Info

Publication number
JP2002115256A
JP2002115256A JP2000311074A JP2000311074A JP2002115256A JP 2002115256 A JP2002115256 A JP 2002115256A JP 2000311074 A JP2000311074 A JP 2000311074A JP 2000311074 A JP2000311074 A JP 2000311074A JP 2002115256 A JP2002115256 A JP 2002115256A
Authority
JP
Japan
Prior art keywords
connection fitting
pile
reinforcing bar
foundation pile
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2000311074A
Other languages
Japanese (ja)
Other versions
JP4239394B2 (en
Inventor
Masanobu Okamoto
政信 岡本
Makoto Ikeda
真 池田
Yoshiyuki Kokuni
嘉之 小國
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Sumitomo Metal Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Industries Ltd filed Critical Sumitomo Metal Industries Ltd
Priority to JP2000311074A priority Critical patent/JP4239394B2/en
Publication of JP2002115256A publication Critical patent/JP2002115256A/en
Application granted granted Critical
Publication of JP4239394B2 publication Critical patent/JP4239394B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a structure for a head part of a foundation pile, enabling an improvement in workability, economical execution, and the easy and reliable mounting of a joining reinforcing bar for joining the pile head part and a footing to the head part of the foundation pile. SOLUTION: A plurality of connecting fittings 2 are protrusively installed on the outer periphery of the upper end of a steel pipe pile 1 at prescribed intervals in the peripheral direction of the pile 1. In the connecting fittings 2, there are protrusively installed the respective joining reinforcing bars 4 for joining the pile head part of the pile 1 to the footing 3 constructed on the upper side of the head part. The connecting fitting 2 has an arc-shaped part 2a below, and the reinforcing bar 4 is formed in a U shape corresponding to the arc- shaped part 2a of the connecting fitting 2.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、建造物の基礎杭
として地盤中に施工された鋼管杭または鋼管コンクリー
ト杭またはコンクリート杭などの基礎杭頭部の構造に関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure of a foundation pile head such as a steel pipe pile or a steel pipe concrete pile or a concrete pile constructed in the ground as a foundation pile of a building.

【0002】[0002]

【従来の技術】鉄筋コンクリート構造の基礎として、フ
ーチングまたは基礎スラブ(以下「フーチング」とい
う)直下の地盤の耐力があまり期待できないために、フ
ーチングを介して伝えられる上部構造の応力を、耐力が
期待できる地盤まで杭によって伝える杭基礎が知られて
いる。
2. Description of the Related Art As the foundation of a reinforced concrete structure, the strength of the ground immediately below a footing or a foundation slab (hereinafter referred to as "footing") cannot be expected very much. There is known a pile foundation that transmits a pile to the ground.

【0003】この場合の基礎杭として、例えば鋼管杭ま
たは鋼管コンクリート杭などが使用され、これらの杭頭
部はフーチングと一体に接合されている。これまで、基
礎杭の杭頭部をフーチングと一体的に接合する方法とし
ては、例えば図5(a)に図示するような、基礎杭20
の上端部に杭頭部とフーチングとを接合するための接合
鉄筋21として鉄筋かごを突設する鉄筋かご方式、図5
(b)に図示するような、基礎杭20の上端部の外周に
接合鉄筋21を直接溶接して突設するひげ筋方式、図5
(c)に図示するような、基礎杭20の上端部の外周に
ねじ式カプラーまたはナット22を溶接し、このカプラ
ーまたはナット22に接合鉄筋21を螺合して突設する
カプラー方式が知られている。
[0003] In this case, as a foundation pile, for example, a steel pipe pile or a steel pipe concrete pile is used, and the pile heads are integrally joined to the footing. Heretofore, as a method of integrally joining the pile head of the foundation pile with the footing, for example, as shown in FIG.
5 is a reinforcing bar cage system in which a reinforcing bar is projected as a connecting reinforcing bar 21 for connecting the pile head and the footing to the upper end of the pile.
As shown in FIG. 5 (b), a beard bar system in which a joint reinforcing bar 21 is directly welded to the outer periphery of the upper end of the foundation pile 20 to protrude, FIG.
As shown in (c), there is known a coupler system in which a threaded coupler or a nut 22 is welded to an outer periphery of an upper end portion of a foundation pile 20 and a joining reinforcing bar 21 is screwed to the coupler or the nut 22 to project therefrom. ing.

【0004】いずれの方式においても、基礎杭20の上
端部に突設された接合鉄筋21がフーチングのコンクリ
ート内に定着されることで、基礎杭20の杭頭部とフー
チグとが一体的に接合される。
[0004] In either method, the joint head 21 of the foundation pile 20 and the footing are integrally joined by fixing the joint reinforcing bar 21 projecting from the upper end of the foundation pile 20 in the concrete of the footing. Is done.

【0005】[0005]

【発明が解決しようとする課題】しかし、鉄筋かご方式
の場合、接合鉄筋21としての鉄筋かごは鋼管杭20a
の上端部に充填されたコンクリート20b内に挿入して
突設されることから、鉄筋の配筋スペースがせまく、過
密配筋になりやすい。このため困難な施工を強いられる
だけでなく、力学性能が劣る等の課題があった。
However, in the case of the reinforced cage system, the reinforced cage serving as the joining reinforcing bar 21 is made of a steel pipe pile 20a.
Since it is inserted into the concrete 20b filled in the upper end of the steel bar and protruded, the space for reinforcing bars is narrowed and the reinforcing bars are apt to be overcrowded. For this reason, not only was the construction difficult, but there were also problems such as poor mechanical performance.

【0006】また、ひげ筋方式には現場溶接の品質保証
が難しい等の課題があり、カプラー方式には鉄筋かご方
式やひげ筋方式の上述するような問題点は解決できるも
のの、コスト高になる等の課題があった。
Further, the beard bar method has a problem that it is difficult to assure the quality of field welding, and the coupler system can solve the above-mentioned problems of the rebar cage method and the beard bar method, but increases the cost. And other issues.

【0007】また、カプラー方式の場合、多角柱状のカ
プラーを鋼管杭の外周に直接溶接して取り付ける際、例
えば図5(e)に図示するようにカプラー22の一側面
を鋼管杭20aの側面部に当接させ、その両端部を鋼管
杭20aに溶接することとなるが、この溶接がきわめて
面倒なものであった。
In the case of the coupler system, when a polygonal column-shaped coupler is directly welded to the outer periphery of the steel pipe pile, one side of the coupler 22 is connected to the side of the steel pipe pile 20a as shown in FIG. , And both ends are welded to the steel pipe pile 20a, but this welding is extremely troublesome.

【0008】しかも、カプラー22を鋼管杭20aの外
周に溶接できても、この両端の溶接部間の距離sがきわ
めて短いため、基礎杭20が水平方向に力Pを受けた時
などにモーメント抵抗が小さく、力学的な弱点になりや
すいという問題があった。
Moreover, even if the coupler 22 can be welded to the outer periphery of the steel pipe pile 20a, the distance s between the welded portions at both ends is extremely short, so that when the foundation pile 20 receives a force P in the horizontal direction, the moment resistance is reduced. However, there is a problem that it is small and easily becomes a mechanical weak point.

【0009】このようなカプラー方式の問題点を解決す
る方法が、例えば特開平11−247184号公報に掲
載されている。本公報に掲載の方法では、図5(d)に
図示するようにカプラー(ねじ孔付接続具)の代わりに
通常の鋼管23を使ってねじ鉄筋からなる接合鉄筋21
を固定するため、コスト的にはカプラー方式に比べて改
善されるが、鋼管23を杭頭部の外周に溶接するのは、
多角柱のカプラー22を溶接する場合よりもさらに困難
なだけでなく、溶接部が力学的弱点であることにかわり
がない。
A method for solving such a problem of the coupler system is disclosed in, for example, JP-A-11-247184. In the method described in this publication, as shown in FIG. 5D, a joint reinforcing bar 21 composed of a screw reinforcing bar is used by using a normal steel pipe 23 instead of a coupler (connector with a screw hole).
In order to fix the steel pipe 23, the cost is improved as compared with the coupler method.
Not only is it more difficult than in the case of welding the polygonal coupler 22, but the weld is still a mechanical weak point.

【0010】さらに、カプラー方式と異なり、鋼管23
に接合鉄筋21としてねじ鉄筋を貫通させて固定するた
めには、鋼管23の下端部と上端部から接合鉄筋21に
固定ナット24と25をそれぞれ締め付ける必要があ
り、この場合、杭頭部に鋼管23を取り付けたあと後か
ら下側の固定ナット24を接合鉄筋21に締め付けるの
は容易でない。
Further, unlike the coupler system, the steel pipe 23
In order to penetrate and fix the screw rebar as the joint rebar 21, it is necessary to fasten the fixing nuts 24 and 25 to the joint rebar 21 from the lower end and the upper end of the steel pipe 23, respectively. It is not easy to fasten the lower fixing nut 24 to the joint reinforcing bar 21 after attaching the 23.

【0011】また、接合鉄筋21に作用する軸力は固定
ナット24および25を介して鋼管23に伝達される
が、鋼管23の断面力は接合鉄筋21の軸力と同程度に
なるため、かなり肉厚の鋼管を必要とし、現実的でない
等の課題がある。
The axial force acting on the joint reinforcing bar 21 is transmitted to the steel pipe 23 via the fixing nuts 24 and 25. However, since the sectional force of the steel tube 23 is substantially the same as the axial force of the joint reinforcing bar 21, it is considerably large. There is a problem that it requires a thick steel pipe and is not realistic.

【0012】この発明は、以上の課題を解決するために
なされたもので、基礎杭の頭部に杭頭部とフーチングと
を接合するため接合鉄筋を簡単かつ確実に取り付けるこ
とができて、施工性の向上と経済施工を可能にした基礎
杭頭部の構造を提供することを目的とする。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and a joining reinforcing bar can be easily and reliably attached to a head of a foundation pile for joining the pile head and a footing. An object of the present invention is to provide a structure of a foundation pile head capable of improving workability and economic construction.

【0013】[0013]

【課題を解決するための手段】請求項1記載の基礎杭頭
部の構造は、杭頭部の外周に取り付けられた接続金具に
接合鉄筋が固定されてなる基礎杭頭部の構造において、
下方に円弧状部を有する前記接続金具に、この接続金具
の円弧状部に対応してU字形状に形成さた接合鉄筋が国
定されていることを特徴とする。
According to a first aspect of the present invention, there is provided a foundation pile head having a structure in which a joint reinforcing bar is fixed to a connection fitting attached to an outer periphery of the pile head.
The connection fitting having an arcuate portion below has a U-shaped joining rebar corresponding to the arcuate portion of the connection fitting, which is nationally defined.

【0014】請求項2記載の基礎杭頭部の構造は、請求
項1記載の基礎杭頭部の構造において、接続金具の両側
部と下端部に接合鉄筋が係合可能な溝状部が両側部から
下端部に連続して形成されていることを特徴とする。
According to a second aspect of the present invention, there is provided a foundation pile head structure according to the first aspect, in which groove-shaped portions on both sides and a lower end of the connection fitting are engageable with joint reinforcing bars. It is characterized by being formed continuously from the portion to the lower end.

【0015】請求項3記載の基礎杭頭部の構造は、請求
項1または2記載の基礎杭頭部の構造において、接続金
具の両側部と下端部に鉄筋係止部が両側部から下端部に
連続して形成されていることを特徴とする。
According to a third aspect of the present invention, there is provided a structure of a foundation pile head according to the first or second aspect, wherein reinforcing bar locking portions are provided at both side portions and a lower end portion of the connection fitting. Is formed continuously.

【0016】請求項4記載の基礎杭頭部の構造は、請求
項2記載の基礎杭頭部の構造において、接続金具の両側
部と下端部に鉄筋係止部が両側部から下端部に連続して
形成され、前記鉄筋係止部は断面ほぼL字状に形成され
ているとともに、その内周は溝状部と連続する断面ほぼ
溝状に形成されていることを特徴とする。
According to a fourth aspect of the present invention, there is provided a structure of a foundation pile head according to the second aspect, wherein a reinforcing bar engaging portion is continuous from both sides and a lower end to both sides and a lower end of the connection fitting. The rebar engaging portion is formed to have a substantially L-shaped cross section, and the inner periphery thereof is formed to have a substantially groove-shaped cross section continuous with the groove portion.

【0017】[0017]

【発明の実施の形態】発明の実施の形態1.図1と図2
は、この発明に係る基礎杭頭部の構造の一例を示し、図
において基礎杭として施工された鋼管杭1の上端部の外
周に、接続金具2が鋼管杭1の周方向に所定間隔おきに
複数突設され、この接続金具2に鋼管杭1の杭頭部とそ
の上側に施工されたフーチング3とを接合するための接
合鉄筋4がそれぞれ突設されている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiment 1 of the Invention 1 and 2
Shows an example of the structure of the foundation pile head according to the present invention. In the figure, a connection fitting 2 is provided at predetermined intervals in the circumferential direction of the steel pipe pile 1 on the outer periphery of the upper end of the steel pipe pile 1 constructed as the foundation pile. A plurality of projections are provided, and joint bars 4 for joining the pile head of the steel pipe pile 1 and the footing 3 installed on the upper side thereof are projected from the connection fitting 2 respectively.

【0018】接続金具2は所定の厚さを有するブロック
状に形成され、その上端部は水平に、両側部は鉛直に、
そして下端部は両側部から連続し、かつ下方向に所定の
曲率で突出する円弧状(以下、「円弧状部2a」とい
う)にそれぞれ形成されている。
The connection fitting 2 is formed in a block shape having a predetermined thickness, the upper end thereof is horizontal, the both sides are vertical,
The lower end portion is formed in an arc shape (hereinafter, referred to as “arc-shaped portion 2a”) that is continuous from both sides and protrudes downward at a predetermined curvature.

【0019】また、接続金具2の両側部には側方に開口
する断面ほぼU字状の溝状部2bが、下端部には下方向
に開口する断面ほぼU字状の溝状部2bがそれぞれ形成
され、双方の溝状部2bは両側部から下端部にかけて連
続している。また、接続金具2の中央には取付孔2cが
複数、上下方向に所定間隔おきに形成されている。
On both sides of the connection fitting 2, there are groove portions 2b having a substantially U-shaped cross section which open laterally, and groove portions 2b having a substantially U-shaped cross section which open downward are formed on the lower end portion. Each groove-shaped portion 2b is formed, and is continuous from both sides to the lower end. A plurality of mounting holes 2c are formed in the center of the connection fitting 2 at predetermined intervals in the vertical direction.

【0020】こうして形成された接続金具2は鋼管杭1
の外側部に添え付けられ、かつ取付孔2cと鋼管杭1に
形成された取付孔1aを貫通する複数の取付ボルト5に
よって固定されている。
The connection fitting 2 thus formed is connected to the steel pipe pile 1.
And is fixed by a plurality of mounting bolts 5 penetrating the mounting hole 2c and the mounting hole 1a formed in the steel pipe pile 1.

【0021】接合鉄筋4は、接続金具2の両側部から下
端部にわたる円弧状部2aに対応して所定の曲率でU字
形状に形成されている。また、接合鉄筋4はU字状部4
aが接続金具2の円弧状部2aに係止され、U字状部4
aから連続する両側の直線部4b,4bは接続金具2の
両側部に沿ってに上方に垂直に立ち上げられ、さらに接
続金具2の両端から上方に所定長さ突出している。
The joint reinforcing bar 4 is formed in a U-shape with a predetermined curvature corresponding to the arc-shaped portion 2a extending from both sides to the lower end of the connection fitting 2. In addition, the joint reinforcing bar 4 has a U-shaped portion 4.
a is locked to the arc-shaped portion 2a of the connection fitting 2, and the U-shaped portion 4
The straight portions 4b, 4b on both sides continuing from a are vertically raised upward along both side portions of the connection fitting 2, and further protrude upward from both ends of the connection fitting 2 by a predetermined length.

【0022】そして、接合鉄筋4の直線部4b,4bに
座金6が取り付けられ、その後から固定ナット7がれぞ
れ螺合されている。こうして、接合鉄筋4は接続金具2
を介して鋼管杭1の外周に突設されている。なお、接合
鉄筋4には丸鋼の他にねじ鉄筋などが使用されている。
Then, a washer 6 is attached to the linear portions 4b, 4b of the joint reinforcing bar 4, and thereafter, fixing nuts 7 are screwed together. In this way, the joint reinforcing bar 4 is connected to the connection fitting 2
And protrudes from the outer periphery of the steel pipe pile 1 through the center. It should be noted that a screw rebar or the like is used for the joint rebar 4 in addition to the round bar.

【0023】このような構成において、接合鉄筋4に作
用する軸力は接続金具2、取付ボルト5、そして鋼管杭
1へと確実に伝達される。
In such a configuration, the axial force acting on the joining rebar 4 is reliably transmitted to the connection fitting 2, the mounting bolt 5, and the steel pipe pile 1.

【0024】発明の実施の形態2.図3(a)〜(c)
は、この発明に係る基礎杭頭部の構造の他の一例を示
し、図1〜図2で説明した例において、特に接続金具2
の両側部と下端部に鉄筋係止部2dが両側部から下端部
に鍔状に連続して形成されている。
Embodiment 2 of the Invention 3 (a) to 3 (c)
Shows another example of the structure of the foundation pile head according to the present invention. In the example described with reference to FIGS.
Rebar engaging portions 2d are formed continuously from both sides to the lower end in a brim shape at both sides and the lower end.

【0025】接続金具2の両側部と下端部に鉄筋係止部
2dが連続して形成されていることで、接合鉄筋4が接
続金具2からはずれるようなことはなく、フーチング3
から伝達される上部構造の応力が鋼管杭1に確実に伝達
される。
Since the reinforcing bar locking portions 2d are continuously formed on both sides and the lower end of the connecting fitting 2, the joint reinforcing bar 4 does not come off from the connecting fitting 2, and the footing 3
The stress transmitted from the upper structure is reliably transmitted to the steel pipe pile 1.

【0026】発明の実施の形態3.図4(a)〜(c)
は、この発明に係る基礎杭頭部の構造の他の一例を示
し、図1〜図3で説明した例において、特に接続金具2
の両側部と下端部に鉄筋係止部2dがそれぞれ形成さ
れ、特に両側部の鉄筋係止部2dは断面ほぼL字状に形
成され、さらにその内周が溝状部2aと連続する断面ほ
ぼU字状に形成されている。
Embodiment 3 of the Invention 4 (a) to 4 (c)
Shows another example of the structure of the foundation pile head according to the present invention. In the example described with reference to FIGS.
Reinforcing bars 2d are formed on both sides and a lower end of each of them. In particular, the reinforcing bars 2d on both sides are formed in a substantially L-shaped cross section, and the inner periphery thereof is substantially continuous in cross section with the groove 2a. It is formed in a U-shape.

【0027】両側部の鉄筋係止部2dがこのように形成
されていることで、接合鉄筋4をより確実に保持するこ
とができて、フーチング3から伝達される上部構造の応
力が鋼管杭1に確実に伝達される。
Since the reinforcing bar locking portions 2d on both sides are formed in this manner, the joint reinforcing bar 4 can be more reliably held, and the stress of the upper structure transmitted from the footing 3 is transmitted to the steel pipe pile 1. Is reliably transmitted.

【0028】[0028]

【発明の効果】この発明は、以上説明したとおりであ
り、特に基礎杭の外周部に取り付けられた接続金具の下
端部は両側部から連続し、下方向に突出する円弧状に形
成され、接合鉄筋は接続金具の下端部の円弧形状に対応
してU字形状に形成されているので、接合鉄筋はU字状
部を接続金具の下端部に係止し、両側の直線部を上に延
ばした後、両側の直線部に固定ナットを締め付ける等の
方法により接合鉄筋を接続金具に簡単かつ確実に取り付
けることができ、また接続金具は基礎杭の外周に溶接で
はなくボルト付けとすることで、接続金具も簡単かつ確
実に取り付けることができるため、これにより施工性の
向上と経済施工が図れる。
The present invention has been described above. In particular, the lower end of the connection fitting attached to the outer peripheral portion of the foundation pile is formed in an arc shape that is continuous from both sides and projects downward. Since the rebar is formed in a U-shape corresponding to the arc shape of the lower end of the connection fitting, the joining rebar locks the U-shaped part to the lower end of the connection fitting and extends the straight portions on both sides upward. After that, the joint reinforcement can be easily and securely attached to the connection fitting by tightening the fixing nut to the straight part on both sides, and the connection fitting is bolted rather than welded to the outer periphery of the foundation pile, The connection fitting can also be easily and reliably attached, thereby improving workability and economical construction.

【0029】また、接続金具の両側部と下端部に接合鉄
筋が係合可能な溝状部と鉄筋係止部が両側部から下端部
に連続して形成されているので、接合鉄筋が接続金具か
らはずれるようなことはなく、フーチングから伝達され
る上部構造の応力を基礎杭に確実に伝達できる。
Further, since a groove-like portion in which the joining rebar can be engaged and a rebar engaging portion are formed continuously from both sides to the lower end, the joining rebar is formed on both sides and the lower end of the connection fitting. And the stress of the superstructure transmitted from the footing can be reliably transmitted to the foundation pile.

【図面の簡単な説明】[Brief description of the drawings]

【図1】基礎杭頭部の構造を示し、(a)は接続金具と
接合鉄筋の取付状態を示す基礎杭頭部の一部正面図、
(b)は平面図、(c)は(a)におけるイ−イ線断面
図である。
FIG. 1 shows a structure of a foundation pile head, (a) is a partial front view of a foundation pile head showing a mounting state of a connection fitting and a joint reinforcing bar,
(B) is a plan view, and (c) is a cross-sectional view taken along the line II in (a).

【図2】接続金具および接合鉄筋の取付状態を示す基礎
杭頭部の一部分解斜視図である。
FIG. 2 is a partially exploded perspective view of a foundation pile head showing a mounting state of a connection fitting and a joint reinforcing bar.

【図3】基礎杭頭部の構造を示し、(a)は接続金具の
取付状態を示す一部正面図、(b)は(a)のイ−イ線
断面図、(c)は接続金具の斜視図である。
3A and 3B show a structure of a foundation pile head, wherein FIG. 3A is a partial front view showing an attached state of a connection fitting, FIG. 3B is a sectional view taken along the line II of FIG. 3A, and FIG. It is a perspective view of.

【図4】基礎杭頭部の構造を示し、(a)は接続金具の
取付状態を示す一部正面図、(b)は(a)のイ−イ線
断面図、(c)は接続金具の斜視図である。
4A and 4B show a structure of a foundation pile head, where FIG. 4A is a partial front view showing an attached state of a connection fitting, FIG. 4B is a sectional view taken along the line II in FIG. It is a perspective view of.

【図5】基礎杭頭部の構造を示し、(a)〜(c)はそ
の縦断面図、(d)は一部側面図、(e)はカプラーの
平面図である。
5 (a) to 5 (c) are longitudinal sectional views, FIG. 5 (d) is a partial side view, and FIG. 5 (e) is a plan view of a coupler.

【符号の説明】[Explanation of symbols]

1 鋼管杭 2 接続金具 2a 円弧状部 2b 溝状部 2c 取付孔 2d 鉄筋係止部 3 フーチング 4 接合鉄筋 4a U字状部 4b 直線部 5 取付ボルト 6 座金 7 固定ナット DESCRIPTION OF SYMBOLS 1 Steel pipe pile 2 Connection metal fitting 2a Arc-shaped part 2b Groove-shaped part 2c Attachment hole 2d Rebar anchoring part 3 Footing 4 Joining reinforcing bar 4a U-shaped part 4b Linear part 5 Mounting bolt 6 Washer 7 Fixing nut

───────────────────────────────────────────────────── フロントページの続き (72)発明者 小國 嘉之 大阪府大阪市中央区北浜4丁目5番33号 住友金属工業株式会社内 Fターム(参考) 2D041 AA02 BA37 CA01 CB05 DB02 DB03 DB05 2D046 CA04  ────────────────────────────────────────────────── ─── Continuing from the front page (72) Inventor Yoshiyuki Oguni 4-53, Kitahama, Chuo-ku, Osaka City, Osaka Prefecture F-term within Sumitomo Metal Industries, Ltd. 2D041 AA02 BA37 CA01 CB05 DB02 DB03 DB05 2D046 CA04

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 杭頭部の外周に取り付けられた接続金具
に接合鉄筋が固定されてなる基礎杭頭部の構造におい
て、下方に円弧状部を有する前記接続金具に、この接続
金具の円弧状部に対応してU字形状に形成さた接合鉄筋
が国定されていることを特徴とする基礎杭頭部の構造。
In a structure of a foundation pile head in which a joint reinforcing bar is fixed to a connection fitting attached to an outer periphery of a pile head, the connection fitting having an arc-shaped portion below has an arc shape of the connection fitting. The structure of a foundation pile head characterized in that U-shaped joint reinforcing bars corresponding to the parts are nationally defined.
【請求項2】 接続金具の両側部と下端部に接合鉄筋が
係合可能な溝状部が両側部から下端部に連続して形成さ
れていることを特徴とする請求項1記載の基礎杭頭部の
構造。
2. The foundation pile according to claim 1, wherein a groove-like portion in which a joining rebar can be engaged is formed continuously from both sides to the lower end at both sides and a lower end of the connection fitting. Head structure.
【請求項3】 接続金具の両側部と下端部に鉄筋係止部
が両側部から下端部に連続して形成されていることを特
徴とする請求項1または2記載の基礎杭頭部の構造。
3. The structure of the foundation pile head according to claim 1, wherein a reinforcing bar locking portion is continuously formed from both sides to the lower end on both sides and a lower end of the connection fitting. .
【請求項4】 接続金具の両側部と下端部に鉄筋係止部
が両側部から下端部に連続して形成され、前記鉄筋係止
部は断面ほぼL字状に形成されているとともに、その内
周は溝状部と連続する断面ほぼ溝状に形成されているこ
とを特徴とする請求項2記載の基礎杭頭部の構造。
4. A reinforcing bar engaging portion is formed on both sides and a lower end portion of the connection fitting so as to be continuous from both sides to a lower end portion, and the reinforcing bar engaging portion is formed to have a substantially L-shaped cross section. The structure of the head of the foundation pile according to claim 2, wherein the inner periphery is formed in a substantially groove shape in cross section continuous with the groove portion.
JP2000311074A 2000-10-11 2000-10-11 Foundation pile head structure Expired - Fee Related JP4239394B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000311074A JP4239394B2 (en) 2000-10-11 2000-10-11 Foundation pile head structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000311074A JP4239394B2 (en) 2000-10-11 2000-10-11 Foundation pile head structure

Publications (2)

Publication Number Publication Date
JP2002115256A true JP2002115256A (en) 2002-04-19
JP4239394B2 JP4239394B2 (en) 2009-03-18

Family

ID=18790902

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000311074A Expired - Fee Related JP4239394B2 (en) 2000-10-11 2000-10-11 Foundation pile head structure

Country Status (1)

Country Link
JP (1) JP4239394B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006241696A (en) * 2005-02-28 2006-09-14 Jfe Steel Kk Joint structure of concrete of foundation or footing to pile head and structure having the joint structure
JP2011012521A (en) * 2009-07-06 2011-01-20 Jfe Steel Corp Pile head connecting structure and construction method for the same
JP2011106240A (en) * 2009-11-20 2011-06-02 Okabe Co Ltd Pile head joint structure

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10245856A (en) * 1997-03-07 1998-09-14 Tootec:Kk Reinforcing bar connection device for steel pipe pile
JPH11140887A (en) * 1997-11-07 1999-05-25 Katashi Sendai Method for anchoring foundation pile to foundation and pile anchor therefor

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10245856A (en) * 1997-03-07 1998-09-14 Tootec:Kk Reinforcing bar connection device for steel pipe pile
JPH11140887A (en) * 1997-11-07 1999-05-25 Katashi Sendai Method for anchoring foundation pile to foundation and pile anchor therefor

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006241696A (en) * 2005-02-28 2006-09-14 Jfe Steel Kk Joint structure of concrete of foundation or footing to pile head and structure having the joint structure
JP4506969B2 (en) * 2005-02-28 2010-07-21 Jfeスチール株式会社 Bonding structure between concrete and pile head of foundation or footing and structure having the bonding structure
JP2011012521A (en) * 2009-07-06 2011-01-20 Jfe Steel Corp Pile head connecting structure and construction method for the same
JP2011106240A (en) * 2009-11-20 2011-06-02 Okabe Co Ltd Pile head joint structure

Also Published As

Publication number Publication date
JP4239394B2 (en) 2009-03-18

Similar Documents

Publication Publication Date Title
JP2000144906A (en) Column/beam joint section between cft structural column and src structural beam and beam main bar fixing metal fixture
JP2001159140A (en) Landslide-countermeasure structure
WO2008102955A1 (en) Composite girder having connection structure of inclined members in composite girder with steel truss web using embedded t-type perfobond and such connection structure
JP2002115256A (en) Structure for head part of foundation pile
JP2006188864A (en) Joint structure of column and beam
JP2973812B2 (en) Joint structure between steel members and concrete members
JP2004218429A (en) Bridge structure
JP4110729B2 (en) Foundation pile head structure
JPH10245856A (en) Reinforcing bar connection device for steel pipe pile
JPH08312061A (en) Steel column member and leg part fixing structure thereof
JP2004003236A (en) Structure of joint between steel-concrete composite structure and reinforced concrete structure
JP4154099B2 (en) Joint structure of steel pipe member and concrete member
JP4653353B2 (en) Joint structure of steel pipe column or steel column and beam reinforcement
JP3855922B2 (en) Pile head joint structure and construction method of pile head joint
JPH09189128A (en) Fixing structure of form for precast reinforced concrete foundation
JP4085023B2 (en) Connection structure of steel column or steel pipe column and beam reinforcement
JP3169887B2 (en) Column base structure of steel pipe column and its construction method
JP2001146756A (en) Earth-retaining wall and rc synthetic structure
JPH06185140A (en) Steel beam joining structure with reinforced concrete earthquake resisting wall
KR102428827B1 (en) Composite column
JP3096660B2 (en) Pile head structure of cast-in-place steel pipe concrete pile and its construction method
JP7565121B1 (en) Connecting fitting set and connecting method
JP3399917B2 (en) Joint structure of steel pipe column and beam
JP2005171705A (en) Double-tube structure of bridge pier
JP2762899B2 (en) Steel pipe concrete pillar and beam connection structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060601

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080618

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080819

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081006

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20081202

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20081215

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120109

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4239394

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130109

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130109

Year of fee payment: 4

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130109

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140109

Year of fee payment: 5

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees