JP2001040675A - Foundation structure for building - Google Patents

Foundation structure for building

Info

Publication number
JP2001040675A
JP2001040675A JP11218767A JP21876799A JP2001040675A JP 2001040675 A JP2001040675 A JP 2001040675A JP 11218767 A JP11218767 A JP 11218767A JP 21876799 A JP21876799 A JP 21876799A JP 2001040675 A JP2001040675 A JP 2001040675A
Authority
JP
Japan
Prior art keywords
foundation
underground beam
concrete
anchor
anchor frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11218767A
Other languages
Japanese (ja)
Other versions
JP3731394B2 (en
Inventor
Shinichiro Kato
真一郎 加藤
Junichi Tobimatsu
淳一 飛松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Sumitomo Metal Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Industries Ltd filed Critical Sumitomo Metal Industries Ltd
Priority to JP21876799A priority Critical patent/JP3731394B2/en
Publication of JP2001040675A publication Critical patent/JP2001040675A/en
Application granted granted Critical
Publication of JP3731394B2 publication Critical patent/JP3731394B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To shorten the term of works, save labor in construction work, improve work accuracy and also reduce cross section of foundation. SOLUTION: An underground beam 4 made of shape steel having a plurality of studs with heads 12 is installed at the bottom of continuous gutter in ridge direction. A stud with head 12 is projected out at the bottom surface of the underground beam. A plurality of side panels 5a are installed as the form of foundation at both the side of underground beam 4. Foundation concrete is poured surrounding the underground beam 4 between the side panel 5a.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、低層建物の基礎
構造に関し、主に倉庫、スーパー、工場、体育館などの
建物の基礎として利用されるものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a foundation structure of a low-rise building, and is mainly used as a foundation of a warehouse, a supermarket, a factory, a gymnasium and the like.

【0002】[0002]

【従来の技術】一般に建物の基礎は、上部構造の応力を
地盤または基礎下に施工された割り栗石などによる地業
に伝えるもので、ほとんどの基礎が鉄筋コンクリートで
施工されている。
2. Description of the Related Art In general, the foundation of a building transmits the stress of the superstructure to the ground or the earthwork by means of split rubble stones constructed under the foundation. Most foundations are constructed of reinforced concrete.

【0003】図6は、従来の基礎の一例を示し、図にお
いて、桁行き方向に溝状に連続して根切り(掘削)され
た底の地盤上に割り栗石30、捨てコンクリート31が
順に施工され、捨てコンクリート31の上に地中ばり3
2が鉄筋コンクリートによって施工されている。
[0003] Fig. 6 shows an example of a conventional foundation. In the figure, a split stone 30 and a discarded concrete 31 are constructed in this order on the ground at the bottom which is continuously cut and excavated in a groove shape in the girder direction. And the underground beam 3 on the discarded concrete 31
2 is constructed of reinforced concrete.

【0004】また、柱33が建て付けられている位置の
直下にフーチング34が地中ばり32と一体に鉄筋コン
クリートで施工されている。
A footing 34 is constructed of reinforced concrete integrally with the underground beam 32 immediately below the position where the column 33 is built.

【0005】[0005]

【発明が解決しようとする課題】しかし、鉄筋コンクリ
ートによる地中ばりの施工は、フーチング34を有する
等の理由により、深く、しかも広めに根切りをおこなう
必要があるため、掘削土が大量に排出される等の課題が
あった。
However, the construction of an underground beam using reinforced concrete requires deep and wide excavation because of the footing 34 and the like, so that a large amount of excavated soil is discharged. And other issues.

【0006】また、フーチング34を含む基礎全体の断
面形状が複雑になるため、型枠の加工、組み立て、さら
には鉄筋の加工、配筋などの基礎工事に多くの手間がか
かり、工期の長期化が免れないだけでなく、施工が繁雑
化して施工精度が落ちる等の課題があった。
In addition, since the cross-sectional shape of the entire foundation including the footing 34 becomes complicated, much work is required for processing and assembling the formwork, as well as for the foundation work such as the processing of the reinforcing bar and the arrangement of the reinforcing bars, and the construction period is prolonged. In addition to this, there is a problem that the construction is complicated and the construction accuracy is reduced.

【0007】また、フーチング34間にスパン(はり
間)方向に連続する地中ばりが配置されない場合、スパ
ン方向に作用する水平外力によってフーチング34に大
きなせん断力と曲げモーメントが生じることから、これ
に備えてフーチング34の底面積を相当大きくする必要
がある等の課題もあった。
If an underground beam continuous in the span (between beams) direction is not arranged between the footings 34, a large shear force and a bending moment are generated in the footings 34 due to a horizontal external force acting in the span direction. In addition, there is also a problem that the bottom area of the footing 34 needs to be considerably increased.

【0008】この発明は、以上の課題を解決するために
なされたもので、工期の短縮化、施工の省力化、施工精
度の向上、さらに基礎断面の低減などを可能にした建物
の基礎構造を提供することを課題とする。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and provides a basic structure of a building capable of shortening a construction period, saving labor of construction, improving construction accuracy, and further reducing a foundation section. The task is to provide.

【0009】[0009]

【課題を解決するための手段】以上の課題を解決するた
めの手段として、この発明に係る建物の基礎構造は、請
求項1として、地中ばりとして形鋼を設置し、この地中
ばりの下面にシアコネクターを設ける。
According to a first aspect of the present invention, there is provided a foundation structure for a building according to the present invention, in which a section steel is installed as an underground beam. A shear connector is provided on the lower surface.

【0010】請求項2として、請求項1の建物の基礎構
造において、桁行き方向に間隔をおいてアンカーフレー
ムを設ける。請求項3として、請求項1または2の建物
の基礎構造において、地中ばりおよび/またはアンカー
フレームの上面の、柱を設置する位置の近傍にシアコネ
クターを設ける。
According to a second aspect of the present invention, in the foundation structure of the building according to the first aspect, anchor frames are provided at intervals in the girder direction. According to a third aspect, in the foundation structure of the building according to the first or second aspect, a shear connector is provided on the upper surface of the underground beam and / or the anchor frame near the position where the pillar is installed.

【0011】請求項4として、請求項1ないし3の建物
の基礎構造において、基礎型枠として、上部に腰パネル
を積層可能な側パネルを用いる。
According to a fourth aspect of the present invention, in the foundation structure of a building according to the first to third aspects, a side panel on which a waist panel can be laminated is used as a foundation formwork.

【0012】[0012]

【発明の実施の形態】図1と図2は、この発明に係る建
物の基礎構造の一例を示し、図において桁行き方向に連
続する根切りの底の地盤上に割り栗石1が敷き詰めら
れ、その上に墨出し等をおこなうための前処理として捨
てコンクリート2が所定の厚さに打設されている。
1 and 2 show an example of a foundation structure of a building according to the present invention. In the figures, split stones 1 are spread on the ground at the bottom of a root cutting continuous in a girder direction. On top of that, a waste concrete 2 is cast to a predetermined thickness as a pretreatment for performing ink removal or the like.

【0013】また、捨てコンクリート2の上に複数のア
ンカーフレーム3と地中ばり4がそれぞれ設置され、そ
の両側に側パネル5a,5bがそれぞれ設置されてい
る。さらに、両側の側パネル5a,5b間に基礎コンク
リート6が打設され、基礎コンクリート6内にアンカー
フレーム3と地中ばり4が埋め込まれている。こうし
て、桁行き方向に連続する断面略矩形状の基礎7が形成
されている。
Further, a plurality of anchor frames 3 and underground beams 4 are installed on the discarded concrete 2, and side panels 5a and 5b are installed on both sides thereof. Further, the foundation concrete 6 is cast between the side panels 5a and 5b on both sides, and the anchor frame 3 and the underground beam 4 are embedded in the foundation concrete 6. In this way, a base 7 having a substantially rectangular cross section continuous in the girder direction is formed.

【0014】また、基礎7の上に鉄骨の柱8が建て付け
られ、かつ屋外側の側パネル5aの上に腰パネル9が設
置されている。さらに、基礎7の上に床部分から連続し
て土間コンクリート10が打設されている。
A steel column 8 is erected on the foundation 7 and a waist panel 9 is installed on the outdoor side panel 5a. Further, a concrete slab 10 is cast on the foundation 7 continuously from the floor.

【0015】アンカーフレーム3は、捨てコンクリート
2の上に材軸方向(長手方向)をスパン(はり間)方向
と一致させ、かつ複数のレベル調整体11を介して桁行
き方向に所定間隔をおいて設置されている。
The anchor frame 3 is arranged on the discarded concrete 2 so that the axial direction (longitudinal direction) of the anchor frame 3 matches the span (between beams) direction and a predetermined interval in the girder direction via a plurality of level adjusters 11. It is installed.

【0016】地中ばり4は捨てコンクリート2の上の各
アンカーフレーム3,3間に、材軸方向を桁行き方向と
一致させて架け渡され、その両端はアンカーフレーム3
の側部に接合プレートと接合ボルト等でそれぞれ接合さ
れている。
The underground beam 4 is bridged between the anchor frames 3 and 3 on the discarded concrete 2 in such a manner that the axial direction of the beam coincides with the girder direction, and both ends thereof are anchor frames 3.
Are joined to each other by joining plates and joining bolts.

【0017】なお、地中ばり4はアンカーフレームを用
いず、例えば図3と図4に図示するように連続して設置
されていてもよい。アンカーフレーム3と地中ばり4は
ともにH形鋼などの形鋼で形成され、各地中ばり4の下
面にシアコネクターとして複数の頭付きスタッド12が
桁行き方向に所定間隔に突設され、また地中ばり4およ
び/またはアンカーフレーム3の上面にもシアコネクタ
ーとして複数の頭付きスタッド13が突設されている。
The underground beam 4 does not use an anchor frame, but may be installed continuously as shown in FIGS. 3 and 4, for example. The anchor frame 3 and the underground beam 4 are both formed of a shape steel such as an H-beam, and a plurality of headed studs 12 are provided as sheer connectors on the lower surface of the underground beam 4 at predetermined intervals in the girder direction. A plurality of headed studs 13 project from the underground beam 4 and / or the anchor frame 3 as sheer connectors.

【0018】特に、頭付きスタッド12は地中ばり4の
下面に一列ないし複数列に突設されている。このよう
に、地中ばり4の下面に頭付きスタッド12が突設され
ていることで、基礎7は地中ばり4と基礎コンクリート
6とから合成構造をなし、支持地盤からの地反力による
曲げモーメントに対して合成ばりとして機能するので、
基礎の深さを浅くすることができて、掘削土量を低減す
ることができる。
In particular, the headed studs 12 project from the undersurface of the underground beam 4 in one or more rows. As described above, since the studs 12 with the head project from the undersurface of the underground beam 4, the foundation 7 forms a composite structure from the underground beam 4 and the foundation concrete 6, and is formed by the ground reaction force from the supporting ground. Since it functions as a composite beam against the bending moment,
The depth of the foundation can be reduced, and the amount of excavated soil can be reduced.

【0019】また、地中ばり4および/またはアンカー
フレーム3の上面に頭付きスタッド13が突設されてい
ることで、基礎7と土間コンクリート10が一体構造を
なし、柱8の柱脚に作用する水平力を土間コンクリート
10に分担させることができる。また、これにより基礎
7に作用する曲げモーメントを低減できるため、基礎7
の基礎幅を低減できる。
Further, since the studs 13 with heads are protrudingly provided on the upper surface of the underground beam 4 and / or the anchor frame 3, the foundation 7 and the slab concrete 10 form an integral structure and act on the column base of the column 8. The horizontal force to be applied can be shared by the soil concrete 10. Further, since the bending moment acting on the foundation 7 can be reduced by this, the foundation 7
Base width can be reduced.

【0020】なお、シアコネクターとしては、鋼板のよ
うに連続した板状体を用いてもよいし、突起物を間隔を
おいて設けてもよい。また、地中ばり4やアンカーフレ
ーム3の表面に凹凸が形成されていてもよく、地中ばり
4と基礎コンクリート6との付着力、地中ばり4および
/またはアンカーフレーム3と土間コンクリート10と
の付着力が十分に得られる構造になっていればよい。ま
た、土間コンクリート10にも必要に応じて土間補強筋
が配筋されている。
As the shear connector, a continuous plate-like body such as a steel plate may be used, or projections may be provided at intervals. In addition, irregularities may be formed on the surface of the underground beam 4 and the anchor frame 3, and the adhesion between the underground beam 4 and the foundation concrete 6, the underground beam 4 and / or the anchor frame 3 and the interstitial concrete 10. What is necessary is just to be the structure which can obtain sufficient adhesive force. The soil concrete 10 is also provided with soil reinforcement as necessary.

【0021】地中ばり4とアンカーフレーム3の上面に
シアコネクターを設ける位置は、特に制限されないが、
コンクリートがシアコネクターの周りに十分に廻るよう
に柱8から50mm以上離しておくのが好ましく、曲げ
モーメントを低減する効果を十分に発揮するためには柱
8から500mm以内とするのがよい。
The position where the shear connector is provided on the upper surface of the underground beam 4 and the anchor frame 3 is not particularly limited.
It is preferable to keep the concrete at a distance of 50 mm or more from the column 8 so that the concrete sufficiently turns around the shear connector, and it is preferable that the concrete be within 500 mm from the column 8 in order to sufficiently exhibit the effect of reducing the bending moment.

【0022】また、地中ばり4とアンカーフレーム3の
上面に設けるシアコネクターも下面に設けるものと同
様、頭付きスタッドや鋼板などを用いることができる。
シアコネクターとして鋼板などの板状体を利用する場合
には、その長手方向は桁行き方向と垂直であっても平行
であってもよく、これらを組み合わせた平面視L字型や
平面視十字型のものであってもよい。
The shear connector provided on the upper surface of the underground beam 4 and the anchor frame 3 may be a stud with a head, a steel plate or the like, similarly to the connector provided on the lower surface.
When a plate-like body such as a steel plate is used as the shear connector, its longitudinal direction may be perpendicular or parallel to the girder direction. May be used.

【0023】さらに、アンカーフレーム3を設ける場合
には、その下面にもシアコネクターとして頭付きスタッ
ド12が突設されていてもよい。レベル調整体11は固
定金具11a、可動金具11bおよびレベル調整ボルト
11cなどで構成され、地中ばり4を形成する形鋼の端
部に設置されてる。
Further, when the anchor frame 3 is provided, a stud 12 with a head may be protruded from the lower surface thereof as a shear connector. The level adjusting body 11 is composed of a fixing metal 11a, a movable metal 11b, a level adjusting bolt 11c, and the like, and is installed at an end of a section steel forming the underground beam 4.

【0024】また、アンカーフレーム3を設ける場合に
は、各アンカーフレーム3の両端側にそれぞれ設置され
ている。固定金具11aは捨てコンクリート2の上にア
ンカーボルト14で固定され、また可動金具11bは固
定金具11aの側部に固定ボルト15で固定され、さら
に可動金具11bは地中ばり4またはアンカーフレーム
3の端部にボルト等で連結されている。
When the anchor frames 3 are provided, they are provided on both ends of each anchor frame 3. The fixing metal 11a is fixed on the discarded concrete 2 by the anchor bolt 14, the movable metal 11b is fixed to the side of the fixing metal 11a by the fixing bolt 15, and the movable metal 11b is fixed to the underground beam 4 or the anchor frame 3. It is connected to the end by a bolt or the like.

【0025】また、固定金具11aと可動金具11bは
ともに溝形鋼やL形鋼などの形鋼で形成されている。レ
ベル調整ボルト11cは固定金具11aの近くに立設さ
れ、レベル調整ボルト11cによって可動金具10b
は、固定金具11aに固定される前、高さ調整と水平出
しがなされている。
Further, both the fixed metal member 11a and the movable metal member 11b are formed of a section steel such as a channel steel or an L-section steel. The level adjusting bolt 11c is erected near the fixing bracket 11a, and is movable by the level adjusting bolt 11c.
Before being fixed to the fixture 11a, height adjustment and leveling are performed.

【0026】このようにして、高さ調整と水平出しが可
能なことにより、アンカーフレーム3と地中ばり4の取
付精度を高めることができ、これにより施工精度の向上
が図れる。
As described above, since the height can be adjusted and the leveling can be performed, the mounting accuracy of the anchor frame 3 and the underground beam 4 can be increased, and the construction accuracy can be improved.

【0027】レベル調整ボルト11cには、軸方向(上
下方向)に移動するレベル調整ナット11dが螺合され
ており、レベル調整ナット11dを回して可動金具11
bを自由に上げ下げできるようになっている。
A level adjusting nut 11d that moves in the axial direction (vertical direction) is screwed into the level adjusting bolt 11c, and the movable metal fitting 11 is turned by turning the level adjusting nut 11d.
b can be raised and lowered freely.

【0028】なお、レベル調整ボルト11cはレベル調
整を終了した後、レベル調整ボルト11dとともに撤去
され、繰り返し利用できるようにしてもよい。側パネル
5a,5bは、基礎7の型枠を兼ねるとともに基礎7の
表面材として放置されるもので、例えばFRC板などの
乾式パネルで形成されている。
After completing the level adjustment, the level adjustment bolt 11c may be removed together with the level adjustment bolt 11d so that the level adjustment bolt 11c can be used repeatedly. The side panels 5a and 5b also serve as the formwork of the foundation 7 and are left as a surface material of the foundation 7, and are formed of, for example, a dry panel such as an FRC plate.

【0029】また、側パネル5aと5bは捨てコンクリ
ート2の上に取り付けられた、真上に開口する断面略溝
状のランナー16に下端部を建て込んで固定されてい
る。なお、ランナー16は軽量溝形鋼や2本の軽量山形
鋼などで形成されている。
The side panels 5a and 5b are fixed to the runner 16 mounted on the discarded concrete 2 and having a substantially groove-shaped cross-section opening right above. The runner 16 is formed of a lightweight channel steel or two lightweight angle steels.

【0030】側パネル5aおよび5bとしては、上部に
腰パネル9を積層可能な形状のものを用いるのがよく、
例えば側パネルの上端部と腰パネル9の下端部とを嵌合
しうるような凹凸形状にしておくとよい。
As the side panels 5a and 5b, those having a shape in which the waist panel 9 can be laminated on the upper part are preferably used.
For example, it is preferable to form an uneven shape such that the upper end of the side panel and the lower end of the waist panel 9 can be fitted.

【0031】柱8は地中ばり4またはアンカーフレーム
3の上に柱脚金具17を介してそれぞれ立設され、各柱
8の下端部は柱脚金具17に数本の固定ボルト19で固
定されている。
The columns 8 are respectively erected on the underground beam 4 or the anchor frame 3 via column bases 17, and the lower ends of the columns 8 are fixed to the column bases 17 with several fixing bolts 19. ing.

【0032】また、柱脚金具17は地中ばり4またはア
ンカーフレーム3の上にアンカーボルト18で固定され
ている。アンカーボルト18は地中ばり4またはアンカ
ーフレーム3を下方に貫通し、下側で桁行き方向に折り
曲げられ、かつ桁行き方向に所定長さ延長されているこ
とで、充分な定着長さが得られている。
The column base bracket 17 is fixed on the underground beam 4 or the anchor frame 3 with anchor bolts 18. The anchor bolt 18 penetrates the underground beam 4 or the anchor frame 3 downward, is bent in the girder direction on the lower side, and is extended a predetermined length in the girder direction, so that a sufficient anchoring length can be obtained. Have been.

【0033】なお、アンカーボルト18は、地中ばり4
またはアンカーフレーム3の下側でスパン方向(地中ば
りの軸直角方向)に折り曲げられ、かつスパン方向に所
定の長さ延長されていてもよい。また、アンカーボルト
18には高力ボルトまたは中ボルト等が使用されてい
る。
The anchor bolt 18 is used for the underground beam 4
Alternatively, it may be bent in the span direction (the direction perpendicular to the axis of the underground beam) below the anchor frame 3 and extended a predetermined length in the span direction. In addition, a high-strength bolt or a middle bolt is used for the anchor bolt 18.

【0034】図3と図4は、同じくこの発明に係る建物
の基礎構造の一例を示し、特に前述するようなアンカー
フレームがなく、捨てコンクリート2の上に地中ばり4
だけが設置されている。
FIGS. 3 and 4 show an example of the foundation structure of a building according to the present invention. In particular, there is no anchor frame as described above, and the underground beam 4
Only have been installed.

【0035】地中ばり4は捨てコンクリート2の上に材
軸方向を桁行き方向と一致させ、かつ複数のレベル調整
体11を介して複数連ねて設置され、その両端は接合プ
レート20と接合ボルト21で互いに接合されている。
The underground beam 4 is disposed on the discarded concrete 2 in such a manner that the axial direction of the beam coincides with the direction of the girder, and a plurality of the underground beams are connected via a plurality of level adjusters 11. At 21 they are joined together.

【0036】そして、レベル調整体11によって地中ば
り4の高さ調整と水平出しを行うことで、地中ばり4の
取付精度を高めることができ、これにより施工精度の向
上が図れるようになっている。
By adjusting the height of the underground beam 4 and leveling it out with the level adjusting body 11, the mounting accuracy of the underground beam 4 can be increased, and the construction accuracy can be improved. ing.

【0037】また、柱8はアンカーフレームの上にでは
なく、地中ばり4の上に柱脚金具17を介して立設され
ている。各柱8の下端部は柱脚金具17に複数の固定ボ
ルト19で固定されている。柱脚金具17は地中ばり4
の上に複数のアンカーボルト22で固定されている。
The column 8 is erected not on the anchor frame but on the underground beam 4 via the column base bracket 17. The lower end of each column 8 is fixed to the column base 17 with a plurality of fixing bolts 19. Pillar bracket 17 is underground beam 4
Is fixed on the base with a plurality of anchor bolts 22.

【0038】アンカーボルト22は地中ばり4を下方に
貫通し、下端部に取り付けられている定着プレート23
によって互いに連結され、かつ基礎コンクリート6内に
定着されている。また、アンカーボルト22は、その上
端部に螺合されているアンカーナット24を後から再度
締め付けられるように、いわゆるアンボンド構造になっ
ている。
An anchor bolt 22 penetrates the underground beam 4 downward, and a fixing plate 23 attached to a lower end portion.
And are anchored in the foundation concrete 6. The anchor bolt 22 has a so-called unbonded structure so that the anchor nut 24 screwed to the upper end portion can be tightened again later.

【0039】また、基礎型枠を兼ねる一方の側パネル5
aは、捨てコンクリート2の上に凹溝を形成するように
取り付けられた、例えば軽量山形鋼などからなる2本の
ランナー25,25間に下端部を建て込んで固定されて
いる。
Further, one side panel 5 also serving as a base formwork
a is fixed with its lower end erected between two runners 25, 25 made of, for example, lightweight angle irons, which are mounted on the discarded concrete 2 so as to form concave grooves.

【0040】さらに、ランナー25,25間の捨てコン
クリート2の上には、レベル調整ボルト26が突設さ
れ、このレベル調整ボルト26を回して上げ下げするこ
とで、側パネル5aのレベル調整と水平出しがおこなえ
るよにうなっている。その他の構成は、図1と図2に図
示するものと略同じである。
Further, a level adjusting bolt 26 is protrudingly provided on the waste concrete 2 between the runners 25, 25, and the level adjusting bolt 26 is turned up and down to adjust the level of the side panel 5a and level out. Howl can be done. Other configurations are substantially the same as those shown in FIGS. 1 and 2.

【0041】このような構成において、次に施工方法を
簡単に説明する(図5参照)。 最初に、桁行き方向に溝状に連続する根切りAを行
う。そして、根切り底の地盤上に割り栗石1を入念に転
圧しながら敷きつめ、かつその上に捨てコンクリート2
を所定の厚さに打設する。 次に、捨てコンクリート2の上に墨出し位置に従っ
てレベル調整体11とランナー16をそれぞれ取り付
け、また基礎補強筋27として丸鋼または異形鉄筋を必
要量、配筋する。 次に、レベル調整体11,11間にアンカーフレー
ム3をそれぞれ架け渡し、可動金具11bにそれぞれ固
定する。
In such a configuration, a construction method will be briefly described next (see FIG. 5). First, root cutting A that is continuous in a groove shape in the girder direction is performed. Then, crushed stone 1 was carefully laid on the ground at the bottom of the root cut while being compacted, and concrete 2 was discarded on top of it.
Is cast to a predetermined thickness. Next, the level adjuster 11 and the runner 16 are respectively mounted on the discarded concrete 2 in accordance with the marking position, and a necessary amount of round steel or deformed reinforcing bar is laid as the basic reinforcing bar 27. Next, the anchor frames 3 are respectively bridged between the level adjusters 11 and 11 and fixed to the movable fittings 11b.

【0042】また、レベル調整体11のレベル調整ボル
ト11cとレベル調整ナット11dでアンカーフレーム
3の水平出しとレベル調整を行う。そして、固定ボルト
15を締め付けて可動金具11bを固定金具11aに固
定する。 次に、各アンカーフレーム3に柱脚金具17とアン
カーボルト18をそれぞれ取り付ける。なお、柱脚金具
17とアンカーボルト18はアンカーフレーム3に予め
取り付けておいてもよい。 次に、アンカーフレーム3,3間に地中ばり4をそ
れぞれ架け渡し、両端をアンカーフレーム3に接合プレ
ートと接合ボルトでそれぞれ接合する。
The level adjustment bolt 11c and the level adjustment nut 11d of the level adjustment body 11 level the anchor frame 3 and adjust the level. Then, the movable fitting 11b is fixed to the fixing fitting 11a by tightening the fixing bolt 15. Next, the column base bracket 17 and the anchor bolt 18 are attached to each anchor frame 3 respectively. The column base 17 and the anchor bolt 18 may be attached to the anchor frame 3 in advance. Next, the underground beam 4 is bridged between the anchor frames 3 and 3, and both ends are joined to the anchor frame 3 with joining plates and joining bolts.

【0043】また、アンカーフレーム3の上端に頭付き
スタッド13、地中ばり4の下端に頭付きスタッド12
をそれぞれ突設する。なお、頭付きスタッド12と13
はあらかじめ取りつけておくのが望ましい。 次に、アンカーフレーム3と地中ばり4の両側に、
基礎型枠を兼ねて側パネル5をそれぞれ建て付ける。そ
の際、側パネル5の下端はランナー16に差し込んで固
定する。 次に、両側の側パネル5aと5b間に基礎コンクリ
ート6を打設する。また側パネル5aと5bの外側を埋
戻土28でそれぞれ埋め戻す。なお、基礎コンクリート
6の打設前に埋戻土28を埋戻してもよい。
A stud 13 with a head is provided at the upper end of the anchor frame 3, and a stud 12 is provided at a lower end of the underground beam 4.
Respectively. Note that studs 12 and 13 with heads
It is desirable to install in advance. Next, on both sides of the anchor frame 3 and the underground beam 4,
Each of the side panels 5 is also erected as a base formwork. At this time, the lower end of the side panel 5 is inserted into the runner 16 and fixed. Next, the foundation concrete 6 is cast between the side panels 5a and 5b on both sides. The outside of the side panels 5a and 5b is backfilled with backfill soil 28, respectively. The backfill soil 28 may be buried before the foundation concrete 6 is cast.

【0044】こうして、側パネル5aと5b間に基礎コ
ンクリート6を打設することで、アンカーフレーム3と
地中ばり4は基礎コンクリート6内に埋めこまれ、これ
により桁行き方向に連続する断面略矩形状の布基礎7が
形成される。 次に、アンカーフレーム3の上に柱8を、柱脚金具
17に下端部を固定ボルト19で固定してそれぞれ建て
付ける。
By laying the foundation concrete 6 between the side panels 5a and 5b in this manner, the anchor frame 3 and the underground beam 4 are embedded in the foundation concrete 6, whereby the cross-section substantially continuous in the girder direction. A rectangular cloth base 7 is formed. Next, the column 8 is mounted on the anchor frame 3 and the lower end is fixed to the column base bracket 17 with fixing bolts 19, respectively.

【0045】また、側パネル5aの上に腰パネル9を設
置する。その際、腰パネル9を布基礎7の側パネル5と
面一に取り付けることができ、施工性がきわめてよい。 次に、基礎7の上に土間部分から連続させて土間コ
ンクリート10を打設する。
The waist panel 9 is set on the side panel 5a. At this time, the waist panel 9 can be attached flush with the side panel 5 of the cloth foundation 7, and the workability is extremely good. Next, the soil concrete 10 is cast on the foundation 7 continuously from the soil portion.

【0046】なお、柱8を建て付ける前に土間コンクリ
ート10を先に打設し、その後に柱8を建て付けるよう
にしてもよいが、その場合には、柱脚金具17が土間コ
ンクリート10に埋まらないように、柱脚金具17の周
囲にコンクリートを堰き止める枠体(図省略)を矩形状
に設けて、いわゆる箱抜きをする。
In addition, before the column 8 is erected, the slab concrete 10 may be cast first, and then the column 8 may be erected. In this case, the column base bracket 17 is attached to the slab concrete 10. A frame (not shown) for blocking concrete is provided around the column base bracket 17 in a rectangular shape so as not to be buried, and a so-called box is removed.

【0047】[0047]

【発明の効果】この発明に係る建物の基礎構造は以上説
明した通りであり、桁行き方向に連続する根切りの底
に、シアコネクターを有する形鋼からなる地中ばりが設
置され、かつその周囲に基礎コンクリートが打設されて
いることにより、形鋼とコンクリートからなる合成構造
をなしているので、断面を小さくすることができ、掘削
土量を少なくすることができる等の効果がある。
The foundation structure of a building according to the present invention is as described above, and an underground beam made of a section steel having a shear connector is installed at the bottom of a root cutting continuous in a girder direction. Since the base concrete is cast in the periphery, the composite structure composed of the shape steel and the concrete is formed, so that the cross section can be reduced and the amount of excavated soil can be reduced.

【0048】また、基礎が形鋼とコンクリートから合成
構造をなし、また地中ばりまたはアンカーフレームの上
面にシアコネクターが突設されていることで、床部分か
ら基礎の上まで連続して打設された基礎と土間コンクリ
ートとが一体構造をなしているため、柱脚部に作用する
水平力を土間コンクリートに分担させることができ、か
つこれにより基礎に作用する曲げモーメントも小さくで
きるため、基礎の幅を低減できて基礎断面を小さくする
ことができる。
Further, the foundation is made of a composite structure of shaped steel and concrete, and the shear connector is protruded from the underground beam or the upper surface of the anchor frame, so that the foundation is continuously cast from the floor to the top of the foundation. Since the foundation and soil concrete have an integral structure, the horizontal force acting on the column base can be shared by the soil concrete, and the bending moment acting on the foundation can be reduced. The width can be reduced, and the basic section can be reduced.

【0049】また、レベル調整体によってアンカーフレ
ームの高さ調整と水平出しが可能なことにより、アンカ
ーフレームと地中ばりの取付精度を高めることができ、
これにより施工精度の向上が図れる。
Further, since the height of the anchor frame can be adjusted and leveled out by the level adjuster, the mounting accuracy of the anchor frame and the underground beam can be improved.
Thereby, improvement of construction accuracy can be achieved.

【0050】さらに、アンカーフレームと地中ばりの両
側に、基礎型枠として設置されている側パネルを基礎の
表面材として放置することにより、鉄筋の加工、配筋作
業とともに型枠の解体・撤去作業も省略でき、施工の大
幅な省力化、工期の大幅な短縮化が図れる。
Further, by leaving the side panels installed as the foundation formwork on both sides of the anchor frame and the underground beam as the surface material of the foundation, the work of rebars, the rebar arrangement work, and the formwork disassembly / removal. The work can also be omitted, and the labor can be saved significantly and the construction period can be significantly shortened.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明に係る基礎構造の一例を示し、(a)
はその縦断面図、(b)は(a)におけるイ部拡大図で
ある。
FIG. 1 shows an example of a basic structure according to the present invention, wherein (a)
FIG. 2 is a longitudinal sectional view, and FIG. 2B is an enlarged view of a portion A in FIG.

【図2】この発明に係る基礎構造の一例を示す一部斜視
図である。
FIG. 2 is a partial perspective view showing an example of a basic structure according to the present invention.

【図3】この発明に係る基礎構造の一例を示す縦断面図
である。
FIG. 3 is a longitudinal sectional view showing an example of a basic structure according to the present invention.

【図4】この発明に係る基礎構造の一例を示す縦断面図
である。
FIG. 4 is a longitudinal sectional view showing an example of a basic structure according to the present invention.

【図5】(a)〜(g)は施工方法の一例を示す断面図
である。
5A to 5G are cross-sectional views illustrating an example of a construction method.

【図6】従来の基礎の一例を示す一部斜視図である。FIG. 6 is a partial perspective view showing an example of a conventional foundation.

【符号の説明】[Explanation of symbols]

1 割り栗 2 捨てコンクリート 3 アンカーフレーム 4 地中ばり 5a 側パネル 5b 側パネル 6 基礎コンクリート 7 基礎 8 柱 9 腰パネル 10 土間コンクリート 11 レベル調整体 11a 固定金具 11b 可動金具 11c レベル調整ボルト 11d レベル調整ナット 12 頭付きスタッド(シアコネクター) 13 頭付きスタッド(シアコネクター) 14 アンカーボルト 15 固定ボルト 16 ランナー 17 柱脚金具 18 アンカーボルト 19 固定ボルト 20 接合プレート 21 接合ボルト 22 アンカーボルト 23 定着プレート 24 アンカーナット 25 ランナー 26 レベル調整ボルト 27 基礎補強筋 28 埋戻土 DESCRIPTION OF SYMBOLS 1 Split chestnut 2 Discarded concrete 3 Anchor frame 4 Underground beam 5a Side panel 5b side panel 6 Foundation concrete 7 Foundation 8 Column 9 Waist panel 10 Soil concrete 11 Level adjuster 11a Fixing bracket 11b Movable bracket 11c Level adjusting bolt 11d Level adjusting nut 12 Stud with Head (Shear Connector) 13 Stud with Shear (Shear Connector) 14 Anchor Bolt 15 Fixing Bolt 16 Runner 17 Column Base 18 Anchor Bolt 19 Fixing Bolt 20 Joining Plate 21 Joining Bolt 22 Anchor Bolt 23 Fixing Plate 24 Anchor Nut 25 Runner 26 Level adjustment bolt 27 Foundation reinforcement 28 Backfill soil

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 地中ばりとして形鋼が用いられた基礎で
あって、この地中ばりの下面にシアコネクターが設けら
れていることを特徴とする建物の基礎構造。
1. A foundation for a building, wherein a section steel is used as an underground beam, and a shear connector is provided on a lower surface of the underground beam.
【請求項2】 桁行き方向に間隔をおいてアンカーフレ
ームが設けられていることを特徴とする請求項1記載の
建物の基礎構造。
2. The foundation structure of a building according to claim 1, wherein anchor frames are provided at intervals in the girder direction.
【請求項3】 地中ばりおよび/またはアンカーフレー
ムの上面であって、柱を設置する位置の近傍にシアコネ
クターが設けられていることを特徴とする請求項1また
は2記載の建物の基礎構造。
3. The foundation structure of a building according to claim 1, wherein a shear connector is provided on an undersurface beam and / or an upper surface of the anchor frame near a position where the pillar is installed. .
【請求項4】 基礎型枠として、上部に腰パネルを積層
可能な側パネルが用いられていることを特徴とする請求
項1ないし3記載の建物の基礎構造。
4. The foundation structure of a building according to claim 1, wherein a side panel on which a waist panel can be stacked is used as the foundation formwork.
JP21876799A 1999-08-02 1999-08-02 Building basic structure Expired - Lifetime JP3731394B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21876799A JP3731394B2 (en) 1999-08-02 1999-08-02 Building basic structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21876799A JP3731394B2 (en) 1999-08-02 1999-08-02 Building basic structure

Publications (2)

Publication Number Publication Date
JP2001040675A true JP2001040675A (en) 2001-02-13
JP3731394B2 JP3731394B2 (en) 2006-01-05

Family

ID=16725086

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21876799A Expired - Lifetime JP3731394B2 (en) 1999-08-02 1999-08-02 Building basic structure

Country Status (1)

Country Link
JP (1) JP3731394B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014231702A (en) * 2013-05-29 2014-12-11 株式会社住金システム建築 Column base fixing structure of steel frame column
KR101809064B1 (en) * 2017-07-24 2017-12-14 주식회사 아이에스중공업 Non-foundation flooring system for building
JP2019210737A (en) * 2018-06-06 2019-12-12 積水ハウス株式会社 Reinforced fixed body and foundation structure of building
JP2019210736A (en) * 2018-06-06 2019-12-12 積水ハウス株式会社 Foundation structure of building and method for constructing the same
JP2021055409A (en) * 2019-09-30 2021-04-08 大和ハウス工業株式会社 Foundation structure and method of constructing foundation
CN114086591A (en) * 2021-11-19 2022-02-25 中建七局城市投资运营管理有限公司 Assembled lamp stand basis
CN114809056A (en) * 2022-05-24 2022-07-29 中建八局南方建设有限公司 Mounting method and mounting system based on beam-slab separation

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014231702A (en) * 2013-05-29 2014-12-11 株式会社住金システム建築 Column base fixing structure of steel frame column
KR101809064B1 (en) * 2017-07-24 2017-12-14 주식회사 아이에스중공업 Non-foundation flooring system for building
JP2019210737A (en) * 2018-06-06 2019-12-12 積水ハウス株式会社 Reinforced fixed body and foundation structure of building
JP2019210736A (en) * 2018-06-06 2019-12-12 積水ハウス株式会社 Foundation structure of building and method for constructing the same
JP7124470B2 (en) 2018-06-06 2022-08-24 積水ハウス株式会社 Reinforcing bar fixtures and foundation structures of buildings
JP2021055409A (en) * 2019-09-30 2021-04-08 大和ハウス工業株式会社 Foundation structure and method of constructing foundation
CN114086591A (en) * 2021-11-19 2022-02-25 中建七局城市投资运营管理有限公司 Assembled lamp stand basis
CN114809056A (en) * 2022-05-24 2022-07-29 中建八局南方建设有限公司 Mounting method and mounting system based on beam-slab separation

Also Published As

Publication number Publication date
JP3731394B2 (en) 2006-01-05

Similar Documents

Publication Publication Date Title
US5588784A (en) Soil or rock nail wall with outer face and method of constructing the same
JP2001040675A (en) Foundation structure for building
JP2004100157A (en) Retaining wall structure and its construction method
KR102595835B1 (en) Seismic retrofit system using foundation integrated PC panel
US9951493B2 (en) Precast integral post and retaining wall and method for installing same
JP3465026B2 (en) Forming method of pressure plate type foundation
JP2002121747A (en) Semi-fixed direct foundation of steel column and pile foundation structure
JP3896032B2 (en) Construction method of precast column head and pier column head
JP2787806B2 (en) Earth retaining wall
KR101483865B1 (en) Construction Method of Underground Structure using Composite Wale
JPH1136332A (en) Underground structure and construction thereof
JPH08177059A (en) Footing block, and integrated method for constructing continuous footing employing footing block
JP3178390B2 (en) Building seismic isolation foundation
JP2517822B2 (en) Precast concrete basics
JPH09203053A (en) Precast reinforced concrete foundation structure
JP2002285562A (en) Foundation construction for building
JPH08296231A (en) Construction method for stabilizing slope, and construction method for extension in slope
JP2512254B2 (en) Structure of artificial ground and structure of house
JPS60258351A (en) Construction of concrete block wall
JPH1121916A (en) Basement made of steel and construction method thereof
JPH0988086A (en) Continuous footing by using unequal-width h-steel
JPH1018303A (en) Foundation structure for convenient building
JP2784449B2 (en) Steel reinforced concrete foundation
JPH01315525A (en) Snowslide preventing and slope stabilizing structure
JP2776620B2 (en) Basic structure of building

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050207

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050517

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050627

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050920

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051003

R150 Certificate of patent or registration of utility model

Ref document number: 3731394

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081021

Year of fee payment: 3

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081021

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091021

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101021

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111021

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121021

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131021

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

EXPY Cancellation because of completion of term