JP2003160944A - Construction method for precast concrete reservoir - Google Patents
Construction method for precast concrete reservoirInfo
- Publication number
- JP2003160944A JP2003160944A JP2001359564A JP2001359564A JP2003160944A JP 2003160944 A JP2003160944 A JP 2003160944A JP 2001359564 A JP2001359564 A JP 2001359564A JP 2001359564 A JP2001359564 A JP 2001359564A JP 2003160944 A JP2003160944 A JP 2003160944A
- Authority
- JP
- Japan
- Prior art keywords
- pillars
- beams
- wall
- support
- precast concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、内空高さの大きい
地下埋設型のプレキャストコンクリート製貯水槽を構築
するに際して好適である、プレキャストコンクリート製
貯水槽の構築工法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a water tank made of precast concrete, which is suitable for constructing an underground buried type water tank made of precast concrete having a large inner height.
【0002】[0002]
【従来の技術】都市部においては、都市型水害の防止又
は多目的な水利用を目的として、地下に雨水貯留槽や多
目的貯水槽を構築する事例が近年増加している。2. Description of the Related Art In urban areas, cases of constructing rainwater storage tanks and multipurpose storage tanks underground have been increasing in recent years for the purpose of preventing urban flood damage or using water for multiple purposes.
【0003】一方都市環境の面から、騒音、公害を最小
限に止めるべく工期短縮の要求がある。又近年、熟練工
不足の労務事情もあって、かかる工期短縮を、熟練工な
しでも実現できる構築工法が求められている。On the other hand, from the aspect of urban environment, there is a demand for shortening the construction period in order to minimize noise and pollution. In recent years, due to labor shortage due to lack of skilled workers, there is a demand for a construction method capable of realizing such shortening of the work period without skilled workers.
【0004】このような背景から、熟練工なしでも施工
でき、しかも工期短縮を実現できるように各種のプレキ
ャストコンクリート製貯水槽の構築工法(以下プレキャ
スト工法という)が提案されている。例えば図49に示
すようなボックス型ブロックaを所要間隔をおいて並設
し、その上端相互間を頂版ブロックbで連結するプレキ
ャスト工法、図50に示すような、端部のL字型ブロッ
クcと中間のI字型ブロックdを所要間隔をおいて並設
すると共に、その上端相互を頂版ブロックeを用いて連
結するプレキャスト工法、又図51で示すように、L字
型壁ブロックfや支柱ブロックg、連結梁ブロックh、
頂版ブロックj等を用い、一方向で隣り合う支柱ブロッ
クg,gの上端相互を前記連結梁ブロックhで連結する
プレキャスト工法等が実用に供されていた。[0004] Against this background, various precast concrete water tank construction methods (hereinafter referred to as precast methods) have been proposed so that construction can be performed without skilled workers and the construction period can be shortened. For example, a precast method in which box-shaped blocks a as shown in FIG. 49 are arranged side by side at a required interval, and their upper ends are connected to each other by a top slab block b, and L-shaped blocks at the ends as shown in FIG. c and an intermediate I-shaped block d are arranged side by side at a required interval, and their upper ends are connected by a top plate block e, or an L-shaped wall block f as shown in FIG. 51. Column block g, connecting beam block h,
A precast method or the like has been put to practical use in which the top blocks j and the like are used to connect the upper ends of the pillar blocks g adjacent to each other in one direction with the connecting beam block h.
【0005】かかるプレキャスト工法は、深さが5〜6
m程度の掘削空間で施工する、内空高さの比較的小さい
小規模貯水槽の構築に対してのものであって、これに用
いる土留壁は、地盤が良好である場合は、鋼矢板を打ち
込んだだけの自立型土留壁で対応できた。そして地盤が
良好でない場合は、一段の切梁を具える支保工によって
土留壁を支持することが行なわれていた。かかる一段切
梁の支保工による場合は、各種プレキャストコンクリー
ト製部材を切梁の下側で設置できるために、部材相互を
接合する貯水槽構築を支障なく行なうことができた。Such a precast method has a depth of 5-6.
It is for the construction of a small-scale water tank with a relatively small inner space height, which is constructed in an excavation space of about m, and the earth retaining wall used for this is steel sheet pile if the ground is good. It was possible to deal with the self-supporting earth retaining wall that was just driven in. And when the ground is not good, the retaining wall was supported by the support work with a single beam. In the case of supporting the single-stage cut beam, various precast concrete members can be installed below the cut beam, so that the water tank for joining the members can be constructed without any trouble.
【0006】しかし、貯水槽の内空高さが例えば5m以
上と大きくなると、必然的に掘削深さが深くなるため
に、鋼矢板を打ち込んだだけの自立型土留壁や一段切梁
の支保工では対応できない。そこで、鋼矢板を打ち込ん
で形成した土留壁を、切梁を上下複数段に設けた支保工
で支持せざるを得ない。[0006] However, if the inner height of the water tank becomes large, for example, 5 m or more, the excavation depth will inevitably become deeper. Therefore, the support work for the self-supporting earth retaining wall and the single-level girder simply by driving the steel sheet pile is performed. Can't handle it. Therefore, the earth retaining wall formed by driving the steel sheet pile has to be supported by the supporting work in which the cross beams are provided in the upper and lower stages.
【0007】しかしながら、かかる工法によるときは、
左右方向と前後方向の切梁が格子状に交差する切梁枠組
が、掘削空間に上下複数段に存在することになる。その
ため、前記従来タイプのプレキャスト工法を、かかる内
空高さの大なる貯水槽構築に応用するときは、中間及び
最下段に存する切梁が障害となって、前記した各ブロッ
クを縦横に延長敷設することが困難であった。又、壁板
を横方向や上下方向で付設する際に、中間及び最下段に
存する切梁が障害となって、横方向や上下方向での壁板
の連続した付設が困難となる問題が発生した。However, when such a construction method is used,
The crossbeam framework in which the crossbeams in the left-right direction and the front-rear direction intersect in a grid pattern is present in the excavation space in a plurality of upper and lower stages. Therefore, when applying the above-mentioned conventional type precast method to construct a water tank with such a large inner air height, the beams in the middle and bottom steps become an obstacle, and the above-mentioned blocks are extended vertically and horizontally. It was difficult to do. Also, when installing the wallboard in the horizontal or vertical direction, the crossbeams existing in the middle and the lowest steps become an obstacle, which makes it difficult to install the wallboard continuously in the horizontal or vertical direction. did.
【0008】一方向で隣り合う支柱ブロックg,gの上
端相互を連結梁ブロックhで連結する前記プレキャスト
工法(図51)について付言すれば、これが、内空高さ
が5mまでの比較的小規模の貯水槽を対象にしたもので
あるときは、前記した1段切梁による支保工で対応でき
る。このような支保工による場合は、連結梁ブロックh
と支柱ブロックg,g相互を、作業スペースを確保して
容易に連結できるようにするため、図52に示すよう
に、該支柱ブロックgを、格子状の切梁kが形成する矩
形状の区画nの一辺pに近接させてその中央部で立設す
るのが一般的であった。そしてかかるプレキャスト工法
によるときは、その切梁の下側で貯水槽構築を完了で
き、又その構築完了後における埋め戻し、及び切梁等か
らなる支保工を解体、撤去するという工事も、支障なく
行なうことができた。As for the precast method (FIG. 51) in which the upper ends of the pillar blocks g, which are adjacent to each other in one direction, are connected by the connecting beam block h, this is a relatively small scale with an inner height of up to 5 m. When it is intended for the water storage tank of No. 1, it can be dealt with by the support work by the above-mentioned one-step beam. In the case of such support work, connecting beam block h
In order to secure a working space and to easily connect the column blocks to each other, the column block is formed into a rectangular section formed by a grid-shaped cut beam k, as shown in FIG. It was common to stand upright at the center of one side p of n. When the precast method is used, the construction of the water tank can be completed under the beam, and after the completion of the construction, the backfilling and the work of dismantling and removing the supporting structure including the beam can be done without any problems. I was able to do it.
【0009】しかしながら貯水槽の内空高さが5m以上
と大きくなると、切梁kが前記のように複数段になる。
そして、支柱ブロックの上端は、通常、上段の切梁kの
稍下側に位置せしめられる。このように切梁kが複数段
になる場合は、これらの切梁が存在したままの状態で貯
水槽構築を行なわんとしても、前記のように、中間及び
最下段の切梁が障害となって、かかる施工は極めて困難
となる。これを解決するためには、下から上に向けての
壁板の付設に伴って、該壁板と土留壁との間に埋め戻し
を行ない、埋め戻し後、その直上の切梁を解体、撤去し
ながら貯水槽構築を進める必要がある。このように施工
する場合は、本発明の請求項10,11に係る技術を応
用して、埋め戻し土から圧力を受ける壁板を支持する支
柱ブロックの安定化を図るたために、隣り合う支柱間の
全てを前記連結梁ブロックによって連結することが考え
られる。つまり、連結梁ブロックを前記のような一方向
だけではなく、互いに直交する二方向に設ける必要が生
ずるのである。However, when the inner air height of the water storage tank is increased to 5 m or more, the crossbeams k have a plurality of stages as described above.
Then, the upper end of the pillar block is normally positioned on the slightly lower side of the upper cross beam k. In this way, when the crossbeams k have a plurality of stages, even if the water tank is constructed with these crossbeams existing, as described above, the middle and the lowest crossbeams become obstacles. Therefore, such construction becomes extremely difficult. In order to solve this, with the attachment of the wall plate from the bottom to the top, backfilling is performed between the wall plate and the retaining wall, and after the backfilling, the cutting beam immediately above is dismantled, It is necessary to proceed with water tank construction while removing it. When the construction is performed in this manner, the technique according to claims 10 and 11 of the present invention is applied to stabilize the strut block that supports the wall plate that receives the pressure from the backfill soil, so It is conceivable to connect all of them with the connecting beam block. That is, it is necessary to provide the connecting beam blocks not only in one direction as described above but also in two directions orthogonal to each other.
【0010】その場合、前記のように、矩形状の区画の
一辺pに近接させてその中央部で支柱ブロックを立設し
たのでは、連結梁ブロックを、前記のように一方向(図
52に矢印F1で示す方向)で連結する作業は容易に行
なうことができても、これと直交する方向(図52に矢
印F2で示す方向)で連結せんとするときは、切梁が障
害となる問題が生ずることになる。このことを、以下
に、図面に基づいてより詳しく説明する。In that case, as described above, since the pillar block is erected at the center of the rectangular section in close proximity to one side p, the connecting beam block is unidirectional as described above (see FIG. 52). Even if the work of connecting in the direction indicated by the arrow F1) can be easily performed, when the connection is made in the direction orthogonal thereto (the direction indicated by the arrow F2 in FIG. 52), the crossbeam will be an obstacle. Will occur. This will be described in more detail below with reference to the drawings.
【0011】即ち、連結梁ブロックhによって支柱ブロ
ックgの上端相互を連結する工程は、先ず図53に示す
ように、両端部q,qが前記連結梁ブロックhの両端側
r,rに固定されたワイヤーからなる吊下ロープsの中
央部をクレーンのフックtに引っ掛けて吊り上げる。該
吊下ロープsの傾斜片u,uの角度は、例えば60度に
設定される。今、前記一方向F1で隣り合う支柱ブロッ
クg,gの上端相互を連結梁ブロックhで連結せんとす
る場合は、前記区画nで吊り下ろした連結梁ブロックh
の横移動を、図54に示すように、前記吊下ロープsの
傾斜辺uが切梁kに接触しない状態で行なうことができ
る。しかしながら直交方向F2で隣り合う支柱ブロック
g,gの上端相互を連結せんとする場合は、前記区画n
で吊り下ろした連結梁ブロックhを横移動させる際に、
前記吊下ロープsの傾斜片uが図55に示すように切梁
kに当たる。そのため図56に示すように、該吊下ロー
プsの端部qの付け替えを行なわない限り、該前後方向
の支柱ブロックg,gの上端相互を連結梁ブロックhで
連結することが極めて困難となる。仮に図56に示すよ
うに、前記吊下ロープsの端部の付け替えを行なう場合
は、連結梁ブロックgを吊り下げた状態のままでその作
業を行なうことになるため、その付け替えに、非常に面
倒で且つ危険な作業を強いられるという問題が生じて、
全く実用的でない。このように、前記一方向と直交する
方向F2で支柱ブロックの上端相互を連結せんとすると
きは、切梁が障害となる問題が生ずることになるのであ
る。That is, in the step of connecting the upper ends of the pillar blocks g to each other by the connecting beam block h, first, as shown in FIG. 53, both ends q and q are fixed to both ends r and r of the connecting beam block h. The central part of the hanging rope s composed of a wire is hooked on the hook t of the crane and lifted. The angle between the inclined pieces u, u of the suspension rope s is set to, for example, 60 degrees. When the upper ends of the pillar blocks g adjacent to each other in the one direction F1 are to be connected by the connecting beam block h, the connecting beam block h suspended in the section n is used.
As shown in FIG. 54, the lateral movement can be performed in a state where the slanted side u of the suspension rope s does not contact the cross beam k. However, when the upper ends of the pillar blocks g, g adjacent to each other in the orthogonal direction F2 are to be connected to each other, the partition n
When laterally moving the connecting beam block h suspended by
The slanting piece u of the hanging rope s hits the cross beam k as shown in FIG. Therefore, as shown in FIG. 56, it is extremely difficult to connect the upper ends of the column blocks g in the front-rear direction with the connecting beam block h unless the end q of the suspension rope s is replaced. . As shown in FIG. 56, when replacing the end portion of the suspension rope s, the work is performed while the connecting beam block g is suspended. Therefore, the replacement is extremely difficult. The problem that it is troublesome and forced to do dangerous work,
Not practical at all. As described above, when the upper ends of the pillar blocks are connected to each other in the direction F2 which is orthogonal to the one direction, there arises a problem that the cutting beam becomes an obstacle.
【0012】そのため従来においては、内空高さの大き
い(内空高さが、例えば5〜10m)貯水槽は現場打ち
施工によって構築していた。かかる現場打ち施工による
場合は、切梁が格子状に交差する切梁枠組が上下複数段
に設けられていたとしても、前後左右の切梁が形成する
矩形状の囲いを通して掘削空間内に材料を導入でき、材
料の横移動も自由であるために、目的とする貯水槽を比
較的容易に構築できる利点はあった。しかし、柱部や壁
部を上方に延長する施工途中の段階で埋め戻しした際に
該柱部や壁部が土圧で不安定化しないようにするため、
これらを、中間の水平な支え梁部で支持する必要があっ
た。ところが、このように支え梁部で支持するには、該
支え梁部を形成するための型枠の組立てや該型枠を支持
するための支保工が特別に必要となって、貯水槽構築の
ための工期の長期化と施工コストの上昇を招く問題があ
った。又このように支え梁部を設けることから、その分
だけ貯水槽の内部容積が減少してしまう問題もあった。For this reason, conventionally, a water tank having a large inner air height (inner air height is, for example, 5 to 10 m) has been constructed by cast-in-place construction. In the case of such cast-in-place construction, even if a crossbeam frame assembly in which the crossbeams intersect in a grid pattern is provided in a plurality of upper and lower stages, the material is placed in the excavation space through the rectangular enclosure formed by the front, rear, left, and right cut beams. Since it can be introduced and the lateral movement of the material is also free, there was an advantage that the desired water tank could be constructed relatively easily. However, in order to prevent the pillars and walls from being destabilized by earth pressure when they are backfilled during the process of extending the pillars and walls upward,
It was necessary to support them with a horizontal support beam portion in the middle. However, in order to support the supporting beam portion in this way, it is necessary to specially assemble a formwork for forming the supporting beam part and a supporting work for supporting the formwork, and therefore, it is necessary to construct a water tank. Therefore, there was a problem that the construction period was prolonged and the construction cost was increased. Further, since the supporting beam portion is provided in this manner, there is a problem that the internal volume of the water storage tank is reduced by that amount.
【0013】[0013]
【発明が解決しようとする課題】本発明は、かかる従来
の問題点に鑑みて開発されたものであり、連結梁による
支柱相互の連結を容易とし、更に進んで、外周に存する
支柱間に壁板を容易に付設可能とすることによって、内
空高さの大きい貯水槽を、短い工期でしかも熟練工を必
要とせずに能率よく構築可能とするプレキャストコンク
リート製貯水槽の構築工法の提供を課題とするものであ
る。SUMMARY OF THE INVENTION The present invention has been developed in view of the above-mentioned problems of the prior art, and facilitates the connection of columns with each other by a connecting beam, and further advances the wall between the columns existing on the outer periphery. The problem is to provide a construction method for a water tank made of precast concrete that makes it possible to efficiently construct a water tank with a large inner air height by making it possible to attach plates easily in a short construction period and without requiring skilled workers. To do.
【0014】[0014]
【課題を解決するための手段】前記課題を解決するた
め、本発明は以下の手段を採用する。即ち、本発明に係
るプレキャストコンクリート製貯水槽の構築工法(以下
構築工法という)の第1の態様は、左右方向の切梁と前
後方向の切梁とが平面視で格子状に交差する如く組み立
てられた切梁枠組を上下複数段に具える土留壁支保工を
設けた掘削空間において、プレキャストコンクリート製
の貯水槽を構築する構築工法であり、前記土留壁支保工
において、上下複数段に配設された左右方向の切梁及
び、上下複数段に配設された前後方向の切梁は、夫々平
面視で略重なる如くなす。又前記掘削空間の底部で支柱
を所要配置に立設し、該支柱の上端を、最上段の切梁の
下側に位置させ、隣り合う支柱の上端相互を連結梁で連
結し、外周に存する支柱には、該外周の支柱間を覆うよ
うに下から上に向けて順次付設される壁板を支持させる
ものとし、又、前記外周の支柱の内側に配置する支柱
は、前後左右の切梁が形成する矩形状の区画内に1本づ
つ存在せしめ、該支柱を、矩形状の区画の同一コーナ部
において立設することを特徴とするものである。In order to solve the above problems, the present invention adopts the following means. That is, the first aspect of the construction method of the precast concrete water storage tank according to the present invention (hereinafter referred to as the construction method) is assembling so that the cross beams in the left-right direction and the cross beams in the front-rear direction intersect in a grid pattern in a plan view. It is a construction method to construct a water tank made of precast concrete in the excavation space where the earth retaining wall support is provided in the upper and lower stages of the timber frame structure. The left and right horizontal beams and the front and rear vertical beams arranged in a plurality of upper and lower stages are formed so as to substantially overlap each other in a plan view. Further, a pillar is erected in a required arrangement at the bottom of the excavation space, the upper end of the pillar is located below the uppermost beam, and the upper ends of the adjacent pillars are connected to each other by a connecting beam, which exists on the outer circumference. The pillars shall support the wall plates sequentially attached from the bottom to the top so as to cover the spaces between the pillars on the outer circumference, and the pillars arranged inside the pillars on the outer circumference are the front, rear, left and right beams. The columns are made to exist one by one in the rectangular section formed by, and the columns are erected at the same corner portion of the rectangular section.
【0015】前記構築工法において、前後左右の切梁が
形成する矩形状の区画の内、外周に存する区画の所要の
ものに、壁板を支持しない支柱と合わせて、壁板を支持
する支柱も存在させることがある。In the above-mentioned construction method, among the rectangular compartments formed by the front, rear, left and right beams, the required ones of the compartments on the outer periphery are combined with the pillars which do not support the wall board, and also the pillars which support the wall board. May be present.
【0016】本発明に係る構築工法のより具体的な態様
(第2の態様)は、平面視で格子状に交差する如く組み
立てられた左右方向の切梁と前後方向の切梁とを具える
土留壁支保工を設けた掘削空間において、プレキャスト
コンクリート製の貯水槽を構築する構築工法であり、前
記土留壁支保工において、上下複数段に配設された左右
方向の切梁及び、上下複数段に配設された前後方向の切
梁は、夫々平面視で略重なる如くなす。又前記掘削空間
の底部で支柱を所要配置に立設し、該支柱の上端を、最
上段の切梁の下側に位置させ、隣り合う支柱の上端相互
を連結梁で連結し、外周に存する支柱には、該外周の支
柱間を覆うように下から上に向けて順次付設される壁板
を支持させるものとし、又、前記外周の支柱の内側に配
置する支柱は、前後左右の切梁が形成する矩形状の区画
内に1本づつ存在せしめ、該支柱を、矩形状の区画の同
一コーナ部において立設すると共に、前後左右の切梁が
形成する矩形状の区画の外側に存する区画に配設する支
柱は、前記コーナ部に立設されている支柱と前後対向す
る状態で或いは左右対向する状態で切梁に近接して立設
し、左右方向で見て隣り合う支柱の中心間の距離を、十
字状に交わる切梁交差点の内の隣り合う左右の交差点間
の距離に略等しく設定すると共に、前後方向で見て隣り
合う支柱の中心間の距離を、十字状に交わる切梁交差点
の内の隣り合う前後の交差点間の距離に略等しく設定す
ることを特徴とするものである。A more specific aspect (second aspect) of the construction method according to the present invention comprises a left-right beam and a front-back beam which are assembled so as to intersect in a grid pattern in a plan view. A construction method for constructing a water tank made of precast concrete in an excavation space provided with earth retaining wall support, wherein in the earth retaining wall support, horizontal beams and vertical upper and lower stages arranged in a plurality of upper and lower stages. The cross beams in the front-rear direction, which are arranged in the above, respectively, are formed so as to substantially overlap each other in a plan view. Further, a pillar is erected in a required arrangement at the bottom of the excavation space, the upper end of the pillar is located below the uppermost beam, and the upper ends of the adjacent pillars are connected to each other by a connecting beam, which exists on the outer circumference. The pillars shall support the wall plates sequentially attached from the bottom to the top so as to cover the spaces between the pillars on the outer circumference, and the pillars arranged inside the pillars on the outer circumference are the front, rear, left and right beams. One of each of the columns is present in the rectangular section formed by, and the pillars are erected at the same corner portion of the rectangular section, and are located outside the rectangular section formed by the front, rear, left, and right cutting beams. The pillars to be installed on the corners are installed standing close to the crossbeam in a state of being opposed to the pillars standing at the corner portion in the front-rear direction or in a state of being opposed to the left-right direction. The distance between adjacent left and right crossing beam intersections The distance between the centers of the columns adjacent to each other when viewed in the front-rear direction is set to be substantially equal to the distance between the adjacent front and rear intersections of the cross beam intersections intersecting in a cross shape. To do.
【0017】前記第1、第2の態様において、隣り合う
支柱の上端相互を前記連結梁で連結するに際し、両端部
分が前記連結梁の両端側に固定された吊下ロープの中央
部をフックで吊り上げ、該連結梁を、前記左右方向や前
後方向に対し傾いた状態で前記矩形状の区画内で吊り下
ろし、前記最上段の切梁の下側において、該連結梁の向
きを左右方向又は前後方向にして後、該連結梁を左右方
向又は前後方向で横移動させ、該吊下ロープの傾斜辺
が、該隣り合う支柱間に存する切梁に接触状態となる前
に、或いは、該吊下ロープの傾斜辺が該切梁に接触して
も該傾斜辺が撓み変形しない状態で、該連結梁の両端部
分を隣り合う支柱の上端に載せることとするのがよい。In the first and second aspects, when the upper ends of the adjacent columns are connected to each other by the connecting beam, both ends of the hanging rope are fixed to both ends of the connecting beam by a hook. Hoisting, the connection beam is hung in the rectangular section in a state of being inclined with respect to the left-right direction and the front-rear direction, and the direction of the connection beam is changed in the left-right direction or the front-rear direction below the uppermost cut beam. Direction, and then the connecting beam is laterally moved in the left-right direction or the front-back direction, before the slanted side of the suspending rope comes into contact with the cross beam existing between the adjacent columns, or It is preferable that both end portions of the connecting beam are placed on the upper ends of the adjacent columns in a state where the inclined side of the rope is not bent and deformed even when the inclined side comes into contact with the cutting beam.
【0018】又前記第1、第2の態様において、前記土
留壁支保工は、切梁を下方から支持する支持杭を、左右
方向の切梁と前後方向の切梁との交差部分の同一のコー
ナ部で立設して形成し(同一のコーナ部の全てで立設す
るとは限らない)、前記支柱を、前記支持杭と対角配置
で立設するのがよい。Further, in the first and second aspects, the earth retaining wall support work includes a support pile for supporting the cutting beam from below, which is the same at an intersection portion of the cutting beam in the left-right direction and the cutting beam in the front-rear direction. It is preferable that the pillars are formed by being erected at the corner portions (not necessarily erected at all of the same corner portions), and the pillars are erected in a diagonal arrangement with the support piles.
【0019】前記各構築工法において、前記支柱は、そ
の上端で、支持突部が側方向に張り出し形成されたもの
とし、前記連結梁の端部分を該支持突部に載せることと
するのがよい。この場合、平面視で、前記支持突部の側
端と、これに対向する切梁との間の間隔を10〜40c
mに設定するのがよい。In each of the construction methods described above, it is preferable that the pillar has a support projection formed at the upper end thereof so as to project laterally, and the end portion of the connecting beam is placed on the support projection. . In this case, in plan view, the distance between the side end of the support protrusion and the girder facing it is 10 to 40c.
It is better to set to m.
【0020】又、前記第1、第2の態様において、外周
に存する隣り合う支柱間を覆うように壁板を付設するに
際し、両端部分が前記壁板の両端側に固定された吊下ロ
ープの中央部をフックで吊り上げ、該壁板を、前記左右
方向や前後方向に対し傾いた状態で、前記支柱が存する
前記区画内で吊り下ろし、該壁板の向きを左右方向又は
前後方向にして後、該壁板を左右方向又は前後方向で横
移動させ、前記吊下ロープの傾斜辺が、隣り合う支柱間
に存する切梁に接触状態となる前に、或いは、該吊下ロ
ープの傾斜辺が該切梁に接触しても該傾斜辺が撓み変形
しない状態で、該壁板の両端部分を隣り合う支柱の外面
側で支持させることとするのがよい。In addition, in the first and second aspects, when attaching the wall plate so as to cover between the adjacent columns existing on the outer periphery, both ends of the hanging rope fixed to both end sides of the wall plate. The central part is hung up with a hook, and the wall plate is hung in the section in which the stanchions are present with the wall plate inclined with respect to the left-right direction and the front-rear direction, and the direction of the wall plate is changed to the left-right direction or the front-rear direction. , The wall plate is laterally moved in the left-right direction or the front-rear direction, and before the slanted side of the hanging rope comes into contact with a beam which exists between adjacent columns, or the slanted side of the hanging rope is It is preferable that both end portions of the wall plate are supported on the outer surface side of the adjacent columns in a state where the inclined side does not bend and deform even when the pillar is contacted.
【0021】又前記各構築工法において、前記支柱は、
その外面側で、壁板受部が側方向に張り出し形成された
ものとし、前記壁板の端部分を該壁板受部で支持させる
こととするがよい。Further, in each of the construction methods, the pillar is
It is preferable that the wall plate receiving portion is formed so as to project laterally on the outer surface side, and the end portion of the wall plate is supported by the wall plate receiving portion.
【0022】又前記第1、第2の態様において、前記外
周の支柱間を覆うように下から上に向けて順次前記壁板
を付設するに際し、各段の壁板付設毎に、或いは複数段
の壁板付設毎に、該壁板と土留壁との間に埋め戻しを行
い、且つ該埋め戻しを行って後、その直上にある切梁を
撤去できるように、切梁の上下配置を考慮して設定され
た上下高さを有する壁板を付設するのがよい。或いは、
前記外周の支柱間を覆うように下から上に向けて順次前
記壁板を付設するに際し、各段の壁板付設毎に、或いは
複数段の壁板付設毎に、該壁板と土留壁との間に埋め戻
しを行い、且つ該埋め戻しを行って後、その直上にある
切梁を撤去できるように、壁板の上下高さを考慮して切
梁の上下配置を設定するのがよい。In addition, in the first and second aspects, when the wall plates are sequentially attached from the bottom to the top so as to cover between the columns of the outer periphery, the wall plates are attached at each stage or at a plurality of stages. Each time a wall plate is attached to the wall plate, backfill is performed between the wall plate and the retaining wall, and after the backfill is performed, the vertical arrangement of the cut beams is considered so that the cut beam directly above can be removed. It is advisable to attach a wall plate having a vertical height set by the above method. Alternatively,
When the wall plates are sequentially attached from the bottom to the top so as to cover between the columns of the outer periphery, the wall plates and the earth retaining wall are provided for each stage of the wall plates attached or for each of the stages of the wall plates attached. It is preferable to set the vertical arrangement of the beams in consideration of the vertical height of the wall plate so that the vertical beams of the wall boards can be removed so that the vertical beams of the wall beams can be removed after performing the backfilling after the backfilling. .
【0023】なお本発明において貯水槽とは、大量の雨
水を一時的に貯留する雨水一時貯留槽や、植栽、融雪等
の各種用途に複合利用し得る水槽を含むものである。In the present invention, the water storage tank includes a rainwater temporary storage tank for temporarily storing a large amount of rainwater, and a water tank which can be used in combination for various purposes such as planting and snow melting.
【0024】[0024]
【発明の実施の形態】以下、本発明の実施の形態を図面
に基づいて説明する。本発明に係る構築工法は、内空高
さの大きい図1に示す貯水槽1を構築するに際して、図
2に示すように、平面視で格子状に交差する如く組み立
てられた左右方向F1の切梁2aと前後方向F2の切梁
2bとを具える切梁枠組3が上下複数段に設けられた土
留壁支保工5が存在する掘削空間6において、平面視で
格子状に分割されてなる各区画7の夫々で、その底部8
で支柱9を立設し、隣り合う支柱9,9の上端10,1
0相互を連結梁11で連結し、又図1に示すように、外
周に存する支柱9a,9a間を覆うように壁板12を付
設するものである。これを、工程順に、より具体的に説
明すれば以下のようである。BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below with reference to the drawings. In the construction method according to the present invention, when constructing the water storage tank 1 shown in FIG. 1 having a large inner height, as shown in FIG. 2, a cut in the left-right direction F1 assembled so as to intersect in a grid pattern in a plan view. In the excavation space 6 in which the earth retaining wall support 5 having the beams 2a and the beams 2b extending in the front-rear direction F2 are provided in a plurality of upper and lower stages, each of which is divided into a lattice shape in a plan view. In each of the compartments 7, its bottom 8
The pillar 9 is erected on the upper side, and the upper ends 10, 1 of the adjacent pillars 9, 9 are
0s are connected to each other by a connecting beam 11, and a wall plate 12 is attached so as to cover between the columns 9a existing on the outer periphery, as shown in FIG. This will be described below in more detail in the order of steps.
【0025】まず図3〜4に示すように、前記貯水槽1
を地下埋設するために掘り下げるべき地盤13を周方向
で取り囲むように、継手15,15相互を接続させて鋼
矢板16を連続壁状に打ち込んで(通常図4に示すよう
に、鋼矢板16の上端17を、地面19に位置させ
る)、平面視で例えば矩形状の土留壁20を形成する。
併せて、地盤を掘り下げたときに該土留壁20を支持す
るための土留壁支保工5を構成する支持杭21を、例え
ば図3に示すように前後方向及び左右方向に所要間隔を
おいて地盤13に打ち込む。First, as shown in FIGS.
The steel sheet pile 16 is driven into a continuous wall shape by connecting the joints 15 and 15 to each other so as to surround the ground 13 to be dug in order to bury it underground (usually, as shown in FIG. The upper end 17 is located on the ground surface 19), and a soil retaining wall 20 having a rectangular shape in plan view is formed.
At the same time, the support piles 21 that constitute the earth retaining wall support 5 for supporting the earth retaining wall 20 when the earth is dug down are provided with the required intervals in the front-rear direction and the left-right direction as shown in FIG. Type in 13.
【0026】その後、前記のように構築された土留壁2
0の内側を掘り下げる。この掘り下げは、例えば10〜
11m程度の深さにまで行う。この掘り下げに際して
は、所定深さの掘削が完了する毎に、図2に示すよう
に、例えば最上段と中段と最下段の3個所に切梁枠組3
a,3b,3cを形成する。各切梁枠組の形成高さは、
土留壁20の安定支持を考慮して設定する。例えば最上
段の切梁枠組3aは、図5に示し又図6に一点鎖線で示
す深さDにまで掘り下げた状態で形成する。Then, the retaining wall 2 constructed as described above.
Dig inside 0. This digging is, for example, 10
Perform to a depth of about 11 m. At the time of this digging, each time the digging to a predetermined depth is completed, as shown in FIG.
a, 3b, 3c are formed. The forming height of each girder frame is
It is set in consideration of stable support of the retaining wall 20. For example, the uppermost girder framework 3a is formed in a state of being dug down to a depth D shown in FIG.
【0027】該切梁枠組3a,3b,3cは、図2、図
5、図7に示すように、鋼矢板16の内面の所定高さ位
置に固設される腹起し22と、対向する左右の腹起し2
2a,22a間に例えば5m間隔で平行して架設された
左右方向の切梁2aと、前記左右方向の腹起し22aよ
りも一段高い位置で固設された対向する前後の腹起し2
2b,22b間に、例えば5mの間隔をおいて平行して
架設された前後方向の切梁2bとを具え、左右方向の切
梁2a上に前後方向の切梁2bが載置されてなる。そし
て、左右方向の腹起し22aと前後方向の腹起し22b
の端部側相互は火打ち23で連結されると共に、切梁の
所要のもの2a1,2b1の端部側と腹起し22a,2
2bとが火打ち25で連結されて補強される。このよう
に構成された最上段と中段と最下段の切梁枠組3a,3
b,3cを構成する左右方向の切梁2aと前後方向の切
梁2bは、図7に示すように夫々、平面視で略重なる。
そして前記支持杭21は、左右方向の切梁2aと前後方
向の切梁2bとが形成する十字状交差部分26の同一コ
ーナ部27(図7)の所要のもので立設される如くな
し、該切梁2a,2bを、図示しないブラケットを介し
て前記支持杭21に支持させる。これによって、前記矩
形状の土留壁20の内側に形成された掘削空間6を平面
視で格子状に分割し、多数の矩形状の区画7を形成す
る。このように形成された区画7には、図7に示すよう
に、前後左右の切梁によって4辺が形成された第1の区
画7aと、1辺乃至2辺が前記腹起し22a,22bに
よって形成された第2の区画7bとがあり、該第2の区
画7bが前記第1の区画7aの外周に配置されている。As shown in FIG. 2, FIG. 5, and FIG. 7, the cross beam frames 3a, 3b, and 3c face an uprising 22 that is fixedly installed at a predetermined height position on the inner surface of the steel sheet pile 16. Right and left angry 2
2a, 22a, for example, a left-right beam girder 2a installed in parallel at intervals of 5 m, and a front-rear ridge 2 facing each other fixed at a position higher than the left-right ridge 22a.
A front and rear direction cutting beam 2b is provided between 2b and 22b in parallel at a distance of 5 m, for example, and the front and rear direction cutting beam 2b is placed on the left and right direction cutting beam 2a. Then, the right and left uprising 22a and the front and rear uprising 22b
The end side of each of them is connected by a flint 23, and is raised with the end side of the required ones 2a1 and 2b1 of the beam.
2b and reinforced by being connected by fire 25. The top, middle, and bottom girder frames 3a, 3 configured in this way
The left and right cutting beams 2a and the front and rear cutting beams 2b forming b and 3c substantially overlap each other in plan view as shown in FIG.
The support piles 21 are formed so as to be erected at required parts of the same corner portion 27 (FIG. 7) of the cross-shaped crossing portion 26 formed by the left and right cutting beams 2a and the front and rear cutting beams 2b. The cutting beams 2a and 2b are supported by the support pile 21 via a bracket (not shown). As a result, the excavation space 6 formed inside the rectangular earth retaining wall 20 is divided into a lattice shape in plan view, and a large number of rectangular sections 7 are formed. In the partition 7 thus formed, as shown in FIG. 7, a first partition 7a having four sides formed by front, rear, left, and right beams, and one or two sides of the uprising 22a, 22b. A second section 7b formed by the second section 7b, and the second section 7b is arranged on the outer periphery of the first section 7a.
【0028】前記のように、最上段と中段と最下段の3
個所に切梁枠組3a,3b,3cを形成して後、図2、
図6に示すように、掘削空間6の底部8に、現場打ち施
工により、例えば1m程度の厚さにコンクリートを打設
して底盤部30を築造する。そして、該築造した底盤部
30が土留壁20を支持できるように、例えば図6に示
す如く、該底盤部30と土留壁20との間に支持材28
を介在させて後、図8に示すように、前記最下段の切梁
枠組3cを構成する左右方向及び前後方向の切梁2a,
2bを解体撤去する。なお図2においては、土留壁支保
工5の全体構成を説明する都合上、最下段の切梁枠組3
cを図示しているが、支柱9が立設された状態では、こ
の切梁枠組3cは存在しない。As described above, the top, middle, and bottom 3
After forming the girder frames 3a, 3b, 3c at the points, as shown in FIG.
As shown in FIG. 6, on the bottom portion 8 of the excavation space 6, by concrete-casting on site, concrete is cast to a thickness of, for example, about 1 m to construct the bottom plate portion 30. Then, as shown in FIG. 6, for example, as shown in FIG. 6, a support member 28 is provided between the bottom plate portion 30 and the soil retaining wall 20 so that the built bottom plate portion 30 can support the soil retaining wall 20.
After the interposition, as shown in FIG. 8, cut beams 2a in the left-right direction and in the front-rear direction, which form the cut beam framework 3c in the lowermost stage,
2b is dismantled and removed. Note that, in FIG. 2, for the sake of convenience of explaining the entire structure of the retaining wall support work 5, the lowermost beam girder framework 3 is shown.
Although c is illustrated, this girder framework 3c does not exist in a state in which the column 9 is erected.
【0029】次に、前記矩形状の区画7の夫々につい
て、図8〜9に示すように、掘削空間の底部8(前記底
盤部30)で1本の支柱9を立設する。これらの支柱9
は、前後左右の切梁が形成する第1の区画7a内におい
ては、図10〜11に示すように、その同一コーナ部3
2で立設させるものとし、左右方向F1に並設される各
支柱の中心33を同一直線35上に存在させ、且つ、前
後方向F2に並設される各支柱の中心33も同一直線3
6上に存在させる。そして、左右方向で見た支柱の中心
33,33間の距離L1を、十字状に交わる切梁交差点
の内の隣り合う左右の交差点37,37間の距離L2に
略等しく設定すると共に、前後方向で見た支柱の中心3
3,33間の距離L3を、十字状に交わる切梁交差点の
内の隣り合う前後の交差点37,37間の距離L4に略
等しく設定する。そして、前記十字状交差部分で支持杭
21が立設されている場合は、該立設された支柱9と支
持杭21とが対角配置になる。Next, for each of the rectangular sections 7, as shown in FIGS. 8 to 9, one column 9 is erected at the bottom 8 (the bottom plate 30) of the excavation space. These stanchions 9
In the first section 7a formed by the front, rear, left and right beams, as shown in FIGS.
2, the centers 33 of the columns arranged in the left-right direction F1 are arranged on the same straight line 35, and the centers 33 of the columns arranged in the front-rear direction F2 are also arranged on the same line 3.
6 to exist. Then, the distance L1 between the centers 33, 33 of the columns viewed in the left-right direction is set substantially equal to the distance L2 between the adjacent left and right intersections 37, 37 of the cross beam intersections intersecting each other in the cross direction, and Center 3 of the pillar seen in
The distance L3 between 3 and 33 is set to be approximately equal to the distance L4 between the front and rear intersections 37, 37 that are adjacent to each other among the cross beam intersections that intersect in a cross shape. When the support piles 21 are erected at the cross-shaped intersections, the erected supports 9 and the support piles 21 are diagonally arranged.
【0030】本実施の形態においては、図10に示すよ
うに、左右方向で見た第1の区画7aの列の両外側に存
する区画(前記第2の区画)7b,7b、及び前後方向
で見た第1の区画7aの列の両外側に存する区画(前記
第2の区画)7b,7bにも1本づつの支柱9を立設す
るのであるが、該外周の支柱9bの中心33は、前記左
右方向の直線35の延長線上、及び前記前後方向の直線
36の延長線上に存在せしめる。なお本実施の形態にい
ては、左右方向の支柱間の間隔及び前後方向の支柱間の
間隔は等しく設定されている。従って、前記第2の区画
7a内に存する支柱9bは、平面視で、該区画7aの同
一コーナ部39に存在し、或いは左右方向の切梁2a又
は前後方向の切梁2bに近接する。このように立設され
た支柱9の上端10は、図8に示すように、最上段の切
梁枠組3aを構成する切梁2の下側に位置せしめられ
る。In this embodiment, as shown in FIG. 10, the sections (the second sections) 7b and 7b existing on both outer sides of the row of the first sections 7a as viewed in the left-right direction and in the front-rear direction. One strut 9 is erected in each of the compartments (second compartments) 7b, 7b existing on both outer sides of the first compartment 7a seen, but the center 33 of the outer pillar 9b is , On the extension line of the straight line 35 in the left-right direction and on the extension line of the straight line 36 in the front-rear direction. In addition, in the present embodiment, the interval between the columns in the left-right direction and the interval between the columns in the front-rear direction are set to be equal. Therefore, the columns 9b existing in the second section 7a are present in the same corner portion 39 of the section 7a or are close to the left and right cutting beams 2a or the front and rear cutting beams 2b in a plan view. As shown in FIG. 8, the upper ends 10 of the stanchions 9 thus erected are located below the beams 2 that form the uppermost beam framework 3a.
【0031】なお、立設された支柱9の上端10を、最
上段の切梁枠組3aの上方に位置させることも考えられ
ないではないが、前記最上段の切梁枠組3aが、通常、
前記鋼矢板の上端(地面19)17から70〜80cm
下方に配設される関係上、このように立設された支柱の
上端相互を連結梁11で連結したときは、該連結梁11
の上下高さが、大きいものでは120〜150cmにも
なるために、該連結梁11が地面19から大きく突出し
てしまうことになる。このような不都合があるために、
現在構築されている貯水槽の圧倒的大部分は、連結梁1
1を地面19に突出させないタイプのものである。Although it is not considered that the upper end 10 of the upright pillar 9 is located above the uppermost beam structure 3a, the uppermost beam structure 3a is usually
70 to 80 cm from the upper end (ground 19) 17 of the steel sheet pile
Because of the arrangement below, when the upper ends of the erected columns are connected by the connecting beam 11, the connecting beam 11
In the case of a large one, the vertical height is as large as 120 to 150 cm, so that the connecting beam 11 largely projects from the ground 19. Due to such inconvenience,
The overwhelming majority of the water tanks currently constructed are the connecting beams 1.
1 is a type that does not project onto the ground 19.
【0032】本発明は、この種の貯水槽を構築する工法
であるため、連結梁の上下高さを考慮して、支柱9の上
端10を、最上段の切梁枠組3aの下側に位置させるこ
ととしているのである。Since the present invention is a construction method for constructing this kind of water storage tank, the upper end 10 of the column 9 is positioned below the uppermost beam structure 3a in consideration of the vertical height of the connecting beam. It is supposed to be done.
【0033】ここで前記支柱9の構成を説明すれば、第
1の区画7aに存する支柱9aは、本実施の形態におい
ては図12に示すように、支柱本体38が横断面正方形
状を呈する角柱状に形成されている。又第2の区画7b
に存する支柱9bは、図27や図29に示すように、そ
の外面側40が両側に稍拡がるように横断面が台形状に
形成されており、前記壁板12の端部分41,41を支
持する壁板受部42,42が、該支柱9bの外面両側部
分で側方向に張り出し形成されている。なお支柱9に
は、例えば図14や図22に示すように垂直鉄筋64が
上方向に突設されるが 、説明の便宜上、これら以外の
図においては該垂直鉄筋64を省略している。Explaining the structure of the support column 9 here, the support column 9a in the first section 7a is a corner in which the support column 38 has a square cross section as shown in FIG. 12 in the present embodiment. It has a columnar shape. The second section 7b
As shown in FIG. 27 and FIG. 29, the pillar 9b present in FIG. 27 has a trapezoidal cross section so that its outer surface side 40 spreads on both sides, and supports the end portions 41, 41 of the wall plate 12. The wall plate receiving portions 42, 42 are formed so as to project laterally on both sides of the outer surface of the column 9b. It should be noted that, although vertical rebars 64 project upward from the columns 9 as shown in FIGS. 14 and 22, for convenience of description, the vertical rebars 64 are omitted in other figures.
【0034】かかる構成の支柱9は、例えば図13に示
すように、前記底盤部30の所要部位で立ち上げた連結
主筋43を、支柱9の下端部分に設けた継ぎ手スリーブ
45に挿入状態として底盤部30上に立設される。そし
て該支柱9の上端には、図12、図14に示すように、
前記連結梁11の両端部分46,46を支持する支持突
部47が側方向に張り出し形成されている。As shown in FIG. 13, for example, the supporting column 9 having such a structure is constructed by inserting the connecting main bar 43, which is erected at a required portion of the bottom plate portion 30, into the joint sleeve 45 provided at the lower end portion of the supporting column 9, and then the bottom plate. It is erected on the section 30. And, as shown in FIGS. 12 and 14, at the upper end of the column 9,
A support protrusion 47 that supports both end portions 46, 46 of the connecting beam 11 is formed to project laterally.
【0035】なお本実施の形態においては、平面視で、
前記支持突部47の側端49がこれに対向する切梁2か
ら10〜40cm程度離れた状態となるように、支柱9
をコーナ部39に立設することとしている。この間隔を
図17においてL5で示す。この程度に離した立設状態
とするのは、支柱9を、切梁2に接触しないようにして
前記第1の区画7a内で吊り下ろすことができると共
に、隣り合う支柱9,9の上端相互を連結するために後
述のように横移動させる連結梁11の移動量を、極力小
さくするためである。In the present embodiment, in plan view,
The support column 9 is arranged so that the side end 49 of the support protrusion 47 is separated from the facing girder 2 by about 10 to 40 cm.
Is to be installed upright on the corner portion 39. This interval is indicated by L5 in FIG. The erected state in which the columns 9 are separated by such a degree is that the columns 9 can be hung in the first section 7a without contacting the beams 2, and the upper ends of the columns 9 adjacent to each other can be mutually suspended. This is to minimize the amount of movement of the connecting beam 11 that is laterally moved to connect the two as described later.
【0036】次に、隣り合う支柱9,9の上端相互を連
結梁11で連結する。該連結梁11は、本実施の形態に
おいては図14、図1に示すように、上下方向に稍長い
断面長方形状を呈しており、後述する蓋版50の側部分
51を下方向から受ける支持突条52が、連結梁の長さ
方向に連続するように側面部38,38に設けられたも
のと、かかる支持突条52を有さないものの2種類があ
る。又両端面62,62には、突き出し鉄筋63が突設
されている。なお該連結梁11は、前記支持突条52が
設けられた一種類で構成されることもある。Next, the upper ends of the adjacent columns 9 are connected to each other by the connecting beam 11. In this embodiment, as shown in FIGS. 14 and 1, the connecting beam 11 has a rectangular cross section that is vertically long, and supports a side portion 51 of a lid plate 50, which will be described later, from below. There are two types of ridges 52, one provided on the side surface portions 38, 38 so as to be continuous in the length direction of the connecting beam, and one not having such support ridges 52. Further, protruding reinforcing bars 63 are provided on both end surfaces 62, 62. The connecting beam 11 may be composed of one type in which the supporting protrusion 52 is provided.
【0037】該連結梁11による連結工程を、隣り合う
第1の区画7a,7a内に存在する支柱9,9の上端1
0,10相互を連結する場合について説明すれば、先ず
図15に示すように、両端部53,53が前記連結梁1
1の両端側55,55に固定されたワイヤからなる吊下
ロープ56の中央部をクレーンのフック57に引っ掛け
て吊り上げる。該吊下ロープ56の傾斜辺59,59の
角度は、40〜60度に、好ましくは図15に示すよう
に60度に設定する。その後、該連結梁11を、前記左
右方向や前後方向に対し水平面内で傾いた状態にして、
第1の区画7a内で吊り下ろす。なお連結梁11は、こ
れを左右方向又は前後方向にしたままの状態で吊り下ろ
すことができる場合は、そのようにして吊り下ろせばよ
いため、水平面内で傾いた状態にして吊り下ろすことは
必ずしも必要ではないが、傾いた状態にすれば、吊り下
ろし作業を容易且つ安全に行い得る利点がある。The connecting step by the connecting beam 11 is performed by the upper end 1 of the columns 9, 9 existing in the adjacent first sections 7a, 7a.
The case of connecting 0 and 10 with each other will be described. First, as shown in FIG.
The center portion of the hanging rope 56 made of wires fixed to both ends 55 of the No. 1 is hooked on the hook 57 of the crane and lifted. The angle of the inclined sides 59, 59 of the suspension rope 56 is set to 40 to 60 degrees, preferably 60 degrees as shown in FIG. After that, the connecting beam 11 is tilted in a horizontal plane with respect to the left-right direction and the front-back direction,
It is suspended in the first compartment 7a. In addition, if the connecting beam 11 can be hung in a state where the connecting beam 11 is left or right or in the front-rear direction, the connecting beam 11 may be hung in such a manner. Therefore, it is not always necessary to hang it in an inclined state in a horizontal plane. Although not necessary, the tilted state has an advantage that the hanging operation can be performed easily and safely.
【0038】このように吊り下ろした状態で、該連結梁
11の下端60の高さを、立設状態にある前記支柱9の
上端10高さに略等しく設定する。この状態で、該連結
梁11は図17に示すように、最上段の切梁2の下側に
位置する。その後、例えば図16に矢印で示すように、
該連結梁11の長さ方向を左右方向又は前後方向に合わ
せて該連結梁11を左右方向又は前後方向で横移動さ
せ、該連結梁11の両端部分46,46を、隣り合う支
柱9,9の上端に形成されている前記支持突部47,4
7に載せる。In this suspended state, the height of the lower end 60 of the connecting beam 11 is set to be substantially equal to the height of the upper end 10 of the pillar 9 in the upright state. In this state, the connecting beam 11 is located below the uppermost beam 2 as shown in FIG. After that, for example, as shown by the arrow in FIG.
The connection beam 11 is laterally moved in the left-right direction or the front-rear direction by adjusting the length direction of the connection beam 11 to the left-right direction or the front-back direction, and the both end portions 46, 46 of the connection beam 11 are adjacent to each other. The support protrusions 47, 4 formed at the upper end of the
Put on 7.
【0039】かかる連結梁11の横移動は、支柱9が第
1の区画7aのコーナ部39で立設されているために、
その移動の際、吊下ロープ56の前記傾斜辺59が切梁
2に接触しない状態で行うことができる。或いは、該吊
下ロープ56の傾斜辺59が該切梁2に接触しても、該
傾斜辺59が撓み変形しない状態で無理なく行うことが
できる。The lateral movement of the connecting beam 11 is as follows because the pillar 9 is erected at the corner portion 39 of the first section 7a.
The movement can be performed in a state where the slanted side 59 of the suspension rope 56 does not come into contact with the truss 2. Alternatively, even if the slanted side 59 of the suspension rope 56 comes into contact with the girder 2, the slanted side 56 can be reasonably performed in a state in which the slanted side 59 does not bend and deform.
【0040】もしも図18に示すように、隣り合う支柱
9,9を、左右方向や前後方向で見て、第1の区画7
a,7aの辺61に近接させてその中央部分で立設した
とすれば、該区画で吊り下ろした連結梁11を、切梁2
を挟んで等距離に存する支柱9A、9Bの上端相互を連
結するために矢印方向に移動させる際、前記吊下ロープ
56の傾斜辺59が図19に示すように切梁2に当た
る。そのため、該吊下ロープ56の端部53の付け替え
を行わない限り、支柱9,9の上端相互を連結梁11で
連結するのが極めて困難となる。仮に図20に示すよう
に、前記吊下ロープ56の端部の付け替えを行なう場合
は、連結梁11を吊り下げた状態のままでその作業を行
うことになるため、その付け替えに、非常に面倒で且つ
危険な作業を強いられるという問題が生じて、全く実用
的でない。本発明には、切梁2が障害となることなく、
支柱9,9の上端相互を連結梁11で容易に連結できる
利点がある。If, as shown in FIG. 18, the adjacent columns 9, 9 are viewed in the left-right direction or the front-back direction, the first section 7
If it is assumed that the side portions 61 of a and 7a are placed close to each other and are erected at the central portion thereof, the connecting beam 11 suspended in the section is divided into two beams.
When the upper ends of the columns 9A and 9B that are equidistant from each other are moved in the arrow direction in order to connect them, the inclined side 59 of the suspension rope 56 hits the beam 2 as shown in FIG. Therefore, unless the end portion 53 of the suspension rope 56 is replaced, it becomes extremely difficult to connect the upper ends of the columns 9 with the connecting beam 11. As shown in FIG. 20, when the end portion of the suspension rope 56 is replaced, the work is performed while the connecting beam 11 is suspended. Therefore, the replacement is very troublesome. However, there is a problem of being forced to perform dangerous work, which is not practical at all. In the present invention, the girder 2 does not become an obstacle,
There is an advantage that the upper ends of the columns 9, 9 can be easily connected by the connecting beam 11.
【0041】又、前記第1の区画7a内に存在する支柱
9aと、その外周の第2の区画7b内に存する支柱9b
の上端相互を連結する場合や、外周に存する、隣り合う
第2の区画7b,7b内に存する支柱9b,9bの上端
相互を連結する場合は、図21に示すように、切梁2と
支柱9との間隔が大なる区画7b1側で連結梁11を吊
り下ろして後、該連結梁11を、切梁2と支柱9との間
隔が小さい区画7b2側の支柱9に向けて左右方向又は
前後方向に横移動させ、図21に一点鎖線で示すよう
に、支柱9,9の上端相互を連結梁11で連結する。こ
の場合における連結梁11の横移動も、前記吊下ロープ
56の傾斜辺59が該切梁2に接触しない状態で行うこ
とができる。或いは、該吊下ロープ56の傾斜辺59が
該切梁2に接触しても該傾斜辺59が撓み変形しない状
態で、無理なく行うことができる。Further, the pillar 9a existing in the first compartment 7a and the pillar 9b existing in the second compartment 7b on the outer periphery thereof.
When connecting the upper ends of each other, or when connecting the upper ends of the columns 9b, 9b existing in the adjacent second sections 7b, 7b on the outer periphery, as shown in FIG. After suspending the connecting beam 11 on the side of the section 7b1 having a large distance from the column 9, the connecting beam 11 is directed leftward or rightward or backward toward the pillar 9 on the side of the section 7b2 having a small distance between the cutting beam 2 and the pillar 9. 21, the upper ends of the columns 9, 9 are connected to each other by a connecting beam 11, as shown by a chain line in FIG. In this case, the lateral movement of the connecting beam 11 can also be performed in a state where the slanted side 59 of the suspension rope 56 does not come into contact with the cutting beam 2. Alternatively, it can be reasonably performed in a state in which the inclined side 59 of the suspension rope 56 does not bend and deform even when the inclined side 59 contacts the beam girder 2.
【0042】そして、支柱9と連結梁11の端部分46
とを一体化するには、例えば図22に示すように、該支
柱9の支持突部47で支持されている連結梁11,1
1、11,11の向き合う端面62,62で水平に突設
された前記突き出し鉄筋63,63相互を溶接する共
に、前記支柱9の上端10で上方向に垂直鉄筋64を突
設し、その後、型枠を組みコンクリートを打設して図2
3、図1に示す支柱接合部65を形成して行う。Then, the end portions 46 of the column 9 and the connecting beam 11 are
In order to integrate and, the connecting beams 11 and 1 supported by the supporting protrusions 47 of the column 9 are integrated as shown in FIG.
The protruding reinforcing bars 63, 63 horizontally projected at the facing end surfaces 62, 62 of 1, 11, 11 are welded to each other, and the vertical reinforcing bars 64 are projected upward at the upper end 10 of the column 9, and then, Figure 2 after placing the formwork and placing concrete
3 and the pillar joint part 65 shown in FIG. 1 are formed.
【0043】然る後、図24〜25、図1に示すよう
に、外周に位置する支柱9b,9b間にプレキャストコ
ンクリート製の壁板12を付設する。本実施の形態にお
いては、壁板12を上下4段に付設する。そのための施
工工程は、先ず図26に示すように、外周に位置する第
2の区画7bにおいて、前記壁板12を、前記左右方向
や前後方向に対し水平面内で傾いた状態にして、前記区
画7b内で所要位置にまで吊り下ろす。この状態で、該
壁板12は図24に示すように、その後に解体、撤去さ
れる中段の切梁枠組3bの下側に位置する。その後図2
6に示すように、該壁板12の長さ方向を左右方向や前
後方向に合わせて、該壁板12を、切梁2を挟んで左右
方向や前後方向で対向する支柱の内の、切梁2に近接し
た状態にある支柱9b1に向けて横移動させ、該壁板1
2の両端部分41,41を、隣り合う支柱9b,9bに
設けられた前記壁板受部42,42で支持させる。Thereafter, as shown in FIGS. 24 to 25 and FIG. 1, a wall plate 12 made of precast concrete is attached between the columns 9b, 9b located on the outer circumference. In the present embodiment, the wall plates 12 are attached in upper and lower four stages. As shown in FIG. 26, the construction process for that purpose is as follows. First, in the second section 7b located on the outer periphery, the wall plate 12 is tilted in the horizontal plane with respect to the left-right direction and the front-back direction, Suspend to the required position in 7b. In this state, as shown in FIG. 24, the wall plate 12 is positioned below the middle beam frame 3b to be disassembled and removed thereafter. Then Figure 2
As shown in FIG. 6, by aligning the length direction of the wall plate 12 with the left-right direction and the front-rear direction, the wall plate 12 is cut between the columns facing each other in the left-right direction and the front-back direction with the cross beam 2 interposed therebetween. The wall plate 1 is moved laterally toward the pillar 9b1 in the state of being close to the beam 2.
Both end portions 41, 41 of 2 are supported by the wall plate receiving portions 42, 42 provided on the adjacent columns 9b, 9b.
【0044】該壁板12の端面66には、本実施の形態
においては図27、図29に示すように、コ字状の突き
出し鉄筋67が上下方向に所要間隔を置いて突設されて
いるため、前記支持は、壁板12,12の向き合う端面
66,66で突設された前記突き出し鉄筋67と、前記
外周の支柱9bの外面側で突設された突き出し鉄筋68
を噛み合う状態とする(図28)。この場合、突き出し
鉄筋68の突出量をより大きくして、該突き出し鉄筋6
8,68相互が噛み合う状態とされることもある。或い
は、壁板12の端面66で突設された前記突き出し鉄筋
67と、コーナ支柱9bの外面側で突設された突き出し
鉄筋68を噛み合う状態とする(図30)。この場合、
該突き出し鉄筋68の突出量を、図示したものより大き
くすることもある。その後、矩形環状や三角形環状をな
す環状鉄筋69を所要の重ね合わせ状態で取り付けると
共に、縦主筋70を所要に配筋する。然る後、壁板相互
の接合部分で型枠を組みコンクリートを打設し、壁板接
合部71を形成する。In this embodiment, as shown in FIGS. 27 and 29, U-shaped protruding reinforcing bars 67 are provided on the end surface 66 of the wall plate 12 in the vertical direction at a predetermined interval. Therefore, the support is provided by the projecting rebar 67 projecting at the end faces 66, 66 of the wall plates 12, 12 facing each other, and the projecting rebar 68 projecting at the outer surface side of the column 9b on the outer periphery.
Are engaged with each other (FIG. 28). In this case, the protruding amount of the protruding reinforcing bar 68 is increased to make the protruding reinforcing bar 6
There may be a case where the 8, 68 mesh with each other. Alternatively, the protruding reinforcing bars 67 protruding on the end surface 66 of the wall plate 12 and the protruding reinforcing bars 68 protruding on the outer surface side of the corner strut 9b are engaged with each other (FIG. 30). in this case,
The protruding amount of the protruding reinforcing bar 68 may be made larger than that shown in the drawing. After that, the annular reinforcing bars 69 having a rectangular annular shape or a triangular annular shape are attached in a required overlapping state, and the longitudinal main reinforcing bars 70 are arranged as required. After that, the formwork is assembled at the joints between the wall plates and concrete is poured to form the wall plate joints 71.
【0045】その後図24に示すように、該壁板12
(12a)の上端72の稍下方位置(例えば30〜40
cm程度下方位置)にまで、該壁板12と土留壁20と
の間に埋め戻しを行う。この埋め戻し土68により、土
留壁20を支持させる。同様にして図25に示すよう
に、2段目の壁板12を支柱間に付設し、且つ壁板相互
の接合部分で型枠を組んでコンクリートを打設し、該壁
板12と土留壁20との間に埋め戻しを行い、この埋め
戻し土68により、土留壁20を支持させる。これを繰
り返して貯水槽1の壁面73を形成する。なお上下の壁
板間75(図25)にはグラウトが充填され、上下の壁
板12,12相互が、図25に示す連結棒74を介し
て、止水を確保して連結される。又壁板12は、柱間の
外面側に付設されることの他、支柱の内面側や支柱の幅
の中間で付設されることもある。Thereafter, as shown in FIG. 24, the wall plate 12
A slightly lower position (for example, 30 to 40) of the upper end 72 of (12a).
Backfilling is performed between the wall plate 12 and the retaining wall 20 up to about a cm lower position. The earth retaining wall 20 is supported by the backfill soil 68. Similarly, as shown in FIG. 25, the second-stage wall plate 12 is attached between the columns, and the frame is assembled at the joints between the wall plates to pour the concrete into the wall plate 12 and the retaining wall. The soil retaining wall 20 is supported by the backfilling soil 68 by performing backfilling with the soil 20. By repeating this, the wall surface 73 of the water storage tank 1 is formed. Note that the space 75 (FIG. 25) between the upper and lower wall plates is filled with grout, and the upper and lower wall plates 12, 12 are connected to each other via the connecting rod 74 shown in FIG. The wall plate 12 may be attached to the outer surface side between the pillars, or may be attached to the inner surface side of the pillar or in the middle of the width of the pillar.
【0046】所要段数目の壁板、例えば1段目の壁板1
2aを付設して後、前記中段の切梁枠組3bを構成する
左右方向及び前後方向の切梁2a,2bを解体、撤去す
る。前記のように、埋め戻し土68により土留壁20が
支持されるため、該切梁を解体、撤去しても、土留壁2
0の安定状態を保持できる。又、最上段の壁板12bを
支柱間に付設し且つ所要の埋め戻しを行って後、最上段
の切梁枠組3aを構成する左右方向及び前後方向の切梁
2a,2bを解体、撤去する。然る後、前記支持杭21
を前記底盤部30の上面で溶断して撤去する。これによ
って、土留壁支保工5は全て解体、撤去される。The required number of steps of the wall plate, for example, the first step wall plate 1
After attaching 2a, the cross beams 2a, 2b in the left-right direction and the front-rear direction which form the middle-level cross beam framework 3b are disassembled and removed. As described above, since the earth retaining wall 20 is supported by the backfill soil 68, even if the cutting beam is dismantled and removed, the earth retaining wall 2
A stable state of 0 can be maintained. Also, after installing the uppermost wall plate 12b between the columns and performing necessary backfilling, the left and right cutting beams 2a and 2b forming the uppermost cutting beam framework 3a are disassembled and removed. . After that, the support pile 21
Is melted off on the upper surface of the bottom plate portion 30 and removed. As a result, all the retaining wall support works 5 are dismantled and removed.
【0047】然る後図31、図1に示すように、隣り合
う連結梁11,11の側面に対向して設けられた前記支
持突条52,52で蓋版50の両側部分51,51を水
平に支持させ、スラブ76を形成する。これにより所要
の貯水槽1が構築される。その後、該スラブ76上に所
要に配筋をしてコンクリートを打設し、貯水槽の天井部
77を形成する。これにより、例えば、内空高さが9〜
10m程度の貯水槽1が構築されることとなる。その
後、図31に一点鎖線で示すように、貯水槽の上部全体
に埋め戻しを行い、該埋め戻しの完了後、前記鋼矢板1
6を引き抜く。なお該鋼矢板16は、埋め殺しされるこ
ともある。Then, as shown in FIG. 31 and FIG. 1, both side portions 51, 51 of the lid plate 50 are separated by the supporting protrusions 52, 52 provided so as to face the side surfaces of the adjacent connecting beams 11, 11. The slab 76 is formed by supporting it horizontally. As a result, the required water storage tank 1 is constructed. After that, concrete is placed on the slab 76 and the concrete is placed to form the ceiling 77 of the water tank. Thereby, for example, the inner sky height is 9 to
A water storage tank 1 of about 10 m will be constructed. After that, as shown by the alternate long and short dash line in FIG. 31, backfilling is performed on the entire upper part of the water storage tank, and after completion of the backfilling, the steel sheet pile 1
Pull out 6. The steel sheet pile 16 may be buried.
【0048】〔その他の実施の形態〕本発明は、前記実
施の形態で示したものに限定されるものでは決してな
く、「特許請求の範囲」の記載内で種々の設計変更が可
能であることは言うまでもない。その一例を挙げれば次
のようである。
(1) 図32〜33は、本発明に係る構築工法の他の態様
を示すものであり、図10に示す前記四隅の支柱9b
1,9b2,9b3,9b4を省略し、代わりに、平面
視で三角形状を呈し、或いはL字状等を呈する壁板12
Aを該支柱の代わりに配設する場合に関するものであ
る。図33では、壁板12Aが三角形状を呈する。この
場合は、該三角形状壁板12Aの両端面80,80と、
これに隣り合う支柱9aとの間に平板状壁板12Bを配
設し、該平板状壁板12Bの端面79と該三角形状壁板
12Aの端面80との間に、現場打ち施工により接合部
78を形成するものである。その他の構成は、前記実施
の形態で示した構築工法と同様であるため、その説明を
省略する。[Other Embodiments] The present invention is by no means limited to those shown in the above embodiments, and various design modifications are possible within the scope of the claims. Needless to say. An example is as follows. (1) FIGS. 32 to 33 show another aspect of the construction method according to the present invention, and the pillars 9b at the four corners shown in FIG.
1, 9b2, 9b3, 9b4 are omitted, and instead, a wall plate 12 having a triangular shape in a plan view, or an L shape, etc.
This is related to the case where A is arranged instead of the column. In FIG. 33, the wall plate 12A has a triangular shape. In this case, the both end surfaces 80, 80 of the triangular wall plate 12A,
A flat plate-shaped wall plate 12B is arranged between the adjacent pillars 9a, and a joint portion is formed between the end face 79 of the flat plate-shaped wall plate 12B and the end face 80 of the triangular shaped wall plate 12A by in-situ casting. To form 78. The other construction is the same as the construction method shown in the above-mentioned embodiment, and therefore its explanation is omitted.
【0049】(2) 又本発明に係る構築工法においては、
図34や図35に示すように、外周に位置する第1の区
画7a、或いは第2の区画7bに、壁板を支持する外周
の支柱9bを、壁板を支持しない支柱9aと共に存在さ
せることもある。このように構成した場合、図1に示す
前記四隅の支柱9b1,9b2,9b3,9b4が立設
されるときは、同図に示すように、コーナ部をL字状壁
板12cで覆う場合、該L字状壁板12cを小型に形成
でき、その輸送が容易となる利点がある。図36は、各
区画7に一本づつの支柱9を立設させた場合を示すもの
であるが、コーナ部をL字状壁板12cで覆うとき、該
L字状壁板12cが大型となる不具合がある。(2) In the construction method according to the present invention,
As shown in FIG. 34 and FIG. 35, a column 9b for supporting the wall plate and a column 9a not supporting the wall plate should be present in the first section 7a or the second section 7b located on the outer periphery. There is also. With such a configuration, when the pillars 9b1, 9b2, 9b3, 9b4 at the four corners shown in FIG. 1 are erected, as shown in the figure, when the corner portion is covered with the L-shaped wall plate 12c, There is an advantage that the L-shaped wall plate 12c can be formed in a small size and can be easily transported. FIG. 36 shows a case where one column 9 is erected in each section 7, and when the corner portion is covered with the L-shaped wall plate 12c, the L-shaped wall plate 12c is considered to be large. There is a problem that becomes.
【0050】(3) 図37は、支柱9が立設される底部8
の他の態様を示すものである。(3) FIG. 37 shows the bottom portion 8 on which the column 9 is erected.
It shows another embodiment of the.
【0051】(4) 支柱の横断面形状は、前記した円形状
には特定されない。又、連結梁11の端部分を載せるた
めの支持突部47は、該端部分を安定的に載せることが
できるものであれば、前記実施の形態で示したものには
特定されない。図38〜42は、これらの一例を示すも
のである。(4) The cross-sectional shape of the pillar is not limited to the circular shape described above. Further, the support protrusion 47 for mounting the end portion of the connecting beam 11 is not limited to the one shown in the above-mentioned embodiment as long as the end portion can be stably mounted. 38 to 42 show an example of these.
【0052】(5) 壁板12の端部分41を支持するため
の壁板受部42は、該端部分を安定的に支持させること
ができるものであれば、前記実施の形態で示したものに
は特定されず、例えば図43に示すように上下連続した
突条として構成することができ、又図44に示すよう
に、上下方向で途切れ状態に構成することもできる。そ
して図45〜46は、これらの場合等において、壁板受
部42が壁板12の端部分41を支持した状態の一例を
示すものである。(5) The wall plate receiving portion 42 for supporting the end portion 41 of the wall plate 12 is the one shown in the above embodiment as long as it can stably support the end portion. However, it may be configured as a continuous ridge as shown in FIG. 43, or may be discontinuous in the vertical direction as shown in FIG. 45 to 46 show an example of a state in which the wall plate receiving portion 42 supports the end portion 41 of the wall plate 12 in these cases and the like.
【0053】(6) 図47は、土留壁20の他の態様を示
す部分平面図であり、地盤を上下方向で削孔し、且つそ
の内部で削孔土とセメントミルクとの攪拌混合物を硬化
させてなるソイルセメント状の柱状物81を、その側部
相互がオーバーラップする配置で周方向に連続させて形
成し、必要に応じて、該柱状物81に例えばH形鋼から
なる補強材82を上下方向で埋設している。(6) FIG. 47 is a partial plan view showing another embodiment of the soil retaining wall 20, in which the ground is drilled in the vertical direction and the agitated mixture of the drilled soil and cement milk is hardened therein. Soil-cement-shaped pillars 81 thus formed are continuously formed in the circumferential direction in such a manner that their side portions overlap each other, and if necessary, a reinforcing material 82 made of, for example, H-shaped steel, is formed on the pillars 81. Is buried vertically.
【0054】(7) 前記実施の形態においては、土留壁2
0を矩形状に形成しているが、該土留壁20は、構築す
べき貯水槽の敷地形状に応じて例えば図48に示すもの
等、各種に形成される。この場合、外周に配置される第
2の区画7bには、矩形状のものに加え、台形状や三角
形状等を呈したものも含まれる。(7) In the above embodiment, the retaining wall 2
Although 0 is formed in a rectangular shape, the earth retaining wall 20 is formed in various shapes according to the site shape of the water storage tank to be constructed, such as that shown in FIG. In this case, the second section 7b arranged on the outer circumference includes not only a rectangular shape but also a trapezoidal shape or a triangular shape.
【0055】(8) 前記最下段の切梁枠組3cは、底部8
で支柱9を立設した後、壁板12が付設されるまでの間
で解体、撤去されることもある。(8) The lowermost beam structure 3c has a bottom portion 8
In some cases, after the pillar 9 is erected upright, the pillar 9 may be disassembled and removed until the wall plate 12 is attached.
【0056】(9) 本発明に係る構築工法は、前記外周の
支柱間を覆うように下から上に向けて順次前記壁板を付
設するに際して、各段の壁板付設毎に、或いは複数段の
壁板付設毎に、該壁板と土留壁との間に埋め戻しを行
い、且つ該埋め戻しを行って後、その直上にある切梁を
撤去できるように、壁板の上下高さを考慮して切梁の上
下配置を設定するように構成することもできる。(9) In the construction method according to the present invention, when the wall plates are sequentially attached from the bottom to the top so as to cover the columns of the outer periphery, the wall plates are attached at each stage or at a plurality of stages. Each time the wall board is attached, backfilling is performed between the wallboard and the retaining wall, and after performing the backfilling, the vertical height of the wallboard is adjusted so that the cutting beam directly above it can be removed. It is also possible to configure the vertical arrangement of the beams in consideration.
【0057】[0057]
【発明の効果】本発明は以下の如き優れた効果を奏す
る。
(1) 本発明に係る構築工法は、左右方向の切梁と前後方
向の切梁とが平面視で格子状に交差する如く組み立てら
れた切梁枠組を上下複数段に具える土留壁支保工を設け
た掘削空間において、プレキャストコンクリート製の貯
水槽を構築する構築工法であり、前記土留壁支保工にお
いて、上下複数段に配設された左右方向の切梁及び、上
下複数段に配設された前後方向の切梁は、夫々平面視で
略重なる如くなし、前記掘削空間の底部で支柱を所要配
置に立設し、該支柱の上端を、最上段の切梁の稍下側に
位置させ、隣り合う支柱の上端相互を連結梁で連結し、
外周に存する支柱には、該外周の支柱間を覆うように下
から上に向けて順次付設される壁板を支持させるものと
し、又、前記外周の支柱の内側に存する支柱を、前後左
右の切梁が形成する矩形状の区画内に1本づつ存在せし
め、該支柱を、矩形状の区画の同一コーナ部において立
設する構成を採用している。The present invention has the following excellent effects. (1) A construction method according to the present invention is a retaining wall support work that includes a cross beam frame structure that is assembled so that the cross beams in the left-right direction and the cross beams in the front-rear direction intersect in a grid pattern in plan view in a plurality of upper and lower stages. Is a construction method for constructing a water tank made of precast concrete in the excavation space provided with, and in the earth retaining wall support work, horizontal beam beams arranged in upper and lower stages and upper and lower stages are arranged. The cross beams in the front-rear direction are arranged so as to substantially overlap each other in a plan view, and the columns are erected in a required arrangement at the bottom of the excavation space, and the upper ends of the columns are positioned on the lower side of the uppermost beam. , Connect the upper ends of adjacent columns with connecting beams,
The pillars existing on the outer circumference shall support the wall plates sequentially attached from the bottom to the top so as to cover the spaces between the pillars on the outer circumference. A structure is employed in which each of the columns is present in a rectangular section formed by a truss and the columns are erected at the same corner of the rectangular section.
【0058】従って本発明によるときは、切梁が縦横に
且つ複数段に配置されてはいても、隣り合う支柱の上端
相互を連結梁で連結するに際し、吊下ロープの両端部を
該連結梁の両端側に固定して該吊下ロープをクレーンで
吊り上げる場合に、吊下ロープの傾斜辺が切梁に接触し
ないように、或いは、該吊下ロープの傾斜辺が前記切梁
に接触しても該傾斜辺が撓み変形しない状態で、該連結
梁の横移動量を小さくしながら、該連結梁の両端部分を
隣り合う支柱の上端に載せることができる。これによ
り、吊下ロープの付け替えを行なうことなく該連結梁を
横移動させて、隣り合う支柱の上端相互を連結梁で容易
に連結できる利点がある。このようなことから本発明に
よるときは、内空高さが5〜10mを越える大型のプレ
キャストコンクリート製貯水槽であっても、土留壁支保
工が障害となることなく構築できる利点がある。Therefore, according to the present invention, even when the cross beams are arranged vertically and horizontally in a plurality of stages, when the upper ends of the adjacent columns are connected by the connecting beams, both ends of the suspension rope are connected to each other. When suspending the suspension rope by fixing it to both ends of the suspension rope with a crane, do not allow the inclined side of the suspension rope to come into contact with the crossbeam, or if the inclined side of the suspension rope comes into contact with the crossbeam. Even in the state where the inclined side is not flexibly deformed, both end portions of the connecting beam can be placed on the upper ends of the adjacent columns while reducing the lateral movement amount of the connecting beam. Accordingly, there is an advantage that the connecting beams can be laterally moved without replacing the hanging ropes and the upper ends of the adjacent columns can be easily connected by the connecting beams. Therefore, according to the present invention, there is an advantage that even a large precast concrete water storage tank having an inner air height of more than 5 to 10 m can be constructed without hindering the retaining wall support.
【0059】内空高さの大きい大型のプレキャストコン
クリート製貯水槽は、前記のように、従来は現場打ち施
工によって構築せざるを得なかったのであるが、本発明
によるときは、これを施工能率良く構築できることとな
るのである。又現場打ち施工の貯水槽にあっては、前記
のように中間の支え梁部を必要としたが、本発明による
ときは、隣り合う支柱の上端相互を連結梁で連結できる
ために、このような中間の支え梁部を必要としない。そ
して、かかる支え梁部を形成するための支保工も不要と
なるため、施工コストの低減を期し得ると共に、中間の
支え梁部が必要でないことから、その分だけ貯水槽の容
積増大が図られ、容量効率の高い貯水槽を構築し得るこ
ととなる。As described above, the large precast concrete water tank having a large inner air height had to be constructed by the cast-in-place construction in the past, but according to the present invention, the construction efficiency is increased. It will be well built. In addition, in the case of the water tank that is constructed in-situ, the intermediate supporting beam portion is required as described above. However, according to the present invention, since the upper ends of the adjacent columns can be connected by the connecting beam, No intermediate support beam is needed. Further, since the supporting work for forming the supporting beam portion is not necessary, it is possible to reduce the construction cost, and the intermediate supporting beam portion is not necessary. Therefore, the volume of the water tank can be increased accordingly. Therefore, it is possible to construct a water storage tank with high capacity efficiency.
【0060】(2) 前記支柱を、その上端で支持突部が突
設されたものとして構成し、前記連結梁の端部分を該支
持突部に載せるときは、支柱本体38(図10)を切梁
2a,2bから離しながらも、連結梁の端部分を支持す
る支柱部分83(図10)を切梁2a,2bにより接近
させ得るため、支柱の上端相互を連結梁で連結する際に
おける該連結梁の横移動量を極力小さくできる利点があ
る。(2) When the pillar is constructed such that a supporting projection is provided at the upper end thereof, and the end portion of the connecting beam is placed on the supporting projection, the pillar body 38 (FIG. 10) is used. The pillar portion 83 (FIG. 10) supporting the end portions of the connecting beams can be moved closer to the cutting beams 2a and 2b while being separated from the cutting beams 2a and 2b. There is an advantage that the lateral movement amount of the connecting beam can be minimized.
【0061】(3) 支柱を、その外面側に壁板受部が突設
されたものとして構成することにより、外周の支柱間を
壁板で覆うに際し、壁板の端部分を支持する支柱部分8
4(図10)を切梁24により接近させ得るため、外周
に存する支柱間を壁板で覆う際、該壁板の横移動量を極
力小さくできる利点がある。(3) By constructing the support pillars so that the wall plate receiving portion projects on the outer surface side thereof, the support pillar portion that supports the end portion of the wall board when the outer peripheral support pillars are covered with the wall board. 8
4 (FIG. 10) can be made closer to each other by the trusses 24, so that there is an advantage that the lateral movement amount of the wall plates can be made as small as possible when covering the pillars existing on the outer periphery with the wall plates.
【0062】(4) 前後左右の切梁が形成する矩形状の区
画内のうち、外周に存する区画に、壁板を支持しない支
柱と共に、壁板を支持する支柱をも存在させるときは、
特に、貯水槽のコーナ部分に支柱を立設させる場合にお
いて該コーナ部分をL字状の壁板で覆う際、例えば図3
4〜35と図36を比較すれば明らかなように、該L字
状壁板をより小さく構成でき、その輸送を容易とし又輸
送効率の向上を期し得ることとなる。(4) Among the rectangular partitions formed by the front and rear and left and right trusses, when the columns that support the wall plate as well as the columns that do not support the wall plate are present in the partition existing on the outer periphery,
In particular, when a pillar is erected on the corner portion of the water tank, when covering the corner portion with an L-shaped wall plate, for example, as shown in FIG.
As is clear from comparison between FIGS. 4 to 35 and FIG. 36, the L-shaped wall plate can be made smaller, which facilitates the transportation and improves the transportation efficiency.
【0063】(5) 外周の支柱間を覆うように下から上に
向けて順次壁板を付設する際、各段の壁板付設毎に或い
は複数段の壁板付設毎に、該壁板と土留壁との間に埋め
戻しを行い、且つ該埋め戻しを行なって後、その直上に
ある切梁を撤去できるように、切梁の上下配置を考慮し
て設定された上下高さを有する壁板を付設し、或いは、
壁板の上下高さを考慮して切梁の配置を設定するとき
は、埋め戻し土によって土留壁を安定的に支持しなが
ら、切梁の解体、撤去を下から順次行なうことができ
る。これにより、内空高さの大きい貯水槽であっても、
切梁を撤去した後に形成された開放空間で上方向への壁
板付設を難なく行なうことができる等によって、該貯水
槽を効率よく構築できる利点がある。そして、このよう
に構築する場合は、埋め戻し土からの圧力を受ける壁板
を支持する支柱の安定化を図るために、隣り合う支柱間
の全てを連結梁で連結することが必要となるのである
が、本発明によるときは、前記したように、左右方向及
び前後方向での連結梁の連結作業を、吊下した連結梁の
横移動の容易性によって難無く行うことができる。(5) When the wall plates are sequentially attached from the bottom to the top so as to cover the space between the columns on the outer periphery, when the wall plates are attached at each stage or the wall plates are attached at a plurality of stages, A wall having a vertical height set in consideration of the vertical arrangement of the cutting beams so that the back beams can be backfilled with the retaining wall and the cutting beams immediately above can be removed after the backfilling. Attach a board, or
When setting the layout of the cutting beams in consideration of the vertical height of the wallboard, the cutting beams can be disassembled and removed sequentially from the bottom while stably supporting the retaining wall by the backfill soil. As a result, even if the water tank has a large inner height,
There is an advantage that the water storage tank can be efficiently constructed by, for example, attaching the wall plate upward in the open space formed after removing the cutting beam without difficulty. Then, in the case of constructing in this way, it is necessary to connect all the adjacent columns with connecting beams in order to stabilize the columns that support the wall plate that receives pressure from the backfill soil. However, according to the present invention, as described above, the connecting work of the connecting beams in the left-right direction and the front-rear direction can be easily performed due to the ease of lateral movement of the hanging connecting beams.
【図1】本発明によって構築された貯水槽を示す一部欠
切斜視図である。FIG. 1 is a partially cutaway perspective view showing a water tank constructed according to the present invention.
【図2】土留壁支保工が設けられた掘削空間に支柱を立
設し、支柱相互を連結梁で連結した状態を示す部分斜視
図である。FIG. 2 is a partial perspective view showing a state in which columns are erected in an excavation space provided with a retaining wall support and the columns are connected to each other by connecting beams.
【図3】鋼矢板の打ち込みによって形成された土留壁
を、打ち込まれた支持杭と共に示す平面図である。FIG. 3 is a plan view showing a retaining wall formed by driving steel sheet piles together with driven support piles.
【図4】鋼矢板の打ち込み状態を示す断面図である。FIG. 4 is a cross-sectional view showing a driven state of a steel sheet pile.
【図5】地盤を掘り下げて最上段の切梁枠組を形成した
状態を示す部分斜視図である。FIG. 5 is a partial perspective view showing a state where the ground is dug down to form the uppermost beam girder framework.
【図6】土留壁支保工を示す断面図である。FIG. 6 is a sectional view showing a retaining wall support work.
【図7】土留壁支保工を示す平面図である。FIG. 7 is a plan view showing a retaining wall support work.
【図8】土留壁支保工を設けた掘削空間において支柱を
立設し、支柱相互を連結梁で連結した状態を示す断面図
である。FIG. 8 is a cross-sectional view showing a state in which columns are erected in an excavation space provided with a retaining wall support and columns are connected to each other by connecting beams.
【図9】土留壁支保工を設けた掘削空間において支柱を
立設した状態を示す斜視図である。FIG. 9 is a perspective view showing a state in which a column is erected in an excavation space provided with a retaining wall support.
【図10】その平面図である。FIG. 10 is a plan view thereof.
【図11】土留壁支保工を設けた掘削空間における支柱
の立設要領を説明する説明図である。FIG. 11 is an explanatory view for explaining a manner of standing upright columns in an excavation space provided with a retaining wall support.
【図12】第1の区画と第2の区画に立設される支柱を
示す斜視図である。FIG. 12 is a perspective view showing pillars provided upright in a first section and a second section.
【図13】支柱を底盤部に立設した状態を示す部分側面
図である。FIG. 13 is a partial side view showing a state in which a column is erected on the bottom plate portion.
【図14】支柱の上側部分を、支柱相互を連結する連結
梁と共に示す斜視図である。FIG. 14 is a perspective view showing an upper portion of a support column together with a connecting beam connecting the support columns to each other.
【図15】連結梁の吊下状態を示す正面図である。FIG. 15 is a front view showing a suspended state of a connecting beam.
【図16】第1の区画内で連結梁を吊り下ろし、該連結
梁で支柱相互を連結する工程を説明する平面図である。FIG. 16 is a plan view illustrating a step of suspending a connecting beam in the first section and connecting the columns to each other by the connecting beam.
【図17】連結梁を、支柱相互を連結するように吊り下
ろした状態を示す正面図である。FIG. 17 is a front view showing a state where the connecting beam is hung so as to connect the columns to each other.
【図18】第1の区画の辺の中央部分に近接させて支柱
を立設した状態を示す平面図である。FIG. 18 is a plan view showing a state in which a column is erected in the vicinity of the central portion of the side of the first section.
【図19】その場合の問題点を説明する正面図である。FIG. 19 is a front view illustrating a problem in that case.
【図20】その場合の他の問題点を説明する正面図であ
る。FIG. 20 is a front view illustrating another problem in that case.
【図21】隣り合う第2の区画内に存する支柱の上端相
互を連結梁で連結する工程を説明する平面図である。FIG. 21 is a plan view illustrating a step of connecting the upper ends of the columns existing in the adjacent second sections with each other by a connecting beam.
【図22】支柱の上端に載置された連結梁の端部分と支
柱の上端とを一体化するための配筋状態を示す断面図で
ある。FIG. 22 is a cross-sectional view showing a bar arrangement state for integrating the end portion of the connecting beam placed on the upper end of the column and the upper end of the column.
【図23】その一体化された状態を示す平面図である。FIG. 23 is a plan view showing the integrated state.
【図24】外周の支柱間に最下段の壁板を付設した状態
を示す断面図である。FIG. 24 is a cross-sectional view showing a state in which a lowermost wall plate is attached between columns on the outer circumference.
【図25】外周の支柱間の上下全体に壁板を付設した状
態を示す断面図である。FIG. 25 is a cross-sectional view showing a state in which wall plates are attached to the entire upper and lower portions between columns on the outer periphery.
【図26】外周の支柱間に壁板を付設する工程を説明す
る平面図である。FIG. 26 is a plan view illustrating a step of attaching a wall plate between support posts on the outer circumference.
【図27】壁板相互を直線状に接合する工程を説明する
斜視図である。FIG. 27 is a perspective view illustrating a step of linearly joining wall plates to each other.
【図28】壁板相互を直線状に接合した状態を示す一部
欠切斜視図である。FIG. 28 is a partially cutaway perspective view showing a state where the wall plates are linearly joined together.
【図29】壁板相互を直角に接合する工程を説明する斜
視図である。FIG. 29 is a perspective view illustrating a step of joining wall plates to each other at a right angle.
【図30】壁板相互を直角に接合した状態を示す一部欠
切斜視図である。FIG. 30 is a partially cutaway perspective view showing a state where the wall plates are joined at a right angle.
【図31】貯水槽の天井部分の構造を説明する断面図で
ある。FIG. 31 is a cross-sectional view illustrating the structure of the ceiling portion of the water storage tank.
【図32】土留壁支保工が設けられた掘削空間に支柱を
立設するに際し、四隅の支柱を省力した状態を示す平面
図である。FIG. 32 is a plan view showing a state in which the pillars at the four corners are labor-saving when the pillars are erected in the excavation space provided with the retaining wall support.
【図33】その四隅部分におけるL字状壁板の付設状態
を示す断面図である。FIG. 33 is a cross-sectional view showing an attached state of L-shaped wall plates at the four corners thereof.
【図34】外周に位置する第2の区画に、壁板を支持す
る支柱と壁板を支持しない支柱を共に立設した状態を、
コーナ部のL字状壁板の付設状態と共に示す断面図であ
る。FIG. 34 shows a state in which a column supporting a wall plate and a column not supporting a wall plate are both erected in a second section located on the outer periphery.
It is sectional drawing shown with the attachment state of the L-shaped wall board of a corner part.
【図35】外周に位置する第1の区画に、壁板を支持す
る支柱と壁板を支持しない支柱を共に立設した状態を、
コーナ部におけるL字状壁板の付設状態と共に示す断面
図である。FIG. 35 shows a state in which a column supporting a wall plate and a column not supporting a wall plate are both erected in a first section located on the outer periphery,
It is sectional drawing shown with the attachment state of the L-shaped wall board in a corner part.
【図36】全ての区画に1本の支柱を立設した場合の問
題点を説明する断面図である。FIG. 36 is a cross-sectional view illustrating a problem in the case where one column is erected in all the sections.
【図37】支柱が立設された底部の他の態様を示す部分
斜視図である。FIG. 37 is a partial perspective view showing another aspect of the bottom portion on which the support columns are erected.
【図38】支柱の他の態様を示す一部欠切部分斜視図で
ある。FIG. 38 is a partial cutaway perspective view showing another aspect of the support column.
【図39】支柱のその他の態様を示す部分斜視図であ
る。FIG. 39 is a partial perspective view showing another aspect of the column.
【図40】支柱のその他の態様を示す部分斜視図であ
る。FIG. 40 is a partial perspective view showing another aspect of the support column.
【図41】支柱のその他の態様を示す部分斜視図であ
る。FIG. 41 is a partial perspective view showing another aspect of the column.
【図42】支柱のその他の態様を示す部分斜視図であ
る。FIG. 42 is a partial perspective view showing another aspect of the column.
【図43】支柱のその他の態様を示す部分斜視図であ
る。FIG. 43 is a partial perspective view showing another aspect of the support column.
【図44】支柱のその他の態様を示す部分斜視図であ
る。FIG. 44 is a partial perspective view showing another aspect of the column.
【図45】壁板受部で壁板の端部分を支持した他の態様
を示す平面図である。FIG. 45 is a plan view showing another mode in which the end portion of the wall plate is supported by the wall plate receiving portion.
【図46】壁板受部で壁板の端部分を支持したその他の
態様を示す平面図である。FIG. 46 is a plan view showing another aspect in which the end portion of the wall plate is supported by the wall plate receiving portion.
【図47】土留壁の他の態様を示す部分平面図である。FIG. 47 is a partial plan view showing another aspect of the retaining wall.
【図48】土留壁の他の形態を、土留壁支保工と共に示
す平面図である。FIG. 48 is a plan view showing another form of the retaining wall together with the retaining wall support.
【図49】従来のプレキャスト工法の一例を示す部分断
面図である。FIG. 49 is a partial cross-sectional view showing an example of a conventional precast method.
【図50】従来のプレキャスト工法の他の態様を示す部
分断面図である。FIG. 50 is a partial cross-sectional view showing another aspect of the conventional precast method.
【図51】従来のプレキャスト工法のその他の態様を示
す部分斜視図である。FIG. 51 is a partial perspective view showing another aspect of the conventional precast method.
【図52】図51に係るプレキャスト工法の問題点を説
明する平面図である。52 is a plan view explaining a problem of the precast method according to FIG. 51. FIG.
【図53】そのプレキャスト工法における連結梁の吊下
状態を示す正面図である。FIG. 53 is a front view showing a suspended state of the connecting beam in the precast method.
【図54】そのプレキャスト工法において、連結梁を、
支柱相互を連結するように吊り下ろした状態を示す正面
図である。[Fig. 54] In the precast method, connecting beams are
FIG. 6 is a front view showing a state in which the columns are suspended so as to be connected to each other.
【図55】そのプレキャスト工法において、区画の辺の
中央部分に近接させて支柱を立設したときの問題点を説
明する正面図である。FIG. 55 is a front view for explaining a problem in the precast construction method when the pillar is erected in the vicinity of the central portion of the side of the section.
【図56】その場合の他の問題点を説明する正面図であ
る。FIG. 56 is a front view illustrating another problem in that case.
1 貯水槽 2 切梁 2a 左右方向の切梁 2b 前後方向の切梁 3 切梁枠組 5 土留壁支保工 6 掘削空間 7 区画 8 底部 9 支柱 10 支柱の上端 11 連結梁 12 壁板 13 地盤 20 土留壁 21 支持杭 22 腹起し 26 十字状交差部分 27 同一コーナ部 30 底盤部 33 支柱の中心 37 切梁交差点 39 区画の同一コーナ部 41 壁板の端部分 42 壁板受部 46 連結梁の端部分 47 支持突部 50 蓋版 52 支持突条 56 吊下ロープ 59 傾斜辺 1 water tank 2 beams 2a Horizontal beam 2b Front and rear beams 3 Girder frame 5 Soil retaining wall support 6 excavation space 7 divisions 8 bottom 9 props 10 Upper end of column 11 connecting beams 12 wall boards 13 ground 20 earth retaining wall 21 Support pile 22 upset 26 Cross-shaped intersection 27 Same corner 30 Bottom plate 33 Center of pillar 37 Cross beam intersection 39 corners with the same corner 41 Edge of wallboard 42 Wall plate receiving part 46 End part of connecting beam 47 Support protrusion 50 lid version 52 Support ridges 56 hanging rope 59 Inclined side
Claims (11)
面視で格子状に交差する如く組み立てられた切梁枠組を
上下複数段に具える土留壁支保工を設けた掘削空間にお
いて、プレキャストコンクリート製の貯水槽を構築する
構築工法であり、 前記土留壁支保工において、上下複数段に配設された左
右方向の切梁及び、上下複数段に配設された前後方向の
切梁は、夫々平面視で略重なる如くなし、 又前記掘削空間の底部で支柱を所要配置に立設し、該支
柱の上端を、最上段の切梁の下側に位置させ、隣り合う
支柱の上端相互を連結梁で連結し、外周に存する支柱に
は、該外周の支柱間を覆うように下から上に向けて順次
付設される壁板を支持させるものとし、又、前記外周の
支柱の内側に配置する支柱は、前後左右の切梁が形成す
る矩形状の区画内に1本づつ存在せしめ、該支柱を、矩
形状の区画の同一コーナ部において立設することを特徴
とするプレキャストコンクリート製貯水槽の構築工法。1. In an excavation space provided with a retaining wall support structure having a plurality of upper and lower stages of a crossbeam frame assembly assembled so that the crossbeams in the left-right direction and the crossbeams in the front-rear direction intersect in a grid pattern in a plan view. , A construction method for constructing a water tank made of precast concrete, in the earth retaining wall support work, horizontal crossbeams arranged in a plurality of upper and lower steps and front and rear cut beams in a plurality of upper and lower steps Are arranged so as to substantially overlap each other in a plan view, and the pillars are erected in a required arrangement at the bottom of the excavation space, and the upper ends of the pillars are positioned below the uppermost beams, and the upper ends of the adjacent pillars are arranged. The pillars that are connected to each other by connecting beams, and the pillars existing on the outer circumference are supported by the wall plates that are sequentially attached from the bottom to the top so as to cover the pillars on the outer circumference. The pillars to be placed in the One are allowed to be present by one, a strut, construction method of precast concrete reservoir, characterized in that the upright in the same corners of the rectangular compartments within.
の内、外周に存する区画の所要のものに、壁板を支持す
る支柱も存在させることを特徴とする請求項1記載のプ
レキャストコンクリート製貯水槽の構築工法。2. The precast according to claim 1, characterized in that among the rectangular sections formed by the front, rear, left and right beams, a column for supporting the wall plate is provided in a required section of the outer section. Construction method of concrete water tank.
られた左右方向の切梁と前後方向の切梁とを具える土留
壁支保工を設けた掘削空間において、プレキャストコン
クリート製の貯水槽を構築する構築工法であり、 前記土留壁支保工において、上下複数段に配設された左
右方向の切梁及び、上下複数段に配設された前後方向の
切梁は、夫々平面視で略重なる如くなし、 前記掘削空間の底部で支柱を所要配置に立設し、該支柱
の上端を、最上段の切梁の下側に位置させ、隣り合う支
柱の上端相互を連結梁で連結し、外周に存する支柱に
は、該外周の支柱間を覆うように下から上に向けて順次
付設される壁板を支持させるものとし、又、前記外周の
支柱の内側に配置する支柱は、前後左右の切梁が形成す
る矩形状の区画内に1本づつ存在せしめ、該支柱を、矩
形状の区画の同一コーナ部において立設すると共に、 前後左右の切梁が形成する矩形状の区画の外側に存する
区画に配設する支柱は、前記コーナ部に立設されている
支柱と前後対向する状態で或いは左右対向する状態で切
梁に近接して立設し、左右方向で見て隣り合う支柱の中
心間の距離を、十字状に交わる切梁交差点の内の隣り合
う左右の交差点間の距離に略等しく設定すると共に、前
後方向で見て隣り合う支柱の中心間の距離を、十字状に
交わる切梁交差点の内の隣り合う前後の交差点間の距離
に略等しく設定することを特徴とするプレキャストコン
クリート製貯水槽の構築工法。3. A water tank made of precast concrete is provided in an excavation space provided with earth retaining wall supports having left and right cutting beams and front and rear cutting beams assembled so as to intersect each other in a grid pattern in a plan view. It is a construction method to build, in the earth retaining wall support work, the horizontal beams which are arranged in a plurality of upper and lower steps and the longitudinal beams which are arranged in a plurality of upper and lower steps are substantially overlapped in plan view. As a result, the pillars are erected in a required arrangement at the bottom of the excavation space, the upper ends of the pillars are located below the uppermost cross beam, and the upper ends of the adjacent pillars are connected to each other by a connecting beam. The pillars existing in the above shall support the wall plates sequentially attached from the bottom to the top so as to cover the spaces between the pillars on the outer periphery, and the pillars arranged inside the pillars on the outer periphery are Make sure there are one in each of the rectangular sections formed by the beams. The pillars are erected at the same corner portion of the rectangular section, and the pillars that are arranged outside the rectangular section formed by the front, rear, left, and right beam beams are erected at the corner sections. Standing close to the cross beam in a state of facing the front and rear or facing left and right, the distance between the centers of the adjacent posts as seen in the left and right direction is the The distance between the right and left intersecting intersections is set to be approximately equal, and the distance between the centers of the columns that are adjacent to each other when viewed in the front-rear direction is approximately equal to the distance between the adjacent front and rear intersections of the cross beam intersection that intersects each other. Construction method of precast concrete water tank characterized by setting.
クリート製貯水槽の構築工法において、隣り合う支柱の
上端相互を前記連結梁で連結するに際し、両端部分が前
記連結梁の両端側に固定された吊下ロープの中央部をフ
ックで吊り上げ、該連結梁を、前記左右方向や前後方向
に対し傾いた状態で前記矩形状の区画内で吊り下ろし、
前記最上端の切梁の下側において、該連結梁の向きを左
右方向又は前後方向にして後、該連結梁を左右方向又は
前後方向で横移動させ、該吊下ロープの傾斜辺が、隣り
合う支柱間に存する切梁に接触状態となる前に、或い
は、該吊下ロープの傾斜辺が該切梁に接触しても該傾斜
辺が撓み変形しない状態で、該連結梁の両端部分を隣り
合う支柱の上端に載せることを特徴とするプレキャスト
コンクリート製貯水槽の構築工法。4. The method for constructing a water tank made of precast concrete according to claim 1 or 3, wherein both end portions are fixed to both end sides of the connecting beam when the upper ends of adjacent columns are connected to each other by the connecting beam. The central portion of the hanging rope is hung with a hook, and the connecting beam is hung in the rectangular section in a state of being inclined with respect to the left-right direction and the front-back direction,
Below the uppermost cut beam, after the connecting beam is oriented in the left-right direction or the front-rear direction, the connecting beam is laterally moved in the left-right direction or the front-rear direction, and the slanted sides of the suspension rope are adjacent to each other. Before contacting the cutting beam existing between the supporting columns, or in a state where the slanted side of the suspension rope does not bend and deform even when the slanted side of the hanging rope contacts the cutting beam, both end portions of the connecting beam are A construction method for a water tank made of precast concrete that is placed on the upper ends of adjacent columns.
持する支持杭を、左右方向の切梁と前後方向の切梁との
交差部分の同一コーナ部で立設して形成し、前記支柱
を、前記支持杭と対角配置で立設することを特徴とする
請求項1又は3記載のプレキャストコンクリート製貯水
槽の構築工法。5. The retaining wall support work is formed by vertically arranging support piles for supporting the cutting beam from below at the same corner portion at the intersection of the cutting beam in the left-right direction and the cutting beam in the front-rear direction. The method for constructing a precast concrete water storage tank according to claim 1 or 3, characterized in that the pillars are erected in a diagonal arrangement with the support piles.
方向に張り出し形成されており、前記連結梁の端部分を
該支持突部に載せることを特徴とする請求項1〜5のい
ずれかに記載のプレキャストコンクリート製貯水槽の構
築工法。6. A support projection is laterally formed on the upper end of the column, and an end portion of the connecting beam is placed on the support projection. The construction method for a precast concrete water storage tank according to any one of the above.
に対向する切梁との間の間隔を10〜40cmに設定す
ることを特徴とする請求項6記載のプレキャストコンク
リート製貯水槽の構築工法。7. The water storage made of precast concrete according to claim 6, wherein a distance between a side end of the support protrusion and a girder facing the support protrusion is set to 10 to 40 cm in plan view. Construction method of tank.
クリート製貯水槽の構築工法において、外周に存する隣
り合う支柱間を覆うように壁板を付設するに際し、両端
部分が前記壁板の両端側に固定された吊下ロープの中央
部をフックで吊り上げ、該壁板を、前記左右方向や前後
方向に対し傾いた状態で、前記支柱が存する前記区画内
で吊り下ろし、該壁板の向きを左右方向又は前後方向に
して後、該壁板を左右方向又は前後方向で横移動させ、
前記吊下ロープの傾斜辺が、隣り合う支柱間に存する切
梁に接触状態となる前に、或いは、該吊下ロープの傾斜
辺が該切梁に接触しても該傾斜辺が撓み変形しない状態
で、該壁板の両端部分を隣り合う支柱の外面側で支持さ
せることを特徴とするプレキャストコンクリート製貯水
槽の構築工法。8. The method for constructing a water tank made of precast concrete according to claim 1 or 3, wherein both end portions are located at both end sides of the wall plate when the wall plate is attached so as to cover between adjacent columns existing on the outer circumference. The central part of the fixed hanging rope is hung up with a hook, and the wall board is hung in the section in which the pillars are present with the wall board inclined with respect to the left-right direction and the front-back direction, and the direction of the wall board is changed to the left-right direction. Direction or front-back direction, then move the wallboard laterally or in the front-back direction,
Before the slanted side of the suspension rope comes into contact with the crossbeam existing between adjacent columns, or even when the slanted side of the suspension rope contacts the crossbeam, the slanted side does not flex and deform. A construction method for a water tank made of precast concrete, characterized in that, in this state, both end portions of the wall plate are supported by the outer surfaces of adjacent columns.
側方向に張り出し形成されており、前記壁板の端部分を
該壁板受部で支持させることを特徴とする請求項1〜5
のいずれかに記載のプレキャストコンクリート製貯水槽
の構築工法。9. The pillar has a wall plate receiving portion formed on the outer surface side thereof so as to project in the lateral direction, and an end portion of the wall plate is supported by the wall plate receiving portion. 1-5
The method for constructing a water tank made of precast concrete according to any one of 1.
上に向けて順次前記壁板を付設するに際し、各段の壁板
付設毎に、或いは複数段の壁板付設毎に、該壁板と土留
壁との間に埋め戻しを行い、且つ該埋め戻しを行って
後、その直上にある切梁を撤去できるように、切梁の上
下配置を考慮して設定された上下高さを有する壁板を付
設することを特徴とする請求項1又は2記載のプレキャ
ストコンクリート製貯水槽の構築工法。10. When the wall plates are sequentially attached from the bottom to the top so as to cover between the columns of the outer periphery, the wall plates are attached at each stage of the wall plates or at each stage of the wall plates. Perform the backfilling between the plate and the retaining wall, and after performing the backfilling, the vertical height set in consideration of the vertical arrangement of the cutting beams so that the cutting beams immediately above can be removed. The precast concrete water storage tank construction method according to claim 1 or 2, wherein a wall plate having the same is attached.
上に向けて順次前記壁板を付設するに際し、各段の壁板
付設毎に、或いは複数段の壁板付設毎に、該壁板と土留
壁との間に埋め戻しを行い、且つ該埋め戻しを行って
後、その直上にある切梁を撤去できるように、壁板の上
下高さを考慮して切梁の上下配置を設定することを特徴
とする請求項1又は2記載のプレキャストコンクリート
製貯水槽の構築工法。11. When the wall plates are attached sequentially from the bottom to the top so as to cover between the columns of the outer periphery, the wall plates are attached for each stage of the wall plates or for each stage of the wall plates. Perform backfilling between the board and the retaining wall, and after performing the backfilling, consider the vertical height of the wallboard so that the cut beams above and below can be removed vertically. The method for constructing a water tank made of precast concrete according to claim 1 or 2, which is set.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001359564A JP3684347B2 (en) | 2001-11-26 | 2001-11-26 | Construction method of precast concrete water tank |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001359564A JP3684347B2 (en) | 2001-11-26 | 2001-11-26 | Construction method of precast concrete water tank |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003160944A true JP2003160944A (en) | 2003-06-06 |
JP3684347B2 JP3684347B2 (en) | 2005-08-17 |
Family
ID=19170546
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001359564A Expired - Lifetime JP3684347B2 (en) | 2001-11-26 | 2001-11-26 | Construction method of precast concrete water tank |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3684347B2 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012082645A (en) * | 2010-10-14 | 2012-04-26 | Tokyo Electric Power Co Inc:The | Lifting jig for prefabricated manhole and lifting method of prefabricated manhole using lifting jig for prefabricated manhole |
JP2012158937A (en) * | 2011-02-01 | 2012-08-23 | Pleasure Co Ltd | Earth retaining method and earth retaining structure |
CN109505609A (en) * | 2018-11-21 | 2019-03-22 | 中交第四公路工程局有限公司 | Shallow buried covered excavation Urban Underground pipe gallery non-stand construction method and pipe gallery |
CN110017141A (en) * | 2019-04-22 | 2019-07-16 | 中建三局基础设施建设投资有限公司 | A kind of ultra-deep shaft concrete ring grid beam quick template supporting system and its construction method |
KR20200124373A (en) * | 2019-04-23 | 2020-11-03 | 지에스건설 주식회사 | Precast wall structure composited column member and outer wall construction method therewith |
KR20220027375A (en) * | 2020-08-26 | 2022-03-08 | 지에스건설 주식회사 | Precast multi-layer hollow wall structure composited column member and outer wall construction method therewith |
KR20220027373A (en) * | 2020-08-26 | 2022-03-08 | 지에스건설 주식회사 | Precast multi hollow wall structure composited column member and outer wall construction method therewith |
CN115305919A (en) * | 2022-07-06 | 2022-11-08 | 中煤浙江基础建设有限公司 | Foundation pit excavation earthwork landslide prevention enclosure structure and construction method thereof |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63277341A (en) * | 1987-05-07 | 1988-11-15 | 株式会社竹中工務店 | Reverse execution of underground story |
JPH11229412A (en) * | 1998-02-10 | 1999-08-24 | Takaaki Endo | Construction method of large-sized box culvert |
JP2002088785A (en) * | 2000-09-12 | 2002-03-27 | Ando Corp | Continuous construction method for precast concrete column wall member |
-
2001
- 2001-11-26 JP JP2001359564A patent/JP3684347B2/en not_active Expired - Lifetime
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63277341A (en) * | 1987-05-07 | 1988-11-15 | 株式会社竹中工務店 | Reverse execution of underground story |
JPH11229412A (en) * | 1998-02-10 | 1999-08-24 | Takaaki Endo | Construction method of large-sized box culvert |
JP2002088785A (en) * | 2000-09-12 | 2002-03-27 | Ando Corp | Continuous construction method for precast concrete column wall member |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012082645A (en) * | 2010-10-14 | 2012-04-26 | Tokyo Electric Power Co Inc:The | Lifting jig for prefabricated manhole and lifting method of prefabricated manhole using lifting jig for prefabricated manhole |
JP2012158937A (en) * | 2011-02-01 | 2012-08-23 | Pleasure Co Ltd | Earth retaining method and earth retaining structure |
CN109505609A (en) * | 2018-11-21 | 2019-03-22 | 中交第四公路工程局有限公司 | Shallow buried covered excavation Urban Underground pipe gallery non-stand construction method and pipe gallery |
CN109505609B (en) * | 2018-11-21 | 2023-11-14 | 中交建筑集团有限公司 | Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack |
CN110017141A (en) * | 2019-04-22 | 2019-07-16 | 中建三局基础设施建设投资有限公司 | A kind of ultra-deep shaft concrete ring grid beam quick template supporting system and its construction method |
KR20200124373A (en) * | 2019-04-23 | 2020-11-03 | 지에스건설 주식회사 | Precast wall structure composited column member and outer wall construction method therewith |
KR102307968B1 (en) * | 2019-04-23 | 2021-10-05 | 지에스건설주식회사 | Precast wall structure composited column member and outer wall construction method therewith |
KR20220027375A (en) * | 2020-08-26 | 2022-03-08 | 지에스건설 주식회사 | Precast multi-layer hollow wall structure composited column member and outer wall construction method therewith |
KR20220027373A (en) * | 2020-08-26 | 2022-03-08 | 지에스건설 주식회사 | Precast multi hollow wall structure composited column member and outer wall construction method therewith |
KR102413091B1 (en) * | 2020-08-26 | 2022-06-28 | 지에스건설주식회사 | Precast multi hollow wall structure composited column member and outer wall construction method therewith |
KR102413093B1 (en) * | 2020-08-26 | 2022-06-28 | 지에스건설주식회사 | Precast multi-layer hollow wall structure composited column member and outer wall construction method therewith |
CN115305919A (en) * | 2022-07-06 | 2022-11-08 | 中煤浙江基础建设有限公司 | Foundation pit excavation earthwork landslide prevention enclosure structure and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP3684347B2 (en) | 2005-08-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2003160944A (en) | Construction method for precast concrete reservoir | |
KR200372315Y1 (en) | Moving-fabricated supporting bracket structure of downward construction system | |
KR200370135Y1 (en) | Forms for edge girder construction | |
JP2004263502A (en) | Work execution method for bridge | |
JPS6137692Y2 (en) | ||
KR100620366B1 (en) | Construction method of underground structures comprising composite reinforced concrete girders and beams using FRP | |
JPH11107293A (en) | Foundation structure of building, foundation construction method, and block for foundation | |
JPH04330119A (en) | Building foundation constructing method | |
KR20210017645A (en) | Underground structure using strut and method construturing the same | |
JPH09273205A (en) | Rain water storage tank | |
JPH07138972A (en) | Construction method for underground skeleton | |
JP2894217B2 (en) | Building structural frame | |
JP3803018B2 (en) | Formwork and manufacturing method thereof, underground beam construction method and column and beam construction method | |
JPH0598653A (en) | Steel pipe concrete pillar in underground inverter construction method | |
JPH0657769A (en) | Underground concrete structure and working method thereof | |
JP3002026B2 (en) | Structure of residential continuous foundation | |
JP3045838B2 (en) | Unit building and its construction method | |
JPS63277342A (en) | Reverse execution of underground story | |
JP2504658B2 (en) | Foundation structure in middle-high-rise buildings | |
JP2000096578A (en) | Form panel for earth retaining and foundation, and form | |
JP2781643B2 (en) | Basement building block unit | |
JP2001254366A (en) | Method for constructing foundation by using left-in- place-steel form | |
JPH01230815A (en) | Lathing formation for underground structure | |
JPH06193050A (en) | Construction method for steel framed reinforced concrete construction continuous underground wall | |
JPH07331784A (en) | Flat slab structure and execution method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050426 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050530 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3684347 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080603 Year of fee payment: 3 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313532 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080603 Year of fee payment: 3 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110603 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110603 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120603 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130603 Year of fee payment: 8 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |