JP2003064868A - Form assembling method and assembly metal fitting used for it - Google Patents

Form assembling method and assembly metal fitting used for it

Info

Publication number
JP2003064868A
JP2003064868A JP2001254148A JP2001254148A JP2003064868A JP 2003064868 A JP2003064868 A JP 2003064868A JP 2001254148 A JP2001254148 A JP 2001254148A JP 2001254148 A JP2001254148 A JP 2001254148A JP 2003064868 A JP2003064868 A JP 2003064868A
Authority
JP
Japan
Prior art keywords
plate
weir
plates
dam
attached
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001254148A
Other languages
Japanese (ja)
Inventor
Yukihiro Takemura
幸宏 竹村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HYAKUNEN JUTAKU SHIJO KK
Original Assignee
HYAKUNEN JUTAKU SHIJO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HYAKUNEN JUTAKU SHIJO KK filed Critical HYAKUNEN JUTAKU SHIJO KK
Priority to JP2001254148A priority Critical patent/JP2003064868A/en
Publication of JP2003064868A publication Critical patent/JP2003064868A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PROBLEM TO BE SOLVED: To dispense with timber mounting work to a sheathing board and to reduce a time required for form assembly and a cost of the sheathing board by simply inserting a vertical batter into a recess part of an assembling apparatus in comparison with a conventional method, in which square timbers are mounted in the four circumferential sides of the sheathing board, the sheathing boards are connected one another, and then, the vertical batter and a waling are mounted to the sheathing board. SOLUTION: In this form assembling method, the sheathing boards 4 arranged in parallel in the lateral and longitudinal directions are connected one another by means of assembly metal fittings K each having a U-shaped part, while the vertical batters 6a are inserted into recesses K' of the assembly metal fittings. Then, the form is assembled while the lateral battens 6b are arranged by means of form ties N.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、堰板を、適宜、接
合するとともに、接合された堰板を、桟木や縦端太や横
端太等の支保工で支持するようにした型枠組み立て方法
及び該方法に使用する組立金具に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a formwork assembly in which weir plates are appropriately joined together and the joined weir plates are supported by a supporting member such as a splint or a vertical edge or horizontal edge. The present invention relates to a method and an assembly fitting used for the method.

【0002】[0002]

【従来の技術】従来、堰板の4つの周辺に、角材を取り
付けて補強し、このように角材で補強された堰板を、適
宜、連結して型枠を組み立て、その後、縦端太及び横端
太で補強するようにした型枠組み立て方法が知られてい
る。
2. Description of the Related Art Conventionally, square bars are attached around four barrier plates for reinforcement, and the barrier plates thus reinforced with the square bars are appropriately connected to assemble a formwork, and then the vertical thick and There is known a method of assembling a form which is reinforced by a lateral edge.

【0003】[0003]

【発明が解決しようとする課題】上述した従来の型枠組
み立て方法においては、堰板への角材の取り付け作業に
時間と労力を要し、従って、型枠の組み立て作業の作業
性が悪いという問題があった。
In the conventional method of assembling the formwork described above, it takes time and labor to attach the square members to the dam plate, and therefore the workability of the work of assembling the formwork is poor. was there.

【0004】また、角材で補強された堰板を連結して型
枠を組み立てた後、縦端太及び横端太で補強する際に、
堰板を支えるものがないために、縦端太及び横端太の取
り付け作業を不安定な状態で行わなければならないとい
う問題があった。
In addition, after the dam plates reinforced by the square members are connected to each other to assemble the formwork, when reinforcing the vertical and horizontal ends,
Since there is nothing to support the weir plate, there is a problem that the work of attaching the vertical edge and the horizontal edge must be performed in an unstable state.

【0005】更に、堰板が設置される床スラブの上面の
レベルが一定でなく、凸凹を有しているために、各堰板
のレベルを揃えるのが困難であるという問題があった。
Further, since the level of the upper surface of the floor slab on which the dam plate is installed is not constant and has unevenness, there is a problem that it is difficult to align the level of each dam plate.

【0006】本発明の目的は、上述した従来の型枠組み
立て方法が有する課題を解決することにある。
An object of the present invention is to solve the problems of the above-described conventional method for assembling a mold.

【0007】[0007]

【課題を解決するための手段】本発明は、上述した目的
を達成するために、型枠組み立て方法において、横方向
及び縦方向に並設された堰板を、コの字状部を有する組
立金具により連結するとともに、組立金具の凹部に、縦
端太を挿入し、その後、フォームタイにより、横端太を
配設して、型枠を組み立てるようにしたものであり、ま
た、コの字状部と、該コの字状部を形成する平行板部の
端部から、該平行板部に対して垂直に、且つ、互いに遠
ざかる方向に延在する取付板部とからなる上記の型枠組
み立て方法に使用する組立金具に関するものである。
In order to achieve the above-mentioned object, the present invention is a method for assembling a form, in which a weir plate arranged in a horizontal direction and a vertical direction is assembled with a U-shaped portion. The mold is assembled by connecting with the metal fittings, inserting the vertical thickness into the recess of the assembly metal fitting, and then arranging the horizontal thickness with the form tie to assemble the formwork. The above-mentioned formwork comprising a plate-shaped portion and a mounting plate portion extending from an end portion of the parallel plate portion forming the U-shaped portion in a direction perpendicular to the parallel plate portion and away from each other. The present invention relates to an assembly fitting used for an assembly method.

【0008】[0008]

【実施例】以下に、本発明の実施例について説明する
が、本発明の趣旨を越えない限り何ら、本実施例に限定
されるものではない。
EXAMPLES Examples of the present invention will be described below, but the present invention is not limited to these examples as long as the gist of the present invention is not exceeded.

【0009】先ず最初に、図1及び図2を用いて、複数
の堰板を縦横に並設して、型枠を組み立てる際に使用さ
れる組立金具Kとレベル調整部材Hについて説明する。
First, referring to FIG. 1 and FIG. 2, a description will be given of an assembly metal fitting K and a level adjusting member H used when assembling a plurality of weir plates arranged side by side vertically and horizontally.

【0010】組立金具Kは、平板部k1aと該平板部k
1aの両端から平板部k1aに対して垂直に、且つ、互
いに平行に延在する平行板部k1bとからなるコの字状
部k1と、該コの字状部k1を形成する平行板部k1b
の端部から、平行板部k1bに対して垂直に、且つ、互
いに遠ざかる方向に延在する取付板部k2とにより構成
されており、一対の取付板部k2には、螺子やビスや釘
等の適当な固着具が挿通可能な透孔k2aが、上方と下
方に、それぞれ適当数、穿設されている。組立金具K
は、一例として、帯状金属板を、適当に折り曲げること
により形成される。なお、組立金具Kは、図1に示され
ているように、コの字状部k1を構成する平板部k1a
と平行板部k1b及び取付板部k2が、垂直になるよう
に、後述する堰板に取着される。
The assembly metal fitting K includes a flat plate portion k1a and the flat plate portion k.
1a, a U-shaped portion k1 composed of parallel plate portions k1b extending perpendicularly to the flat plate portion k1a and parallel to each other, and a parallel plate portion k1b forming the U-shaped portion k1.
From the end of the parallel plate part k1b, and perpendicular to the parallel plate part k1b, and the mounting plate part k2 extending in a direction away from each other. The pair of mounting plate parts k2 has a screw, a screw, a nail, or the like. The appropriate number of through holes k2a through which appropriate fasteners can be inserted are formed in the upper and lower portions, respectively. Assembly bracket K
Is formed by, for example, appropriately bending a strip-shaped metal plate. As shown in FIG. 1, the assembly metal fitting K has a flat plate portion k1a forming a U-shaped portion k1.
The parallel plate part k1b and the mounting plate part k2 are attached to a dam plate described later so as to be vertical.

【0011】レベル調整部材Hは、垂直部h1と、垂直
部h1の上端から水平方向に延在する上部水平部h2
と、垂直部h1の下端から水平方向に、且つ、上部水平
部h2と同方向に延在する下部水平部h3とを有してお
り、垂直部h1と上部水平部h2と下部水平部h3とに
より、略コの字状の支持枠H’が構成されている。上部
水平部h2及び下部水平部h3とには、平面から見て重
なるように、透孔h2a、h3aがそれぞれ穿設されて
おり、また、上部水平部h2の下面には、上部水平部h
2に穿設された透孔h2aと一致するような螺子孔h4
aを有するナットh4が取着されている。h5は、ネジ
棒であり、ネジ棒h5は、上部水平部h2の下面に取着
されたナットh4の螺子孔h4aに螺合されているとと
もに、下部水平部h3に穿設された透孔h3aに挿通さ
れている。また、垂直部h1には、螺子やビスや釘等の
適当な固着具が挿通可能な透孔h1aが、適当数、穿設
されている。
The level adjusting member H includes a vertical portion h1 and an upper horizontal portion h2 extending horizontally from the upper end of the vertical portion h1.
And a lower horizontal portion h3 extending horizontally from the lower end of the vertical portion h1 and in the same direction as the upper horizontal portion h2. The vertical portion h1, the upper horizontal portion h2, and the lower horizontal portion h3 Thus, a substantially U-shaped support frame H'is formed. Through holes h2a and h3a are formed in the upper horizontal portion h2 and the lower horizontal portion h3 so as to overlap each other when seen from a plane, and the lower surface of the upper horizontal portion h2 has an upper horizontal portion h2a.
2 has a screw hole h4 that matches the through hole h2a.
A nut h4 having a is attached. h5 is a threaded rod, and the threaded rod h5 is screwed into a screw hole h4a of a nut h4 attached to the lower surface of the upper horizontal portion h2 and also a through hole h3a formed in the lower horizontal portion h3. Has been inserted into. Further, the vertical portion h1 is provided with an appropriate number of through holes h1a through which appropriate fasteners such as screws, screws and nails can be inserted.

【0012】次に、上述した組立金具Kやレベル調整部
材Hを用いた型枠の組み立てについて説明する。
Next, the assembly of the mold using the above-mentioned assembly metal fitting K and the level adjusting member H will be described.

【0013】1は、角材からなる桟木であり、桟木1
は、予め、床スラブ2の上面に墨出しされた線に沿って
配置されるとともに、釘やビス等の適当な固着具(な
お、本実施例には、固着具としてビスが用いられている
例が示されているので、以下においては、固着具として
のビスには、符号3を使用した。)を桟木1に打ち込む
ことにより、床スラブ2に取り付けられる。図1には、
一例として、2本の桟木1a、1bの端部を揃えてL字
状に形成された2組の桟木部材B1を構成する一方の角
材1bを、所定の間隔を置いて平行に配置するととも
に、上記の2組の桟木部材B1を構成するもう一方の桟
木1aに、所定の間隔を置いて平行に、桟木1cを直線
状に配置した桟木部材B2が、床スラブ2に取着された
例が示されている。
Reference numeral 1 denotes a pier made of timber, and the pier 1
Is arranged in advance along the line marked out on the upper surface of the floor slab 2, and an appropriate fastener such as a nail or a screw (in this embodiment, a screw is used as the fastener. Since an example is shown, in the following, a screw as a fastener uses the reference numeral 3.) is attached to the floor slab 2 by driving it into the splint 1. In Figure 1,
As an example, one timber 1b forming two L-shaped timber members B1 having the ends of the two timbers 1a, 1b aligned with each other is arranged in parallel at a predetermined interval. An example is shown in which a pier member B2 in which the piers 1c are linearly arranged in parallel to the other pier 1a constituting the above-mentioned two sets of pier members B1 is attached to the floor slab 2 in parallel. It is shown.

【0014】型枠を組み立てるために、横方向及び縦方
向に配列される堰板は、高さ、幅及び厚さが同一に形成
されており、堰板としては、木毛や木片や木材チップ等
の木質材料とセメントとからなる木質系セメント板(木
毛セメント板や木片セメント板)を使用することが好ま
しい。
The weir plates arranged in the horizontal and vertical directions for assembling the formwork are formed to have the same height, width and thickness. The weir plate is made of wood wool, wood chips or wood chips. It is preferable to use a wood-based cement board (wood wool cement board or wood chip cement board) composed of a wood material and cement.

【0015】先ず最初に、2枚の堰板4a、4aを、一
方の堰板4aの垂直端面4a1が、他方の堰板4aの側
面4a3に当接するように接触させて、平面形状がL字
状に配置するとともに、2枚の堰板4a、4aの上下端
面を揃えた後、ビスや釘等の適当な固着具を用いて、互
いに固定する。
First, the two dam plates 4a, 4a are brought into contact with each other so that the vertical end surface 4a1 of one dam plate 4a abuts the side surface 4a3 of the other dam plate 4a, and the plane shape is L-shaped. After aligning the upper and lower end surfaces of the two dam plates 4a and 4a, they are fixed to each other using an appropriate fastener such as a screw or a nail.

【0016】上述したようにしてL字状に組み立てられ
た2枚の堰板4a、4aの互いに当接していない側の垂
直端面4a1付近で、且つ、桟木1が位置する側面に、
2つのレベル調整部材H1、H2を配置するとともに、
レベル調整部材H1、H2の垂直部h1に穿設された透
孔h1aに、ビス3を挿通し、堰板4a、4aに打ち込
むことにより、2つのレベル調整部材H1、H2を、堰
板4a、4aに取着する。同様のレベル調整部材部材H
3を、L字状に組み立てられた堰板4a、4aの一方の
堰板4aの隅部付近で、且つ、桟木1bが位置する側面
に、1つのレベル調整部材H3を配置するとともに、レ
ベル調整部材H3の垂直部h1に穿設された透孔h1a
に、ビス3を挿通し、堰板4aに打ち込むことにより、
レベル調整部材H3を、堰板4aに取着する。上記のよ
うにして堰板4a、4aに取着されたレベル調整部材H
1、H2、H3は、ネジ棒h1の下端が、床スラブ2に
当接するか、或いは、接近するように、堰板枠4a、4
aに取着される。
In the vicinity of the vertical end faces 4a1 of the two weir plates 4a, 4a assembled in the L-shape as described above on the side not contacting each other, and on the side face on which the pier 1 is located,
While arranging the two level adjusting members H1 and H2,
By inserting the screw 3 into the through hole h1a formed in the vertical portion h1 of the level adjusting members H1 and H2 and driving it into the dam plates 4a and 4a, the two level adjusting members H1 and H2 are moved to the dam plate 4a and Attach to 4a. Similar level adjusting member H
3, one level adjusting member H3 is arranged near the corner of one of the weir plates 4a, 4a assembled in an L shape, and on the side surface on which the pier 1b is located, and level adjustment is performed. Through hole h1a formed in the vertical portion h1 of the member H3
By inserting the screw 3 into the
The level adjusting member H3 is attached to the barrier plate 4a. The level adjusting member H attached to the barrier plates 4a, 4a as described above.
1, H2, H3 are the dam plate frames 4a, 4 so that the lower end of the screw rod h1 abuts on or approaches the floor slab 2.
attached to a.

【0017】上述したようにして堰板4a、4aに取着
されたレベル調整部材H1、H2、H3の何れかのネジ
棒h1を、適当に回転させることにより、下端が床スラ
ブ2に当接している状態のネジ棒h1に対して支持枠
H’を上下動させて、支持枠H’に取着されている堰板
4a、4aを上下動させるとともに、堰板4a、4aの
上端面4a2に載置される適当な水準器を用いて、堰板
4a、4aのレベル出しを行う。その後、上述したと同
様に、ビス3を用いて、角部を構成する堰板4a、4a
を、桟木1a、1bに取着する。このようにして、図4
に示されているように、2枚の堰板4a、4aにより、
型枠の角部が組み立てられることになる。このようなレ
ベル調整部材H1、H2、H3を使用することにより、
堰板4a、4aの微妙な上下動を行うことができ、従っ
て、精度の向上したレベル出しを行うことができるとと
もに、作業員のレベル出し作業の作業性が向上する。上
記のネジ棒h1の回転は、ネジ棒h1の上端部を、公知
のネジ棒回転工具で把持して行うことが好ましい。
By appropriately rotating any one of the screw rods h1 of the level adjusting members H1, H2, H3 attached to the barrier plates 4a, 4a as described above, the lower end is brought into contact with the floor slab 2. The support frame H ′ is moved up and down with respect to the screw rod h1 in the state of being held, and the weir plates 4a and 4a attached to the support frame H ′ are moved up and down, and the upper end surfaces 4a2 of the weir plates 4a and 4a are moved. Leveling of the weir plates 4a, 4a is performed by using an appropriate level placed on the. After that, in the same manner as described above, using the screws 3, the dam plates 4a and 4a forming the corners are formed.
Are attached to the piers 1a and 1b. In this way, FIG.
As shown in Fig. 2, by the two dam plates 4a, 4a,
The corners of the formwork will be assembled. By using such level adjusting members H1, H2, H3,
The weir plates 4a, 4a can be slightly moved up and down, so that the leveling with improved accuracy can be performed, and the workability of the leveling work of the worker is improved. It is preferable to rotate the screw rod h1 by gripping the upper end of the screw rod h1 with a known screw rod rotating tool.

【0018】上述したように、L字状に配置された角部
を構成する2枚の堰板4a、4aを、桟木1a、1bに
固定した後、角部を構成する一方の堰板4aに、別の堰
板4bを並設するとともに、角部を構成する堰板4aの
一方の垂直端面4a1と堰板4bの一方の垂直端面4b
1とが当接し、且つ、角部を構成する堰板4aの上端面
4a2と堰板4bの上端面4b2とが面一になるように
配置し、この状態で、組立金具K1が、角部を構成する
堰板4aの垂直端面4a1と堰板4bの垂直端面4b1
との当接線f1の上端から、略半分ほど突出するように
配置し、その後、組立金具K1の取付板部k2に穿設さ
れた下方に位置する透孔k2aにビス3を挿通するとと
もに堰板4a、4bに打ち込んで、組立金具K1によ
り、角部を構成する堰板4aと該堰板4aに並設された
堰板4bとを連結する。次いで、角部を構成する堰板4
aが並設されていない側の堰板4bの垂直端面4b1付
近で、且つ、桟木1bが位置する側面に、1つのレベル
調整部材H4を配置するとともに、レベル調整部材H4
の垂直部h1に穿設された透孔h1aに、ビス3を挿通
するとともに、堰板4bに打ち込むことにより、レベル
調整部材H4を、堰板4bに取着する。次いで、堰板4
bに取着されたレベル調整部材H4のネジ棒h1を、適
当に回転させることにより、下端が床スラブ2に当接し
ている状態のネジ棒h1に対して支持枠H’を上下動さ
せて、支持枠H’が取着されている堰板4bを上下動さ
せるとともに、堰板4bの上端面4b2に載置される適
当な水準器を用いて、堰板4bのレベル出しを行い、そ
の後、上述したと同様に、ビス3を用いて、図5に示さ
れているように、角部を構成する一方の堰板4aに並設
された堰板4bを、桟木1bに取着する。また、組立金
具K2を、堰板4bの垂直端面4b1及び上端面4b2
から略半分飛び出るように、角部を構成する堰板4aと
反対側に位置する堰板4bの上部角部に配置し、その
後、組立金具K2の取付板部k2に穿設された下方に位
置する透孔k2aにビス3を挿通するとともに堰板4b
に打ち込んで、組立金具K2を堰板4bの上部角部に取
着する。
As described above, after fixing the two dam plates 4a, 4a forming the corners arranged in the L shape to the piers 1a, 1b, the one dam plate 4a forming the corners is fixed. , Another weir plate 4b is provided in parallel, and one vertical end face 4a1 of the weir plate 4a and one vertical end face 4b of the weir plate 4b that form a corner portion.
1, and the upper end surface 4a2 of the barrier plate 4a and the upper end surface 4b2 of the barrier plate 4b, which are in contact with each other, are flush with each other. And the vertical end face 4a1 of the barrier plate 4a and the vertical end face 4b1 of the barrier plate 4b
Is arranged so as to project from the upper end of the contact line f1 with about halfway, and then the screw 3 is inserted into the through hole k2a located in the lower part of the mounting plate part k2 of the assembly metal fitting K1 and the dam plate is formed. The weir plates 4a forming the corners and the weir plates 4b juxtaposed on the weir plates 4a are connected to each other by driving into the weir plates 4a and 4b and using the assembly fitting K1. Next, weir plate 4 forming the corners
One level adjusting member H4 is arranged in the vicinity of the vertical end surface 4b1 of the dam plate 4b on the side where a is not provided side by side, and on the side surface on which the pier 1b is located.
The level adjusting member H4 is attached to the dam plate 4b by inserting the screw 3 into the through hole h1a formed in the vertical portion h1 and driving the screw 3 into the dam plate 4b. Next, weir plate 4
By appropriately rotating the screw rod h1 of the level adjusting member H4 attached to b, the support frame H ′ is moved up and down with respect to the screw rod h1 whose lower end is in contact with the floor slab 2. , The weir plate 4b to which the support frame H'is attached is moved up and down, and the weir plate 4b is leveled by using an appropriate leveler placed on the upper end surface 4b2 of the weir plate 4b, and then Similarly to the above, using the screw 3, as shown in FIG. 5, the weir plate 4b juxtaposed to the one weir plate 4a forming the corner portion is attached to the pier 1b. Further, the assembly metal fitting K2 is attached to the vertical end face 4b1 and the upper end face 4b2 of the barrier plate 4b.
It is arranged at the upper corner of the weir plate 4b located on the opposite side of the weir plate 4a forming the corner so as to protrude almost half from the above, and then located below the mounting plate portion k2 of the assembly metal fitting K2. The screw 3 is inserted into the through hole k2a, and the dam plate 4b is formed.
Then, the assembly metal fitting K2 is attached to the upper corner of the barrier plate 4b.

【0019】次に、上述した堰板4bに、別の堰板4c
を並設するとともに、堰板4bの垂直端面4b1と堰板
4bに並設された堰板4cの垂直端面4c1とが当接
し、且つ、堰板4bの上端面4b2と堰板4cの上端面
4c2とが面一になるように配置し、その後、堰板4b
に取着されている組立金具K2の取付板部k2に穿設さ
れた下方に位置する透孔k2aに、ビス3を挿通すると
ともに堰板4cに打ち込んで、組立金具K2により、堰
板4bと堰板4cとを連結する。次いで、堰板4bが並
設されていない側の堰板4cの垂直端面4c1付近で、
且つ、桟木1bが位置する側面に、1つのレベル調整部
材H5を配置するとともに、レベル調整部材H5の垂直
部h1に穿設された透孔h1aに、ビス3を挿通すると
ともに、堰板4cに打ち込むことにより、レベル調整部
材H5を、堰板4cに取着する。次いで、堰板4cに取
着されたレベル調整部材H5のネジ棒h1を、適当に回
転させることにより、下端が床スラブ2に当接している
状態のネジ棒h1に対して支持枠H’を上下動させて、
支持枠H’が取着されている堰板4cを上下動させると
ともに、堰板4cの上端面4c2に載置される適当な水
準器を用いて、堰板4cのレベル出しを行い、その後、
上述したと同様に、ビス3を用いて、図6に示されてい
るように、堰板4bに並設された堰板4cを、桟木1b
に取着する。また、組立金具K3を、堰板4cの垂直端
面4c1及び上端面4c2から略半分飛び出るように、
堰板4bと反対側に位置する堰板4cの上部角部に配置
し、その後、組立金具K3の取付板部k2に穿設された
下方に位置する透孔k2aにビス3を挿通するとともに
堰板4cに打ち込んで、組立金具K3を堰板4cの上部
角部に取着する。
Next, another weir plate 4c is added to the weir plate 4b described above.
And the vertical end surface 4b1 of the barrier plate 4b and the vertical end surface 4c1 of the barrier plate 4c arranged side by side on the barrier plate 4b contact each other, and the upper end surface 4b2 of the barrier plate 4b and the upper end surface of the barrier plate 4c. 4c2 are arranged so as to be flush with each other, and then the weir plate 4b
The screw 3 is inserted in the lower through hole k2a formed in the mounting plate portion k2 of the assembly metal fitting K2 attached to the same and is driven into the dam plate 4c. It connects with the barrier plate 4c. Next, near the vertical end surface 4c1 of the barrier plate 4c on the side where the barrier plates 4b are not juxtaposed,
Moreover, one level adjusting member H5 is arranged on the side surface where the pier 1b is located, and the screw 3 is inserted into the through hole h1a formed in the vertical portion h1 of the level adjusting member H5, and the weir plate 4c is inserted. The level adjusting member H5 is attached to the barrier plate 4c by driving. Next, by appropriately rotating the screw rod h1 of the level adjusting member H5 attached to the barrier plate 4c, the support frame H ′ is attached to the screw rod h1 whose lower end is in contact with the floor slab 2. Move it up and down,
The weir plate 4c to which the support frame H'is attached is moved up and down, and the weir plate 4c is leveled by using an appropriate level placed on the upper end surface 4c2 of the weir plate 4c, and then,
In the same manner as described above, using the screw 3, as shown in FIG. 6, the weir plate 4c juxtaposed with the weir plate 4b is attached to the pier 1b.
Attach to. In addition, the assembly metal fitting K3 is protruded from the vertical end surface 4c1 and the upper end surface 4c2 of the barrier plate 4c by about half.
The screw 3 is arranged at the upper corner of the weir plate 4c located on the opposite side of the weir plate 4b, and then the screw 3 is inserted into the through hole k2a located below the mounting plate part k2 of the assembly metal fitting K3 and the weir is formed. The metal fitting K3 is driven into the plate 4c and attached to the upper corner of the barrier plate 4c.

【0020】更に、堰板4cに、別の堰板4dを配置す
るとともに、堰板4cに取着されている組立金具K3に
より、堰板4cと堰板4dを連結し、更に、堰板4dに
レベル調整部材Hを取着し、堰板4dのレベル出しを行
った後、堰板4dを、桟木1bに取着する。このように
して、順次、適当数の堰板4を並設する。同様に、角部
を構成するもう一方の堰板4aにも、順次、堰板4を並
設する。
Further, another weir plate 4d is arranged on the weir plate 4c, and the weir plate 4c and the weir plate 4d are connected by an assembly metal fitting K3 attached to the weir plate 4c. After the level adjusting member H is attached to the barrier plate 4d to level the barrier plate 4d, the barrier plate 4d is attached to the pier 1b. In this way, a suitable number of weir plates 4 are sequentially arranged in parallel. Similarly, the weir plate 4 is sequentially arranged in parallel also on the other weir plate 4a that constitutes the corner portion.

【0021】上述したようにして、一段目の堰板4が、
桟木1a、1bに取着されることになるが、一段目の堰
板4a、4b、4c、4d・・・は、レベル調整部材H
により、その上端面のレベル出しが行われているので、
一段目の堰板4a、4b、4c、4d・・・の上端面に
載置される二段目の堰板4’のレベル出しを行う必要が
ない。また、一段目の堰板4a、4b、4c、4d・・
・に取着されている組立金具K1、K2、K3・・・
は、その略半分が、一段目の堰板4a、4b、4c、4
d・・・の上端面4a2、4b2、4c2、4d2・・
・から上方に飛び出しているので、二段目の堰板4’
を、一段目の堰板4a、4b、4c、4d・・・の上端
面4a2、4b2、4c2、4d2・・・に載置した
後、組立金具K1、K2、K3・・・の取付板部k2に
穿設された上方に位置する透孔k2aにビス3を挿通す
るとともに二段目の堰板4’に打ち込んで、図8に示さ
れているように、二段目の堰板4’と一段目の堰板4
a、4b、4c、4d・・・とを、組立金具Kにより連
結する。また、隣接する二段目の堰板4’の垂直端面同
士が当接して形成される当接線f’の上端から、組立金
具Kが、略半分ほど突出するように、組立金具Kを配置
するとともに、組立金具Kの取付板部k2に穿設された
下方に位置する透孔k2aにビス3を挿通するとともに
二段目の堰板4’に打ち込んで、二段目の堰板4’に、
組立金具Kを取着しておく。
As described above, the first barrier plate 4 is
The dams 4a, 4b, 4c, 4d, ... Of the first stage are attached to the piers 1a, 1b.
The leveling of the upper end surface is done by
It is not necessary to level the second dam plate 4'mounted on the upper end surfaces of the first dam plates 4a, 4b, 4c, 4d, .... In addition, the first step weir plates 4a, 4b, 4c, 4d ...
・ Assembled metal fittings K1, K2, K3 ...
About half of the barrier plates 4a, 4b, 4c, 4
upper end surfaces 4a2, 4b2, 4c2, 4d2 of d ...
・ Since it protrudes from above, the second weir plate 4 '
Are mounted on the upper end surfaces 4a2, 4b2, 4c2, 4d2 ... Of the first-stage dam plates 4a, 4b, 4c, 4d. As shown in FIG. 8, the screw 3 is inserted into the through hole k2a located at the upper side of the k2 and is driven into the second step dam plate 4 ', and as shown in FIG. And the first step weir plate 4
a, 4b, 4c, 4d, ... In addition, the assembly metal fitting K is arranged such that the assembly metal fitting K projects approximately half from the upper end of the contact line f ′ formed by the vertical end surfaces of the adjacent second barrier plates 4 ′ contacting each other. At the same time, the screw 3 is inserted into the through hole k2a located in the lower portion of the mounting plate portion k2 of the assembly metal fitting K, and the screw 3 is driven into the second step weir plate 4 ', so that the second step weir plate 4'is formed. ,
Attach the mounting bracket K.

【0022】上述したように、一段目の堰板4a、4
b、4c、4d・・・に、組立金具K1、K2、K3・
・・を介して連結された二段目の堰板4’の上端面に、
必要に応じて、三段目の堰板4”を載置するとともに、
二段目の堰板4’に取着されている組立金具Kの取付板
部k2に穿設された上方に位置する透孔k2aにビス3
を挿通するとともに三段目の堰板4”に打ち込んで、図
9に示されているように、三段目の堰板4”と二段目の
堰板4’とを、組立金具Kにより連結する。また、三段
目の堰板4”の上に、更に、四段目の堰板4を載置する
場合には、上述したと同様に、隣接する三段目の堰板
4”の垂直端面同士が当接して形成される当接線の上端
から、組立金具Kが、略半分ほど突出するように、組立
金具Kを配置するとともに、組立金具Kの取付板部k2
に穿設された下方に位置する透孔k2aにビス3を挿通
するとともに三段目の堰板4”に打ち込んで、三段目の
堰板4”に、組立金具Kを取着することになるが、三段
目の堰板4”の上に、四段目の堰板4を載置しない場合
には、図9に示されているように、組立金具Kは、三段
目の堰板4”の上端部に取着される回り縁部材を考慮し
て、隣接する三段目の堰板4”の垂直端面同士が当接し
て形成される当接線f”の上端から下がった位置に取着
される。
As described above, the first barrier plates 4a, 4
b, 4c, 4d ..., Assembling metal fittings K1, K2, K3.
.. on the upper end surface of the second step weir plate 4'connected via
If necessary, place the 3rd barrier plate 4 ",
A screw 3 is inserted into the through hole k2a located at the upper side of the mounting plate portion k2 of the assembly metal fitting K attached to the second barrier plate 4 '.
9 is inserted and driven into the third step weir plate 4 ", and as shown in FIG. 9, the third step weir plate 4" and the second step weir plate 4'are attached by the assembly metal fitting K. Link. In addition, when the fourth step weir plate 4 is further placed on the third step weir plate 4 ″, the vertical end face of the adjacent third step weir plate 4 ″ is also performed as described above. The assembly metal fitting K is arranged such that the assembly metal fitting K projects approximately half from the upper end of the contact line formed by the mutual contact, and the mounting plate portion k2 of the assembly metal fitting K is arranged.
The screw 3 is inserted into the through hole k2a located at the lower side of the hole and is driven into the third step weir plate 4 ", and the assembly metal fitting K is attached to the third step weir plate 4". However, when the fourth step weir plate 4 is not placed on the third step weir plate 4 ″, as shown in FIG. Considering the rim member attached to the upper end of the plate 4 ", the position is lowered from the upper end of the contact line f" formed by contacting the vertical end faces of the adjoining third step weir plate 4 ". Be attached.

【0023】上述したようにして、L字状に形成された
2組の桟木部材B1を構成する一方の桟木部材B1に、
一段目の堰板4a、4b、4c、4d・・・、二段目の
堰板4’及び三段目の堰板4”を、横方向及び縦方向に
並設するとともに、組立金具Kにより連結するが、この
ように堰板4を組み立てている間は、堰板4が倒壊しな
いように、適宜、木材等で、仮支えをしておく。また、
上下方向に配置された組立金具Kのコの字状部k1を構
成する平板部k1aと平行板部k1bとにより形成され
る凹部K’が、平面的に見て略一致するように、組立金
具Kは、堰板4に取着される。
As described above, one of the wood members B1 constituting the two L-shaped wood members B1 is
The first step weir plates 4a, 4b, 4c, 4d ..., the second step weir plate 4'and the third step weir plate 4 "are arranged side by side in the horizontal and vertical directions, and Although they are connected, while the weir plate 4 is assembled in this way, temporary support is appropriately made with wood or the like so that the weir plate 4 does not collapse.
The assembly metal fitting K is so arranged that the recess K ′ formed by the flat plate portion k1a and the parallel plate portion k1b forming the U-shaped portion k1 of the assembly metal fitting K arranged in the up-down direction substantially match each other in plan view. K is attached to the dam plate 4.

【0024】次に、図10を用いて、相対する堰板4間
に配設されるスペーサーSについて説明する。
Next, referring to FIG. 10, the spacer S arranged between the opposing barrier plates 4 will be described.

【0025】s1は、両端部にネジ溝が刻設された軸で
あり、軸s1の両端には、ネジ孔s2’が穿設されたス
ペーサー筒体s2が螺合されている。s3は、スペーサ
ー筒体s2の内側に螺合された止めナットである。s4
は、軸s1の反対側から、スペーサー筒体s2のネジ孔
s2’に螺合されたネジ軸であり、s5は、ネジ軸s4
に螺合されるナットである。
Reference numeral s1 is a shaft having thread grooves formed on both ends thereof, and a spacer cylinder s2 having screw holes s2 'formed therein is screwed into both ends of the shaft s1. s3 is a lock nut screwed inside the spacer cylinder s2. s4
Is a screw shaft screwed into the screw hole s2 ′ of the spacer cylinder s2 from the opposite side of the shaft s1, and s5 is a screw shaft s4.
It is a nut that is screwed into.

【0026】上述した構成を有するスペーサーSを、堰
板4間に配置するには、図9に示されているように、相
対する堰板4の一方の堰板4が、横方向及び縦方向に組
み立てられた時点で、一方の堰板4に形成された透孔5
に、スペーサー筒体s2のネジ孔s2’に螺合されたネ
ジ軸s4を、スペーサー筒体s2が堰板4に当接するま
で挿通し、その後、堰板4から突き出たネジ軸s4にナ
ットs5を螺合して、スペーサー筒体s2とナットs5
により、堰板4を挟持する。次いで、後述するようにし
て、上記の堰板4に相対するように配置された堰板4に
穿設された透孔5に、もう一方のスペーサー筒体s2の
ネジ孔s2’に螺合されたネジ軸s4を挿通し、その
後、同様に、ネジ軸s4にナットs5を螺合して、スペ
ーサー筒体s2とナットs5により、もう一方の堰板4
を挟持する。このようにして、相対する堰板4間の適当
な箇所にスペーサーSを配設する。なお、後述するよう
に、堰板4間に、生コンクリートを充填し、生コンクリ
ートがある程度、固化した後に、堰板4の外側に突出し
ているナットs5及びネジ軸s4を取り外す。
In order to dispose the spacer S having the above-mentioned structure between the dam plates 4, as shown in FIG. 9, one of the facing dam plates 4 is moved in the horizontal direction and the vertical direction. Through hole 5 formed in one weir plate 4 when assembled into
Then, the screw shaft s4 screwed into the screw hole s2 ′ of the spacer cylinder s2 is inserted until the spacer cylinder s2 contacts the dam plate 4, and then the screw shaft s4 protruding from the dam plate 4 is attached to the nut s5. By screwing together the spacer cylinder s2 and nut s5
Thus, the barrier plate 4 is clamped. Then, as will be described later, the through hole 5 formed in the barrier plate 4 arranged so as to face the barrier plate 4 is screwed into the screw hole s2 ′ of the other spacer cylinder s2. The screw shaft s4 is inserted, and then the nut s5 is similarly screwed onto the screw shaft s4, and the spacer cylinder s2 and the nut s5 are used to insert the other weir plate 4
To pinch. In this way, the spacer S is arranged at an appropriate position between the opposing barrier plates 4. As will be described later, after filling the space between the dam plates 4 with fresh concrete and solidifying the fresh concrete to some extent, the nut s5 and the screw shaft s4 protruding to the outside of the dam plate 4 are removed.

【0027】次いで、上述したようにして、L字状に形
成された2組の桟木部材B1を構成するもう一方の桟木
部材B1に、一段目の堰板4a、4b、4c、4d・・
・、二段目の堰板4’及び三段目の堰板4”を、横方向
及び縦方向に並設するとともに、組立金具Kにより連結
する。更に、L字状に形成された2組の桟木部材B1を
構成する桟木1aに、所定の間隔を置いて平行に、且
つ、直線状に配置された桟木部材B2を構成する桟木1
cに、上述したと同様にして、堰板4を並設する。例え
ば、図4に示されているように、上述した角部を構成す
る2枚の堰板4a、4aのうち、2つのレベル調整部材
H1、H3が取着された堰板4aのように、1つの堰板
4に、2つのレベル調整部材H1、H3を取着する。こ
のように、2つのレベル調整部材H1、H3が取着され
た堰板4を、桟木部材B2を構成する桟木1cに沿って
配置し、次いで、上述したと同様に、レベル調整部材H
1、H3のネジ棒h1を、適当に回転させることによ
り、下端が床スラブ2に当接している状態のネジ棒h1
に対して支持枠H’を上下動させて、支持枠H’に取着
されている堰板4を上下動させるとともに、堰板4の上
端面に載置される適当な水準器を用いて、堰板4のレベ
ル出しを行い、その後、上述したと同様に、ビス3を用
いて、堰板4を、桟木1cに取着する。その後、角部を
構成する堰板4aに、堰板4b、4c、4d・・・を並
設するとともに、組立金具K1、K2、K3・・・によ
り連結したと同様の順序により、上記の桟木部材B2を
構成する桟木1cに取着された堰板4に、適当数の堰板
4を並設し連結する。
Then, as described above, the other deck members B1 constituting the two sets of the deck members B1 formed in the L-shape are attached to the first step weir plates 4a, 4b, 4c, 4d ...
., The second step weir plate 4 ′ and the third step weir plate 4 ″ are arranged side by side in the horizontal direction and the vertical direction, and are connected by the assembling metal fitting K. Furthermore, two sets formed in an L shape 1 which constitutes the pier member B2 which is arranged in parallel and linearly at a predetermined interval to the pier 1a which constitutes the pier member B1.
In the same manner as described above, the weir plate 4 is provided in c. For example, as shown in FIG. 4, among the two dam plates 4a and 4a forming the above-mentioned corner portion, like the dam plate 4a to which the two level adjusting members H1 and H3 are attached, Two level adjusting members H1 and H3 are attached to one barrier plate 4. In this way, the barrier plate 4 to which the two level adjusting members H1 and H3 are attached is arranged along the pier 1c which constitutes the pier member B2, and then, similarly to the above, the level adjusting member H.
By appropriately rotating the threaded rods h1 of H1 and H3, the threaded rods h1 whose lower end is in contact with the floor slab 2
The support frame H ′ is moved up and down with respect to the weir plate 4 attached to the support frame H ′, and an appropriate level is placed on the upper end surface of the weir plate 4. The level of the dam plate 4 is set, and then the dam plate 4 is attached to the pier 1c by using the screw 3 in the same manner as described above. After that, the weir plates 4b, 4c, 4d, ... Are arranged in parallel on the weir plate 4a that forms the corner portion, and the above-mentioned piers are arranged in the same order as they are connected by the assembly metal fittings K1, K2, K3. An appropriate number of weir plates 4 are juxtaposed and connected to the weir plate 4 attached to the pier 1c that constitutes the member B2.

【0028】上述したようにして、L字状に形成された
2組の桟木部材B1を構成する一方の桟木部材B1に、
一段目の堰板4a、4b、4c、4d・・・を取着し、
更に、一段目の堰板4a、4b、4c、4d・・・に、
二段目の堰板4’及び三段目の堰板4”を、横方向及び
縦方向に並設するとともに、組立金具K1、K2、K3
・・・により連結し、次いで、一段目の堰板4a、4
b、4c、4d・・・、二段目の堰板4’及び三段目の
堰板4”にスペーサーSを取り付ける。また、L字状に
形成された2組の桟木部材B1を構成するもう一方の桟
木部材B1に、同様に、一段目の堰板4a、4b、4
c、4d・・・を取着し、更に、一段目の堰板4a、4
b、4c、4d・・・に、二段目の堰板4’及び三段目
の堰板4”を並設し連結するとともに、桟木部材B2を
構成する桟木1cに、堰板4を、適当数、並設し連結し
た後、上下方向に配置され平面的に見て略一致する取着
された組立金具Kの凹部K’に、図11に示されている
ように、縦端太6aを挿入する。
As described above, one of the wood member B1 constituting the two L-shaped wood member B1 is
Attach the first step weir plates 4a, 4b, 4c, 4d ...
Further, on the first step weir plates 4a, 4b, 4c, 4d, ...
The second weir plate 4'and the third weir plate 4 "are arranged side by side in the horizontal and vertical directions, and the metal fittings K1, K2, K3 are arranged.
Are connected to each other, and then the first step weir plates 4a, 4
b, 4c, 4d ..., Spacers S are attached to the second weir plate 4'and the third weir plate 4 ". Further, two sets of L-shaped pier members B1 are formed. Similarly to the other pier member B1, the first step weir plates 4a, 4b, 4
c, 4d ... are attached, and further the first barrier plates 4a, 4
b, 4c, 4d, etc., a second weir plate 4'and a third weir plate 4 "are arranged in parallel and connected, and the weir plate 4 is attached to the pier 1c constituting the pier member B2. After an appropriate number of side-by-side connections are made and connected, as shown in FIG. Insert.

【0029】次に、図12〜図14を用いて、型枠を補
強するためのフォームタイNについて説明する。
Next, a foam tie N for reinforcing the form will be described with reference to FIGS. 12 to 14.

【0030】フォームタイNは、先端にフランジn1を
有するフランジ付きネジ棒n2と、横端太6bを保持す
るための保持金具n3とを有している。そして、フラン
ジ付きネジ棒n2のフランジn1側の端部には、上述し
たスペーサーSを構成するスペーサー筒体s2のネジ孔
s2’に螺合されたネジ軸s4が螺合可能なネジ孔n
1’が形成されている。また、保持金具n3は、方形状
の金属製板材の両端部を、同じ方向に略垂直に折り曲げ
て形成された係止片n4を有しているとともに、保持金
具n3の中央部n5には、フランジ付きネジ棒n2が挿
入可能な透孔n6が穿設されている。
The foam tie N has a flanged threaded rod n2 having a flange n1 at its tip, and a holding metal fitting n3 for holding the lateral end thick 6b. A screw shaft s4 screwed into the screw hole s2 'of the spacer cylinder s2 constituting the spacer S is screwed into the end of the flanged screw rod n2 on the flange n1 side.
1'is formed. Further, the holding metal fitting n3 has a locking piece n4 formed by bending both ends of a rectangular metal plate material in a substantially vertical direction in the same direction, and at the center portion n5 of the holding metal fitting n3, A through hole n6 into which the flanged screw rod n2 can be inserted is formed.

【0031】一例として、堰板4、4を補強するために
は、組み立てられた堰板4、4に穿設された透孔5から
突き出ている、スペーサー筒体s2のネジ孔s2’に螺
合されたネジ軸s4に、フォームタイNのフランジ付き
ネジ棒n2に形成されたネジ孔n1’を螺合させて、ス
ペーサーSにフランジ付きネジ棒n2を取り付ける。こ
のようにして、補強したい堰板4部分に位置するスペー
サーSに、適当数のフランジ付きネジ棒n2を取り付け
る。次いで、2本の横端太6bを、フランジ付きネジ棒
n2を挟んで水平状態に並設するとともに、保持金具n
3の透孔n6にフランジ付きネジ棒n2を挿通する。こ
の際、保持金具n3の係止片n4が、それぞれ、2本の
横端太6bの上下壁面6b1、6b2に当接するように
構成されている。次いで、フランジ付きネジ棒n2にナ
ットn7を螺合させて、保持金具n3と堰板4に垂直状
に取着された縦端太6aとにより、水平状に並設された
2本の横端太6bを挟持すると同時に、横端太6bによ
り、縦端太6aを、堰板4に押し付ける。このようにし
て、堰板4の支持を更に補強する。なお、横端太6bが
配設された後は、組立金具Kは不用であるので、横端太
6bが配設された後で、生コンクリートが打設される前
に、組立金具Kを取り外すこともできる。
As an example, in order to reinforce the barrier plates 4 and 4, screwing into the screw hole s2 'of the spacer cylinder s2 protruding from the through hole 5 formed in the assembled barrier plates 4 and 4. The combined screw shaft s4 is screwed into the screw hole n1 ′ formed in the flanged screw rod n2 of the form tie N, and the flanged screw rod n2 is attached to the spacer S. In this way, an appropriate number of threaded rods n2 with flanges are attached to the spacer S located at the portion of the dam plate 4 to be reinforced. Next, the two horizontal end thicknesses 6b are horizontally arranged side by side with the flanged screw rod n2 interposed therebetween, and the holding metal fitting n
The threaded rod with flange n2 is inserted into the through hole n6 of No. 3. At this time, the locking pieces n4 of the holding metal fittings n3 are configured to abut the upper and lower wall surfaces 6b1 and 6b2 of the two lateral thick ends 6b, respectively. Then, a nut n7 is screwed onto the threaded rod with flange n2, and two horizontal ends are provided side by side by the holding metal fitting n3 and the vertical end thicker 6a vertically attached to the dam plate 4. At the same time as sandwiching the thick thickness 6b, the vertical thickness 6a is pressed against the dam plate 4 by the lateral thickness 6b. In this way, the support of the barrier plate 4 is further reinforced. Since the assembly fitting K is no longer needed after the horizontal end thickness 6b is provided, the assembly fitting K is removed after the horizontal end thickness 6b is provided and before the fresh concrete is poured. You can also

【0032】図15には、上述したようにして配設され
た縦端太6a間に、更に、追加縦端太6a1が配設され
た例が示されている。一例として、図15には、二段目
の堰板4’と三段目の堰板4”とに跨がるように、組立
金具K4を取着し、該組立金具K4の凹部K’に、追加
縦端太6a1を挿入し、更に、型枠を補強するようにし
た例が示されている。
FIG. 15 shows an example in which an additional vertical end thickness 6a1 is further provided between the vertical end thicknesses 6a arranged as described above. As an example, in FIG. 15, the assembly metal fitting K4 is attached so as to straddle the second weir plate 4 ′ and the third weir plate 4 ″, and is attached to the recess K ′ of the assembly metal fixture K4. , An example in which an additional vertical end thicker 6a1 is inserted and the formwork is further reinforced is shown.

【0033】上述したようにして組み立てられた型枠を
構成する堰板4間に形成された空間に、公知にように、
生コンクリートを充填する。そして、生コンクリートが
硬化した後に、組立金具Kや縦端太6aや横端太6bや
追加縦端太6a1を取り外すとともに、堰板4を除去す
る。
In a space formed between the dam plates 4 constituting the formwork assembled as described above, as is known,
Fill with fresh concrete. Then, after the ready-mixed concrete is hardened, the assembling metal fitting K, the vertical end thickness 6a, the horizontal end thickness 6b, and the additional vertical end thickness 6a1 are removed, and the dam plate 4 is removed.

【0034】上述した堰板4として、木毛や木片や木材
チップ等の木質材料とセメントとからなる木質系セメン
ト板(木毛セメント板や木片セメント板)を使用した場
合には、堰板4間に充填された生コンクリートのセメン
ト液が、木質系セメント板に浸入し、生コンクリートが
硬化した後、木質系セメント板の堰板とコンクリートと
の密着性が良好であるので、コンクリートから、木質系
セメント板の堰板を剥離する必要はない。特に、木質系
セメント板は、ビスや釘等の固着具に対する保持力が大
きし、また、断熱性能や遮音性能が高いので、木質系セ
メント板としての堰板を、そのままにしておくことが好
ましい。
When a wood-based cement board (wood wool cement board or wood chip cement board) composed of wood material such as wood wool, wood chips or wood chips and cement is used as the dam board 4 described above, The cement liquid of the fresh concrete filled in between penetrates into the wood-based cement board, and after the ready-mixed concrete hardens, the weir board of the wood-based cement board and the concrete have good adhesion. It is not necessary to peel off the weir board of the system cement board. In particular, since the wood-based cement board has a large holding power for fasteners such as screws and nails, and also has high heat insulation performance and sound insulation performance, it is preferable to leave the weir board as the wood-based cement board as it is. .

【0035】特に、木質系セメント板としては、木毛セ
メント板を使用することが好ましいく、特に、嵩比重
が、0.7以上である曲げ強度や破壊強度の大きな硬質
木毛セメント板を用いると、ビスや釘等の固着具に対す
る保持力や曲げ強度や剪断強度が著しく向上する。
Particularly, it is preferable to use a wood wool cement board as the wood-based cement board, and in particular, a hard wood wool cement board having a bulk specific gravity of 0.7 or more and having a large bending strength and breaking strength is used. With this, the holding force, the bending strength, and the shear strength with respect to fasteners such as screws and nails are remarkably improved.

【0036】なお、上述した実施例においては、角部を
構成する堰板4a、4aは、堰板4a、4aに取着され
たレベル調整部材H1、H2、H3により、レベル出し
が行われており、また、使用される堰板4は、同一形状
を有しているので、角部を構成する堰板4a、4aに並
設される堰板4b、4c、4d・・・の各堰板4b、4
c、4d・・・に、レベル調整部材Hを取着することな
く、単に、角部を構成する堰板4aと該堰板4aに並設
される堰板4の垂直端面と上端面を揃えれば、充分なレ
ベル出しが行われるので、必ずしも、角部を構成する堰
板4a、4aに並設される堰板4b、4c、4d・・・
の各堰板4b、4c、4d・・・の全部に、レベル調整
部材Hを取着する必要はない。角部を構成する堰板4
a、4aに並設される堰板4b、4c、4d・・・の幾
つかを、それらの垂直端面と上端面を揃えた後、組立金
具Kにより連結し、その後、複数の堰板4b、4c、4
d・・・の1つにレベル調整部材Hを取着し、該レベル
調整部材Hにより、複数の堰板4b、4c、4d・・・
のレベル出しを行うように構成することもできる。
In the above embodiment, the weir plates 4a, 4a forming the corners are leveled by the level adjusting members H1, H2, H3 attached to the weir plates 4a, 4a. Further, since the dam plates 4 used have the same shape, the dam plates 4b, 4c, 4d ... Which are arranged in parallel with the dam plates 4a, 4a forming the corners. 4b, 4
Without attaching the level adjusting member H to c, 4d, and the like, simply align the vertical end face and the upper end face of the dam plate 4a forming the corner portion and the dam plate 4 juxtaposed on the dam plate 4a. For example, since sufficient leveling is performed, weir plates 4b, 4c, 4d ...
It is not necessary to attach the level adjusting member H to all of the barrier plates 4b, 4c, 4d ,. Weir plate 4 forming the corner
a, 4a are arranged side by side, and some of the weir plates 4b, 4c, 4d ... Are aligned with their vertical end faces and upper end faces, and then connected by an assembly metal fitting K, and then a plurality of weir plates 4b, 4c, 4
The level adjusting member H is attached to one of the d ..., and the plurality of barrier plates 4b, 4c, 4d ...
It can also be configured to perform leveling of.

【0037】上述したように、横方向及び縦方向に並設
された堰板4を、コの字状部k1を有する組立金具Kに
より連結するとともに、組立金具Kの凹部K’に、縦端
太6aを挿入し、その後、フォームタイNにより、横端
太6bを配設し、型枠を組み立てるようにしたので、堰
板の4つの周辺に角材を取り付け、その後、堰板を、連
結し、堰板に、縦端太及び横端太に取着するようにした
従来の型枠組み立て方法に比べて、本発明の型枠組み立
て方法においては、堰板4に、角材を取り付ける作業が
不用であるとともに、縦端太6aは、単に、組立金具K
の凹部K’に挿入するだけであるので、型枠の組立作業
に要する時間が短縮化されるとともに、堰板4のコスト
を低減化することができる。
As described above, the weir plates 4 juxtaposed in the horizontal and vertical directions are connected by the assembly metal fitting K having the U-shaped portion k1, and the vertical end is formed in the recess K'of the assembly metal fitting K. Since the thick end 6a is inserted, and the lateral end thick end 6b is then arranged by the form tie N to assemble the formwork, square members are attached around the four barrier plates, and then the barrier plates are connected. Compared to the conventional formwork assembling method in which the vertical and horizontal ends are attached to the weir plate, the work of assembling the lumber to the weir plate 4 is unnecessary in the formwork assembling method of the present invention. In addition, the thick vertical edge 6a is simply
Since it is only inserted into the concave portion K ′, the time required for the work of assembling the mold can be shortened and the cost of the dam plate 4 can be reduced.

【0038】角部を構成する堰板4a、4aに取着され
たレベル調整部材H1、H2、H3を用いて、角部を構
成する堰板4a、4aのレベル出しを行った後、或い
は、桟木部材B2に配設された1つの堰板4に取着され
たレベル調整部材Hを用いて、堰板4のレベル出しを行
った後、角部を構成する堰板4a、4a及び桟木部材B
2に配設された1つの堰板4と、角部を構成する堰板4
a、4a及び桟木部材B2に配設された1つの堰板4に
並設される堰板4とを、それらの垂直端面と上端面を揃
え、組立金具Kにより連結するようにしたので、型枠を
構成する堰板4のレベル出しを正確に行うことができ
る。
After leveling the barrier plates 4a, 4a forming the corners by using the level adjusting members H1, H2, H3 attached to the barrier plates 4a, 4a forming the corners, or After leveling the dam plate 4 by using the level adjusting member H attached to one dam plate 4 arranged on the dam member B2, the dam plates 4a and 4a forming the corners and the dam member B
2, one weir plate 4 and one weir plate 4 forming a corner
a, 4a and the weir plate 4 arranged side by side on the one weir plate 4 disposed on the pier member B2 are arranged so that their vertical end faces and upper end faces are aligned and connected by the assembly metal fitting K. The level of the dam plate 4 forming the frame can be accurately set.

【0039】角部を構成する堰板4a、4aに取着され
たレベル調整部材H1、H2、H3を用いて、角部を構
成する堰板4a、4aのレベル出しを行った後、或い
は、桟木部材B2に配設された1つの堰板4に取着され
たレベル調整部材Hを用いて、堰板4のレベル出しを行
った後、角部を構成する堰板4a、4a及び桟木部材B
2に配設された1つの堰板4と、角部を構成する堰板4
a、4a及び桟木部材B2に配設された1つの堰板4に
並設される堰板4とを、それらの垂直端面と上端面を揃
え、組立金具Kにより連結し、その後、角部を構成する
堰板4a、4a及び桟木部材B2に配設された1つの堰
板4に並設された堰板4に取着されたレベル調整部材H
によりレベル出しを行うようにしたので、型枠を構成す
る堰板4のレベル出しをより正確に行うことができる。
After leveling the dam plates 4a, 4a forming the corners by using the level adjusting members H1, H2, H3 attached to the dam plates 4a, 4a forming the corners, or After leveling the dam plate 4 by using the level adjusting member H attached to one dam plate 4 arranged on the dam member B2, the dam plates 4a and 4a forming the corners and the dam member B
2, one weir plate 4 and one weir plate 4 forming a corner
a, 4a and the weir plate 4 arranged side by side on the one weir plate 4 arranged on the pier member B2, their vertical end faces and upper end faces are aligned and connected by the assembly metal fitting K, and then the corners are The level adjusting members H attached to the weir plates 4 a and 4 a and the one weir plate 4 arranged in parallel with the weir plate 4 that are arranged on the dam member B2.
Since the leveling is performed by the above method, the leveling of the dam plate 4 forming the formwork can be performed more accurately.

【0040】[0040]

【発明の効果】本発明は、以上説明した構成を有してい
るので、以下に記載する効果を奏するものである。
Since the present invention has the constitution described above, it has the following effects.

【0041】堰板の4つの周辺に角材を取り付け、その
後、堰板を連結し、該堰板に、縦端太及び横端太に取着
するようにした従来の型枠組み立て方法に比べて、本発
明の型枠組み立て方法においては、堰板に、角材を取り
付ける作業が不用であるとともに、縦端太は、単に、組
立金具の凹部に挿入するだけであるので、型枠の組立作
業に要する時間が短縮化されるとともに、堰板のコスト
を低減化することができる。
Compared to the conventional formwork assembling method in which square members are attached to the four periphery of the weir plate, and then the weir plates are connected and attached to the weir plate at the vertical and horizontal ends. In the formwork assembling method of the present invention, it is not necessary to attach a square member to the dam plate, and the vertical end thickness is simply inserted into the recess of the assembly fitting. The required time can be shortened and the cost of the barrier plate can be reduced.

【図面の簡単な説明】[Brief description of drawings]

【図1】図1は本発明の型枠組み立て方法において使用
される組立金具の斜視図である。
FIG. 1 is a perspective view of an assembly metal fitting used in a method for assembling a mold according to the present invention.

【図2】図2は本発明の型枠組み立て方法において使用
されるレベル調整部材の斜視図である。
FIG. 2 is a perspective view of a level adjusting member used in the mold assembling method of the present invention.

【図3】図3は本発明の型枠組み立て方法において、一
例としての床スラブ上に配設された桟木の斜視図であ
る。
FIG. 3 is a perspective view of a pier arranged on a floor slab as an example in the method for assembling a mold according to the present invention.

【図4】図4は本発明の型枠組み立て方法における堰板
の組み立て順序を説明するための堰板等の斜視図であ
る。
FIG. 4 is a perspective view of a weir plate or the like for explaining an assembling order of the weir plate in the method for assembling a form according to the present invention.

【図5】図5は同じく本発明の型枠組み立て方法におけ
る堰板の組み立て順序を説明するための堰板等の斜視図
である。
FIG. 5 is a perspective view of a weir plate and the like for explaining the assembling order of the weir plate in the formwork assembling method of the present invention.

【図6】図6は同じく本発明の型枠組み立て方法におけ
る堰板の組み立て順序を説明するための堰板等の斜視図
である。
FIG. 6 is a perspective view of a weir plate and the like for explaining the assembling order of the weir plate in the formwork assembling method of the present invention.

【図7】図7は同じく本発明の型枠組み立て方法におけ
る堰板組み立て順序を説明するための堰板等の一部断面
を含む正面図である。
FIG. 7 is a front view including a partial cross section of a weir plate and the like for explaining the weir plate assembling order in the formwork assembling method of the present invention.

【図8】図8は図7と同様の本発明の型枠組み立て方法
における堰板組み立て順序を説明するための堰板等の一
部断面を含む正面図である。
8 is a front view including a partial cross section of a weir plate and the like for explaining the weir plate assembling sequence in the mold assembling method of the present invention similar to FIG. 7. FIG.

【図9】図9は図7と同様の本発明の型枠組み立て方法
における堰板組み立て順序を説明するための堰板等の一
部断面を含む正面図である。
9 is a front view including a partial cross section of a weir plate and the like for explaining the weir plate assembling order in the mold assembling method of the present invention similar to FIG. 7. FIG.

【図10】図10は堰板間に配置されるスペーサーの分
解斜視図である。
FIG. 10 is an exploded perspective view of a spacer arranged between the dam plates.

【図11】図11は図7と同様の本発明の型枠組み立て
方法における堰板組み立て順序を説明するための堰板等
の一部断面を含む正面図である。
FIG. 11 is a front view including a partial cross section of a weir plate and the like for explaining the weir plate assembling order in the mold assembling method of the present invention similar to FIG. 7.

【図12】図12はスペーサーや分解されたフォームタ
イ等を含む部分斜視図である。
FIG. 12 is a partial perspective view including a spacer, a disassembled foam tie, and the like.

【図13】図13は縦端太やフォームタイが配設された
型枠の斜視図である。
FIG. 13 is a perspective view of a mold having vertical edges and foam ties.

【図14】図14は縦端太や横端太等が配設された型枠
の斜視図である。
FIG. 14 is a perspective view of a mold in which vertical and horizontal thicknesses are arranged.

【図15】図15は縦端太や横端太等が配設された型枠
の別の実施例の堰板等の一部断面を含む正面図である。
FIG. 15 is a front view including a partial cross-section of a dam plate and the like of another embodiment of a formwork in which vertical and horizontal thicknesses are arranged.

【符号の説明】[Explanation of symbols]

H・・・・・・・・・・・レベル調整部材 K・・・・・・・・・・・組立金具 N・・・・・・・・・・・フォームタイ S・・・・・・・・・・・スペーサー 1・・・・・・・・・・・桟木 4・・・・・・・・・・・堰板 H ・ ・ ・ ・ ・ ・ ・ ・ Level adjustment member K ... Assembly metal fittings N: Form tie S ・ ・ ・ ・ ・ ・ ・ ・ Spacer 1 ... 4 ・ ・ ・ ・ ・ ・ ・ Weir board

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】横方向及び縦方向に並設された堰板を、コ
の字状部を有する組立金具により連結するとともに、組
立金具の凹部に、縦端太を挿入し、その後、フォームタ
イにより、横端太を配設して、型枠を組み立てるように
したことを特徴とする型枠組み立て方法。
1. A weir plate, which is arranged side by side in a horizontal direction and a vertical direction, is connected by an assembly fitting having a U-shaped portion, and a vertical end thickness is inserted into a recess of the assembly fitting, and then a foam tie is formed. According to the above method, the lateral edges are arranged to assemble the formwork.
【請求項2】コの字状部と、該コの字状部を形成する平
行板部の端部から、該平行板部に対して垂直に、且つ、
互いに遠ざかる方向に延在する取付板部とからなる前記
型枠組み立て方法に使用される組立金具。
2. A U-shaped portion and an end portion of the parallel plate portion forming the U-shaped portion, perpendicular to the parallel plate portion, and
An assembly metal fitting for use in the above-described method of assembling a frame, which comprises a mounting plate portion extending in a direction away from each other.
JP2001254148A 2001-08-24 2001-08-24 Form assembling method and assembly metal fitting used for it Pending JP2003064868A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001254148A JP2003064868A (en) 2001-08-24 2001-08-24 Form assembling method and assembly metal fitting used for it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001254148A JP2003064868A (en) 2001-08-24 2001-08-24 Form assembling method and assembly metal fitting used for it

Publications (1)

Publication Number Publication Date
JP2003064868A true JP2003064868A (en) 2003-03-05

Family

ID=19082345

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001254148A Pending JP2003064868A (en) 2001-08-24 2001-08-24 Form assembling method and assembly metal fitting used for it

Country Status (1)

Country Link
JP (1) JP2003064868A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101008411B1 (en) * 2010-01-26 2011-01-14 유한회사 네모프리시스템 Panel for built-up form
JP2011012532A (en) * 2009-06-02 2011-01-20 Kajima Corp Form panel, assembling method therefor, and curvature regulation jig for the form panel
KR101109492B1 (en) * 2010-02-22 2012-01-31 안종준 Structure for construction mold of foam panel
KR101139843B1 (en) 2010-03-22 2012-04-30 서갑수 The combination of reinforcement means for mold
KR101139844B1 (en) 2012-01-17 2012-04-30 서갑수 The combination of reinforcement means for mold
KR101144609B1 (en) 2012-01-17 2012-05-11 서갑수 The combination of reinforcement means for mold

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011012532A (en) * 2009-06-02 2011-01-20 Kajima Corp Form panel, assembling method therefor, and curvature regulation jig for the form panel
KR101008411B1 (en) * 2010-01-26 2011-01-14 유한회사 네모프리시스템 Panel for built-up form
WO2011093628A2 (en) * 2010-01-26 2011-08-04 유한회사 네모프리시스템 Prefabricated mold panel
WO2011093628A3 (en) * 2010-01-26 2012-01-05 유한회사 네모프리시스템 Prefabricated mold panel
KR101109492B1 (en) * 2010-02-22 2012-01-31 안종준 Structure for construction mold of foam panel
KR101139843B1 (en) 2010-03-22 2012-04-30 서갑수 The combination of reinforcement means for mold
KR101139844B1 (en) 2012-01-17 2012-04-30 서갑수 The combination of reinforcement means for mold
KR101144609B1 (en) 2012-01-17 2012-05-11 서갑수 The combination of reinforcement means for mold

Similar Documents

Publication Publication Date Title
US7882665B2 (en) Construction configurations and construction methods of steel houses
JP2003064868A (en) Form assembling method and assembly metal fitting used for it
JP7339865B2 (en) How to install wall panels
JP3771177B2 (en) Joining structure of reinforced concrete column and steel column, and joining method thereof
JP7470243B1 (en) Composite beams and methods for constructing composite beams
JPH0754427A (en) Construction method of wall and device thereof
JP2617740B2 (en) Formwork equipment
JPH0318561Y2 (en)
JP2004027501A (en) Wall construction for building
JP7281129B2 (en) Foundation formwork structure
JPS6157732A (en) Construction of multilayered building skeletal by precast reinforced concrete unit
JP2001279924A (en) Method of assembling form
JPH06346471A (en) Construction of reinforced concrete retaining wall by use of large size precast slab
JPS5913621B2 (en) block panel
JP3004605B2 (en) Building panel
JPH1181526A (en) Alc panel for corner and execution method of outer wall
JP3033014U (en) Concrete formwork
JP2001227062A (en) Reinforcement structure of building
CN117966933A (en) Butt-joint prefabricated wallboard
JPH05156804A (en) Independent columnar formwork assembling method
JPS58178745A (en) Mold frame material for use with finishing foundation
KR200249981Y1 (en) A mold panel fix device
JPS60109422A (en) Stabilization work for slope
JP2024092794A (en) Panel-type throw-away formwork for building foundations
JPS5923159Y2 (en) Formwork equipment for manufacturing walls and floor slabs of buildings