JP2003293364A - Method for constructing pile - Google Patents
Method for constructing pileInfo
- Publication number
- JP2003293364A JP2003293364A JP2002094004A JP2002094004A JP2003293364A JP 2003293364 A JP2003293364 A JP 2003293364A JP 2002094004 A JP2002094004 A JP 2002094004A JP 2002094004 A JP2002094004 A JP 2002094004A JP 2003293364 A JP2003293364 A JP 2003293364A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- spiral blade
- tip
- blade
- soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、建物などを支える
杭の施工方法、特に、支持層の深い軟弱地盤に対して有
効的に用いることができる杭の施工方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a pile for supporting a building or the like, and more particularly to a method for constructing a pile which can be effectively used for soft ground having a deep support layer.
【0002】[0002]
【従来の技術及び課題】軟弱地盤において支持層が深
く、そのため施工機械の能力の限界などによって、杭を
支持層まで打ち込むのが困難であるような場合には、従
来より、多翼杭が用いられている。しかしながら、多翼
杭は、杭軸の外周部に多数の翼を取り付けなければなら
ず、その製造コストが高くつくという問題があった。2. Description of the Related Art Conventionally, multi-blade piles have been used when it is difficult to drive the piles to the support layer due to the depth of the support layer in soft ground and therefore due to the limit of capacity of construction machines. Has been. However, the multi-blade pile has a problem that a large number of blades must be attached to the outer peripheral portion of the pile shaft, resulting in high manufacturing cost.
【0003】本発明は、上記のような従来の問題点に鑑
み、多翼杭のような多くの翼を必要とせず、しかも、軟
弱地盤において大きな支持力を得ることができる杭の施
工方法を提供することを課題とする。In view of the above conventional problems, the present invention provides a method for constructing a pile which does not require many blades such as a multi-blade pile and can obtain a large supporting force on soft ground. The challenge is to provide.
【0004】[0004]
【課題を解決するための手段】上記の課題は、先端側の
外周に側方に張り出す翼を備えた中杭と、内径寸法が中
杭の外周径よりも大きく、かつ、先端側の外周に側方に
張り出す螺旋翼を備えた筒状の外杭とを用い、中杭を地
盤に回転圧入により打ち込んだのち、外杭を中杭に対し
て同心状となるように地盤に回転圧入により打ち込んで
いき、外杭の先端側螺旋翼が地中で中杭の先端翼よりも
所定の高さ寸法上方に間隔をおいた状態で外杭の打込み
を停止し、しかる後、外杭を、その深度を固定しながら
逆回転させることにより、外杭の先端側螺旋翼でそれよ
りも上方の土を下方に送り込んでいき、中杭の先端翼と
外杭の先端側螺旋翼との間の領域の土を圧縮させていく
ことを特徴とする杭の施工方法によって解決される。[Means for Solving the Problems] The above-mentioned problems are as follows: a middle pile provided with blades projecting laterally on the outer circumference on the tip side, and an outer circumference on the tip side having an inner diameter larger than the outer diameter of the middle pile. Using a cylindrical outer pile with spiral wings protruding laterally, the inner pile was driven into the ground by rotational press-fitting, and then the outer pile was rotationally press-fitted into the ground so as to be concentric with the medium pile. Drive the outer pile with the tip side spiral blade of the outer pile at a predetermined height above the tip blade of the middle pile in the ground, and stop the driving of the outer pile. , By rotating it in reverse while fixing the depth, the soil above the tip of the spiral wing of the outer pile is sent downward, and between the tip wing of the middle pile and the tip spiral of the outer pile. It is solved by a method of constructing a pile, which is characterized by compressing the soil in the area.
【0005】この方法では、中杭と外杭とに備えられた
翼によって、軟弱地盤であっても支持力を得ることがで
きるのはもちろん、外杭を打ち込んだのちにこれを逆回
転させることで中杭の先端翼と外杭の先端側螺旋翼との
間の領域の土を圧縮させるようにしているので、この領
域部分の地盤の圧縮によって、非常に大きな支持力が得
られる。According to this method, the blades provided on the middle pile and the outer pile can obtain the supporting force even on soft ground, and the outer pile can be driven in reverse after being driven. Since the soil in the area between the tip blade of the middle pile and the tip side spiral blade of the outer pile is compressed, a very large bearing force can be obtained by compressing the ground in this area.
【0006】上記の方法において、外杭が、その基端側
の外周に側方に張り出す螺旋翼を備え、外杭の打込み
を、その基端側螺旋翼が地中に入り込んだ状態で停止
し、外杭の逆回転によってその基端側螺旋翼でそれより
も上方の土を下方に送り込むようにするのもよい。In the above method, the outer pile is provided with a spiral blade projecting laterally on the outer periphery of the base end side, and the driving of the outer pile is stopped in a state where the base end side spiral blade penetrates into the ground. However, it is also possible to send the soil above it downward by the spiral blade on the base end side by the reverse rotation of the outer pile.
【0007】この場合は、外杭の先端側螺旋翼よりも上
方の土を中杭の先端翼と外杭の先端側螺旋翼との間の領
域にスムーズに送り込んでいくことができ、中杭の先端
翼と外杭の先端側螺旋翼との間の領域を効果的に圧縮し
ていくことができる。In this case, the soil above the tip side spiral blade of the outer pile can be smoothly fed into the region between the tip blade of the middle pile and the tip side spiral blade of the outer pile. It is possible to effectively compress the region between the tip blade of the and the tip side spiral blade of the outer pile.
【0008】外杭を逆回転させている間に外杭の基端側
螺旋翼の上方の土がなくなるような場合には、外杭の基
端側螺旋翼の上方に土を補給していけば、外杭の基端側
螺旋翼と先端側螺旋翼との間の領域における外杭外周面
と地盤との摩擦力を低くしてしまうこともない。If the soil above the base side spiral blade of the outer pile is lost while the outer pile is rotated in the reverse direction, replenish the soil above the base side spiral blade of the outer pile. For example, the frictional force between the outer peripheral surface of the outer pile and the ground in the region between the base side spiral blade and the front side spiral blade of the outer pile is not reduced.
【0009】外杭の基端側翼のピッチを外杭の先端側翼
のピッチよりも大きくし、外杭の逆回転中、外杭の基端
側螺旋翼と先端側螺旋翼との間の領域の土が圧縮される
ようにする場合は、より大きな支持力を得ることができ
る。The pitch of the blades on the base end side of the outer pile is made larger than the pitch of the blades on the tip end side of the outer pile, and the region between the base end spiral blade and the tip end spiral blade of the outer pile is rotated during the reverse rotation of the outer pile. Greater bearing capacity can be obtained if the soil is to be compressed.
【0010】そして、この方法によれば、翼の数は、従
来の多翼杭の場合に比べて少なくすることができ、杭の
コストを低く抑えることができるし、また、施工におい
ても、中杭と外杭とを同じ回転圧入機を用いて打ち込ん
で行くことができ、しかも、同じ回転圧入機で外杭の逆
回転を行うことができ、施工もコストを高くすることな
く行っていくことができる。According to this method, the number of blades can be reduced as compared with the case of the conventional multi-blade pile, the cost of the pile can be kept low, and also in the construction, The pile and the outer pile can be driven in using the same rotary press-fitting machine, and the outer pile can be rotated in the reverse direction with the same rotary press-fitting machine, and construction can be performed without increasing the cost. You can
【0011】[0011]
【発明の実施の形態】次に、本発明の実施形態を図1乃
至図4に基づいて説明する。BEST MODE FOR CARRYING OUT THE INVENTION Next, an embodiment of the present invention will be described with reference to FIGS.
【0012】本実施形態の施工方法において使用する杭
は、図1に示すように、中杭1と外杭2とからなる。As shown in FIG. 1, the pile used in the construction method of this embodiment comprises an intermediate pile 1 and an outer pile 2.
【0013】中杭1は鋼管からなっており、その先端側
の外周に、側方に張り出す翼3が一体的に備えられてい
る。なお、この翼3は、螺旋翼からなっていてもよい
し、螺旋によらない拡底機能を備えた翼からなっていて
もよい。また、中杭1は鋼管に限らず形鋼や中実材など
からなっていてもよい。The intermediate pile 1 is made of a steel pipe, and a wing 3 protruding laterally is integrally provided on the outer periphery of the tip end side thereof. The blade 3 may be a spiral blade or a blade having a bottom expanding function that does not depend on a spiral. Further, the middle pile 1 is not limited to the steel pipe, and may be made of shaped steel or solid material.
【0014】外杭2も同じく鋼管からなっているが、た
だ、その内径寸法が中杭1の外径寸法よりも大きく設計
されていて、中杭1を外杭2の内部に差し込むことがで
きるようになっている。そして、外杭2の基端側の外周
と先端側の外周の上下2箇所に螺旋方向を同じくする螺
旋翼4,5が一体的に備えられ、外杭2の長さ寸法は、
中杭1よりも短く設計されていて、外杭2の内部に中杭
1を、基端部高さ位置を同じ高さ位置にするように差し
込んだ状態で、外杭2の先端側螺旋翼4が中杭1の長さ
方向の中間部に位置し、この先端側螺旋翼4と中杭1の
先端翼3とが所定の寸法だけ間隔をおくように設計され
ている。なお、外杭2において先端側と基端側の螺旋翼
4,5は同じ螺旋方向のものからなっている。The outer pile 2 is also made of steel pipe, but its inner diameter is designed to be larger than the outer diameter of the middle pile 1 so that the middle pile 1 can be inserted inside the outer pile 2. It is like this. Then, spiral blades 4 and 5 having the same spiral direction are integrally provided at upper and lower two locations of the outer periphery on the base end side and the outer periphery on the tip end side of the outer pile 2, and the length dimension of the outer pile 2 is
It is designed to be shorter than the middle pile 1 and the middle pile 1 is inserted inside the outer pile 2 so that the base end height position is the same height position. 4 is located in the middle of the middle pile 1 in the longitudinal direction, and the tip side spiral blade 4 and the tip blade 3 of the middle pile 1 are designed to be spaced by a predetermined dimension. In the outer pile 2, the spiral blades 4 and 5 on the front end side and the base end side have the same spiral direction.
【0015】支持層の深い軟弱地盤6に対する杭の施工
は、上記の中杭1と外杭2を用いて次のようにして行
う。即ち、図2(イ)に示すように、まず、軟弱地盤6
に対し、外杭2を建柱車等の回転圧入機で回転圧入して
打ち込む。Construction of piles on the soft ground 6 having a deep support layer is carried out as follows using the above-mentioned middle pile 1 and outer pile 2. That is, as shown in FIG. 2A, first, the soft ground 6
On the other hand, the outer stake 2 is rotationally press-fitted with a rotary press-fitting machine such as a building column car and driven.
【0016】次いで、図2(ロ)及び図3(ハ)に示す
ように、外杭2を中杭1に対して同心状となるようにし
て地盤6に回転圧入により打ち込んでいき、図3(ニ)
に示すように、外杭2の基端側螺旋翼5が地中に入り込
み、かつ、外杭2の先端側螺旋翼4が地中で中杭1の先
端翼3よりも所定の高さ寸法上方に間隔をおいた状態
で、外杭2の打込みを停止する。なお、外杭2の回転の
方向は、螺旋翼4,5が地盤6に食い込んでいく方向で
ある。Next, as shown in FIGS. 2B and 3C, the outer pile 2 is driven into the ground 6 by rotary press-fitting so as to be concentric with the middle pile 1, and FIG. (D)
As shown in FIG. 3, the base side spiral blades 5 of the outer piles 2 penetrate into the ground, and the tip side spiral blades 4 of the outer piles 2 have a predetermined height dimension below the tip wings 3 of the underground piles 1. The driving of the outer pile 2 is stopped with a space above. The direction of rotation of the outer pile 2 is the direction in which the spiral blades 4 and 5 bite into the ground 6.
【0017】しかる後、図4(ホ)に示すように、外杭
2を、その深度を固定しながら逆回転させていく。これ
により、図中に矢印で示すように、外杭2の先端側と基
端側の各螺旋翼4,5が、それらの螺旋送り機能によっ
て、土を上から下へと送っていき、中杭1の先端翼3と
外杭2の先端側螺旋翼4との間の領域の土7が圧縮され
ていく。その際、外杭2の基端側の螺旋翼5の上方の土
8は、外杭2の逆回転によって下に送り込まれて減少し
ていくので、補給用の土9を杭の周囲に用意し、減少分
を補給していくようにするとよい。Thereafter, as shown in FIG. 4 (e), the outer pile 2 is reversely rotated while fixing the depth thereof. As a result, as shown by the arrow in the figure, the spiral blades 4 and 5 on the tip side and the base end side of the outer pile 2 send soil from the top to the bottom by their spiral feeding function, The soil 7 in the region between the tip blade 3 of the pile 1 and the tip spiral blade 4 of the outer pile 2 is compressed. At that time, the soil 8 above the spiral blade 5 on the base end side of the outer pile 2 is fed downward by the reverse rotation of the outer pile 2 and is reduced, so that the soil 9 for supply is prepared around the pile. However, it is better to replenish the reduced amount.
【0018】その結果、図4(へ)に示すように、中杭
1の先端翼3と外杭2の先端側螺旋翼4との間の領域
に、翼3,4よりも外方に膨らむこぶ状の圧縮部7が形
成される。このこぶ状膨らみ圧縮部7によって非常に大
きな支持力が得られる。As a result, as shown in FIG. 4 (), the region between the tip blade 3 of the middle pile 1 and the tip side spiral blade 4 of the outer pile 2 bulges outward more than the blades 3, 4. A bump-shaped compression portion 7 is formed. A very large supporting force can be obtained by this hump-shaped bulging compression section 7.
【0019】しかも、外杭2の基端側螺旋翼5と先端側
螺旋翼4との間の領域10については、基端側螺旋翼5
によって土9を補給していくので、その領域10におけ
る外杭2の外周面と地盤6との摩擦力も低くなることは
ない。なお、外杭2の基端側螺旋翼5のピッチを外杭2
の先端側螺旋翼4のピッチよりも大きくし、外杭2の逆
回転中、外杭2の基端側翼5と先端側翼4との間の領域
の土10が圧縮されるようにしておけば、より大きな支
持力を得ることができる。もちろん、各翼3,4,5に
よっても大きな支持力が得られる。Moreover, regarding the region 10 between the proximal spiral blade 5 and the distal spiral blade 4 of the outer pile 2, the proximal spiral blade 5 is provided.
Since the soil 9 is replenished by the soil 9, the frictional force between the outer peripheral surface of the outer pile 2 and the ground 6 in the area 10 does not decrease. In addition, the pitch of the base end side spiral blade 5 of the outer pile 2 is set to the outer pile 2
If the pitch is larger than the pitch of the tip side spiral wing 4 of the above, and the soil 10 in the region between the base side wing 5 of the outer pile 2 and the tip side wing 4 is compressed during the reverse rotation of the outer pile 2. , A larger supporting force can be obtained. Of course, a large supporting force can be obtained by the blades 3, 4, 5 as well.
【0020】このように、上記の杭施工方法によれば、
支持層の深い軟弱地盤6においても大きな支持力を得る
ことができ、しかも、翼の数は、従来の多翼杭の場合に
比べて少なくすることができ、即ち、3つの翼でよく、
杭のコストを低く抑えることができる。また、施工にお
いても、中杭1と外杭2とを同じ回転圧入機を用いて打
ち込んで行けばよく、しかも、同じ回転圧入機で外杭2
を逆回転させることができ、施工もコストを高くするこ
となく行っていくことができる。更に、杭がいわゆる内
外二重構造になっているので、水平力に対しても大きな
抵抗力を得ることができる。Thus, according to the above pile construction method,
A large supporting force can be obtained even in the soft ground 6 having a deep supporting layer, and the number of blades can be reduced as compared with the conventional multi-blade pile, that is, three blades are sufficient,
The cost of piles can be kept low. Further, also in construction, it is sufficient to drive the inner pile 1 and the outer pile 2 by using the same rotary press-fitting machine, and moreover, the outer pile 2 can be driven by the same rotary press-fitting machine.
Can be rotated in reverse and construction can be performed without increasing the cost. Further, since the pile has a so-called double inner / outer structure, it is possible to obtain a large resistance force against a horizontal force.
【0021】以上に、本発明の実施形態を示したが、本
発明はこれに限られるものではなく、発明思想を逸脱し
ない範囲で、各種の変更が可能である。例えば上記の実
施形態では、外杭2に備えさせる螺旋翼を2つとした場
合を示しているが、先端側の1つとしてもよいし、ある
いは、3つ以上としてもよいし、2つあるいは3つ以上
とする場合であっても、多翼杭の場合よりも翼の数を少
なくすることができる。また、上記の実施形態では、外
杭2の逆回転中に土9を補給していく場合を示している
が、外杭2の基端側の翼5が地面からある程度深い位置
に位置するような場合は、外杭2の逆回転終了後に土9
の補給を行うようにしてもよいし、補給の必要がなけれ
ば補給しなくともよい。Although the embodiment of the present invention has been described above, the present invention is not limited to this, and various modifications can be made without departing from the spirit of the invention. For example, in the above embodiment, the case where the outer pile 2 is provided with two spiral blades is shown, but the number may be one on the tip side, or three or more, or two or three. Even when the number is three or more, the number of blades can be reduced as compared with the case of the multi-blade pile. Further, in the above-described embodiment, the case where the soil 9 is replenished during the reverse rotation of the outer pile 2 is shown, but the blades 5 on the base end side of the outer pile 2 are positioned at a position deep to some extent from the ground. In such a case, soil 9 will be left after the reverse rotation of the outer pile 2 is completed.
May be replenished, or may not be replenished if there is no need for replenishment.
【0022】[0022]
【発明の効果】本発明は、以上のとおりのものであるか
ら、多翼杭のような多くの翼を必要とせず、しかも、軟
弱地盤において大きな支持力を得ることができる。EFFECTS OF THE INVENTION Since the present invention is as described above, a large supporting force can be obtained on soft ground without requiring many blades such as a multi-blade pile.
【図1】実施形態の施工方法に用いる杭の側面図であ
る。FIG. 1 is a side view of a pile used in a construction method of an embodiment.
【図2】図(イ)及び図(ロ)は図3及び図4とともに
施工方法を順次に示す側面図である。2A and 2B are side views sequentially showing a construction method together with FIGS. 3 and 4. FIG.
【図3】図(ハ)及び図(ニ)は図2及び図4とともに
施工方法を順次に示す側面図である。3 (c) and FIG. 3 (d) are side views sequentially showing the construction method together with FIG. 2 and FIG.
【図4】図(ホ)及び図(へ)は図2及び図3とともに
施工方法を順次に示す側面図である。4 (e) and FIG. 4 (e) are side views sequentially showing the construction method together with FIG. 2 and FIG.
1…中杭 2…外杭 3…先端側の翼 4…先端側の螺旋翼 5…基端側の螺旋翼 6…軟弱地盤 7…こぶ状圧縮部 9…補給用の土 1 ... Middle pile 2 ... outer pile 3 ... Tip wing 4 ... Spiral blade on the tip side 5 ... Spiral blade on the base side 6 ... Soft ground 7 ... Hub-shaped compression part 9… Soil for replenishment
Claims (3)
た中杭と、 内径寸法が中杭の外周径よりも大きく、かつ、先端側の
外周に側方に張り出す螺旋翼を備えた筒状の外杭とを用
い、 中杭を地盤に回転圧入により打ち込んだのち、 外杭を中杭に対して同心状となるように地盤に回転圧入
により打ち込んでいき、外杭の先端側螺旋翼が地中で中
杭の先端翼よりも所定の高さ寸法上方に間隔をおいた状
態で外杭の打込みを停止し、しかる後、 外杭を、その深度を固定しながら逆回転させることによ
り、外杭の先端側螺旋翼でそれよりも上方の土を下方に
送り込んでいき、中杭の先端翼と外杭の先端側螺旋翼と
の間の領域の土を圧縮させていくことを特徴とする杭の
施工方法。1. A middle pile provided with blades protruding laterally on the outer circumference on the tip side, and a spiral blade having an inner diameter larger than the outer diameter of the middle pile and projecting laterally on the outer circumference on the tip side. Using the provided cylindrical outer pile, drive the middle pile into the ground by rotary press-fitting, then drive the outer pile into the ground by rotary press-fitting so that it is concentric with the middle pile, and the tip of the outer pile The driving of the outer piles is stopped with the side spiral blades spaced a predetermined height above the tip blades of the inner piles in the ground, and then the outer piles are rotated in reverse while fixing the depth. By doing so, the soil on the tip side of the outer pile is sent downward, and the soil in the area between the tip blade of the middle pile and the tip side of the outer pile is compressed. A method of constructing a pile, which is characterized in that.
張り出す螺旋翼を備え、 外杭の打込みを、その基端側螺旋翼が地中に入り込んだ
状態で停止し、 外杭の逆回転によってその基端側螺旋翼でそれよりも上
方の土を下方に送り込む請求項1に記載の杭の施工方
法。2. The outer pile is provided with a spiral blade projecting laterally on the outer periphery of the base end side thereof, and driving of the outer pile is stopped in a state where the base end side spiral blade has entered the ground, The method for constructing a pile according to claim 1, wherein the soil above the outer spiral pile is fed downward by the spiral blade on the base end side by the reverse rotation of the outer pile.
翼の上方に土を補給していく請求項2に記載の杭の施工
方法。3. The method for constructing a pile according to claim 2, wherein soil is replenished above the base side spiral blade while the outer pile is rotated in the reverse direction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002094004A JP4027702B2 (en) | 2002-03-29 | 2002-03-29 | Pile construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002094004A JP4027702B2 (en) | 2002-03-29 | 2002-03-29 | Pile construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003293364A true JP2003293364A (en) | 2003-10-15 |
JP4027702B2 JP4027702B2 (en) | 2007-12-26 |
Family
ID=29238202
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002094004A Expired - Fee Related JP4027702B2 (en) | 2002-03-29 | 2002-03-29 | Pile construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4027702B2 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005171621A (en) * | 2003-12-11 | 2005-06-30 | Porta- Seizo Kk | Steel pipe pile and construction method for driving the same |
JP2005282186A (en) * | 2004-03-30 | 2005-10-13 | Daiwa House Ind Co Ltd | Yield strength increasing method of pile driven in ground surface and pile surrounding earth compacting tool |
JP2014077299A (en) * | 2012-10-11 | 2014-05-01 | H G Service Kk | Foundation pile |
JP2015143462A (en) * | 2013-12-27 | 2015-08-06 | Jfeスチール株式会社 | steel pipe pile |
JP7116516B1 (en) | 2022-02-08 | 2022-08-10 | 株式会社スペース二十四インフォメーション | Strut fixing method |
-
2002
- 2002-03-29 JP JP2002094004A patent/JP4027702B2/en not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005171621A (en) * | 2003-12-11 | 2005-06-30 | Porta- Seizo Kk | Steel pipe pile and construction method for driving the same |
JP2005282186A (en) * | 2004-03-30 | 2005-10-13 | Daiwa House Ind Co Ltd | Yield strength increasing method of pile driven in ground surface and pile surrounding earth compacting tool |
JP4490149B2 (en) * | 2004-03-30 | 2010-06-23 | 大和ハウス工業株式会社 | Strengthening method of pile driven into the ground |
JP2014077299A (en) * | 2012-10-11 | 2014-05-01 | H G Service Kk | Foundation pile |
JP2015143462A (en) * | 2013-12-27 | 2015-08-06 | Jfeスチール株式会社 | steel pipe pile |
JP7116516B1 (en) | 2022-02-08 | 2022-08-10 | 株式会社スペース二十四インフォメーション | Strut fixing method |
JP2023115864A (en) * | 2022-02-08 | 2023-08-21 | 株式会社スペース二十四インフォメーション | Brace fixing method |
Also Published As
Publication number | Publication date |
---|---|
JP4027702B2 (en) | 2007-12-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2003293364A (en) | Method for constructing pile | |
JP2006312825A (en) | Rotational penetration pile and its construction method | |
JP4085492B2 (en) | Winged screw pile | |
JP2007247189A (en) | Method of forming improved body, and screw shaft for use in the method | |
JP3932173B2 (en) | Steel pipe pile construction member and steel pipe pile construction method | |
JP3932174B2 (en) | Steel pipe pile construction member and steel pipe pile construction method | |
JP4594224B2 (en) | Pile head reinforcement structure for steel pipe pile construction and steel pipe pile construction method | |
JP5963301B2 (en) | Assembled blade member for steel pipe pile, steel pipe pile, composite pile and method for manufacturing composite pile | |
JP4490149B2 (en) | Strengthening method of pile driven into the ground | |
JP2000336646A (en) | Pile driving method | |
JP2001241036A (en) | Pile for foundation, upper pile member constituting foundation pile, joint fittings provided in upper pile member, and work method for foundation pile | |
JP4114875B2 (en) | Root pile and ready-made pile | |
JP4967899B2 (en) | Agitation head used for agitation of soil in columnar improvement of ground | |
JP2007132008A (en) | Structure of jacking pile, and its burying method | |
US6540444B2 (en) | Rotating pile for undergrounding | |
JP2003176534A (en) | Steel pipe pile and its construction method | |
JP4786958B2 (en) | Tip blade for rotary press-in pile and rotary press-in pile with the tip blade | |
JPH08284160A (en) | Steel pipe pile with spiral blade | |
US20240318399A1 (en) | Soil displacement pile assembly and method of forming foundation pile | |
CN114164821B (en) | Steel pipe pile for surface grouting of shallow-buried bias tunnel and construction method thereof | |
JP2013249685A (en) | Band-like blade member for steel pipe pile, steel pipe pile, and composite pile and method of manufacturing the same | |
JP2003155743A (en) | Structure for attaching pile tip having longitudinal tooth and propeller-like tooth | |
JPH09302650A (en) | Buried pile for foundation construction | |
JPH0350045B2 (en) | ||
JP3929332B2 (en) | Displacement control type compacted sand pile construction hollow tube and compacted sand pile construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050322 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070326 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070710 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070907 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20071009 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20071010 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101019 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4027702 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101019 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131019 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |