JP2001033001A - Steam supply system with set-up time calculation device - Google Patents

Steam supply system with set-up time calculation device

Info

Publication number
JP2001033001A
JP2001033001A JP11205857A JP20585799A JP2001033001A JP 2001033001 A JP2001033001 A JP 2001033001A JP 11205857 A JP11205857 A JP 11205857A JP 20585799 A JP20585799 A JP 20585799A JP 2001033001 A JP2001033001 A JP 2001033001A
Authority
JP
Japan
Prior art keywords
time
steam
boiler
warm
calculation circuit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11205857A
Other languages
Japanese (ja)
Inventor
Yasushi Tabuchi
靖 田渕
Yukiko Yokoyama
由貴子 横山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SAMSON CO Ltd
Original Assignee
SAMSON CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SAMSON CO Ltd filed Critical SAMSON CO Ltd
Priority to JP11205857A priority Critical patent/JP2001033001A/en
Publication of JP2001033001A publication Critical patent/JP2001033001A/en
Pending legal-status Critical Current

Links

Landscapes

  • Control Of Steam Boilers And Waste-Gas Boilers (AREA)

Abstract

PROBLEM TO BE SOLVED: To enable the operation of a steam boiler to start at the most appropriate timing by correctly calculating a set-up time for steam supply. SOLUTION: A steam supply system comprises a steam boiler 1, steam supply piping 2 and a controller 4, wherein the controller 4 includes a pipe warming time storage device 7 and a set-up time calculation circuit 8, and the steam supply pipe 2 connects the steam boiler 1 and use points 9 to feed steam generated in the steam boiler 1 to the use points 9. The pipe warming time storage device 7 stores therein pipe warming time that is the time required for warming the steam piping as far as the use points 9, while the set-up time calculation circuit 8 calculates time that is earlier than input time, at which the use of steam starts in the use points 9, by preparation time, which is the total of steam starting time required for generating steam in the boiler and the pipe warming time, as the start time of boiler operation.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、準備時間算出装置を設
けた蒸気供給装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a steam supply device provided with a preparation time calculation device.

【0002】[0002]

【従来の技術】蒸気を使用するプラントの場合、蒸気ボ
イラとユースポイントの間を蒸気供給配管で結んでお
き、蒸気ボイラの稼働により蒸気を発生させ、ユースポ
イントへ蒸気の供給が行われる。蒸気ボイラのコールド
スタート時、蒸気ボイラは稼働を開始しても内部の缶水
が沸騰温度に達するまでは蒸気を発生させることができ
ないため、蒸気ボイラの稼働は実際に蒸気を使用し始め
るよりも前に開始する必要がある。また、蒸気ボイラで
発生させた蒸気は蒸気供給配管を通して送られるもので
あるが、蒸気供給配管の温度が低いと蒸気の熱は蒸気供
給配管の加熱に使用され、蒸気供給配管内で蒸気の温度
が低下することとなるため、予め蒸気供給配管を加熱し
ておく暖管運転が必要となる。
2. Description of the Related Art In a plant using steam, a steam supply pipe is connected between a steam boiler and a point of use, steam is generated by operating the steam boiler, and steam is supplied to the point of use. During a cold start of the steam boiler, the steam boiler cannot start producing steam until the internal boiler reaches the boiling temperature even after the steam boiler starts operating. Need to start before. The steam generated by the steam boiler is sent through a steam supply pipe.If the temperature of the steam supply pipe is low, the heat of the steam is used to heat the steam supply pipe, and the temperature of the steam in the steam supply pipe is reduced. Therefore, it is necessary to perform a warm-up operation in which the steam supply pipe is heated in advance.

【0003】蒸気ボイラの運転スイッチを入れてから蒸
気が発生し始めるまでの起蒸時間はボイラごとにほぼ一
定であるが、暖管運転に要する時間は蒸気のユースポイ
ントごとに異なる。ボイラの操作者はユースポイントで
の蒸気使用開始時刻から、蒸気供給の準備に要する時間
分早めてボイラの運転を開始させる必要があり、ユース
ポイントが複数存在する場合は、ユースポイントごとに
ボイラの運転開始時刻を求め、その中から最も早い時刻
を選び出すという煩雑な作業が必要であった。準備時間
はボイラ操作者によって計算しているが、準備時間を正
確に算出するのは面倒なものであり、ボイラの運転開始
が早すぎるとボイラを無駄に運転させることとなり、運
転開始が遅すぎるとユースポイントでの蒸気必要時に蒸
気が間に合わなくなるという問題が発生する。
[0003] The steaming time from when the operation switch of the steam boiler is turned on until the start of generation of steam is almost constant for each boiler, but the time required for the warm tube operation differs for each use point of steam. It is necessary for the boiler operator to start the operation of the boiler earlier than the time required for preparing the steam supply from the start time of using steam at the use point, and if there are multiple use points, the boiler Complicated work of finding the operation start time and selecting the earliest time from it was necessary. The preparation time is calculated by the boiler operator, but it is troublesome to calculate the preparation time accurately, and if the operation start of the boiler is too early, the boiler is wastefully operated, and the operation start is too slow. When the steam at the use point is needed, a problem occurs that the steam cannot be made in time.

【0004】[0004]

【発明が解決しようとする課題】本発明が解決しようと
する課題は、蒸気供給のための準備時間を正確に算出
し、最適なタイミングで蒸気ボイラの運転を開始できる
ようにすることにある。
SUMMARY OF THE INVENTION It is an object of the present invention to accurately calculate a preparation time for steam supply and to start operation of a steam boiler at an optimum timing.

【0005】[0005]

【課題を解決するための手段】蒸気ボイラと、蒸気供給
配管と、制御装置を有する蒸気供給装置であって、制御
装置は、暖管運転時間記憶装置と、準備時間算出回路を
有し、蒸気供給配管は、蒸気ボイラとユースポイントを
接続し、蒸気ボイラで発生させた蒸気をユースポイント
まで送るものであり、暖管運転時間記憶装置にはユース
ポイントまでの蒸気配管部分の暖管運転に要する時間で
ある暖管運転時間を記憶させておき、準備時間算出回路
は入力されたユースポイントでの蒸気使用開始時刻か
ら、ボイラの蒸気発生に要する時間である起蒸時間と、
暖管運転時間を合計した準備時間分早い時刻をボイラ運
転開始時刻として算出する。
A steam supply device having a steam boiler, a steam supply pipe, and a control device, wherein the control device has a warm pipe operation time storage device and a preparation time calculation circuit, The supply pipe connects the steam boiler and the point of use, and sends the steam generated by the steam boiler to the point of use. The warm pipe operation time storage device is required for the warm pipe operation of the steam pipe to the point of use. The warm-up operation time, which is the time, is stored, and the preparation time calculation circuit calculates the steaming time, which is the time required for the steam generation of the boiler, from the input steam use start time at the use point,
The time earlier by the preparation time obtained by adding the warm-up operation time is calculated as the boiler operation start time.

【0006】[0006]

【発明の実施の形態】本発明の一実施例を図面を用いて
説明する。図1は本発明を実施している蒸気供給装置の
フロー図、図2はユースポイントでの蒸気使用開始時刻
とボイラ運転開始時刻の関係を示した説明図である。蒸
気ボイラ1は3カ所のユースポイント9に蒸気を供給す
るものであり、各ユースポイント9をそれぞれユースポ
イントA、ユースポイントB、ユースポイントCとす
る。蒸気ボイラ1と各ユースポイントの間は蒸気供給配
管2で接続しておき、蒸気供給配管2には途中に蒸気ヘ
ッダ5を設ける。蒸気ボイラ1で発生させた蒸気は、蒸
気供給配管2を通して一旦蒸気ヘッダ5へ送られ、蒸気
ヘッダ5から各ユースポイント9へ送られるようになっ
ており、各ユースポイントへ接続している蒸気供給配管
2にはそれぞれに蒸気供給制御弁6を設ける。蒸気ボイ
ラ1の制御は制御装置4によって行われ、蒸気ボイラ1
の各作動部は制御装置4からの信号に基づき作動する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the present invention will be described with reference to the drawings. FIG. 1 is a flow chart of a steam supply device embodying the present invention, and FIG. 2 is an explanatory diagram showing a relationship between a steam use start time at a use point and a boiler operation start time. The steam boiler 1 supplies steam to three use points 9, and the use points 9 are referred to as use points A, B, and C, respectively. The steam boiler 1 and each use point are connected by a steam supply pipe 2, and a steam header 5 is provided on the steam supply pipe 2. The steam generated in the steam boiler 1 is once sent to the steam header 5 through the steam supply pipe 2 and is sent from the steam header 5 to each use point 9, and the steam supply connected to each use point Each of the pipes 2 is provided with a steam supply control valve 6. The control of the steam boiler 1 is performed by the control device 4, and the steam boiler 1 is controlled.
Each of the operating units operates based on a signal from the control device 4.

【0007】制御装置4には準備時間算出装置3とタイ
マ装置10を設けておき、準備時間算出装置3には、暖
管運転時間記憶装置7と、準備時間算出回路8を設けて
おく。蒸気供給の必要なユースポイントに接続されてい
る蒸気供給配管2途中の蒸気供給制御弁6を開き、蒸気
ボイラで蒸気を発生させると、蒸気が蒸気供給配管2を
通ってユースポイント9へ送られる。蒸気供給配管2に
蒸気を送ることで蒸気供給配管の暖管運転が行え、暖管
運転に要する時間は、各ユースポイントごとに予め求め
て、暖管運転時間記憶装置7に記憶させておく。
The control device 4 is provided with a preparation time calculation device 3 and a timer device 10, and the preparation time calculation device 3 is provided with a warm-up operation time storage device 7 and a preparation time calculation circuit 8. When the steam supply control valve 6 in the middle of the steam supply pipe 2 connected to the use point requiring steam supply is opened and steam is generated by the steam boiler, the steam is sent to the use point 9 through the steam supply pipe 2. . By sending steam to the steam supply pipe 2, warm-up operation of the steam supply pipe can be performed, and the time required for the warm-up operation is determined in advance for each use point and stored in the warm-up operation time storage device 7.

【0008】ここでは、ユースポイントAまでの蒸気供
給配管2を暖管する暖管運転時間をtA、ユースポイン
トBまでの蒸気供給配管2の暖管運転時間をtB、ユー
スポイントCまでの蒸気供給配管2の暖管運転時間をt
Cとする。通常の場合蒸気供給配管の長さが長いほど暖
管運転時間は長くなり、各暖管運転時間はtA<tB<
tCとなっている。蒸気ボイラの運転スイッチを入れて
から蒸気が発生し始めるまでの時間である起蒸時間はど
のユースポイントに蒸気を供給する場合であっても一定
であり、起蒸時間t1は準備時間算出回路8に設定して
おく。
Here, the warm-up operation time for warming up the steam supply pipe 2 up to the use point A is tA, the warm-up operation time of the steam supply pipe 2 up to the use point B is tB, and the steam supply up to the use point C is performed. The warm-up operation time of pipe 2 is t
C. In the normal case, the longer the length of the steam supply pipe, the longer the warm-up operation time, and each warm-up operation time is tA <tB <
tC. The steaming time, which is the time from when the operation switch of the steam boiler is turned on until the steam starts to be generated, is constant regardless of the use point at which steam is supplied, and the steaming time t1 is determined by the preparation time calculating circuit 8 Set to.

【0009】複数のユースポイントにて蒸気を使用する
場合は、それぞれのユースポイントごとにボイラの運転
開始時刻を求め、その中で最も早い時刻をボイラの運転
開始時刻とする。ユースポイントAで蒸気の使用を開始
する時刻がT1、ユースポイントBで蒸気の使用を開始
する時刻がT2であって、冷態状態にある蒸気ボイラ1
を適切な時刻に運転開始させる場合について説明する。
When steam is used at a plurality of use points, the operation start time of the boiler is obtained for each of the use points, and the earliest time is determined as the operation start time of the boiler. The time at which the use of steam at the use point A is started is T1, the time at which the use of steam is started at the use point B is T2, and the steam boiler 1 is in a cold state.
The case where the operation is started at an appropriate time will be described.

【0010】準備時間算出回路8へユースポイントAの
蒸気使用開始時刻T1を入力すると、準備時間算出回路
8は暖管運転時間記憶装置7からユースポイントAの暖
管運転時間tAを読み込み、暖管運転時間tAと起蒸時
間t1を加えた準備時間(tA+t1)を求め、ユース
ポイントAで蒸気使用を開始する時刻T1より準備時間
分早い時刻T3を求める。同様に、準備時間算出回路8
へユースポイントBの蒸気使用開始時刻T2を入力する
と、準備時間算出回路8は暖管運転時間記憶装置7から
ユースポイントBの暖管運転時間tBを読み込み、暖管
運転時間tBと起蒸時間t1を加えた準備時間(tB+
t1)を求め、ユースポイントBで蒸気使用を開始する
時刻T2より準備時間分早い時刻T4を求める。
When the steam use start time T1 of the use point A is inputted to the preparation time calculation circuit 8, the preparation time calculation circuit 8 reads the warm-up operation time tA of the use point A from the warm-up operation time storage device 7, and performs the warm-up operation. A preparation time (tA + t1) obtained by adding the operation time tA and the steaming time t1 is obtained, and a time T3 earlier by the preparation time than the time T1 at which the use of steam at the use point A is started is obtained. Similarly, the preparation time calculation circuit 8
When the steam use start time T2 of the use point B is input, the preparation time calculation circuit 8 reads the warm-up time tB of the use-point B from the warm-up time operation time storage device 7, and the warm-up time tB and the transpiration time t1. Preparation time (tB +
t1) is obtained, and a time T4 earlier by the preparation time than the time T2 at which the use of steam at the use point B is started is obtained.

【0011】準備時間算出回路8では、求めた時刻T3
と時刻T4を比較し、最も早い時刻をボイラ運転開始時
刻とする。ユースポイントAとユースポイントBでは、
起蒸時間t1は同じであるが、暖管運転時間tAよりも
暖管運転時間tBの方が大きいため、ボイラ運転開始時
刻T3よりもボイラ運転開始時刻T4の方が早くなって
おり、ボイラ運転開始時刻としては時刻T4を算出す
る。
In the preparation time calculation circuit 8, the calculated time T3
And the time T4, and the earliest time is set as the boiler operation start time. In use point A and use point B,
The steaming time t1 is the same, but since the warm-up time tB is longer than the warm-up time tA, the boiler operation start time T4 is earlier than the boiler operation start time T3. Time T4 is calculated as the start time.

【0012】算出したボイラ運転開始時刻である時刻T
4は、制御装置4のタイマ装置10へ送られ、算出され
たボイラ運転開始時刻にボイラの運転を開始するように
設定することで、タイマ装置10は時刻T4でボイラの
運転を開始させる。
Time T, which is the calculated boiler operation start time
4 is sent to the timer device 10 of the control device 4 and is set to start the operation of the boiler at the calculated boiler operation start time, so that the timer device 10 starts the operation of the boiler at time T4.

【0013】[0013]

【発明の効果】本発明を実施することにより、最適なタ
イミングで蒸気ボイラの運転を開始できるようになる。
また煩雑な計算を行う手間を省くこともできる。
According to the present invention, the operation of the steam boiler can be started at an optimum timing.
Also, the trouble of performing complicated calculations can be saved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明を実施している蒸気供給装置のフロー
FIG. 1 is a flow chart of a steam supply device embodying the present invention.

【図2】 ユースポイントでの蒸気使用開始時刻とボイ
ラ運転開始時刻の関係を示した説明図
FIG. 2 is an explanatory diagram showing a relationship between a steam use start time at a use point and a boiler operation start time.

【符号の説明】[Explanation of symbols]

1 蒸気ボイラ 2 蒸気供給配管 3 準備時間算出装置 4 制御装置 5 蒸気ヘッダ 6 蒸気供給制御弁 7 暖管運転時間記憶装置 8 準備時間算出回路 9 ユースポイント 10 タイマ装置 DESCRIPTION OF SYMBOLS 1 Steam boiler 2 Steam supply pipe 3 Preparation time calculation device 4 Control device 5 Steam header 6 Steam supply control valve 7 Warm-up operation time storage device 8 Preparation time calculation circuit 9 Use point 10 Timer device

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 蒸気使用開始時刻入力手段と、準備時間
算出回路と、ボイラ運転開始時刻出力手段を有する準備
時間算出装置を設けた蒸気供給装置であって、蒸気使用
開始時刻入力手段は、蒸気使用開始時刻を準備時間算出
回路へ入力するものであり、準備時間算出回路は、入力
された蒸気使用開始時刻から所定時間分早い時刻をボイ
ラ運転開始時刻として算出するものであり、ボイラ運転
開始時刻出力手段は、準備時間算出回路で算出されたボ
イラ運転開始時刻を出力する準備時間算出装置を設けた
蒸気供給装置。
1. A steam supply device comprising a steam use start time input means, a preparation time calculation circuit, and a preparation time calculation device having a boiler operation start time output means, wherein the steam use start time input means comprises a steam use start time input means. The use start time is input to a preparation time calculation circuit, and the preparation time calculation circuit calculates a time earlier by a predetermined time from the input steam use start time as a boiler operation start time. The output means is a steam supply device provided with a preparation time calculation device for outputting the boiler operation start time calculated by the preparation time calculation circuit.
【請求項2】 蒸気ボイラと、蒸気供給配管と、制御装
置を有する蒸気供給装置であって、制御装置は、暖管運
転時間記憶装置と、準備時間算出回路を有し、蒸気供給
配管は、蒸気ボイラとユースポイントを接続し、蒸気ボ
イラで発生させた蒸気をユースポイントまで送るもので
あり、暖管運転時間記憶装置にはユースポイントまでの
蒸気配管部分の暖管運転に要する時間である暖管運転時
間を記憶させておき、準備時間算出回路は入力されたユ
ースポイントでの蒸気使用開始時刻から、ボイラの蒸気
発生に要する時間である起蒸時間と、暖管運転時間を合
計した準備時間分早い時刻をボイラ運転開始時刻として
算出する蒸気供給装置。
2. A steam supply device having a steam boiler, a steam supply pipe, and a control device, wherein the control device has a warm-up operation time storage device and a preparation time calculation circuit. The steam boiler is connected to the point of use and the steam generated by the steam boiler is sent to the point of use. The warm-pipe operation time storage device stores the warm-up time required for the warm-pipe operation of the steam piping section up to the point of use. The tube operation time is stored, and the preparation time calculation circuit calculates the sum of the steaming time, which is the time required for steam generation of the boiler, and the warm-up tube operation time from the input steam use start time at the use point. A steam supply device that calculates a minute earlier as the boiler operation start time.
【請求項3】 請求項2に記載の蒸気供給装置におい
て、ユースポイントが複数ある場合、暖管運転時間記憶
装置には各ユースポイントまでの蒸気配管ごとの暖管運
転時間を、各ユースポイント毎に記憶させておき、準備
時間算出回路は入力されたユースポイントでの蒸気使用
開始時刻から、起蒸時間と該当ユースポイントの暖管運
転時間を合計した準備時間分早い時刻をボイラ運転開始
時刻として算出する蒸気供給装置。
3. The steam supply device according to claim 2, wherein when there are a plurality of use points, the warm-pipe operation time storage device stores a warm-pipe operation time for each steam pipe to each use point. The preparation time calculation circuit sets a time earlier by the preparation time obtained by adding the steaming time and the warm-up time of the corresponding use point as the boiler operation start time from the steam use start time at the input use point. Steam supply device to calculate.
【請求項4】 請求項3に記載の蒸気供給装置におい
て、準備時間算出回路に複数のユースポイントでの蒸気
使用開始時刻を入力する場合、準備時間算出回路は入力
された各ユースポイントごとに、蒸気使用開始時刻か
ら、起蒸時間と該当ユースポイントの暖管運転時間を合
計した準備時間分早い時刻をそれぞれ求め、その中から
最も早い時刻をボイラ運転開始時刻として算出する蒸気
供給装置。
4. The steam supply device according to claim 3, wherein when the start time of using steam at a plurality of use points is input to the preparation time calculation circuit, the preparation time calculation circuit performs, for each input use point, A steam supply device that obtains an earlier time corresponding to a preparation time obtained by adding a steaming time and a warm-up operation time of a corresponding use point from a steam use start time, and calculates the earliest time as a boiler operation start time.
【請求項5】 請求項2から請求項4に記載の蒸気供給
装置において、制御装置に設定の時刻となると蒸気ボイ
ラの運転を開始させるタイマ装置を設け、準備時間算出
回路で算出したボイラ運転開始時刻は前記タイマ装置に
入力させる構成としておき、準備時間算出回路で算出し
たボイラ運転開始時刻となると、自動的にボイラの運転
を開始させるタイマ起動機能を持たせた蒸気供給装置。
5. The steam supply device according to claim 2, further comprising a timer device for starting operation of the steam boiler when a set time is reached in the control device, and starting the boiler operation calculated by the preparation time calculation circuit. A steam supply device having a timer start function for automatically inputting the time to the timer device and automatically starting the operation of the boiler when the boiler operation start time calculated by the preparation time calculation circuit is reached.
JP11205857A 1999-07-21 1999-07-21 Steam supply system with set-up time calculation device Pending JP2001033001A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11205857A JP2001033001A (en) 1999-07-21 1999-07-21 Steam supply system with set-up time calculation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11205857A JP2001033001A (en) 1999-07-21 1999-07-21 Steam supply system with set-up time calculation device

Publications (1)

Publication Number Publication Date
JP2001033001A true JP2001033001A (en) 2001-02-09

Family

ID=16513872

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11205857A Pending JP2001033001A (en) 1999-07-21 1999-07-21 Steam supply system with set-up time calculation device

Country Status (1)

Country Link
JP (1) JP2001033001A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014228192A (en) * 2013-05-22 2014-12-08 三浦工業株式会社 Boiler system
CN113091327A (en) * 2021-04-06 2021-07-09 丁胜 Electric boiler system and electric boiler control method
CN114963298A (en) * 2021-08-03 2022-08-30 华能(浙江)能源开发有限公司玉环分公司 Online quantitative calculation method and system for energy storage of steam pipe network

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014228192A (en) * 2013-05-22 2014-12-08 三浦工業株式会社 Boiler system
CN113091327A (en) * 2021-04-06 2021-07-09 丁胜 Electric boiler system and electric boiler control method
CN113091327B (en) * 2021-04-06 2022-06-17 丁胜 Electric boiler system and electric boiler control method
CN114963298A (en) * 2021-08-03 2022-08-30 华能(浙江)能源开发有限公司玉环分公司 Online quantitative calculation method and system for energy storage of steam pipe network
CN114963298B (en) * 2021-08-03 2024-01-23 华能(浙江)能源开发有限公司玉环分公司 Online quantitative calculation method and system for energy storage of steam pipe network

Similar Documents

Publication Publication Date Title
JP4613459B2 (en) Hot water system
JP2001033001A (en) Steam supply system with set-up time calculation device
JP5122850B2 (en) Control method of heat utilization device
JP6886412B2 (en) Cryogenic cooling system
JP5964029B2 (en) Auxiliary feed valve control device for steam generator
JP2003035109A5 (en)
JP6283984B2 (en) Hot water storage system
JPS58197408A (en) Starting device for combined plant
JP4984302B2 (en) Water pressure control system and water pressure control method
JPH07234014A (en) Hot water supplying apparatus
JP2007107842A (en) Hot water system
JP2001248911A (en) Method for controlling hot water supply temperature and hot water supply apparatus
JP3962640B2 (en) Water heater
JP2004085112A (en) Space heating apparatus
JP2000248904A (en) Output control method for thermal power plant
JP4314519B2 (en) Heating device and cogeneration system
JP4244877B2 (en) Hot water heating system
JP2003013807A (en) Cogeneration system
JPS6315473B2 (en)
JP2000274703A (en) Heat source unit
JPH10141089A (en) Gas turbine power generating system
KR20220062899A (en) Cascade water heater system control device and heater driving method thereof
JP3056880B2 (en) Feedwater heater controller
JP2003148804A (en) Hot water temperature control method for solar water heater supplying hot water of table temperature
JPH0838364A (en) Steam supply in heating and warming device