JP2003176535A - Steel pipe pile and its construction method - Google Patents
Steel pipe pile and its construction methodInfo
- Publication number
- JP2003176535A JP2003176535A JP2001375313A JP2001375313A JP2003176535A JP 2003176535 A JP2003176535 A JP 2003176535A JP 2001375313 A JP2001375313 A JP 2001375313A JP 2001375313 A JP2001375313 A JP 2001375313A JP 2003176535 A JP2003176535 A JP 2003176535A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- tip
- shaft
- pipe pile
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】この発明は、軟弱地盤におけ
る住宅等の不同沈下防止等のために使用される鋼管杭及
びその施工方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a steel pipe pile used for preventing uneven settlement of a house or the like on soft ground and a method of constructing the same.
【0002】[0002]
【従来の技術】周知のように、軟弱地盤における住宅等
の不同沈下を防止する方法や上部荷重を地盤に伝達する
方法としては、例えば、騒音や振動等の問題がない鋼管
杭の回転貫入工法がある。2. Description of the Related Art As is well known, as a method of preventing uneven settlement of a house or the like in soft ground and a method of transmitting an upper load to the ground, for example, a rotary penetration method for steel pipe piles without problems such as noise and vibration. There is.
【0003】この回転貫入工法においては、図11及び
図12に示すように、螺旋翼2が先端3a付近の外周に
螺旋状に突設され、例えば三角板状の掘削片4を一面側
5aに突設した底板5の他面側5bが先端3aに固着さ
れた鋼管製の軸管3からなる鋼管杭51を使用すること
が多い。施工に際しては、鋼管杭51の頭部51bを重
機で押さえながら、あるいは支持しながら回転を加えて
地盤に貫入するのが一般的である。回転貫入後において
は、螺旋翼2を含む鋼管杭51の先端51aが受ける地
盤反力(先端支持力)と、鋼管杭51と地盤との間に発
生する摩擦力(周面摩擦力)とによって支持力を得る構
造となっている。In this rotary penetration method, as shown in FIGS. 11 and 12, a spiral blade 2 is provided in a spiral shape on the outer periphery near the tip 3a. For example, a triangular plate-shaped excavation piece 4 is projected on one surface side 5a. In many cases, the steel pipe pile 51 including the shaft pipe 3 made of a steel pipe having the other surface side 5b of the bottom plate 5 provided fixed to the tip 3a is used. At the time of construction, it is general that the head 51b of the steel pipe pile 51 is pressed or supported by a heavy machine to be rotated and penetrate into the ground. After the rotary penetration, due to the ground reaction force (tip supporting force) received by the tip 51a of the steel pipe pile 51 including the spiral blade 2 and the frictional force (peripheral surface friction force) generated between the steel pipe pile 51 and the ground. It has a structure that gains supportive power.
【0004】[0004]
【発明が解決しようとする課題】しかしながら、上記の
ような従来の鋼管杭51においては、地盤への回転貫入
時に鋼管杭51の1回転当りの貫入量が螺旋翼2の周回
ピッチPより小さい場合、地盤中に螺旋翼2によって乱
されたまま残る部分が発生する。また、掘削片4によっ
て乱されたまま残る部分も発生する。そのため、鋼管杭
51に荷重が作用すれば住宅等を支持する上で有害な沈
下が発生するおそれがあり、地盤に対する先端支持力は
あまり大きくないという問題点がある。However, in the conventional steel pipe pile 51 as described above, when the amount of penetration of the steel pipe pile 51 per revolution is smaller than the revolution pitch P of the spiral blade 2 when the steel pipe pile 51 is rotationally penetrated into the ground. A part of the ground that remains undisturbed by the spiral wing 2 is generated. In addition, a portion that remains undisturbed by the excavated piece 4 also occurs. Therefore, if a load is applied to the steel pipe pile 51, harmful subsidence may occur in supporting a house or the like, and there is a problem that the tip supporting force for the ground is not so large.
【0005】この発明は、以上のような問題点に鑑みて
なされたものであり、地盤に対する先端支持力を向上で
きる鋼管杭及びその施工方法を提供することを目的とす
る。The present invention has been made in view of the above problems, and an object of the present invention is to provide a steel pipe pile capable of improving the tip supporting force for the ground and a construction method thereof.
【0006】[0006]
【課題を解決するための手段】上記目的を達成するため
の請求項1の鋼管杭は、少なくとも1つの螺旋翼が先端
付近の外周に螺旋状に突設された鋼管製の軸管と、この
軸管の内径より外径が少し小さい鋼管製で、少なくとも
1つの掘削片を一面側に突設した底板の他面側が先端に
固着され、前記軸管内に前記掘削片を軸管の先端側に向
けて挿入された内管とを備えたものである。In order to achieve the above object, a steel pipe pile according to a first aspect of the present invention comprises a steel pipe shaft tube in which at least one spiral blade is provided in a spiral shape on the outer periphery near the tip, and Made of steel pipe with an outer diameter slightly smaller than the inner diameter of the shaft pipe, the other side of the bottom plate having at least one drilling piece projecting on one surface side is fixed to the tip, and the drilling piece is placed inside the shaft pipe on the tip side of the shaft pipe. And an inner tube inserted toward the end.
【0007】請求項2の施工方法は、請求項1記載の鋼
管杭の施工方法であって、前記掘削片を前記軸管の先端
から突出させた状態で鋼管杭を地盤の所定深さまで回転
貫入した後、鋼管杭を回転させながら上下に移動させ、
鋼管杭の先端付近の地盤を砕くことによって砕土部を設
け、この砕土部内の所定高さに前記軸管の先端が位置
し、かつこの軸管から前記内管を引き抜いた状態で砕土
部内にモルタルを圧入して硬化させることによって、前
記軸管の先端に改良土部を設けるものである。A construction method of claim 2 is the construction method of the steel pipe pile according to claim 1, wherein the steel pipe pile is rotationally penetrated to a predetermined depth of the ground in a state where the excavated piece is projected from the tip of the shaft pipe. After that, move the steel pipe pile up and down while rotating,
A crushed soil portion is provided by crushing the ground near the tip of the steel pipe pile, the tip of the shaft pipe is located at a predetermined height in the crushed soil portion, and the inner pipe is pulled out from the shaft pipe. By press-fitting and hardening it, an improved soil portion is provided at the tip of the shaft tube.
【0008】請求項3の施工方法においては、前記モル
タルの圧入時における前記砕土部の底面から前記軸管の
先端までの高さが前記螺旋翼の外径以上である。In the construction method of claim 3, the height from the bottom surface of the crushed soil portion to the tip of the shaft tube when the mortar is press-fitted is equal to or greater than the outer diameter of the spiral blade.
【0009】請求項4の施工方法は、前記モルタルを前
記砕土部内に圧入すると共に、このモルタルが前記軸管
の先端の内部に充填された状態で硬化させるものであ
る。According to a fourth aspect of the present invention, the mortar is press-fitted into the crushed soil portion, and the mortar is hardened while being filled inside the tip of the shaft tube.
【0010】請求項5の施工方法は、前記モルタルを、
前記軸管内に挿入されたモンケンの自由落下によって前
記砕土部内に圧入するものである。According to a fifth aspect of the construction method, the mortar is
The Monken inserted into the shaft tube is pressed into the crushed soil portion by free fall.
【0011】[0011]
【発明の実施の形態】以下、この発明の実施形態を図面
に基づいて説明する。なお、従来技術と同じ構成につい
ては、同一符号を付している。BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings. The same components as those of the conventional technique are designated by the same reference numerals.
【0012】図1乃至図3に示すように、この実施形態
に係る鋼管杭1は、螺旋翼2が先端3a付近の外周に螺
旋状に突設された鋼管製の軸管3と、この軸管3の内径
より外径が少し小さい鋼管製で、掘削片4を一面側5a
に突設した底板5の他面側5bが先端6aに固着され、
軸管3内に掘削片4を軸管3の先端3a側に向けて挿入
された内管6とを備えたものである。As shown in FIGS. 1 to 3, in a steel pipe pile 1 according to this embodiment, a shaft pipe 3 made of steel pipe in which a spiral blade 2 is provided in a spiral shape on the outer periphery near a tip 3a, and this shaft The outer diameter of the pipe 3 is slightly smaller than the inner diameter of the pipe 3.
The other surface side 5b of the bottom plate 5 protruding from the
The shaft pipe 3 is provided with an excavation piece 4 and an inner pipe 6 inserted toward the tip 3a side of the shaft pipe 3.
【0013】軸管3は、例えば、外径が約10〜数十c
m、肉厚が数mmの円管状の鋼管製で、数m〜十数mの
長尺に形成されている。The shaft tube 3 has, for example, an outer diameter of about 10 to several tens of c.
It is made of a circular tubular steel pipe having a wall thickness of m and a wall thickness of several mm, and is formed in a long length of several m to several tens of m.
【0014】螺旋翼2は、例えば鋼板製で、軸管3の先
端3a付近の外周に溶接等により螺旋状に突設されてい
る。なお、この実施形態においては、1周しか周回させ
ていないが、これに限定されるものではなく、それ以上
周回させてもよい。また、螺旋翼2の数も1つに限定さ
れるものではなく、軸管3の長さ方向に沿って複数個突
設してもよい。The spiral blade 2 is made of, for example, a steel plate, and is provided in a spiral shape by welding or the like on the outer periphery of the shaft tube 3 near the tip 3a. In this embodiment, only one round is made, but it is not limited to this, and more rounds may be made. The number of spiral blades 2 is not limited to one, and a plurality of spiral blades 2 may be provided so as to project along the length direction of the shaft tube 3.
【0015】内管6は、軸管3と同様の円管状の鋼管製
であるが、軸管3の内径より外径が少し小さく形成され
ており、軸管3内に掘削片4を軸管3の先端3a側に向
けて出し入れ自在に挿入されている。なお、内管6の長
さは軸管3とほぼ同じでよいが、特に限定されるもので
はなく、地盤7への回転貫入時に掘削片4を軸管3の先
端3aから突出させた状態で内管6と軸管3とを重機等
により同時に回転可能な長さであればよい。The inner pipe 6 is made of a circular tubular steel pipe similar to the shaft pipe 3, but has an outer diameter slightly smaller than the inner diameter of the shaft pipe 3, and the excavation piece 4 is formed in the shaft pipe 3. 3 is inserted into and taken out toward the tip 3a side. The length of the inner pipe 6 may be substantially the same as that of the shaft pipe 3, but is not particularly limited, and in a state where the excavated piece 4 is projected from the tip 3a of the shaft pipe 3 when the ground 7 is rotationally penetrated. The length may be such that the inner pipe 6 and the shaft pipe 3 can be simultaneously rotated by a heavy machine or the like.
【0016】底板5は、例えば円板状の鋼板製で、一面
側5aに掘削片4が溶接等により突設されていると共
に、他面側5bが内管6の先端6aに溶接等により固着
されている。掘削片4は例えば三角板状の鋼板製である
が、この掘削片4の形状、サイズ、数、突設位置、突設
角度等は特に限定されるものではなく、必要に応じて適
宜変更可能である。The bottom plate 5 is made of, for example, a disc-shaped steel plate, and the excavation piece 4 is projected on one side 5a by welding or the like, and the other side 5b is fixed to the tip 6a of the inner pipe 6 by welding or the like. Has been done. The excavated piece 4 is made of, for example, a triangular plate-shaped steel plate, but the shape, size, number, protruding position, protruding angle, etc. of the excavated piece 4 are not particularly limited and can be appropriately changed as necessary. is there.
【0017】次に、上記のように構成された鋼管杭1の
施工方法について説明する。鋼管杭1の施工に際して
は、まず、図4に示すように、掘削片4を軸管3の先端
3aから突出させた状態で鋼管杭1を地盤7の所定深さ
まで回転貫入する。この場合、重機等により軸管3と内
管6とを同時に同じ方向に回転させればよい。あるい
は、従来公知の固定手段により軸管3と内管6とを固定
した状態で回転させてもよい。Next, a method of constructing the steel pipe pile 1 constructed as described above will be described. When constructing the steel pipe pile 1, first, as shown in FIG. 4, the steel pipe pile 1 is rotationally penetrated to a predetermined depth of the ground 7 with the excavated piece 4 protruding from the tip 3 a of the shaft pipe 3. In this case, the shaft tube 3 and the inner tube 6 may be simultaneously rotated in the same direction by a heavy machine or the like. Alternatively, the shaft tube 3 and the inner tube 6 may be rotated while being fixed by a conventionally known fixing means.
【0018】そして、図5に示すように、鋼管杭1を重
機等により回転させながら上下に移動させ、鋼管杭1の
先端1a付近の地盤7を砕くことによって砕土部8を設
ける。この場合、鋼管杭1の回転や移動は適宜の方向に
行えばよく、螺旋翼2で地盤7の所定範囲を砕いて砕土
部8とすればよい。Then, as shown in FIG. 5, the steel pipe pile 1 is moved up and down while being rotated by a heavy machine or the like, and the ground 7 near the tip 1a of the steel pipe pile 1 is crushed to provide a crushed soil portion 8. In this case, the steel pipe pile 1 may be rotated or moved in an appropriate direction, and a predetermined range of the ground 7 may be crushed by the spiral blade 2 to form the crushed soil portion 8.
【0019】更に、図6及び図7に示すように、砕土部
8内の所定高さに軸管3の先端3aが位置するように例
えば鋼管杭1を上方へ移動させた後、軸管3から内管6
を引き抜く。なお、内管6を軸管3から引き抜くタイミ
ングは特に限定されるものではなく、軸管3のみを上方
へ移動させた後で引き抜いてもよいし、あるいは内管6
を引き抜いてから軸管3を上方へ移動させてもよい。Further, as shown in FIGS. 6 and 7, for example, the steel pipe pile 1 is moved upward so that the tip 3a of the shaft pipe 3 is located at a predetermined height in the crushed soil portion 8, and then the shaft pipe 3 is moved. To inner tube 6
Pull out. The timing of pulling out the inner pipe 6 from the shaft pipe 3 is not particularly limited, and it may be pulled out after moving only the shaft pipe 3 upward, or the inner pipe 6 may be pulled out.
The shaft tube 3 may be moved upward after pulling out.
【0020】次いで、図8及び図9に示すように、軸管
3を通してモルタル9を砕土部8内に投入した後、軸管
3内にワイヤーロープ10等を介して自由落下及び引き
上げ自在に挿入されたモンケン11等によりモルタル9
を砕土部8内に圧入する。圧入に際しては、この実施形
態のように、砕土部8の周囲が外方へ圧縮されて砕土部
8が拡大するようにしてもよい。なお、モルタル9は、
圧縮空気等により砕土部8に圧入することもできるが、
この実施形態のようなモンケン11の自由落下によれ
ば、簡単にかつ大荷重で圧入できるという利点がある。Then, as shown in FIGS. 8 and 9, after the mortar 9 is put into the crushed soil portion 8 through the shaft tube 3, the mortar 9 is inserted into the shaft tube 3 through the wire rope 10 or the like so as to freely fall and pull up. Mortar 9 by the Monken 11 etc.
Is pressed into the crushed soil portion 8. At the time of press fitting, the periphery of the crushed soil portion 8 may be compressed outward so that the crushed soil portion 8 expands as in this embodiment. The mortar 9 is
It can be pressed into the crushed soil section 8 by compressed air,
According to the free fall of the Monken 11, like this embodiment, there is an advantage that it can be easily press-fitted with a large load.
【0021】圧入後、所定期間放置してモルタル9を硬
化させれば、図10に示すように、軸管3の先端3aに
改良土部12が形成される。軸管3の頭部3bは、必要
に応じて所定長さ切除した後、円板状の鋼板製等の上板
13を溶接等により固着すればよい。布基礎14等の基
礎は、従来公知の方法により軸管3の上方に施工すれば
よい。ここで、モルタル9の圧入時における砕土部8の
底面8dから軸管3の先端3aまでの高さが螺旋翼2の
外径以上であれば、十分な高さの改良土部12を形成で
きると共に、モルタル9を圧入し易いという利点があ
る。また、モルタル9を砕土部8内に圧入すると共に、
このモルタル9が軸管3の先端3aの内部に充填された
状態で硬化させれば、軸管3の先端3aが改良土部12
に確実に埋設されるので、軸管3と改良土部12とがず
れるおそれがないという利点がある。After press-fitting, the mortar 9 is hardened by leaving it for a predetermined period of time to form an improved soil portion 12 at the tip 3a of the shaft tube 3, as shown in FIG. The head portion 3b of the shaft tube 3 may be cut off by a predetermined length as necessary, and then the upper plate 13 made of a disc-shaped steel plate may be fixed by welding or the like. The foundation such as the cloth foundation 14 may be installed above the shaft tube 3 by a conventionally known method. Here, if the height from the bottom surface 8d of the crushed soil portion 8 to the tip 3a of the shaft tube 3 when the mortar 9 is pressed in is equal to or greater than the outer diameter of the spiral blade 2, the improved soil portion 12 having a sufficient height can be formed. At the same time, there is an advantage that the mortar 9 can be easily press-fitted. Also, while pressing the mortar 9 into the crushed soil portion 8,
If the mortar 9 is cured while being filled inside the tip 3a of the shaft tube 3, the tip 3a of the shaft tube 3 will improve the soil portion 12.
Since it is surely buried in the structure, there is an advantage that the shaft tube 3 and the improved soil portion 12 are not likely to be displaced.
【0022】このようにして軸管3の先端3aに改良土
部12を設ければ、地盤7に対する先端支持力が大きく
なるので、軸管3に荷重が作用しても沈下量を小さく抑
えることができるという利点がある。By providing the improved soil portion 12 at the tip 3a of the shaft tube 3 in this manner, the tip supporting force for the ground 7 becomes large, so that the subsidence amount should be kept small even if a load is applied to the shaft tube 3. The advantage is that
【0023】[0023]
【発明の効果】以上のように、請求項1の発明によれ
ば、軸管と内管とを備えているので、軸管の先端に改良
土部を設けるための鋼管杭として好適に使用できる。As described above, according to the invention of claim 1, since the shaft pipe and the inner pipe are provided, it can be suitably used as a steel pipe pile for providing an improved soil portion at the tip of the shaft pipe. .
【0024】請求項2の発明によれば、既述のようにし
て軸管の先端に改良土部を設けるので、地盤に対する先
端支持力が大きくなり、そのため軸管に荷重が作用して
も沈下量を小さく抑えることができる。According to the second aspect of the invention, since the improved soil portion is provided at the tip of the shaft tube as described above, the tip supporting force for the ground becomes large, and therefore the sinking of the shaft tube even when a load acts on it. The amount can be kept small.
【0025】請求項3の発明によれば、モルタルの圧入
時における砕土部の底面から軸管の先端までの高さが螺
旋翼の外径以上であるので、十分な高さの改良土部を形
成できると共に、モルタルを圧入し易い。According to the invention of claim 3, the height from the bottom surface of the crushed soil portion to the tip of the shaft tube when the mortar is press-fitted is equal to or larger than the outer diameter of the spiral blade, so that the improved soil portion having a sufficient height can be obtained. It can be formed and it is easy to press mortar.
【0026】請求項4の発明によれば、モルタルを砕土
部内に圧入すると共に、このモルタルが軸管の先端の内
部に充填された状態で硬化させるので、軸管の先端が改
良土部に確実に埋設され、軸管と改良土部とがずれるお
それがない。According to the fourth aspect of the present invention, since the mortar is pressed into the crushed soil portion and the mortar is hardened in a state where the mortar is filled inside the tip end of the shaft tube, the tip end of the shaft tube is surely placed in the improved soil portion. There is no risk of the shaft tube and the improved soil being misaligned.
【0027】請求項5の発明によれば、モルタルをモン
ケンの自由落下によって砕土部内に圧入するので、簡単
にかつ大荷重で圧入できる。According to the invention of claim 5, the mortar is press-fitted into the crushed soil portion by free fall of the Monken, so that the mortar can be easily press-fitted with a large load.
【図1】実施形態に係る鋼管杭の一部省略正面図。FIG. 1 is a partially omitted front view of a steel pipe pile according to an embodiment.
【図2】鋼管杭の底面図。FIG. 2 is a bottom view of the steel pipe pile.
【図3】内管の一部省略正面図。FIG. 3 is a front view of the inner pipe with a part thereof omitted.
【図4】鋼管杭を地盤の所定深さまで回転貫入した後の
状態を示す一部省略断面図。FIG. 4 is a partially omitted cross-sectional view showing a state after the steel pipe pile is rotationally penetrated to a predetermined depth of the ground.
【図5】砕土部を設けた後の状態を示す一部省略断面
図。FIG. 5 is a partially omitted cross-sectional view showing a state after the crushed soil portion is provided.
【図6】鋼管杭を上方へ移動させた後の状態を示す一部
省略断面図。FIG. 6 is a partially omitted cross-sectional view showing a state after the steel pipe pile has been moved upward.
【図7】軸管から内管を引き抜く様子を示す一部省略断
面図。FIG. 7 is a partially omitted cross-sectional view showing a state where an inner pipe is pulled out from a shaft pipe.
【図8】砕土部内にモルタルを投入する様子を示す一部
省略断面図。FIG. 8 is a partially omitted cross-sectional view showing how mortar is put into the crushed soil portion.
【図9】砕土部内にモルタルを圧入する様子を示す一部
省略断面図。FIG. 9 is a partially omitted cross-sectional view showing how mortar is press-fitted into the crushed soil portion.
【図10】軸管の先端に改良土部を設けた後の状態を示
す一部省略断面図。FIG. 10 is a partially omitted cross-sectional view showing a state after the improved soil portion is provided at the tip of the shaft tube.
【図11】従来例の一部省略正面図。FIG. 11 is a partially omitted front view of a conventional example.
【図12】従来例の底面図。FIG. 12 is a bottom view of a conventional example.
【符号の説明】 1 鋼管杭 1a 先端 2 螺旋翼 3 軸管 3a 先端 4 掘削片 5 底板 5a 一面側 5b 他面側 6 内管 6a 先端 7 地盤 8 砕土部 8d 底面 9 モルタル 11 モンケン 12 改良土部[Explanation of symbols] 1 steel pipe pile 1a tip 2 spiral wings 3-axis tube 3a tip 4 excavated pieces 5 bottom plate 5a One side 5b Other side 6 inner tube 6a tip 7 ground 8 crushed soil 8d bottom 9 Mortar 11 Monken 12 improved soil
───────────────────────────────────────────────────── フロントページの続き (72)発明者 大西 義武 大阪市北区大淀中1丁目1番88号 積水ハ ウス株式会社内 (72)発明者 山田 順三郎 大阪府箕面市船場西1−13−3 Fターム(参考) 2D041 AA02 BA12 BA13 BA35 BA52 CA05 DB02 FA03 FA07 FA13 FA14 2D050 AA06 AA16 BB07 CA05 CB05 CB13 ─────────────────────────────────────────────────── ─── Continued front page (72) Inventor Yoshitake Onishi Sekisui Ha, 1-188 Oyodo-Naka, Kita-ku, Osaka-shi Inside Us Co., Ltd. (72) Inventor Junsaburo Yamada 1-13-3 Senba Nishi, Minoh City, Osaka Prefecture F-term (reference) 2D041 AA02 BA12 BA13 BA35 BA52 CA05 DB02 FA03 FA07 FA13 FA14 2D050 AA06 AA16 BB07 CA05 CB05 CB13
Claims (5)
周に螺旋状に突設された鋼管製の軸管と、この軸管の内
径より外径が少し小さい鋼管製で、少なくとも1つの掘
削片を一面側に突設した底板の他面側が先端に固着さ
れ、前記軸管内に前記掘削片を軸管の先端側に向けて挿
入された内管とを備えたことを特徴とする鋼管杭。1. A shaft pipe made of a steel pipe in which at least one spiral blade is projected in a spiral shape on the outer periphery near the tip, and a steel pipe having an outer diameter slightly smaller than the inner diameter of the shaft pipe, and at least one excavated piece. The steel pipe pile, wherein the other surface side of the bottom plate protruding from the one surface side is fixed to the tip, and the inner pipe is inserted into the shaft pipe so that the excavated piece is inserted toward the front end side of the shaft pipe.
て、 前記掘削片を前記軸管の先端から突出させた状態で鋼管
杭を地盤の所定深さまで回転貫入した後、鋼管杭を回転
させながら上下に移動させ、鋼管杭の先端付近の地盤を
砕くことによって砕土部を設け、この砕土部内の所定高
さに前記軸管の先端が位置し、かつこの軸管から前記内
管を引き抜いた状態で砕土部内にモルタルを圧入して硬
化させることによって、前記軸管の先端に改良土部を設
けることを特徴とする鋼管杭の施工方法。2. The method for constructing a steel pipe pile according to claim 1, wherein the steel pipe pile is rotationally penetrated to a predetermined depth of the ground in a state where the excavated piece is projected from the tip of the shaft pipe, and then the steel pipe pile is installed. While rotating, it moves up and down to provide a crushed soil portion by crushing the ground near the tip of the steel pipe pile, the tip of the shaft pipe is located at a predetermined height in the crushed soil portion, and the inner pipe is moved from this shaft pipe. A method for constructing a steel pipe pile, characterized in that an improved soil portion is provided at the tip of the shaft tube by press-fitting and hardening mortar in the crushed soil portion in the pulled-out state.
部の底面から前記軸管の先端までの高さが前記螺旋翼の
外径以上である請求項2記載の鋼管杭の施工方法。3. The method for constructing a steel pipe pile according to claim 2, wherein the height from the bottom surface of the crushed soil portion to the tip of the shaft pipe when the mortar is press-fitted is equal to or larger than the outer diameter of the spiral blade.
と共に、このモルタルが前記軸管の先端の内部に充填さ
れた状態で硬化させる請求項2又は3記載の鋼管杭の施
工方法。4. The method for constructing a steel pipe pile according to claim 2, wherein the mortar is press-fitted into the crushed soil portion and hardened in a state where the mortar is filled inside the tip of the shaft pipe.
たモンケンの自由落下によって前記砕土部内に圧入する
請求項2乃至4のいずれか記載の鋼管杭の施工方法。5. The method for constructing a steel pipe pile according to claim 2, wherein the mortar is press-fitted into the crushed soil portion by free fall of a Monken inserted in the shaft pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001375313A JP3932173B2 (en) | 2001-12-10 | 2001-12-10 | Steel pipe pile construction member and steel pipe pile construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001375313A JP3932173B2 (en) | 2001-12-10 | 2001-12-10 | Steel pipe pile construction member and steel pipe pile construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003176535A true JP2003176535A (en) | 2003-06-24 |
JP3932173B2 JP3932173B2 (en) | 2007-06-20 |
Family
ID=19183715
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001375313A Expired - Fee Related JP3932173B2 (en) | 2001-12-10 | 2001-12-10 | Steel pipe pile construction member and steel pipe pile construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3932173B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009091807A (en) * | 2007-10-09 | 2009-04-30 | Kurimoto Ltd | Rotary penetration pile |
CN102864776A (en) * | 2012-09-12 | 2013-01-09 | 杭州宝毅科技有限公司 | Spiral ground pile |
JP2017071907A (en) * | 2015-10-05 | 2017-04-13 | 新日鐵住金株式会社 | Device to reduce penetration resistance, penetration structure of steel pipe pile, and construction method for steel pipe pile |
CN107165165A (en) * | 2017-05-23 | 2017-09-15 | 温州市隆尚建设有限公司 | Piling machine and its piling component and pile-driving method |
-
2001
- 2001-12-10 JP JP2001375313A patent/JP3932173B2/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009091807A (en) * | 2007-10-09 | 2009-04-30 | Kurimoto Ltd | Rotary penetration pile |
CN102864776A (en) * | 2012-09-12 | 2013-01-09 | 杭州宝毅科技有限公司 | Spiral ground pile |
JP2017071907A (en) * | 2015-10-05 | 2017-04-13 | 新日鐵住金株式会社 | Device to reduce penetration resistance, penetration structure of steel pipe pile, and construction method for steel pipe pile |
CN107165165A (en) * | 2017-05-23 | 2017-09-15 | 温州市隆尚建设有限公司 | Piling machine and its piling component and pile-driving method |
Also Published As
Publication number | Publication date |
---|---|
JP3932173B2 (en) | 2007-06-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5069873B2 (en) | Steel pipe pile construction method | |
TW202012747A (en) | Plie foundation | |
JP5470070B2 (en) | Pile structure, steel pipe pile insertion method | |
JP2003176535A (en) | Steel pipe pile and its construction method | |
JP2003176536A (en) | Steel pipe pile and its construction method | |
JP5133625B2 (en) | Steel pipe pile | |
JP3171898U (en) | Casing for installing finned steel pipe piles | |
JP2003176534A (en) | Steel pipe pile and its construction method | |
JP3135220B2 (en) | Flanged expanded steel pipe pile | |
JP5777167B2 (en) | Ground reinforcement method using small-diameter concrete cast-in-place pile. | |
KR100932952B1 (en) | Piles that have variable end | |
JP4943363B2 (en) | Steel pipe pile and its construction method | |
JP2007224537A (en) | Foundation for steel pipe pole, and foundation method therefor | |
JP2003176533A (en) | Steel pipe pile and its construction method | |
JP4049373B2 (en) | Pile placing method, pile supporting method, and plug member used in these methods | |
KR20170046362A (en) | Helix steel pipe pile for reinforcement of buckling and construction method of the same | |
JP2004218341A (en) | Steel pipe pile | |
JP6993747B1 (en) | Rotating press-fit pile | |
JP2003232035A (en) | Base-enlarged plate for rotary buried steel pipe pile, and method for mounting the base-enlarged plate on rotary buried steel pipe pile | |
JP3086621U (en) | Rotating penetration expanded steel pipe pile | |
JP2001303563A (en) | Method for constructing concrete pile combined with soil cement | |
JP2001064966A (en) | Foundation pile | |
JP2007132008A (en) | Structure of jacking pile, and its burying method | |
JP4572292B2 (en) | Ready-made pile with tip shoe and method of burying ready-made pile | |
JP2003155743A (en) | Structure for attaching pile tip having longitudinal tooth and propeller-like tooth |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040910 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060626 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060706 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060822 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20061114 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070109 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070308 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070309 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100323 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130323 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130323 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20160323 Year of fee payment: 9 |
|
LAPS | Cancellation because of no payment of annual fees |