JP2003022118A - Production process management device - Google Patents

Production process management device

Info

Publication number
JP2003022118A
JP2003022118A JP2001205600A JP2001205600A JP2003022118A JP 2003022118 A JP2003022118 A JP 2003022118A JP 2001205600 A JP2001205600 A JP 2001205600A JP 2001205600 A JP2001205600 A JP 2001205600A JP 2003022118 A JP2003022118 A JP 2003022118A
Authority
JP
Japan
Prior art keywords
time
vehicle
processes
scheduled
production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001205600A
Other languages
Japanese (ja)
Other versions
JP4734787B2 (en
Inventor
Koichi Nakamura
孝一 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toyota Motor Corp
Original Assignee
Toyota Motor Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyota Motor Corp filed Critical Toyota Motor Corp
Priority to JP2001205600A priority Critical patent/JP4734787B2/en
Publication of JP2003022118A publication Critical patent/JP2003022118A/en
Application granted granted Critical
Publication of JP4734787B2 publication Critical patent/JP4734787B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

PROBLEM TO BE SOLVED: To solve the problem that a worker in the conventional production processes can not properly perform work management since the worker does not know a true target time to make up delay of the production processes. SOLUTION: A vehicle production management part 30 first sets scheduled time of start of construction and scheduled time of completion of the respective processes for the respective vehicles based on vehicle information of vehicles which is scheduled to be produced. The respective processes transmit result time of start of construction of the processes in which the construction is actually started for the respective vehicles to the vehicle production managing part 30 and the vehicle production managing part 30 calculates target time of completion of the processes to complete the respective processes for the respective vehicles based on the result time of start of the construction. The worker of the respective processes can exactly grasp by what time works for the various vehicles is performed by a fact that the scheduled time of start of construction of the processes, the scheduled time of completion of the processes and the target time of completion of the processes for the respective vehicles are outputted to the respective processes.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、製品を生産する工
程を管理する装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus for controlling a process of producing a product.

【0002】[0002]

【従来の技術】車両生産工場では、生産車両の納期を遵
守するために、各車両ごとに細部工程の通過予定時刻が
算出されている。ところが、実際の生産においては、進
捗に遅れや進みが発生する。遅れが発生した場合には、
極力早い段階で検出し、後の工程の作業を急がせること
により遅れを挽回する必要がある。従来の方法では、ボ
ディ部分を作るボディ工程の生産を開始する前に、最終
的な検査工程完了までの各工程通過予定時刻を算出して
いる。この工程通過予定時刻と実際に個々の車両が各工
程を通過した時刻とを比較し、遅れがある場合には、各
工程の作業者は遅れを取り戻すように促されている。
2. Description of the Related Art In a vehicle production plant, a scheduled passage time of a detailed process is calculated for each vehicle in order to comply with the delivery date of the production vehicle. However, in actual production, progress may be delayed or advanced. In case of delay,
It is necessary to detect it as early as possible and recover the delay by rushing the work of the subsequent process. In the conventional method, the scheduled passage time of each process until the final inspection process is completed is calculated before the production of the body process for making the body portion is started. The scheduled passage time is compared with the time when each vehicle actually passed each process, and if there is a delay, the worker of each process is urged to recover the delay.

【0003】[0003]

【発明が解決しようとする課題】設備故障その他の理由
により、車両生産の進捗に大きな遅れが発生した場合に
は、直後の工程だけで遅れを取り戻すことは困難であ
る。そのため、検査工程までの各工程で、遅れを少しず
つ取り戻すことが必要である。この場合には、最初に設
定された通過予定時刻は意味をなさなくなり、各工程ご
との工程を完了する時刻が不明確となる。このため、作
業者は、遅れを取り戻すための真の目標時刻がわからな
いので、作業管理を適切に行うことができなかった。
When a large delay occurs in the progress of vehicle production due to equipment failure or other reasons, it is difficult to recover the delay only in the process immediately after. Therefore, it is necessary to gradually recover the delay in each process up to the inspection process. In this case, the scheduled passage time initially set does not make sense, and the time to complete each process becomes unclear. For this reason, the worker does not know the true target time for catching up the delay, so that the work management cannot be properly performed.

【0004】そこで本発明は、上記の課題を解決するこ
とのできる生産工程管理装置を提供することを目的とす
る。
Therefore, an object of the present invention is to provide a production process control device which can solve the above problems.

【0005】[0005]

【課題を解決するための手段】即ち、本発明は、複数の
要素工程を経て製品を生産する工程を管理する生産工程
管理装置であって、製品について、各要素工程に着手す
る工程着工予定時刻、および各要素工程を完了する工程
完了予定時刻を設定する手段と、製品について、各要素
工程が実際に着手された工程着工実績時刻を取得する手
段と、工程着工実績時刻が工程着工予定時刻よりも遅れ
ている要素工程がある場合に、その要素工程を完了すべ
き工程完了目標時刻を設定する手段と、工程着工予定時
刻および工程完了目標時刻を各要素工程に出力する手段
と、を備える。
That is, the present invention is a production process management apparatus for managing a process for producing a product through a plurality of element processes, and a scheduled process start time for starting each element process for a product. , And a means for setting a scheduled process completion time for completing each element process, a means for acquiring a process start actual time when each element process is actually started for the product, and a process start actual time is more than the process start scheduled time. When there is an element process that is delayed, a means for setting a process completion target time for completing the element process, and a means for outputting the scheduled process start time and the process completion target time to each element process.

【0006】ここで、要素工程とは、たとえば車両の生
産工程でいえば、ボディ工程、塗装工程、艤装工程、お
よび検査工程などである。
Here, the element processes include, for example, a vehicle production process, a body process, a painting process, an outfitting process, and an inspection process.

【0007】工程着工目標時刻は、工程着工実績時刻、
その要素工程に通常要する時間、およびその要素工程を
短縮可能な時間から算出される。
The process start target time is the process start actual time,
It is calculated from the time normally required for the element process and the time during which the element process can be shortened.

【0008】[0008]

【発明の実施の形態】以下、発明の実施の形態を通じて
本発明を説明する。
BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, the present invention will be described through embodiments of the invention.

【0009】図1は、本発明の実施形態に係る生産工程
管理装置10の構成を示すブロック図である。本実施形
態の車両の生産工程は、ボディ工程、塗装工程、艤装工
程、および検査工程からなり、この順に車両の生産工程
が進行する。生産工程管理装置10は、上記各工程にお
ける納期、および進捗状況を管理する。
FIG. 1 is a block diagram showing the configuration of a production process control apparatus 10 according to an embodiment of the present invention. The vehicle production process of this embodiment includes a body process, a painting process, an outfitting process, and an inspection process, and the vehicle production process proceeds in this order. The production process management device 10 manages the delivery date and the progress status in each process.

【0010】生産工程管理装置10は、車両生産情報受
付部20、車両生産管理部30、車両生産情報データベ
ース40、車両生産情報出力部50、および車両通過情
報受付部60を有する。
The production process management device 10 has a vehicle production information reception unit 20, a vehicle production management unit 30, a vehicle production information database 40, a vehicle production information output unit 50, and a vehicle passage information reception unit 60.

【0011】車両生産情報受付部20は、この生産工程
で生産が予定される車両について、車両を識別するため
の車両ID、および車種、色などの仕様に関する情報を
含む車両情報を受け付ける。受け付けた車両情報は、次
の車両生産管理部30に送られる。
The vehicle production information receiving unit 20 receives vehicle information including a vehicle ID for identifying the vehicle and information regarding specifications such as vehicle type and color of the vehicle scheduled to be produced in this production process. The received vehicle information is sent to the next vehicle production management unit 30.

【0012】車両生産管理部30は、車両情報に基づい
て、各車両の生産計画を作成する。これにより、各車両
について、各工程に投入される投入予定時刻、各工程で
の作業を終え搬出される搬出予定時刻等が設定される。
車両生産管理部30で設定された予定時刻等は、車両生
産情報データベース40に書き込まれる。また、車両生
産管理部30は、後述する車両通過情報受付部60か
ら、各車両が各工程を実際に通過したときの時刻を受け
取った場合に、その後の工程の通過予定時刻等を再計算
し、車両生産情報データベース40に書き込む。車両生
産管理部30による、各車両の生産計画の作成について
の詳細は後述する。
The vehicle production management unit 30 creates a production plan for each vehicle based on the vehicle information. As a result, for each vehicle, the scheduled loading time to be loaded into each process, the scheduled shipping time to carry out the work in each process, and the like are set.
The scheduled time set by the vehicle production management unit 30 is written in the vehicle production information database 40. In addition, when the vehicle production management unit 30 receives the time when each vehicle actually passed each process from the vehicle passage information reception unit 60 described later, the vehicle production management unit 30 recalculates the scheduled passage time of the subsequent processes. , Write in the vehicle production information database 40. Details of the production planning of each vehicle by the vehicle production management unit 30 will be described later.

【0013】車両生産情報データベース40は、各車両
ごとについて予定時刻等が記憶された工程予定テーブ
ル、および各工程別の遅れ時間を集計した集計テーブル
を格納する。
The vehicle production information database 40 stores a process schedule table in which scheduled times and the like are stored for each vehicle, and a total table in which delay times for each process are totaled.

【0014】車両生産情報出力部50は、車両生産情報
データベース40から各工程の搬出予定時刻等を読出
し、各工程に送信する。
The vehicle production information output unit 50 reads out the scheduled delivery time of each process from the vehicle production information database 40 and sends it to each process.

【0015】各工程には、車両ごとに、投入予定時刻、
搬出予定時刻、投入実績時刻、搬出目標時刻(1)、搬
出目標時刻(2)などが遅れ表示板、プリンタなどに出
力され、作業者に当該車両の生産遅れ状況を通知する。
In each process, the scheduled time of introduction for each vehicle,
The scheduled delivery time, the actual delivery time, the targeted delivery time (1), the targeted delivery time (2), etc. are output to a delay display plate, a printer, etc., to notify the operator of the production delay status of the vehicle.

【0016】各工程では、各車両についてその工程での
作業を終えたときに、車両を識別する情報とともに、工
程の種別、工程を終えた(通過した)時刻についての情
報を車両通過情報として、車両通過情報受付部60に送
信される。
In each step, when the work of each vehicle is completed, the information for identifying the vehicle, the type of the step, and the time when the step is completed (passed) are used as vehicle passage information. It is transmitted to the vehicle passage information reception unit 60.

【0017】車両通過情報受付部60は、各工程から、
施工に実際に着手した工程着工実績時刻、および施工が
実際に完了した工程完了実績時刻を受け付け、受け付け
た工程着工実績時刻、および工程完了実績時刻を、車両
生産管理部30に送信する。
The vehicle passage information receiving section 60 is provided with
The process start actual time when the construction is actually started and the process completion actual time when the construction is actually completed are received, and the received process start actual time and the process completion actual time are transmitted to the vehicle production management unit 30.

【0018】以下に、車両生産管理部30における生産
計画の作成について説明する。
The production of the production plan in the vehicle production management unit 30 will be described below.

【0019】図2は、車両生産情報データベース40に
含まれる工程予定テーブル100の一例である。この工
程予定テーブル100を参照して、車両生産管理部30
における生産管理を説明する。工程予定テーブル100
には、車両IDに関連付けて、工程名、工程通過標準時
間、工程着工予定時刻、工程完了予定時刻、工程着工実
績時刻、工程完了実績時刻、工程完了目標時刻(1)、
および工程完了目標時刻(2)が格納されている。
FIG. 2 shows an example of the process schedule table 100 included in the vehicle production information database 40. With reference to the process schedule table 100, the vehicle production management unit 30
Production control in. Process schedule table 100
Is associated with the vehicle ID, the process name, the standard process passage time, the scheduled process start time, the scheduled process completion time, the process start actual time, the process complete actual time, the process completion target time (1),
And the process completion target time (2) is stored.

【0020】ここで、「車両ID」とは、車両を識別す
るための情報である。「工程名」とは、各工程の名称で
ある。「工程通過標準時間」とは、各工程の作業に要す
る標準時間(工程を通過するのに要する標準時間)のこ
とである。工程通過標準時間は仕様によって変わり、予
め仕様ごとに設定されている。「工程着工予定時刻」と
は、各車両について所定の工程が着工される予定時刻の
ことである。「工程完了予定時刻」とは、各車両につい
て所定の工程での作業を完了するときの予定時刻のこと
である。工程完了予定時刻は、工程着工予定時刻にその
工程での工程通過標準時間を加算することにより得られ
る。「工程着工実績時刻」とは、各車両について、所定
の工程が実際に着工された時刻である。「工程完了実績
時刻」とは、各車両について、所定の工程が実際に完了
した時刻である。「工程完了目標時刻(1)」とは、所
定の工程での「工程着工実績時刻」にその工程の「工程
通過標準時間」を加算して得られる時刻である。「工程
完了目標時刻(2)」とは、各工程について、遅れを取
り戻すために設定された時刻である。
Here, the "vehicle ID" is information for identifying the vehicle. The “process name” is the name of each process. The “process passing standard time” is the standard time required for the work of each process (the standard time required for passing through the process). The standard process passage time varies depending on the specifications and is preset for each specification. The "scheduled process start time" is a scheduled time when a predetermined process is started for each vehicle. The “process completion scheduled time” is a scheduled time when the work in a predetermined process is completed for each vehicle. The scheduled process completion time is obtained by adding the scheduled process start time to the standard process passage time for the process. The “process start actual time” is the time when a predetermined process is actually started for each vehicle. The “process completion record time” is the time when a predetermined process is actually completed for each vehicle. The “process completion target time (1)” is a time obtained by adding the “process passing standard time” of the process to the “process start actual time” of the predetermined process. The “process completion target time (2)” is a time set to recover the delay for each process.

【0021】まず、生産工程の最初の工程であるボディ
工程について、他の車両について設定された着工予定時
刻を参照(ボディ工程の空き状況を考慮)し、当該車両
についてボディ工程についての工程着工予定時刻が設定
される。続いて、車両情報に含まれる仕様でボディ工程
での作業を行う場合に、予め定められた工程通過標準時
間を工程着工予定時刻に加算することにより、ボディ工
程に対する工程完了予定時刻が得られる。
First, with respect to the body process, which is the first process of the production process, reference is made to the scheduled start time of another vehicle (considering the availability of the body process), and the process start of the body process for the vehicle is scheduled. The time is set. Subsequently, when the work in the body process is performed according to the specifications included in the vehicle information, the predetermined process passage standard time is added to the process start scheduled time to obtain the process completion scheduled time for the body process.

【0022】ボディ工程に続く塗装工程については、塗
装工程の空き状況を鑑みながら、ボディ工程の工程完了
予定時刻以降に、ボディ工程に対する工程着工予定時刻
が設定される。以下、同様に各工程についての工程着工
予定時刻および工程完了予定時刻が設定される。
For the coating process subsequent to the body process, the scheduled process start time for the body process is set after the scheduled process completion time of the body process in consideration of the availability of the coating process. Hereinafter, similarly, a scheduled process start time and a scheduled process completion time for each process are set.

【0023】図2の塗装工程の例では、工程着工予定時
刻が13:00に設定されている。車両ID(000
1)についての、車両情報に含まれる仕様でボディ工程
での作業を行う場合の工程通過標準時間(ここでは、3
時間とする)を工程着工予定時刻(13:00)に加算
することにより、工程完了予定時刻(16:00)が設
定されている。
In the example of the painting process shown in FIG. 2, the scheduled process start time is set to 13:00. Vehicle ID (000
Regarding 1), the process passage standard time (here, 3 when the body process is performed according to the specifications included in the vehicle information)
The scheduled process completion time (16:00) is set by adding (time) to the scheduled process start time (13:00).

【0024】塗装工程に実際に着工した工程着工実績時
刻(ここでは、13:30とする)が取得されると、こ
れに工程通過標準時間を加算することにより、工程完了
目標時刻(1)(16:30)が設定される。工程完了
目標時刻(1)は、塗装工程を工程通過標準時間で生産
した場合の目標時刻である。しかし、このままでは、工
程完了予定時刻に遅れたままになるので、この遅れを取
り戻すべく工程完了目標時刻(2)が別途設定される。
工程完了目標時刻(2)は、各工程について、施工時間
を切り詰めることにより、遅れを取り戻すことができる
時間に基づいて決定される。たとえば、塗装工程につい
ては、15分間の遅れを取り戻すことが可能とした場合
には、工程完了目標時刻(1)(16:30)から15
分を引いた時刻(16:15)が工程完了目標時刻
(2)となる。なお、塗装工程で取り戻すことができな
かった遅れは、後続の艤装工程および検査工程で順次取
り戻すことにより、最終的な納期に間に合うように調整
される。
When the actual process start time (13:30 in this case) at which the coating process is actually started is acquired, the process passing standard time is added to this to obtain the process completion target time (1) ( 16:30) is set. The process completion target time (1) is a target time when the coating process is produced in the process passing standard time. However, if this is left as it is, the process completion target time (2) is set separately in order to recover the delay.
The process completion target time (2) is determined for each process based on the time when the delay can be recovered by cutting down the construction time. For example, in the case of the coating process, if it is possible to recover the delay of 15 minutes, the process completion target time (1) (16:30) to 15
The time when the minutes are subtracted (16:15) becomes the process completion target time (2). Incidentally, the delay that could not be recovered in the painting process is adjusted in time for the final delivery date by sequentially recovering it in the subsequent outfitting process and inspection process.

【0025】このように、塗装工程における工程着工実
績時刻が、工程着工予定時刻から遅れた場合には、工程
着工実績時刻に基づいて工程完了目標時刻(2)が設定
される。この工程完了目標時刻(2)は、塗装工程に送
信され、出力等されることにより、塗装工程の作業者
は、実際の生産工程の進捗状況に応じた工程完了目標時
刻(2)を容易に認知することができ、自工程において
生産工程の遅れを何分取り戻せばよいのかを確実に知る
ことができる。
In this way, when the process start actual time in the coating process is delayed from the process start scheduled time, the process completion target time (2) is set based on the process start actual time. This process completion target time (2) is transmitted to the painting process and output, etc., so that the worker of the painting process can easily set the process completion target time (2) according to the progress status of the actual production process. It is possible to recognize, and it is possible to surely know how many minutes of the delay in the production process should be recovered in the own process.

【0026】また、車両生産管理部30は、工程ごと
に、各車両に対して得られた工程予定テーブル100を
参照し、生産の遅れ状況を集計し、車両生産情報データ
ベース40に記録する。図3は、この生産の遅れ状況の
集計テーブル110の例である。この集計テーブル11
0は、特定の工程について、その工程の生産過程で生じ
た遅れ時間と、該当する車両の台数とを対応づけた表で
ある。その工程の施工過程で生じた遅れ時間は、たとえ
ば、工程着工実績時刻が13:30で、工程完了目標時
刻(2)が16:15のところ、工程完了実績時刻が1
6:30だった場合には、遅れ時間が15分となる。
Further, the vehicle production management unit 30 refers to the process schedule table 100 obtained for each vehicle for each process, collects the production delay situation, and records it in the vehicle production information database 40. FIG. 3 is an example of the aggregation table 110 of the production delay situation. This tabulation table 11
For a specific process, 0 is a table in which the delay time caused in the production process of the process and the number of corresponding vehicles are associated with each other. The delay time caused in the construction process of the process is, for example, the process start actual time is 13:30, the process completion target time (2) is 16:15, and the process complete actual time is 1
If it was 6:30, the delay time would be 15 minutes.

【0027】このように、各生産工程の実績を集計する
ことによって、工程別にどのような遅れが発生している
かが把握でき、生産管理に活用することができる。
As described above, by accumulating the results of each production process, it is possible to grasp what kind of delay has occurred for each process and utilize it for production management.

【0028】[0028]

【発明の効果】上記説明から明らかなように、本発明に
よれば、各生産工程に着手される時刻が、予め予定され
た時刻より遅れた場合にも、各生産工程の作業員は、自
分の作業をいつまでに終えれば良いかという目標を把握
することができる。
As is apparent from the above description, according to the present invention, even if the time when each production process is started is behind the scheduled time, the worker of each production process is Can grasp the goal of when to finish the work of.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本発明の実施形態に係る生産工程管理装置1
0の構成を示すブロック図である。
FIG. 1 is a production process management device 1 according to an embodiment of the present invention.
It is a block diagram which shows the structure of 0.

【図2】 車両生産情報データベース40に含まれる工
程予定テーブル100の一例を示す図である。
FIG. 2 is a diagram showing an example of a process schedule table 100 included in a vehicle production information database 40.

【図3】 生産の遅れ状況の集計テーブル110の例を
示す図である。
FIG. 3 is a diagram showing an example of a summary table 110 of production delay situations.

【符号の説明】[Explanation of symbols]

10 生産工程管理装置、20 車両生産情報受付部、
30 車両生産管理部、40 車両生産情報データベー
ス、50 車両生産情報出力部、60 車両通過情報受
付部、100 工程予定テーブル、110 集計テーブ
ル。
10 production process management device, 20 vehicle production information reception section,
30 vehicle production management section, 40 vehicle production information database, 50 vehicle production information output section, 60 vehicle passage information acceptance section, 100 process schedule table, 110 total table.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 複数の要素工程を経て製品を生産する工
程を管理する生産工程管理装置であって、 製品について、各要素工程に着手する工程着工予定時
刻、および各要素工程を完了する工程完了予定時刻を設
定する手段と、 製品について、各要素工程が実際に着手された工程着工
実績時刻を取得する手段と、 工程着工実績時刻が工程着工予定時刻よりも遅れている
要素工程がある場合に、その要素工程を完了すべき工程
完了目標時刻を設定する手段と、 工程着工予定時刻および工程完了目標時刻を各要素工程
に出力する手段と、 を備えることを特徴とする生産工程管理装置。
1. A production process management apparatus for managing a process for producing a product through a plurality of element processes, the process start scheduled time to start each element process for a product, and the process completion for completing each element process. If there is a means to set the scheduled time, a means to acquire the process start actual time when each element process was actually started for the product, and an element process whose process start actual time is behind the scheduled process start time A production process management apparatus comprising: a unit for setting a process completion target time for completing the element process; and a unit for outputting the process start scheduled time and the process completion target time to each of the element processes.
【請求項2】 工程着工目標時刻は、工程着工実績時
刻、その要素工程に通常要する時間、およびその要素工
程を短縮可能な時間から算出されることを特徴とする請
求項1に記載の生産工程管理装置。
2. The production process according to claim 1, wherein the process start target time is calculated from a process start actual time, a time normally required for the element process, and a time at which the element process can be shortened. Management device.
JP2001205600A 2001-07-06 2001-07-06 Production process management device Expired - Fee Related JP4734787B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001205600A JP4734787B2 (en) 2001-07-06 2001-07-06 Production process management device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001205600A JP4734787B2 (en) 2001-07-06 2001-07-06 Production process management device

Publications (2)

Publication Number Publication Date
JP2003022118A true JP2003022118A (en) 2003-01-24
JP4734787B2 JP4734787B2 (en) 2011-07-27

Family

ID=19041879

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001205600A Expired - Fee Related JP4734787B2 (en) 2001-07-06 2001-07-06 Production process management device

Country Status (1)

Country Link
JP (1) JP4734787B2 (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63156647A (en) * 1986-12-20 1988-06-29 Toyota Motor Corp Working instruction system
JPH06337880A (en) * 1993-05-31 1994-12-06 Tokyo Electric Co Ltd Production management system
JPH07311615A (en) * 1994-05-19 1995-11-28 Nissan Motor Co Ltd Prediction device for operation flow of production line
JPH08315033A (en) * 1995-05-11 1996-11-29 Casio Comput Co Ltd Advancement managing device
JPH11353385A (en) * 1998-06-10 1999-12-24 Toyota Motor Corp Method for planning delivery of product and method for managing production
JP2000001988A (en) * 1998-06-17 2000-01-07 Daiken Trade & Ind Co Ltd Process control supporting device for building construction, and computer-readable recording medium recording process control supporting program for building construction
JP2000056808A (en) * 1998-08-04 2000-02-25 Hitachi Ltd Automatic correction method for schedule management table

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63156647A (en) * 1986-12-20 1988-06-29 Toyota Motor Corp Working instruction system
JPH06337880A (en) * 1993-05-31 1994-12-06 Tokyo Electric Co Ltd Production management system
JPH07311615A (en) * 1994-05-19 1995-11-28 Nissan Motor Co Ltd Prediction device for operation flow of production line
JPH08315033A (en) * 1995-05-11 1996-11-29 Casio Comput Co Ltd Advancement managing device
JPH11353385A (en) * 1998-06-10 1999-12-24 Toyota Motor Corp Method for planning delivery of product and method for managing production
JP2000001988A (en) * 1998-06-17 2000-01-07 Daiken Trade & Ind Co Ltd Process control supporting device for building construction, and computer-readable recording medium recording process control supporting program for building construction
JP2000056808A (en) * 1998-08-04 2000-02-25 Hitachi Ltd Automatic correction method for schedule management table

Also Published As

Publication number Publication date
JP4734787B2 (en) 2011-07-27

Similar Documents

Publication Publication Date Title
US10360740B2 (en) Methods and systems for diagnosing a vehicle using sound
EP3644148B1 (en) Test terminal for tests of an infrastructure of a vehicle
JP2006293755A5 (en)
DE102016124784A1 (en) Manufacturing management device that corrects work process delays of a manufacturing cell
US20140214263A1 (en) Method, device and computer program for assisting the maintenance of an aircraft system using a diagnostic assistance tool and experience feedback data
DE102018216914A1 (en) Spot welding system
JP5347178B2 (en) Production sequence replanning system, production sequence replanning apparatus and method
EP2314424A2 (en) Method and device for controlling a multi-machine system
JP2003022118A (en) Production process management device
US10719640B2 (en) Data analysis apparatus and data analysis method
US20040181325A1 (en) Method for updating an electronic service tool
US6772028B1 (en) Method for processing order changes in a manufacturing system
US20190302733A1 (en) Integrated simulation system having improved operability
JP2004295188A (en) Method for managing production using delivery time expectation
US7162320B2 (en) Assembly line quality control
WO2019145209A1 (en) Apparatus and method for registering and monitoring autonomous vehicles
US20150254582A1 (en) Quality information apparatus and method
KR20230100893A (en) Method and system for recoding and managing vehicle generated data
JP4168639B2 (en) Production progress management system, production progress management method, and production progress management program
CN110490447B (en) Pull type production task regulation and control method, device and equipment
US20190294146A1 (en) System and method for assembling and/or testing articles
US20110015887A1 (en) Method for manufacturing and testing the functionality in manufacturing
US20240135345A1 (en) Platooning assistance device, platooning assistance method, and program
WO2023233796A1 (en) Production management system, production management method, and program
US20050256597A1 (en) Method for transferring production lots for experiment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20071207

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100527

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100608

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100804

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20101019

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20101208

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110111

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110309

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110329

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110411

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140513

Year of fee payment: 3

LAPS Cancellation because of no payment of annual fees