを更新
する保守頻度演算手段8を備えることが好ましい。この
ような記憶手段7および演算手段8を備えれば、原水負
荷に応じて保守頻度や耐用期間が変化する、例えば濾過
フィルタやイオン交換樹脂等に対する保守経費の見積精
度を高めることができる等の効果が奏せられる。
In addition to the operating condition storing means 7 which can be rewritten from the information input section 5 such as the amount of raw water treated in the water treatment facility (for example, m 3 / day) and water quality data, the operating condition storing means is provided. It is preferable to include maintenance frequency calculation means 8 for calculating the data in the equipment database 3, that is, the maintenance frequency and the like based on the data stored in 7, and updating the data in the equipment database 3. If the storage unit 7 and the calculation unit 8 are provided, the maintenance frequency and the service life change depending on the raw water load, and the accuracy of estimating the maintenance cost for the filtration filter, the ion exchange resin, or the like can be improved. It is effective.

【0015】一方、前記見積処理部10は、保守時期を
異にする複数の保守項目が求められるような場合、これ
らの保守項目に従って保守計画を作成する保守計画作成
手段14を備える。この保守計画作成手段14は、例え
ば水処理設備の運用期間を10年として設定した場合、
1年目、2年目、3年目、…等として定められる管理期
間毎にそれぞれ必要となる保守項目を分類し、各年にお
いてそれぞれ実行すべき保守の内容(保守項目)を整理
することで、その保守計画を立案する。
On the other hand, when the plurality of maintenance items with different maintenance times are required, the estimation processing unit 10 includes a maintenance plan creating means 14 for creating a maintenance plan according to these maintenance items. This maintenance plan creating means 14 is, for example, when the operation period of the water treatment facility is set to 10 years,
By classifying the maintenance items required for each management period defined as the first year, the second year, the third year, etc., and organizing the maintenance contents (maintenance items) to be executed in each year. , Make a maintenance plan for it.

【0016】前述した見積作成手段13は、このように
して水処理設備の保守計画が作成された場合には、この
保守計画に従って前記保守経費算出手段12において各
保守項目毎にそれぞれ求められた保守経費を上記管理期
間毎に集計する等して、その水処理設備の所定期間に亘
る保守に関する見積書(総括見積書)を作成する。この
見積書は、前記保守計画と共に前記見積提示部6を介し
て前記水処理設備を運用するユーザ(設備管理者)に対
して提示される。
When the maintenance plan of the water treatment facility is prepared in this way, the above-mentioned estimate preparing means 13 determines the maintenance required for each maintenance item in the maintenance cost calculating means 12 according to this maintenance plan. Costs are totaled for each management period, and an estimate (general estimate) for maintenance of the water treatment facility over a predetermined period is created. This estimate is presented to the user (equipment manager) who operates the water treatment facility via the estimate presenting unit 6 together with the maintenance plan.

【0017】また前記見積処理部10は、上述した基本
的な見積処理機能に加えて、上記水処理設備の長期間に
亘る保守に伴う経費の支払計画を立案する支払計画作成
手段15を備える。この支払計画作成手段15は、水処
理設備の保守を行う毎に発生する保守経費を、一般的に
はその都度決済することに代えて、所定期間に亘る保守
経費の総額に着目し、この総額を上記所定期間内におい
て複数回に亘って分割して決済する為の計画を作成する
ものである。即ち、この支払計画は、水処理設備の運用
が長期間に及んだときには、その保守経費が次第に嵩む
ようになり、その保守経費をその都度決済した場合に
は、その初期時には比較的軽かった金銭的負担が次第に
大きくなることを防止するべく、例えばその金銭的負担
がほぼ一定となるように調整する役割を担う。
In addition to the basic estimate processing function described above, the estimate processing section 10 also includes a payment plan preparation means 15 for preparing a payment plan for expenses associated with maintenance of the water treatment facility for a long period of time. This payment plan preparation means 15 pays attention to the total maintenance cost over a predetermined period instead of generally paying the maintenance cost each time the water treatment facility is maintained, and paying the total amount. A plan for dividing and paying a plurality of times within the predetermined period is created. That is, this payment plan is such that when the water treatment facility is operated for a long period of time, the maintenance cost will gradually increase, and if the maintenance cost is settled each time, the monetary amount that was relatively light at the initial stage. In order to prevent the financial burden from increasing gradually, for example, it plays a role of adjusting the financial burden to be almost constant.

【0018】具体的には支払計画作成手段15は、前記
見積作成手段13にて求められた所定期間に亘る保守経
費の総額を求める機能を備える。そして支払パターン選
択部16にて選択指定された支払パターンに従って前記
水処理設備の所定期間に亘る保守経費の総額を、例えば
各年毎に配分することで、前記水処理設備の設備管理者
(ユーザ)がその保守管理者(メンテナンス会社)に支
払う保守経費を年単位で分散させて設定した支払計画を
作成するものとなっている。
Specifically, the payment plan preparation means 15 has a function of calculating the total amount of the maintenance cost for the predetermined period calculated by the estimation preparation means 13. Then, according to the payment pattern selected and designated by the payment pattern selection unit 16, by distributing the total maintenance cost of the water treatment facility over a predetermined period, for example, every year, a facility manager (user of the water treatment facility). ) Creates a payment plan in which maintenance expenses to be paid to the maintenance manager (maintenance company) are dispersed by year.

【0019】ちなみに分割支払いパターンは、図2に例
示するように所定期間に亘る保守経費がパターンXとし
て示すように年々増大するような場合、斜線部の面積と
して示される保守経費の総額を、年毎にほぼ一定の額と
して平準化する分割支払いパターンYとして設定され
る。またこの分割支払いパターンは、水処理設備に対す
る期待度の高い初期時における保守経費を高くし、数年
先には水処理設備の仕様が古くなり、その期待度が低下
することを見込んで、その保守経費を徐々に低くする分
割支払いパターンZ等として設定される。
Incidentally, in the case of the split payment pattern, when the maintenance cost over a predetermined period increases year by year as shown in FIG. 2, the total maintenance cost shown as the shaded area is calculated as It is set as a split payment pattern Y that is leveled as an almost constant amount for each. In addition, this installment payment pattern increases maintenance costs in the early stage when expectations for water treatment equipment are high, and expects that the specifications of the water treatment equipment will become old in a few years and the expectation level will decrease. It is set as a split payment pattern Z or the like that gradually reduces the maintenance cost.

【0020】このような分割支払いパターンの設定は、
例えば予め準備されている複数種の分割支払いパターン
Y,Z,…の中からその1つを選択することにより行われ
る。この際、分割支払いパターン自体(支払額の変化の
傾向)を可変設定することも可能である。そしてこのよ
うな分割支払いパターンに従って作成された保守経費の
支払計画が、前記見積提示部6を介して前記水処理設備
を運用するユーザ(設備管理者)に対して提示される。
The setting of such a divided payment pattern is as follows.
For example, it is performed by selecting one of a plurality of types of divided payment patterns Y, Z, ... Prepared in advance. At this time, it is also possible to variably set the installment payment pattern itself (the tendency of change in payment amount). Then, a maintenance cost payment plan created in accordance with such an installment payment pattern is presented to the user (equipment manager) who operates the water treatment facility via the estimate presentation unit 6.

【0021】図3は上述した機能を備えて構成された保
守経費見積システムの概略的な処理手順の一例を示して
いる。この処理手順に示すように、本システムにおいて
は情報入力部5からユーザ名や設備IDを入力して見積
処理対象とする水処理設備を特定すれば[ステップS
1]、設備データベース1を検索することによって当該
水処理設備を構築している設備機器が求められる[ステ
ップS2]。そして特定された設備機器毎に前記機器デ
ータベース3を検索することによって、その設備機器の
耐用期間や保守頻度の情報を求めることが可能となる
[ステップS3]。
FIG. 3 shows an example of a schematic processing procedure of the maintenance cost estimation system having the above-mentioned functions. As shown in this processing procedure, in the present system, if the user name or equipment ID is input from the information input unit 5 and the water treatment equipment to be subjected to the estimation processing is specified [Step S
1], by searching the equipment database 1, the equipment that constructs the water treatment equipment is obtained [step S2]. By searching the equipment database 3 for each specified equipment, it becomes possible to obtain information on the service life and maintenance frequency of the equipment [step S3].

【0022】しかる後、前記情報入力部5から与えられ
る保守の見積期間に従って、その見積期間内に保守を必
要とする設備機器が存在するか否かを判定する。そして
上記見積期間内において保守を必要とする設備機器につ
いては、その設備機器名とその保守時期とを保守項目と
して抽出する[ステップS4]。この際、保守時期を異
にする複数の保守項目が求められた場合には、前述した
ようにして所定期間に亘る保守計画を作成する[ステッ
プS5]。そして上記保守項目毎に費用データベース4
を参照してその保守経費を求め[ステップS6]、複数
の保守項目がある場合には、その保守経費の総額を求め
る[ステップS7]。
Thereafter, according to the maintenance estimation period given from the information input unit 5, it is determined whether or not there is equipment requiring maintenance within the estimation period. Then, for the equipment requiring maintenance within the estimated period, the equipment name and the maintenance time are extracted as maintenance items [step S4]. At this time, when a plurality of maintenance items with different maintenance periods are required, a maintenance plan for a predetermined period is created as described above [step S5]. And the cost database 4 for each of the above maintenance items
, The maintenance cost is calculated [step S6], and if there are a plurality of maintenance items, the total maintenance cost is calculated [step S7].

【0023】以上のようにして保守すべき設備機器とそ
の保守経費とを求めたならば、前述した保守項目に従っ
てその設備機器名と保守経費とを一覧表形式で記載した
見積書を作成し[ステップS8]、これをユーザに提示
する。またその見積期間が長期間に亘るような場合に
は、必要に応じて保守経費の支払パターンを設定し[ス
テップS9]、その支払パターンに従って支払経費の総
額の分割支払計画を作成し[ステップS10]、これを
ユーザに提示する。
When the facility equipment to be maintained and the maintenance cost are obtained as described above, an estimate sheet is prepared in which the equipment name and the maintenance cost are listed in the form of a list according to the maintenance items described above. Step S8], which is presented to the user. If the estimated period is long, a maintenance expense payment pattern is set as necessary [step S9], and a total payment expense installment payment plan is created according to the payment pattern [step S10]. ], And presents this to the user.

【0024】かくして上述したように構成される見積処
理システムによれば、ユーザ名や設備ID等を入力し
て、保守に関わる見積もりの対象となる水処理設備を指
定(特定)すれば、その入力情報に従って設備データベ
ース1が検索されて当該水処理設備を構成している複数
の設備機器が求められ、更に機器データベース3を検索
することでこれらの設備機器の耐用期間等が求められ
る。そしてこれらの耐用期間等の情報に従い、当該水処
理設備の運用開始日や、履歴データベース2により示さ
れる最終メンテナンス日から所定の保守対象期間内に保
守すべき設備機器があるか否かが判定されてその保守項
目が抽出され、費用データベース4を参照することでそ
の保守項目について費用が求められる。
Thus, according to the quotation processing system configured as described above, by inputting the user name, equipment ID, etc., and designating (specifying) the water treatment equipment to be the quotation related to maintenance, the input The equipment database 1 is searched according to the information to find a plurality of equipment devices that make up the water treatment equipment, and by searching the equipment database 3, the service life of these equipment devices is found. Then, according to the information such as the service life, it is determined whether or not there is equipment to be maintained within a predetermined maintenance target period from the operation start date of the water treatment facility or the last maintenance date shown by the history database 2. Then, the maintenance item is extracted, and the cost is calculated for the maintenance item by referring to the cost database 4.

【0025】この結果、ユーザ名や設備ID等を用いて
水処理設備を特定するだけで、その水処理設備の保守す
べき項目(設備機器)とその保守に必要となる費用を簡
易に求めることが可能となる。また長期間に亘って水処
理設備の保守を行うような場合には、その保守期間に亘
る保守計画が作成され、この保守計画に基づく見積が作
成されるので、どの時点でどのような保守が必要であ
り、またそのときの保守経費がどの程度であるかを容易
に整理して求めることができる。従って上記保守計画と
その見積とに従って、水処理設備の効果的な運用計画を
立てることが可能となる。
As a result, by simply specifying the water treatment facility by using the user name, facility ID, etc., it is possible to easily obtain the item (facility equipment) to be maintained and the cost required for the maintenance of the water treatment facility. Is possible. When water treatment facilities are to be maintained for a long period of time, a maintenance plan for the maintenance period is created and an estimate based on this maintenance plan is created. It is necessary and the maintenance cost at that time can be easily arranged and calculated. Therefore, it is possible to make an effective operation plan of the water treatment facility according to the maintenance plan and the estimate thereof.

【0026】また本システムによれば長期間に亘る見積
経費の総額に応じて、その費用の分割支払計画を種々の
支払パターンの下で作成することができる。従って水処
理設備の運用に伴って発生する保守経費を、例えば将来
的に増大すると見込まれる金銭的な負担を配慮して前倒
し的に支払うことで、その運用コストの平準化を図るこ
とが可能となる等の効果が奏せられる。従って水処理設
備を長期間に亘って運用する場合であっても、将来にお
いて、その予想を越えた莫大な保守経費が発生すること
を未然に防止することが可能となる等の効果が奏せられ
る。
Further, according to the present system, the installment payment plan of the cost can be created under various payment patterns according to the total amount of the estimated cost over a long period of time. Therefore, it is possible to equalize the operation cost by paying the maintenance cost that accompanies the operation of the water treatment facility in advance in consideration of the financial burden expected to increase in the future. The effect such as is achieved. Therefore, even if the water treatment facility is operated for a long period of time, it is possible to prevent the occurrence of enormous maintenance costs beyond the expectation in the future. To be

【0027】換言すれば将来的に必要となる保守経費を
見込んで、月毎または年毎に必要とする保守経費を平準
化することができ、金銭的負担を軽減した保守契約を結
ぶことが可能となる。また運転者(顧客)側の事情に応
じた水処理設備の運用計画、特にその運用に必要な経費
に対する資金計画を容易に作成することが可能となる等
の効果が奏せられる。
In other words, in anticipation of maintenance expenses required in the future, the maintenance expenses required monthly or yearly can be leveled, and maintenance contracts with reduced financial burden can be concluded. Becomes Further, it is possible to easily prepare an operation plan of the water treatment facility according to the circumstances of the driver (customer) side, in particular, a financial plan for the cost required for the operation can be easily produced.

【0028】尚、本発明は上述した実施形態に限定され
るものではない。ここでは水処理設備における運用コス
ト(保守コスト)の平準化を例に説明したが、他の設備
における運用コストの平準化についても同様に適用する
ことができる。また見積処理を行う期間については、そ
の設備の耐用期間や運用年数等を考慮して定めればよい
ものである。更には分割支払いパターンについても種々
設定可能であり、要はその要旨を逸脱しない範囲で種々
変形して実施することができる。
The present invention is not limited to the above embodiment. Here, the leveling of the operating cost (maintenance cost) in the water treatment facility has been described as an example, but the leveling of the operating cost in other facilities can be similarly applied. Further, the period for which the estimation process is performed may be determined in consideration of the service life of the equipment and the number of years of operation. Further, various payment patterns can be set, and the point is that various modifications can be made without departing from the scope of the invention.

【0029】[0029]

【発明の効果】以上説明したように本発明によれば水処
理設備の所定期間に亘る保守経費を容易に見積もること
ができ、また長期間に亘る保守計画を作成することで、
その保守経費を把握することが可能となる。また予め設
定した分割支払いパターンに応じて分配して、その保守
経費の支払いの形態を変更することができるので、経費
的に無理のない長期に亘る運用計画を容易に作成するこ
とができ、設備を長期間に亘って運用した際に、多大な
保守経費が発生することを未然に防ぐことができる等の
実用上多大なる効果が奏せられる。
As described above, according to the present invention, the maintenance cost of a water treatment facility over a predetermined period can be easily estimated, and a maintenance plan for a long period can be created.
It is possible to grasp the maintenance cost. In addition, since it is possible to distribute according to a preset payment pattern and change the form of payment of maintenance costs, it is possible to easily create a long-term operation plan that is reasonably cost-effective, and When operated for a long period of time, it is possible to prevent a large maintenance cost from occurring, which is a great practical effect.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施形態に係る水処理設備の保守経
費見積システムの概略構成図。
FIG. 1 is a schematic configuration diagram of a maintenance cost estimation system for a water treatment facility according to an embodiment of the present invention.

【図2】保守経費の分割支払いパターンの例を示す図。FIG. 2 is a diagram showing an example of a divided payment pattern of maintenance expenses.

【図3】本システムにおける概略的な見積処理手順を示
す図。
FIG. 3 is a diagram showing a schematic estimation processing procedure in the present system.

【符号の説明】[Explanation of symbols]

1 設備データベース 2 履歴データベース 3 機器データベース 4 費用データベース 5 情報入力部 6 見積提示部 7 運転条件記憶手段 8 保守頻度演算手段 11 保守項目抽出手段 12 保守経費算出手段 13 見積作成手段 14 保守計画作成手段 15 支払計画作成手段 16 支払いパターン選択手段 1 Equipment database 2 History database 3 equipment database 4 Cost database 5 Information input section 6 Estimate presentation section 7 Operating condition storage means 8 Maintenance frequency calculation means 11 Maintenance item extraction means 12 Maintenance cost calculation means 13 Estimating means 14 Maintenance plan creation means 15 Payment plan creation means 16 Payment pattern selection means

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 複数種の設備機器により構築された水処
理設備の情報を記憶した設備情報記憶手段と、 前記各設備機器の耐用期間および/または保守頻度を記
憶した機器情報記憶手段と、 前記各設備機器の交換または保守に関わる物品単価およ
び/または工事費用を記憶した費用記憶手段と、 前記設備情報記憶手段および前記機器情報記憶手段を参
照して所定期間に亘る前記水処理設備の保守計画を立案
する保守計画作成手段と、 上記保守計画に従って前記費用記憶手段を参照して前記
水処理設備に対する保守経費を算出する保守経費算出手
段とを具備したことを特徴とする水処理設備の保守経費
見積システム。
1. A facility information storage unit that stores information on a water treatment facility constructed by a plurality of types of facility devices; a device information storage unit that stores a service life and / or maintenance frequency of each facility device; A cost storage unit that stores a unit price of goods and / or a construction cost related to replacement or maintenance of each equipment, and a maintenance plan of the water treatment facility for a predetermined period by referring to the equipment information storage unit and the equipment information storage unit Maintenance plan of the water treatment facility, and maintenance cost calculation means for calculating the maintenance cost for the water treatment facility by referring to the cost storage means according to the maintenance plan. Quotation system.
【請求項2】 前記保守費用算出手段は、前記水処理設
備の所定期間に亘る保守費用の総額を求める手段を備え
てなる請求項1に記載の水処理設備の保守経費見積シス
テム。
2. The maintenance cost estimation system for a water treatment facility according to claim 1, wherein the maintenance cost calculation means comprises means for determining a total maintenance cost of the water treatment facility over a predetermined period.
【請求項3】 請求項1に記載の水処理設備の保守経費
見積システムであって、 更に指定された分割支払いパターンに応じて前記水処理
設備の所定期間に亘る保守経費の分割支払い計画を作成
する支払計画作成手段を備えることを特徴とする水処理
設備の保守経費見積システム。
3. The maintenance cost estimation system for a water treatment facility according to claim 1, further comprising: creating a plan for payment of maintenance expenses for a predetermined period of the water treatment facility according to a designated installment payment pattern. A maintenance cost estimation system for a water treatment facility, which is equipped with a payment plan creating means.
【請求項4】 前記分割支払いパターンは、予め設定さ
れた複数種のパターンの中から選択指定されるものであ
って、 前記保守経費の分割支払い計画は、前記所定期間に亘る
保守経費の総額を上記選択指定された分割支払いパター
ンに従って分配して作成されるものである請求項3に記
載の水処理設備の保守経費見積システム。
4. The installment payment pattern is selected and specified from a plurality of preset patterns, and the installment payment plan of the maintenance cost includes a total amount of the maintenance cost over the predetermined period. The maintenance cost estimation system for a water treatment facility according to claim 3, wherein the maintenance cost estimation system is created by distributing in accordance with the selected and designated installment payment pattern.
JP2002141549A 2002-05-16 2002-05-16 Maintenance expense estimation system for water treatment equipment Pending JP2003331164A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002141549A JP2003331164A (en) 2002-05-16 2002-05-16 Maintenance expense estimation system for water treatment equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002141549A JP2003331164A (en) 2002-05-16 2002-05-16 Maintenance expense estimation system for water treatment equipment

Publications (1)

Publication Number Publication Date
JP2003331164A true JP2003331164A (en) 2003-11-21

Family

ID=29702099

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002141549A Pending JP2003331164A (en) 2002-05-16 2002-05-16 Maintenance expense estimation system for water treatment equipment

Country Status (1)

Country Link
JP (1) JP2003331164A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014092852A (en) * 2012-11-01 2014-05-19 Hitachi Information & Control Solutions Ltd Arithmetic processing apparatus and arithmetic processing program
RU167657U1 (en) * 2016-08-29 2017-01-10 Федеральное государственное военное образовательное учреждение высшего профессионального образования Михайловская военная артиллерийская академия A device for calculating the average annual economic cost of operating a complex of simulators during the development of a sample of a complex technical system
JP2017170274A (en) * 2016-03-18 2017-09-28 栗田工業株式会社 Proposal support device, proposal support method, and program for water treatment system
CN110482815A (en) * 2019-07-23 2019-11-22 湖南九层台环境科技有限公司 A kind of rural area village septic tank handles O&M expense low level management system
JP7328397B1 (en) 2022-05-12 2023-08-16 株式会社Nttファシリティーズ support system
JP7549495B2 (en) 2020-06-22 2024-09-11 古河電気工業株式会社 Management device, management method, management program, and management system

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014092852A (en) * 2012-11-01 2014-05-19 Hitachi Information & Control Solutions Ltd Arithmetic processing apparatus and arithmetic processing program
JP2017170274A (en) * 2016-03-18 2017-09-28 栗田工業株式会社 Proposal support device, proposal support method, and program for water treatment system
RU167657U1 (en) * 2016-08-29 2017-01-10 Федеральное государственное военное образовательное учреждение высшего профессионального образования Михайловская военная артиллерийская академия A device for calculating the average annual economic cost of operating a complex of simulators during the development of a sample of a complex technical system
CN110482815A (en) * 2019-07-23 2019-11-22 湖南九层台环境科技有限公司 A kind of rural area village septic tank handles O&M expense low level management system
CN110482815B (en) * 2019-07-23 2022-04-08 湖南九层台环境科技有限公司 Rural village septic tank handles operation and maintenance cost extensive management system
JP7549495B2 (en) 2020-06-22 2024-09-11 古河電気工業株式会社 Management device, management method, management program, and management system
JP7328397B1 (en) 2022-05-12 2023-08-16 株式会社Nttファシリティーズ support system
JP2023167614A (en) * 2022-05-12 2023-11-24 株式会社Nttファシリティーズ support system

Similar Documents

Publication Publication Date Title
KR101902586B1 (en) Qualification system and method for chilled water plant operations
US9120688B2 (en) Seawater desalination plant system
JP4999051B2 (en) Asset management system, asset management method, and asset management program
JP2011170496A (en) Device and method for supporting plant construction plan
KR20030045140A (en) Recycle parts utilization promoting system, and recycle parts utilization promoting method
JP2003331164A (en) Maintenance expense estimation system for water treatment equipment
CA2545911A1 (en) Method and system for water quality trading
JP2017170274A (en) Proposal support device, proposal support method, and program for water treatment system
Hegde et al. Site selection for a ‘sure service terminal’
DE10311947A1 (en) Demand planning and supply chain management method in which exchange balances between raw material, unfinished products and end products are considered when ordering raw material and unfinished products for end product assembly
Donaghy et al. Optimal investment in a tax increment financing district
US20090171702A1 (en) System and method for maintenance of residences
JP2003114989A (en) Water treatment plant estimation system
KR20010112094A (en) Method and system for comprehensive management of chemical materials
JPH1161893A (en) Controller for water-supply plant
Sidiropoulos et al. Well locations and constraint handling in groundwater pumping cost minimization via genetic algorithms
JP2010257097A (en) Plant monitoring device
JP4351230B2 (en) Design document data generation system and design document data generation method
JP2008233998A (en) Land property value acquisition system, land property value acquisition method and computer program
JP6558460B1 (en) Water treatment facility management equipment
WO2019176706A1 (en) Water treatment facility management device
JP6558459B1 (en) Water treatment facility management equipment
Pretorius et al. Investigation of the maintenance organisation for hot rolling mills
JP2005157967A (en) Equipment management system, method and program therefor
Wu A benchmark study for minimizing energy cost of constant and variable speed pump operation

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040924

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070328

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070523

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20070620