JP2001172956A - Soil improvement method - Google Patents

Soil improvement method

Info

Publication number
JP2001172956A
JP2001172956A JP35789899A JP35789899A JP2001172956A JP 2001172956 A JP2001172956 A JP 2001172956A JP 35789899 A JP35789899 A JP 35789899A JP 35789899 A JP35789899 A JP 35789899A JP 2001172956 A JP2001172956 A JP 2001172956A
Authority
JP
Japan
Prior art keywords
ground
earth auger
aggregate
improvement method
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP35789899A
Other languages
Japanese (ja)
Other versions
JP3594121B2 (en
Inventor
Shoji Sakagami
昭二 坂上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KUROKI CREATIVE KK
Original Assignee
KUROKI CREATIVE KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KUROKI CREATIVE KK filed Critical KUROKI CREATIVE KK
Priority to JP35789899A priority Critical patent/JP3594121B2/en
Publication of JP2001172956A publication Critical patent/JP2001172956A/en
Application granted granted Critical
Publication of JP3594121B2 publication Critical patent/JP3594121B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a soil improvement method excellent in compatibility with an environment and capable of effectively consolidating the circumference of an excavated hole. SOLUTION: The excavated hole 11 with a specific depth is formed while forwarding an earth auger 5. An then, the earth auger 5 is reversed at a low speed and, at the same time, axial force in the direction of excavation is added, and horizontal force is added to aggregate 12 cast from the ground surface 3 by the earth auger 5 to consolidate the circumference of the excavated hole 11 and the inside of the excavated hole. Soil around the excavated hole 11 is effectively compacted to make it possible to carry out soil improvement by reversing the earth auger 5 at a low speed in a state to add axial force to the direction of excavation.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、アースオーガーを
用いた地盤改良工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a ground improvement method using an earth auger.

【0002】[0002]

【発明が解決しようとする課題】従来、この種の地盤改
良工法として、特開昭51−136315号公報には、
地盤中に挿入されるケーシング内に砂を充填してケーシ
ングを引上げ、地盤中に形成された砂柱を通じて排水す
ることにより地盤を締固め、次いで前記砂柱にグラウト
材を注入して固締させる地盤改良工法があり、また、特
公昭52−606号公報には、地表に直立される架構体
に沿って昇降できるようにされた駆動機構を有し、下方
先端部に掘削スクリューと、これに続く上方に断続した
螺旋状の攪拌および破砕プレートをそれぞれ設けた中空
筒状のオーガを、前記駆動機構により可逆転できるよう
に結合され(公報特許請求の範囲)、この提案された工
法は、先端部に掘削スクリュー、これに続く部分に攪拌
および破砕プレートなどを各々設けると共に、内部に生
石灰又は消石灰(以下石灰という)給送スクリューコン
ベヤと圧縮空気通路とを、前記先端部に各々開口して構
成したオーガーを用い、掘削土をできるだけ排出させる
ことのないようにして土壌を柱状に掘削し、かつ同時に
掘削土を掘削孔内で攪拌砕土させ、この砕土された掘削
土中に前記スクリューコンベヤにより給送される石灰を
圧縮空気によって噴出させ、掘削土および土中水とを攪
拌混合して、この石灰を掘削土および土中水と反応させ
て、軟弱地盤中に強固な石灰と掘削土とにより柱状体を
造成するものであり(公報第3欄第19〜32行)、さら
に、特開平7−216866号公報には、アースオーガ
ーを用いて、地盤に所定深さの掘削孔を形成する工程
と、前記掘削孔の先端部にて、前記アースオーガーのオ
ーガーヘッドよりパイル先端部固定液を選択的に注入す
る工程と、前記パイル先端部固定液の注入後、前記オー
ガーヘッドよりパイル周辺部充填液の注入後、前記掘削
孔にパイルを建て込む工程と、前記パイルが所定高さレ
ベルになるように、該パイルを前記地盤に定着させる工
程と、を備えるセメントミルク公報における孔壁地盤改
良方法(特許請求の範囲)があり、この地盤改良方法で
は、セメントミルクは、パイル先端部固定液とパイル周
辺部充填液を2種類用いるが、それぞれの場合における
成分配合を好適に選定する事により、摩擦力及び支持力
等を大幅に向上させることができる。特に、パイル周辺
部充填液は、普通ポルトランドセメント及びセメント系
固化材を主成分として、これに適量のベントナイトが添
加されたものである。例えば、特に砂質土に対しては普
通ポルトランドセメントが、また粘性土に対しては、セ
メント系固化材がそれぞれ地盤改良効果を発揮し、これ
により地盤強度を各段に高めることができる(第000
9段)と記載されている。
Conventionally, as this kind of ground improvement method, Japanese Patent Laid-Open No. 51-136315 discloses
The casing inserted into the ground is filled with sand, the casing is pulled up, the ground is compacted by draining through a sand column formed in the ground, and then the grout material is injected into the sand column and compacted. There is a ground improvement method, and Japanese Patent Publication No. 52-606 has a drive mechanism capable of ascending and descending along a frame structure standing upright on the ground surface. A hollow cylindrical auger provided with a spiral stirring and crushing plate, which is intermittently connected upward, is connected so as to be able to reversibly rotate by the driving mechanism (claims). Excavation screw is provided in the section, stirring and crushing plate etc. are provided in the section following this, and the inside of quick lime or slaked lime (hereinafter referred to as lime) feeding screw conveyor and compressed air And, using an auger configured with each opening at the tip end, excavating the excavated soil in a columnar manner so as not to discharge as much as possible, and at the same time the excavated soil is stirred and crushed in the excavation hole, The lime fed by the screw conveyor is blown out by compressed air into the crushed excavated soil, and the lime is stirred and mixed with the excavated soil and the soil water, and the lime is reacted with the excavated soil and the soil water, In the soft ground, a columnar body is formed by strong lime and excavated soil (Publication, column 3, lines 19 to 32). Further, JP-A-7-216866 discloses the use of an earth auger. Forming a drilling hole of a predetermined depth in the ground; selectively injecting a pile tip fixing liquid from an auger head of the earth auger at a tip of the drilling hole; Injection After pouring the filling liquid around the pile from the auger head, setting a pile in the excavation hole, and fixing the pile to the ground so that the pile has a predetermined height level. There is a perforated wall ground improvement method in the cement milk publication (claims). In this ground improvement method, two types of cement milk are used: a pile tip fixing liquid and a pile peripheral filling liquid. By suitably selecting the composition, the frictional force, the supporting force, and the like can be significantly improved. In particular, the filling liquid at the periphery of the pile is a liquid containing ordinary Portland cement and a cement-based solidifying material as a main component, to which an appropriate amount of bentonite is added. For example, ordinary Portland cement, especially for sandy soil, and cement-based solidifying material, for cohesive soil, respectively, exhibit soil improvement effects, thereby increasing the ground strength in each step (No. 000
9).

【0003】上記従来のものは、いずれも石灰やセメン
ト等の固化材を多量に使用して地中に柱状体を形成する
ことにより地盤の改良を図るものであり、それらの材料
費がかさむと共に、固化材などの使用により環境への影
響も懸念される。また、掘削部分のみ強固な柱状部に形
成するため、掘削部分の周囲における締め固め効果に劣
る面があった。
[0003] All of the above-mentioned conventional ones are intended to improve the ground by forming a columnar body in the ground by using a large amount of solidifying material such as lime or cement, thereby increasing the material cost. There is also concern about the impact on the environment due to the use of solidified materials. Further, since only the excavated portion is formed into a strong columnar portion, there is a surface that is inferior in the compaction effect around the excavated portion.

【0004】そこで、本発明は、環境への適合性に優
れ、掘削孔の周囲を効果的に圧密することができる地盤
改良工法を提供することを目的とする。
[0004] Therefore, an object of the present invention is to provide a ground improvement method which has excellent adaptability to the environment and can effectively consolidate the periphery of an excavation hole.

【0005】[0005]

【課題を解決するための手段】本件発明者は、縦方向か
らの圧密と横方向からの圧密との違いを研究し、横方向
からの静止土圧係数付近の強さで加圧することにより従
来より早く圧密が進むことを見出すに至った。例えて平
易に説明すれば、豆腐のようなものの水抜きにおいて
は、適当な荷重を加えることにより比較的短時間で水が
抜け、前記荷重が大きすぎると水抜きに必要以上の時間
がかかり、かつ崩れる場合がある。
Means for Solving the Problems The present inventor studied the difference between the compaction in the vertical direction and the compaction in the horizontal direction, and applied the conventional method by applying a pressure near the static earth pressure coefficient in the horizontal direction. It has been found that consolidation proceeds more quickly. For example, in a simple manner, in draining water such as tofu, water is drained in a relatively short time by applying an appropriate load, and it takes more time than necessary to drain the water if the load is too large. And it may collapse.

【0006】そこで、発明者は鋭意研究により、掘削
後、加圧する際にはアースオーガーの回転を毎分25回
転以下、好ましくは20回転程度の低速に押えることに
より、効果的な圧密を可能とし、また、骨材も大きな骨
材だけでは加圧力の制御が難しくなるため、山砂などの
粒子配合の良いものを用いた。さらに、極軟質な地盤で
微粒子で構成される地盤等については生石灰などの混合
も有効であった。
The inventor of the present invention has conducted intensive studies to enable effective consolidation by pressing the earth auger at a low speed of 25 rotations per minute or less, preferably about 20 rotations per minute when pressurizing after excavation. In addition, since it is difficult to control the pressing force with only the large aggregate, the aggregate having a good particle mixture such as mountain sand is used. Furthermore, mixing of quicklime and the like was effective for the ground and the like composed of fine particles in the extremely soft ground.

【0007】そして、請求項1の発明は、アースオーガ
ーを正転しながら所定深さの掘削孔を形成し、この後、
前記アースオーガーを低速で逆回転すると共に、垂直方
向の軸力を加え、前記アースオーガーにより地表部から
投入した骨材に水平方向の力を加えて掘削孔の周囲及び
掘削孔内を圧密する地盤改良工法である。
According to the first aspect of the present invention, an excavation hole having a predetermined depth is formed while rotating the earth auger, and thereafter,
Ground that reversely rotates the earth auger at a low speed, applies a vertical axial force, and applies a horizontal force to the aggregate introduced from the surface by the earth auger to consolidate around and inside the excavation hole; This is an improved construction method.

【0008】この請求項1の構成によれば、掘削方向に
軸力を加えた状態でアースオーガーを低速で逆回転する
ことにより、掘削孔周囲の地盤を効果的に締め固めるこ
とができる。
According to the first aspect of the present invention, the ground around the excavation hole can be effectively compacted by reversely rotating the earth auger at a low speed while applying an axial force in the excavation direction.

【0009】また、請求項2の発明は、前記アースオー
ガーの逆回転が、毎分25回転以下である地盤改良工法
である。
A second aspect of the present invention is a ground improvement method in which the reverse rotation of the earth auger is 25 rotations per minute or less.

【0010】この請求項2の構成によれば、比較的低速
回転することにより、オーガーの回転により骨材に静止
土圧係数に近い適度な加圧力を付与することができる。
According to the structure of the second aspect, by rotating the auger at a relatively low speed, it is possible to apply an appropriate pressing force close to the static earth pressure coefficient to the aggregate by the rotation of the auger.

【0011】また、請求項3の発明は、改良地盤容積に
対して、6〜10%の骨材を追加する地盤改良工法であ
る。
Further, the invention of claim 3 is a ground improvement method in which an aggregate of 6 to 10% is added to the improved ground volume.

【0012】この請求項3の構成によれば、地盤が崩壊
することなく、適切な圧密を行うことができる。
According to the structure of the third aspect, appropriate compaction can be performed without the ground being collapsed.

【0013】[0013]

【発明の実施形態】以下、本発明の実施形態を添付図面
を参照して説明する。図1ないし図4は、本発明の一実
施例を示し、同図に示すように、レッカー車などの作業
車のブーム1の先端にリーダー2を連結し、このリーダ
ー2を地表部3に立設し、前記リーダー2に沿って減速
機付き回転手段4を移動可能に設け、この回転手段4に
アースオーガー5を回動可能に垂設している。このアー
スオーガー5は筒部6の外周に螺旋ねじ状の掘削羽根7
を有し、さらに、下端には先鋭な円錐部8が設けられて
いる。
Embodiments of the present invention will be described below with reference to the accompanying drawings. FIGS. 1 to 4 show an embodiment of the present invention. As shown in FIG. 1, a leader 2 is connected to the tip of a boom 1 of a working vehicle such as a tow truck, and the leader 2 is erected on the ground surface portion 3. A rotating means 4 with a speed reducer is provided movably along the leader 2, and an earth auger 5 is suspended from the rotating means 4 so as to be rotatable. The earth auger 5 has a spiral screw-shaped excavating blade 7
And a sharp conical portion 8 is provided at the lower end.

【0014】次に、本発明の地盤改良工法の手順につい
て説明する。まず、地盤改良を行う地表部3において、
ボーリングを行い、地中からサンプルを採取し、所定の
試験を行う。これにより、後述する各種データを算出す
る。まず、図1及び図2に示すように、アースオーガー
5を掘削方向に回転して所定深さの掘削孔11を形成す
る。この後、アースオーガー5を低速で逆回転し、地表
部から骨材12を投入する。この場合、図3に示すように
アースオーガー5に加える垂直荷重Wである軸力は、2
〜3トン程度とし、アースオーガー5は毎分25回転以
下、好ましくは20回転程度とする。また、骨材12に
は、アースオーガー5の掘削により排出された掘削土及
び砂たる山砂13を用いることができ、この場合、改良地
盤容積の6%程度から10%未満,好ましくは6%程度
から7%程度の骨材12を投入する。すなわち、改良地盤
容積の6%程度から10%程度の骨材12を追加し、掘削
土を全て掘削孔11に戻して用いる場合は、追加する山砂
13は地盤改良容量の6%程度から7%程度とすることが
好ましい。尚、前記改良地盤容積とは、地盤を改良する
箇所の面積に掘削孔11の掘削深さをかけたものであり、
具体的に図4により説明すると、周囲の丸5,丸4,丸
9,丸13,丸17,丸21,丸22,丸23,丸24,丸20,丸1
6,丸12,丸3,丸8,丸7,丸6に示す掘削孔11の中心
線により囲まれた部分(図中一点鎖線で表示)が地表部
3の改良地盤面積であり、この面積に図2に示した掘削
孔11の深さをかけたものが改良地盤容積となる。そし
て、この地盤改良容積の6%程度から10%未満,好ま
しくは6%程度から7%程度の骨材12を追加し、各掘削
孔11には、全体の追加量を掘削孔11の数で割った量にほ
ぼ相当する量の骨材12を追加する。さらに、軟質地盤で
は前記骨材12に、生石灰14を含むことができる。生石灰
14を用いる場合は、生石灰14と山砂13とを混合した後に
掘削孔11に投入したり、先に生石灰14を掘削孔11に投入
した後、山砂13を投入したりすることができる。このよ
うにアースオーガー5に加える垂直荷重Wと回転数とを
設定することにより、骨材12が水平方向に向かう力を効
果的に得ることができ、掘削孔11の周囲の地盤を効果的
に圧密することができる。尚、アースオーガー5と回転
手段4とを合わせた自重が2〜3トン程度であれば、こ
の例では、別個にウエートなどを設けることなく、垂直
荷重Wを得ることができる。また、垂直荷重Wを大きく
設定する場合は、回転手段4にウエート(図示せず)を
設けたり、該回転手段4にワイヤー(図示せず)などを
連結し、このワイヤーを巻き取るなどして下向きの荷重
を付加するようにすれば良い。
Next, the procedure of the ground improvement method of the present invention will be described. First, in the ground surface part 3 that performs ground improvement,
Boring, taking samples from underground, and conducting prescribed tests. Thereby, various data described later is calculated. First, as shown in FIGS. 1 and 2, the earth auger 5 is rotated in the excavation direction to form the excavation hole 11 having a predetermined depth. Thereafter, the earth auger 5 is reversely rotated at a low speed, and the aggregate 12 is charged from the surface. In this case, as shown in FIG. 3, the axial force which is the vertical load W applied to the earth auger 5 is 2
The earth auger 5 is set to 25 rpm or less, preferably about 20 rpm. As the aggregate 12, excavated earth and sand 13 excavated by the excavation of the earth auger 5 can be used, and in this case, about 6% to less than 10%, preferably 6% of the improved ground volume. About 7% of aggregate 12 is introduced. In other words, if the aggregate 12 of about 6% to about 10% of the improved ground volume is added and all the excavated soil is returned to the excavation hole 11,
It is preferable that 13 is about 6% to about 7% of the ground improvement capacity. The improved ground volume is obtained by multiplying the area of the site where the ground is to be improved by the digging depth of the digging hole 11,
Specifically, referring to FIG. 4, the surrounding circle 5, circle 4, circle 9, circle 13, circle 17, circle 21, circle 22, circle 23, circle 24, circle 20, circle 1
The part surrounded by the center line of the excavation hole 11 shown by 6, 12, 12, 3, 8, 7 (indicated by a dashed line in the figure) is the improved ground area of the ground surface part 3, and this area 2 multiplied by the depth of the excavation hole 11 shown in FIG. Then, about 6% to less than 10%, preferably about 6% to about 7% of the ground improvement volume is added to the aggregate 12, and the total amount added to each drill hole 11 is the number of the drill holes 11. An amount of aggregate 12 approximately equivalent to the divided amount is added. Furthermore, in soft ground, the aggregate 12 may include quicklime 14. quicklime
When using 14, the quicklime 14 and the sand 13 can be mixed and then put into the drilling hole 11, or the quicklime 14 can be first charged into the drilling hole 11 and then the sand 13 can be charged. By setting the vertical load W and the number of rotations applied to the earth auger 5 in this manner, the force in which the aggregate 12 moves in the horizontal direction can be effectively obtained, and the ground around the excavation hole 11 can be effectively formed. Can be compacted. If the combined weight of the earth auger 5 and the rotating means 4 is about 2 to 3 tons, in this example, the vertical load W can be obtained without providing a separate weight or the like. When the vertical load W is set to be large, a weight (not shown) is provided on the rotating means 4, or a wire (not shown) is connected to the rotating means 4 and the wire is wound. What is necessary is just to add a downward load.

【0015】ここで作用について詳述すると、粘性土を
攪拌すると液状の柔らかさになり、この状態で放置する
と液性の性質を失ったり、剛な状態になったりするが、
この攪拌がランダムで静的に近い(静止土圧係数に近い
状況)応力で加圧すると、構造配列が不完全配向構造か
ら配向構造に近い上記に変化する。この現象をシキソト
ロピー現象と呼び、古くから認識されている。
The action will be described in detail here. When the viscous soil is agitated, it becomes liquid soft, and when left in this state, it loses the liquid property or becomes rigid.
When the stirring is pressurized with a random and nearly static stress (a condition close to the static earth pressure coefficient), the structural arrangement changes from the incompletely oriented structure to the above-mentioned one close to the oriented structure. This phenomenon is called the thixotropy phenomenon and has been recognized for a long time.

【0016】一方、高速道路などの盛土試験で実際の変
位値と今までの理論値に違いが見られ、この違いは異方
圧密によるせん断強度の増加と説明されている。すなわ
ち、地盤の中の要素を検討すると、等方圧密は特殊な場
合であり、普通は有効土かぶり圧と側方の拘束圧力の値
は異なるわけである。そこで、地盤中のひずみは鉛直
(垂直)方向のみに生じ、水平方向にはひずみは生じな
い。従って、このような地盤中の応力やひずみの条件に
合わせた圧密試験を現在K0試験と呼んでいる。静止土
圧係数K0の値は、0.95−sinΦ´に近似する
(Φ´は土中の内部摩擦角)。
On the other hand, in embankment tests on expressways and the like, a difference is found between the actual displacement value and the theoretical value up to now, and this difference is explained as an increase in shear strength due to anisotropic consolidation. That is, considering the elements in the ground, isotropic consolidation is a special case, and the value of the effective earth covering pressure and the value of the lateral restraining pressure are usually different. Therefore, distortion in the ground occurs only in the vertical (vertical) direction, and no distortion occurs in the horizontal direction. Therefore, such a consolidation test adapted to the conditions of stress and strain in the ground is currently called a K0 test. The value of the static earth pressure coefficient K0 approximates 0.95-sin Φ '(Φ' is the internal friction angle in the soil).

【0017】静止土圧係数K0をSkemptonらの異方圧密
された正規圧密粘性土の非排水せん断試験より考慮する
と、以下の考えられる。1)含水比が等しい場合には、
K0圧密を受けたものの方が大きい非排水せん断強度を
持つ。2)せん断に要した時間の差などからシキソトロ
ピー的な要因を有する可能性がある。3)応力履歴が異
なると粘土の骨格構造が異なってくる。
Considering the static earth pressure coefficient K0 from the undrained shear test of an anisotropically consolidated normally consolidated viscous soil by Skempton et al. 1) If the water content is equal,
Those subjected to K0 consolidation have greater undrained shear strength. 2) There is a possibility of having a thixotropic factor due to a difference in time required for shearing. 3) If the stress history is different, the skeleton structure of the clay is different.

【0018】さらに、軸に縦方向の荷重を加えて強制付
加することに伴う含水量の変化を考慮すると、機械反力
となる全荷重ξ(実施例では2〜3トン)と事前の土中
の含水量δ(初期含水量)、アースオーガー5の使用に
よる影響半径Rには単純な線形関係が見られる。ここ
で、前記影響半径Rは1.6m(メートル)とした。
Further, considering the change in water content caused by forcibly applying a vertical load to the shaft, the total load 機械 (2 to 3 tons in the embodiment) serving as a mechanical reaction force is determined in advance in the soil. Has a simple linear relationship between the water content δ (initial water content) and the radius of influence R due to the use of the earth auger 5. Here, the influence radius R was set to 1.6 m (meter).

【0019】C=ξ*A(ε/δ*1.6) 上記式で機械的付加速度Cが得られ、この機械的付加速
度Cは、アースオーガー5の回転速度に関連する。尚、
上記式で、εは含水比係数であり、下記の表1に示すよ
うに、改良すべき地盤の含水比により決まる。
C = ξ * A (ε / δ * 1.6) The above equation gives the mechanical additional speed C, which is related to the rotation speed of the earth auger 5. still,
In the above equation, ε is a moisture content coefficient, which is determined by the moisture content of the ground to be improved as shown in Table 1 below.

【0020】[0020]

【表1】 [Table 1]

【0021】これらのことから、改良後の地盤強度は次
の式で現すことができる。
From these, the ground strength after improvement can be expressed by the following equation.

【0022】[0022]

【数1】 (Equation 1)

【0023】上記において、Aは土中の間隙圧係数,N
は土中の強度係数(標準貫入試験値+1)である。
In the above, A is the pore pressure coefficient in soil, N
Is the strength coefficient in soil (standard penetration test value + 1).

【0024】そして、静止土圧係数近くの力で水平に近
い応力を加えながらゆっくりと加圧することにより最低
の応力の増加が地盤内にほぼ均質に起こることとなる。
この加圧はアースオーガー5を逆回転させ、その重量と
回転速度を制御することにより調整可能となり、静止土
圧係数を大幅に越えて加圧すると地盤全体の破壊を招く
ため、そのような地盤では、生石灰14を混ぜることによ
り、生石灰14の吸水発熱と吸水膨張により調整する。そ
して、骨材12の投入量は、改良地盤容積の6%程度から
10%未満,好ましくは6%程度から7%程度を追加し
た量であり、すなわち掘削土に追加する骨材12の山砂13
は地盤改良容積の6%〜7%とすることにより、地盤破
壊のない安定した施工が可能となる。尚、骨材投入量が
地盤改良容積の10%を超えると地盤破壊の可能性が増
加する。
[0024] By applying a pressure near the static earth pressure coefficient and applying a pressure close to the horizontal while slowly applying pressure, the minimum stress increase occurs almost uniformly in the ground.
This pressurization can be adjusted by rotating the earth auger 5 in the reverse direction and controlling its weight and rotation speed. Pressurization that greatly exceeds the static earth pressure coefficient causes destruction of the entire ground. Then, by adjusting the quick lime 14 by mixing with the quick lime 14, the adjustment is made by the heat generation and the water absorption expansion of the quick lime 14. The input amount of the aggregate 12 is about 6% to less than 10%, preferably about 6% to 7% of the improved ground volume, that is, the pile sand of the aggregate 12 added to the excavated soil. 13
By setting 6% to 7% of the ground improvement volume, stable construction without ground destruction becomes possible. If the aggregate input amount exceeds 10% of the ground improvement volume, the possibility of ground failure increases.

【0025】図4は施工手順を示す平面図であり、丸に
記載した数値の順に掘削孔11箇所の地盤改良を行うこと
により、広い範囲の地盤改良を効率良く行うことができ
る。そして、図4に示すように、隣合う掘削孔11,11を
桝目の交差位置に配置し、相互の間隔を2mとし、対角
線位置の間隔Hを略2.83mとし、これにより、間隔
Hを前記影響半径R(1.6m)の2倍以下としたか
ら、隣合う掘削孔11位置において影響半径Rが重なり合
い、確実な地盤改良を行うことができる。
FIG. 4 is a plan view showing a construction procedure. By performing ground improvement at 11 excavation holes in the order of numerical values described in circles, ground improvement over a wide range can be efficiently performed. Then, as shown in FIG. 4, the adjacent excavation holes 11 and 11 are arranged at the intersections of the cells, the interval between them is 2 m, and the interval H between the diagonal positions is approximately 2.83 m. Since the radius of influence R is set to be equal to or less than twice the radius of influence R (1.6 m), the radius of influence R overlaps at the position of the adjacent excavation hole 11, and the ground improvement can be reliably performed.

【0026】このように本実施例では、請求項1に対応
して、アースオーガー5を正転しながら所定深さの掘削
孔11を形成し、この後、アースオーガー5を低速で逆回
転すると共に、掘削方向の軸力を加え、アースオーガー
5により地表部3から投入した骨材12に水平方向の力を
加えて掘削孔11の周囲及び掘削孔11内を圧密する地盤改
良工法であるから、掘削方向に軸力を加えた状態でアー
スオーガー5を低速で逆回転することにより、掘削孔11
周囲の地盤を効果的に締め固めて地盤改良を行うことが
できる。また、生石灰14などを添加する場合もその使用
量を少なく押えることができる。
As described above, in the present embodiment, the drilling hole 11 having a predetermined depth is formed while rotating the earth auger 5 in the forward direction, and thereafter, the earth auger 5 is reversely rotated at a low speed. At the same time, the ground improvement method is to apply an axial force in the excavation direction and apply a horizontal force to the aggregate 12 introduced from the ground surface portion 3 by the earth auger 5 to consolidate the periphery of the excavation hole 11 and the inside of the excavation hole 11. When the earth auger 5 is reversely rotated at a low speed while applying an axial force in the excavation direction,
The ground improvement can be performed by effectively compacting the surrounding ground. Also, when quicklime 14 or the like is added, the amount of use can be reduced.

【0027】また、このように本実施例では、請求項2
に対応して、前記アースオーガーの逆回転が、毎分25
回転以下であるから、比較的低速回転することにより、
オーガー5の回転により骨材12に静止土圧係数K0に近
い適度な加圧力を付与することができる。
As described above, according to the present embodiment, claim 2
Corresponding to the reverse rotation of the earth auger, 25
Because it is less than rotation, by rotating at a relatively low speed,
By the rotation of the auger 5, an appropriate pressing force close to the static earth pressure coefficient K0 can be applied to the aggregate 12.

【0028】また、このように本実施例では、請求項3
に対応して、改良地盤容積に対して、6〜10%の骨材
を追加するから、地盤が崩壊することなく、適切な圧密
を行うことができる。
As described above, according to the present embodiment, claim 3
Accordingly, an aggregate of 6 to 10% is added to the improved ground volume, so that appropriate consolidation can be performed without the ground being collapsed.

【0029】さらに、実施例上の効果として、改良前に
ボーリングにより調査を行い、少なくとも採取したサン
プルの室内土質試験により含水比を得ると共に、圧密試
験結果の値を得るようにし、また、内部摩擦角Φ´に基
いた静止土圧係数K0,初期含水量δ,間隙圧係数A,
強度係数Nや含水比係数εを算出することにより、現場
に適した機械的な付加速度Cと機械の付加全荷重ξによ
り、好適な垂直荷重Wとアースオーガー5の回転速度を
設定することができる。また、骨材12に添加するものが
生石灰14であるから、自然環境に適した安全なものとな
る。
Further, as an effect on the embodiment, before the improvement, a survey was conducted by drilling, and at least a water content ratio was obtained by a laboratory soil test of the collected sample, and a value of a consolidation test result was obtained. The static earth pressure coefficient K0 based on the angle Φ ', the initial water content δ, the pore pressure coefficient A,
By calculating the strength coefficient N and the water content coefficient ε, it is possible to set a suitable vertical load W and a rotation speed of the earth auger 5 based on the mechanical additional speed C and the total additional load 適 し of the machine suitable for the site. it can. Further, since what is added to the aggregate 12 is quicklime 14, it is safe and suitable for the natural environment.

【0030】尚、本発明は上記実施例に限定されるもの
ではなく、本発明の要旨の範囲内において、種々の変形
実施が可能である。例えば、アースオーガーは各種のも
のを用いることができる。
The present invention is not limited to the above-described embodiment, and various modifications can be made within the scope of the present invention. For example, various earth augers can be used.

【0031】[0031]

【発明の効果】請求項1の発明は、アースオーガーを正
転しながら所定深さの掘削孔を形成し、この後、前記ア
ースオーガーを低速で逆回転すると共に、垂直方向の軸
力を加え、前記アースオーガーにより地表部から投入し
た骨材に水平方向の力を加えて掘削孔の周囲及び掘削孔
内を圧密する地盤改良工法であり、環境への適合性に優
れ、掘削孔の周囲を効果的に圧密することができる地盤
改良工法を提供することができる。
According to the first aspect of the present invention, an excavation hole having a predetermined depth is formed while rotating the earth auger forward, and thereafter, the earth auger is reversely rotated at a low speed and a vertical axial force is applied. This is a ground improvement method in which a horizontal force is applied to the aggregate supplied from the ground surface by the earth auger to consolidate the surroundings of the excavation hole and the inside of the excavation hole. A ground improvement method capable of effectively consolidating can be provided.

【0032】また、請求項2の発明は、前記アースオー
ガーの逆回転が、毎分25回転以下である地盤改良工法
であり、環境への適合性に優れ、掘削孔の周囲を効果的
に圧密することができる地盤改良工法を提供することが
できる。
[0032] The invention of claim 2 is a ground improvement method in which the reverse rotation of the earth auger is 25 rotations per minute or less, which is excellent in environmental compatibility and effectively consolidates the periphery of the excavation hole. A ground improvement method that can be performed can be provided.

【0033】また、請求項3の発明は、改良地盤容積に
対して、6〜10%の骨材を追加する地盤改良工法であ
り、環境への適合性に優れ、掘削孔の周囲を効果的に圧
密することができる地盤改良工法を提供することができ
る。
[0033] The invention of claim 3 is a ground improvement method in which 6 to 10% of aggregate is added to the improved ground volume, which is excellent in environmental compatibility and effective in surrounding the excavation hole. And a ground improvement method capable of compacting the ground.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施例を示す掘削開始初期の断面図
である。
FIG. 1 is a cross-sectional view showing an embodiment of the present invention at the beginning of excavation.

【図2】本発明の一実施例を示す掘削孔を形成した状態
の断面図である。
FIG. 2 is a cross-sectional view showing a state in which an excavation hole is formed according to an embodiment of the present invention.

【図3】本発明の一実施例を示すアースオーガーを逆回
転して圧密作業を行っている状態の断面図である。
FIG. 3 is a cross-sectional view illustrating a state in which the earth auger according to the embodiment of the present invention is rotated in the reverse direction to perform a compacting operation.

【図4】本発明の一実施例を示す地盤改良を行う地表部
の平面図である。
FIG. 4 is a plan view of a ground surface portion for performing ground improvement showing one embodiment of the present invention.

【符号の説明】[Explanation of symbols]

3 地表部 5 アースオーガー 11 掘削孔 12 骨材 13 山砂 14 生石灰 3 Ground surface part 5 Earth auger 11 Drilling hole 12 Aggregate 13 Mountain sand 14 Quicklime

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 アースオーガーを正転しながら所定深さ
の掘削孔を形成し、この後、前記アースオーガーを低速
で逆回転すると共に、垂直方向の軸力を加え、前記アー
スオーガーにより地表部から投入した骨材に水平方向の
力を加えて掘削孔の周囲及び掘削孔内を圧密することを
特徴とする地盤改良工法。
An excavation hole having a predetermined depth is formed while rotating the earth auger, and thereafter, the earth auger is reversely rotated at a low speed, and a vertical axial force is applied. A ground improvement method characterized in that a horizontal force is applied to the aggregate supplied from above to consolidate around and inside the excavation hole.
【請求項2】 前記アースオーガーの逆回転が、毎分2
5回転以下であることを特徴とする請求項1記載の地盤
改良工法。
2. A reverse rotation of the earth auger is performed at a rate of 2 / min.
The ground improvement method according to claim 1, wherein the rotation speed is 5 rotations or less.
【請求項3】 改良地盤容積に対して、6〜10%の骨
材を追加することを特徴とする請求項1又は2記載の地
盤改良工法。
3. The ground improvement method according to claim 1, wherein an aggregate of 6 to 10% is added to the improved ground volume.
JP35789899A 1999-12-16 1999-12-16 Ground improvement method Expired - Lifetime JP3594121B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP35789899A JP3594121B2 (en) 1999-12-16 1999-12-16 Ground improvement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP35789899A JP3594121B2 (en) 1999-12-16 1999-12-16 Ground improvement method

Publications (2)

Publication Number Publication Date
JP2001172956A true JP2001172956A (en) 2001-06-26
JP3594121B2 JP3594121B2 (en) 2004-11-24

Family

ID=18456509

Family Applications (1)

Application Number Title Priority Date Filing Date
JP35789899A Expired - Lifetime JP3594121B2 (en) 1999-12-16 1999-12-16 Ground improvement method

Country Status (1)

Country Link
JP (1) JP3594121B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008075447A (en) * 2007-12-10 2008-04-03 Asahi Tec Corp Soil improvement method
JP2008267016A (en) * 2007-04-20 2008-11-06 Hikari Kensetsu:Kk Soil improving method
JP5311430B1 (en) * 2012-04-17 2013-10-09 昭二 坂上 Ground improvement method
JP2018135749A (en) * 2018-04-26 2018-08-30 株式会社新生工務 Construction method of pile reinforcement structure and apparatus of the same

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008267016A (en) * 2007-04-20 2008-11-06 Hikari Kensetsu:Kk Soil improving method
JP2008075447A (en) * 2007-12-10 2008-04-03 Asahi Tec Corp Soil improvement method
JP5311430B1 (en) * 2012-04-17 2013-10-09 昭二 坂上 Ground improvement method
JP2018135749A (en) * 2018-04-26 2018-08-30 株式会社新生工務 Construction method of pile reinforcement structure and apparatus of the same

Also Published As

Publication number Publication date
JP3594121B2 (en) 2004-11-24

Similar Documents

Publication Publication Date Title
KR100394413B1 (en) In-situ soil mixing pile by multi-auger machine and column wall set up method
JP4827020B2 (en) Ground improvement method
JPH10204876A (en) Soil improvement method by using pile
EP0539079B1 (en) Apparatus and method for constructing compacted granular or stone columns in soil masses
JP4852732B2 (en) Column replacement construction method
JP4027264B2 (en) How to construct soil cement composite piles
JP3594121B2 (en) Ground improvement method
JP4232952B2 (en) Ground improvement method and apparatus
JP3920974B2 (en) Earth auger excavator and construction method of deep underground column wall in collapsible gravel layer
JP2005009240A (en) Method for installing soil hardened matter on-site-manufactured pile and prefabricated pile
JP2819025B2 (en) Soft ground improvement method
JP2001152448A (en) Construction method for underground concrete structure
JPH07189241A (en) Ground improving machine and method of ground improving construction
JP5726007B2 (en) Ground improvement method
KR19980020441A (en) Pile foundation construction method and device
JPH08134891A (en) Stabilization of soft ground
JP7435060B2 (en) How to build underground structures
JP2783525B2 (en) Ground improvement method
Leznicki et al. Loss of ground during CFA pile installation in inner urban areas
JP4867044B2 (en) Column replacement construction method
KR200266338Y1 (en) In-situ soil mixing pile by multi-auger machine
JP2001164550A (en) Improvement method of construction ground for underground structure
JPH0627405B2 (en) Ready-made pile burying method
JPH08134893A (en) Stabilization of soft ground
Warner et al. Limited Mobility Grouting--Past, Present, and Future

Legal Events

Date Code Title Description
A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040825

R150 Certificate of patent or registration of utility model

Ref document number: 3594121

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R154 Certificate of patent or utility model (reissue)

Free format text: JAPANESE INTERMEDIATE CODE: R154

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070910

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080910

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090910

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090910

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100910

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110910

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110910

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120910

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120910

Year of fee payment: 8

S202 Request for registration of non-exclusive licence

Free format text: JAPANESE INTERMEDIATE CODE: R315201

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120910

Year of fee payment: 8

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120910

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130910

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term