JP2002021489A - Manufacturing method for compound segment - Google Patents
Manufacturing method for compound segmentInfo
- Publication number
- JP2002021489A JP2002021489A JP2000201499A JP2000201499A JP2002021489A JP 2002021489 A JP2002021489 A JP 2002021489A JP 2000201499 A JP2000201499 A JP 2000201499A JP 2000201499 A JP2000201499 A JP 2000201499A JP 2002021489 A JP2002021489 A JP 2002021489A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- plate
- steel shell
- joint
- plates
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
- Lining And Supports For Tunnels (AREA)
- Moulds, Cores, Or Mandrels (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は合成セグメントの製
造方法に関するものであり、特に、コンクリートの打設
と共にセグメントの内面外周にコンクリート溝を容易
に、且つ、精度よく形成することができる合成セグメン
トの製造方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for manufacturing a synthetic segment, and more particularly to a method for manufacturing a synthetic segment in which a concrete groove can be easily and accurately formed on the inner peripheral surface of the segment while the concrete is being poured. It relates to a manufacturing method.
【0002】[0002]
【従来の技術】従来の合成セグメントは図6(a)に示
すように、外周側に円弧状に設けられるスキンプレート
5と該スキンプレート5の両側部に配設される鋼板から
なる主桁4,4と該スキンプレート5の両端部に配設さ
れる継手板3,3とで鋼殻1を構成し、その内部に複数
の補強筋6,6…と中央部にグラウト注入管7とを配設
する。更に、該継手板3,3には、各セグメントピース
を円周方向にリング状に組立てるための継手ボルト孔
2,2を設け、又、該主桁4,4にもセグメントリング
同士を結合するための継手ボルト孔2,2,2を設けて
いる。2. Description of the Related Art As shown in FIG. 6 (a), a conventional synthetic segment is a main girder 4 composed of a skin plate 5 provided on an outer peripheral side in an arc shape and steel plates provided on both sides of the skin plate 5. , 4 and joint plates 3, 3 arranged at both ends of the skin plate 5, constitute a steel shell 1 having a plurality of reinforcing bars 6, 6,... And a grout injection pipe 7 in the center. Arrange. Further, the joint plates 3, 3 are provided with joint bolt holes 2, 2 for assembling the respective segment pieces in a ring shape in the circumferential direction, and the segment rings are also connected to the main beams 4, 4. Bolt holes 2, 2, 2 are provided.
【0003】その後、図6(b)に示すように、該鋼殻
1の内空にミキサー車(図示せず)等からコンクリート
10を充填して合成セグメントを製造する。その際、該
継手板3,3及び該主桁4,4の該継手ボルト孔2,2
…に対応する該鋼殻1内にボルトボックス(図示せず)
を配設し、ボルト操作用空間部8,8…を設ける。又、
該コンクリート10の充填後に該合成セグメントの内面
のコンクリートは、該継手板3,3及び該主桁4,4の
高さを基準として鏝仕上げを行い、面一に形成する。従
って、該鋼殻1と該コンクリート10との内面は共にフ
ラットな構造となる。After that, as shown in FIG. 6 (b), concrete 10 is filled into the inside of the steel shell 1 from a mixer truck (not shown) or the like to produce a composite segment. At this time, the joint bolt holes 2, 2 of the joint plates 3, 3 and the main girders 4, 4
A bolt box (not shown) in the steel shell 1 corresponding to ...
Are provided, and bolt operation spaces 8, 8,... Are provided. or,
After the concrete 10 is filled, the concrete on the inner surface of the composite segment is iron-finished based on the height of the joint plates 3 and 3 and the main girders 4 and 4, and is formed flush. Therefore, the inner surfaces of the steel shell 1 and the concrete 10 both have a flat structure.
【0004】更に、図示は省略するが、シールド機によ
る地山の掘削と共に、該シールド機内のエレクターで該
合成セグメントを円筒状に組み立てトンネルを構築する
が、該合成セグメントはコンクリート面を該トンネルの
内部に向けて組み立てられる。[0004] Further, although not shown, a tunnel is constructed by assembling the composite segment into a cylindrical shape by an erector in the shield machine together with excavation of the ground by the shield machine. Assembled inside.
【0005】[0005]
【発明が解決しようとする課題】前述したように、合成
セグメントの内面側でトンネル内部を形成するので、前
記鋼殻同士の継手部から該鋼殻を腐食させる水等の物質
が侵入する危険性が生じ、防錆処理を施す必要がある。As described above, since the inside of the tunnel is formed on the inner surface side of the composite segment, there is a danger that a substance such as water which corrodes the steel shells enters from the joint between the steel shells. Occurs and it is necessary to perform rust prevention treatment.
【0006】通常、該トンネルの構築に当って該合成セ
グメントの内側にモルタル等を吹き付ける二次覆工が行
われるならば、該継手部の隙間が埋められ、前記内面が
フラットな構造の合成セグメントを用いても問題はな
い。Normally, if a secondary lining for spraying mortar or the like on the inside of the composite segment is performed in constructing the tunnel, the gap between the joints is filled, and the composite segment having a flat inner surface is used. There is no problem with using.
【0007】しかし、近年、合成セグメントを内水圧対
応無二次覆工用として使用する際には、前記防錆処理を
行うため前記鋼殻内のコンクリートを増し打ちしてコン
クリート溝(コーキング溝)を形成する必要がある。該
コンクリート溝の形成は、コンクリートの増し打ちのた
めの基準がないので困難な作業となる。[0007] However, in recent years, when the synthetic segment is used for a secondary lining for internal water pressure, concrete in the steel shell is additionally struck in order to perform the rust prevention treatment, and concrete grooves (caulking grooves) are formed. Need to be formed. Forming the concrete grooves is a difficult task because there is no standard for concrete overfilling.
【0008】そこで、コンクリートの打設と共にセグメ
ントの内面外周にコンクリート溝を容易に形成すること
ができる合成セグメントの製造方法を得るために解決す
べき技術的課題が生じてくるのであり、本発明は該課題
を解決することを目的とする。Therefore, there arises a technical problem to be solved in order to obtain a method of manufacturing a composite segment in which a concrete groove can be easily formed on the inner periphery of the inner surface of the segment together with the casting of concrete. An object is to solve the problem.
【0009】[0009]
【課題を解決するための手段】本発明は上記目的を達成
するために提案せられたものであり、継手ボルト孔を有
する継手板及び主桁並びにスキンプレートで外周を囲繞
する鋼殻の内空にコンクリートを充填してなる合成セグ
メントの製造方法に於て、該継手板及び該主桁の上部よ
り直角に該鋼殻外へ所定長さ突出させるプレートを該継
手ボルト孔に着脱自在に取着して、該継手板及び該主桁
に沿って全周に配設した後、該鋼殻の内部に該プレート
の上面まで該コンクリートを充填し、その後、該プレー
トを取り外し、該コンクリートの外周に沿ってコンクリ
ート溝を形成する合成セグメントの製造方法、及び、前
記鋼殻の内部に前記コンクリートを充填する際、前記プ
レートの上部にコンクリート押え板をコッタで該プレー
トに取着して架設すると共に、前記継手板の近傍にコン
クリート投入口を設ける合成セグメントの製造方法を提
供するものである。SUMMARY OF THE INVENTION The present invention has been proposed in order to achieve the above object, and has a joint plate having a joint bolt hole, a main girder, and an inner space of a steel shell surrounding the outer periphery with a skin plate. In the method for manufacturing a composite segment in which concrete is filled into a joint, a plate for projecting a predetermined length out of the steel shell at right angles from the upper part of the joint plate and the main girder is detachably attached to the joint bolt hole. Then, after the joint plate and the main girder are disposed all around, the concrete is filled into the inside of the steel shell up to the upper surface of the plate, and then the plate is removed. A method for manufacturing a composite segment forming a concrete groove along the same, and when filling the steel shell with the concrete, a concrete holding plate is attached to the plate with a cotter above the plate and erected. Rutotomoni, in the vicinity of the joint plate is to provide a method of manufacturing a synthetic segments to provide a concrete inlet.
【0010】[0010]
【発明の実施の形態】以下、本発明の一実施の形態を図
1乃至図5に従って詳述する。尚、従来例と同一構成部
分については同一符号を用いて説明するものとする。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the present invention will be described below in detail with reference to FIGS. The same components as those of the conventional example will be described using the same reference numerals.
【0011】図1は合成セグメントを製造するための鋼
殻1の斜視図である。該鋼殻1は外周側に円弧状に設け
られるスキンプレート5とリング方向に所定間隔で配設
する鋼板からなる主桁4,4と円周方向に所定間隔で配
設する鋼板からなる継手板3,3とで構成される。該主
桁4,4の側面形状は、該スキンプレート5の曲率と同
じ形状を有し、該スキンプレート5に対し垂直に立設す
ると共に該継手板3,3は矩形状とし、且つ、円周方向
の継手形状に合せて傾斜して立設される。尚、該主桁
4,4と該継手板3,3の上部端面位置は同一高さに形
成される。FIG. 1 is a perspective view of a steel shell 1 for manufacturing a composite segment. The steel shell 1 is composed of main plates 4 and 4 made of steel plates arranged at a predetermined interval in the ring direction with a skin plate 5 provided in an arc shape on the outer peripheral side and a joint plate made of steel plates arranged at a predetermined interval in the circumferential direction. 3 and 3. The side shapes of the main girders 4 and 4 have the same shape as the curvature of the skin plate 5, and stand upright with respect to the skin plate 5, and the joint plates 3 and 3 have a rectangular shape and a circular shape. It is erected in accordance with the joint shape in the circumferential direction. The main girders 4, 4 and the upper end face positions of the joint plates 3, 3 are formed at the same height.
【0012】又、該主桁4,4の上部近傍には所定間隔
で各合成セグメントをリング方向に結合するための継手
ボルト孔2,2…が開穿され、更に、該継手板3,3の
上部近傍にも所定間隔で各合成セグメントを円周方向に
結合するための継手ボルト孔2,2…が開穿されてい
る。In the vicinity of the upper portions of the main girders 4, 4, joint bolt holes 2, 2,... For connecting the respective composite segments in the ring direction are formed at predetermined intervals. Are formed at predetermined intervals in the vicinity of the upper part of the joint bolt holes 2, 2,... For connecting the respective composite segments in the circumferential direction.
【0013】次に図3(a)に示すように、該主桁4,
4及び該継手板3,3の上部より直角に前記鋼殻1外へ
所定長さ突出させた鋼製のプレート11をブラケット1
2a(12b)に固着し、該ブラケット12a(12
b)に開穿されたボルト孔と前記継手ボルト孔2とにボ
ルト13(図1参照)を挿入し、該主桁4,4及び該継
手板3,3とに夫々着脱自在に取着する。Next, as shown in FIG.
4 and a steel plate 11 projecting a predetermined length out of the steel shell 1 at right angles from the upper portions of the joint plates 3 and 3.
2a (12b) and the bracket 12a (12b).
A bolt 13 (see FIG. 1) is inserted into the bolt hole drilled in b) and the joint bolt hole 2, and detachably attached to the main girders 4, 4 and the joint plates 3, 3, respectively. .
【0014】尚、該ブラケット12aはアングル材を使
用し、該プレート11に対しL字形に固着する。又、該
ブラケット12a(12b)を用いず、該プレート11
自体をL字形に形成してもよい。The bracket 12a uses an angle material and is fixed to the plate 11 in an L-shape. Also, the plate 11 is not used without using the bracket 12a (12b).
It may itself be formed in an L-shape.
【0015】更に、該プレート11の厚さは後述するコ
ンクリート溝(コーキング溝)15の深さと同一とし、
該プレート11の該鋼殻1側の先端部11aは該コンク
リート溝15の形状に合せて上部に開口状にテーパを付
けるものとする。従って、図1に示すように、該鋼殻1
の外周を形成する該主桁4,4及び該継手板3,3の上
部全周に該プレート11を配設することになる。尚、該
プレート11は鋼製に限らずプラスチック材、木材等で
形成してもよい。Further, the thickness of the plate 11 is the same as the depth of a concrete groove (caulking groove) 15 described later,
The tip 11a of the plate 11 on the side of the steel shell 1 is tapered so as to have an opening at an upper portion in accordance with the shape of the concrete groove 15. Therefore, as shown in FIG.
The plate 11 is disposed on the entire periphery of the main girders 4 and 4 and the joint plates 3 and 3 which form the outer periphery of the joint. The plate 11 is not limited to steel and may be formed of a plastic material, wood, or the like.
【0016】図4(a)は該主桁4及び該継手板3上に
該プレート11,11を取付けた状態を示す拡大斜視図
である。FIG. 4A is an enlarged perspective view showing a state in which the plates 11, 11 are mounted on the main beam 4 and the joint plate 3.
【0017】尚、前記継手ボルト孔2,2…に前記ブラ
ケット12a(12b)を取着する際、該鋼殻1内に後
述するコンクリート10の打設後にボルト操作用空間部
8を形成するためのボルトボックス14を同時に取着し
て置く。該ボルトボックス14の上面位置は、後述する
該コンクリート10の上面10aと同一高さとする。When the brackets 12a (12b) are attached to the joint bolt holes 2, 2,..., A bolt operation space 8 is formed after the concrete 10 described below is poured into the steel shell 1. Bolt box 14 is attached and placed at the same time. The position of the upper surface of the bolt box 14 is the same as the upper surface 10a of the concrete 10 described later.
【0018】次に、図2により該鋼殻1内への該コンク
リート10の打設方法を説明する。先ず、前記プレート
11を配設した該鋼殻1を水平且つ平行に設置されたH
型鋼21,21上に水平に載置する。その後、前記継手
板3,3側両端部に設ける後述するホッパ16設置場所
を除いた該鋼殻1上にコンクリート押え板19を取り付
ける。該コンクリート押え板19は、前記主桁4,4上
に配設する該プレート11,11上に沿って架設され、
両端を該プレート11,11の所定箇所に設置されるコ
ッタ20,20…で止着してコンクリート打設時の流出
を防止する。尚、該コンクリート押え板19の内面には
脱型を容易にするため、コンクリート打設前に剥離剤を
塗布しておくとよい。Next, a method of placing the concrete 10 into the steel shell 1 will be described with reference to FIG. First, the steel shell 1 on which the plate 11 is disposed is placed on a horizontal and parallel H
It is placed horizontally on the shape steels 21 and 21. Thereafter, a concrete holding plate 19 is mounted on the steel shell 1 except for a place where a hopper 16 described later provided at both ends of the joint plates 3 and 3 is provided. The concrete holding plate 19 is erected along the plates 11, 11 provided on the main girders 4, 4.
Both ends are fixed with cotters 20, 20,... Installed at predetermined locations on the plates 11, 11, to prevent runoff during concrete casting. It is preferable to apply a release agent to the inner surface of the concrete holding plate 19 before casting the concrete in order to facilitate removal.
【0019】次に、コンクリート打設のためのホッパ1
6を該継手板3,3の近傍に設置する。該ホッパ16
は、側板17a,17aを前記主桁4,4の内面に合せ
て略三角形状に夫々立設し、且つ、正面板17bを該側
板17a,17a間に固着して前記コンクリート押え板
19上から立設し、上部及び下部に所定の大きさのコン
クリート投入口18が開口されている簡易なものであ
る。コンクリートの打設速度を早めるため図示のホッパ
16は前記鋼殻1の両端に設けたが、小さなセグメント
の場合には片側だけでもよい。Next, a hopper 1 for placing concrete
6 is installed near the joint plates 3 and 3. The hopper 16
The side plates 17a, 17a are erected in a substantially triangular shape so as to match the inner surfaces of the main girders 4, 4, respectively, and the front plate 17b is fixed between the side plates 17a, 17a so that the concrete holding plate 19 It is a simple one that stands upright and has concrete input ports 18 of a predetermined size opened in the upper and lower parts. Although the illustrated hoppers 16 are provided at both ends of the steel shell 1 in order to increase the concrete casting speed, only one side may be provided for small segments.
【0020】コンクリート打設は、ミキサー車(図示せ
ず)等から該コンクリート投入口18へコンクリート1
0を投入し、該鋼殻1内に充填した後、前記ホッパ16
を撤去し撤去部のコンクリート10を鏝等で均す。次
に、ある程度該コンクリート10が緩まなくなった時点
で前記コッタ20,20…を外して前記コンクリート押
え板19を撤去する。更に、前記プレート11,11…
に沿って鏝等でコンクリート面10a(図3参照)を均
す。その後、所定時間経過後、大鏝でコンクリート面1
0aの粗仕上げを行う。更に、所定時間経過後、鏝でコ
ンクリート面10aの中仕上げを行う。更に又、所定時
間経過後、該プレート11,11…及び前記ボルトボッ
クス14,14…を取り外し、最終鏝仕上げを行う。Concrete is poured from a mixer truck (not shown) or the like to the concrete inlet 18 into the concrete 1.
0 and charged into the steel shell 1, the hopper 16
Is removed, and the concrete 10 at the removed portion is leveled with a trowel or the like. Next, when the concrete 10 does not loosen to some extent, the cotters 20, 20,... Are removed and the concrete holding plate 19 is removed. Further, the plates 11, 11 ...
The concrete surface 10a (see FIG. 3) is leveled by a trowel or the like along the line. After a lapse of a predetermined time, the concrete surface 1
A rough finish of 0a is performed. Further, after a lapse of a predetermined time, the concrete surface 10a is semi-finished with a trowel. Further, after a lapse of a predetermined time, the plates 11, 11,... And the bolt boxes 14, 14,.
【0021】従って、仕上がりは図4(b)に示すよう
に前記主桁4及び前記継手板3の上部にコンクリート1
0が該プレート11,11により精度よく均等に所定高
増し打ちされたコンクリート溝(コーキング溝)15,
15…が形成される。次に、翌朝、仕上がり状態のセグ
メントを養生場に運搬し、養生を行い強度の強い合成セ
グメントを完成させる。Accordingly, as shown in FIG. 4B, the concrete 1 is placed on the main girder 4 and the joint plate 3 as shown in FIG.
0 is a concrete groove (caulking groove) 15, which has been beaten by the plates 11 and 11 accurately and evenly to a predetermined height.
15 are formed. Next, on the next morning, the finished segment is transported to a curing station, where it is cured to complete a strong composite segment.
【0022】図5は完成した合成セグメントの1ピース
の斜視図であり、該合成セグメントの内面外周に該コン
クリート溝15,15…が形成されると共に、前記主桁
4及び前記継手板3の前記継手ボルト孔2,2…の前記
コンクリート10側には、前記ボルト操作用空間部8,
8…が形成される。又、該合成セグメントの中央部には
グラウト注入管7が埋設されている。FIG. 5 is a perspective view of one piece of the completed composite segment, in which the concrete grooves 15, 15... Are formed on the outer periphery of the inner surface of the composite segment, and the main girder 4 and the joint plate 3 are formed. On the concrete 10 side of the joint bolt holes 2, 2,.
8 are formed. A grout injection pipe 7 is buried in the center of the synthetic segment.
【0023】次に、該合成セグメントをシールド機(図
示せず)の後方でリング状に組み立て、円筒状のトンネ
ルを構築するが、該トンネルを構成する合成セグメント
の隣り合う前記主桁4,4及び前記継手板3,3の上部
は図3(b)に示すようにコンクリート溝15が形成さ
れ、該合成セグメントが内水圧対応無二次覆工用として
使用された場合には該コンクリート溝15をコーキング
溝として用い防錆処理を行う。Next, the composite segment is assembled in a ring shape behind a shield machine (not shown) to construct a cylindrical tunnel, and the main girders 4, 4 adjacent to the composite segment forming the tunnel are constructed. 3 (b), a concrete groove 15 is formed in the upper part of the joint plates 3, 3, and when the composite segment is used for internal water pressure-free secondary lining, the concrete groove 15 is formed. Is used as a caulking groove to perform rust prevention treatment.
【0024】尚、本発明は、本発明の精神を逸脱しない
限り種々の改変を為すことができ、そして、本発明が該
改変されたものに及ぶことは当然である。The present invention can be variously modified without departing from the spirit of the present invention, and it goes without saying that the present invention extends to the modified ones.
【0025】[0025]
【発明の効果】以上説明したように、請求項1記載の発
明は、鋼殻を形成する継手板及び主桁の上部より直角に
該鋼殻外へ所定長さ突出させるプレートを全周に配設し
てコンクリートを充填するので、該鋼殻の上部外周にコ
ンクリートの打設と同時に該プレートをガイドとしてコ
ンクリート溝を容易に、且つ、精度よく形成することが
できる。As described above, according to the first aspect of the present invention, the joint plate forming the steel shell and the plate projecting a predetermined length outside the steel shell at right angles from the upper part of the main girder are arranged on the entire circumference. Since the concrete is filled with concrete, the concrete groove can be easily and accurately formed using the plate as a guide at the same time as the concrete is poured on the upper outer periphery of the steel shell.
【0026】又、該プレートの厚さ、形状等を変化させ
ることにより任意の深さ、形状のコンクリート溝が形成
できる。更に、該プレートを主桁及び継手板の継手ボル
ト孔に着脱自在に取着して配設するので、該主桁及び該
継手板の該継手ボルト孔を加工することなくそのまま利
用できると共に取り付け、取り外しが容易であり、該プ
レートをそのまま次の合成セグメントの製造に転用する
ことができる。Also, by changing the thickness, shape, etc. of the plate, a concrete groove having an arbitrary depth and shape can be formed. Further, since the plate is detachably attached to the main girder and the joint bolt hole of the joint plate and disposed, the joint girder hole of the main girder and the joint plate can be used as it is without being processed and attached. It is easy to remove and the plate can be diverted directly to the production of the next synthetic segment.
【0027】請求項2記載の発明は、前記請求項1記載
の発明の効果に加えて該プレートの上部にコンクリート
押え板をコッタで該プレートに取着して架設し、更に、
該継手板の近傍にコンクリート投入口を設けるので、前
記鋼殻内に迅速にコンクリートを充填させることができ
ると共に、コンクリート押え板によりコンクリートの流
出を防止し、且つ、コンクリート内面形状を容易に形成
できる。According to a second aspect of the present invention, in addition to the effects of the first aspect of the present invention, a concrete pressing plate is attached to the plate by a cotter on the upper portion of the plate and erected.
Since the concrete inlet is provided near the joint plate, concrete can be quickly filled in the steel shell, and concrete can be prevented from flowing out by the concrete holding plate, and the concrete inner surface shape can be easily formed. .
【0028】斯くして、合成セグメントの内面外周部に
容易に、且つ、精度よくコンクリート溝を形成でき、該
コンクリート溝をコーキング溝として利用できる等、正
に諸種の著大なる効果を奏する発明である。Thus, concrete grooves can be easily and accurately formed on the outer peripheral portion of the inner surface of the composite segment, and the concrete grooves can be used as caulking grooves. is there.
【図1】本発明の一実施の形態を示し、合成セグメント
を製造するための鋼殻の斜視図。1 shows an embodiment of the present invention and is a perspective view of a steel shell for producing a composite segment.
【図2】鋼殻内にコンクリートを充填させる状態を示す
鋼殻の斜視図。FIG. 2 is a perspective view of a steel shell showing a state in which concrete is filled in the steel shell.
【図3】(a)プレートの取付け状態を示す図1のイ−
断面図。 (b)図3(a)の口詳細を示し、合成セグメントの継
手部の断面図。FIG. 3 (a) shows the state of attachment of a plate.
Sectional view. (B) is a cross-sectional view of the joint portion of the synthetic segment, showing the details of the mouth in FIG.
【図4】(a)プレートの取付け状態を示す一部切欠き
斜視図。 (b)コンクリート溝の形成状態を示す一部切欠き斜視
図。FIG. 4A is a partially cutaway perspective view showing a mounting state of a plate. (B) A partially cutaway perspective view showing the state of formation of a concrete groove.
【図5】合成セグメントの斜視図。FIG. 5 is a perspective view of a synthetic segment.
【図6】(a)従来例の鋼殻の斜視図。 (b)従来例の合成セグメントの斜視図。FIG. 6A is a perspective view of a conventional steel shell. (B) A perspective view of a conventional synthetic segment.
1 鋼殻 2 継手ボルト孔 3 継手板 4 主桁 5 スキンプレート 10 コンクリート 11 プレート 15 コンクリート溝 18 コンクリート投入口 19 コンクリート押え板 20 コッタ DESCRIPTION OF SYMBOLS 1 Steel shell 2 Joint bolt hole 3 Joint plate 4 Main girder 5 Skin plate 10 Concrete 11 Plate 15 Concrete groove 18 Concrete inlet 19 Concrete holding plate 20 Cotta
フロントページの続き Fターム(参考) 2D055 BA01 BB01 EB05 EB10 GD05 KA00 KB04 4G053 AA01 BB09 BD04 4G058 GA01 GB02 GC03 GE06 GF00Continued on front page F-term (reference) 2D055 BA01 BB01 EB05 EB10 GD05 KA00 KB04 4G053 AA01 BB09 BD04 4G058 GA01 GB02 GC03 GE06 GF00
Claims (2)
びにスキンプレートで外周を囲繞する鋼殻の内空にコン
クリートを充填してなる合成セグメントの製造方法に於
て、該継手板及び該主桁の上部より直角に該鋼殻外へ所
定長さ突出させるプレートを該継手ボルト孔に着脱自在
に取着して、該継手板及び該主桁に沿って全周に配設し
た後、該鋼殻の内部に該プレートの上面まで該コンクリ
ートを充填し、その後、該プレートを取り外し、該コン
クリートの外周に沿ってコンクリート溝を形成すること
を特徴とする合成セグメントの製造方法。1. A method for manufacturing a composite segment comprising a joint plate having a joint bolt hole, a main girder, and a concrete shell filled with concrete inside a steel shell surrounding the outer periphery with a skin plate. A plate for projecting a predetermined length out of the steel shell at a right angle from the upper part of the girder is detachably attached to the joint bolt hole, and disposed around the joint plate and the main girder all around. A method for manufacturing a composite segment, comprising: filling a concrete inside a steel shell up to an upper surface of the plate; removing the plate; and forming a concrete groove along an outer periphery of the concrete.
填する際、前記プレートの上部にコンクリート押え板を
コッタで該プレートに取着して架設すると共に、前記継
手板の近傍にコンクリート投入口を設けることを特徴と
する請求項1記載の合成セグメントの製造方法。2. When the concrete is filled in the inside of the steel shell, a concrete holding plate is attached to the plate with a cotter on the plate and erected, and a concrete inlet is provided near the joint plate. The method for producing a synthetic segment according to claim 1, wherein the composite segment is provided.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000201499A JP3406280B2 (en) | 2000-07-03 | 2000-07-03 | Manufacturing method of synthetic segment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000201499A JP3406280B2 (en) | 2000-07-03 | 2000-07-03 | Manufacturing method of synthetic segment |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2002021489A true JP2002021489A (en) | 2002-01-23 |
JP3406280B2 JP3406280B2 (en) | 2003-05-12 |
Family
ID=18699184
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000201499A Expired - Fee Related JP3406280B2 (en) | 2000-07-03 | 2000-07-03 | Manufacturing method of synthetic segment |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3406280B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2015168986A (en) * | 2014-03-07 | 2015-09-28 | Jfe建材株式会社 | Jig for manufacturing concrete-filled steel segment |
CN108748653A (en) * | 2018-07-26 | 2018-11-06 | 西南交通大学 | A kind of shield tunnel sheet mold making multi-form tenon |
CN109676749A (en) * | 2018-12-21 | 2019-04-26 | 中铁十四局集团房桥有限公司 | The method of tunnel rail flowering structure prefabricated section mold and its prefabricated tunnel rail flowering structure |
-
2000
- 2000-07-03 JP JP2000201499A patent/JP3406280B2/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2015168986A (en) * | 2014-03-07 | 2015-09-28 | Jfe建材株式会社 | Jig for manufacturing concrete-filled steel segment |
CN108748653A (en) * | 2018-07-26 | 2018-11-06 | 西南交通大学 | A kind of shield tunnel sheet mold making multi-form tenon |
CN108748653B (en) * | 2018-07-26 | 2023-06-23 | 西南交通大学 | Shield tunnel segment mold capable of manufacturing multi-form tenons |
CN109676749A (en) * | 2018-12-21 | 2019-04-26 | 中铁十四局集团房桥有限公司 | The method of tunnel rail flowering structure prefabricated section mold and its prefabricated tunnel rail flowering structure |
CN109676749B (en) * | 2018-12-21 | 2023-12-01 | 中铁十四局集团房桥有限公司 | Prefabricated block mold for tunnel rail lower structure and method for prefabricating tunnel rail lower structure by using prefabricated block mold |
Also Published As
Publication number | Publication date |
---|---|
JP3406280B2 (en) | 2003-05-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20070059690A (en) | Mold-concrete composite crossbeam and construction method using the same | |
CN105275097A (en) | A post-cast strip water-stop steel plate and demolition-free template net installing method | |
JP3146396B2 (en) | Construction method of composite underground structure using soil cement column wall | |
CN113334568B (en) | Segment whole ring structure and segment whole ring prefabrication method | |
JP2002021489A (en) | Manufacturing method for compound segment | |
JP2001214534A (en) | Anchor structure and its work execution method | |
JP7154506B2 (en) | Attachment structure of permeable sheet in formwork for tunnel lining | |
CN110984691A (en) | Construction method of enclosure upright post | |
JPH06235297A (en) | Synthetic tunnel liner and its manufacture | |
JP2000159290A (en) | Tank and structural material for tank | |
JPH0813692A (en) | Columnar structure and construction method therefor | |
JPH05287802A (en) | Construction method of centrifugal casting pca column | |
JPH0349199Y2 (en) | ||
US5108671A (en) | Concrete formwork and method for forming a draft tube | |
JP7449540B2 (en) | How to install plate members for joint formation | |
JP7360128B2 (en) | How to pull out and remove the joint forming plate member | |
JPS61290137A (en) | Construction of columnar pillar | |
JPH05287983A (en) | Construction of underground space having long and large diametral dimension | |
JPH08100432A (en) | Footing device | |
JP3035500B2 (en) | Manufacturing method of precast concrete splice wall for use in special part of electric wire joint groove | |
JP3316587B2 (en) | Plate of steel shell joint and its casting method in outer shell preceding tunnel method | |
JPH04194157A (en) | Formation of precast building column | |
JP3567387B2 (en) | How to build an underground skeleton | |
JPH04131204A (en) | Composite concrete column and manufacture thereof | |
JPS59213815A (en) | Concrete pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090307 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090307 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100307 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110307 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110307 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120307 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130307 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130307 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140307 Year of fee payment: 11 |
|
LAPS | Cancellation because of no payment of annual fees |