JP2000248542A - Solidifying material outflow preventive method from element in steel underground continuous wall construction method and steel underground continuous wall member used therefor - Google Patents

Solidifying material outflow preventive method from element in steel underground continuous wall construction method and steel underground continuous wall member used therefor

Info

Publication number
JP2000248542A
JP2000248542A JP11055175A JP5517599A JP2000248542A JP 2000248542 A JP2000248542 A JP 2000248542A JP 11055175 A JP11055175 A JP 11055175A JP 5517599 A JP5517599 A JP 5517599A JP 2000248542 A JP2000248542 A JP 2000248542A
Authority
JP
Japan
Prior art keywords
continuous wall
underground continuous
steel
concrete
steel underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11055175A
Other languages
Japanese (ja)
Inventor
Makoto Arizono
誠 有薗
Yoshio Takamori
義雄 高盛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TONE GEO TECH CO Ltd
Original Assignee
TONE GEO TECH CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TONE GEO TECH CO Ltd filed Critical TONE GEO TECH CO Ltd
Priority to JP11055175A priority Critical patent/JP2000248542A/en
Publication of JP2000248542A publication Critical patent/JP2000248542A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PROBLEM TO BE SOLVED: To completely restrain the outflow of a solidifying material such as a concrete filled at preceding element execution work even if an excavating wall surface is not smooth. SOLUTION: In this steel underground continuous wall construction method, excavation is performed while stabilizing a groove wall by a stabilizing liquid, and after completing the excavation equivalent to the preceding element section length, steel underground continuous wall member 1A to 1E are built up while mutually connecting these, and next, after placing foot protection concrete 12 under the steel underground continuous wall members 1A to 1E, concrete is filled inside an excavating groove. Above preceding element execution prevents the outflow of a solidifying material such as the concrete filled by arranging packer bodies 6, 6 by filling mortar or concrete brought into close contact with an excavating groove wall on an outside surface of the steel underground continuous wall members 1A to 1E arranged in both end parts among the plural underground continuous wall members 1A to 1E.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、鋼製地中連続壁工
法において、エレメントへのコンクリート打設(固化材
充填)時に、継手部側へ固化材が流出するのを防止する
ための固化材流出防止方法およびこれに用いられる鋼製
地中連続壁用部材に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a solidified material for preventing a solidified material from flowing out to a joint portion when concrete is poured into an element (solidified material filling) in a steel underground continuous wall method. The present invention relates to an outflow prevention method and a steel underground continuous wall member used for the method.

【0002】[0002]

【従来の技術】従来より、地中連続壁と言えば、安定液
を用いて溝壁の安定を図りながら掘削を行い、所定の掘
削完了後に、鉄筋かごを建て込み安定液と置換しながら
コンクリートを打設して地中に埋設した鉄筋コンクリー
ト連続壁体を構築するものがほとんどであったが、近年
は「NS−BOX」と呼ばれる、両端部に嵌合継手部を
有する断面略H形状またはボックス形状の鋼製地中連続
壁用部材(以下、単に鋼製連壁部材ともいう。)を掘削
後に建込み、必要に応じてコンクリート等の固化材を充
填することにより高強度かつ薄壁の連続壁体を構築する
方法が提案・実用化されている。
2. Description of the Related Art Conventionally, underground continuous walls have been excavated while stabilizing a trench wall using a stabilizing liquid, and after completion of a predetermined excavation, a reinforcing steel cage is erected and replaced with a stabilizing liquid. In most cases, a continuous reinforced concrete wall body buried in the ground is constructed by installing a reinforced concrete wall, but in recent years, it is called "NS-BOX" and has a substantially H-shaped cross section or box having fitting joints at both ends. A steel underground continuous wall member (hereinafter simply referred to as a steel continuous wall member) having a shape is built after excavation, and is filled with a solidifying material such as concrete as needed to provide high strength and thin wall continuous. A method of constructing a wall has been proposed and put to practical use.

【0003】前記鋼製地中連続壁工法は、従来の鉄筋籠
を建て込んでコンクリートを充填する地中連続壁工法に
比べて、壁厚を小さく出来る。プレファブ工法であ
るため、溶接工などの人工を減らす事ができ省力化が可
能となる。工場製品であるため現場に加工ヤードが不
要となる。短い鋼製連壁部材をボルト接合によって接
続することによりハンドリングが容易となり、狭い作業
場所でも施工が可能となる。左右の鋼製連壁部材を嵌
合継手で連結するため50mを超える大深度においても
精度の確保が可能である、等の利点を有し、近年多用さ
れるようになってきた地中連続壁工法である。
[0003] The steel underground continuous wall method can reduce the wall thickness as compared with the conventional underground continuous wall method in which a steel cage is built and filled with concrete. Since it is a prefabrication method, it is possible to reduce the number of man-made operations such as welding work and to save labor. Since it is a factory product, there is no need for a processing yard on site. By connecting the short steel continuous wall members by bolting, handling becomes easy and construction is possible even in a narrow work place. Since the left and right steel connecting wall members are connected by a fitting joint, accuracy can be ensured even at a large depth exceeding 50 m, and the like. It is a construction method.

【0004】施工に当たっては、従来と同様に、連続壁
構築予定部分をコンクリートの打設ブロック単位となる
エレメントに割付けする。施工手順としては、先行エレ
メントと後行エレメントとを連壁方向に交互に割付け
し、先に先行エレメントの掘削およびコンクリート打設
を行った後、後行エレメントの掘削およびコンクリート
打設を行う方法と、連壁の一方側に向かって順番にエレ
メント毎の掘削とコンクリート打設とを行い連壁を延長
させる、所謂片押し方法とがある。なお、1エレメント
当たりは複数ガット(掘削単位)とされる。
At the time of construction, a portion where a continuous wall is to be constructed is allocated to elements serving as concrete placing blocks, as in the prior art. As a construction procedure, a method in which the preceding element and the following element are alternately allocated in the direction of the continuous wall, excavation of the preceding element and concrete placement are performed first, and then excavation of the subsequent element and concrete placement are performed. There is a so-called one-sided pushing method in which excavation for each element and concrete casting are sequentially performed toward one side of the continuous wall to extend the continuous wall. A plurality of guts (units of excavation) are used per element.

【0005】以下、先行エレメントの施工方法と後行エ
レメントに分けて行う施工方法例について図面に基づい
て概説すると、先ず、先行エレメントの施工は、図7に
示されるように、掘削機50により安定液により溝壁保
護を図りながら掘削を行ったならば、相互の継手を接合
させながら鋼製連壁部材51,51…の建込みを行い、
次工程のコンクリート打設によって鋼製連壁部材51,
51…が移動しないように根固めコンクリート52を打
設し、最後にコンクリート等の固化材53を充填する。
なお、図8は固化材充填後の連壁平面図である。
[0005] An example of a method of constructing the preceding element and a method of constructing the latter element separately will now be described with reference to the drawings. First, the construction of the preceding element is stabilized by the excavator 50 as shown in FIG. If the excavation is performed while protecting the groove wall with the liquid, the steel connecting wall members 51, 51,.
Steel concrete wall member 51,
The concrete 52 is poured to prevent the 51... From moving, and finally a solidified material 53 such as concrete is filled.
FIG. 8 is a plan view of the continuous wall after the solidification material is filled.

【0006】一方、後行エレメントの施工は、図9に示
されるように、先行エレメントに挟まれた区間を掘削機
50を用い掘削により掘削し、継手清掃機54により継
手部の洗浄(ジェット洗浄またはブラシ洗浄)を行い、
次いで鋼製連壁部材51,51…の建込みを行った後、
コンクリート等の固化材53を打設する。
[0009] On the other hand, as shown in FIG. 9, the section between the preceding elements is excavated by excavation using an excavator 50, and the joint is cleaned by a joint cleaner 54 (jet cleaning), as shown in FIG. 9. Or brush cleaning)
Then, after installing the steel connecting wall members 51, 51 ...
A solidifying material 53 such as concrete is cast.

【0007】前記先行エレメント施工時においては、打
設したコンクリート(固化材)が後行エレメントとの継
手部側へ流出するのを防止するために、必ずコンクリー
トの流出防止措置が採られる。なお、鋼製連壁部材の底
部開口からのコンクリート流出は根固めコンクリートに
よって防止されるため、鋼製連壁部材の側部からの流出
防止対策が採られる。
When the preceding element is constructed, concrete leakage prevention measures are always taken to prevent the poured concrete (solidified material) from flowing toward the joint portion with the succeeding element. Since concrete is prevented from flowing out from the bottom opening of the steel continuous wall member by the solidified concrete, measures are taken to prevent the concrete from flowing out from the side portion of the steel continuous wall member.

【0008】図10に示される流出防止構造例は、両端
部に配置される鋼製連壁部材51,51のフランジ外面
の端部位置にフランジ面に直交する押え板54を溶接等
に固設するとともに、この押え板54の先端部にゴムシ
ート55を連結することによりコンクリートの流出を防
止するようにした例である。これは一例であるが、従来
のほとんどのものは取付構造に多少の違いはあってもゴ
ムシートを部材長手方向に設けることによりコンクリー
トの流出を防止しようとするものがほとんどである。な
お、符号56は継手内部にコンクリートや裏込砕石が流
入するのを防止するために設置された継手防護プレート
である。
In the example of the outflow prevention structure shown in FIG. 10, a pressing plate 54 orthogonal to the flange surface is fixed to the end position of the flange outer surface of the steel continuous wall members 51, 51 disposed at both ends by welding or the like. This is an example in which a rubber sheet 55 is connected to the tip of the holding plate 54 to prevent concrete from flowing out. This is an example, but most of the conventional ones attempt to prevent the concrete from flowing out by providing a rubber sheet in the longitudinal direction of the member even though the mounting structure is slightly different. Reference numeral 56 denotes a joint protection plate provided to prevent concrete or back crushed stone from flowing into the inside of the joint.

【0009】[0009]

【発明が解決しようとする課題】しかしながら、前述し
た押え板54とゴムシート55とによる固化材流出防止
構造の場合には、掘削精度が地盤深さ方向に亘って高い
精度で確保され、かつ壁面の平滑性が確保されていれば
固化材流出防止効果がかなり望めるけれども、実際には
壁面の平滑性が悪かったり、壁面の肌落ち、崩落などに
より掘削幅に部分的な誤差が生じてしまうため、部分的
に形成される隙間からコンクリート等の固化材が流出し
てしまうなどの問題が依然として発生していた。
However, in the case of the above-described structure for preventing the solidified material from flowing out by the holding plate 54 and the rubber sheet 55, the excavation accuracy is secured with high accuracy in the depth direction of the ground, and the wall surface is secured. If the smoothness is secured, the effect of preventing solidified material from flowing out can be quite expected, but in practice, the smoothness of the wall surface is poor, and the excavation width has a partial error due to the wall surface falling, falling down etc. However, there still remains a problem that a solidified material such as concrete flows out of a partially formed gap.

【0010】そこで本発明の主たる課題は、たとえ壁面
の肌落ちや崩落等により掘削壁面が平滑でなくても固化
材の流出を完全に押さえることができる鋼製地中連続壁
工法における先行エレメントからの固化材流出防止方法
を提供するとともに、これに用いられる鋼製地中連続壁
用部材を提供することにある。
[0010] Therefore, the main object of the present invention is to provide a steel underground continuous wall construction method that can completely suppress the outflow of the solidified material even if the excavated wall is not smooth due to surface fall or collapse. To provide a method for preventing solidified material from flowing out and to provide a steel underground continuous wall member used for the method.

【0011】[0011]

【課題を解決するための手段】前記課題を解決するため
に本発明は、安定液により溝壁の安定を図りながら掘削
を行い、エレメント区間長分の掘削完了後に、断面略H
状またはボックス状鋼製部材のフランジ端部にそれぞれ
雄または雌継手を備えた鋼製地中連続壁用部材を相互に
連結させながら複数建込み、次いで前記鋼製地中連続壁
用部材の下部に根固めコンクリートを打設した後、掘削
溝内部に固化材充填を行う鋼製地中連続壁工法における
エレメント施工において、前記複数の鋼製地中連続壁用
部材の内、両端部に配置されている鋼製地中連続壁用部
材の外面部分に、掘削溝壁に密着するモルタルまたはコ
ンクリート充填によるパッカー体を設けることにより前
記固化材の流出を防止するようにしたことを特徴とする
ものである。
According to the present invention, in order to solve the above-mentioned problems, excavation is performed while stabilizing the groove wall with a stabilizing liquid, and after excavation for the element section length is completed, the cross section is approximately H.
A plurality of steel underground continuous wall members each having a male or female joint are connected to each other at the flange end of the steel or box-shaped steel member, and then the lower part of the steel underground continuous wall members is connected. After laying concrete in the ground, in the element construction in the steel underground continuous wall construction method of filling the inside of the excavation trench with solidification material, among the plurality of steel underground continuous wall members, disposed at both ends On the outer surface of the steel underground continuous wall member, a packer body made of mortar or concrete filled in close contact with the excavation groove wall is provided to prevent the solidified material from flowing out. is there.

【0012】より具体的態様では、安定液により溝壁の
安定を図りながら掘削を行い、エレメント区間長分の掘
削完了後に、断面略H状またはボックス状鋼製部材のフ
ランジ端部にそれぞれ雄または雌継手を備えた鋼製地中
連続壁用部材を相互に連結させながら複数建込み、次い
で前記鋼製地中連続壁用部材の下部に根固めコンクリー
トを打設した後、掘削溝内部に固化材充填を行う鋼製地
中連続壁工法におけるエレメント施工において、前記複
数の鋼製地中連続壁用部材の内、端部に配置される鋼製
地中連続壁用部材については、フランジの外面端部位置
にそれぞれ部材長手方向に連続する起立片が固設される
とともに、フランジ外面の両端部に固設された起立片を
対として、これら起立片間にパッカー用シートを掛け渡
してある鋼製地中連続壁用部材を用いることとし、前記
固化材充填の施工前に、前記パッカー用シート内部にモ
ルタルまたはコンクリートを充填し掘削溝壁に密着する
パッカー体を形成することにより前記固化材の流出を防
止するようにしたことを特徴とするものである。
In a more specific mode, excavation is performed while stabilizing the groove wall with a stabilizing liquid, and after excavation for the element section length is completed, a male or female member is formed at the flange end of the substantially H-shaped or box-shaped steel member in cross section, respectively. A plurality of steel underground continuous wall members provided with female joints are connected to each other, and a plurality of steel underground continuous wall members are connected to each other, and then concrete is poured into the lower part of the steel underground continuous wall members, and then solidified in the excavation trench. In the element construction in the steel underground continuous wall method for filling the material, among the plurality of steel underground continuous wall members, for the steel underground continuous wall member disposed at the end, the outer surface of the flange Standing pieces that are respectively continuous in the longitudinal direction of the member are fixed at the end positions, and a pair of the rising pieces fixed to both ends of the outer surface of the flange, and a sheet for a packer is stretched between these standing pieces. During production Prevent the outflow of the solidified material by filling the inside of the sheet for packer with mortar or concrete and forming a packer body that is in close contact with the excavation groove wall before the filling of the solidified material is performed by using a member for the connecting wall. It is characterized by doing so.

【0013】本発明においては、両端部に配置される鋼
製地中連続壁用部材の外面にパッカー体を設けるように
したため、壁面の肌落ちや崩落が生じ掘削壁面が平滑で
無くても、膨張したパッカー体が掘削壁面に完全に密着
して固化材の流出を完全に押さえることができるように
なる。
[0013] In the present invention, since the packer body is provided on the outer surface of the steel underground continuous wall member disposed at both ends, even if the surface of the excavated wall is not smooth even if the wall surface falls or collapses. The expanded packer body is completely adhered to the excavation wall surface, so that the outflow of the solidified material can be completely suppressed.

【0014】他方で、前記両端部に配置される鋼製地中
連続壁用部材は、予め工場製作とすることが望ましく、
前記固化材流出防止方法に用いられる鋼製地中連続壁用
部材は、断面略H状またはボックス状鋼製部材のフラン
ジ端部にそれぞれ雄または雌継手を備えた鋼製地中連続
壁用部材において、前記フランジの外面端部位置にそれ
ぞれ部材長手方向に連続する起立片を固設するととも
に、フランジ外面の両端部に固設された起立片を対とし
て、これら起立片間にパッカー用シートを掛け渡してあ
ることを特徴とするものである。
On the other hand, the steel underground continuous wall members disposed at both ends are desirably manufactured in advance in a factory.
The steel underground continuous wall member used in the method of preventing solidified material outflow is a steel underground continuous wall member having a male or female joint at a flange end of a substantially H-shaped or box-shaped steel member, respectively. In the above, the upright pieces continuous in the longitudinal direction of the member are fixedly provided at the outer surface end positions of the flange, and the upright pieces fixed at both ends of the outer surface of the flange are paired, and the packer sheet is interposed between these upright pieces. It is characterized by being passed over.

【0015】[0015]

【発明の実施の形態】以下、本発明の実施の形態につい
て図面を参照しながら詳述する。図1は本発明に係る固
化材流出防止方法に使用される鋼製地中連続壁用部材1
を上面から視た斜視図であり、図2はパッカー体の全体
施工状況図である。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is a steel underground continuous wall member 1 used in the method for preventing solidified material from flowing out according to the present invention.
FIG. 2 is a perspective view of the packer body as viewed from above, and FIG.

【0016】鋼製地中連続壁用部材1は、ウエブ2とフ
ランジ3,4とにより断面略H状に成形された鋼製部材
の前記フランジ3,4端部にそれぞれ雄または雌継手、
図示の例ではC字状雌継手5,5…を備えた部材であ
り、前述したように、掘削完了後の溝内部に相互に連結
させながら建て込まれる。なお、前記継手形状について
は、標準タイプとされるものを図示したが、他に複数種
類のものが予め用意されている。
A steel underground continuous wall member 1 comprises a steel member formed into a substantially H-shaped cross-section by a web 2 and flanges 3 and 4 at male and female joints at ends of the flanges 3 and 4 respectively.
In the illustrated example, the member is provided with the C-shaped female joints 5, 5,..., And as described above, is built while being connected to each other inside the groove after the excavation is completed. In addition, as for the joint shape, a standard type is illustrated, but a plurality of other types are prepared in advance.

【0017】本発明では、特に既製の鋼製連壁部材1に
手を加えて、フランジ3,4外面部分にモルタルまたは
コンクリート充填によるパッカー体6,6を設けるよう
にしている。具体的には、フランジ3,4の外面両端部
位置にそれぞれ部材長手方向に沿って連続する断面L字
状の起立片7,7…を固設するとともに、フランジ3
(4)の両端部に固設された対峙する一対の起立片7,
7を組みとして、これら起立片7,7間にパッカー用シ
ート8を掛け渡すことによりパッカー体6を構成するよ
うにしてある。前記起立片7に対するパッカー用シート
8の固定方法は、起立片7の水平フランジ面に前記パッ
カー用シート8の端部を押え板9によって挟み付け、部
材長手方向に所定の間隔でビス10,10…によって止
着するようにしているが、他の固定方法であっても構わ
ない。なお、符号11は前記パッカー用シート8内部に
モルタルまたはコンクリートを充填するための注入パイ
プである。
In the present invention, particularly, the ready-made steel continuous wall member 1 is modified so that the outer surfaces of the flanges 3 and 4 are provided with the packers 6 and 6 filled with mortar or concrete. Specifically, standing pieces 7, 7,... Having an L-shaped cross section, which are respectively continuous along the longitudinal direction of the member, are fixed to both ends of the outer surfaces of the flanges 3, 4, respectively.
(4) a pair of opposing standing pieces 7, which are fixed at both ends,
The packer body 6 is formed by bridging a packer sheet 8 between the standing pieces 7, 7. A method of fixing the packer sheet 8 to the upright piece 7 is as follows. An end of the packer sheet 8 is sandwiched by a pressing plate 9 on a horizontal flange surface of the upright piece 7, and screws 10, 10 are arranged at predetermined intervals in the longitudinal direction of the member. .., But other fixing methods may be used. Reference numeral 11 denotes an injection pipe for filling mortar or concrete inside the packer sheet 8.

【0018】施工に当たっては、安定液により溝壁の安
定を図りながら掘削を行い、先行エレメント区間長分の
掘削完了後に、図2に示されるように、左右の雄または
雌継手を相互に連結させながら複数、本例では5本の鋼
製連壁部材1A〜1Eの建て込みを行う。これらの鋼製
連壁部材1A〜1Eの内、両端部の鋼製連壁部材1A、
1Eについては、図1に示されフランジ外面にパッカー
体6を備えた鋼製連壁部材1が用いられ、中間の鋼製連
壁部材1B〜1Dについては既製品の鋼製連壁部材がそ
のまま用いられる。
In the construction, excavation is performed while stabilizing the groove wall with a stabilizing liquid, and after excavation for the length of the preceding element section is completed, the left and right male or female joints are interconnected as shown in FIG. However, a plurality of, in this example, five steel continuous wall members 1A to 1E are erected. Of these steel continuous wall members 1A to 1E, steel continuous wall members 1A at both ends,
1E, the steel connecting wall member 1 shown in FIG. 1 and having the packer body 6 on the outer surface of the flange is used, and the intermediate steel connecting wall members 1B to 1D are the existing steel connecting wall members as they are. Used.

【0019】鋼製連壁部材1A〜1Eの建込みが完了し
たならば、根固めコンクリート12の打設と、前記パッ
カー体6に対するモルタルまたはコンクリート充填を行
う。
When the steel connecting wall members 1A to 1E have been completely installed, the reinforced concrete 12 is placed and the mortar or concrete is filled into the packer body 6.

【0020】施工順序としては、根固めコンクリート1
2→パッカー体6の順で施工を行った場合には、鋼製連
壁部材1の下部において、パッカー体6が掘削壁面にき
っちりと密着しない状況になることが考えられるため、
先ずパッカー体6に対してモルタルまたはコンクリート
充填を所定の高さ位置(根固めコンクリート12上面よ
り少なくとも上側位置)まで行った後、根固めコンクリ
ート12の打設を行い、次いで再びパッカー体6の施工
を行うようにするのが望ましい。
The order of construction is as follows:
If the construction is performed in the order of 2 → packer body 6, the packer body 6 may not be in close contact with the excavated wall at the lower part of the steel continuous wall member 1.
First, the mortar or concrete is filled into the packer body 6 to a predetermined height position (at least an upper position from the upper surface of the compacted concrete 12), and then the compacted concrete 12 is poured. It is desirable to carry out.

【0021】パッカー体6に対するモルタルまたはコン
クリート充填作業は、注入パイプ11をガイドウォール
上にて支持しながら、起重機13などを用いて所定長の
単位注入パイプ11aを供給・接続することにより所定
の深さ位置まで延長したならば、前記注入パイプ11と
搬送ポンプ16のホースとを接続し、生コンプラントか
らミキサー車14によって搬入されたモルタルまたはコ
ンクリートをホッパー15に投入することにより行う。
The mortar or concrete filling operation for the packer body 6 is performed by supplying and connecting a unit injection pipe 11a having a predetermined length by using a hoist 13 or the like while supporting the injection pipe 11 on a guide wall. After the extension to the position, the injection pipe 11 and the hose of the transport pump 16 are connected, and the mortar or concrete carried by the mixer 14 from the ready-mixed plant is put into the hopper 15.

【0022】所定の高さ位置まで注入パイプ11を介し
てモルタルまたはコンクリートの充填を行い、鋼製連壁
部材1A、1E外面下部にきっちりとパッカー体6を完
成させたならば、図示しないトレミー管を用いて根固め
コンクリート12を所定高さ位置まで打設する。この根
固めコンクリート12は、コンクリート(固化材)充填
時に鋼製連壁部材1A〜1Eが移動しないように支持す
るとともに、中詰めされるコンクリート等の固化材が鋼
製連壁部材1A〜1Eの下端口から外部に流出しないよ
うにする2つの機能を合わせ持つものである。
When the mortar or concrete is filled to a predetermined height through the injection pipe 11 and the packer body 6 is completely formed at the lower portion of the outer surfaces of the steel continuous wall members 1A and 1E, a tremy pipe (not shown) And the concrete 12 is poured to a predetermined height. The consolidation concrete 12 supports the steel continuous wall members 1A to 1E so as not to move when the concrete (solidified material) is filled, and the solidified material such as the concrete to be filled with the steel continuous wall members 1A to 1E. It has two functions to prevent it from flowing out from the lower end.

【0023】根固めコンクリート12の打設を終えたな
らば、図3に示されるように、注入パイプ11を利用し
てパッカー体6内部にモルタルまたはコンクリートの充
填を再び行いパッカー体6を完成させる。前記搬送ポン
プ16からの供給量は、充填されるモルタルまたはコン
クリートの上面レベルが3〜5m/h の速度で上昇する程
度の早さを目安として行い、モルタルまたはコンクリー
ト中に対する根入れ長Sは常に1〜3m程度に保持され
るように注入パイプ11を適時引抜きながら行うように
する。なお、モルタルまたはコンクリートの充填量に合
わせながら適時、単位注入パイプ11aを抜取ることに
よりパイプ長を徐々に短くしていく。図4はパッカー体
6完成状態を示す斜視図である。
When the placing of the reinforced concrete 12 is completed, as shown in FIG. 3, the inside of the packer body 6 is filled with mortar or concrete again using the injection pipe 11 to complete the packer body 6. . The feed rate from the transfer pump 16 is set so that the top level of the mortar or concrete to be filled rises at a speed of 3 to 5 m / h as a guide. The injection pipe 11 is pulled out at appropriate times so as to be maintained at about 1 to 3 m. In addition, the length of the pipe is gradually shortened by extracting the unit injection pipe 11a as appropriate while adjusting to the filling amount of mortar or concrete. FIG. 4 is a perspective view showing a completed state of the packer body 6.

【0024】次いで、端部の鋼製連壁部材1A、1Eの
C字状雌継手5,5に継手防護プレート17を設けたな
らば、掘削溝内部、正確には図5に図示されるように、
鋼製連壁部材1A〜1Eによって囲まれたボックス内部
と、フランジ面と掘削壁面との間の狭空間であって、か
つパッカー体6,6によって挟まれた空間内部にコンク
リート、モルタル、泥土モルタル、泥水固化材などの固
化材をトレミー管を使用して充填する。このコンクリー
ト打設に併行してまたはコンクリート打設に先行して前
記継手防護プレート17、17の背面側に砕石を投入す
るようにする。
Next, if the joint protection plate 17 is provided on the C-shaped female joints 5, 5 of the steel connecting wall members 1A, 1E at the ends, the inside of the excavation groove, more precisely, as shown in FIG. To
Concrete, mortar, and mud mortar in the narrow space between the inside of the box surrounded by the steel continuous wall members 1A to 1E and the space between the flange surface and the excavation wall surface and between the packer bodies 6, 6. A solidifying material such as a mud solidifying material is filled using a tremy tube. In parallel with or prior to the concrete casting, crushed stones are introduced into the back side of the joint protection plates 17, 17.

【0025】その後、先行エレメントの施工が完了し、
後行エレメントの掘削が完了した段階で、図6に示され
るように、継手清掃機20により端部鋼製連壁部材1
A,1Eの清掃することにより、後行エレメントに打設
されるコンクリートと一体化を図るようにする。この継
手清掃機20は、端部鋼製連壁部材1A,1EのC字状
雌継手5,5に嵌合挿入される脚部20b,20bを備
え、ワイヤ吊りによって昇降自在とされる装置で、内面
側に設けられた噴射ノズル20aからジェット水を噴射
することにより端部鋼製連壁部材1A,1E内部を清掃
するものである。
Thereafter, the construction of the preceding element is completed,
At the stage where the excavation of the following element is completed, as shown in FIG.
By cleaning A and 1E, integration with the concrete poured into the following element is achieved. This joint cleaning machine 20 is provided with legs 20b, 20b fitted and inserted into the C-shaped female joints 5, 5 of the end steel continuous wall members 1A, 1E, and is a device which can be raised and lowered by hanging wires. The inside of the end steel continuous wall members 1A and 1E is cleaned by jetting jet water from a jet nozzle 20a provided on the inner surface side.

【0026】[0026]

【発明の効果】以上詳説のとおり本発明によれば、両端
部に配置される鋼製地中連続壁用部材の外面にパッカー
体を設けるようにしたため、たとえ壁面の肌落ちや崩落
が生じて掘削壁面が平滑でなくても、先行エレメント施
工時に充填されるコンクリート等の固化材の流出を完全
に押さえることができるようになる。
As described above in detail, according to the present invention, since the packer body is provided on the outer surface of the steel ground wall member disposed at both ends, even if the wall surface is peeled off or collapsed. Even if the excavation wall surface is not smooth, it is possible to completely suppress the outflow of the solidified material such as concrete filled at the time of constructing the preceding element.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る鋼製地中連続壁用部材1を上面か
ら視た斜視図である。
FIG. 1 is a perspective view of a steel underground continuous wall member 1 according to the present invention as viewed from above.

【図2】パッカー体6の全体施工要領図である。FIG. 2 is an overall construction procedure diagram of the packer body 6;

【図3】パッカー体6内部へのモルタルまたはコンクリ
ート充填要領図である。
FIG. 3 is a view showing a procedure for filling mortar or concrete into a packer body 6;

【図4】パッカー体完成状態を示す斜視図である。FIG. 4 is a perspective view showing a completed packer body.

【図5】コンクリート(固化材)打設状況の平面図であ
る。
FIG. 5 is a plan view of a concrete (solidified material) casting situation.

【図6】後行エレメント施工時の継手清掃要領図であ
る。
FIG. 6 is a view showing a joint cleaning procedure when a subsequent element is constructed.

【図7】従来一般の鋼製地中連続壁の平面図である。FIG. 7 is a plan view of a conventional general steel underground continuous wall.

【図8】鋼製地中連続壁工法における先行エレメント施
工段階図である。
FIG. 8 is a diagram showing a preceding element construction stage in the steel underground continuous wall method.

【図9】鋼製地中連続壁工法における後行エレメント施
工段階図である。
FIG. 9 is a subsequent element construction stage diagram in the steel underground continuous wall method.

【図10】先行エレメント施工時の固化材流出防止対策
例を示す平面図である。
FIG. 10 is a plan view showing an example of a measure for preventing solidified material from flowing out during construction of a preceding element.

【符号の説明】[Explanation of symbols]

1…鋼製地中連続壁用部材、2…ウエブ、3・4…フラ
ンジ、5…C字状雌継手、6…パッカー体、7…起立
片、8…パッカー用シート、9…押え板、10…ビス、
11…注入パイプ、12…根固めコンクリート、17…
継手防護プレート、18…砕石、20…継手清掃機
DESCRIPTION OF SYMBOLS 1 ... Steel underground continuous wall member, 2 ... Web, 3/4 ... flange, 5 ... C-shaped female joint, 6 ... Packer body, 7 ... Standing piece, 8 ... Packer sheet, 9 ... Holding plate, 10 ... Screw,
11 ... Injection pipe, 12 ... Consolidation concrete, 17 ...
Joint protection plate, 18: crushed stone, 20: joint cleaning machine

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】安定液により溝壁の安定を図りながら掘削
を行い、エレメント区間長分の掘削完了後に、断面略H
状またはボックス状鋼製部材のフランジ端部にそれぞれ
雄または雌継手を備えた鋼製地中連続壁用部材を相互に
連結させながら複数建込み、次いで前記鋼製地中連続壁
用部材の下部に根固めコンクリートを打設した後、掘削
溝内部に固化材充填を行う鋼製地中連続壁工法における
エレメント施工において、 前記複数の鋼製地中連続壁用部材の内、両端部に配置さ
れている鋼製地中連続壁用部材の外面部分に、掘削溝壁
に密着するモルタルまたはコンクリート充填によるパッ
カー体を設けることにより前記固化材の流出を防止する
ようにしたことを特徴とする鋼製地中連続壁工法におけ
るエレメントからの固化材流出防止方法。
1. Excavation is performed while stabilizing a groove wall with a stabilizing liquid.
A plurality of steel underground continuous wall members each having a male or female joint are connected to each other at the flange end of the steel or box-shaped steel member, and then the lower part of the steel underground continuous wall members is connected. In the element construction in the steel underground continuous wall method of filling the solidification material inside the excavation trench after placing concrete in the foundation, the steel underground continuous wall members are disposed at both ends. The outer surface portion of the steel underground continuous wall member is provided with a packer body filled with mortar or concrete that is in close contact with the excavation groove wall to prevent the solidified material from flowing out. A method for preventing solidified material from flowing out of elements in underground continuous wall construction.
【請求項2】安定液により溝壁の安定を図りながら掘削
を行い、エレメント区間長分の掘削完了後に、断面略H
状またはボックス状鋼製部材のフランジ端部にそれぞれ
雄または雌継手を備えた鋼製地中連続壁用部材を相互に
連結させながら複数建込み、次いで前記鋼製地中連続壁
用部材の下部に根固めコンクリートを打設した後、掘削
溝内部に固化材充填を行う鋼製地中連続壁工法における
エレメント施工において、 前記複数の鋼製地中連続壁用部材の内、端部に配置され
る鋼製地中連続壁用部材については、フランジの外面端
部位置にそれぞれ部材長手方向に連続する起立片が固設
されるとともに、フランジ外面の両端部に固設された起
立片を対として、これら起立片間にパッカー用シートを
掛け渡してある鋼製地中連続壁用部材を用いることと
し、 前記固化材充填の施工前に、前記パッカー用シート内部
にモルタルまたはコンクリートを充填し掘削溝壁に密着
するパッカー体を形成することにより前記固化材の流出
を防止するようにしたことを特徴とする鋼製地中連続壁
工法におけるエレメントからの固化材流出防止方法。
2. Excavation is performed while stabilizing the groove wall with a stabilizing liquid.
A plurality of steel underground continuous wall members each having a male or female joint are connected to each other at the flange end of the steel or box-shaped steel member, and then the lower part of the steel underground continuous wall members is connected. In the element construction in the steel underground continuous wall method of filling the solidification material inside the excavation trench after placing the concrete in the foundation, the steel underground continuous wall member is arranged at an end portion of the members. For steel underground continuous wall members, upright pieces continuous in the longitudinal direction of the member are fixedly provided at the outer surface end positions of the flange, and the upright pieces fixed at both end portions of the outer surface of the flange are paired. A steel underground continuous wall member in which a packer sheet is stretched between the standing pieces is used, and before the solidification material is filled, mortar or concrete is filled inside the packer sheet and excavated. Solidifying material outflow preventing method from elements in steel underground continuous wall method being characterized in that so as to prevent the outflow of the solidified material by forming a packer body in close contact with the groove wall.
【請求項3】断面略H状またはボックス状鋼製部材のフ
ランジ端部にそれぞれ雄または雌継手を備えた鋼製地中
連続壁用部材において、 前記フランジの外面端部位置にそれぞれ部材長手方向に
連続する起立片を固設するとともに、フランジ外面の両
端部に固設された起立片を対として、これら起立片間に
パッカー用シートを掛け渡してあることを特徴とする鋼
製地中連続壁用部材。
3. A steel underground continuous wall member provided with a male or female joint at a flange end of a substantially H-shaped or box-shaped steel member in cross-section, respectively, wherein said flange is disposed at an end position of an outer surface of said flange. And a pair of standing pieces fixed to both ends of the outer surface of the flange, and a sheet for a packer is stretched between these standing pieces. Wall members.
JP11055175A 1999-03-03 1999-03-03 Solidifying material outflow preventive method from element in steel underground continuous wall construction method and steel underground continuous wall member used therefor Pending JP2000248542A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11055175A JP2000248542A (en) 1999-03-03 1999-03-03 Solidifying material outflow preventive method from element in steel underground continuous wall construction method and steel underground continuous wall member used therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11055175A JP2000248542A (en) 1999-03-03 1999-03-03 Solidifying material outflow preventive method from element in steel underground continuous wall construction method and steel underground continuous wall member used therefor

Publications (1)

Publication Number Publication Date
JP2000248542A true JP2000248542A (en) 2000-09-12

Family

ID=12991397

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11055175A Pending JP2000248542A (en) 1999-03-03 1999-03-03 Solidifying material outflow preventive method from element in steel underground continuous wall construction method and steel underground continuous wall member used therefor

Country Status (1)

Country Link
JP (1) JP2000248542A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002285549A (en) * 2001-03-26 2002-10-03 Toyo Constr Co Ltd Cutoff method
JP2009046853A (en) * 2007-08-17 2009-03-05 Ohbayashi Corp Water cutoff structure of earth retaining wall, and water cutoff structure construction method
JP2014101710A (en) * 2012-11-21 2014-06-05 Kajima Corp Continuous wall construction method
JP2014101711A (en) * 2012-11-21 2014-06-05 Kajima Corp Continuous wall member and continuous wall construction method
JP2018016954A (en) * 2016-07-25 2018-02-01 鹿島建設株式会社 Construction method of underground wall
JP2020204222A (en) * 2019-06-19 2020-12-24 ケミカルグラウト株式会社 Earth retaining wall construction method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002285549A (en) * 2001-03-26 2002-10-03 Toyo Constr Co Ltd Cutoff method
JP4543358B2 (en) * 2001-03-26 2010-09-15 東洋建設株式会社 Deadline method
JP2009046853A (en) * 2007-08-17 2009-03-05 Ohbayashi Corp Water cutoff structure of earth retaining wall, and water cutoff structure construction method
JP2014101710A (en) * 2012-11-21 2014-06-05 Kajima Corp Continuous wall construction method
JP2014101711A (en) * 2012-11-21 2014-06-05 Kajima Corp Continuous wall member and continuous wall construction method
JP2018016954A (en) * 2016-07-25 2018-02-01 鹿島建設株式会社 Construction method of underground wall
JP2020204222A (en) * 2019-06-19 2020-12-24 ケミカルグラウト株式会社 Earth retaining wall construction method
JP7250627B2 (en) 2019-06-19 2023-04-03 ケミカルグラウト株式会社 Retaining wall construction method

Similar Documents

Publication Publication Date Title
CN110656954B (en) Tunnel collapse processing method for convergent collapsed cavity
CH615236A5 (en)
CN207512745U (en) A kind of caisson device and its foundation pit structure
CN110778328B (en) Loess tunnel entrance section construction method for passing through landslide body
CN203924116U (en) Portable side wall formwork jumbo
JP4881555B2 (en) Construction method of underground structure
JP2000248542A (en) Solidifying material outflow preventive method from element in steel underground continuous wall construction method and steel underground continuous wall member used therefor
CN110905529B (en) Construction method of loess tunnel penetrating through landslide mass
CN210395378U (en) Slope protection device
CN203960878U (en) A kind of construction formwork of retaining engineering
CN115748786A (en) Drainage sinking construction method for pipe-jacking circular open caisson
CN211038666U (en) Sleeve lining pouring construction structure based on assembled scaffold
CN100381647C (en) Construction process of bagged concrete foundation with limit device for immersed tube tunnel
CN112610240A (en) Secondary lining construction process for mountain tunnel
CN110725319B (en) Large-angle concrete pouring method
CN209523201U (en) The structure of form concrete between a kind of subway station fender post
JP3561869B2 (en) Underground continuous wall construction method and groove wall protection plate
CN217460670U (en) Subway station plate wall structure for staged construction
CN116145739B (en) Vibration reduction structure of wood formwork of bottom plate without dismantling and construction method of vibration reduction structure
JP2004132124A (en) Pneumatic caisson and pneumatic caisson constructing method
CN112709217B (en) Formwork assembly of reverse construction method retaining wall and retaining wall construction method
AU603257B2 (en) A precast diaphragm wall method
JP2001164559A (en) Construction method of continuous underground wall guide wall making use of l-type precast member
JPH0665919A (en) Water jet device for joint steel plate cleaning device for underground continuous wall joint
JP2779879B2 (en) How to construct a suspended water wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051214

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070628

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20071022