JP2002513877A - Fixing method and device of tip support type for external prestress reinforcement method - Google Patents

Fixing method and device of tip support type for external prestress reinforcement method

Info

Publication number
JP2002513877A
JP2002513877A JP2000547328A JP2000547328A JP2002513877A JP 2002513877 A JP2002513877 A JP 2002513877A JP 2000547328 A JP2000547328 A JP 2000547328A JP 2000547328 A JP2000547328 A JP 2000547328A JP 2002513877 A JP2002513877 A JP 2002513877A
Authority
JP
Japan
Prior art keywords
fixing
fixing plate
plate
tension
tip support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000547328A
Other languages
Japanese (ja)
Inventor
マン ヨプ ハン
Original Assignee
マン ヨプ ハン
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by マン ヨプ ハン filed Critical マン ヨプ ハン
Publication of JP2002513877A publication Critical patent/JP2002513877A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/12Anchoring devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

(57)【要約】 橋梁または橋脚のようなコンクリート構造物のたわみまたはたるみにより亀裂が発生するなど深刻な損傷を受けたコンクリート構造物を補修補強するための外部プレストレス補強工法のための先端支持方式の定着方法及び装置が開始される。本発明では、先端支持方式で外部鋼線の緊張力をガーダ端部に位置した端部板と当接したコンクリートが受けるように、端部板の延長線に突っ張りを設けて突っ張りと端部板との溶接長さを延ばして支持力を増大させることによって先端支持方式の弱い端部溶接部の強度を高める。これにより、少数の短いアンカーボルトを使用できるために原構造物の損傷を避けることができ、端部での溶接長さを確保すれば支持力が増加するので定着板と端部板との角部の応力集中による損傷可能性を縮められる。 (57) [Summary] Tip support for external prestressing reinforcement method to repair and reinforce concrete structures that have been severely damaged such as cracks caused by bending or sagging of concrete structures such as bridges or piers The fixing method and apparatus of the system are started. In the present invention, the extension of the end plate is provided with a tension so that the tension of the external steel wire is received by the concrete in contact with the end plate located at the end of the girder by the tip support method. The strength of the weak end welds of the tip support type is increased by extending the welding length of the end support to increase the supporting force. As a result, damage to the original structure can be avoided because a small number of short anchor bolts can be used, and if the welding length at the end is secured, the supporting force increases, so that the angle between the fixing plate and the end plate is increased. The possibility of damage due to stress concentration in the part is reduced.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【技術分野】【Technical field】

本発明は橋梁または橋脚のようなコンクリート構造物のたわみまたはたるみに
より亀裂が発生するなど深刻に損傷されたコンクリート構造物を補修補強するた
めの外部プレストレス補強工法のための先端支持方式の定着方法及び装置に係り
、より詳細には先端支持方式で外部鋼線の緊張力をガーダ端部に位置した端部板
と当接したコンクリートが受けるように、端部板の延長線に突っ張りを置いて突
っ張りと端部板との溶接長さを延ばして支持力を増大させ、先端支持方式の弱い
端部溶接部の強度を高めた先端支持方式の定着方法及び装置に関する。
The present invention relates to a fixing method of a tip support type for an external pre-stress reinforcement method for repairing and reinforcing a seriously damaged concrete structure such as a bridge or a pier which is cracked due to bending or sagging of the concrete structure. More specifically, a tension is applied to the extension line of the end plate so that the concrete in contact with the end plate located at the end of the girder receives the tension of the external steel wire by the tip support method in more detail. The present invention relates to a fixing method and an apparatus of a tip support system in which a welding length between a strut and an end plate is extended to increase a supporting force and a strength of a weak end weld portion of the tip support system is increased.

【0002】[0002]

【背景技術】[Background Art]

全ての構造物は時間が経つにつれて支持力が弱くなり寿命が短くなる。また産
業の発達と共に橋梁の破損現象が深刻化している。現在多数の橋梁は総重量32
トンに耐えられる2等級橋梁が占めているところ、これら橋梁は橋梁の支持力よ
り大きい車両の通過によって損傷が加速化している。これを防止するためには、
既存橋梁の支持力を増やして総重量43トンに耐えられる1等級橋梁の支持力を
有する橋梁に補強する効率的で経済的な補修補強工法の開発が至急な状態である
Over time, all structures have reduced bearing capacity and reduced life. Also, with the development of industry, the damage phenomenon of bridges has become more serious. Many bridges currently have a total weight of 32
Where tonnes of second-grade bridges occupy, these bridges are being damaged more rapidly by the passage of vehicles than the bridges can support. To prevent this,
The development of an efficient and economical repair and reinforcement method to increase the supporting capacity of existing bridges and reinforce them to bridges having the supporting capacity of first class bridges that can withstand a total weight of 43 tons is urgent.

【0003】 このような問題点を解決するための工法では、床板再施工工法、鋼板補強工法
、及び外部鋼線補強工法などがある。
[0005] Construction methods for solving such problems include a floor plate reconstruction method, a steel plate reinforcement method, and an external steel wire reinforcement method.

【0004】 床板再施工法は、既存橋梁の床板を完全に除去した後高強度コンクリートを用
いた工法であって一部使われているが、床板の再施工に従う莫大な工事コストと
人手及び長い工事期間がかかり、工事期間中車両を完全に統制すべき問題点があ
って現在広く使われない実情である。
The floor slab rebuilding method is a method using high-strength concrete after completely removing the floor slab of an existing bridge, and is partially used. However, the enormous construction cost, manpower, and long time required for rebuilding the floor slab are required. It takes a long period of construction, and there is a problem that the vehicle must be completely controlled during the construction period.

【0005】 そして大部分の橋梁及び橋脚の補強工事に鋼板補強工法が主種をなしてきたが
、最近になって使用材料、施工品質の確保及び維持管理上の問題点などによって
使用例が段々縮まっている。また炭素繊維など高強度の高弾性材料を使用した補
強工法も段々その使用例が増えているが、橋梁への適用例はまだ少ない実情であ
る。
[0005] The steel plate reinforcement method has been the main type of reinforcement work for most bridges and piers. However, recently, examples of use have been gradually increased due to problems in materials used, construction quality assurance and maintenance and management. Shrinking. The use of reinforcing methods using high-strength, high-elastic materials such as carbon fibers has been increasingly used, but there are still few applications to bridges.

【0006】 これに対して外部鋼線を用いた既存構造体の補強工法は、構造体に対する適応
性と補強効率が高くて多様な構造体の補強に活発に用いられている。このような
外部鋼線を用いた工法は、定着具の設置によって大きく4つに分れて実際構造物
の補強においてたくさん用いられているが、このような色々な定着方法には多く
の問題点がある。即ち、不安全であったりだいぶ大きい圧縮力を加えるべきだっ
たり、荷重伝達構造が複雑で定着具の設計が不可能であったりする点である。
[0006] On the other hand, a method of reinforcing an existing structure using an external steel wire has high adaptability to the structure and a high reinforcing efficiency, and is actively used for reinforcing various structures. Such a construction method using an external steel wire is roughly divided into four depending on the installation of a fixing device, and is used a lot in reinforcing a structure in practice. However, such various fixing methods have many problems. There is. That is, it is insecure or a relatively large compressive force should be applied, or the load transmitting structure is complicated and the fixing tool cannot be designed.

【0007】 前記既存の定着具の種類を以下簡単に要約、紹介する。外部プレストレス補強
工法を用いて既存の橋梁を補強することにおいて、外部鋼線の緊張力を構造体に
伝達する方法で色々な方式の定着装置を使用している。
The types of the existing fixing tools are briefly summarized and introduced below. In reinforcing existing bridges using an external prestress reinforcement method, various types of fixing devices are used in a method of transmitting the tension of an external steel wire to a structure.

【0008】 これら定着装置は代表的には剪断支持方式、先端支持方式、摩擦支持方式及び
複合支持方式など4つに区分でき、これら定着方式は定着具の構造と設置位置に
よって荷重伝達概念がだいぶ差を示しており、これに対する施工上の特徴及び長
短所は次の通りである。
These fixing devices can be typically classified into four types, such as a shear support type, a tip support type, a friction support type, and a composite support type. In these fixing types, the concept of load transmission depends on the structure and installation position of the fixing device. The differences are shown, and the construction features and advantages and disadvantages for this are as follows.

【0009】 先ず、剪断支持方式は図1に示したように、PS鋼線17の緊張力Pをアンカー
ボルト13の剪断力Vanで支持する方式であって、緊張力が増加すればアンカー
ボルト13の個数を増やすべきである。
[0009] First, as the shear support type shown in FIG. 1, a method for supporting the tension P of the PS steel wire 17 with a shear force V an, the anchor bolt 13, the anchor bolt if tension is increased Thirteen should be increased.

【0010】 施工順序を調べれば、先ず定着板11を製作し原コンクリートPSコンクリート
ガーダ18に穿孔した後アンカーボルト13を取付けて定着板11を固定する。
その後定着板11とコンクリートとの間をエポキシで充填し、最後に定着具14
、15を設けて鋼線17を緊張させる。
If the order of construction is checked, first, the fixing plate 11 is manufactured and perforated in the original concrete PS concrete girder 18, and then the anchor bolt 13 is attached to fix the fixing plate 11.
Thereafter, the space between the fixing plate 11 and the concrete is filled with epoxy, and finally, the fixing device 14 is filled.
, 15 to tension the steel wire 17.

【0011】 荷重伝達過程は、鋼線管16内の鋼線17を緊張させれば緊張力Pは定着具1
4、15を通じて定着板12と突っ張り10とに加わり、その力は定着板11を
伝わってコンクリートに設けられているアンカーボルト13に到達してアンカー
ボルト13の剪断力Vanにより支持される。
In the load transmission process, if the steel wire 17 in the steel wire tube 16 is tightened, the tension P is fixed to the fixing device 1.
Joined the 10 Brace the fixing plate 12 through 4, 15, the force is supported by the shear force V an, of the anchor bolt 13 reaches the anchor bolt 13 which transmitted the fixing plate 11 is provided in the concrete.

【0012】 この工法は、資材の購入が容易で施工が簡単である長所がある反面に多くの短
所を有している。
This method has an advantage that materials can be easily purchased and construction is simple, but has many disadvantages.

【0013】 第1、アンカーボルトの設置のための穿孔作業時、既存コンクリート構造体の
鋼線17や定着装置などを傷つける恐れが高くて、これによってむしろ原構造物
の支持力を低める。また、PSコンクリートガーダ端部の応力集中部に穿孔による
断面欠損によって端部が破壊される恐れがあり、コンクリート構造体の強度が弱
い場合アンカーボルトが抜かれる恐れがある。これは、アンカーボルトの剪断支
持力の大きさがコンクリート強度の大きさに左右されて品質管理や設計が難しい
という問題点をもたらす。特に既存構造物でコンクリートの強度を推定する適切
な方法がないために強度測定に対する信頼性が非常に落ちる。
First, during the drilling work for installing the anchor bolts, there is a high possibility of damaging the steel wire 17 and the fixing device of the existing concrete structure, thereby lowering the supporting force of the original structure. In addition, there is a possibility that the end portion may be broken due to a cross-sectional defect due to perforation at a stress concentration portion at an end portion of the PS concrete girder, and when the strength of the concrete structure is weak, an anchor bolt may be pulled out. This poses a problem that quality control and design are difficult because the magnitude of the shear supporting force of the anchor bolt depends on the strength of the concrete. In particular, there is no appropriate method for estimating the strength of concrete in existing structures, so the reliability of strength measurement is greatly reduced.

【0014】 第2、第1の短所のため、アンカーボルトの設置の限界に従う導入可能な緊張
力に限界がある。剪断支持方式は緊張力の大部分をアンカーボルトが支持するが
、既存コンクリートガーダを傷つけたりコンクリートの品質が正確に分からない
場合はアンカーボルトの設置を制限するしかない。従って緊張力の導入にも限界
がある。
[0014] The second and first disadvantages limit the amount of tension that can be introduced according to the limitations of anchor bolt installation. In the shear support method, most of the tension is supported by the anchor bolt. However, if the existing concrete girder is damaged or the quality of the concrete is not accurately determined, the installation of the anchor bolt is limited only. Therefore, there is a limit to the introduction of tension.

【0015】 第3、緊張力に対してかかるアンカーボルトの個数が多くて定着具が大きくな
る。アンカーボルトは一定間隔以上を確保した時にかかる剪断力を得られる。も
しボルトの設置間隔が狭い時はそれだけの減少係数を導入してボルトの剪断力を
再び算定すべきである。従って緊張力が大きくなるほど多くのアンカーボルトが
必要になりそれだけの間隔も確保すべきなので定着板が大きくならなければなら
ない。したがってガーダの面積が小さい場合にはこの工法を使用できない。
Third, the number of anchor bolts applied to the tension increases and the size of the fixing device increases. The anchor bolt can obtain the shearing force applied when a certain distance or more is secured. If the spacing of the bolts is small, a corresponding reduction factor should be introduced to recalculate the shear forces of the bolts. Therefore, as the tension increases, more anchor bolts are required, and the spacing between them must be ensured, so that the fixing plate must be larger. Therefore, this method cannot be used when the area of the girder is small.

【0016】 第4、ボルトの支持力はボルトの直径に比例するが、ボルト1個当りの支持力
が2〜3トン以内であって、外部プレストレスに必要な支持力を確保するために
は適正間隔以上をおいて充分の個数のボルトを使用すべきである。これは前述し
た定着板が大きくなることと同じ理由である。
Fourth, the supporting force of the bolt is proportional to the diameter of the bolt, but the supporting force per bolt is within 2 to 3 tons, and in order to secure the supporting force necessary for external prestress, A sufficient number of bolts should be used at appropriate intervals or more. This is the same reason that the above-mentioned fixing plate becomes large.

【0017】 摩擦支持方式は図2に示したように、PS鋼棒29を固定させるボルトを用いて
定着板に大きな圧縮力を加え、この圧縮力による定着板21と原構造物との付着
剪断摩擦力によってPS鋼線27の緊張力Pを支持する方式である。一般に鋼棒2
9は平均40トン程度の緊張力で定着具とPSコンクリートガーダとの間を緊張さ
せる。
In the friction support method, as shown in FIG. 2, a large compressive force is applied to the fixing plate using bolts for fixing the PS steel rod 29, and the adhesive force between the fixing plate 21 and the original structure due to the compressive force is applied. In this method, the tension P of the PS steel wire 27 is supported by the frictional force. Generally steel bar 2
No. 9 tensions the fixing tool and the PS concrete girder with an average tension of about 40 tons.

【0018】 施工順序は、先ず定着板21を製作しPSコンクリートガーダに穿孔して鋼棒2
9を挿入した後定着板21を設ける。定着板21とコンクリートとの空間をエポ
キシで充填する。そして、最後に定着具25を設けて緊張させる。
The working order is as follows. First, the fixing plate 21 is manufactured, and the steel plate 2 is formed by piercing the PS concrete girder.
After inserting the fixing plate 9, the fixing plate 21 is provided. The space between the fixing plate 21 and the concrete is filled with epoxy. Then, finally, the fixing device 25 is provided and tensioned.

【0019】 荷重伝達過程は、鋼線管26内の鋼線27を緊張させれば緊張力Pは他の方式
のように定着板や突っ張りがないので直ちに定着具を固定している定着板に加わ
るが、この力は鋼棒により発生した摩擦力によって支持される。
In the load transmitting process, when the steel wire 27 in the steel wire tube 26 is tightened, the tension P is fixed to the fixing plate immediately fixing the fixing device because there is no fixing plate and no tension as in other systems. In addition, this force is supported by the frictional force generated by the steel bar.

【0020】 この工法の特徴は、先端支持方式で施工不可能なガーダとガーダとの間隔が狭
い場合に施工が可能で外観が良好でサイズが小さいという長所がある。
The feature of this construction method is that the construction is possible when the gap between the girders, which cannot be constructed by the tip support method, is narrow, and the appearance is good and the size is small.

【0021】 反面に短所は第1、PS鋼棒の値段が高くこれを施工するのに専門技術を要する
。定着具が緊張力に耐えられるためにはその大きさに相応する数十トンの圧縮力
を定着板に与えるべきであるが、そのためには鋼棒及びボルトとナットとの特殊
製作が必至で、40トンに達する引張力を与えるためには締め作業また特殊装備
が必要になる。また、ナットを締める時トルクによる計測と締めることによる圧
縮力は、一定の比例関係で増加しないために緊張力に対する正確な圧縮力を計算
できないという短所もある。
On the other hand, the first disadvantage is that the cost of PS steel rods is high and requires specialized skills to construct them. In order for the fixing device to withstand the tension, a compressive force of several tens tons corresponding to its size should be applied to the fixing plate, but special production of steel rods and bolts and nuts is inevitable, Tightening work and special equipment are required to provide a tensile force of up to 40 tons. Further, there is a disadvantage in that an accurate compression force with respect to the tension cannot be calculated because the measurement based on the torque when tightening the nut and the compression force due to the tightening do not increase in a fixed proportional relationship.

【0022】 第2、緊張材の最終定着位置が橋脚まで延びないので定着装置と支持点との応
力分布と安全性に対する検討が必要である。これはたとえ全体的に圧縮力を受け
ている状態でも、引張棒の孔周辺では引張応力の発生や応力歪曲現象が発生でき
るからである。
Second, since the final anchoring position of the tendon does not extend to the pier, it is necessary to study the stress distribution and safety between the anchor and the support point. This is because the generation of tensile stress and the stress distortion phenomenon can occur around the hole of the tensile bar even when the whole is under a compressive force.

【0023】 次に、先端支持方式はPSコンクリートガーダ端部に端部板39と定着板31と
を匸字形態で設けて端部板39と接触するコンクリート面が外部鋼線37の緊張
力を支持する方式である。図3で分かるように、前述された剪断支持方式とは違
って定着板31が小さくなりアンカーボルトの数が少なくなり長さも短くなった
。これは緊張力を端部で受けるからである。
Next, according to the tip support method, an end plate 39 and a fixing plate 31 are provided in a zigzag form at the end of the PS concrete girder, and the concrete surface in contact with the end plate 39 reduces the tension of the external steel wire 37. It is a method to support. As can be seen from FIG. 3, unlike the above-described shearing support method, the fixing plate 31 was small, the number of anchor bolts was small, and the length was short. This is because tension is applied at the ends.

【0024】 施工順序は、先ず定着板31を製作しコンクリートに穿孔してアンカーボルト
33を設けた後、定着板31を設ける。この時アンカーボルトは作業中に定着板
31をもとの位置に固定するためだけなので、剪断支持方式とは違って孔を深く
穿孔する必要はない。その後、端部板39を定着板31と溶接し定着板31と端
部板39との空隙をエポキシで充填する。最後に定着具34、35を設けて鋼線
管36内の鋼線37を緊張させればよい。
The fixing sequence is as follows. First, the fixing plate 31 is manufactured, the anchor bolt 33 is provided by piercing the concrete, and then the fixing plate 31 is provided. At this time, since the anchor bolts are only used to fix the fixing plate 31 to the original position during the work, it is not necessary to drill holes deeply unlike the shear support method. Thereafter, the end plate 39 is welded to the fixing plate 31, and the gap between the fixing plate 31 and the end plate 39 is filled with epoxy. Finally, fixing devices 34 and 35 may be provided to tension the steel wire 37 in the steel wire tube 36.

【0025】 荷重伝達過程は、鋼線37を緊張させれば緊張力Pは剪断支持方式と同じよう
に定着板32(cross anchoring plate)に加わり、その力は突っ張り30及び定
着板31に剪断される。しかしそれ以降の荷重伝達過程は剪断支持方式とは違う
。定着板31に加わった力は定着板31を越えて端部板39に到達し、この力は
最後に端部板に当接したコンクリートガーダfcが支持する。この工法は、荷重伝
達過程で分かるように、緊張力が定着板31を経て端部板39に到達する過程で
図4に示したように、定着板31と端部板39との角部に大きい応力が作用して
溶接部が落ちる危険がいつも存在する。即ち、定着板に緊張力がかかれば端部板
39が変形を起こしながらこれら板の接合部の内側面に引張亀裂が発生して溶接
部を傷つける現象が示される問題点がある。
In the load transmission process, when the steel wire 37 is tensioned, the tension P is applied to the fixing plate 32 (cross anchoring plate) in the same manner as in the shearing support system, and the force is sheared by the tension plate 30 and the fixing plate 31. You. However, the subsequent load transfer process is different from the shear support method. The force applied to the fixing plate 31 reaches the end plate 39 beyond the fixing plate 31, and this force is supported by the concrete girder fc that has finally contacted the end plate. As shown in FIG. 4, in this process, as shown in FIG. 4, in the process in which the tension reaches the end plate 39 via the fixing plate 31, the tension is applied to the corner between the fixing plate 31 and the end plate 39. There is always the danger that the weld will fall off due to high stresses. That is, if a tension is applied to the fixing plate, the end plate 39 is deformed, and a tensile crack is generated on the inner surface of the joint portion of these plates, thereby causing a problem that the welded portion is damaged.

【0026】 この工法は、資材の購入及び施工が簡単で外部鋼線の効果を全ての支間に均等
に与えられる長所がある。
This construction method has an advantage that the purchase and construction of materials are easy, and the effect of the external steel wire can be given evenly to all the spans.

【0027】 反面に短所は、最初のPSコンクリートガーダ端部の角部の溶接部が破壊される
恐れが高い。PSコンクリートガーダの端部は既存の鋼線が密集している部分であ
って応力がだいぶ集中している所で鉄筋がたくさん配筋されているが、端部側に
相当な圧縮力を導入する場合、局部的な破壊現象が発生する恐れが多い。また、
PSコンクリートガーダの端部には緊張装着具の突出を隠すためにリセスブロック
があるが、これは緊張作業完了後一般のセメントモルタルで埋めるようになって
いるが、状態が不良な場合が多いために外部鋼線により相当な圧縮力が作用する
場合には亀裂発生の恐れが多いといえる。亀裂発生の問題を解決するために、コ
ンクリート構造体と端部板そして定着板間の空間にエポキシを用いて充填すべき
である。
On the other hand, the disadvantage is that there is a high possibility that the weld at the corner at the end of the first PS concrete girder is broken. The end of the PS concrete girder is where the existing steel wires are dense and where the stress is quite concentrated and a lot of reinforcing bars are arranged, but a considerable compressive force is introduced to the end side In such a case, a local destruction phenomenon is likely to occur. Also,
There is a recess block at the end of the PS concrete girder to hide the projection of the tension mounting device, but this is filled with general cement mortar after completion of the tensioning work, but the condition is often poor When a considerable compression force acts on the external steel wire, it can be said that cracks are likely to occur. In order to solve the problem of crack initiation, the space between the concrete structure and the end plates and the fixing plate should be filled with epoxy.

【0028】 第二、施工上に制約がありうるという問題点がある。この定着方式はPSコンク
リートガーダの端部に最小限3cm以上の間隔があってこそ適用できるために、PS
コンクリートガーダが連続化していたり間隔が狭い場合には充分の端部板の厚さ
を確保し難い問題点がある。
Second, there is a problem that there may be restrictions on construction. This fixing method can be applied only when there is a minimum gap of 3 cm or more at the end of the PS concrete girder.
When the concrete girder is continuous or at a narrow interval, there is a problem that it is difficult to secure a sufficient end plate thickness.

【0029】 第三、橋梁の挙動を制約するという点である。これは前述した制約を他の側面
で検討したことであるが、PSコンクリートガーダとPSコンクリートガーダとの間
隔は温度の影響による橋梁の伸縮を吸収するようになっているが、この間に定着
のための金物が挿入される場合は結局PSコンクリートガーダの伸縮膨脹のための
空間を縮める結果になる。従って、この工法はガーダ間隔が最小3cm以上の広い
場合にのみ適用できる。
Third, the behavior of the bridge is restricted. This is because the above-mentioned restrictions were examined in other aspects.The spacing between the PS concrete girder and the PS concrete girder is designed to absorb the expansion and contraction of the bridge due to the effect of temperature, but during this period When the hardware is inserted, the space for the expansion and contraction of the PS concrete girder is reduced. Therefore, this method can be applied only when the girder interval is at least 3 cm or more.

【0030】 最後に、剪断支持方式と先端支持方式とを混用した複合支持方式を説明する。
複合支持方式は前述した短所を補完し難いために考案された方法であって、ある
論理的な解決策を提示した方法というよりは、前述した色々な方法を適切に組合
して相互補完作用があることを期待する方法に過ぎないといえる。
Finally, a composite support system in which the shear support system and the tip support system are mixed will be described.
The composite support method is a method devised because it is difficult to compensate for the disadvantages described above. Rather than a method that presents a certain logical solution, the mutual complementation effect is achieved by appropriately combining the various methods described above. It's just a way to expect something.

【0031】 施工順序は、先ず定着板51を製作しアンカーボルト53を設けるための穿孔
を行い、中央側に設けるべき鋼棒53'の場合は既存ガーダにこれを設けられる
孔がある場合にのみ設置が可能で、新たな孔をあけて設けるということはほとん
ど不可能に近いので、実際にはこれを適用できる場合が多くないといえる。アン
カーボルトが設けられた後定着板51と端部板59とを溶着し、最後に定着具5
4、55を設けて鋼線管56内の鋼線57を緊張させる。
The work order is as follows. First, the fixing plate 51 is manufactured, and a hole for providing the anchor bolt 53 is formed. In the case of the steel bar 53 ′ to be provided on the center side, only when the existing girder has a hole for providing the same. Since installation is possible and it is almost impossible to make a new hole, it can be said that this is not often applicable in practice. After the anchor bolts are provided, the fixing plate 51 and the end plate 59 are welded.
4 and 55 are provided to tighten the steel wire 57 in the steel wire tube 56.

【0032】 荷重伝達過程は剪断支持方式と先端支持方式を混合した場合であるので、前述
した2つの方式の荷重伝達過程と類似である。即ち、荷重は突っ張り50、定着
具52を経て端部板59と定着板51とに伝達されるが、荷重伝達過程の最後で
複合支持方式はアンカーボルト53と端部のコンクリート、二つの部分が全て緊
張力Pを受けることだけ違う。
Since the load transmitting process is a case where the shear supporting method and the tip supporting method are mixed, the load transmitting process is similar to the load transmitting process of the above two types. That is, the load is transmitted to the end plate 59 and the fixing plate 51 via the strut 50 and the fixing device 52. At the end of the load transmitting process, the composite support method uses the anchor bolt 53 and the concrete at the end. The only difference is that they all receive tension P.

【0033】 この工法の長所は、色々な定着方法を複合的に使用するので全体的な支持力の
増加を期待できるということであるが、次のような短所がある。
An advantage of this method is that various fixing methods are used in combination, so that an increase in the overall supporting force can be expected. However, there are the following disadvantages.

【0034】 短所としては、第一、いろいろな支持方式が同時に作用することではなく、先
端支持機能をする端部板59が十分に変形された後に定着板51が前方に移動す
ればアンカーボルト53や鋼棒53'に剪断力が作用し始める。これは施工上ア
ンカーボルトの設置のためには定着板のボルト孔がボルトより大きいべきである
ので、1-2mm以内程度の変形が発生する前にはボルトに剪断力が作用しないの
で剪断支持効果が先端支持効果と同時に発生することを期待することは非常に難
しいからである。従って複合的な支持方式はそれぞれの支持力の和に該当する支
持力を有することではなく、各定着機具の支持力が順次に発生することであるた
め、本方法の実際支持力は各方法の支持力の和より大きく減る。従ってこの方法
の定着力を計算する時単純に各方法の支持力を合算することは、支持力を過多計
算して定着装置が破壊される可能性が非常に多い。また各定着方法の荷重分配率
を計算し難いので定着具の設計が不可能に近いといえる。
Disadvantages are that, first, the various support methods do not work at the same time. Instead, if the fixing plate 51 moves forward after the end plate 59 serving as the tip support function is sufficiently deformed, the anchor bolt 53 Shear force begins to act on the steel bar 53 '. This is because the bolt holes in the fixing plate should be larger than the bolts for installation of the anchor bolts in the construction, so no shearing force acts on the bolts before deformation of about 1-2 mm or less occurs, so the shear support effect Is very difficult to expect to occur simultaneously with the tip support effect. Therefore, since the composite support system does not have the support force corresponding to the sum of the respective support forces, but the support force of each fixing device is generated sequentially, the actual support force of the method is the same as that of each method. It is much smaller than the sum of the supporting forces. Therefore, when the fixing force of this method is calculated, simply adding the supporting forces of the respective methods has a great possibility that the fixing device is destroyed due to excessive calculation of the supporting force. In addition, since it is difficult to calculate the load distribution ratio of each fixing method, it can be said that the design of the fixing device is almost impossible.

【0035】 第二、PSコンクリートガーダの移動時に用いられる孔が鋼棒を挿入できない位
置、即ち、ガーダの下端や上端に位置している場合が大部分であるので鋼棒の設
置が不可能な場合が大部分であるといえる。
Second, since the holes used when moving the PS concrete girder cannot be inserted with steel rods, that is, most are located at the lower end or upper end of the girder, it is impossible to install steel rods. The case can be said to be the majority.

【0036】 第三、アンカーボルトの設置によって剪断支持方式の問題点と同じ原構造物を
傷つける恐れがある問題点が存在する。即ち、アンカーボルトによる剪断力を期
待するためにはボルトの埋立て深度が深くなるべきなので、原構造物、特に内部
鋼線や定着装置の損傷は必至であるといえる。
Third, there is a problem that the same original structure as that of the shear support method may be damaged due to the installation of the anchor bolt. That is, in order to expect the shearing force of the anchor bolt, the landfill depth of the bolt should be deep, and it can be said that damage to the original structure, especially the internal steel wire and the fixing device is inevitable.

【0037】 以上説明したように、従来の外部ストレス鋼線を用いた定着技術は端部の角部
に応力集中が発生したり亀裂が発生する問題点がありえ、アンカーボルトの設置
作業が容易でないだけでなく、設置作業時橋梁の主要部材に深刻な損傷を与えや
すい短所がある。また、各部分の荷重分配率を計算し難いために定着具の設計が
非常に難しい問題点がある。
As described above, the fixing technique using the conventional external stressed steel wire may have a problem that stress concentration occurs at an end corner or a crack occurs, and thus the installation work of the anchor bolt is not easy. In addition, there is a disadvantage that the major members of the bridge are likely to be seriously damaged during the installation work. In addition, there is a problem that it is very difficult to calculate the load distribution ratio of each part, so that it is very difficult to design a fixing device.

【0038】[0038]

【発明の開示】DISCLOSURE OF THE INVENTION

本発明が解決しようとする技術的課題は、前述した従来の定着装置の問題点を
解決するために、先端支持方式を改良して、鋼線を緊張させる時定着装置端部の
角部附近で発生する応力集中現象を緩和するように端部板と定着板に突っ張りを
おく方法で定着装置端部の損傷を防止する外部プレストレス補強工法のための先
端支持方式の定着方法及び装置を提供することである。
The technical problem to be solved by the present invention is to solve the above-mentioned problems of the conventional fixing device by improving the tip support method so that when the steel wire is tightened, the vicinity of the corner at the end of the fixing device is improved. Provided is a fixing method and apparatus of a front end supporting type for an external prestress reinforcement method for preventing damage to an end of a fixing device by a method in which an end plate and a fixing plate are stretched so as to reduce a generated stress concentration phenomenon. That is.

【0039】 本発明が解決しようとする他の技術的課題は、定着具の設置作業を容易にし、
狭い空間でも設置が可能で、施工時既存橋梁に与える損傷を最小化する外部プレ
ストレス補強工法のための先端支持方式の定着方法及び装置を提供することであ
る。
Another technical problem to be solved by the present invention is to facilitate the work of installing the fixing device,
An object of the present invention is to provide a fixing method and apparatus of a tip support type for an external prestress reinforcement method which can be installed in a small space and minimize damage to an existing bridge during construction.

【0040】 前記課題を達成するための本発明の外部プレストレス補強工法のための先端支
持方式の定着方法及び装置は、PSコンクリートガーダに定着板を少数のアンカー
ボルトで付着しPSコンクリートガーダの端部に端部板を前記定着板と溶接して付
着し、前記定着板上に定着板を設け定着板に支持された定着具を通じて外部鋼線
を緊張させる外部プレストレス補強工法のための先端支持方式の定着方法及び装
置において、前記端部板の延長線上に少なくとも一枚以上の四角突っ張りを設け
、前記突っ張りと端部板及び定着板との間を溶着する。これにより、既存の先端
支持方式の弱い端部に突っ張りを追加溶接、付着して支持力を増やせる。
In order to achieve the above object, the present invention provides a fixing method and an apparatus of a tip support type for an external prestress reinforcement method, wherein a fixing plate is attached to a PS concrete girder with a small number of anchor bolts, and an end of the PS concrete girder is provided. A tip support for an external prestress reinforcement method in which an end plate is welded to and adhered to the fixing plate, a fixing plate is provided on the fixing plate, and an external steel wire is tensioned through a fixing tool supported by the fixing plate. In the fixing method and apparatus of the type, at least one or more square struts are provided on an extension of the end plate, and the struts are welded to the end plate and the fixing plate. As a result, it is possible to increase the support force by additionally welding and attaching a strut to the weak end of the existing tip support method.

【0041】[0041]

【発明を実施するための最良の態様】BEST MODE FOR CARRYING OUT THE INVENTION

以下、本発明に係る外部プレストレス補強工法のための先端支持方式の定着方
法及び装置の実施例に対して添付した図面を参照してより詳細に説明する。
Hereinafter, an embodiment of a fixing method and an apparatus of a tip support type for an external prestress reinforcement method according to the present invention will be described in more detail with reference to the accompanying drawings.

【0042】 図6は、本発明の外部プレストレス補強工法のための先端支持方式の定着方法
を説明するための平面図であり、図7は図6の正面図である。図6及び図7に示
したように、本発明に係る外部プレストレス補強工法のための先端支持方式の定
着方法は、既存の先端支持方式で鋼線管66内の外部鋼線67の緊張力Pをガー
ダ端部に位置した端部板69と当接したコンクリートが受けるように、端部板6
9の延長線に突っ張り60をおいて突っ張り60と端部板69との溶接長さを延
ばして支持力を増やし先端支持方式の弱い端部溶接部の強度を高め、この部位の
荷重による形状変形を改善させる。この際、図8に示したように、突っ張り60
は定着板61に直角部で少なくとも一枚以上設けられることができる。
FIG. 6 is a plan view for explaining a fixing method of a tip support method for an external prestress reinforcement method of the present invention, and FIG. 7 is a front view of FIG. As shown in FIGS. 6 and 7, the fixing method of the tip support method for the external prestress reinforcement method according to the present invention is based on the tension of the external steel wire 67 in the steel wire tube 66 by the existing tip support method. P is received by the concrete in contact with the end plate 69 located at the end of the girder.
9, the length of the weld between the tension plate 60 and the end plate 69 is increased by increasing the tension of the tension plate 60, the supporting force is increased, and the strength of the weak end weld portion of the tip support system is increased. To improve. At this time, as shown in FIG.
May be provided on the fixing plate 61 at at least one right-angled portion.

【0043】 本発明の外部プレストレス補強工法のための先端支持方式の定着装置は、PSコ
ンクリートガーダ68の端部に端部板69と定着板61とを匸状で設けて端部板
69と接触するコンクリート面が外部鋼線67の緊張力を支持する方式で設計さ
れている。図6で分かるように、前述された既存の先端支持方式とは違って定着
板61と端部板69とに突っ張り60が溶着されて荷重を受けられる溶接長さを
大幅に延ばせる。
The fixing device of the tip support type for the external prestress reinforcement method according to the present invention is provided with an end plate 69 and a fixing plate 61 at the end of a PS concrete girder 68 in a zigzag manner. The contacting concrete surface is designed to support the tension of the external steel wire 67. As can be seen from FIG. 6, unlike the above-mentioned existing tip support method, the tension 60 is welded to the fixing plate 61 and the end plate 69, so that the welding length capable of receiving a load can be greatly extended.

【0044】 施工順序は、先ず定着板61を製作しPSコンクリートガーダ68に穿孔を行っ
て長さの短いアンカーボルト63を設けた後、定着板61を設ける。そして端部
板69をガーダ68の端部に位置させて端部板69と定着板61とを溶接する。
この時、定着板61に溶着されている突っ張り60を端部板69に同時に溶接し
て組立を完了する。次に、定着板61とコンクリートとの間と、端部板69とコ
ンクリートとの間の空隙をエポキシで充填する。ここでエポキシ注入は非常に重
要である。その理由は、緊張力作用時に小さい空隙でもあればその空間でコンク
リートの変形が起きて亀裂が発生できるからである。最後に定着具64、65及
び定着板62を設け鋼線管66内の鋼線67を緊張させれば作業が完了する。本
発明でアンカーボルト63の役割は単に定着板61がエポキシで固くなる前に定
着板61を取る役割だけするために、内部鋼線67の損傷防止のために長さ10
cm以内の短いボルトを使用してもよいことがまた大きい長所である。本発明で鋼
棒を使用しない理由は、既存の複合的な定着方法のように定着装置の端部に鋼棒
を設ける場合はPSコンクリートガーダの運搬孔がガーダの中央部に位置した場合
のみに適用できるが、実際には運搬孔がガーダの下端に位置した場合が大部分で
あり、全くない場合も多いのでこの場合は鋼棒の設置が全く不可能になるからで
ある。
The fixing sequence is as follows. First, the fixing plate 61 is manufactured, the PS concrete girder 68 is pierced to provide the short anchor bolt 63, and then the fixing plate 61 is provided. Then, the end plate 69 is positioned at the end of the girder 68, and the end plate 69 and the fixing plate 61 are welded.
At this time, the tension 60 welded to the fixing plate 61 is simultaneously welded to the end plate 69 to complete the assembly. Next, the space between the fixing plate 61 and the concrete and the space between the end plate 69 and the concrete are filled with epoxy. Here epoxy injection is very important. The reason for this is that even if a small gap is formed during the action of tension, the concrete may be deformed in that space and a crack may be generated. Finally, the fixing devices 64 and 65 and the fixing plate 62 are provided, and the steel wire 67 in the steel wire tube 66 is tensioned to complete the operation. In the present invention, the role of the anchor bolt 63 is to merely take the fixing plate 61 before the fixing plate 61 is hardened by epoxy, and to prevent the inner steel wire 67 from being damaged, the length of the anchor bolt 63 is 10 mm.
It is also a great advantage that you can use short bolts within cm. The reason that the steel rod is not used in the present invention is that when the steel rod is provided at the end of the fixing device as in the existing composite fixing method, only when the transport hole of the PS concrete girder is located at the center of the girder. Although it can be applied, in most cases, the carrying hole is actually located at the lower end of the girder, and in many cases there is no such hole at all, and in this case, it is impossible to install a steel rod at all.

【0045】 この方法の荷重伝達過程は、鋼線67を緊張させれば緊張力Pは剪断支持方式
と同じく定着板62に加わり、その力は突っ張り60、定着板61及び端部板6
0に剪断される。即ち、定着板61に加わった力は定着板61と突っ張り60と
を通じて端部板69に到達し、この力は最後に端部板69に当接したコンクリー
トガーダfcが支持する。本発明は荷重伝達過程で分かるように、緊張力が定着板
61を経て端部板69に到達する過程で図8に示したように、溶接部が長くなる
のでそれだけ支持力が増加し、端部板と定着板との角部で発生する引張応力が減
少する。このような引張応力の減少は引張亀裂の発生可能性を縮められるために
、亀裂の前進に従う定着装置の破壊を防止できる。
In the load transmitting process of this method, when the steel wire 67 is tensioned, the tension P is applied to the fixing plate 62 similarly to the shearing support system, and the force is applied to the tension plate 60, the fixing plate 61 and the end plate 6.
Sheared to zero. That is, the force applied to the fixing plate 61 reaches the end plate 69 through the fixing plate 61 and the strut 60, and this force is supported by the concrete girder fc that has finally contacted the end plate 69. According to the present invention, as can be seen in the load transmission process, as shown in FIG. 8, when the tension reaches the end plate 69 via the fixing plate 61, as shown in FIG. The tensile stress generated at the corner between the component plate and the fixing plate is reduced. Such a decrease in the tensile stress reduces the possibility of the occurrence of a tensile crack, so that it is possible to prevent the fixing device from being destroyed as the crack advances.

【0046】 図8によれば、既存の先端支持方式は、後方向突っ張りの形態が三角形になっ
て端部板と当接する溶接部分が一直線であるが、本発明では突っ張り60の形態
が四角形で端部板69もさらに長くなってこの部分の溶接長さが長くなってそれ
だけの定着装置の支持力が増加する。既存の先端支持方式での定着板と端部板の
当接部分の角部での応力集中を、本発明では端部板69が突っ張り60と共に長
くなりながら端部板69と定着板61の溶接部が分けて受けることによって角部
の引張応力が減少する。
According to FIG. 8, in the existing tip support method, the shape of the rearward strut is triangular and the welded portion in contact with the end plate is straight, but in the present invention, the shape of the strut 60 is square. The length of the end plate 69 is further increased, so that the welding length of this portion is increased, and the supporting force of the fixing device is increased accordingly. In the present invention, the stress concentration at the corner of the abutting portion between the fixing plate and the end plate in the existing tip support method can be reduced by welding the end plate 69 and the fixing plate 61 while the end plate 69 becomes longer together with the tension 60. By receiving the parts separately, the tensile stress at the corners is reduced.

【0047】 前述したように、本発明の外部プレストレス補強工法のための先端支持方式の
定着方法及び装置は、短いアンカーボルト63を使用できるために原構造物内の
鋼線や定着装置などの損傷を避けることができ、端部での溶接長さを確保して定
着力を発揮することであるので設計が可能で、既存の先端支持方式の長所の定着
具をコンパクトにすることができる長所があり、既存の先端支持方式の短所であ
る定着板と端部板との角部の応力集中による定着装置の損傷を減らせる長所があ
る。また溶接部の形状が平面的でないために、定着板との境界部で損傷が発生し
ても、これら亀裂が突っ張りの溶接部まで前進する間の変形が大きく発生するは
ずなので外観上維持管理のための観測が容易になる長所がある。また増加した定
着力は大きい力の緊張力を与えられるということを意味するために、必要時には
再緊張作業によって緊張力を増やせる長所がある。また本方法は資材の購入及び
施工が簡単で、外部鋼線の効果を全ての支間に均等に与えられるという長所があ
る。
As described above, the fixing method and apparatus of the tip support type for the external pre-stress reinforcement method of the present invention can use the short anchor bolts 63, so that the steel wires and the fixing device of the original structure can be used. The advantage is that it can avoid damage, secure the welding length at the end and exert the anchoring force, so it can be designed, and it can make the fixing tool of the existing tip support type compact. There is an advantage that damage to the fixing device due to concentration of stress at the corner between the fixing plate and the end plate, which is a disadvantage of the existing tip support method, can be reduced. Also, since the shape of the weld is not planar, even if damage occurs at the boundary with the fixing plate, these cracks will be greatly deformed while advancing to the strut weld, so maintenance of appearance is important. Has the advantage of making observation easier. Further, since the increased fixing force means that a large tension is applied, there is an advantage that the tension can be increased by re-tensioning when necessary. In addition, this method has an advantage that the purchase and construction of the material are easy, and the effect of the external steel wire can be given equally to all the spans.

【0048】[0048]

【産業上の利用可能性】[Industrial applicability]

本発明の先端支持方式の定着方法及び装置は、外部プレストレス補強工法のた
めに改良された先端支持方式を採用して橋梁や橋脚の補強に使われる。特に、設
置が容易で既存の橋梁及び橋脚への損傷を最小化し、狭い空間でも補強作業が可
能である。
INDUSTRIAL APPLICABILITY The fixing method and apparatus of the tip support method according to the present invention are used for reinforcing a bridge or a pier by adopting an improved tip support method for an external prestress reinforcement method. In particular, it is easy to install, minimizes damage to existing bridges and piers, and can be reinforced in narrow spaces.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 従来の外部プレストレス補強工法のための剪断支持方式の定着方法を説明する
ための平面図である。
FIG. 1 is a plan view for explaining a fixing method of a shear support method for a conventional external prestress reinforcement method.

【図2】 従来の外部プレストレス補強工法のための摩擦支持方式の定着方法を説明する
ための正面図である。
FIG. 2 is a front view for explaining a fixing method of a friction support method for a conventional external prestress reinforcement method.

【図3】 従来の外部プレストレス補強工法のための先端支持方式の定着方法を説明する
ための平面図である。
FIG. 3 is a plan view for explaining a fixing method of a tip support method for a conventional external prestress reinforcement method.

【図4】 図3の端部板と定着板との当接する部分の詳細図である。FIG. 4 is a detailed view of a portion where an end plate and a fixing plate of FIG. 3 are in contact with each other.

【図5】 従来の外部プレストレス補強工法のための剪断支持方式と先端支持方式を全て
採用した複合支持方式の定着方法を説明するための平面図である。
FIG. 5 is a plan view for explaining a fixing method of a composite support method employing both a shear support method and a tip support method for a conventional external prestress reinforcement method.

【図6】 本発明の外部プレストレス補強工法を用いた先端支持方式の定着方法を説明す
るための平面図である。
FIG. 6 is a plan view for explaining a fixing method of a front end supporting method using the external prestress reinforcement method of the present invention.

【図7】 図6の正面図である。FIG. 7 is a front view of FIG. 6;

【図8】 図6の先端支持方式による溶接部の詳細図である。FIG. 8 is a detailed view of a welded portion according to the tip support method of FIG.

───────────────────────────────────────────────────── フロントページの続き (81)指定国 EP(AT,BE,CH,CY, DE,DK,ES,FI,FR,GB,GR,IE,I T,LU,MC,NL,PT,SE),OA(BF,BJ ,CF,CG,CI,CM,GA,GN,GW,ML, MR,NE,SN,TD,TG),AP(GH,GM,K E,LS,MW,SD,SL,SZ,UG,ZW),E A(AM,AZ,BY,KG,KZ,MD,RU,TJ ,TM),AL,AM,AT,AU,AZ,BA,BB ,BG,BR,BY,CA,CH,CN,CU,CZ, DE,DK,EE,ES,FI,GB,GD,GE,G H,GM,HR,HU,ID,IL,IN,IS,JP ,KE,KG,KP,KZ,LC,LK,LR,LS, LT,LU,LV,MD,MG,MK,MN,MW,M X,NO,NZ,PL,PT,RO,RU,SD,SE ,SG,SI,SK,SL,TJ,TM,TR,TT, UA,UG,US,UZ,VN,YU,ZW Fターム(参考) 2D059 BB39 CC02 GG40 2E163 DA02 FA12 FD03 FD12 FD25 FD43 FF12 2E164 AA02 AA13 AA31 BA12 DA01 DA03 DA12 DA22 ──────────────────────────────────────────────────続 き Continuation of front page (81) Designated country EP (AT, BE, CH, CY, DE, DK, ES, FI, FR, GB, GR, IE, IT, LU, MC, NL, PT, SE ), OA (BF, BJ, CF, CG, CI, CM, GA, GN, GW, ML, MR, NE, SN, TD, TG), AP (GH, GM, KE, LS, MW, SD, SL, SZ, UG, ZW), EA (AM, AZ, BY, KG, KZ, MD, RU, TJ, TM), AL, AM, AT, AU, AZ, BA, BB, BG, BR, BY , CA, CH, CN, CU, CZ, DE, DK, EE, ES, FI, GB, GD, GE, GH, GM, HR, HU, ID, IL, IN, IS, JP , KE, KG, KP, KZ, LC, LK, LR, LS, LT, LU, LV, MD, MG, MK, MN, MW, MX, NO, NZ, PL, PT, RO, RU, SD, SE, SG, SI, SK, SL, TJ, TM, TR, TT, UA, UG, US, UZ, VN, YU, ZWF Term (reference) 2D059 BB39 CC02 GG40 2E163 DA02 FA12 FD03 FD12 FD25 FD43 FF12 2E164 AA02 AA13 AA31 BA12 DA01 DA03 DA12 DA22

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 PSコンクリートガーダに定着板をアンカーボルトで付着しPS
コンクリートガーダの端部に端部板を前記定着板と溶着し、前記定着板上に定着
板を設け定着板に支持された定着具を通じて外部鋼線を緊張させる外部プレスト
レス補強工法のための先端支持方式の定着方法及び装置において、 前記端部板の延長線上に少なくとも一枚以上の四角突っ張りを設け、前記突っ
張りと端部板及び定着板との間を溶接して付着することを特徴とする外部プレス
トレス補強工法のための先端支持方式の定着方法。
1. A fixing plate is attached to a PS concrete girder with an anchor bolt, and the PS
A tip for an external prestress reinforcement method in which an end plate is welded to an end of a concrete girder and the fixing plate, and a fixing plate is provided on the fixing plate and an external steel wire is tensioned through a fixing device supported by the fixing plate. In the supporting method and the fixing method, at least one square strut is provided on an extension of the end plate, and the strut and the end plate and the fixing plate are welded and adhered. Fixing method of tip support method for external prestress reinforcement method.
【請求項2】 PSコンクリートガーダに定着板をアンカーボルトで付着しPS
コンクリートガーダの端部に端部板を前記定着板と溶着し、前記定着板上に定着
板を設け定着板に支持された定着具を通じて外部鋼線を緊張させる外部プレスト
レス補強工法のための先端支持方式の定着方法及び装置において、 前記端部板の延長線上に少なくとも一枚以上の四角突っ張りを設け、前記突っ
張りと端部板及び定着板との間を溶着することを特徴とする外部プレストレス補
強工法のための先端支持方式の定着装置。
2. Fixing plate is attached to PS concrete girder with anchor bolts
A tip for an external prestress reinforcement method in which an end plate is welded to an end of a concrete girder and the fixing plate, and a fixing plate is provided on the fixing plate and an external steel wire is tensioned through a fixing device supported by the fixing plate. An external prestress, wherein at least one or more square struts are provided on an extension of the end plate, and the strut is welded between the end plate and the fixing plate. Fixing device of tip support type for reinforcement method.
JP2000547328A 1998-05-07 1999-05-07 Fixing method and device of tip support type for external prestress reinforcement method Pending JP2002513877A (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
KR1998/16293 1998-05-07
KR1019980016293A KR100265697B1 (en) 1998-05-07 1998-05-07 Anchoring method and apparatus for improving end bearing structure in external prestress reinforcement
PCT/KR1999/000219 WO1999057390A2 (en) 1998-05-07 1999-05-07 Anchoring method and apparatus in a prestress reinforcement

Publications (1)

Publication Number Publication Date
JP2002513877A true JP2002513877A (en) 2002-05-14

Family

ID=19537099

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000547328A Pending JP2002513877A (en) 1998-05-07 1999-05-07 Fixing method and device of tip support type for external prestress reinforcement method

Country Status (6)

Country Link
EP (1) EP1076742A2 (en)
JP (1) JP2002513877A (en)
KR (1) KR100265697B1 (en)
CN (1) CN1302346A (en)
AU (1) AU3734099A (en)
WO (1) WO1999057390A2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005048586A (en) * 2003-07-28 2005-02-24 Freyssinet Internatl Stup Method for structural reinforcement, and related fixing unit
CN104533105A (en) * 2014-12-24 2015-04-22 宋双阳 Steel-encased reinforcing column pre-tension device
CN106499211A (en) * 2016-11-29 2017-03-15 中国电建集团成都勘测设计研究院有限公司 Newly-increased outrigger framework Baogang anchor traction therapy structure and technique

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100384772B1 (en) * 2000-07-15 2003-05-27 우경건설 주식회사 External prestressing device for tension distribution of continuous bridge
KR100554026B1 (en) * 2000-07-18 2006-02-24 주식회사 인터컨스텍 Open-type steel wire holding device of bridge
KR20010044745A (en) * 2001-03-21 2001-06-05 강창구 A Steel Beam Adapted Prestress in Web Width of Steel Beam Using H-beam or I-beam and Method of Fabricating the same
KR100440622B1 (en) * 2001-08-10 2004-07-21 박재만 Construction method and apparatus for enforcement of bridge beam
CN1300416C (en) * 2004-06-25 2007-02-14 林新 Single slurry molding process for tendon
KR100656284B1 (en) * 2005-01-24 2006-12-11 주식회사 한기엔지니어링건축사사무소 Anchoring structure of external wire for tension and shear reinforcement, and method for reinforcing a building thereof
KR100656286B1 (en) * 2005-02-21 2006-12-11 주식회사 한기엔지니어링건축사사무소 Anchoring structure of external wire for tension and shear reinforcement
CN102409681B (en) * 2011-08-02 2013-10-02 浙江华铁建筑安全科技股份有限公司 Double top seat single-head movable end
CN103147412B (en) * 2013-03-22 2016-08-17 武汉大学 A kind of carbon fibre bar external prestressing stretching and anchoring device and anchoring process
CN103967289B (en) * 2014-04-23 2016-01-13 江苏建研建设工程质量安全鉴定有限公司 A kind ofly be applicable to the bar planting method and the bar planting structure that improve anchoring bearing capacity after plain concrete
CN106193604B (en) * 2016-07-18 2018-12-21 广州建筑股份有限公司 For the stabilization construction method in the sliding of large steel net shell structure
CN106193643B (en) * 2016-07-20 2019-03-12 东南大学 A kind of Prestressed CFRP plate stretching and anchoring device of reinforcing steel beam and combination beam
CN106192780B (en) * 2016-08-31 2018-06-08 刘平原 Self-locking tensioning equipment is layered for the multiaxis of composite material
CN106481021A (en) * 2016-12-16 2017-03-08 福州大学 A kind of prestress combined beam structure and its construction method
CN107654085B (en) * 2017-09-20 2019-11-01 浙江剑锋加固工程有限公司 A method of reinforcing H-shaped girder steel and multispan continuous purline
KR101917812B1 (en) * 2018-04-03 2019-01-23 에스오씨기술지주 주식회사 Outer steel wire fixing part and construction method thereof
WO2021032176A1 (en) * 2019-08-21 2021-02-25 杭州钜力锚杆科技有限公司 Self-locking anchorage device with low stress loss and low retraction

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3371909A (en) * 1966-11-23 1968-03-05 F M Stinton Inc Hydraulic apparatus for applying tension to cables
US3647184A (en) * 1969-11-25 1972-03-07 William L Vanderhurst Apparatus for tensioning tendons
GB1431088A (en) * 1972-04-06 1976-04-07 Wey J A Joint structure including two preformed reinforced structural elements
JP2579577B2 (en) * 1992-05-21 1997-02-05 オリエンタル建設株式会社 Method of introducing prestress into concrete member using hollow PC steel rod

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005048586A (en) * 2003-07-28 2005-02-24 Freyssinet Internatl Stup Method for structural reinforcement, and related fixing unit
JP4563747B2 (en) * 2003-07-28 2010-10-13 フレシネ Method for reinforcing a structure and associated fixing unit
CN104533105A (en) * 2014-12-24 2015-04-22 宋双阳 Steel-encased reinforcing column pre-tension device
CN106499211A (en) * 2016-11-29 2017-03-15 中国电建集团成都勘测设计研究院有限公司 Newly-increased outrigger framework Baogang anchor traction therapy structure and technique

Also Published As

Publication number Publication date
WO1999057390A3 (en) 2000-08-03
KR19990084496A (en) 1999-12-06
EP1076742A2 (en) 2001-02-21
AU3734099A (en) 1999-11-23
WO1999057390A2 (en) 1999-11-11
CN1302346A (en) 2001-07-04
KR100265697B1 (en) 2000-09-15

Similar Documents

Publication Publication Date Title
JP2002513877A (en) Fixing method and device of tip support type for external prestress reinforcement method
Badie et al. Large shear studs for composite action in steel bridge girders
Engindeniz et al. Repair and strengthening of reinforced concrete beam-column joints: State of the art
CN104847129A (en) Method for constructing fastening device of reinforced concrete girder and floor slab
JP2759755B2 (en) Prestressed bridge reinforcement method using lower cable
JP2001220712A (en) Pre-fabricated steel base plate girder and connecting structure of the same
US20120222375A1 (en) Method to Compress Prefabricated Deck Units by Tensioning Elements at Intermediate Supports
JP6444912B2 (en) Steel structure reinforcement and repair structure and method
CN110469140B (en) Construction method for prestress reinforcement of frame beam
JPH04285247A (en) Member for introducing prestress and method of introducing prestress
CN112012112B (en) Construction method for asynchronous cradle of corrugated steel web cast-in-place cantilever box girder
JP7186670B2 (en) Concrete floor slab repair method
CN107558733B (en) The construction method of post-concreted expansion strip lower die frame system dismounting synchronous with periphery support for shuttering
KR100426611B1 (en) Connecting device for enhancing steel wire for a bridge
KR100370177B1 (en) Compression bracket for external prestressing reinforcement of girder
JP2002332645A (en) Foundation structure of rail for ground-traveling crane and laying method for foundation
JP2533830B2 (en) Girder section stress improvement method
CN111809498A (en) Beam bridge combined structure of inverted groove-shaped steel-concrete bridge deck and construction method thereof
CN115125855B (en) Anti-seismic auxiliary structure for continuous beam and construction method thereof
JP2003064621A (en) Hanging floor slab bridge and reinforcing method of hanging floor slab
JPH08253912A (en) Bride structure
CN216108142U (en) Shearing-resistant reinforcing device for hollow plate girder
CN220394322U (en) Anchor cable buckling device for combined beam cable-stayed bridge no-cable area no-bracket construction
Mungur et al. A Comparative Analysis on the Methods of Strengthening Isolated Reinforced Concrete Columns
JP2003049487A (en) Connection structure between steel member and concrete member