JP2001303550A - Method for cutting off water at intersection of soil cement continuous wall - Google Patents

Method for cutting off water at intersection of soil cement continuous wall

Info

Publication number
JP2001303550A
JP2001303550A JP2000119672A JP2000119672A JP2001303550A JP 2001303550 A JP2001303550 A JP 2001303550A JP 2000119672 A JP2000119672 A JP 2000119672A JP 2000119672 A JP2000119672 A JP 2000119672A JP 2001303550 A JP2001303550 A JP 2001303550A
Authority
JP
Japan
Prior art keywords
continuous wall
continuous
joint hole
constructed
intersection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000119672A
Other languages
Japanese (ja)
Inventor
Hisashi Tarumi
尚志 垂水
Masaru Tateyama
勝 舘山
Atsuo Fukuda
厚生 福田
Shigeru Yoshida
茂 吉田
Shuji Kami
上  周史
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Railway Technical Research Institute
Tenox Corp
Original Assignee
Railway Technical Research Institute
Tenox Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Railway Technical Research Institute, Tenox Corp filed Critical Railway Technical Research Institute
Priority to JP2000119672A priority Critical patent/JP2001303550A/en
Publication of JP2001303550A publication Critical patent/JP2001303550A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To prevent leaks due to a cold joint at the intersection of intersecting soil cement continuous walls constructed at different times. SOLUTION: A joint hole 5 filled with a solution containing a non-setting water-impermeable material is formed in advance at the intersection of a previously constructed continuous wall 41 and another continuous wall 44 constructed afterwards, and the ends of the intersecting continuous walls 41 and 44 are interconnected within the joint hole 5.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は互いに交差し、時
間差が付いて構築されるソイルセメント連続壁の交差部
におけるコールドジョイントによる漏水を防止するソイ
ルセメント連続壁交差部の止水方法に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of stopping water at a crossing point of a continuous soil cement wall to prevent water leakage due to a cold joint at the crossing point of the continuous wall of the cement cement which is constructed with a time difference. .

【0002】[0002]

【従来の技術及び発明が解決しようとする課題】切削刃
を有する無端チェーンをカッターポストの周囲で循環さ
せ、地中に固化材液を吐出しながら、カッターポストを
地中で横行させて構築されるソイルセメントの連続壁を
例えば山止め壁や遮水壁として箱形に周回させて、もし
くはL形等に交差させて構築する場合、または既設の連
続壁に交差させて新規に連続壁を構築する場合、先行し
て構築される連続壁と後から構築される連続壁との交差
部には連続壁からなる構築物の外部からの漏水防止上、
連続性が要求される。
2. Description of the Related Art An endless chain having a cutting blade is circulated around a cutter post, and the cutter post is traversed underground while discharging solidified material liquid into the ground. For example, when the continuous wall of soil cement is built around a box shape as a retaining wall or a water impervious wall, or crossed with an L shape, etc., or a new continuous wall is built by crossing an existing continuous wall. In the case of, in order to prevent water leakage from the outside of the structure consisting of the continuous wall at the intersection of the continuous wall that is built earlier and the continuous wall that is built later,
Continuity is required.

【0003】しかしながら、連続壁を箱形に周回させる
場合には最後に構築される連続壁の構築が終了した時点
で、その施工終了部分が連続すべき、最初に構築されて
いる連続壁の施工開始部分が固化し始めているため、先
行する連続壁と後から構築された連続壁の交差部がコー
ルドジョイントとなり、ソイルセメントの連続性を確保
することができない。
However, in the case where the continuous wall is made to go around in a box shape, when the construction of the last constructed continuous wall is completed, the construction end portion should be continuous. Since the starting portion has begun to solidify, the intersection of the preceding continuous wall and the subsequently constructed continuous wall becomes a cold joint, and the continuity of the soil cement cannot be ensured.

【0004】同様のことは連続壁をL形等に交差させる
場合や、既設の連続壁に新規の連続壁を交差させる場合
の交差部にも言える。
[0004] The same can be said for the case where the continuous wall intersects in an L shape or the like, or the case where a new continuous wall intersects an existing continuous wall.

【0005】このように時間差が付いて構築されるソイ
ルセメント連続壁の交差部におけるコールドジョイント
に対しては従来、格別な対策が採られることはなく、山
止め壁等の場合に内側での施工に支障のない程度に漏水
を抑える対策が施されるに過ぎない。
Conventionally, no special countermeasures have been taken for cold joints at the intersections of soil cement continuous walls constructed with such a time lag. Only measures to control water leakage to the extent that does not hinder the operation are taken.

【0006】また後から構築される連続壁と先行する連
続壁との交差部においては先行する連続壁との接続のた
めに、無端チェーンが先行する連続壁に食い込むように
施工されるため、図7−(a) に示すように先行し、固結
している連続壁がカッターポストから押し込み力を受け
ることで、その側に亀裂が入ることが考えられる。亀裂
が入れば、その部分での漏水も問題になる。
At the intersection of a continuous wall constructed later and a preceding continuous wall, an endless chain is constructed so as to cut into the preceding continuous wall for connection with the preceding continuous wall. As shown in FIG. 7- (a), it is conceivable that the continuous wall, which is preceding and solidified, receives a pushing force from the cutter post, so that a crack is formed on that side. If there is a crack, water leakage at that part becomes a problem.

【0007】この発明は上記背景より、時間差が付いて
構築されるソイルセメント連続壁のコールドジョイント
による漏水を防止する方法を提案するものである。
In view of the above background, the present invention proposes a method for preventing water leakage due to a cold joint of a continuous soil cement wall constructed with a time difference.

【0008】[0008]

【課題を解決するための手段】本発明では先行して構築
される連続壁と後から構築される連続壁との交差部に、
予め非固結性の不透水性材料を含む液を充満させたジョ
イント孔を形成し、このジョイント孔中で交差する連続
壁の端部を互いに接続させることにより、時間差が付い
て構築されるソイルセメント連続壁の交差部におけるコ
ールドジョイントによる漏水を防止する。
According to the present invention, at the intersection of a continuous wall constructed before and a continuous wall constructed later,
A soil constructed with a time difference by forming a joint hole previously filled with a liquid containing a non-consolidating water-impermeable material and connecting ends of continuous walls intersecting in the joint hole. Prevents cold joint leakage at the intersection of cement continuous walls.

【0009】連続壁の交差部分においては、図6−(b)
に示すように先行して構築されているいずれか一方の連
続壁に対して他方の施工終了部分が食い込むように施工
されるため、先行する連続壁が固化している場合には両
連続壁の接続面がコールドジョイントとなり、矢印で示
すように構築物の外部から接続面を通じて地下水が浸入
することになる。
At the intersection of the continuous walls, FIG.
As shown in the above, since the construction end portion of the other is cut into one of the continuous walls built earlier, if the preceding continuous wall is solidified, The connecting surface becomes a cold joint, and groundwater infiltrates from the outside of the structure through the connecting surface as shown by the arrow.

【0010】これに対し、本発明では図6−(a) に示す
ように非固結性の不透水性材料を含む液を充満させたジ
ョイント孔において隣接する連続壁の端部が接続され、
二方向の連続壁の接続面が不透水性材料中に位置するこ
とで、地下水の浸入経路が遮断されるため、交差部にお
ける漏水が防止される。仮に連続壁の表面と接続面を伝
って水が浸入することがあっても、水の通過経路が(b)
の場合より長くなるため、見かけの透水係数は小さくな
る。
On the other hand, in the present invention, as shown in FIG. 6A, ends of adjacent continuous walls are connected at a joint hole filled with a liquid containing a non-consolidating water-impermeable material,
Since the connecting surface of the two-way continuous wall is located in the water-impermeable material, the groundwater intrusion path is blocked, so that water leakage at the intersection is prevented. Even if water invades along the surface of the continuous wall and the connecting surface, the water passage path is (b)
In this case, the apparent hydraulic conductivity becomes smaller.

【0011】また先行する連続壁と後から構築される連
続壁との交差部に連続壁の幅より大きい径の、円柱状等
のジョイント孔が形成されることで、仮にカッターポス
トからの押し込み力によって先行する連続壁に亀裂が生
じていても、ジョイント孔が亀裂の発生箇所を包囲する
ため、亀裂による漏水の問題は解消される。図面ではジ
ョイント孔を円柱状に記載しているが、ジョイント孔の
断面は矩形その他の形状にする場合もある。
[0011] In addition, since a joint hole having a diameter larger than the width of the continuous wall is formed at the intersection of the preceding continuous wall and the continuous wall to be subsequently formed, the pushing force from the cutter post is temporarily reduced. Therefore, even if the preceding continuous wall has a crack, the problem of water leakage due to the crack is eliminated because the joint hole surrounds the location where the crack occurs. In the drawings, the joint hole is illustrated as having a cylindrical shape, but the cross section of the joint hole may be rectangular or another shape.

【0012】または前記不透水性材料を含む液中に固化
材を添加し、ジョイント孔を固結させれば、図7−(b)
に示すようにジョイント孔が連続壁の幅より大きい径を
持たなくとも、先行する連続壁に接続するジョイント孔
が後から構築される連続壁の施工時の、カッターポスト
からの押し込み力に対して十分な抵抗力を発揮するた
め、先行する連続壁における亀裂の発生が防止される。
Alternatively, if a solidifying material is added to the liquid containing the water-impermeable material to solidify the joint hole, the liquid can be mixed as shown in FIG.
Even if the joint hole does not have a diameter larger than the width of the continuous wall as shown in the figure, the joint hole connecting to the preceding continuous wall is Since sufficient resistance is exhibited, the occurrence of cracks in the preceding continuous wall is prevented.

【0013】この場合、固結しているジョイント孔とそ
れに後から接続する連続壁との接続部がコールドジョイ
ントとなる可能性があるが、その場合でもジョイント孔
がない場合より水の通過経路が長くなるため、漏水の可
能性は低下する。
In this case, the joint between the solidified joint hole and the continuous wall connected to the joint hole may be a cold joint. Even in this case, the water passage path is smaller than when there is no joint hole. The longer, the lower the possibility of water leakage.

【0014】連続壁を例えば箱形に周回させる場合には
請求項2に記載のようにコールドジョイントが発生す
る、最初に構築される連続壁の施工開始部分と、最後に
構築される連続壁の施工終了部分との交差部にジョイン
ト孔を形成すれば足りるが、全連続壁の交差部にジョイ
ント孔を形成することもある。
In the case where the continuous wall is made to circulate in a box shape, for example, a cold joint is generated as described in claim 2, and the construction start portion of the first constructed continuous wall and the last constructed continuous wall are formed. It is sufficient to form a joint hole at the intersection with the construction end portion, but a joint hole may be formed at the intersection of all continuous walls.

【0015】その場合は請求項3に記載のように各連続
壁の両端の位置に予め非固結性の不透水性材料を充満さ
せたジョイント孔を形成する一方、いずれか一方のジョ
イント孔を始点として他方のジョイント孔まで連続壁を
構築する作業を繰り返し、交差する連続壁の端部をジョ
イント孔中で互いに接続させることが行われる。
In this case, a joint hole previously filled with a non-consolidating water-impermeable material is formed at both ends of each continuous wall as described in claim 3, and one of the joint holes is formed. The operation of constructing the continuous wall as the starting point up to the other joint hole is repeated, and the ends of the intersecting continuous walls are connected to each other in the joint hole.

【0016】[0016]

【発明の実施の形態】この発明は図1,図2に示すよう
にソイルセメントの連続壁4を交差させて構築する方法
において、交差する連続壁4,4のいずれかの交差部
に、予めベントナイト液等の非固結性の不透水性材料を
含む液を充満させたジョイント孔5を形成し、交差する
連続壁4,4の端部をジョイント孔5中で互いに接続さ
せ、連続壁4,4の交差部における漏水を防止する方法
である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS As shown in FIGS. 1 and 2, the present invention relates to a method for constructing a continuous cross-section of continuous walls 4 of soil cement. A joint hole 5 filled with a liquid containing a non-consolidating water-impermeable material such as bentonite liquid is formed, and the ends of the intersecting continuous walls 4 and 4 are connected to each other in the joint hole 5. , 4 to prevent water leakage.

【0017】図1,図2では連続壁4を箱形に周回させ
た場合を示しているが、単に二方向に交差させて構築す
る場合や、既設の連続壁4に交差させて新規に連続壁4
を構築する場合もある。
FIGS. 1 and 2 show a case where the continuous wall 4 is made to circulate in a box shape. However, the continuous wall 4 may be constructed by simply crossing in two directions, or may be newly formed by crossing the existing continuous wall 4. Wall 4
In some cases.

【0018】連続壁4は図4に示すように切削刃1を有
する無端チェーン2をカッターポスト3の周囲で循環さ
せ、地中に、または地表から固化材液を吐出しながら、
カッターポスト3を地中で横行させることにより構築さ
れる。
As shown in FIG. 4, the continuous wall 4 circulates the endless chain 2 having the cutting blade 1 around the cutter post 3 while discharging the solidified material liquid into the ground or from the ground.
It is constructed by traversing the cutter post 3 in the ground.

【0019】図1,図2に示すように連続壁4を箱形に
周回させて構築する場合、連続壁4の施工はいずれか一
辺の一端を始点として開始され、他端にカッターポスト
3が到達した時点でカッターポスト3の向きを変え、引
き続いて隣接する連続壁4が構築されるため、ジョイン
ト孔5はカッターポスト3が向きを変える位置に形成さ
れる。カッターポスト3の方向転換は一旦地上に引き上
げた後に、または地中に挿入したまま行われる。
As shown in FIGS. 1 and 2, when the continuous wall 4 is constructed so as to revolve in a box shape, the construction of the continuous wall 4 is started from one end of one side, and the cutter post 3 is attached to the other end. When the cutter post 3 reaches the position, the cutter post 3 is turned, and subsequently the adjacent continuous wall 4 is constructed, so that the joint hole 5 is formed at a position where the cutter post 3 turns. The direction change of the cutter post 3 is performed after the cutter post 3 is once pulled up to the ground or while being inserted into the ground.

【0020】ジョイント孔5は先行して構築される連続
壁41,42,43と、後から構築され、先行して構築される
連続壁41,42,43に交差する連続壁42,43,44との全交
差部の内、少なくともコールドジョイントが発生し得る
いずれかの交差部に形成される。
The joint hole 5 has a continuous wall 41, 42, 43 which is constructed in advance and a continuous wall 42, 43, 44 which is constructed later and intersects the continuous wall 41, 42, 43 which is constructed in advance. Are formed at any intersection where at least a cold joint may occur.

【0021】図1,図2の場合、ジョイント孔5は全交
差部の内、時間差が最も長くなる最初に構築される連続
壁41の施工開始部分と、最後に構築される連続壁44の施
工終了部分との交差部にジョイント孔5を形成すれば足
りるが、図面では全連続壁41,42,43,44の交差部にジ
ョイント孔5を形成している。
In the case of FIGS. 1 and 2, the joint hole 5 is formed at the start of the construction of the first continuous wall 41 having the longest time difference and the construction of the last continuous wall 44 at the longest time. It is sufficient to form the joint hole 5 at the intersection with the end portion, but in the drawing, the joint hole 5 is formed at the intersection of all the continuous walls 41, 42, 43, 44.

【0022】ジョイント孔5は図5−(a) に示すように
アースドリル等の掘削装置6により非固結性の不透水性
材料を含む液を満たしながら掘削することにより、また
は(b) に示すように非固結性の不透水性材料を含み、セ
メントミルク等の固化材を添加した液を吐出しながら、
掘削翼と攪拌翼を持つ掘削攪拌装置7による深層混合処
理により形成される。
As shown in FIG. 5A, the joint hole 5 is drilled by a drilling device 6 such as an earth drill while being filled with a liquid containing a non-consolidating water-impermeable material, or as shown in FIG. While containing a non-consolidating water-impermeable material as shown, while discharging a liquid containing a solidifying material such as cement milk,
It is formed by a deep mixing process by a drilling and stirring device 7 having a drilling blade and a stirring blade.

【0023】固化材を添加する場合、ジョイント孔5は
基本的に完全な液体の性状を示す泥水で満たす場合と、
粘性が高く、流動性のない泥土で満たす場合がある。前
者の場合は泥水中に固化材が添加され、混合されること
によりジョイント孔5は最終的には円柱状の固結体とし
て形成されるが、相対的に先行する連続壁41,42,43
と、後から施工される連続壁42,43,44との交差部での
施工中にジョイント孔5が固化することがなければ、コ
ールドジョイントの発生は回避される。
When the solidifying material is added, the joint hole 5 is basically filled with muddy water exhibiting completely liquid properties.
May be filled with viscous, non-fluid mud. In the former case, the joint hole 5 is finally formed as a columnar solidified body by adding and mixing the solidifying material into the muddy water, but the relatively preceding continuous walls 41, 42, 43
If the joint hole 5 does not solidify during the construction at the intersection with the continuous walls 42, 43, 44 to be constructed later, the occurrence of a cold joint is avoided.

【0024】この連続的、もしくは継続的に施工される
連続壁4,4の交差部分においては、図1に破線で示す
ように交差する連続壁4,4の境界はジョイント孔5中
では明確に表れない。泥土で満たす場合には泥土と固化
材は混合されないため、図2に示すように交差する連続
壁4,4の境界は明確に表れる。
At the intersection of the continuous or continuously constructed continuous walls 4, 4, the boundary between the continuous walls 4, 4 intersecting is clearly defined in the joint hole 5 as shown by a broken line in FIG. It doesn't show up. When the mud is filled with the mud, the mud and the solidified material are not mixed, so that the boundaries of the intersecting continuous walls 4, 4 clearly appear as shown in FIG.

【0025】連続壁4を箱形に周回させて構築する場合
は、最初に構築される連続壁41の施工開始部分と、最後
に構築される連続壁44の施工終了部分との交差部に非固
結性の不透水性材料のみを満たしたジョイント孔5を形
成し、他の連続的に施工される交差部においては非固結
性の不透水性材料に固化材を添加した液を吐出しなが
ら、もしくは固化材のみを吐出しながら攪拌混合処理す
ることもある。
In the case where the continuous wall 4 is constructed so as to circulate in a box shape, a non-exposed portion is formed at the intersection of the construction start portion of the first constructed continuous wall 41 and the construction end portion of the continuously constructed continuous wall 44. A joint hole 5 filled only with the solidified water-impermeable material is formed, and a liquid obtained by adding a solidifying material to the non-solidified water-impermeable material is discharged at other continuously constructed intersections. In some cases, the stirring and mixing process may be performed while discharging only the solidifying material.

【0026】いずれの場合も最初に構築される連続壁41
の施工開始部分と、最後に構築される連続壁44の施工終
了部分との交差部のジョイント孔5は二方向の連続壁4
1,44の端面が実質的に完全にジョイント孔5中に位置
する程度以上の大きさの径で形成される。
In each case, the first continuous wall 41 is constructed.
The joint hole 5 at the intersection of the construction start part of the construction and the construction end part of the construction of the continuous wall 44 to be built last
1, 44 are formed with a diameter larger than or equal to the extent that the end face is substantially completely located in the joint hole 5.

【0027】連続壁4の構築はジョイント孔5中にカッ
ターポスト3を挿入し、セメントミルク等の固化材液を
吐出し、無端チェーン2をカッターポスト3の周囲で循
環させることにより開始される。
The construction of the continuous wall 4 is started by inserting the cutter post 3 into the joint hole 5, discharging a solidifying material liquid such as cement milk, and circulating the endless chain 2 around the cutter post 3.

【0028】ジョイント孔5は連続壁4の施工開始前に
その位置に形成され、他端へのカッターポスト3の到達
前にその位置に形成されていればよいため、連続壁4の
両端位置に予めジョイント孔5,5を形成する場合と、
施工開始位置に先行してジョイント孔5を形成し、連続
壁4の施工中に施工終了位置にジョイント孔5を形成す
る場合がある。
The joint hole 5 may be formed at that position before the construction of the continuous wall 4 is started, and may be formed at that position before the cutter post 3 reaches the other end. When the joint holes 5 and 5 are formed in advance,
In some cases, the joint hole 5 is formed prior to the construction start position, and the joint hole 5 is formed at the construction end position during construction of the continuous wall 4.

【0029】連続壁4を箱形に周回させて構築する場合
は、隣接する連続壁4,4の交差部の位置に予めジョイ
ント孔5を形成する一方、いずれか一方のジョイント孔
5を始点として他方のジョイント孔5まで連続壁4を構
築する作業を繰り返すことにより構築物が完成する。
In the case where the continuous wall 4 is constructed so as to revolve in a box shape, a joint hole 5 is formed in advance at the intersection of the adjacent continuous walls 4, 4, and one of the joint holes 5 is used as a starting point. The construction is completed by repeating the operation of constructing the continuous wall 4 up to the other joint hole 5.

【0030】図1は最後に構築される連続壁44の終点部
分を除き、先行して構築される連続壁41,42,43の終点
部分の端面が後から構築される連続壁42,43,44の始点
部分の側面に突き当たるように施工した場合、図2は最
後に構築される連続壁44の終点部分を含め、後から構築
される連続壁42,43,44の始点部分を先行して構築され
る連続壁41,42,43の終点部分と重複するように施工し
た場合を示す。
FIG. 1 shows that the end faces of the end points of the continuous walls 41, 42, and 43, which are constructed earlier, are the same as those of the continuous walls 42, 43, and 43, which are constructed later. When the construction is performed so as to abut the side of the starting point of 44, FIG. 2 precedes the starting point of the subsequently constructed continuous walls 42, 43 and 44, including the end of the continuously constructed continuous wall 44. This shows a case where the construction is performed so as to overlap the end points of the continuous walls 41, 42, and 43 to be constructed.

【0031】図1では最後に構築される連続壁44の終点
部分の側面が、最初に構築される連続壁41の端面に突き
当たるように施工している。図1,図2中、矢印は施工
の向きを示す。
In FIG. 1, the construction is performed such that the side face of the end point of the continuous wall 44 constructed lastly comes into contact with the end face of the continuous wall 41 constructed first. 1 and 2, arrows indicate the direction of construction.

【0032】図3は図1に示す最初に構築された連続壁
41の両端と、その両側に隣接する連続壁42,44との交差
部の拡大図を示す。最初に構築された連続壁41の始点部
分は最後に構築された連続壁44の終点部分と接合される
際に固化が進行しているため、コールドジョイントとな
る可能性があるが、最初に構築された連続壁41の終点部
分とそれに続いて施工される連続壁42の始点部分は固化
材液の吐出と攪拌を伴う連続壁42の施工によってジョイ
ント孔5中で一体となり、前記の通り、二方向の連続壁
41,42の端部の明確な境界は表れない。
FIG. 3 shows the first constructed continuous wall shown in FIG.
The enlarged view of the intersection of both ends of 41 and the continuous walls 42 and 44 adjacent to both sides is shown. Since the solidification of the start point of the first constructed continuous wall 41 is progressing when it is joined to the end point of the last constructed continuous wall 44, it may become a cold joint, but the first The end point portion of the continuous wall 41 and the start point portion of the continuous wall 42 to be constructed subsequently are united in the joint hole 5 by the construction of the continuous wall 42 with discharge and agitation of the solidifying material liquid. Directional wall
No clear boundaries appear at the ends of 41 and 42.

【0033】図3において最初の連続壁41の始点部分と
最後の連続壁44の終点部分との交差部がコールドジョイ
ントとなっても、交差する連続壁41,44の接続面が完全
にジョイント孔5内に位置することで、水の通過経路が
長くなるため、構築物に関してジョイント孔5の外側に
位置する地下水が交差部の内側に浸入することはない。
In FIG. 3, even if the intersection between the start point of the first continuous wall 41 and the end point of the last continuous wall 44 is a cold joint, the connecting surface of the continuous continuous walls 41 and 44 intersects completely. 5, the passage of water becomes longer, so that groundwater located outside the joint hole 5 with respect to the building does not enter the inside of the intersection.

【0034】[0034]

【発明の効果】先行して構築される連続壁と後から構築
される連続壁との交差部に、予め非固結性の不透水性材
料を含む液を充満させたジョイント孔を形成し、このジ
ョイント孔中で交差する連続壁の端部を互いに接続させ
ることで、地下水の浸入経路を遮断するため、時間差が
付いて構築されるソイルセメント連続壁の交差部におけ
るコールドジョイントによる漏水を防止することができ
る。
According to the present invention, a joint hole previously filled with a liquid containing a non-consolidating water-impermeable material is formed at an intersection of a continuous wall constructed in advance and a continuous wall constructed in a later step. By connecting the ends of the continuous walls that intersect in this joint hole, the path of infiltration of groundwater is cut off, thereby preventing water leakage due to the cold joint at the intersection of the soil cement continuous walls that are constructed with a time difference. be able to.

【0035】また先行する連続壁と後から構築される連
続壁との交差部に連続壁の幅より大きい径の、円柱状の
ジョイント孔を形成することで、仮にカッターポストか
らの押し込み力によって先行する連続壁に亀裂が生じて
いても、ジョイント孔が亀裂の発生箇所を包囲するた
め、亀裂による漏水の問題は解消される。
Further, by forming a columnar joint hole having a diameter larger than the width of the continuous wall at the intersection of the preceding continuous wall and the continuous wall to be constructed later, it is assumed that the cylindrical joint hole is temporarily pushed by the pushing force from the cutter post. Even if a crack occurs in the continuous wall, the joint hole surrounds the location where the crack occurs, so that the problem of water leakage due to the crack is solved.

【0036】または不透水性材料を含む液中に固化材を
添加し、ジョイント孔を固結させれることで、先行する
連続壁に接続するジョイント孔部分が後から構築される
連続壁の施工時の、カッターポストからの押し込み力に
対する十分な抵抗力を発揮するため、先行する連続壁に
おける亀裂の発生が防止される。
Alternatively, a solidifying material is added to a liquid containing a water-impermeable material to solidify the joint hole, so that a joint hole portion connected to the preceding continuous wall is constructed later. In this case, a sufficient resistance to the pushing force from the cutter post is exerted, so that the occurrence of cracks in the preceding continuous wall is prevented.

【0037】この場合、固結しているジョイント孔とそ
れに後から接続する連続壁との接続部がコールドジョイ
ントとなっても、ジョイント孔がない場合より通過経路
が長くなるため、漏水の可能性は低下する。
In this case, even if the joint between the solidified joint hole and the continuous wall connected to the joint hole becomes a cold joint, the passage path becomes longer than when there is no joint hole, so that the possibility of water leakage is increased. Drops.

【図面の簡単な説明】[Brief description of the drawings]

【図1】箱形に周回する連続壁の構築の様子を示した平
面図である。
FIG. 1 is a plan view showing how a continuous wall orbiting in a box shape is constructed.

【図2】箱形に周回する連続壁の他の構築の様子を示し
た平面図である。
FIG. 2 is a plan view showing another construction of a continuous wall orbiting in a box shape.

【図3】図1の一部拡大図である。FIG. 3 is a partially enlarged view of FIG. 1;

【図4】連続壁の構築の様子を示した立面図である。FIG. 4 is an elevational view showing how a continuous wall is constructed.

【図5】(a) ,(b) はジョイント孔の形成の様子を示し
た立面図である。
FIGS. 5 (a) and 5 (b) are elevation views showing how a joint hole is formed.

【図6】(a) は本発明の連続壁の交差部における地下水
の様子を示した平面図、(b) は従来の連続壁の交差部に
おける地下水浸入の様子を示した平面図である。
FIG. 6 (a) is a plan view showing groundwater at an intersection of continuous walls according to the present invention, and FIG. 6 (b) is a plan view showing groundwater infiltration at a conventional intersection of continuous walls.

【図7】(a) は後から構築される連続壁の施工によって
先行する連続壁に亀裂が入ったときの様子を示した平面
図、(b) はジョイント孔を固結させ、施工時に抵抗力を
発揮させるときの様子を示した平面図である。
FIG. 7 (a) is a plan view showing a state in which a preceding continuous wall is cracked by the construction of a continuous wall to be constructed later, and FIG. It is the top view which showed the situation when exerting force.

【符号の説明】[Explanation of symbols]

1……切削刃、2……無端チェーン、3……カッターポ
スト、4,41,42,43,44……連続壁、5……ジョイン
ト孔、6……掘削装置、7……掘削攪拌装置。
1 cutting blade, 2 endless chain, 3 cutter post, 4, 41, 42, 43, 44 continuous wall, 5 joint hole, 6 drilling device, 7 drilling stirring device .

───────────────────────────────────────────────────── フロントページの続き (72)発明者 舘山 勝 東京都国分寺市光町2丁目8番地38 財団 法人鉄道総合技術研究所内 (72)発明者 福田 厚生 東京都港区赤坂6丁目13番7号 株式会社 テノックス内 (72)発明者 吉田 茂 東京都港区赤坂6丁目13番7号 株式会社 テノックス内 (72)発明者 上 周史 東京都港区赤坂6丁目13番7号 株式会社 テノックス内 Fターム(参考) 2D049 EA01 EA02 GA03 GA12 GA15 GA17 GB01 GC11  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Masaru Tateyama 2-8-3 Hikaricho, Kokubunji-shi, Tokyo Inside the Railway Technical Research Institute (72) Inventor Kosei Fukuda 6-13-7 Akasaka, Minato-ku, Tokyo Tenox Co., Ltd. (72) Inventor Shigeru Yoshida 6-13-7 Akasaka, Minato-ku, Tokyo Tenox Co., Ltd. (72) Inventor Shuji Kami 6-13-7 Akasaka, Minato-ku, Tokyo Tenox U. F Terms (reference) 2D049 EA01 EA02 GA03 GA12 GA15 GA17 GB01 GC11

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 切削刃を有する無端チェーンをカッター
ポストの周囲で循環させ、地中に、もしくは地表から固
化材液を吐出しながら、カッターポストを地中で横行さ
せ、ソイルセメントの連続壁を構築する方法において、
先行して構築される連続壁と、後から構築され、先行し
て構築される連続壁に交差する連続壁との交差部に、予
め非固結性の不透水性材料を含む液を充満させたジョイ
ント孔を形成し、このジョイント孔中で前記交差する連
続壁の端部を互いに接続させるソイルセメント連続壁交
差部の止水方法。
An endless chain having a cutting blade is circulated around a cutter post, and the cutter post is traversed in the ground while discharging a solidifying material liquid in the ground or from the surface of the ground, thereby forming a continuous wall of soil cement. In the method of building,
The intersection of the continuous wall that is built before and the continuous wall that is built later and intersects the previously built continuous wall is filled with a liquid containing a non-consolidating impermeable material in advance. A method of stopping water at an intersection of soil cement continuous walls in which a joint hole is formed and ends of the intersecting continuous walls are connected to each other in the joint hole.
【請求項2】 切削刃を有する無端チェーンをカッター
ポストの周囲で循環させ、地中に、もしくは地表から固
化材液を吐出しながら、カッターポストを地中で横行さ
せ、ソイルセメントの連続壁を構築する方法において、
少なくとも最初に構築される連続壁と、最後に構築さ
れ、最初に構築される連続壁に交差する連続壁との交差
部に、予め非固結性の不透水性材料を含む液を充満させ
たジョイント孔を形成し、このジョイント孔中で前記交
差する連続壁の端部を互いに接続させるソイルセメント
連続壁交差部の止水方法。
2. An endless chain having a cutting blade is circulated around a cutter post, and the cutter post is traversed under the ground while discharging a solidifying material liquid in the ground or from the surface of the ground to form a continuous wall of soil cement. In the method of building,
At least the intersection of the continuous wall constructed first and the continuous wall constructed last and intersecting with the first constructed continuous wall was filled with a liquid containing a non-consolidating impermeable material in advance. A method for stopping water at an intersection of a soil cement continuous wall in which a joint hole is formed and ends of the intersecting continuous walls are connected to each other in the joint hole.
【請求項3】 切削刃を有する無端チェーンをカッター
ポストの周囲で循環させ、地中に、もしくは地表から固
化材液を吐出しながら、カッターポストを地中で横行さ
せ、ソイルセメントの連続壁を構築する方法において、
各連続壁の両端の位置に予め非固結性の不透水性材料を
含む液を充満させたジョイント孔を形成する一方、いず
れか一方のジョイント孔を始点として他方のジョイント
孔まで連続壁を構築する作業を繰り返し、交差する連続
壁の端部をジョイント孔中で互いに接続させるソイルセ
メント連続壁交差部の止水方法。
3. An endless chain having a cutting blade is circulated around the cutter post, and the cutter post is traversed under the ground while discharging the solidifying material liquid in the ground or from the surface of the ground, thereby forming a continuous wall of the soil cement. In the method of building,
While forming joint holes pre-filled with a liquid containing a non-consolidating water-impermeable material at both ends of each continuous wall, a continuous wall is constructed starting from one of the joint holes to the other joint hole The method of stopping water at the intersection of soil cement continuous walls in which the ends of the continuous walls intersecting are connected to each other in the joint hole.
JP2000119672A 2000-04-20 2000-04-20 Method for cutting off water at intersection of soil cement continuous wall Pending JP2001303550A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000119672A JP2001303550A (en) 2000-04-20 2000-04-20 Method for cutting off water at intersection of soil cement continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000119672A JP2001303550A (en) 2000-04-20 2000-04-20 Method for cutting off water at intersection of soil cement continuous wall

Publications (1)

Publication Number Publication Date
JP2001303550A true JP2001303550A (en) 2001-10-31

Family

ID=18630603

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000119672A Pending JP2001303550A (en) 2000-04-20 2000-04-20 Method for cutting off water at intersection of soil cement continuous wall

Country Status (1)

Country Link
JP (1) JP2001303550A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535518A (en) * 2012-01-13 2012-07-04 同济大学 Plugging method of large seam of underground diaphragm wall

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535518A (en) * 2012-01-13 2012-07-04 同济大学 Plugging method of large seam of underground diaphragm wall
CN102535518B (en) * 2012-01-13 2014-06-25 同济大学 Plugging method of large seam of underground diaphragm wall

Similar Documents

Publication Publication Date Title
US6241426B1 (en) Method for forming an interconnected underground structure
JP2001303550A (en) Method for cutting off water at intersection of soil cement continuous wall
JP3213240B2 (en) Support pile reinforcement structure of existing structure and its reinforcement method
JP4440497B2 (en) Construction method of underground continuous wall and construction method of underground structure
JP4555977B2 (en) Ground improvement method
JP2000355949A (en) Reinforcing method for masonry retaining wall
JP2001303549A (en) Method for cutting off water at intersection of soil cement continuous wall
JPH10121462A (en) Formation method of water permeable part in continuous underground wall
JP3253868B2 (en) Forming method of water passage section in continuous underground wall
JPH0841870A (en) Method of connection precast concrete pile
JP3532449B2 (en) Excavation stirring device and ground improvement method using the same
JPH11158865A (en) Underground structure having wall using steel sheet pile as core and method for constructing the same
JPS6383316A (en) Embeding method for pile
JP4471510B2 (en) Steel pipe soil cement pile, its construction method and construction equipment
JPH07109096B2 (en) Impermeable method for underground wall
JPH03271419A (en) Chemicals feeding process and device therefor
JPH02304119A (en) Stabilizing construction method for slope
JP2002348851A (en) Composite pile and method for executing earth retaining wall
JPH0931972A (en) Construction of underground continuous wall
JP4641369B2 (en) Partially built soil cement composite pile
JP3467221B2 (en) Ground reinforcement method
JPS6011165Y2 (en) Continuous column pile drilling bit
JP2000104247A (en) Structural body and installation method thereof
CN106065596A (en) A kind of oblique steel pipe combines soil cement and forms the construction method of beaer
JPH10252064A (en) Method for constructing cast-in-site pile

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060804

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080514

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080520

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20080924