JP2002294607A - Ballast exchanging system - Google Patents

Ballast exchanging system

Info

Publication number
JP2002294607A
JP2002294607A JP2001092557A JP2001092557A JP2002294607A JP 2002294607 A JP2002294607 A JP 2002294607A JP 2001092557 A JP2001092557 A JP 2001092557A JP 2001092557 A JP2001092557 A JP 2001092557A JP 2002294607 A JP2002294607 A JP 2002294607A
Authority
JP
Japan
Prior art keywords
ballast
vehicle
train
speed
loading
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001092557A
Other languages
Japanese (ja)
Other versions
JP4664515B2 (en
Inventor
Masayuki Tanaka
政之 田中
Takashi Miyamoto
隆司 宮本
Akira Tamai
章 玉井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NIPPON KIKAI HOSEN KK
Mitsubishi Heavy Industries Ltd
Central Japan Railway Co
Original Assignee
NIPPON KIKAI HOSEN KK
Mitsubishi Heavy Industries Ltd
Central Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NIPPON KIKAI HOSEN KK, Mitsubishi Heavy Industries Ltd, Central Japan Railway Co filed Critical NIPPON KIKAI HOSEN KK
Priority to JP2001092557A priority Critical patent/JP4664515B2/en
Publication of JP2002294607A publication Critical patent/JP2002294607A/en
Application granted granted Critical
Publication of JP4664515B2 publication Critical patent/JP4664515B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a ballast exchanging vehicle system for smoothing the operation of a scraping device, if subjected to load change on the side of a ballast working vehicle, without requiring experienced skills. SOLUTION: The ballast exchanging system for exchanging ballast placed on the lower faces of sleepers supporting rails comprises a first organized vehicle including a plurality of ballast loaded vehicles adapted to travel along the rails and loaded with exchanging ballast and a track driven vehicle adapted to travel at a predetermined control speed in connection with the ballast loaded vehicle, a second organized vehicle including a ballast working vehicle having ballast scraping means and using self-advancing means in travelling in proximity to the first organized vehicle in a non-connected condition, and a sensor for sensing a relative speed between the first organized vehicle and the second organized vehicle, the travelling speed of at least one organized vehicle being controllable in accordance with signals from the sensor. The sensor is a speed sensor or a distance sensor for measuring a time-sequence vehicle-to-vehicle distance between both organized vehicles.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は鉄道の軌道保線工事
における道床交換システムに係り、特にレールを支える
枕木の下に敷設されたバラストを交換するシステムに関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a track bed replacement system in railway track maintenance work, and more particularly to a system for replacing a ballast laid under a sleeper supporting a rail.

【0002】[0002]

【従来の技術】レールを支える枕木の下に敷設されたバ
ラストを交換する方法として、従来より、2つの線路を
使った作業方式が提案されている。かかる方式は旧バラ
ストを掻き取るための第1の作業列車と、新バラストを
積載した第3の作業列車とは同一の線路に待機させてい
るが、掻き取った旧バラストを積み込むための第2の作
業列車は、隣り合う他の線路上に待機している。そして
かかる方式においては、第1の作業列車で、旧バラスト
を掻き取搬出コンベアから第2の搬出コンベアを介して
隣の線路に待機している第2の作業列車に向けて搬出さ
れる。一方第3の作業列車は、第1の作業列車による旧
バラストの掻き取り作業が終了した後に掘削部分に移動
し、新バラストを掘削部分に投入する。しかしながらか
かる従来作業方法によると、第1の作業列車で掻き取っ
た旧バラストを隣の線路に待機している第2の作業列車
にに積み込んでいるので、2つの線路を閉塞して作業を
行う必要があり、鉄道車両の運行に支障を来すことがあ
り得る。また、第1ないし第3の作業列車を個々に運行
しなくてはならないので、旧バラストの交換作業そのも
のが大規模なものとなるとともに、多くの人員を必要と
し、費用的な面で問題が残る。
2. Description of the Related Art As a method of replacing a ballast laid under a sleeper supporting a rail, a work method using two tracks has been conventionally proposed. In this method, the first work train for scraping the old ballast and the third work train loaded with the new ballast are on standby on the same track, but the second work train for loading the scraped old ballast is used. 'S work train is waiting on another adjacent track. In this method, the old work ballast is scraped off by the first work train and is carried out from the carry-out conveyor to the second work train waiting on the adjacent track via the second carry-out conveyor. On the other hand, the third work train moves to the excavated portion after the scraping work of the old ballast by the first work train is completed, and throws the new ballast into the excavated portion. However, according to such a conventional work method, the old ballast scraped off by the first work train is loaded on the second work train waiting on the adjacent track, so that the work is performed with the two tracks closed. It may be necessary and may hinder the operation of railway vehicles. In addition, since the first to third work trains must be operated individually, the replacement work of the old ballast itself becomes large-scale, requires a large number of personnel, and poses a problem in terms of cost. Remains.

【0003】かかる欠点を解消するために、一つの線路
を有効に使った作業方式が提案されている。旧バラスト
を掻き取り且つ積み込むための第1の作業列車と、新バ
ラストを積載した第2の作業列車とが夫々一つの編成と
なってバラスト交換を行う同一の線路上に待機し、先
ず、第1の作業列車で旧バラストを掻き取って積み込む
んだ後、新バラストを積載した第2の作業列車2が、旧
バラスト掻き取り作業が終了した線路上の掘削部分に移
動して新バラストを交換する方法が提案されている。
[0003] In order to solve such a drawback, there has been proposed a work system that effectively uses one line. A first work train for scraping and loading the old ballast and a second work train loaded with the new ballast are each formed as a single train and wait on the same track for ballast exchange. After scraping the old ballast and loading it with the first work train, the second work train 2 loaded with the new ballast moves to the excavated part on the track where the old ballast scraping work has been completed and replaces the new ballast A way to do that has been proposed.

【0004】しかしながらかかる従来作業方法において
も、バラストを掻き取って積み込むための第1の作業列
車と、交換すべき新たなバラストを積載した第2の作業
列車との2つの列車を夫々独立して編成しなければなら
ず、言い換えればこれら第1および第2の作業列車を個
々に独立して運行しなくてはならない。このため、尚、
バラストの交換作業に多くの人員を必要とし、資用が嵩
むといった問題があった。
However, in the conventional working method, two trains, a first working train for scraping and loading a ballast and a second working train for loading a new ballast to be replaced, are independently provided. They must be knitted, in other words, these first and second work trains must be operated individually and independently. For this reason,
Ballast replacement requires a large number of personnel, and is expensive.

【0005】また、新バラストを積載した第2の作業列
車は、第1の作業列車によるバラストの掻き取り作業が
終了した後に線路上の掘削部分に移動するため、これら
第1および第2の作業列車の入れ換えに時間がかかり、
バラスト交換に要する作業時間が長くなるといった不具
合がある。
Further, the second work train loaded with the new ballast moves to the excavated portion on the track after the ballast scraping work by the first work train is completed. It takes time to change trains,
There is a problem that the work time required for ballast replacement becomes long.

【0006】かかる欠点を解消するために、本発明者は
先にバラストを掻き取って積み込むための第1の作業列
車と、交換すべき新たなバラストを積載した第2の作業
列車とを一体的に一つの作業車に連結した一編成のバラ
スト交換列車を提案している。(出願番号:特願平11
−259033号、非公知)
In order to solve such a drawback, the inventor of the present invention has integrated a first work train for scraping and loading a ballast and a second work train for loading a new ballast to be replaced. Has proposed a single ballast exchange train connected to one work vehicle. (Application No .: Japanese Patent Application No. Hei 11)
(No.-259033, unknown)

【0007】図2は、先の発明に係るバラストを交換す
る際に使用するーつの編成からなる作業編成列車5を概
略的に示しているもので、この作業編成列車5は、バラ
ストを掻取り投入するバラスト作業車1と、バラストバ
ラスト積載車としての五両のホッパ車5a〜5eと、こ
れらバラスト作業車1やホッパ車5a〜5eを牽引する
ニ両の軌道駆動車9a、9bとで構成され、これらは全
て連結器11a〜11gにより連結されている。又駆動
車9a側の最前部ホッパ車5eには新バラスト10は堆
積されていない。
FIG. 2 schematically shows a work train 5 consisting of two trains used for exchanging ballasts according to the above-mentioned invention. A ballast work vehicle 1 to be loaded, five hopper vehicles 5a to 5e as ballast ballast loading vehicles, and two track driving vehicles 9a and 9b tow the ballast work vehicle 1 and the hopper vehicles 5a to 5e. These are all connected by connectors 11a to 11g. Further, no new ballast 10 is deposited on the frontmost hopper wheel 5e on the side of the driving wheel 9a.

【0008】最後部に連結されているバラスト作業車1
は、車体後部に据え付けられているバラスト掻取装置2
と、掻き取ったバラストを搬出手段としての搬出コンベ
ア3とを装備している。バラスト掻取装置2は、従来の
バラスト掻き取り装置と同様の構成を有するため、その
詳細な説明を省略する。
[0008] Ballast work vehicle 1 connected to the rearmost part
Is a ballast scraping device 2 installed at the rear of the vehicle
And a carry-out conveyor 3 as a means for carrying out the scraped ballast. Since the ballast scraping device 2 has the same configuration as the conventional ballast scraping device, detailed description thereof will be omitted.

【0009】バラスト掻き取り装置2によって掻き取ら
れたバラストは、搬出コンベア3を介してバラスト作業
車1の車体上部より、第1のホッパ車5a上部のベルト
コンベア7aに搬出され、以下、ホッパ車5b…上部の
ベルトコンベア7b…を順次経由して最前部のからのホ
ッパ車5eに移載される。
The ballast scraped by the ballast scraping device 2 is carried out from the upper part of the body of the ballast work vehicle 1 via the carry-out conveyor 3 to the belt conveyor 7a above the first hopper car 5a. 5b are sequentially transferred via the upper belt conveyor 7b to the hopper wheel 5e from the forefront.

【0010】一方、旧バラストの掻き取りと同時に、最
後部のホッパ車5aに積載されている新バラスト10が
ホッパ車5a荷台下方に設けた第2及び第3のベルトコ
ンベア8a、6aを介して、バラスト作業車1の投入コ
ンベア4に移送し、投入コンベア4を介して旧バラスト
を掻き取った跡の掘削部分に新バラスト10が投入され
る。前記投入と並行して最後部より2段目のホッパ車5
bに積載されている新バラスト10が第2のベルトコン
ベア8bおよび第3のベルトコンベア6bを介して最後
部のホッパ車5aに移載され、以下順次第2のベルトコ
ンベア8c…および第3のベルトコンベア6c…を介し
て順次ホッパ車5d→ホッパ車5c→ホッパ車5bに最
後部のホッパ車5aに移載される。この間、掻取り後の
バラストは最後部のホッパ車5eに堆積が行われている
が、最後部のホッパ車5eが満杯になった時点で、次の
ホッパ車5dの新バラストが前段側のホッパ車5cに全
て移載されて次のホッパ車5dが空になっている。
On the other hand, at the same time as the old ballast is scraped, the new ballast 10 loaded on the rearmost hopper 5a passes through the second and third belt conveyors 8a, 6a provided below the hopper 5a. The new ballast 10 is transferred to the input conveyor 4 of the ballast work vehicle 1 and is excavated through the input conveyor 4 to the excavated portion where the old ballast has been scraped off. The second-stage hopper truck 5 from the rear end in parallel with the loading
b is transferred to the rearmost hopper wheel 5a via the second belt conveyor 8b and the third belt conveyor 6b, and the new ballast 10 is sequentially transferred to the second belt conveyor 8c. The hopper wheel 5d is sequentially transferred to the rearmost hopper wheel 5a via the belt conveyor 6c, and the hopper wheel 5d → the hopper wheel 5c → the hopper wheel 5b. During this time, the ballast after being scraped is deposited on the last hopper wheel 5e, but when the last hopper wheel 5e is full, the new ballast of the next hopper wheel 5d is replaced with the previous hopper wheel 5e. The entire hopper car 5d is empty after being transferred to the car 5c.

【0011】そこで最前部のホッパ車5eに堆積され満
杯になったバラストを第2のベルトコンベア8eおよび
第3のベルトコンベア6eを介して次のホッパ車5dに
送る。以下も同様に最後部のホッパ車5eより順次中間
のホッパ車5d〜5bに移載されより該ホッパ車5bに
旧バラストが移載され満杯になった段階で作業が終了す
る。一方新バラスト10も同様に次段のホッパ車5dよ
り順次中間のホッパ車5c〜5bに移載され、ホッパ車
5aに移載されバラスト作業車1の投入コンベア58を
介して掘削部分に投入された段階で作業が終了する。従
ってバラストの交換作業が進展するに従い、ホッパ車5
a〜5dの荷台から新たなバラストが送り出されていく
とともに、ホッパ車5e〜5bの荷台に掻き取られたバ
ラスト10積み込まれていくことになり、一編成の作業
編成列車51の中で積載された新たなバラスト10と掻
き取られたバラストとの入れ換えが行われる為に、ホッ
パ車5a〜5eの荷台がオーバフローすることなく、掻
き取られたバラストは、ホッパ車5b〜5eの荷台に均
等に積み込まれる。
The full ballast deposited on the forefront hopper wheel 5e is sent to the next hopper wheel 5d via the second belt conveyor 8e and the third belt conveyor 6e. In the following, similarly, the operation is completed when the old ballast is transferred to the intermediate hopper wheels 5d to 5b sequentially from the last hopper wheel 5e to the hopper wheel 5b and becomes full. On the other hand, similarly, the new ballast 10 is similarly transferred to the intermediate hopper cars 5c to 5b sequentially from the next hopper car 5d, transferred to the hopper car 5a, and put into the excavation portion via the loading conveyor 58 of the ballast work vehicle 1. The work is completed at the stage where it is completed. Therefore, as ballast replacement progresses, the hopper 5
As new ballasts are sent out from the loading platforms a to 5d, the scraped ballasts 10 are loaded onto the loading platforms of the hopper trucks 5e to 5b, and are loaded in one train train 51. Since the replacement of the new ballast 10 with the scraped ballast is performed, the scraped ballasts are evenly placed on the hopper cars 5b to 5e without overflowing of the hopper cars 5a to 5e. Be loaded.

【0012】[0012]

【発明が解決しようとする課題】かかる道床交換システ
ムは、軌道駆動車9a、9bにより、バラスト作業車
1、ホッパ車5a〜5eを定低速で牽引しながら、バラ
スト作業車1のバラスト掻取装置2で道床を掻き上げ旧
バラストと新バラスト10の交換を行う方式である。軌
道駆動車9、バラスト作業車1、ホッパ車5a〜5eは
それぞれ連結機11a〜11gで連結された連結編成構
造になっているている。しかし、バラスト作業車1の掻
取装置2部での掻き上げスピードが、道床の状態により
異なる為、軌道駆動車9で常に定低速牽引すると掻取装
置2に大きな負荷が生じ、掘削能力を低下させ、最悪の
場合掻取装置2を破損させる恐れがある。また、それを
回避する為には、軌道駆動車9のオペレーターが、別途
カメラ等の監視モニタ、バラスト作業車付近の作業員と
の無線連絡等を使用してバラスト作業車1の稼動状況を
見ながら、軌道駆動車9の車速を制御しなければならな
い為、大変困難で熟練を要する。
In such a roadbed replacement system, the ballast scraping device for the ballast work vehicle 1 is pulled by the track drive vehicles 9a and 9b while pulling the ballast work vehicle 1 and the hopper vehicles 5a to 5e at a constant low speed. In this method, the old ballast and the new ballast 10 are exchanged by scraping the ballast in step 2. The track driving vehicle 9, the ballast work vehicle 1, and the hopper vehicles 5a to 5e have a connected knitting structure connected by connecting machines 11a to 11g, respectively. However, the speed at which the ballast work vehicle 1 scrapes up at the scraping device 2 varies depending on the state of the roadbed. Therefore, if the track driving vehicle 9 constantly pulls at a constant low speed, a large load is generated on the scraping device 2 and the excavating capacity is reduced. In the worst case, the scraper 2 may be damaged. In order to avoid this, the operator of the track driving vehicle 9 checks the operation status of the ballast work vehicle 1 using a monitoring monitor such as a camera separately, wireless communication with a worker near the ballast work vehicle, or the like. However, since the speed of the track driving vehicle 9 must be controlled, it is very difficult and requires skill.

【0013】本発明の目的は、かかる課題に鑑み、バラ
スト作業車側の掻取装置の負荷変動が生じても円滑に且
つ熟練度を必要とすることなく、運転の出来るバラスト
交換車両システムを提供することにある。
An object of the present invention is to provide a ballast replacement vehicle system which can be operated smoothly and without requiring skill even if a load variation of a scraping device on a ballast work vehicle occurs in view of the above problem. Is to do.

【0014】[0014]

【課題を解決するための手段】本発明はかかる課題を解
決するために、レールを支える枕木等の下面に敷設され
た、バラストを交換する道床交換システムであって、上
記レール上に沿って走行され、交換用バラストが積載さ
れた複数のバラスト積載車と、該バラスト積載車を連結
して所定制御速度で走行する軌道駆動車とを含む第1の
編成車と、少なくともバラストを掻き取る掻取手段を有
するバラスト作業車を有し、前記第1の編成車に非連結
の状態で自走手段にて近接走行する第2の編成車と、前
記第1の編成車と第2の編成車との間の相対速度を検知
するセンサとを具え、該センサの信号に基づいて少なく
とも一方の編成車の走行速度を制御可能に構成した事を
特徴とする。前記センサは速度センサ若しくは時系列的
な両編成車の車間距離を測定する距離センサで構成され
る。例えば、請求項2に記載のように、前記第1の編成
車と第2の編成車との間の車間距離を検知する距離セン
サとを具え、該距離センサの信号に基づいて少なくとも
一方の編成車の走行速度を制御可能に構成してもよい。
SUMMARY OF THE INVENTION In order to solve the above-mentioned problems, the present invention relates to a ballast exchange system for exchanging ballasts, which is laid on a lower surface of a sleeper or the like for supporting rails, and which runs along the rails. A first knitting vehicle including a plurality of ballast loaded vehicles on which replacement ballasts are loaded, and a track driving vehicle connected to the ballast loaded vehicles and running at a predetermined control speed; A second train having a ballast work vehicle having a means and running close to the first train in a self-propelled manner in a non-connected state; and the first train and the second train. And a sensor for detecting a relative speed between the two trains, wherein the running speed of at least one train is controlled based on a signal from the sensor. The sensor is a speed sensor or a distance sensor that measures the inter-vehicle distance of both trains in time series. For example, as described in claim 2, a distance sensor for detecting an inter-vehicle distance between the first train and the second train is provided, and at least one train is formed based on a signal from the distance sensor. You may comprise so that the driving speed of a vehicle can be controlled.

【0015】かかる発明は前記先願技術のように負荷の
変動するバラスト作業者側を切り離し、バラスト積載車
側を所定車間距離範囲内に入るように速度若しくは距離
制御するもので、これによりバラスト作業車が有する掻
取装置の掘削速度に合わせて、軌道駆動車の速度を自動
で制御できる為、掻取装置に必要以上の負荷をかける事
無く、また、軌道駆動車のオペレータも速度制御に熟練
を有する必要がなくなる。勿論、請求項3記載のよう
に、前記第1の編成車と第2の編成車との間の距離変位
と相対速度変位を組み合わせて少なくとも一方の編成車
の走行速度を制御可能に構成することにより、一層緻密
な制御が可能となる。
This invention separates the ballast worker whose load fluctuates, as in the prior application, and controls the speed or distance so that the ballast loading vehicle is within a predetermined inter-vehicle distance range. The speed of the track driven vehicle can be automatically controlled in accordance with the excavation speed of the scraping device of the car, so that no unnecessary load is applied to the scraping device and the operator of the track driven vehicle is skilled in speed control. It is no longer necessary to have Of course, as set forth in claim 3, the travel speed of at least one train can be controlled by combining the distance displacement and the relative speed displacement between the first train and the second train. This allows more precise control.

【0016】請求項4記載の発明は、前記バラスト作業
車側の第2の編成車と、これと離間したバラスト積載車
側の第1の編成車夫々に設けた、バラスト回収コンベア
と交換用バラスト移送コンベア夫々の、搬入端と搬出端
とを互いに非接触の状態で重合させるとともに、該重合
部間が完全に離間しないように、前記2つの編成車の車
間距離を維持して、少なくとも一方の編成車の走行速度
を制御可能に構成した事を特徴とする。かかる発明によ
れば、前記第1の編成車と第2の編成車とを離間させて
も、バラストの回収と投入が線路上に落ちることなく円
滑に行われる。
According to a fourth aspect of the present invention, there is provided a ballast collection conveyor and a replacement ballast provided respectively on the second train on the ballast work vehicle side and the first train on the ballast loading vehicle side separated from the second train. At each of the transfer conveyors, the carry-in end and the carry-out end are superimposed in a non-contact state with each other, and the inter-vehicle distance is maintained between the two trains so that the superimposed portions are not completely separated from each other. It is characterized in that the running speed of the train is controllable. According to this invention, even if the first train and the second train are separated from each other, the ballast can be collected and put in smoothly without falling on the track.

【0017】請求項5記載の発明は、前記バラスト作業
車の回収のための回収コンベア群が、該作業車より最も
遠い位置にあるバラスト積載車に向けて復動方向に順次
形成され、一方最も遠い位置にあるバラスト積載車から
バラスト作業車への投入用バラストの移送コンベアが、
往動方向に順次形成されるとともに、第2の編成車と、
これと離間した編成車と対面する、バラスト回収コンベ
アとバラスト移送コンベア夫々の搬入端と搬出端とを互
いに非接触の状態で重合させていることを特徴とする。
According to a fifth aspect of the present invention, the collection conveyor group for collecting the ballast working vehicle is formed in the backward movement direction toward a ballast loading vehicle located farthest from the work vehicle, and is formed on the other hand. A ballast transfer conveyor from a distant ballast loading vehicle to a ballast work vehicle,
A second train is formed sequentially in the forward movement direction,
It is characterized in that the carry-in end and the carry-out end of the ballast collection conveyor and the ballast transfer conveyor facing the formation car separated from this are overlapped in a non-contact state.

【0018】作業車側の第2編成車とバラスト積載車側
の第1の編成車間が切り離されていても、両者間のバラ
スト回収コンベアとバラスト移送コンベア夫々の搬入端
と搬出端とを互いに非接触の状態で重合させている為
に、バラストが誤って線路上に落下することなく、バラ
ストの掻き取りから積載及び新バラストの投入までのー
連の工程を連続して行うことができ、この点でも作業時
間の短縮化に寄与するとともに、鉄道車両の運行に支障
を来すこともない。
Even if the second train on the work vehicle side and the first train on the ballast loading vehicle side are separated from each other, the carry-in end and the carry-out end of the ballast collection conveyor and the ballast transfer conveyor between them are not separated from each other. Because it is superposed in the state of contact, the ballast can be continuously performed from scraping of the ballast to loading and loading of new ballast without the ballast accidentally falling on the track. This also contributes to shortening the working time and does not hinder the operation of railway vehicles.

【0019】バラスト作業車は、掻き取られたバラスト
をバラスト積載車側に搬出する搬出手段と、バラスト掘
削部分にバラスト積載車側より新バラストを投入する投
入手段とともに、自走手段を具えている事を特徴とす
る。
The ballast work vehicle has self-propelled means together with unloading means for unloading the scraped ballast to the ballast loading vehicle and input means for inputting a new ballast from the ballast loading vehicle side to the ballast excavation part. It is characterized by things.

【0020】請求項7記載の発明は、前記バラスト作業
車側の第2の編成車、若しくはこれと離間した第1の編
成車側に連結された一のバラスト積載車が、作業開始前
に交換用バラストが積載されていない空の荷台車であっ
て、該空の荷台車を利用して回収バラストの積載と交換
用バラストの移送により入れ替えが、両者が混載される
ことなく行われることを特徴とする。これにより、バラ
ストの掻き取りから積載及び新バラストの投入までのー
連の工程を精度良く確実に連続して行うことができる。
According to a seventh aspect of the present invention, the second train on the side of the ballast working vehicle or one ballast loading vehicle connected to the first train on the side of the first train separated from the second train is replaced before the start of work. An empty trolley on which no ballast is loaded, wherein replacement of the loaded ballast and loading of the replacement ballast using the empty trolley is performed without mixing both. And Thereby, consecutive steps from scraping of the ballast to loading and loading of the new ballast can be performed continuously with high accuracy.

【0021】[0021]

【発明の実施の形態】以下、本発明を図に示した実施例
を用いて詳細に説明する。但し、この実施例に記載され
る構成部品の寸法、形状、その相対配置などは特に特定
的な記載がない限り、この発明の範囲をそれのみに限定
する趣旨ではなく単なる説明例に過ぎない。図1は本発
明の実施形態にかかる道床交換編成車両を示す概略図で
ある。尚、本発明の各車両毎の構成は基本的に前記先願
技術と同様なために、前記先願技術との違いを中心に説
明する。この道床交換編成列車50は、バラストを掻取
り投入する自走可能なバラスト作業車12、中間台車2
2と、バラスト積載車としての5両のホッパ車19a〜
19eのみを牽引する2両の軌道駆動車20a、20b
とで構成され、これらは全て連結器27a〜27fによ
り連結されている。又駆動車20a側の最前部ホッパ車
19eには新バラスト10は堆積されていない。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the present invention will be described in detail with reference to an embodiment shown in the drawings. However, unless otherwise specified, dimensions, shapes, relative arrangements, and the like of the components described in this embodiment are not intended to limit the scope of the invention, but are merely illustrative examples. FIG. 1 is a schematic diagram showing a roadbed change-forming vehicle according to an embodiment of the present invention. Since the configuration of each vehicle of the present invention is basically the same as the prior application technology, the description will be focused on the differences from the prior application technology. This train 50 is a self-propelled ballast work vehicle 12 for scraping and injecting ballast, an intermediate bogie 2
2 and 5 hopper cars 19a to 5 as ballast loading cars
Two track driven vehicles 20a, 20b towing only 19e
And these are all connected by connectors 27a to 27f. Further, no new ballast 10 is deposited on the frontmost hopper wheel 19e on the side of the driving wheel 20a.

【0022】最後部に連結されているバラスト作業車1
は、車体後部に据え付けられているバラスト掻取装置1
3と、掻き取ったバラストを搬出手段としての搬出コン
ベア14とを装備している。バラスト掻取装置13は、
従来のバラスト掻き取り装置と同様の構成を有するた
め、その詳細な説明を省略する。バラスト作業車12と
中間台車22は連結装置23で連結され、バラスト作業
車によって駆動される。軌道駆動車20a、20bとホ
ッパ車19a〜19eは連結装置27a〜27fでそれ
ぞれ連結されている。バラスト作業車12の掻取装置1
3で道床を掻き上げ、搬出コンベア14を通って中間台
車22の上部ベルトコンベア25に送られ、更に後続の
ホッパ車19a…の上部ベルトコンベア17a…によっ
て順次後続ホッパ車19b…上部のベルトコンベア17
b…を順次経由して最前部のからのホッパ車19eに移
載される。
Ballast work vehicle 1 connected to the rear end
Is a ballast scraping device 1 installed at the rear of the vehicle body
3 and an unloading conveyor 14 as an unloading means for scraping the ballast. The ballast scraping device 13
Since it has the same configuration as the conventional ballast scraping device, its detailed description is omitted. The ballast work vehicle 12 and the intermediate carriage 22 are connected by a connection device 23, and are driven by the ballast work vehicle. The track driving vehicles 20a and 20b and the hopper vehicles 19a to 19e are connected by connecting devices 27a to 27f, respectively. Scraping device 1 for ballast work vehicle 12
3 and is sent to the upper belt conveyor 25 of the intermediate carriage 22 through the unloading conveyor 14 and further successively by the upper belt conveyor 17a of the succeeding hopper car 19a.
are sequentially transferred to the hopper wheel 19e from the foremost part through b.

【0023】一方、旧バラストの掻き取りと同時に、最
後部のホッパ車5aに積載されている新バラスト10が
ホッパ車19a荷台下方に設けた第2及び第3のベルト
コンベア18a、16aを介して中間台車22に送ら
れ、該台車22内の下部ベルトコンベア24を介してバ
ラスト作業車1の投入コンベア15に移送し、投入コン
ベア15を介して旧バラストを掻き取った跡の掘削部分
に新バラスト10が投入される。前記投入と並行して最
後部より2段目のホッパ車19bに積載されている新バ
ラスト10が第2のベルトコンベア18bおよび第3の
ベルトコンベア16bを介して最後部のホッパ車19a
に移載され、以下順次第2のベルトコンベア18c…お
よび第3のベルトコンベア16c…を介して順次ホッパ
車19d→ホッパ車19c→ホッパ車19bに最後部の
ホッパ車19aに移載される。この間、掻取り後のバラ
ストは最後部のホッパ車19eに堆積が行われている
が、最後部のホッパ車19eが満杯になった時点で、次
のホッパ車19dの新バラストが前段側のホッパ車19
cに全て移載されて次のホッパ車19dが空になってい
る。
On the other hand, at the same time as the old ballast is scraped, the new ballast 10 loaded on the rearmost hopper 5a passes through the second and third belt conveyors 18a and 16a provided below the hopper 19a. The ballast is transferred to the intermediate carriage 22, transferred to the loading conveyor 15 of the ballast working vehicle 1 via the lower belt conveyor 24 in the carriage 22, and a new ballast is formed on the excavated portion where the old ballast is scraped off via the loading conveyor 15. 10 is input. In parallel with the loading, the new ballast 10 loaded on the second-stage hopper wheel 19b from the rearmost position is moved to the rearmost hopper wheel 19a via the second belt conveyor 18b and the third belt conveyor 16b.
, And then sequentially transferred via the second belt conveyor 18c and the third belt conveyor 16c to the hopper wheel 19a, the hopper wheel 19c, and the hopper wheel 19b to the last hopper wheel 19a. During this time, the ballast after the scraping is deposited on the last hopper wheel 19e, but when the last hopper wheel 19e becomes full, the new ballast of the next hopper wheel 19d is replaced with the previous hopper wheel 19e. Car 19
c, and the next hopper 19d is empty.

【0024】そこで最前部のホッパ車19eに堆積され
満杯になったバラストを第2のベルトコンベア18eお
よび第3のベルトコンベア16eを介して次のホッパ車
19dに送る。以下も同様に最後部のホッパ車19eよ
り順次ホッパ車19d〜19aに移載されることにより
該最後尾のホッパ車19aに旧バラストが移載され満杯
になった段階で作業が終了する。
The full ballast accumulated on the forefront hopper wheel 19e is sent to the next hopper wheel 19d via the second belt conveyor 18e and the third belt conveyor 16e. In the same manner, the operation is completed when the old ballast is transferred to the last hopper wheel 19a and becomes full by being sequentially transferred from the last hopper wheel 19e to the hopper wheels 19d to 19a.

【0025】かかる構成は中間台車を有する以外は前記
先願技術と同様であるが、最後尾のホッパ車19aと中
間台車22間は、連結器で連結されていないために、両
車両の多少の離間によっても中間台車22の上部ベルト
コンベアの排出端と最後部のホッパ車5aのベルトコン
ベア17a搬入端は重合させ、誤って搬出途中のバラス
トが線路上に落ちないように設定する。又、最後部のホ
ッパ車5aの下部ベルトコンベア17a搬出端と中間台
車22の下部ベルトコンベア24の搬入端も重合させ、
誤って投入途中のバラストが線路上に落ちないように設
定する。
This configuration is the same as that of the prior application except that the vehicle has an intermediate bogie. However, since the rearmost hopper wheel 19a and the intermediate bogie 22 are not connected by a coupler, some of the two The discharge end of the upper belt conveyor of the intermediate carriage 22 and the carry-in end of the belt conveyor 17a of the rearmost hopper car 5a are also superimposed even by the separation, so that the ballast being carried out is prevented from dropping onto the track by mistake. Also, the unloading end of the lower belt conveyor 17a of the rearmost hopper truck 5a and the loading end of the lower belt conveyor 24 of the intermediate bogie 22 are overlapped,
Make settings so that ballasts during loading do not accidentally fall on the track.

【0026】そして本発明は、最後尾のホッパ車19a
には、中間台車22との距離を測る距離センサ26が取
り付けられている。距離センサ26で測定されたホッパ
車19aと中間台車22の間の距離は軌道駆動車20に
フィードバックされ、車間距離が一定になる様、軌道駆
動車20の車速制御する。
The present invention relates to a rear hopper wheel 19a.
Is mounted with a distance sensor 26 for measuring a distance from the intermediate carriage 22. The distance between the hopper car 19a and the intermediate bogie 22 measured by the distance sensor 26 is fed back to the track drive vehicle 20, and the vehicle speed of the track drive vehicle 20 is controlled so that the inter-vehicle distance becomes constant.

【0027】次にかかる道床交換編成列車50の車速制
御方法を、図3の制御フロー図で説明する。制御フロー
は、まず軌道駆動車20とバラスト作業車12の速度差
領域と、中間台車22と最後尾のホッパ車19aの車間
領域を設定する。(S1) 最後尾ホッパ車19aの距離センサ26から送られてく
る中間台車22との距離を基に軌道駆動車20とバラス
ト作業車12の相対速度を算出する。相対速度は距離セ
ンサで得られた距離信号を時系列的に微分して得てもよ
く、又軌道駆動車20に設けた速度計に基づいて検出し
た車両速度Vとバラスト作業車12の速度計に基づいて
検出した掘削速度V′との差に基づいて相対速度(V−
V′)を求めても良い。(S2)
Next, a method of controlling the vehicle speed of the train 50 with the change of roadbed will be described with reference to a control flowchart of FIG. In the control flow, first, a speed difference region between the track driving vehicle 20 and the ballast work vehicle 12 and an inter-vehicle region between the intermediate bogie 22 and the last hopper vehicle 19a are set. (S1) The relative speed between the track driving vehicle 20 and the ballast work vehicle 12 is calculated based on the distance from the intermediate bogie 22 sent from the distance sensor 26 of the last hopper vehicle 19a. The relative speed may be obtained by differentiating the distance signal obtained by the distance sensor in time series, and the vehicle speed V detected based on the speedometer provided on the track driving vehicle 20 and the speedometer of the ballast work vehicle 12 may be obtained. Based on the difference from the excavation speed V ′ detected based on the relative speed (V−
V ′) may be obtained. (S2)

【0028】次に下記の条件にて出力信号を決定する。 車間距離が中間台車22と最後尾のホッパ車19aと
の最小車間領域(前もって設定する。)より小さい場合
(近付き過ぎ)(S3) 相対速度が正(軌道駆動車の車速>バラスト作業車の車
速)であれば最小車間領域より離れる方向にあるためそ
のまま速度維持する。(S4) 相対速度が0以下(軌道駆動車の車速≦バラスト作業車
の車速)であれば最小車間領域より近づく方向にあるた
め軌道駆動車の増速量を算出して増速を行い、適正車間
領域に移行する。(S5)
Next, the output signal is determined under the following conditions. When the inter-vehicle distance is smaller than the minimum inter-vehicle area (set in advance) between the intermediate bogie 22 and the last hopper car 19a (too close) (S3), the relative speed is positive (vehicle speed of track-driven vehicle> vehicle speed of ballast work vehicle) ), The speed is maintained as it is in the direction away from the minimum inter-vehicle area. (S4) If the relative speed is 0 or less (vehicle speed of the track-driven vehicle ≦ vehicle speed of the ballast work vehicle), the vehicle is approaching the minimum inter-vehicle region, and the speed increase amount of the track-driven vehicle is calculated to increase the speed. Move to the inter-vehicle area. (S5)

【0029】車間距離が最大車間領域と最小車間領域
のあいだの適正車間領域にある場合適正車間領域であっ
ても相対速度(V−V′)が最小速度差領域より小さい場
合は軌道駆動車の増速量を算出して増速を行い、適正車
間領域の維持を図る。(S5) 適正車間領域であっても相対速度(V−V′)が最大速度
差領域より大きい場合は軌道駆動車の減速量を算出して
減速を行い、適正車間領域の維持を図る。(S7) 適正車間領域であって相対速度(V−V′)が速度差領域
内であればその速度維持を図る。(S6)
When the inter-vehicle distance is in the proper inter-vehicle region between the maximum inter-vehicle region and the minimum inter-vehicle region, the relative speed (V-V ') is smaller than the minimum speed difference region. Calculate the amount of speed increase to increase the speed, and maintain an appropriate inter-vehicle area. (S5) If the relative speed (V-V ') is larger than the maximum speed difference region even in the appropriate inter-vehicle region, the deceleration amount of the track-driven vehicle is calculated and decelerated to maintain the appropriate inter-vehicle region. (S7) If the relative speed (V-V ') is within the speed difference region in the proper inter-vehicle region, the speed is maintained. (S6)

【0030】 車間距離が最大車間領域より大きい場
合(離れ過ぎ)(S9) 相対速度が0以上(軌道駆動車の車速≧バラスト作業車
の車速)であれば最大車間領域より離れる方向にあるた
め軌道駆動車の減速量を算出して減速を行い、適正車間
領域に移行する。(S7) 相対速度が負(軌道駆動車の車速<バラスト作業車の車
速)であれば最大車間領域より近づいて適正車間領域に
移行途中にあるためそのまま速度維持する。(S8) そして前記距離センサによる距離検出(S10)と軌道
駆動車の速度制御はサイクルタイム毎に行い、軌道駆動
車の自動制御を行う。
If the inter-vehicle distance is larger than the maximum inter-vehicle area (too far away) (S9) If the relative speed is 0 or more (vehicle speed of the track driving vehicle ≧ vehicle speed of the ballast work vehicle), the vehicle is in a direction away from the maximum inter-vehicle area, The deceleration is performed by calculating the deceleration amount of the driving vehicle, and the process shifts to the appropriate headway range. (S7) If the relative speed is negative (the vehicle speed of the track-driven vehicle <the vehicle speed of the ballast work vehicle), the vehicle is approaching the maximum inter-vehicle region and is transitioning to the appropriate inter-vehicle region, so that the speed is maintained as it is. (S8) The distance detection by the distance sensor (S10) and the speed control of the track-driven vehicle are performed for each cycle time, and the track-driven vehicle is automatically controlled.

【0031】[0031]

【発明の効果】以上記載のごとく本発明によれば、軌道
駆動車の速度を、バラスト作業車が有する掻取装置の掘
削(掻取)速度に合わせて自動で制御する為、掻取装置に
必要以上の負荷をかける事無く、また、軌道駆動車のオ
ペレータも速度制御に熟練を有する必要がなくなる。
As described above, according to the present invention, the speed of the track driving vehicle is automatically controlled in accordance with the excavation (scraping) speed of the scraping device of the ballast work vehicle. It does not apply an unnecessarily large load, and the operator of the track-driven vehicle does not need to be skilled in speed control.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の実施例に係る道床交換システムの概
略図である。
FIG. 1 is a schematic diagram of a roadbed replacement system according to an embodiment of the present invention.

【図2】 先願技術に係る道床交換システムの概略図で
ある。
FIG. 2 is a schematic diagram of a roadbed replacement system according to the prior application technology.

【図3】 図1の道床交換システムの制御フロー図であ
FIG. 3 is a control flow chart of the roadbed changing system of FIG. 1;

【符号の説明】[Explanation of symbols]

10 新バラスト 11 連結装置 12 バラスト作業車 13 掻取装置 14 旧バラスト搬送ベルトコンベア 15 新バラスト投入ベルトコンベア 16 送出ベルトコンベア 13 上部ベルトコンベア 18 下部ベルトコンベア 19 ホッパ車 20 軌道駆動車 21 新バラスト 22 中間台車 23 連結装置 24 中間台車送出ベルトコンベア 25 中間台車上部ベルトコンベア 26 距離センサ 23 連結装置 DESCRIPTION OF SYMBOLS 10 New ballast 11 Connecting device 12 Ballast work vehicle 13 Scraping device 14 Old ballast conveyance belt conveyor 15 New ballast loading belt conveyor 16 Sending belt conveyor 13 Upper belt conveyor 18 Lower belt conveyor 19 Hopper vehicle 20 Track drive 21 New ballast 22 Intermediate Bogie 23 Connecting device 24 Intermediate bogie delivery belt conveyor 25 Intermediate bogie upper belt conveyor 26 Distance sensor 23 Coupling device

───────────────────────────────────────────────────── フロントページの続き (72)発明者 田中 政之 神奈川相模原市田名3000番地 三菱重工業 株式会社汎用機・特車事業本部内 (72)発明者 宮本 隆司 愛知県名古屋市中村区名駅1丁目1番4号 東海旅客鉄道株式会社内 (72)発明者 玉井 章 東京都新宿区新宿3丁目36番10号 日本機 械保線株式会社内 Fターム(参考) 2D057 CB01 CB06  ──────────────────────────────────────────────────続 き Continuing from the front page (72) Inventor Masayuki Tanaka 3000 Tana, Kanagawa-Sagamihara-shi Mitsubishi Heavy Industries, Ltd. General-purpose Machinery & Special Vehicles Business Unit (72) Inventor Takashi Miyamoto 1-chome, Nakamura-ku, Nagoya-shi, Aichi Prefecture No. 1-4 Inside the Tokai Railway Company (72) Inventor Akira Tamai 3-36-10 Shinjuku, Shinjuku-ku, Tokyo F-term in Nippon Kikai Line Co., Ltd. 2D057 CB01 CB06

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 レールを支える枕木等の下面に敷設され
た、バラストを交換する道床交換システムであって、 上記レール上に沿って走行され、交換用バラストが積載
された複数のバラスト積載車と、該バラスト積載車を連
結して所定制御速度で走行する軌道駆動車とを含む第1
の編成車と、 少なくともバラストを掻き取る掻取手段を有するバラス
ト作業車を有し、前記第1の編成車に非連結の状態で自
走手段にて近接走行する第2の編成車と、前記第1の編
成車と第2の編成車との間の相対速度を検知するセンサ
とを具え、該センサの信号に基づいて少なくとも一方の
編成車の走行速度を制御可能に構成した事を特徴とする
道床交換システム。
1. A ballast exchange system for exchanging ballasts, which is laid on a lower surface of a sleeper or the like for supporting rails, the system comprising: a plurality of ballast-equipped vehicles that travel along the rails and have exchange ballasts mounted thereon; A track driving vehicle connected to the ballast loading vehicle and running at a predetermined control speed.
A second knitting car having a ballast work vehicle having at least a scraping means for scraping a ballast and running close to the first knitting car by self-propelled means; and A sensor for detecting a relative speed between the first train and the second train, wherein a running speed of at least one train can be controlled based on a signal from the sensor. Roadbed exchange system.
【請求項2】 レールを支える枕木等の下面に敷設され
た、バラストを交換する道床交換システムであって、 上記レール上に沿って走行され、交換用バラストが積載
された複数のバラスト積載車と、該バラスト積載車を連
結して所定制御速度で走行する軌道駆動車とを含む第1
の編成車と、 少なくともバラストを掻き取る掻取手段を有するバラス
ト作業車を有し、前記第1の編成車に非連結の状態で自
走手段にて近接走行する第2の編成車と、前記第1の編
成車と第2の編成車との間の車間距離を検知する距離セ
ンサとを具え、 該距離センサの信号に基づいて少なくとも一方の編成車
の走行速度を制御可能に構成した事を特徴とする道床交
換システム。
2. A ballast exchange system for exchanging ballasts, which is laid on a lower surface of a sleeper or the like for supporting rails, the system comprising: a plurality of ballast-equipped vehicles that travel along the rails and have replacement ballasts loaded thereon. A track driving vehicle connected to the ballast loading vehicle and running at a predetermined control speed.
A second knitting car having a ballast work vehicle having at least a scraping means for scraping a ballast and running close to the first knitting car by self-propelled means; and A distance sensor for detecting an inter-vehicle distance between the first train and the second train, wherein a running speed of at least one train can be controlled based on a signal from the distance sensor. Characteristic roadbed exchange system.
【請求項3】 レールを支える枕木等の下面に敷設され
た、バラストを交換する道床交換システムであって、 上記レールに沿って走行され、交換用バラストが積載さ
れた複数のバラスト積載車と、該バラスト積載車を連結
して所定制御速度で走行する軌道駆動車とを含む第1の
編成車と、 少なくともバラストを掻き取る掻取手段を有するバラス
ト作業車を有し、前記第1の編成車に非連結の状態で自
走手段にて近接走行する第2の編成車とを具え、前記第
1の編成車と第2の編成車との間の距離変位と相対速度
変位を組み合わせて少なくとも一方の編成車の走行速度
を制御可能に構成した事を特徴とする道床交換システ
ム。
3. A ballast exchange system for exchanging ballasts, which is laid on a lower surface of a sleeper or the like for supporting rails, comprising: a plurality of ballast-equipped vehicles that run along the rails and have replacement ballasts loaded thereon; A first train set including a track driven vehicle connected to the ballast loaded vehicle and traveling at a predetermined control speed; and a ballast work vehicle having at least a scraping means for scraping a ballast. And a second train running close to the self-propelled means in a non-connected state, and at least one of a combination of a distance displacement and a relative speed displacement between the first train and the second train. A roadbed replacement system characterized in that the running speed of the train set can be controlled.
【請求項4】 レールを支える枕木等の下面に敷設され
た、バラストを交換する道床交換システムであって、 上記レール上に沿って走行され、交換用バラストが積載
された複数のバラスト積載車と、該バラスト積載車を連
結して所定制御速度で走行する軌道駆動車とを含む第1
の編成車と、 少なくともバラストを掻き取る掻取手段を有するバラス
ト作業車を有し、前記第1の編成車に非連結の状態で自
走手段にて近接走行する第2の編成車とを具え、 前記バラスト作業車側の第2の編成車と、これと離間し
たバラスト積載車側の第1の編成車夫々に設けた、バラ
スト回収コンベアと交換用バラスト移送コンベア夫々
の、搬入端と搬出端とを互いに非接触の状態で重合させ
るとともに、該重合部間が完全に離間しないように、前
記2つの編成車の車間距離を維持して、少なくとも一方
の編成車の走行速度を制御可能に構成した事を特徴とす
る道床交換システム。
4. A ballast exchange system for exchanging ballasts, which is laid on a lower surface of a sleeper or the like for supporting rails, comprising: a plurality of ballast loading vehicles that travel along the rails and have replacement ballasts loaded thereon. A track driving vehicle connected to the ballast loading vehicle and running at a predetermined control speed.
And a second knitting vehicle having a ballast work vehicle having at least a scraping means for scraping the ballast and running close to the first knitting vehicle by self-propelled means without being connected to the first knitting vehicle. The carry-in end and the carry-out end of a ballast collection conveyor and a replacement ballast transfer conveyor provided respectively on the second train on the ballast work vehicle side and the first train on the ballast loading vehicle side separated therefrom. Are superposed in a non-contact state with each other, and the running speed of at least one train is controlled so that the distance between the two trains is maintained so that the overlapping portion is not completely separated. A roadbed exchange system characterized by the following.
【請求項5】 レールを支える枕木等の下面に敷設され
た、バラストを交換する道床交換システムであって、 上記レール上に沿って走行され、交換用バラストが積載
された複数のバラスト積載車と、該バラスト積載車を連
結して所定制御速度で走行する軌道駆動車とを含む第1
の編成車と、 少なくともバラストを掻き取る掻取手段を有するバラス
ト作業車を有し、前記第1の編成車に非連結の状態で自
走手段にて近接走行する第2の編成車とを具え、 前記バラスト作業車の回収のための回収コンベア群が、
該作業車より最も遠い位置にあるバラスト積載車に向け
て復動方向に順次形成され、一方最も遠い位置にあるバ
ラスト積載車からバラスト作業車への投入用バラストの
移送コンベアが、往動方向に順次形成されるとともに、
第2の編成車と、これと離間した編成車と対面する、バ
ラスト回収コンベアとバラスト移送コンベア夫々の搬入
端と搬出端とを互いに非接触の状態で重合させているこ
とを特徴とする鉄道用道床バラスト交換システム。
5. A ballast exchange system for exchanging ballasts, which is laid on a lower surface of a sleeper or the like for supporting rails, the system comprising: a plurality of ballast-equipped vehicles that travel along the rails and are mounted with replacement ballasts. A track driving vehicle connected to the ballast loading vehicle and running at a predetermined control speed.
And a second knitting vehicle having a ballast work vehicle having at least a scraping means for scraping the ballast and running close to the first knitting vehicle by self-propelled means without being connected to the first knitting vehicle. A collection conveyor group for collecting the ballast working vehicle,
The ballast transfer vehicle is sequentially formed in the backward direction toward the ballast loading vehicle located farthest from the work vehicle, while the ballast transfer conveyor for charging the ballast work vehicle from the farthest position to the ballast work vehicle moves in the forward movement direction. Formed sequentially,
For a railway, wherein the loading end and the unloading end of each of the ballast collection conveyor and the ballast transfer conveyor facing the second knitting car and the knitting car separated from the second knitting car are superposed in a non-contact state with each other. Ballast ballast exchange system.
【請求項6】 バラスト作業車は、掻き取られたバラス
トをバラスト積載車側に搬出する搬出手段と、バラスト
掘削部分にバラスト積載車側より新バラストを投入する
投入手段とともに、自走手段を具えている事を特徴とす
る請求項1、2、3、4若しくは5記載の道床交換シス
テム。
6. A ballast working vehicle includes a self-propelled means together with an unloading means for unloading a scraped ballast to a ballast loading vehicle side and an inputting means for inserting a new ballast from a ballast loading vehicle side into a ballast excavation part. The roadbed replacement system according to claim 1, 2, 3, 4, or 5, wherein
【請求項7】 前記バラスト作業車側の第2の編成車、
若しくはこれと離間した第1の編成車側に連結された一
のバラスト積載車が、作業開始前に交換用バラストが積
載されていない空の荷台車であって、該空の荷台車を利
用して回収バラストの積載と交換用バラストの移送によ
り入れ替えが、両者が混載されることなく行われること
を特徴とする請求項1、2、3、4若しくは5記載の道
床交換システム。
7. A second train set on the ballast work vehicle side,
Alternatively, one of the ballast loaded vehicles connected to the first train set side separated from this is an empty luggage truck on which no replacement ballast is loaded before the start of work, and the empty luggage truck is used. The roadbed replacement system according to claim 1, 2, 3, 4, or 5, wherein the replacement is carried out by loading the recovered ballast and transferring the replacement ballast without mixing the two.
JP2001092557A 2001-03-28 2001-03-28 Roadbed changing system Expired - Fee Related JP4664515B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001092557A JP4664515B2 (en) 2001-03-28 2001-03-28 Roadbed changing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001092557A JP4664515B2 (en) 2001-03-28 2001-03-28 Roadbed changing system

Publications (2)

Publication Number Publication Date
JP2002294607A true JP2002294607A (en) 2002-10-09
JP4664515B2 JP4664515B2 (en) 2011-04-06

Family

ID=18946999

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001092557A Expired - Fee Related JP4664515B2 (en) 2001-03-28 2001-03-28 Roadbed changing system

Country Status (1)

Country Link
JP (1) JP4664515B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016183540A (en) * 2015-03-27 2016-10-20 東日本旅客鉄道株式会社 Rail replacement device
CN106283992A (en) * 2016-08-31 2017-01-04 淮阴工学院 One has the small-sized maintenance of equipment of railway of traversing grab bucket clear stone device
CN112758617A (en) * 2020-12-22 2021-05-07 南京钜力智能制造技术研究院有限公司 Intelligent stone conveying system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0692234A (en) * 1992-09-11 1994-04-05 Ooyodo Diesel Kk Mobile working vehicle
JPH0717298A (en) * 1993-07-06 1995-01-20 Mazda Motor Corp Running control device for automobile
JPH07225893A (en) * 1994-02-09 1995-08-22 Fuji Heavy Ind Ltd Inter-vehicle distance controller
JPH106945A (en) * 1996-06-24 1998-01-13 Nissan Motor Co Ltd Collision preventing device for vehicle
JPH11189069A (en) * 1997-12-26 1999-07-13 Fujitsu Ten Ltd Safe distance control device
JP2000257004A (en) * 1999-03-12 2000-09-19 Hosen Kiki Seibi Kk Crushed stone replacing device for ballast renewal work
JP2001081705A (en) * 1999-09-13 2001-03-27 Mitsubishi Heavy Ind Ltd Railroad ballast replacement system and ballast replacement method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0692234A (en) * 1992-09-11 1994-04-05 Ooyodo Diesel Kk Mobile working vehicle
JPH0717298A (en) * 1993-07-06 1995-01-20 Mazda Motor Corp Running control device for automobile
JPH07225893A (en) * 1994-02-09 1995-08-22 Fuji Heavy Ind Ltd Inter-vehicle distance controller
JPH106945A (en) * 1996-06-24 1998-01-13 Nissan Motor Co Ltd Collision preventing device for vehicle
JPH11189069A (en) * 1997-12-26 1999-07-13 Fujitsu Ten Ltd Safe distance control device
JP2000257004A (en) * 1999-03-12 2000-09-19 Hosen Kiki Seibi Kk Crushed stone replacing device for ballast renewal work
JP2001081705A (en) * 1999-09-13 2001-03-27 Mitsubishi Heavy Ind Ltd Railroad ballast replacement system and ballast replacement method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016183540A (en) * 2015-03-27 2016-10-20 東日本旅客鉄道株式会社 Rail replacement device
CN106283992A (en) * 2016-08-31 2017-01-04 淮阴工学院 One has the small-sized maintenance of equipment of railway of traversing grab bucket clear stone device
CN112758617A (en) * 2020-12-22 2021-05-07 南京钜力智能制造技术研究院有限公司 Intelligent stone conveying system
CN112758617B (en) * 2020-12-22 2023-11-14 南京钜力智能制造技术研究院有限公司 Intelligent stone conveying system

Also Published As

Publication number Publication date
JP4664515B2 (en) 2011-04-06

Similar Documents

Publication Publication Date Title
US4307667A (en) Railroad track relaying train
CA2523392C (en) Movable belt conveyor system
CA1130653A (en) Mobile apparatus for continuously renewing track
AU2008266570B2 (en) Machine for the pick-up and storage of track fastenings of a track and method thereof
CN101050615B (en) Constructing method for laying seamless line track by CPG 500 type seamless line long rail laying unit
CZ278534B6 (en) Process of renewing track and a machinery for making the same
CS266555B2 (en) Tools arrrangement for rail&#39;s packing, nivelling and side straightening
CN1329197A (en) Machine for removing old track and laying new track and its operation method
GB2070670A (en) Travelling installation for cleaning the ballast bed of railway tracks
CZ20012064A3 (en) Track recovery machine
CN201137022Y (en) Fragment-free rail long steel rail track laying traction machine
JP2002294607A (en) Ballast exchanging system
CA2206742C (en) A machine for laying a track
CN113968250A (en) Molten iron combined transport toothed rail tractor, operation system and method
KR20100015454A (en) Storage cart for bulk material
CN216511624U (en) TBM rear-matched level-crossing tank truck moving and transporting system
JP2001081705A (en) Railroad ballast replacement system and ballast replacement method
EP1369529B1 (en) System and method for replacement of track bed ballast for railroad
CN205367193U (en) Transfer platform
CN219385829U (en) Rail exchanging operation system
CN214874790U (en) Material transport vehicle
CN216301062U (en) Molten iron intermodal rack track tractor and operating system
JP4651598B2 (en) Falling object collection method for converter equipment
JP2000257004A (en) Crushed stone replacing device for ballast renewal work
JP2000290904A (en) Ballast exchanger

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080314

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20080425

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20080425

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100113

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100319

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100518

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20101210

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110107

R150 Certificate of patent or registration of utility model

Ref document number: 4664515

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140114

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees