JP2003114989A - Water treatment plant estimation system - Google Patents

Water treatment plant estimation system

Info

Publication number
JP2003114989A
JP2003114989A JP2001310283A JP2001310283A JP2003114989A JP 2003114989 A JP2003114989 A JP 2003114989A JP 2001310283 A JP2001310283 A JP 2001310283A JP 2001310283 A JP2001310283 A JP 2001310283A JP 2003114989 A JP2003114989 A JP 2003114989A
Authority
JP
Japan
Prior art keywords
water treatment
unit
equipment
price
units
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001310283A
Other languages
Japanese (ja)
Inventor
Susumu Fukue
晋 福江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kurita Water Industries Ltd
Original Assignee
Kurita Water Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kurita Water Industries Ltd filed Critical Kurita Water Industries Ltd
Priority to JP2001310283A priority Critical patent/JP2003114989A/en
Publication of JP2003114989A publication Critical patent/JP2003114989A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/20Controlling water pollution; Waste water treatment

Abstract

PROBLEM TO BE SOLVED: To provide a water treatment plant estimation system for easily selecting a water treatment plant unit required for constructing a water treatment plant and further easily estimating a plant price required for its installation. SOLUTION: The water treatment plant estimation system is provided with a unit data base 1 in which various plant specifications of a plurality of kinds of units and their plant prices are stored, a unit selecting means 4 for selecting the unit required for constructing the water treatment plant suitable for water treatment specifications by retrieving the unit data base according to the water treatment specifications inputted via a condition input means 3 and a plant price estimating means 5 for estimating the plant price of the water treatment plant to be constructed by the selected unit. The system is further provided with a component replacement plan creating means 7 for planning a replacement plan to constitute the unit and an operation price estimating means 8 for estimating operation prices in accordance with replacement of components.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、水処理設備の構成
要素をなす複数種の構成部品を所定の設備仕様に従って
組み立てた複数種のユニットを用いて構築される水処理
設備を一時的に貸し出すに際して、その水処理設備の設
備価格を見積もるに好適な水処理設備見積システムに関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention temporarily lends out a water treatment facility constructed by using a plurality of types of units in which a plurality of types of components constituting the components of the water treatment facility are assembled according to a predetermined facility specification. At this time, the present invention relates to a water treatment equipment estimation system suitable for estimating the equipment price of the water treatment equipment.

【0002】[0002]

【関連する背景技術】半導体等の製造工場においては、
例えば製造製品の洗浄に塩分等の不純物を除去した処理
水(純水)が大量に使用される。この為、上記工場に
は、専ら、活性炭フィルタやイオン交換器等を備えた水
処理設備が、その付帯設備として設けられる。
[Related Background Art] In a semiconductor manufacturing plant,
For example, a large amount of treated water (pure water) from which impurities such as salt have been removed is used for washing manufactured products. Therefore, in the above factory, a water treatment facility including an activated carbon filter, an ion exchanger and the like is exclusively provided as an incidental facility.

【0003】ちなみに上記水処理設備は、各種工場にお
いて要求される処理水の水量や水質等からなる水処理仕
様に応じてその設備仕様が個別に設計され、工場環境に
応じた独自の設備として構築される。
Incidentally, the above-mentioned water treatment equipment is individually designed according to the water treatment specifications such as the quantity and quality of treated water required in various factories, and is constructed as an original equipment according to the factory environment. To be done.

【0004】[0004]

【発明が解決しようとする課題】ところで上記工場にお
いては、一時的な製品生産規模の拡大に伴い、より大量
の処理水を必要とすることがある。また造船所等におい
ては、船舶へのボイラの組み付け時にだけ、大量の処理
水を必要とすることがある。しかしながらこのような処
理水の一時的な大量需要を見込んで、予め大規模な水処
理設備を設けておくことは多大な設備コストが掛かる。
しかも、常時、その処理能力の全てを発揮させることが
ないので、その稼動コストが甚だ悪いと言う問題があ
る。特に造船所においては、水処理設備を必要とする期
間が限られるので、その稼動効率自体が悪いと言う問題
がある。
By the way, in the above factory, a larger amount of treated water may be required due to the temporary expansion of the product production scale. Further, in a shipyard or the like, a large amount of treated water may be required only when the boiler is assembled to the ship. However, it is very costly to install a large-scale water treatment facility in advance in anticipation of a temporary large demand for such treated water.
In addition, since the processing capacity is not always fully exerted, there is a problem that the operation cost is extremely bad. Particularly in a shipyard, there is a problem that the operating efficiency itself is poor because the period for which water treatment equipment is required is limited.

【0005】そこで水処理設備の構成要素をなす複数種
の構成部品、例えば活性炭フィルタ(CF)、ミリボア
フィルタ(MF)、逆浸透膜モジュール(RO)、電気
式脱イオン装置(KCDI)、非再生型イオン交換器
(DZ)、膜式濾過器(PF)、脱気膜(DC)等の構
成部品を、予め所定の設備仕様に従って組み立てて、貸
し出し用の複数種の標準的な水処理設備ユニットとして
準備しておき、これらのユニットを貸し出すことで一時
的に所望とする水処理仕様の水処理設備を構築すること
が考えられている。
Therefore, a plurality of types of components constituting the water treatment equipment, such as an activated carbon filter (CF), a millibore filter (MF), a reverse osmosis membrane module (RO), an electric deionization device (KCDI), a non- Regenerative ion exchanger (DZ), membrane filter (PF), degassing membrane (DC) and other components are assembled in advance according to the specified equipment specifications, and multiple types of standard water treatment equipment for rental are provided. It is considered that a water treatment facility having a desired water treatment specification is temporarily constructed by preparing them as units and renting out these units.

【0006】しかしながら所望とする水処理仕様の水処
理設備を構築する上で、どの種別のユニットが必要なの
か、またその設備コストがどの程度になるかを把握する
ことが非常に困難である。しかも前述した構成部品の中
には、その使用状況に応じて交換が必要なものもあり、
その交換時期や部品交換等に伴う運用コストを把握する
ことも困難である。
However, in constructing a water treatment facility having a desired water treatment specification, it is very difficult to grasp which type of unit is required and what the facility cost is. Moreover, some of the above-mentioned components need to be replaced according to their usage conditions,
It is also difficult to understand the replacement time and the operating costs associated with parts replacement.

【0007】本発明はこのような事情を考慮してなされ
たもので、その目的は、水処理設備を一時的に貸し出す
に際して、その水処理設備を構築するに必要な水処理設
備ユニットを簡易に選定することができ、更にはその設
置に要する設備価格を容易に見積もることのできる水処
理設備見積システムを提供することにある。また本発明
は、水処理設備の構成要素をなす複数種の構成部品中の
交換が必要な構成部品の交換時期とその運用コストとを
容易に見積もることのできる水処理設備見積システムを
提供することを目的としている。
The present invention has been made in consideration of such circumstances, and an object thereof is to simplify a water treatment equipment unit necessary for constructing the water treatment equipment when the water treatment equipment is temporarily rented out. Another object of the present invention is to provide a water treatment equipment quotation system which can be selected and can easily estimate the equipment price required for its installation. Further, the present invention provides a water treatment equipment estimation system capable of easily estimating the replacement time of a component that needs to be replaced out of a plurality of types of constituent parts constituting the component of the water treatment equipment and its operating cost. It is an object.

【0008】[0008]

【課題を解決するための手段】上述した目的を達成する
べく本発明に係る水処理設備見積システムは、1つまた
は複数種のユニットからなる水処理設備の価格等を見積
もるものであって、複数種の構成部品を所定の設備仕様
に従って組み立てた複数種のユニットの各設備仕様とそ
の設備価格とを記憶したユニット・データベースを備
え、条件入力手段を介して入力された、例えば処理水質
や処理水量等からなる水処理仕様に応じて前記ユニット
・データベースを検索して、上記水処理仕様に見合う水
処理設備を構築するに必要な1つまたは複数のユニット
を選定する(ユニット選定手段)と共に、前記ユニット
・データベースを検索して上記ユニット選定手段により
選定されたユニットにより構築される水処理設備の、例
えば貸出価格からなる設備価格を見積もり(設備価格見
積手段)、上記ユニット選定手段により選定したユニッ
トにより構築される水処理設備の構成と、前記設備価格
見積手段により見積もられた設備価格とを所定の情報提
示手段を用いて提示する機能を備えたことを特徴として
いる。
In order to achieve the above-mentioned object, a water treatment equipment estimation system according to the present invention estimates the price of a water treatment equipment comprising one or a plurality of types of units. It is equipped with a unit database that stores each equipment specification and its equipment price of a plurality of types of units in which various types of component parts are assembled according to predetermined equipment specifications, and for example, the treated water quality and the treated water quantity input through the condition input means. The unit database is searched according to the water treatment specifications including the above, and one or a plurality of units necessary for constructing a water treatment facility corresponding to the water treatment specifications is selected (unit selection means), and For example, from the loan price of the water treatment facility constructed by the unit selected by searching the unit database by the unit selection means. The equipment price is estimated (equipment price estimating means), the configuration of the water treatment equipment constructed by the unit selected by the unit selecting means, and the equipment price estimated by the equipment price estimating means are provided by a predetermined information presenting means. It is characterized by having a function of presenting by using.

【0009】また本発明に係る水処理設備見積システム
は、更に前記各ユニットをそれぞれ構成する構成部品
の、例えば一般的な耐用期間等からなる交換条件とその
部品価格とを記憶した部品データベースを備え、この部
品データベースを検索して前記ユニット選定手段により
選定されたユニットを構成する構成部品中の、使用状況
に応じて交換が必要な構成部品についての交換計画を立
案して(部品交換計画作成手段)、その部品交換計画を
前記情報提示手段を介して提示する機能を備えることを
特徴としている。
Further, the water treatment equipment estimation system according to the present invention further comprises a parts database which stores replacement conditions of the constituent parts constituting each of the units, for example, a general service life and the replacement price thereof. , Searching the parts database, and creating a replacement plan for the constituent parts that constitute the unit selected by the unit selecting means and need to be replaced according to the usage condition (part replacement plan creating means ), And a function of presenting the parts replacement plan via the information presenting means.

【0010】更に本発明に係る水処理設備見積システム
は、前記部品交換計画に従って前記部品データベースを
検索し、選定されたユニットにより構築される水処理設
備の運用に伴って交換が必要となる構成部品の価格を調
べることで該水処理設備の運用価格を見積もり(運用価
格見積手段)、この運用価格を前記部品交換計画と共に
提示する機能を備えることを特徴としている。
Further, the water treatment equipment estimation system according to the present invention searches the parts database according to the parts replacement plan, and requires replacement of the constituent parts as the water treatment equipment constructed by the selected units is operated. It is characterized by having a function of estimating the operation price of the water treatment facility (operation price estimation means) by checking the price of (1) and presenting this operation price together with the parts replacement plan.

【0011】尚、前記条件入力手段および情報提示手段
は、前記ユニット・データベースと前記ユニット選定手
段と前記見積手段とを具備したサーバに対して、所定の
通信回線を介して接続されるものであっても良い。
The condition input means and the information presenting means are connected to a server having the unit database, the unit selecting means and the estimating means via a predetermined communication line. May be.

【0012】[0012]

【発明の実施の形態】以下、図面を参照して本発明の一
実施形態に係るに係る水処理設備見積システムについて
説明する。この水処理設備見積システムは、水処理設備
の構成要素をなす複数種の構成部品を、予め所定の設備
仕様に従って組み立てた複数種の水処理設備ユニットと
して準備しておき、これらのユニットを貸し出して一時
的に所望とする水処理仕様の水処理設備を構築する水処
理設備提供システムに付随して設けられるものである。
BEST MODE FOR CARRYING OUT THE INVENTION A water treatment equipment estimation system according to an embodiment of the present invention will be described below with reference to the drawings. This water treatment equipment quotation system prepares a plurality of types of component parts that are constituent elements of the water treatment equipment as a plurality of types of water treatment equipment units assembled in advance according to predetermined equipment specifications, and lends out these units. It is provided in association with a water treatment facility providing system for temporarily constructing a water treatment facility having a desired water treatment specification.

【0013】ちなみに水処理設備の構成要素をなす複数
種の構成部品は、例えば活性炭フィルタ(CF)、ミリ
ボアフィルタ(MF)、逆浸透膜モジュール(RO)、
電気式脱イオン装置(KCDI)、非再生型イオン交換
器(DZ)、膜式濾過器(PF)、脱気膜(DC)等か
らなる。また前記各ユニット(水処理設備ユニット)
は、例えば所定の大きさのトラック・コンテナ毎に複数
種の構成部品を装備して構築される。そして当該コンテ
ナ(水処理設備ユニット)を貸し出し先の設置現場に据
え付けた後、その給水入口および排水出口を設置現場に
おける水処理水系にそれぞれ連結し、電源を供給するだ
けで作動するように構成される。
By the way, a plurality of types of components constituting the components of the water treatment facility are, for example, activated carbon filter (CF), millibore filter (MF), reverse osmosis membrane module (RO),
It is composed of an electric deionization device (KCDI), a non-regeneration type ion exchanger (DZ), a membrane filter (PF), a degassing membrane (DC) and the like. In addition, each unit (water treatment equipment unit)
Is constructed by equipping a plurality of types of components for each truck / container of a predetermined size. After the container (water treatment equipment unit) is installed at the rented installation site, its water supply inlet and drainage outlet are respectively connected to the water treatment water system at the installation site, and it is configured to operate simply by supplying power. It

【0014】水処理設備見積システムは、このような複
数種の水処理設備ユニットを貸し出して水処理設備を構
築するに際して、どの種別のユニットを用いるか、また
その設備価格が幾らになるかを見積もり、更には上記ユ
ニットを用いて構築された水処理設備の運用コスト等を
見積もるものであり、概略的には図1に示すように構成
される。
The water treatment equipment quotation system estimates which kind of unit to use and how much the equipment price will be when renting out such plural kinds of water treatment equipment units to construct a water treatment equipment. Furthermore, the operating cost of the water treatment facility constructed by using the above unit is estimated, and the configuration is schematically shown in FIG.

【0015】即ち、この水処理設備見積システムは、前
述した複数種のユニットの処理水質や処理水量等からな
る設備仕様とその設備価格(貸出価格)等を記憶したユ
ニット・データベース(DB)1を備えると共に、各ユ
ニットをそれぞれ構成する構成部品の交換条件(交換時
期)とその部品価格とを記憶した部品データベース2を
備える。ちなみにユニット・データベース1に登録され
る各ユニットに関する情報は、そのユニットを構築する
主要構成部品の種類とその使用数、ユニットとしての処
理水量[m3/h]、原水水量[m3/h]、排水水量[m3
h]、原水圧力[MPa]、保証水質(処理水水質)[MΩ・
cm]等からなる設備仕様、およびその貸出価格[円/
月]等からなる。また部品データベース2に登録される
各構成部品に関する情報は、標準的な使用状況における
一般的な耐用期間[月または年]と当該部品の交換に要す
る部品価格等からなる。
That is, this water treatment facility estimation system stores a unit database (DB) 1 which stores facility specifications such as treated water quality and treated water amount of a plurality of types of units and facility price (rental price) thereof. In addition to the above, it also includes a parts database 2 that stores replacement conditions (replacement time) of the constituent parts of each unit and the price of the parts. By the way, the information about each unit registered in the unit database 1 includes the types of main components that make up the unit and the number of used components, the treated water amount [m 3 / h], the raw water amount [m 3 / h]. , Drainage volume [m 3 /
h], raw water pressure [MPa], guaranteed water quality (treated water quality) [MΩ ・
cm] and other equipment specifications, and the rental price [yen /
Moon] etc. Further, the information on each component registered in the component database 2 includes a general service life [month or year] in a standard use situation, a component price required for replacement of the component, and the like.

【0016】さて水処理設備見積システムは、基本的に
は図1に示すようにユーザ(顧客)が要求する水処理設
備の処理水量や処理水水質等からなる水処理仕様を入力
する条件入力部(条件入力手段)3と、この条件入力部
3から入力された水処理仕様に従って前記ユニット・デ
ータベース1を検索して、該水処理仕様に見合う水処理
設備を構築するに必要な1つまたは複数のユニットを選
定する設備構築部(ユニット選定手段)4を備える。こ
の設備構築部4は、ユニット・データベース1に登録さ
れている複数種のユニットの各設備仕様に応じて、前記
条件入力部3から与えられた水処理仕様を満足し、例え
ばそのシステム構成が最小となる水処理設備を構築する
に必要な1つまたは複数のユニットを選定し、選定した
ユニットを用いた水処理設備の推奨システム構成を構築
するものである。
The water treatment equipment estimation system basically has a condition input section for inputting water treatment specifications such as the quantity of treated water and the quality of treated water of a water treatment equipment required by a user (customer) as shown in FIG. (Condition input means) 3 and one or a plurality of units required to search the unit database 1 according to the water treatment specifications input from the condition input unit 3 and construct a water treatment facility that meets the water treatment specifications. The equipment construction unit (unit selection means) 4 for selecting the unit of (4) is provided. This equipment construction unit 4 satisfies the water treatment specifications given from the condition input unit 3 according to the equipment specifications of a plurality of types of units registered in the unit database 1, and, for example, its system configuration is the minimum. One or a plurality of units necessary for constructing the water treatment facility to be used are selected, and a recommended system configuration of the water treatment facility using the selected unit is constructed.

【0017】更にこのシステムは、前記ユニット・デー
タベース1を検索して上記設備構築部4にて選定された
1つまたは複数のユニットの貸出価格をそれぞれ検索
し、これらのユニットにより構築される水処理設備の全
体的な設備価格を見積もる設置コスト見積部(設備価格
見積手段)5を備える。そしてこの設置コスト見積部5
にて求められ設備価格(見積価格)は、前記設備構築部
4にて選定されたユニットにより構築される水処理設備
の情報と共に情報提示部6を介してユーザに提示される
ようになっている。
Further, this system searches the unit database 1 for the lending price of one or a plurality of units selected by the facility construction unit 4, and the water treatment constructed by these units. An installation cost estimation unit (equipment price estimation means) 5 for estimating the overall equipment price of the equipment is provided. And this installation cost estimation unit 5
The equipment price (estimated price) obtained in step 1 is presented to the user via the information presenting part 6 together with information on the water treatment equipment constructed by the unit selected by the equipment constructing part 4. .

【0018】またこのシステムは、前記設備構築部4に
て選定された1つまたは複数のユニットに応じて部品デ
ータベース2を検索し、その水処理期間に応じて前記ユ
ニットを構成する構成部品中の、使用状況に応じて交換
が必要となる部品の交換時期を求め、前記水処理設備の
運用に伴う上記各交換部品についての交換計画を立案す
る部品交換計画作成部(部品交換計画作成手段)7と、
前記部品データベース2を検索して上記交換部品の価格
を求めて前記水処理設備の運用コストを算出する運用コ
スト見積部(運用価格見積手段)8を備える。上記部品
交換計画作成部7にて作成された部品交換計画、および
運用コスト見積部8にて見積もられた運用コストについ
ても、前記情報提示手段6を介してユーザに提示され
る。
This system also searches the parts database 2 according to one or a plurality of units selected by the facility construction unit 4, and selects the constituent parts of the units according to the water treatment period. , A parts replacement plan creation unit (parts replacement plan creation means) 7 that determines the replacement time of the parts that need to be replaced according to the usage status, and draws up a replacement plan for each of the replacement parts that accompanies the operation of the water treatment facility When,
An operation cost estimation unit (operation price estimation means) 8 for searching the parts database 2 for the price of the replacement part and calculating the operation cost of the water treatment facility is provided. The parts replacement plan created by the parts replacement plan creation unit 7 and the operation cost estimated by the operation cost estimation unit 8 are also presented to the user via the information presentation unit 6.

【0019】この際、上述した水処理仕様に加えて水処
理期間(設備使用期間)の情報も入力するようにしてお
けば、入力された水処理期間における部品交換計画とそ
の運用コストを求めることが可能となる。従ってこの運
用コストと前記設備価格との合計を表示するようにすれ
ば、水処理設備を一時的に導入するに際しての総合的な
見積を行うことが可能となる。
At this time, if the information on the water treatment period (equipment use period) is also input in addition to the above-mentioned water treatment specifications, the parts replacement plan and its operating cost in the input water treatment period can be obtained. Is possible. Therefore, by displaying the total of the operation cost and the facility price, it is possible to make a comprehensive estimate when the water treatment facility is temporarily introduced.

【0020】上述した各処理部(機能)4,5,7,8を
備えた見積システムは、基本的には図2にその処理手順
の一例を示すように、先ず条件入力部3を介して水処理
仕様を入力し[ステップS1]、入力された水処理仕様
に従ってユニット・データベース1を検索する[ステッ
プS2]。そしてこの検索結果に従って前記設備構築部
4にて上記水処理仕様に適合する水処理設備を構築する
に必要なユニットを選定し、推奨すべきシステム構成の
水処理設備の例を構築する[ステップS3]。その上で
この水処理設備を構築するユニットの価格を求めて該水
処理設備の設置コストを見積もり[ステップS4]、前
記水処理設備の構成例と共にその見積価格を提示する
[ステップS5]。
The estimation system including the above-mentioned processing units (functions) 4, 5, 7, and 8 basically starts via the condition input unit 3 as shown in an example of the processing procedure in FIG. The water treatment specification is input [step S1], and the unit database 1 is searched according to the input water treatment specification [step S2]. Then, in accordance with this search result, the facility construction unit 4 selects a unit required to construct a water treatment facility that meets the above-mentioned water treatment specifications, and constructs an example of a water treatment facility having a recommended system configuration [step S3. ]. Then, the price of the unit for constructing the water treatment equipment is obtained, the installation cost of the water treatment equipment is estimated [step S4], and the estimated price is presented together with the configuration example of the water treatment equipment [step S5].

【0021】この際、前記水処理設備の構成例に従って
部品データベース2を検索し[ステップS6]、その検
索結果に従って部品交換が必要な構成部品を特定しなが
ら、前記部品交換計画作成部7にて前記ユニットを構成
する構成部品の部品交換計画を作成する[ステップS
7]。更に前記運用コスト見積部8において上記構成部
品の交換に要する運用コスト(部品価格)を見積もり
[ステップS8]、その見積価格を提示する[ステップ
S9]ように作動するものとなっている。
At this time, the parts database 2 is searched according to the configuration example of the water treatment facility [step S6], and the parts replacement plan preparing section 7 is specified according to the search result while specifying the components which need to be replaced. Create a parts replacement plan for the constituent parts of the unit [step S
7]. Further, the operation cost estimating unit 8 operates so as to estimate the operation cost (part price) required for exchanging the component [step S8] and present the estimated price [step S9].

【0022】より具体的に説明すると前述した複数種の
水処理設備ユニットは、例えば図3(a)〜(c)にそれぞ
れ示すように、基本的には活性炭塔、保安フィルタ、ポ
ンプ、および逆浸透膜(RO膜)を順に連結して構成さ
れる。そして逆浸透膜(RO膜)の後段に電気式脱イオ
ン装置(KCDI)を設けるか、或いはデミナー(D
Z)を設けるかによって、その型式(処理方式)が異な
るユニットとして実現されている。即ち、複数種の水処
理設備ユニットは、電気式脱イオン装置(KCDI)を
用いて構成されたユニット(Aタイプ)、デミナーを用
いて構成されたユニット(Bタイプ)、および前記電気
式脱イオン装置(KCDI)に脱気膜ユニットを組み込
んで構成されたユニット(Cタイプ)としてそれぞれ準
備される。
More specifically, the above-mentioned plural kinds of water treatment equipment units basically have activated carbon towers, safety filters, pumps, and reverse filters as shown in FIGS. 3 (a) to 3 (c), respectively. It is configured by connecting permeation membranes (RO membranes) in order. Then, an electric deionization device (KCDI) is provided at the rear stage of the reverse osmosis membrane (RO membrane), or a demister (D
Z) is provided as a unit having a different type (processing method). That is, the plurality of types of water treatment equipment units are a unit (A type) configured by using an electric deionization device (KCDI), a unit (B type) configured by using a dimener, and the electric deionization unit. Each is prepared as a unit (C type) configured by incorporating a degassing membrane unit into the device (KCDI).

【0023】またこれらの各タイプのユニットは、その
処理水量が異なる複数のタイプのユニットとしてそれぞ
れ実現されている。例えば電気式脱イオン装置(KCD
I)を用いたAタイプのユニットは、処理水量が10.
0[m3/h]からなるA1タイプのユニット、および処
理水量が15.0[m3/h]からなるA2タイプのユニッ
トとして2種類準備されている。またデミナーを用いた
Bタイプのユニットは、処理水量が1.0[m3/h]から
なるB1タイプのユニット、処理水量が2.5[m 3/h]
からなるB2タイプのユニット、処理水量が5.0[m3
/h]からなるB3タイプのユニット、処理水量が10.
0[m3/h]からなるB4タイプのユニット、そして処
理水量が15.0[m3/h]からなるB5タイプのユニッ
トとして5種類準備されている。
Each of these types of units
As multiple types of units with different amounts of treated water
Has been realized. For example, an electric deionization device (KCD
The type A unit using I) has a treated water volume of 10.
0 [m3/ H] A1 type unit, and
The amount of water supply is 15.0 [m3/ H] A2 type unit
Two types are prepared as a gift. I also used the denominator
The B type unit has a treated water volume of 1.0 [m3/ H]
B1 type unit, the amount of treated water is 2.5 [m 3/ H]
B2 type unit consisting of, the amount of treated water is 5.0 [m3
/ H] B3 type unit, the amount of treated water is 10.
0 [m3/ H] B4 type unit and
The amount of water supply is 15.0 [m3/ H] B5 type unit
Five kinds are prepared as a gift.

【0024】その他にも、工業用水を扱う場合にその原
水中の濁質等を除去する為のユニットとして、図4(a)
に示すような膜式前処理ユニット(Dタイプ)が準備さ
れ、更に前述した各ユニットにて生成された処理水から
更に高純度な純水を製造する為のサブ・ユニットとし
て、図4(b)に示すような二次純水製造ユニット(Sタ
イプ)が準備されている。尚、二次純水製造ユニット
は、例えばサブタンク、サブポンプ、紫外線(UV)殺
菌機、デミナー、限外濾過(UF)膜を備えて構成され
る。
In addition, as a unit for removing suspended solids in the raw water when handling industrial water, FIG.
A membrane type pretreatment unit (D type) as shown in Fig. 4 is prepared, and as a sub-unit for producing higher-purity pure water from the treated water generated in each unit described above, as a sub-unit, see Fig. 4 (b). The secondary pure water production unit (S type) as shown in () is prepared. The secondary pure water production unit includes, for example, a sub-tank, a sub-pump, an ultraviolet (UV) sterilizer, a deminer, and an ultrafiltration (UF) membrane.

【0025】そして水処理設備を構築する場合には、図
5にその概念を示すように前述したAタイプ、Bタイ
プ、およびCタイプからなる基本水処理ユニットの中か
ら、指定された水処理仕様に適合する水処理設備を構築
するに必要なユニットを選択的に選定し、必要に応じて
更にDタイプのユニットやSタイプのユニットが選定さ
れる。尚、水処理仕様によっては複数の基本水処理ユニ
ットが選定され、これらのユニットを並列に用いること
でその処理水量を確保することも行われる。そしてこれ
らのユニットを用いて、上記水処理仕様に適合する水処
理設備が構築される。
When constructing the water treatment equipment, as shown in the concept of FIG. 5, the water treatment specifications specified from the basic water treatment units of the above-mentioned A type, B type and C type are specified. The units necessary for constructing a water treatment facility that conforms to are selectively selected, and D-type units and S-type units are further selected as needed. Depending on the water treatment specifications, a plurality of basic water treatment units are selected, and these units are used in parallel to secure the amount of treated water. Then, using these units, a water treatment facility that meets the above water treatment specifications is constructed.

【0026】図6は、このようにして複数の種のユニッ
トの中から、指定された水処理仕様に適合する水処理設
備を構築するに必要なユニットを選定するアルゴリズム
の一例を示している。このアルゴリズムを簡単に説明す
ると、先ず前記条件入力部3から入力された水処理仕様
に従って、要求されている処理水水質を判定する[ステ
ップS10]。具体的には処理水水質として5.0[MΩ
・cm]の高純度が要求されているか、或いは1.0[MΩ
・cm]程度の低純度が要求されているかを判定する。そ
して5.0[MΩ・cm]からなる高純度の処理水水質が要
求されている場合には、KCDI搭載型のAタイプまた
はCタイプのユニットを、その選択候補とする[ステッ
プS11]。また逆に1.0[MΩ・cm]程度の低純度の
処理水水質が要求されている場合には、デミナー搭載型
のBタイプのユニットを、その選択候補とする[ステッ
プS12]。
FIG. 6 shows an example of an algorithm for selecting a unit required for constructing a water treatment facility that meets a specified water treatment specification from a plurality of types of units in this way. To briefly explain this algorithm, first, the required treated water quality is determined according to the water treatment specification input from the condition input unit 3 [step S10]. Specifically, the treated water quality is 5.0 [MΩ
・ High purity of cm] is required, or 1.0 [MΩ
・ Determine whether low purity of about [cm] is required. If a high-purity treated water quality of 5.0 [MΩ · cm] is required, the KCDI-installed type A or C type unit is selected as the selection candidate [step S11]. On the other hand, when a low-purity treated water quality of about 1.0 [MΩ · cm] is required, the denominator-installed B type unit is selected as the selection candidate [step S12].

【0027】そしてAタイプまたはCタイプのユニット
を選択候補とした場合には、次にユーザが、より高純度
な水処理を可能とする脱気膜タイプでの処理を望んでい
るか否かを判定し[ステップS13]、脱気膜タイプで
の処理を望んでいる場合には電気式脱イオン装置(KC
DI)に脱気膜ユニットを組み込んで構成されたCタイ
プのユニットを選定する[ステップS14]。これに対
して脱気膜タイプでの処理を要求していない場合には、
次に要求される処理水量を判定し[ステップS15]、
その処理水量に応じて、例えば処理水量が10.0[m3
/h]のA1タイプのユニット、または処理水量が15.
0[m3/h]のA2タイプのユニットを選定する[ステ
ップS16]。この際、1台のユニットだけではその処
理水量が不足するような場合には、A1タイプまたはA
2タイプのユニットが複数台選定される。
When the A type or C type unit is selected as a selection candidate, it is next determined whether or not the user desires a degassing membrane type treatment that enables higher-purity water treatment. [Step S13] If the degassing membrane type process is desired, the electric deionization device (KC
A C type unit configured by incorporating a degassing membrane unit into DI) is selected [step S14]. On the other hand, when the degassing membrane type processing is not required,
Next, the required amount of treated water is determined [step S15],
Depending on the amount of treated water, for example, the amount of treated water is 10.0 [m 3
/ H] A1 type unit, or the amount of treated water is 15.
An A2 type unit of 0 [m 3 / h] is selected [step S16]. At this time, if the amount of treated water is insufficient with only one unit, type A1 or A
Two types of units are selected.

【0028】一方、デミナー搭載型のBタイプのユニッ
トを選択候補とした場合には、前記水処理仕様に示され
る処理水量を判定し[ステップS17]、前述したBタ
イプの5種類のユニットの中からその処理水量に応じた
ユニットを選定する[ステップS18]。具体的には、
例えば処理水量が1.0[m3/h]の場合にはB1タイプ
のユニットを、処理水量が2.5[m3/h]の場合にはB
2タイプのユニットを、処理水量が5.0[m3/h]の場
合にはB3タイプのユニットを、処理水量が10.0[m
3/h]の場合にはB4タイプのユニットを、そして処理
水量が15.0[m3/h]の場合にはB5タイプのユニッ
トを選定する。この場合においても1台のユニットだけ
ではその処理水量が不足する場合には、B1〜B5タイ
プのユニットの中の複数台を選定する。
On the other hand, in the case where the type B unit equipped with a dimener is selected as a candidate for selection, the amount of treated water indicated in the water treatment specification is judged [step S17], and among the five types of unit B type described above. Then, a unit corresponding to the amount of treated water is selected [step S18]. In particular,
For example, when the amount of treated water is 1.0 [m 3 / h], B1 type unit is used. When the amount of treated water is 2.5 [m 3 / h], B1 type unit is used.
2 types of units, when the amount of treated water is 5.0 [m 3 / h], B3 type units, the amount of treated water is 10.0 [m
In case of 3 / h], B4 type unit is selected, and in case of treated water amount of 15.0 [m 3 / h], B5 type unit is selected. Even in this case, if the amount of treated water is insufficient with only one unit, a plurality of B1-B5 units are selected.

【0029】以上のようにして水処理の基本となる1台
または複数台のユニットを選定したならば、次に更なる
高純度化が要求されているか否かを判定する[ステップ
S19]。即ち、高純度の水処理を可能とする前述した
AタイプまたはCタイプのユニットを選定したにも拘わ
らず、更なる高純度化が要求されている否かを判定す
る。そして半導体製造に用いるような高々度の純度が要
求されているような場合には、AタイプまたはCタイプ
のユニットによる処理水を更に二次処理する為のSタイ
プのユニットを追加選定する[ステップS20]。
After selecting one or a plurality of units to be the basis of water treatment as described above, it is next determined whether or not further purification is required [step S19]. That is, it is determined whether or not further high purification is required despite the selection of the above-mentioned A type or C type unit that enables high-purity water treatment. Then, when a high degree of purity such as that used in semiconductor manufacturing is required, an S type unit for further secondary treatment of the treated water by the A type or C type unit is additionally selected [step S20. ].

【0030】また処理対象とする原水が市水であるか、
或いは工業用水であるかを判定する[ステップS2
1]。そして原水が工業用水である場合には、原水中の
濁質等を除去する為のDタイプのユニットを追加選定す
る[ステップS22]。尚、原水が市水である場合や、
前述した更なる高純度が要求されていない場合には、D
タイプおよび/またはSタイプのユニットを追加しない
ことは言うまでもない。
Whether the raw water to be treated is city water,
Alternatively, it is determined whether the water is industrial water [step S2
1]. If the raw water is industrial water, a D type unit for removing turbidity in the raw water is additionally selected [step S22]. If the raw water is city water,
If higher purity as described above is not required, D
It goes without saying that type and / or S type units are not added.

【0031】このようにして条件入力部3から入力され
た水処理仕様に適合する水処理設備を構築するに必要な
ユニットを選定したならば、そのユニットを用いて全体
のシステム構成を決定する[ステップS23]。即ち、
Aタイプ、Bタイプ、またはCタイプからなる1台また
は複数台のユニットにて基本的な水処理設備を構築し、
必要に応じてその前段にDタイプのユニットを、またそ
の後段にSタイプのユニットを設けて全体的な水処理設
備のシステム構成を決定する。
When the unit necessary for constructing the water treatment equipment conforming to the water treatment specification input from the condition input unit 3 is selected in this way, the unit is used to determine the entire system configuration [ Step S23]. That is,
Build a basic water treatment facility with one or more units of A type, B type, or C type,
If necessary, a D type unit is provided in the preceding stage and an S type unit is provided in the subsequent stage to determine the overall system configuration of the water treatment facility.

【0032】このように本発明に係る見積システムによ
れば、条件入力部3から入力された水処理仕様に従い、
その水処理仕様に適合する水処理設備を構築するに必要
なユニットが選定されて、推奨すべき水処理設備のシス
テム構成として提示される。そしてこのシステム構成の
下で、その水処理設備を設置するに必要な設備コストが
見積もられてユーザに提示される。更にはその水処理設
備を構築するユニットにおける、例えば活性炭やイオン
交換樹脂等を含む交換部品について、当該水処理設備を
運用した際の部品交換計画が立案され、部品交換に伴う
運用コストが見積もられることになる。
As described above, according to the estimation system of the present invention, according to the water treatment specification input from the condition input unit 3,
The units required to construct a water treatment facility that meets the water treatment specifications are selected and presented as the recommended water treatment system configuration. Under this system configuration, the equipment cost required to install the water treatment equipment is estimated and presented to the user. Furthermore, for the replacement parts including, for example, activated carbon and ion exchange resin in the unit that constructs the water treatment facility, a part replacement plan is planned when the water treatment facility is operated, and the operating cost associated with the part replacement is estimated. It will be.

【0033】従ってユーザ(顧客)においては、必要な
水処理条件(水処理仕様)を入力するだけで、その水処
理に必要な水処理設備を構築するに必要なユニットと、
その水処理設備を設置するに必要なコスト(設備価
格)、更にはその運用コスト等が提示されるので、一時
的な水処理設備の設置計画を容易に企画することが可能
となる。しかもその運用コストを含めて、水処理設備の
設置計画を立てることが可能となる等の実用上多大なる
効果が奏せられる。
Therefore, the user (customer) only needs to input the necessary water treatment conditions (water treatment specifications) and the units necessary for constructing the water treatment equipment necessary for the water treatment,
Since the cost (equipment price) required to install the water treatment equipment, the operating cost, and the like are presented, it becomes possible to easily plan a temporary water treatment equipment installation plan. Moreover, including the operation cost, it is possible to achieve a great practical effect such that it becomes possible to make a plan for installing the water treatment facility.

【0034】尚、本発明は上述した実施形態に限定され
るものではない。例えばデータベース1,2や設備構築
部4および設置コスト見積部5等の見積機能を備えたサ
ーバを準備し、パーソナルコンピュータ等の端末から上
記サーバをインターネット等の通信回線を介してアクセ
スして水処理設備に対する見積処理を実行するように構
成することも可能である。この場合には、上記端末とし
て条件入力部3と情報提示部6の機能(例えばキーボー
ドとディスプレイ)を備えるだけで良く、見積システム
の利用性を高めることが可能となる。またパーソナルコ
ンピュータ自体に上述した見積システムを組み込むこと
も勿論可能である。
The present invention is not limited to the above embodiment. For example, a server having an estimation function such as the databases 1 and 2, the facility construction unit 4, and the installation cost estimation unit 5 is prepared, and the server is accessed from a terminal such as a personal computer through a communication line such as the Internet to perform water treatment. It can also be configured to perform a quotation process for the equipment. In this case, only the functions of the condition input unit 3 and the information presenting unit 6 (for example, a keyboard and a display) need to be provided as the terminal, and the usability of the estimation system can be improved. It is of course possible to incorporate the above-mentioned estimation system into the personal computer itself.

【0035】またここでは前述したA,B,C,D,Sタイ
プのユニットを用いて水処理設備を構築するものとして
説明したが、更に別の仕様のユニットを用いることも可
能である。また各ユニットの大きさ(仕様)について
は、例えばトラック・コンテナに搭載可能な規模のもの
とすれば十分であり、その大きさについても特に限定さ
れない。その他、本発明はその要旨を逸脱しない範囲で
種々変形して実施することができる。
Although the water treatment equipment is constructed using the units of A, B, C, D and S types described above, it is also possible to use units of other specifications. The size (specification) of each unit is sufficient if it can be mounted in, for example, a truck / container, and the size is not particularly limited. In addition, the present invention can be variously modified and implemented without departing from the scope of the invention.

【0036】[0036]

【発明の効果】以上説明したように本発明によれば、要
求された水処理仕様に適合する水処理設備を構築するに
必要な水処理ユニットを選定し、そのユニットを用いて
構築される水処理設備の価格(設備価格や運用価格)を
容易に見積もることができるので、各種工場やプラント
等において一時的に水処理設備を必要とする場合等、そ
の設置計画を容易に立てることができる等の実用上多大
なる効果が奏せられる。
As described above, according to the present invention, a water treatment unit required for constructing a water treatment facility that meets the required water treatment specifications is selected, and the water constructed using the unit is selected. Since the price of the treatment equipment (equipment price and operating price) can be easily estimated, the installation plan can be easily created when the water treatment equipment is temporarily needed in various factories or plants. The practically great effect can be obtained.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施形態に係る水処理設備見積シス
テムの概略構成図。
FIG. 1 is a schematic configuration diagram of a water treatment facility estimation system according to an embodiment of the present invention.

【図2】図1に示す見積システムにおける概略的な処理
手順の流れを示す図。
FIG. 2 is a diagram showing a flow of a schematic processing procedure in the estimation system shown in FIG.

【図3】水処理設備の構成要素をなす複数種の構成部品
を、予め所定の設備仕様に従って組み立てた基本的な水
処理設備ユニットの構成例を示す図。
FIG. 3 is a diagram showing a configuration example of a basic water treatment facility unit in which a plurality of types of component parts constituting the components of the water treatment facility are assembled in advance in accordance with predetermined facility specifications.

【図4】図3に示す水処理設備ユニットに追加して用い
られるユニットの構成例を示す図。
FIG. 4 is a diagram showing a configuration example of a unit additionally used in the water treatment facility unit shown in FIG.

【図5】複数のユニットを用いて構築される水処理設備
の基本的なシステム系統の例を示す図。
FIG. 5 is a diagram showing an example of a basic system system of a water treatment facility constructed by using a plurality of units.

【図6】水処理仕様に応じたユニットを選択する為のア
ルゴリズムの例を示す図。
FIG. 6 is a diagram showing an example of an algorithm for selecting a unit according to water treatment specifications.

【符号の説明】[Explanation of symbols]

1 ユニット・データベース 2 部品データベース 3 条件入力部 4 設備構築部(ユニット選定手段) 5 設備コスト見積部(設備価格見積手段) 6 情報提示部 7 部品交換計画作成部(部品交換計画作成手段) 8 運用コスト見積部(運用価格見積手段) 1 unit database 2 parts database 3 Condition input section 4 Facility construction department (unit selection means) 5 Equipment cost estimation department (equipment price estimation means) 6 Information presentation section 7 Parts Replacement Plan Creation Department (Parts Replacement Plan Creation Means) 8 Operation cost estimation department (operation price estimation means)

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 1つまたは複数種のユニットからなる水
処理設備の見積システムであって、 複数種の構成部品を所定の設備仕様に従って組み立てた
複数種のユニットの各設備仕様とその設備価格とを記憶
したユニット・データベースと、 水処理仕様を入力する条件入力手段と、 前記ユニット・データベースを検索して上記水処理仕様
に見合う水処理設備を構築するに必要な1つまたは複数
のユニットを選定するユニット選定手段と、前記ユニッ
ト・データベースを検索して上記ユニット選定手段によ
り選定されたユニットにより構築される水処理設備の設
備価格を見積もる設備価格見積手段と、 前記ユニット選定手段により選定されたユニットにより
構築される水処理設備の構成とその設備価格とを提示す
る情報提示手段とを具備したことを特徴とする水処理設
備見積システム。
1. A water treatment equipment quotation system comprising one or a plurality of types of units, wherein the equipment specifications and equipment prices of a plurality of types of units in which a plurality of types of components are assembled according to predetermined equipment specifications are provided. A unit database storing therein, condition input means for inputting a water treatment specification, and selecting one or a plurality of units required to construct a water treatment facility matching the water treatment specification by searching the unit database. Unit selecting means for estimating the equipment price of the water treatment facility constructed by the unit selected by the unit selecting means by searching the unit database, and the unit selected by the unit selecting means The information presenting means for presenting the configuration of the water treatment facility constructed by Water treatment equipment estimate system according to claim.
【請求項2】 請求項1に記載の水処理設備見積システ
ムにおいて、 更に前記各ユニットをそれぞれ構成する構成部品の交換
条件とその部品価格とを記憶した部品データベースと、 この部品データベースを検索して前記ユニット選定手段
により選定されたユニットを構成する構成部品の交換計
画を立案する部品交換計画作成手段と、この部品交換計
画作成手段が立案した部品交換計画を前記情報提示手段
を介して出力する手段とを備えることを特徴とする水処
理設備見積システム。
2. The water treatment facility estimation system according to claim 1, further comprising: a parts database storing replacement conditions of the parts constituting each of the units and parts prices thereof, and searching the parts database. A part replacement plan creating means for creating a replacement plan for the constituent parts of the unit selected by the unit selecting means, and a means for outputting the part replacement plan created by the part replacement plan creating means via the information presenting means. A water treatment equipment estimation system comprising:
【請求項3】 請求項2に記載の水処理設備見積システ
ムにおいて、 更に前記部品交換計画作成手段が立案した部品交換計画
に従って前記部品データベースを検索して、前記水処理
設備の運用に必要な運用価格を見積もる運用価格見積手
段を備えることを特徴とする水処理設備見積システム。
3. The water treatment equipment estimation system according to claim 2, further searching the parts database in accordance with the parts replacement plan prepared by the parts replacement plan creating means, and operating the water treatment equipment to operate. A water treatment equipment estimation system comprising an operating price estimation means for estimating a price.
【請求項4】 前記条件入力手段および情報提示手段
は、前記ユニット・データベースと前記ユニット選定手
段と前記見積手段とを具備したサーバに対して、所定の
通信回線を介して接続されるものである請求項1に記載
の水処理設備見積システム。
4. The condition input means and the information presenting means are connected to a server including the unit database, the unit selecting means and the estimating means via a predetermined communication line. The water treatment equipment estimation system according to claim 1.
JP2001310283A 2001-10-05 2001-10-05 Water treatment plant estimation system Pending JP2003114989A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001310283A JP2003114989A (en) 2001-10-05 2001-10-05 Water treatment plant estimation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001310283A JP2003114989A (en) 2001-10-05 2001-10-05 Water treatment plant estimation system

Publications (1)

Publication Number Publication Date
JP2003114989A true JP2003114989A (en) 2003-04-18

Family

ID=19129285

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001310283A Pending JP2003114989A (en) 2001-10-05 2001-10-05 Water treatment plant estimation system

Country Status (1)

Country Link
JP (1) JP2003114989A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013516707A (en) * 2010-01-08 2013-05-13 フルーア・テクノロジーズ・コーポレイション A system for estimating the cost of preparing a new industrial plant for operation.
JP2013220389A (en) * 2012-04-17 2013-10-28 Japan Organo Co Ltd Construction support apparatus for water treatment system
JP2016196007A (en) * 2016-08-16 2016-11-24 オルガノ株式会社 Construction support apparatus of water treatment system and construction support program of water treatment system
JP2017170274A (en) * 2016-03-18 2017-09-28 栗田工業株式会社 Proposal support device, proposal support method, and program for water treatment system
JP2018142104A (en) * 2017-02-27 2018-09-13 栗田工業株式会社 Water treatment system proposal supporting apparatus, water treatment system proposal supporting method, and program
JP7363644B2 (en) 2020-03-31 2023-10-18 栗田工業株式会社 Design support system and design support method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013516707A (en) * 2010-01-08 2013-05-13 フルーア・テクノロジーズ・コーポレイション A system for estimating the cost of preparing a new industrial plant for operation.
JP2013220389A (en) * 2012-04-17 2013-10-28 Japan Organo Co Ltd Construction support apparatus for water treatment system
JP2017170274A (en) * 2016-03-18 2017-09-28 栗田工業株式会社 Proposal support device, proposal support method, and program for water treatment system
JP2016196007A (en) * 2016-08-16 2016-11-24 オルガノ株式会社 Construction support apparatus of water treatment system and construction support program of water treatment system
JP2018142104A (en) * 2017-02-27 2018-09-13 栗田工業株式会社 Water treatment system proposal supporting apparatus, water treatment system proposal supporting method, and program
JP7363644B2 (en) 2020-03-31 2023-10-18 栗田工業株式会社 Design support system and design support method

Similar Documents

Publication Publication Date Title
Lu et al. Optimum design of reverse osmosis system under different feed concentration and product specification
Zhu et al. Effect of thermodynamic restriction on energy cost optimization of RO membrane water desalination
Lesjean et al. Survey of the European MBR market: trends and perspectives
Yang et al. Water network optimization with wastewater regeneration models
JP2013220389A (en) Construction support apparatus for water treatment system
Fadzil et al. Industrial site water minimisation via one-way centralised water reuse header
Lu et al. The design of reverse osmosis systems with multiple-feed and multiple-product
JP2003114989A (en) Water treatment plant estimation system
JP6200046B2 (en) Water treatment system construction support apparatus and water treatment system construction support program
JP6107303B2 (en) Water treatment process simulation apparatus, method, and program
Karuppiah et al. Optimal design of reverse osmosis‐based water treatment systems
Williams et al. Simultaneous optimization of size and short-term operation for an RO plant
JP4718873B2 (en) Control device for membrane filtration equipment
Zhu et al. Optimal synthesis of water networks for addressing high-concentration wastewater in coal-based chemical plants
JP2002282839A (en) System for leasing water treatment equipment
JP6682935B2 (en) Proposal support device for water treatment system, proposal support method, and program
Bilton et al. A computer architecture for the automatic design of modular systems with application to photovoltaic reverse osmosis
Jia et al. Inter-plant water integration with considerations of water supply constraint and differential water price
Kumar et al. Cost evaluation of water and wastewater treatment plants using water price index
JP6848368B2 (en) Water treatment process design equipment, methods and programs
Suggala et al. Real coded genetic algorithm for optimization of pervaporation process parameters for removal of volatile organics from water
JP6558458B1 (en) Water treatment facility management equipment
Croft et al. Synthesis of an optimal schedule and water network for a multipurpose multiproduct textile industry through a sequential MILP-NLP technique
Hamza et al. Studies on the design of reverse osmosis water desalination systems for cost and energy efficiency
Pinto et al. Design and commissioning of a community scale solar powered membrane-based water purification system in Haiti

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040924

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070328

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070523

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20070620