JP2001115421A - Construction method for temporary bridge and pier - Google Patents
Construction method for temporary bridge and pierInfo
- Publication number
- JP2001115421A JP2001115421A JP29580099A JP29580099A JP2001115421A JP 2001115421 A JP2001115421 A JP 2001115421A JP 29580099 A JP29580099 A JP 29580099A JP 29580099 A JP29580099 A JP 29580099A JP 2001115421 A JP2001115421 A JP 2001115421A
- Authority
- JP
- Japan
- Prior art keywords
- temporary
- pier
- erection
- pile
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、仮橋仮桟橋の架設
方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for erection of a temporary bridge and a temporary pier.
【0002】[0002]
【発明が解決しようとする課題】従来、仮橋、仮桟橋を
構築する際、杭橋脚打設用の仮構台と、上部工作業のた
めの足場構築がそれぞれ必要であり、機材搬入の困難な
山間部、傾斜地では低劣な作業環境の中での作業になり
作業性、安全性の向上が望まれていた。Conventionally, when constructing a temporary bridge and a temporary pier, it is necessary to construct a temporary gantry for driving a pile bridge pier and a scaffold for superstructure work, and it is difficult to carry in equipment. In mountainous areas and sloping lands, work is performed in poor working environments, and workability and safety have been desired to be improved.
【0003】[0003]
【発明の目的】本発明は、上記のような問題点を解決す
るためになされたもので、作業性、安全性の面で優れて
いると共に、安価で、しかも一度に長い距離の施工がで
きる仮橋仮桟橋の架設方法を提供することを目的とす
る。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and is excellent in workability and safety, inexpensive, and can be applied for a long distance at a time. An object of the present invention is to provide a method for erection of a temporary bridge temporary pier.
【0004】[0004]
【課題を解決するための手段】上記課題を解決するため
の手段として本発明は、仮橋仮桟橋の架設方法におい
て、既設ステージから架設方向に張り出した少なくとも
2本のビームの先端側を仮杭で支持する工程と、ビーム
上から仮橋仮桟橋の支柱の打設作業と上部工を行ってス
テージを構築する工程と、ビームを前方に送り出して前
工程で構築した既設ステージから架設方向に張り出させ
て仮杭で支持する工程とを繰り返して行うことを特徴と
する、仮橋仮桟橋の架設方法を提供する。According to the present invention, there is provided a method for erection of a temporary bridge and a temporary pier, the method comprising the steps of: providing at least two beams extending from an existing stage in the installation direction in a temporary pile; Step of constructing the stage by performing the work of placing the temporary bridge temporary pier and superstructure from the beam, and sending the beam forward and stretching the existing stage constructed in the previous process in the direction of erection. And providing a temporary pier and a temporary pier.
【0005】また、上記仮橋仮桟橋の架設方法におい
て、ビームは、既設ステージの両側部から突出した受梁
部上に、片持式に固定したことを特徴とする、仮橋仮桟
橋の架設方法を提供する。[0005] In the above method of erection of a temporary bridge temporary pier, the beam is fixed in a cantilever manner on a receiving portion projecting from both sides of the existing stage. Provide a way.
【0006】また、上記仮橋仮桟橋の架設方法におい
て、ビームの先端側を仮杭に支持する際に、各ビームの
下面側に横架させた受桁を吊り上げてビームのしなりを
修正した後、受桁と仮杭上端部とを連結することによっ
て、受桁の上面にビーム先端側の下面を支持することを
特徴とした、仮橋仮桟橋の架設方法を提供する。In the method of erection of the temporary bridge and the temporary pier, when the front end side of the beam is supported on the temporary pile, the bending of the beam is corrected by lifting up a girder suspended laterally on the lower surface side of each beam. Thereafter, a method for erection of a temporary bridge temporary pier, characterized in that the beam receiving girder and the upper end of the temporary pile are connected to support the lower surface on the beam tip side on the upper surface of the beam receiving girder.
【0007】さらに、上記仮橋仮桟橋の架設方法におい
て、ビームは回転ピースを介在させて既設ステージ上に
傾斜させて設置したことを特徴とする、仮橋仮桟橋の架
設方法を提供する。以下、図面を参照しながら、本発明
の実施の形態について説明する。Further, in the method of erection of the temporary bridge temporary pier, a method of erection of the temporary bridge temporary pier is provided, wherein the beam is installed inclined on an existing stage with a rotating piece interposed. Hereinafter, embodiments of the present invention will be described with reference to the drawings.
【0008】[0008]
【発明の実施の形態】<イ>ベースステージの構築 地山上からクレーン及びバイブロハンマーなどを用い
て、図1、2に示すように、まず最初のステージを構築
する。本実施の形態は、H鋼、鋼管等の支柱1を3本並
列させて2列打設する場合であるが、施工本数は施工規
模等の諸条件によって異なる。また、ベースステージの
構築方法は種々の公知の方法で行うことができる。DESCRIPTION OF THE PREFERRED EMBODIMENTS <A> Construction of base stage First, as shown in FIGS. 1 and 2, a first stage is constructed from above the ground using a crane and a vibro hammer. The present embodiment is a case where three columns 1 of H steel, steel pipe, etc. are arranged in parallel and two rows are cast, but the number of works differs depending on various conditions such as the scale of the work. In addition, the base stage can be constructed by various known methods.
【0009】次に、仮橋の架設方向に対して直交方向に
並ぶ各支柱1の頭部間を、一対の横桁11で挟持して溶
接等により連結する。このとき、横桁11の両端部は、
両端の支柱1から側方に突出させ、後述のビームを搭載
するための受梁部12とする。さらに、パネル化したブ
レス13によって、仮橋の架設方向に並ぶ各支柱1間を
連結して補強する。ブレス13はパネル化することで現
場溶接の手間を削減できる。Next, the heads of the columns 1 arranged in a direction perpendicular to the direction of erection of the temporary bridge are sandwiched between a pair of cross beams 11 and connected by welding or the like. At this time, both ends of the cross beam 11
Protrusions are laterally protruded from the pillars 1 at both ends to form a receiving portion 12 for mounting a beam described later. Further, the struts 1 arranged in the direction of erection of the temporary bridge are connected and reinforced by the panelized breath 13. The breath 13 can be made into a panel, so that the work of on-site welding can be reduced.
【0010】次に、横桁11上の受梁部12間に、仮橋
の架設方向に向けて、複数本の主桁14を適宜間隔をお
いて接合する。主桁14にはH鋼などを使用する。そし
て主桁14上には、複数枚の覆工板15を敷き並べる。Next, a plurality of main girders 14 are joined at appropriate intervals between the receiving beams 12 on the cross girders 11 in the direction of erection of the temporary bridge. The main girder 14 is made of H steel or the like. On the main girder 14, a plurality of lining plates 15 are laid out.
【0011】<ロ>ビームの張り出し 図3に示すように、H鋼等の二本のビーム2の一端側
を、受梁部12上に支圧板21、止め金具22等を用い
て片持式に固定し、ベースステージの両側部から架設方
向に張り出させる。ビーム2間はブレス23等で連結し
て補強する。ビーム2の張り出し作業は、クレーン3で
ビーム2を吊り上げた状態で行う。<B> Projection of Beam As shown in FIG. 3, one end of two beams 2 made of H steel or the like is cantilevered by using a support plate 21, a stopper 22, etc. on a receiving portion 12. And protrude from both sides of the base stage in the erection direction. The beams 2 are connected and reinforced by a breath 23 or the like. The projecting operation of the beam 2 is performed while the beam 2 is lifted by the crane 3.
【0012】また、図示しないが、ビーム2には全長に
沿って作業足場を取り付けておき、ブレス23の設置作
業など、全工程に亘って必要な上部工を行う。なお、図
示しないが、仮橋仮桟橋の規模によっては、ステージの
両側部と中間部に覆工板15を配置しない受梁部12を
設け、3本以上のビーム2を架設することも考えられ
る。Although not shown, a work scaffold is attached to the beam 2 along its entire length, and necessary superstructure work is performed throughout the entire process such as the work of installing the breath 23. Although not shown, depending on the size of the temporary bridge and the temporary pier, it is also conceivable to provide a receiving portion 12 in which the lining plate 15 is not disposed on both sides and an intermediate portion of the stage, and construct three or more beams 2. .
【0013】<ハ>仮杭の打設 2本のビーム2の先端の内側近傍に、H鋼等の仮杭4を
打設する。打設作業は、覆工板15上に乗り入れたクレ
ーン3によって仮杭4を吊り上げ、バイブロハンマーに
よって基面地山に打ち込んで行う。打設作業は現場に合
せて適切な施工法を決定する。なお、この仮杭4を打設
した後に、ビーム2の張り出し作業を行ってもよい。ま
た、ビーム2を3本以上架設する場合は、その数に対応
させて仮杭4も打設する。<C> Placement of temporary pile A temporary pile 4 made of H steel or the like is placed near the inside of the tips of the two beams 2. The placing operation is performed by lifting the temporary pile 4 by the crane 3 that has entered the lining plate 15 and driving the temporary pile 4 into the base ground with a vibro hammer. For the casting work, an appropriate construction method is determined according to the site. After the temporary pile 4 has been driven, the beam 2 may be extended. When three or more beams 2 are erected, the temporary piles 4 are also driven according to the number.
【0014】<ニ>ビーム先端の支持 打設した仮杭4の上端部に、ビーム2の先端を支持させ
る。支持手段は、図3、4に示すようなH鋼等の受桁4
1と、その保持装置5を用いて行う。保持装置5は、図
4に示すように、仮杭4のH鋼のウェブ部等に引っ掛け
るための帯板状等の掛止部材51と、受桁41を保持す
るボックス状の保持部材52とよりなる。<D> Support of Beam Tip The tip of the beam 2 is supported on the upper end of the temporary pile 4 that has been cast. The support means is a girder 4 such as H steel as shown in FIGS.
1 and the holding device 5. As shown in FIG. 4, the holding device 5 includes a strip-shaped holding member 51 for hooking the temporary pile 4 on the H steel web portion or the like, a box-shaped holding member 52 for holding the receiving beam 41, and the like. Consisting of
【0015】掛止部材51は、帯板体等の上端に仮杭4
に引っ掛けるためのフック部を形成する。保持部材52
は、2枚の板体を対向させてボックス状等に構成し、受
桁41を水平方向に挿入するための挿入口53を各板体
に開設する。そして、図4に示すように、両板体間に掛
止部材51を挟んだ状態で、両者に開設した穴54、5
5を重ねてピン56で連結する。なお、ピン56の頭部
側には板状のストッパ57が取り付けてあり、受け溝を
有するストッパ受け58に掛止し、脱落防止を図る。The hanging member 51 is provided at the upper end of the band plate or the like.
To form hooks for hooking on Holding member 52
The two plates are opposed to each other to form a box or the like, and an insertion opening 53 for inserting the receiving beam 41 in the horizontal direction is opened in each plate. Then, as shown in FIG. 4, the holes 54, 5
5 are overlapped and connected by pins 56. Note that a plate-shaped stopper 57 is attached to the head side of the pin 56, and is hooked on a stopper receiver 58 having a receiving groove to prevent the pin 56 from falling off.
【0016】ビーム2の先端の支持方法は、先ず、打設
した仮杭4の上端部に、掛止部材51を予め取り付けお
く。次に、保持部材52を受桁41の両端側に取り付け
た状態で、受桁41をビーム2の下面にブルマン等で固
定する。次に、ビーム2のしなりが修正されるまでクレ
ーン3で受桁41を吊り上げた後、ピン56で掛止部材
51と保持部材52を連結する。これによって、ビーム
2に作用する後述の掘削装置7の作動時の反力及び荷重
が、保持装置5を介して仮杭4に伝達分担される。In the method of supporting the tip of the beam 2, first, a hooking member 51 is attached in advance to the upper end of the temporary pile 4 that has been cast. Next, with the holding members 52 attached to both ends of the receiving beam 41, the receiving beam 41 is fixed to the lower surface of the beam 2 by Bullman or the like. Next, after the receiving beam 41 is lifted by the crane 3 until the bending of the beam 2 is corrected, the hooking member 51 and the holding member 52 are connected by the pin 56. Thereby, the reaction force and the load acting on the beam 2 when the excavator 7 described later is operated are transmitted and shared to the temporary pile 4 via the holding device 5.
【0017】図5は、岩盤施工用の管体状の仮杭42の
場合に用いる保持装置6を示す。この保持装置6は、仮
杭42に掛止するための掛止部材61と、受桁41を保
持するための保持部材62と、それらを連結するための
嵌装部63とよりなる。FIG. 5 shows a holding device 6 used in the case of a tubular temporary pile 42 for rock construction. The holding device 6 includes a hooking member 61 for hooking the temporary pile 42, a holding member 62 for holding the girder 41, and a fitting portion 63 for connecting them.
【0018】掛止部材61は、U字状に曲折しており、
その一端側は仮杭42の管体上端開口部に差し込み可能
で、他端側には複数の穴64aが開設されている。保持
部材62は、2枚の板体を対向させてボックス状等に構
成し、受桁41を水平方向に挿入するための挿入口65
を各板体に開設してある。The hooking member 61 is bent in a U-shape.
One end thereof can be inserted into the upper end opening of the pipe of the temporary pile 42, and a plurality of holes 64a are opened at the other end. The holding member 62 is formed in a box shape or the like with two plate bodies facing each other, and an insertion port 65 for inserting the receiving beam 41 in the horizontal direction.
Is set up on each plate.
【0019】嵌装部63は、仮杭42を挿入可能な管体
であり、その一方側にブラケット66を突設し、ヒンジ
67で保持部材62を回動自在に軸支し、他方側には平
板部68を設けて、ピン69の挿入穴64bを複数開設
する。なお、嵌装部63は半割り状態の管体を開閉自在
にヒンジ連結する構造でもよい。The fitting portion 63 is a tube into which the temporary pile 42 can be inserted. A bracket 66 is protruded from one side of the fitting portion 63. The holding member 62 is pivotally supported by a hinge 67 so as to be rotatable. Is provided with a flat plate portion 68 and a plurality of insertion holes 64b for the pins 69 are formed. Note that the fitting portion 63 may have a structure in which a half-split tube body is hinged so as to be freely opened and closed.
【0020】ビーム2の先端の支持方法は、先ず、保持
部材62及び嵌装部63を受桁41の両端側に取り付け
た状態で、受桁41をビーム2の下面にブルマン等で固
定する。次に、嵌装部63に仮杭42を挿入し、仮杭4
2の上端部をクレーン3で吊った打込ウェイトなどで打
撃して仮杭42を鉛直方向に打ち込む。このとき、ビー
ム2及び保持部材62が斜め姿勢であっても、ヒンジ6
7を介して嵌装部63及び仮杭42の鉛直姿勢を保持す
ることができる。嵌装部63が鉛直姿勢になったら、ヒ
ンジ67を図示しないストッパで固定するAs a method of supporting the tip of the beam 2, first, the receiving beam 41 is fixed to the lower surface of the beam 2 with a Bullman or the like while the holding member 62 and the fitting portion 63 are attached to both ends of the receiving beam 41. Next, the temporary pile 42 is inserted into the fitting portion 63 and the temporary pile 4 is inserted.
The temporary pile 42 is driven in the vertical direction by hitting the upper end of 2 with a driving weight suspended by the crane 3 or the like. At this time, even if the beam 2 and the holding member 62 are in the oblique posture, the hinge 6
The vertical posture of the fitting portion 63 and the temporary stake 42 can be maintained through the connection member 7. When the fitting portion 63 is in the vertical position, the hinge 67 is fixed with a stopper (not shown).
【0021】仮杭42の打設後、仮杭42の上端部に、
掛止部材61を取り付ける。そして、ビーム2のしなり
が修正されるまでクレーン3で受桁41を吊り上げ、掛
止部材61と平板部68の穴64a、64bが重なる部
分にピン69を差し込んで両者を連結固定する。After placing the temporary pile 42, the upper end of the temporary pile 42
The hook member 61 is attached. Then, the receiving beam 41 is lifted by the crane 3 until the bending of the beam 2 is corrected, and the pin 69 is inserted into a portion where the hole 64a, 64b of the latch member 61 and the flat plate portion 68 overlaps to connect and fix them.
【0022】<ホ>支柱の立て込み 両ビーム2を仮杭4に支持した後、図3に示すように、
ビーム2間に架台24を横架し、その上に掘削装置7を
セットする。掘削装置7は、架台24上に固定した回転
装置71と、クレーン3で吊り下げて回転装置71に回
転可能に貫通させたダウンザホールドリル72等の公知
の装置を用いる。<E> Standing up of pillars After both beams 2 are supported on the temporary pile 4, as shown in FIG.
The gantry 24 is horizontally mounted between the beams 2, and the excavator 7 is set thereon. The drilling device 7 uses a known device such as a rotating device 71 fixed on the gantry 24 and a down-the-hole drill 72 suspended by the crane 3 and rotatably penetrating the rotating device 71.
【0023】この掘削装置7で掘削した後、ビーム2に
定規を取り付けて固定し、ビーム2間に支柱1を間隔を
おいて所定本数立て込む。本実施の形態は、図6に示す
ように、ビーム2間方向に間隔をおいて3本配設し、そ
れを架設方向に2列に配列した場合である。After excavation by the excavator 7, a ruler is attached to the beam 2 and fixed, and a predetermined number of columns 1 are erected between the beams 2 at intervals. In the present embodiment, as shown in FIG. 6, three beams are arranged at intervals in the direction between the beams 2 and are arranged in two rows in the erection direction.
【0024】上記のようにビーム上及びベースステージ
上において支柱1の立て込み作業を行えるため、地上で
の架台仮組が不要である。また、ベースステージ上から
50トンクレーンで最大15m先の地盤に支柱1の施工
が可能であるため、1工程の施工距離を長くできる。As described above, the work for setting up the support column 1 can be performed on the beam and the base stage, so that there is no need to temporarily mount the gantry on the ground. In addition, since the column 1 can be installed on the ground at a maximum of 15 m away from the base stage with a 50-ton crane, the installation distance of one process can be increased.
【0025】<ヘ>ステージの構築 図6、7に示すように、ビーム2に吊足場8をセットす
る。そして、この吊足場8や、図示しないがビーム2に
配備したその他の作業足場より、図1、2のベースステ
ージの構造と同じように、新たに打設した6本の支柱1
の上部に、横桁11、ブレス13、主桁14、覆工板1
5等の上部工を施す。このとき、主桁14はベースステ
ージの主桁14と連結し、覆工板15はブレス23を撤
去してベースステージ連続して敷き詰める。これらの上
部工はビーム2上で行えるため、地面からの仮足場の組
立は不要である。<F> Construction of Stage As shown in FIGS. 6 and 7, a suspension scaffold 8 is set on the beam 2. Then, from the suspending scaffold 8 and other working scaffolds (not shown) arranged on the beam 2, similarly to the structure of the base stage in FIGS.
At the top of the cross beam 11, breath 13, main girder 14, lining board 1
Apply a superstructure such as 5th grade. At this time, the main girder 14 is connected to the main girder 14 of the base stage, and the lining plate 15 removes the breath 23 and spreads the base stage continuously. Since these superstructures can be performed on the beam 2, it is not necessary to assemble the temporary scaffold from the ground.
【0026】<ト>ビームの送り出し 覆工終了後、図8に示すように、ビーム2を1ピッチ前
方に送り出し、新設ステージの受梁部12上に、図3と
同様に、ビーム2を片持ち式に固定し、架設方向に張り
出させる。以上の工程を繰り返して行い、所定長の仮橋
仮桟橋を構築する。<G> Beam delivery After the lining is completed, as shown in FIG. 8, the beam 2 is delivered one pitch forward, and the beam 2 is placed on the beam receiving portion 12 of the new stage similarly to FIG. Fix it in a portable manner and project it in the installation direction. The above steps are repeated to build a temporary bridge temporary pier of a predetermined length.
【0027】なお、図9に示すように、ビーム2と受梁
部12との間に公知の回転ピース9を介在させ、かつ架
設方向先端側(図では右側)に、加えてブロック91を
介在させることによって、ビーム2を勾配に応じて傾斜
させて張り出させることが可能となる。As shown in FIG. 9, a known rotating piece 9 is interposed between the beam 2 and the receiving part 12, and a block 91 is interposed between the beam 2 and the receiving part 12 at the front end side (right side in the drawing) in the erection direction. By doing so, it becomes possible to project the beam 2 inclining according to the gradient.
【0028】[0028]
【発明の効果】本発明は以上説明したようになるため、
次のような効果を得ることができる。 <イ>従来のユニット桟橋パネルのような特殊な加工部
材がほとんど不要である。そのため、H鋼などの従来の
安価な重仮設資材を使用でき、経済的である。Since the present invention has been described above,
The following effects can be obtained. <a> Almost no special processing members such as conventional unit pier panels are required. For this reason, conventional inexpensive heavy temporary materials such as H steel can be used, which is economical.
【0029】<ロ>既設ステージ上から50トンクレー
ンで、最大15m先の地盤に支柱施工が可能である。従
って、15m先までの長い距離を1工程で施工が可能で
あり、施工効率の向上を図ることができる。<B> With a 50-ton crane from above the existing stage, it is possible to construct a pillar up to 15 m away from the ground. Therefore, a long distance up to 15 m can be constructed in one process, and construction efficiency can be improved.
【0030】<ハ>既設ステージ上あるいはビーム上の
吊足場からほとんどの作業ができるため、基面上での作
業を極力減らすことができる。従って、地形の影響をほ
とんど受けず仮橋、仮桟橋の作業を安全かつ効率よく行
うことができる。<C> Most of the work can be performed from the suspended scaffold on the existing stage or on the beam, so that the work on the base surface can be reduced as much as possible. Therefore, the work on the temporary bridge and the temporary pier can be performed safely and efficiently without being affected by the topography.
【0031】<ニ>ビームを回転ピースを介在させて既
設ステージ上に設置することによって、ビームを容易か
つ確実に勾配に応じて傾斜させることができる。<D> By arranging the beam on the existing stage with a rotating piece interposed, the beam can be easily and reliably inclined according to the gradient.
【図1】 既設のベースステージの施工工程の説明図FIG. 1 is an explanatory view of a construction process of an existing base stage.
【図2】 既設のベースステージの施工工程の説明図FIG. 2 is an explanatory view of a construction process of an existing base stage.
【図3】 ビーム張り出し、仮杭打設、支柱打設工程の
説明図FIG. 3 is an explanatory view of beam overhanging, provisional pile driving, and strut driving processes.
【図4】 受桁保持装置の説明図FIG. 4 is an explanatory view of a girder holding device.
【図5】 受桁保持装置の説明図FIG. 5 is an explanatory view of a girder receiving device;
【図6】 ビーム張り出し、仮杭打設、支柱打設工程の
説明図FIG. 6 is an explanatory view of beam overhanging, provisional pile driving, and strut driving processes.
【図7】 ビーム張り出し、仮杭打設、支柱打設工程の
説明図FIG. 7 is an explanatory view of beam overhanging, provisional pile driving, and strut driving processes.
【図8】 ビーム送り出し工程の説明図FIG. 8 is an explanatory view of a beam sending step.
【図9】 ビームの傾斜構造の説明図FIG. 9 is an explanatory view of a beam tilt structure.
Claims (4)
のビームの先端側を仮杭で支持する工程と、 ビーム上から仮橋仮桟橋の支柱の打設作業と上部工を行
ってステージを構築する工程と、 ビームを前方に送り出して前工程で構築した既設ステー
ジから架設方向に張り出させて仮杭で支持する工程とを
繰り返して行うことを特徴とする、 仮橋仮桟橋の架設方法。1. A method for erection of a temporary bridge temporary pier, comprising: a step of supporting at least two beams protruding from an existing stage in a direction of erection with temporary piles; It is characterized by repeating the steps of constructing the stage by performing installation work and superstructure work, and sending the beam forward and extending it from the existing stage constructed in the previous process in the erection direction and supporting it with temporary piles. The method of erection of temporary bridge temporary pier.
において、 ビームは、既設ステージの両側部から突出した受梁部上
に、片持式に固定したことを特徴とする、 仮橋仮桟橋の架設方法。2. The method according to claim 1, wherein the beam is fixed in a cantilever manner on a receiving portion protruding from both sides of the existing stage. How to build a temporary bridge pier.
設方法において、 ビームの先端側を仮杭に支持する際に、 各ビームの下面側に横架させた受桁を吊り上げてビーム
のしなりを修正した後、 受桁と仮杭上端部とを連結することによって、 受桁の上面にビーム先端側の下面を支持することを特徴
とした、 仮橋仮桟橋の架設方法。3. The method for erection of a temporary bridge temporary pier according to claim 1 or 2, wherein when the tip end side of the beam is supported on a temporary pile, a receiving girder suspended horizontally on the lower surface side of each beam is lifted. A method for erection of a temporary bridge and a temporary pier, characterized in that after bending of a beam is corrected, a lower beam on a beam tip side is supported on an upper surface of the beam by connecting the beam and the upper end of a temporary pile.
仮桟橋の架設方法において、 ビームは回転ピースを介在させて既設ステージ上に傾斜
させて設置したことを特徴とする、 仮橋仮桟橋の架設方法。4. The temporary bridge according to claim 1, wherein the beam is inclined on an existing stage with a rotary piece interposed therebetween. How to build a temporary pier.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP29580099A JP4219067B2 (en) | 1999-10-18 | 1999-10-18 | Construction method of temporary bridge temporary pier |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP29580099A JP4219067B2 (en) | 1999-10-18 | 1999-10-18 | Construction method of temporary bridge temporary pier |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001115421A true JP2001115421A (en) | 2001-04-24 |
JP4219067B2 JP4219067B2 (en) | 2009-02-04 |
Family
ID=17825337
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP29580099A Expired - Fee Related JP4219067B2 (en) | 1999-10-18 | 1999-10-18 | Construction method of temporary bridge temporary pier |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4219067B2 (en) |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004285735A (en) * | 2003-03-24 | 2004-10-14 | Kouchi Marutaka:Kk | Method of constructing temporary landing bridge by using truss frame |
JP2006161548A (en) * | 2004-11-11 | 2006-06-22 | Sanyo Kenzai Kk | Temporary pier, erection method for temporary pier, carriage used for temporary pier, and pile driving method using temporary pier |
JP2006274736A (en) * | 2005-03-30 | 2006-10-12 | Hitachi Zosen Corp | Construction method for pc floor system and pc floor system |
JP2012162862A (en) * | 2011-02-03 | 2012-08-30 | Kouchi Marutaka:Kk | Scaffold for pier construction and pier construction method |
KR101192052B1 (en) | 2011-01-18 | 2012-10-17 | 주식회사 벤트코리아 | Method for constructing temporary bridge using movable boxgirder |
JP2013147926A (en) * | 2011-12-21 | 2013-08-01 | Yokoyama Kiso Koji:Kk | Tubular pile installation method, excavation method, inner digger device and gripping device |
JP5977904B1 (en) * | 2016-04-13 | 2016-08-24 | ヒロセ株式会社 | Construction method of simple temporary bridge |
JP2019131978A (en) * | 2018-01-29 | 2019-08-08 | 鹿島建設株式会社 | Bridge construction method |
KR20200098214A (en) * | 2019-02-12 | 2020-08-20 | 박상현 | Temporary bridge having a software girder and method of constructing the temporary bridge |
JP2020159162A (en) * | 2019-03-28 | 2020-10-01 | 株式会社奥村組 | Temporary structure and construction method thereof |
CN112627035A (en) * | 2020-12-10 | 2021-04-09 | 上海宝冶集团有限公司 | Design and construction method of large-span Bailey steel trestle |
CN112982131A (en) * | 2021-02-07 | 2021-06-18 | 中交第三航务工程勘察设计院有限公司 | Offshore open type airport runway and construction method thereof |
JP2022021555A (en) * | 2020-07-22 | 2022-02-03 | 鹿島建設株式会社 | Bridge construction method and gondola structure |
CN114319159A (en) * | 2021-12-29 | 2022-04-12 | 杭州萧山交通建设管理有限公司 | Ascending ramp dismantling system and construction method |
CN114703757A (en) * | 2022-04-13 | 2022-07-05 | 中交路桥建设有限公司 | Multifunctional support for steel cross beam of cable-stayed bridge and assembling method of steel cross beam |
JP2022167621A (en) * | 2021-04-23 | 2022-11-04 | 株式会社タイセン工業 | Temporary bridge unit |
JP7301248B1 (en) | 2023-01-27 | 2023-06-30 | 太洋ヒロセ株式会社 | Structure of floor girder unit and temporary pier |
-
1999
- 1999-10-18 JP JP29580099A patent/JP4219067B2/en not_active Expired - Fee Related
Cited By (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004285735A (en) * | 2003-03-24 | 2004-10-14 | Kouchi Marutaka:Kk | Method of constructing temporary landing bridge by using truss frame |
JP2006161548A (en) * | 2004-11-11 | 2006-06-22 | Sanyo Kenzai Kk | Temporary pier, erection method for temporary pier, carriage used for temporary pier, and pile driving method using temporary pier |
JP4504910B2 (en) * | 2004-11-11 | 2010-07-14 | 山陽建材株式会社 | Dolly and method of erection of temporary pier using it |
JP2006274736A (en) * | 2005-03-30 | 2006-10-12 | Hitachi Zosen Corp | Construction method for pc floor system and pc floor system |
KR101192052B1 (en) | 2011-01-18 | 2012-10-17 | 주식회사 벤트코리아 | Method for constructing temporary bridge using movable boxgirder |
JP2012162862A (en) * | 2011-02-03 | 2012-08-30 | Kouchi Marutaka:Kk | Scaffold for pier construction and pier construction method |
JP2013147926A (en) * | 2011-12-21 | 2013-08-01 | Yokoyama Kiso Koji:Kk | Tubular pile installation method, excavation method, inner digger device and gripping device |
JP5977904B1 (en) * | 2016-04-13 | 2016-08-24 | ヒロセ株式会社 | Construction method of simple temporary bridge |
JP2019131978A (en) * | 2018-01-29 | 2019-08-08 | 鹿島建設株式会社 | Bridge construction method |
KR20200098214A (en) * | 2019-02-12 | 2020-08-20 | 박상현 | Temporary bridge having a software girder and method of constructing the temporary bridge |
KR102273565B1 (en) * | 2019-02-12 | 2021-07-05 | 박상현 | Temporary bridge having a software girder and method of constructing the temporary bridge |
JP2020159162A (en) * | 2019-03-28 | 2020-10-01 | 株式会社奥村組 | Temporary structure and construction method thereof |
JP7148080B2 (en) | 2019-03-28 | 2022-10-05 | 株式会社奥村組 | Temporary structure and its construction method |
JP2022021555A (en) * | 2020-07-22 | 2022-02-03 | 鹿島建設株式会社 | Bridge construction method and gondola structure |
JP7356406B2 (en) | 2020-07-22 | 2023-10-04 | 鹿島建設株式会社 | Bridge construction method and gondola structure |
CN112627035A (en) * | 2020-12-10 | 2021-04-09 | 上海宝冶集团有限公司 | Design and construction method of large-span Bailey steel trestle |
CN112982131A (en) * | 2021-02-07 | 2021-06-18 | 中交第三航务工程勘察设计院有限公司 | Offshore open type airport runway and construction method thereof |
JP2022167621A (en) * | 2021-04-23 | 2022-11-04 | 株式会社タイセン工業 | Temporary bridge unit |
JP7207772B2 (en) | 2021-04-23 | 2023-01-18 | 株式会社タイセン工業 | Temporary bridge unit |
CN114319159B (en) * | 2021-12-29 | 2023-08-08 | 杭州萧山交通建设管理有限公司 | Ascending ramp dismantling system and construction method |
CN114319159A (en) * | 2021-12-29 | 2022-04-12 | 杭州萧山交通建设管理有限公司 | Ascending ramp dismantling system and construction method |
CN114703757A (en) * | 2022-04-13 | 2022-07-05 | 中交路桥建设有限公司 | Multifunctional support for steel cross beam of cable-stayed bridge and assembling method of steel cross beam |
CN114703757B (en) * | 2022-04-13 | 2024-04-19 | 中交路桥建设有限公司 | Multifunctional bracket for steel cross beam of cable-stayed bridge and assembly method of steel cross beam |
JP7301248B1 (en) | 2023-01-27 | 2023-06-30 | 太洋ヒロセ株式会社 | Structure of floor girder unit and temporary pier |
Also Published As
Publication number | Publication date |
---|---|
JP4219067B2 (en) | 2009-02-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2001115421A (en) | Construction method for temporary bridge and pier | |
JP3177157U (en) | A simple tower instrument in a high-rise bridge. | |
CN100489198C (en) | Prestressed scaffolding system | |
JP2017210840A (en) | Temporary cut-off method, temporary cut-off structure | |
JP6681148B2 (en) | Bridge construction method, pillars and guide means used in the bridge construction method | |
JP5033726B2 (en) | Formwork support and horizontal force processing member for formwork support | |
JP2017210865A (en) | Temporary cut-off method, temporary cut-off structure, supporting, supporting unit | |
CN108999394B (en) | Construction process of floor type scaffold rotary cantilever type scaffold | |
JP2019131978A (en) | Bridge construction method | |
JP4279189B2 (en) | Temporary strut and its construction method | |
KR100642326B1 (en) | A temporary apparatus for constructing girder by top-down style construction method | |
CN111270685A (en) | Recyclable support truss, foundation pit support system and subway station construction method | |
CN115478710A (en) | High-rise building roof cantilever structure dismantling construction method | |
CN212316934U (en) | Supporting member and foundation pit supporting system | |
JP4516235B2 (en) | Construction members and construction methods for floating structures | |
CN114458050B (en) | Cast house roof protective dismantling method | |
JPH09296601A (en) | Suspended scaffolding and construction method thereof | |
CN212316936U (en) | Recycled support truss and foundation pit supporting system | |
JP2003034939A (en) | Underground inverted construction method | |
CN218813130U (en) | Landing stage board detachable foundation ditch landing stage structure | |
CN114775690B (en) | Construction method of temporary bearing device for roof by cover-excavation method | |
CN216339062U (en) | Auxiliary assembly for mounting bridge diaphragm beam template | |
JP3029324B2 (en) | Temporary enclosures and foundations for temporary enclosures | |
CN219491717U (en) | Roof truss overhanging steel platform formwork device | |
CN216765554U (en) | Connecting structure of bridge tower and bearing platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060620 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20080729 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080812 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20081006 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20081104 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20081111 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111121 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111121 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121121 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121121 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131121 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |