JP2002047653A - Construction method for mortar pile - Google Patents

Construction method for mortar pile

Info

Publication number
JP2002047653A
JP2002047653A JP2000237889A JP2000237889A JP2002047653A JP 2002047653 A JP2002047653 A JP 2002047653A JP 2000237889 A JP2000237889 A JP 2000237889A JP 2000237889 A JP2000237889 A JP 2000237889A JP 2002047653 A JP2002047653 A JP 2002047653A
Authority
JP
Japan
Prior art keywords
mortar
hole
ground
construction
holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000237889A
Other languages
Japanese (ja)
Inventor
Minoru Kiyota
穣 清田
Daizaburo Uga
大三郎 宇賀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KIYOTA KIDO KOGYO KK
Osaka Bousui Construction Co Ltd
Original Assignee
KIYOTA KIDO KOGYO KK
Osaka Bousui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KIYOTA KIDO KOGYO KK, Osaka Bousui Construction Co Ltd filed Critical KIYOTA KIDO KOGYO KK
Priority to JP2000237889A priority Critical patent/JP2002047653A/en
Publication of JP2002047653A publication Critical patent/JP2002047653A/en
Pending legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Piles And Underground Anchors (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a constructing method for a mortar pile requiring no large execution machine, eliminating the effect on surrounding houses by noise or ground upheaval, and allowing execution on a road narrow in width or the like. SOLUTION: The ground 1 is drilled by a easing pipe 2, an H-steel 5 is inserted into a drilled hole 4, mortar 8 is placed in the hole 4, then the easing pipe 2 is extracted. A small boring machine used for casing drilling can be employed according to this construction method, noise or ground upheaval is not generated, thereby execution is allowed without receiving restrictions even on a road narrow in width.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、ケーシング削孔工
法を用いたモルタル杭の造成方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for forming a mortar pile using a casing drilling method.

【0002】[0002]

【従来の技術】止水壁や土留め壁などの地中連続壁を形
成する方法として、従来から様々な工法が採用されてい
る。たとえば、鋼材の矢板を押込装置により打設する鋼
矢板工法、超高圧硬化剤を地盤中に回転噴射させて地盤
を切削すると同時に固結体を形成するCCP(Chemical
Churning Pile)工法、空気を伴った超高圧硬化剤を地
盤中に回転噴射させて地盤を切削し、スライムを地表に
排出させると同時に固結体を形成するJSG(Jumbo Je
t Special Grout )工法、ロッド管より地盤中に水ガラ
ス溶液等の薬液を注入して固化させる薬液注入工法など
がある。
2. Description of the Related Art Conventionally, various construction methods have been adopted as a method for forming an underground continuous wall such as a water stop wall or an earth retaining wall. For example, a steel sheet pile construction method in which a sheet pile of steel is driven by a pushing device, a CCP (Chemical) method in which an ultra-high pressure hardener is rotationally sprayed into the ground to cut the ground and simultaneously form a consolidated body.
Churning Pile method, JSG (Jumbo Je) that cuts the ground by rotatingly spraying an ultra-high pressure hardener with air into the ground, discharges slime to the surface, and forms a consolidated body at the same time.
t Special Grout) There is a chemical liquid injection method in which a liquid chemical such as a water glass solution is injected into the ground from a rod tube and solidified.

【0003】[0003]

【発明が解決しようとする課題】鋼矢板工法は、強度や
水密性、耐久性に優れているが、大型の施工機械を必要
とするため、狭い道路などでは施工ができず、また、施
工時の騒音が大きいという難点がある。CCP工法は、
硬化剤の噴射に方向性をもたせることで、水平・垂直・
斜めのいずれの方向にも施工ができる利点があるが、高
圧噴射による圧力に起因して地盤に隆起等が発生し、近
隣家屋へ悪影響を及ぼすおそれがある。JSG工法は、
騒音が小さく地盤への影響も少ないが、施工時のロッド
継・切用の作業に大型のクレーンを必要とする。薬液注
入工法は、設備・機械がコンパクトで済み工期も短い
が、薬液の注入圧力に起因する地盤隆起が生じて、近隣
家屋へ悪影響を及ぼすおそれがある。
The steel sheet pile construction method is excellent in strength, watertightness and durability, but cannot be constructed on narrow roads because it requires a large construction machine. There is a drawback that the noise is loud. The CCP method is
By giving directionality to the injection of the curing agent, horizontal, vertical,
There is an advantage that the construction can be performed in any diagonal direction, but there is a possibility that a bulge or the like is generated in the ground due to the pressure due to the high-pressure injection, which adversely affects neighboring houses. The JSG method is
Although the noise is small and the effect on the ground is small, a large crane is required for connecting and cutting rods during construction. The chemical solution injection method has a compact facility and machine and requires only a short construction period. However, there is a possibility that ground uplift due to the injection pressure of the chemical solution may occur and adversely affect nearby houses.

【0004】このように、従来の工法は、大型の施工機
械を必要としたり、施工時に大きな騒音が発生したり、
地盤に隆起等が生じたりするため、スペースや近隣家屋
への影響の点で制約が多く、幅の狭い道路での施工には
適していなかった。
As described above, the conventional construction method requires a large construction machine, generates a large noise during construction,
Since the ground was raised, the impact on the space and neighboring houses was limited, and it was not suitable for construction on narrow roads.

【0005】本発明は、このような問題点を解決するも
のであって、大型の施工機械を不要とし、騒音や地盤隆
起による近隣家屋への影響をなくして、幅の狭い道路等
でも施工を可能としたモルタル杭の造成方法を提供する
ことを課題としている。
The present invention solves such a problem and eliminates the need for a large-scale construction machine, eliminates the influence of noise and ground uplift on neighboring houses, and enables construction on narrow roads and the like. It is an object of the present invention to provide a method for forming a mortar pile that has been made possible.

【0006】[0006]

【課題を解決するための手段】本発明では、ケーシング
パイプを用いて地盤に削孔を行ない、削孔された孔にH
形鋼を挿入し、H形鋼が挿入された孔の内部にモルタル
を打設し、その後ケーシングパイプを引き抜くという工
法を採用している。
According to the present invention, a ground hole is drilled using a casing pipe, and a hole is drilled into the drilled hole.
A method is employed in which a section steel is inserted, a mortar is poured into the hole into which the H-section steel is inserted, and then the casing pipe is pulled out.

【0007】このようにすることで、ケーシング削孔に
用いる小型のボーリングマシンを用いて施工を行なえる
ため、スペースに余裕のない場所においても楽に施工を
行うことができる。また、ケーシング削孔は矢板工法な
どに比べて施工時の騒音が少なく、CCP工法や薬液注
入工法のように地盤隆起が生じるおそれもないので、近
隣の家屋へ悪影響を及ぼす懸念も払拭される。したがっ
て、幅の狭い道路であっても制約を受けずに施工するこ
とが可能となる。
[0007] In this way, since the construction can be performed using a small boring machine used for drilling the casing, the construction can be performed easily even in a place where there is not enough space. Moreover, since the casing drilling has less noise during construction than the sheet pile method and the like, and there is no possibility of the ground being raised unlike the CCP method or the chemical liquid injection method, the concern of adversely affecting neighboring houses can be eliminated. Therefore, even on a narrow road, it is possible to construct without restriction.

【0008】本発明では、H形鋼に緩衝材を付設しても
よい。これによると、施工場所がたとえば線路に近い場
所であるような場合に、列車による振動が緩衝材で吸収
されるため、家屋に及ぼす振動の影響を低減することが
できる。また、孔内にケーシングパイプが挿入されてい
るので、H形鋼と緩衝材をパイプの内壁に沿ってスムー
ズに挿入することができる。
In the present invention, a cushioning material may be provided on the H-section steel. According to this, when the construction place is, for example, a place close to the track, the vibration caused by the train is absorbed by the cushioning material, so that the influence of the vibration on the house can be reduced. Further, since the casing pipe is inserted into the hole, the H-section steel and the cushioning material can be inserted smoothly along the inner wall of the pipe.

【0009】また、本発明では、削孔された複数の孔に
緩衝材を付設したH形鋼を間隔をおいて挿入するととも
に、H形鋼を挿入しない孔に緩衝材を挿入してもよい。
これによると、緩衝材がすべての孔に配設されるので、
振動を有効に吸収できるとともに、H形鋼を節約してコ
ストを低減できる利点がある。
Further, in the present invention, an H-shaped steel provided with a cushioning material may be inserted into a plurality of drilled holes at intervals, and a cushioning material may be inserted into a hole where the H-shaped steel is not inserted. .
According to this, the cushioning material is arranged in all holes,
There is an advantage that vibrations can be effectively absorbed and H-shaped steel can be saved to reduce costs.

【0010】また、本発明では、H形鋼を挿入する孔を
間隔をおいて削孔し、孔内に挿入された注入パイプによ
って地盤中へモルタルを噴射することにより、孔と孔と
の間をモルタルで埋めて、止水性を持たせることもでき
る。これによると、孔の削孔工数が少なくて済み、工期
を短縮してコストも低減できる利点がある。
Further, in the present invention, the holes for inserting the H-section steel are drilled at intervals, and mortar is injected into the ground by an injection pipe inserted into the holes, so that the gap between the holes is reduced. Can be filled with mortar to make it waterproof. According to this, there is an advantage that the number of man-hours for drilling holes can be reduced, the construction period can be shortened, and the cost can be reduced.

【0011】[0011]

【発明の実施の形態】本発明の実施形態につき、図を参
照しながら説明する。図1は本発明に係るモルタル杭の
造成方法の一例を示した工程図である。以下、これに従
って施工順序を説明する。まず、(a)のように地盤1
に対してケーシングパイプ2を用いてケーシング削孔を
行なう。ケーシングパイプ2の先端には、ビット3が設
けられており、図示しない小型のボーリングマシンでケ
ーシングパイプ2を回転させながら、ビット3により孔
4を削孔してゆく。このとき、ケーシングパイプ2の先
端から水を吐出させながら削孔を行なう。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described with reference to the drawings. FIG. 1 is a process diagram showing an example of a method for forming a mortar pile according to the present invention. Hereinafter, the construction order will be described in accordance with this. First, as shown in (a), the ground 1
Then, casing drilling is performed using the casing pipe 2. A bit 3 is provided at the tip of the casing pipe 2, and the hole 4 is drilled by the bit 3 while rotating the casing pipe 2 by a small boring machine (not shown). At this time, drilling is performed while discharging water from the end of the casing pipe 2.

【0012】回転ロッドの先端にウイングビットを設け
た通常のボーリングマシンでは、孔の内壁が崩落しない
ように、泥水を吐出させて孔壁に泥膜を形成しながら削
孔を行なうが、ケーシング削孔の場合は、ケーシングパ
イプ2により内壁崩落のおそれはないので、必ずしも泥
水を用いる必要はなく、普通の水であってもよい。ま
た、ケーシング削孔によると、孔4の内径を150mm
程度にすることができ、通常のボーリングマシンを用い
たウイングビットによる削孔の場合(孔径500mm以
上)に比較して、小径の孔を形成することができる。
In a normal boring machine provided with a wing bit at the tip of a rotating rod, drilling is performed while discharging muddy water to form a mud film on the hole wall so that the inner wall of the hole does not collapse. In the case of a hole, since there is no possibility that the inner wall will collapse due to the casing pipe 2, it is not necessary to use muddy water, and ordinary water may be used. According to the casing drilling, the inner diameter of the hole 4 is 150 mm.
And a hole having a smaller diameter can be formed as compared with the case of drilling with a wing bit using a normal boring machine (hole diameter of 500 mm or more).

【0013】次に、図1(b)のように、削孔された孔
4にH形鋼5を挿入する。このとき、孔4にはケーシン
グパイプ2が挿入されているので、H形鋼5はパイプ2
の内壁に案内されてスムーズに挿入される。
Next, as shown in FIG. 1B, an H-section steel 5 is inserted into the hole 4 thus drilled. At this time, since the casing pipe 2 is inserted into the hole 4, the H-section steel 5 is
Is guided smoothly by the inner wall of

【0014】H形鋼5を孔4の下まで挿入したら、次に
図1(c)のように、ポンプ装置6につながった注入ホ
ース7を孔4の中に導入し、ポンプ装置6から注入ホー
ス7を介して、モルタル8を孔4の内部に打設する。モ
ルタル8は、セメント、フライアッシュ、砂、水などが
混合された、いわゆるセメントミルクからなっている。
After the H-section steel 5 is inserted below the hole 4, an injection hose 7 connected to a pump device 6 is introduced into the hole 4 as shown in FIG. The mortar 8 is cast into the hole 4 via the hose 7. The mortar 8 is made of so-called cement milk in which cement, fly ash, sand, water and the like are mixed.

【0015】その後、モルタル8が固化しないうちに、
図1(d)のように、ケーシングパイプ2を孔4から引
き抜く。このとき、H形鋼5は孔4の中に残る。そし
て、時間が経過してモルタル8が固化すると、モルタル
8の中にH形鋼5が芯材として埋設されたモルタル杭M
が造成される。このようなモルタル杭Mは、所定の間隔
で複数個が順次形成され、止水壁や土留め壁として機能
する。
Thereafter, before the mortar 8 is solidified,
As shown in FIG. 1D, the casing pipe 2 is pulled out from the hole 4. At this time, the H-section steel 5 remains in the hole 4. Then, when the mortar 8 is solidified after a lapse of time, the mortar pile M in which the H-section steel 5 is embedded as a core material in the mortar 8.
Is created. A plurality of such mortar piles M are sequentially formed at predetermined intervals, and function as a water blocking wall or a retaining wall.

【0016】上記工法によると、ケーシング削孔用の小
型ボーリングマシンを用いて造成作業を行なえるので、
道幅の狭い道路においても施工が可能である。また、ケ
ーシング削孔は矢板工法のような大きな騒音が発生せ
ず、周囲に迷惑をかけることもない。さらに、地盤に高
圧がかからないので、地盤が隆起するのを抑止すること
ができ、近隣の家屋等への悪影響を回避できる。
According to the above construction method, the formation work can be performed using a small boring machine for casing drilling.
Construction is possible even on narrow roads. Further, the casing bore does not generate a loud noise unlike the sheet pile method, and does not disturb the surroundings. Furthermore, since high pressure is not applied to the ground, it is possible to prevent the ground from rising, and to avoid adverse effects on nearby houses and the like.

【0017】図2は、本発明の他の実施形態を示してお
り、H形鋼5に緩衝材9を付設した例である。緩衝材9
は、たとえば発泡スチロールの角材から形成されてお
り、接着剤やテープなどによってH形鋼5のフランジ内
部に取り付けられている。H形鋼5と緩衝材9とは、図
1(b)の工程において、一体となって孔4に挿入され
る。この場合も、H形鋼5と緩衝材9をケーシングパイ
プ2の内壁で案内して、スムーズに挿入することができ
る。
FIG. 2 shows another embodiment of the present invention, which is an example in which a cushioning material 9 is attached to an H-section steel 5. Cushioning material 9
Is formed from, for example, a styrene foam square member, and is attached to the inside of the flange of the H-section steel 5 with an adhesive or a tape. The H-section steel 5 and the cushioning material 9 are integrally inserted into the hole 4 in the step of FIG. Also in this case, the H-section steel 5 and the cushioning material 9 can be guided smoothly by the inner wall of the casing pipe 2 and can be smoothly inserted.

【0018】これによると、地盤を伝わる振動が緩衝材
9によって吸収されるので、たとえば施工場所が鉄道の
線路近くである場合に、列車の振動による付近の家屋へ
の影響を軽減することができる。
According to this, the vibration transmitted through the ground is absorbed by the cushioning material 9, so that, for example, when the construction site is near a railway track, the influence of the train vibration on nearby houses can be reduced. .

【0019】図3は、本発明の他の実施形態を示してお
り、上述した緩衝材を付設したH形鋼5を複数の孔に間
隔をおいて(ここでは1つおきに)挿入する例である。
複数の孔4a,4b,4cは、隣接かつ連通して形成さ
れており、孔4aと孔4cに緩衝材9を付設したH形鋼
5が挿入されている。孔4bにはH形鋼5が挿入されて
おらず、円柱状の緩衝材10だけが中央部に挿入されて
いる。この緩衝材10も、緩衝材9と同様に、発泡スチ
ロール等から形成されている。
FIG. 3 shows another embodiment of the present invention, in which an H-shaped steel 5 provided with the above-mentioned cushioning material is inserted into a plurality of holes at intervals (here, every other one). It is.
The plurality of holes 4a, 4b, and 4c are formed adjacent and in communication with each other, and an H-section steel 5 having a buffer material 9 attached to the holes 4a and 4c is inserted. The H-section steel 5 is not inserted in the hole 4b, and only the columnar cushioning material 10 is inserted in the center. The cushioning material 10 is also made of styrene foam or the like, like the cushioning material 9.

【0020】図3の工法は土圧が小さい場合に適してお
り、これによると、H形鋼5の数が半分で済むので、鋼
材を節約してコストを低減することができる。また、H
形鋼5が挿入されていない孔4bにも緩衝材10が挿入
されるので、すべての孔に緩衝材が配設されることにな
り、振動吸収の効果が損なわれることがない。
The method shown in FIG. 3 is suitable for a case where the earth pressure is small. According to this method, the number of the H-shaped steel members 5 can be reduced to half, so that the steel material can be saved and the cost can be reduced. Also, H
Since the buffer material 10 is also inserted into the hole 4b into which the shape steel 5 is not inserted, the buffer material is provided in all the holes, and the effect of vibration absorption is not impaired.

【0021】図4は、本発明の他の実施形態を示してお
り、間隔をおいて削孔された孔と孔との間をモルタルで
埋める例である。11は注入パイプであって、H形鋼5
に設けた支持部14に支持されており、図1(b)の工
程においてH形鋼5とともに孔41内へ挿入される。そ
して、図1(c)および(d)の工程を経た後、図4の
ように、注入パイプ11の下端部に設けたノズル12か
ら、セメントミルクであるモルタル13を、地盤1中へ
中圧程度(たとえば3〜5MPa)で噴射させながら、
注入パイプ11を上方へ引き上げて行く。このモルタル
13は、孔41内に充填されたモルタル8と同じもので
ある。
FIG. 4 shows another embodiment of the present invention, and is an example in which a space between holes drilled at intervals is filled with mortar. Reference numeral 11 denotes an injection pipe,
And is inserted into the hole 41 together with the H-beam 5 in the step of FIG. After the steps of FIGS. 1 (c) and 1 (d), as shown in FIG. 4, a mortar 13 as cement milk is injected into the ground 1 through a nozzle 12 provided at the lower end of the injection pipe 11. While spraying at a degree (for example, 3 to 5 MPa),
The injection pipe 11 is pulled up. The mortar 13 is the same as the mortar 8 filled in the hole 41.

【0022】これによって、地盤1に注入されたモルタ
ル13は、施工が完了している孔42へ達し、孔41と
孔42との間がモルタル13によって埋められる。図5
は、この場合の水平断面図を示しており、埋められたモ
ルタル13の部分は、止水壁のような遮断壁として機能
する。
As a result, the mortar 13 injected into the ground 1 reaches the hole 42 where the construction is completed, and the space between the hole 41 and the hole 42 is filled with the mortar 13. FIG.
Shows a horizontal sectional view in this case, in which the buried mortar 13 functions as a blocking wall such as a water blocking wall.

【0023】これによると、複数の孔を間隔を置いて削
孔するので、孔の数やH形鋼の数が少なくなって工数お
よび施工コストが低減し、工期も短縮できる。また、孔
と孔の間はモルタル13で埋められるので、止水性など
の遮断機能が損なわれることもない。
According to this, since a plurality of holes are drilled at intervals, the number of holes and the number of H-section steels are reduced, so that the number of steps and the construction cost are reduced, and the construction period can be shortened. In addition, since the space between the holes is filled with the mortar 13, the blocking function such as the water stopping property is not impaired.

【0024】図6は、本発明の他の実施形態を示してお
り、図4において注入パイプ11をH形鋼5に支持する
ことに代えて、ケーシングパイプ2の内部に注入パイプ
11を支持した例である。注入パイプ11の先端部のノ
ズル12は、ケーシングパイプ2に形成した吐出孔(図
示省略)から突出している。ケーシングパイプ2を抜く
際に、注入パイプ11も一緒に引き上げられるので、こ
の過程でノズル12からモルタル13を地盤1中へ噴射
することにより、図4の場合と同様に、孔43と施工が
完了している孔44との間がモルタル13によって埋め
られる。
FIG. 6 shows another embodiment of the present invention. In FIG. 4, the injection pipe 11 is supported inside the casing pipe 2 instead of supporting the injection pipe 11 on the H-section steel 5. It is an example. The nozzle 12 at the tip of the injection pipe 11 protrudes from a discharge hole (not shown) formed in the casing pipe 2. When the casing pipe 2 is pulled out, the injection pipe 11 is also pulled up together. In this process, the mortar 13 is injected from the nozzle 12 into the ground 1 to complete the construction with the hole 43 as in the case of FIG. The space between the holes 44 is filled with the mortar 13.

【0025】なお、図4および図6では、ノズル12は
1個しか設けられていないが、ノズル12を複数個設け
てもよい。また、ノズル12を左右の両側に設けて、双
方向にモルタル13を噴射させるようにしてもよい。
Although only one nozzle 12 is provided in FIGS. 4 and 6, a plurality of nozzles 12 may be provided. Further, the mortar 13 may be jetted in both directions by providing the nozzles 12 on both the left and right sides.

【0026】[0026]

【発明の効果】本発明によれば、ケーシング削孔の工法
を用いてモルタル杭を造成するので、ボーリングマシン
は小型のものでよく、作業に広いスペースを必要としな
い。また、大きな騒音が発生せず、地盤の隆起も生じな
いので、近隣の家屋に悪影響を与えることもない。この
ため、特に幅の狭い道路での施工にあたって有効な工法
となる。
According to the present invention, since the mortar pile is formed by using the casing drilling method, the boring machine may be small and does not require a large space for the work. Also, since no loud noise is generated and no ground is raised, there is no adverse effect on neighboring houses. For this reason, it is an effective construction method particularly for construction on narrow roads.

【0027】さらに、本発明では、小径の孔を容易に削
孔できるので、小規模な工事にも対応が可能であるとと
もに、ケーシングパイプによりH形鋼をスムーズに挿入
できるので、作業を効率良く行なえる利点がある。
Further, according to the present invention, a small-diameter hole can be easily drilled, so that it is possible to cope with a small-scale construction, and since the H-section steel can be smoothly inserted by the casing pipe, the work can be efficiently performed. There are advantages to do.

【0028】また、H形鋼に緩衝材を付設することで、
地盤を伝わる振動を吸収することができる。この場合、
H形鋼を複数の孔に間隔をおいて挿入し、H形鋼を挿入
しない孔に緩衝材を挿入することで、鋼材を節約してコ
ストを低減できるとともに、振動吸収効果も維持でき
る。
Further, by providing a cushioning material to the H-section steel,
Vibration transmitted through the ground can be absorbed. in this case,
By inserting the H-shaped steel into the plurality of holes at intervals and inserting the cushioning material into the holes where the H-shaped steel is not inserted, the steel material can be saved, the cost can be reduced, and the vibration absorbing effect can be maintained.

【0029】また、H形鋼を挿入する孔を間隔をおいて
削孔し、孔と孔との間をモルタルで埋めることで、工数
およびコストを低減できるとともに、遮断壁としての機
能も維持できる。
Further, by drilling the holes for inserting the H-shaped steel at intervals, and by filling the space between the holes with mortar, the man-hour and cost can be reduced, and the function as a blocking wall can be maintained. .

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係るモルタル杭の造成方法の一例を示
した工程図である。
FIG. 1 is a process diagram showing an example of a method for forming a mortar pile according to the present invention.

【図2】本発明の他の実施形態を示す水平断面図であ
る。
FIG. 2 is a horizontal sectional view showing another embodiment of the present invention.

【図3】本発明の他の実施形態を示す水平断面図であ
る。
FIG. 3 is a horizontal sectional view showing another embodiment of the present invention.

【図4】本発明の他の実施形態を示す垂直断面図および
水平断面図である。
FIG. 4 is a vertical sectional view and a horizontal sectional view showing another embodiment of the present invention.

【図5】孔間がモルタルで埋められた状態を示す水平断
面図である。
FIG. 5 is a horizontal sectional view showing a state in which a space between holes is filled with mortar.

【図6】本発明の他の実施形態を示す垂直断面図および
水平断面図である。
FIG. 6 is a vertical sectional view and a horizontal sectional view showing another embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 地盤 2 ケーシングパイプ 3 ビット 4 孔 5 H形鋼 6 ポンプ装置 7 注入ホース 8 モルタル 9 緩衝材 10 緩衝材 11 注入パイプ 12 ノズル 13 モルタル M モルタル杭 DESCRIPTION OF SYMBOLS 1 Ground 2 Casing pipe 3 Bit 4 hole 5 H-section steel 6 Pump device 7 Injection hose 8 Mortar 9 Buffer material 10 Buffer material 11 Injection pipe 12 Nozzle 13 Mortar M Mortar pile

フロントページの続き (72)発明者 宇賀 大三郎 大阪府大阪市天王寺区餌差町7番6号 株 式会社大阪防水建設社内 Fターム(参考) 2D040 AA01 AA06 AB01 BB03 CA01 2D041 AA03 DA12 DA13 DB02 EA02 EA04 EB05 FA02 2D049 EA01 EA02 EA07 FB03 FB13 FB20 GA02 GA03 GB08 GC11 GE03 2D050 AA13 CA04 CB42 EE08 Continued on the front page (72) Inventor Daisaburo Uga 7-6, Bashizashi-cho, Tennoji-ku, Osaka-shi, Osaka Prefecture F-term (reference) 2D040 AA01 AA06 AB01 BB03 CA01 2D041 AA03 DA12 DA13 DB02 EA02 EA04 EB05 FA02 2D049 EA01 EA02 EA07 FB03 FB13 FB20 GA02 GA03 GB08 GC11 GE03 2D050 AA13 CA04 CB42 EE08

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】以下の(a)ないし(d)の工程を備えた
ことを特徴とするモルタル杭の造成方法。 (a)ケーシングパイプを用いて地盤に削孔を行なう工
程 (b)削孔された孔にH形鋼を挿入する工程 (c)H形鋼が挿入された孔の内部にモルタルを打設す
る工程 (d)モルタルを打設した後にケーシングパイプを引き
抜く工程
1. A method for forming a mortar pile, comprising the following steps (a) to (d). (A) Step of drilling a ground using a casing pipe (b) Step of inserting an H-shaped steel into the drilled hole (c) Driving mortar into the hole where the H-shaped steel is inserted Step (d) Step of pulling out casing pipe after placing mortar
【請求項2】H形鋼に緩衝材を付設した請求項1に記載
のモルタル杭の造成方法。
2. The method for forming a mortar pile according to claim 1, wherein the H-shaped steel is provided with a cushioning material.
【請求項3】削孔された複数の孔に緩衝材を付設したH
形鋼を間隔をおいて挿入するとともに、H形鋼を挿入し
ない孔に緩衝材を挿入する請求項1に記載のモルタル杭
の造成方法。
3. An H in which a cushioning material is attached to a plurality of drilled holes.
The method according to claim 1, wherein the section steels are inserted at intervals, and a buffer material is inserted into a hole in which the H-section steel is not inserted.
【請求項4】H形鋼を挿入する孔を間隔をおいて削孔
し、孔内に挿入された注入パイプによって地盤中へモル
タルを噴射することにより、孔と孔との間をモルタルで
埋める請求項1に記載のモルタル杭の造成方法。
4. A hole for inserting an H-section steel is formed at intervals, and mortar is injected into the ground by an injection pipe inserted into the hole to fill the space between the holes with mortar. The method for forming a mortar pile according to claim 1.
JP2000237889A 2000-08-07 2000-08-07 Construction method for mortar pile Pending JP2002047653A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000237889A JP2002047653A (en) 2000-08-07 2000-08-07 Construction method for mortar pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000237889A JP2002047653A (en) 2000-08-07 2000-08-07 Construction method for mortar pile

Publications (1)

Publication Number Publication Date
JP2002047653A true JP2002047653A (en) 2002-02-15

Family

ID=18729672

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000237889A Pending JP2002047653A (en) 2000-08-07 2000-08-07 Construction method for mortar pile

Country Status (1)

Country Link
JP (1) JP2002047653A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006299601A (en) * 2005-04-19 2006-11-02 Ciatec Ltd Construction method for driving cast-in-place pile
JP2012107444A (en) * 2010-11-18 2012-06-07 Takenaka Komuten Co Ltd Earth retaining wall and construction method of earth retaining wall
JP2020193527A (en) * 2019-05-30 2020-12-03 鹿島建設株式会社 Pile built-in pumping well, and underground water pumping method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006299601A (en) * 2005-04-19 2006-11-02 Ciatec Ltd Construction method for driving cast-in-place pile
JP2012107444A (en) * 2010-11-18 2012-06-07 Takenaka Komuten Co Ltd Earth retaining wall and construction method of earth retaining wall
JP2020193527A (en) * 2019-05-30 2020-12-03 鹿島建設株式会社 Pile built-in pumping well, and underground water pumping method
JP7232712B2 (en) 2019-05-30 2023-03-03 鹿島建設株式会社 Pile-integrated pumping well and groundwater pumping method

Similar Documents

Publication Publication Date Title
CN102146672B (en) Method for constructing pile foundation in karst area
KR101067707B1 (en) The earth retaining wall and waterproof construction technique for which cast in place concrete pile and grouting column was used
KR102009077B1 (en) Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type
KR101378814B1 (en) Microfile construction method using the jet grouting
JP2008031828A (en) Construction method of foundation of structure
KR100375020B1 (en) a pole for mud wall and constrution method of fence for mud
CN110438851A (en) A kind of rotary churning pile vibration isolation barrier and its construction method
KR100933230B1 (en) Reinforcing grouting device
JP2002047653A (en) Construction method for mortar pile
JP2019039140A (en) Method for constructing ground improvement body and method for constructing pile
CN108194101B (en) Tunnel construction process
JP4485006B2 (en) Construction method for underground structures
JP4339803B2 (en) Anti-vibration pile, anti-vibration wall using the same and construction method thereof
JP2011012443A (en) Construction method for soil cement structure and the soil cement structure
KR100996444B1 (en) Method for carrying out improved micro pile and improved micro pile and ribbed section pipe of the improved micro pile
JP2001234531A (en) Steel pipe pile filled with soil cement and method for building the same
KR102028182B1 (en) Construction method of pillar type underground structure using excavation system for structural casing burial
JPH1025734A (en) Bearing-pile reinforcing structure of existing structure and reinforcing method thereof
JP4633273B2 (en) Earth retaining method and equipment
JP2008063787A (en) Liquefaction preventing structure
WO2009139510A1 (en) Construction method for continuous cut-off wall using overlap casing
JP2009062792A (en) Ground vibration propagation restraining structure and its construction method
JP2019183601A (en) Method for building wall-like improvement body
KR102479503B1 (en) Casingless Micro - Pile Construction Method And Construction Device
JP3755472B2 (en) Ground improvement method

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040727

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040817

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20050404