JP2000144892A - Construction method for upper frame of large span girder - Google Patents

Construction method for upper frame of large span girder

Info

Publication number
JP2000144892A
JP2000144892A JP10318557A JP31855798A JP2000144892A JP 2000144892 A JP2000144892 A JP 2000144892A JP 10318557 A JP10318557 A JP 10318557A JP 31855798 A JP31855798 A JP 31855798A JP 2000144892 A JP2000144892 A JP 2000144892A
Authority
JP
Japan
Prior art keywords
girder
upper frame
frame
column
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10318557A
Other languages
Japanese (ja)
Other versions
JP2974025B1 (en
Inventor
Jun Aizawa
恂 相沢
Takao Shinohara
隆雄 篠原
Mitsumasa Tsunoda
光正 角田
Isamu Hirano
勇 平野
Kohei Minowa
幸平 三ノ輪
Hisao Tanaka
久雄 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP31855798A priority Critical patent/JP2974025B1/en
Application granted granted Critical
Publication of JP2974025B1 publication Critical patent/JP2974025B1/en
Publication of JP2000144892A publication Critical patent/JP2000144892A/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve workability by jacking up the pillars of a frame at every provision of an upper frame over one layer on a girder, and letting the girder bear the load of the upper frame. SOLUTION: In a structure having a well under a girder 1 of large span provided on an intermediate story, jacks 4 are provided between the gider 1 and pillars 21 to construct an upper frame 2. In this case, for example, after completing construction of the pillars 21 and the beams 22 of the whole frame 2, the pillars 21 of which the lower ends are connected to the girder 1 and not connected to the pillar 31 of a lower frame are jacked up at every construction of a slab from the lower layer side of the frame 2. At every placing of concrete of each story, a jack-up work of the pillars 21 is repeated until after placing the slab of the uppermost story so as to make zero the vertical displacement generated on the slab or the beam of the directly upper story of the girder 1. Hereby, the girder can bear the load of the upper frame, the burden of the beam of the upper frame can be reduced, and the obstacle for construction under the intermediate story can be eliminated.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は中間階より下に吹
抜けが形成される場合に、吹抜け上に架設される大スパ
ン大梁より上の上部架構の荷重を大スパン大梁に負担さ
せるように上部架構を施工する方法に関するものであ
る。
BACKGROUND OF THE INVENTION The present invention relates to an upper frame so that when an atrium is formed below a middle floor, a load of an upper frame above a large span girder installed on the atrium is applied to the large span girder. And a method of constructing the same.

【0002】[0002]

【従来の技術及び発明が解決しようとする課題】図7に
示すように中間階の下方に吹抜けが形成される構造物で
は、吹抜け上部の架構は、鉛直荷重により柱が軸力と曲
げモーメントを負担するフィーレンディール梁として設
計されることが多いが、設計が複雑になり、また上部架
構の梁の負担が大きくなることから、中間階に架設され
る大スパンの大梁の成を大きくし、その大梁に、その上
に接続する柱の軸力を流すことで上部架構の荷重の多く
を大梁に負担させ、上部架構の梁に負担させない設計を
することがある。
2. Description of the Related Art As shown in FIG. 7, in a structure in which a stairwell is formed below a middle floor, a frame above the stairwell has an axial force and a bending moment due to a vertical load. Although it is often designed as a fieldend beam that bears, the design becomes complicated and the load on the beam of the upper frame increases, so the size of the large span large beam installed on the intermediate floor is increased, In some cases, an axial force of a column connected to the girder is caused to flow through the girder so that much of the load on the upper frame is borne by the girder, but not by the upper frame.

【0003】この場合、大梁上に上部架構を通常通りに
構築すれば、上部架構の梁が柱に接続することで柱の軸
力の一部を負担する構造となるため、大スパンの大梁に
上部架構の荷重の多くを負担させることにならず、設計
の意図が反映されないことになる。
[0003] In this case, if the upper frame is constructed on the girder as usual, the beam of the upper frame is connected to the column so as to bear a part of the axial force of the column. Most of the load on the upper frame will not be borne, and the design intention will not be reflected.

【0004】そこで上部架構の施工に先立ち、図8に示
すように吹抜けの床と吹抜け上部の大梁との間にケーブ
ル9等を架設し、ケーブル9等を緊張することにより大
梁に下向きの変形を強制的に与えておき、上部架構の構
築終了まで変形量を維持させ、変形を残留させること
で、最終的に上部架構の荷重を大梁に負担させることが
行われる。
Therefore, prior to the construction of the upper frame, as shown in FIG. 8, a cable 9 or the like is erected between the floor of the stairwell and a girder above the stairwell, and a downward deformation of the girder is performed by tensioning the cable 9 or the like. By giving it forcibly, maintaining the amount of deformation until the completion of the construction of the upper frame, and leaving the deformation, the load of the upper frame is finally borne by the girder.

【0005】上部架構の施工は大梁に初期に与えた変形
量が維持されるよう、構築が終了した階までの上部架構
の荷重と緊張力の和が常に一定となるように緊張力を調
整しながら行われ、上部架構全体の完成と共に緊張力を
解除することにより、大梁に初期に与えた変形量を生じ
させるだけの上部架構の荷重を大梁に負担させることに
なる。
In the construction of the upper frame, the tension is adjusted so that the sum of the load and the tension of the upper frame up to the floor where the construction is completed is always constant, so that the amount of deformation initially applied to the girder is maintained. The tension is released together with the completion of the entire upper frame, so that the load on the upper frame that causes the amount of deformation initially applied to the girder is applied to the girder.

【0006】この方法では吹抜けの全高に亘る長さのケ
ーブルを必要とする上、その端部を定着するためのアン
カー等の定着装置とカウンターウェイト等の張力導入装
置等、大掛かりな設備を必要とするため、設備費が高く
なる。
In this method, a cable having a length corresponding to the entire height of the stairwell is required, and large-scale equipment such as a fixing device such as an anchor for fixing the end portion and a tension introducing device such as a counterweight is required. As a result, equipment costs increase.

【0007】また上部架構の構築終了までの間、ケーブ
ルが吹抜けの最下階から大梁までの区間に存在するた
め、大梁より下の下部架構の仕上げ工事等をする上で、
施工の障害になる等の不利がある。
[0007] Further, since the cable is present in the section from the lowest floor of the atrium to the girder until the completion of the construction of the upper frame, when finishing the lower frame below the girder, etc.,
There are disadvantages such as obstruction of construction.

【0008】この発明は上記背景より、上部架構の荷重
を大梁に負担させながら、ケーブルを用いる方法の問題
を解消する施工方法を提案するものである。
In view of the above background, the present invention proposes a construction method that solves the problem of the method using a cable while allowing the load on the upper frame to be applied to the girder.

【0009】[0009]

【課題を解決するための手段】本発明では大梁の架設
後、大梁上に立設される上部架構の柱と大梁との間にジ
ャッキを設置し、柱をジャッキに支持させた状態で大梁
上の1層分以上の架構の全体、もしくは架構の一部を構
築する毎に、柱をジャッキアップする作業を繰り返すこ
とにより、上部架構の荷重を大梁に負担させる状態を得
る。上部架構の架構は柱・梁のみの場合と、スラブ、も
しくはスラブと壁を含む場合がある。
According to the present invention, after the girder is erected, a jack is installed between the column of the upper frame standing on the girder and the girder, and the column is supported on the jack. The work of jacking up the columns is repeated every time the entire frame or a part of the frame of one layer or more is constructed, thereby obtaining a state in which the load of the upper frame is borne by the girder. The frame of the upper frame may include only columns and beams, or may include a slab or a slab and a wall.

【0010】上部架構の構築が進むに従い、図6−(a)
に示すように上部架構2の梁22は柱21に接続することで
架構の自重により下向きに撓み、柱21は軸方向に圧縮変
形することになるが、1層分以上の上部架構の全体や一
部を構築する毎に、上部架構2の梁22やスラブの撓みが
なくなるように大梁1に接続する柱21のジャッキアップ
を繰り返すことにより、上部架構2の全梁22やスラブは
水平に保たれる。
As the construction of the upper frame progresses, FIG.
As shown in the figure, by connecting the beam 22 of the upper frame 2 to the column 21, the beam 22 bends downward due to the weight of the frame, and the column 21 is compressed and deformed in the axial direction. Each time a part is constructed, the beam 22 of the upper frame 2 and the pillar 21 connected to the girder 1 are repeatedly jacked up so that the deflection of the slab is eliminated, so that all the beams 22 and the slab of the upper frame 2 are kept horizontal. Dripping.

【0011】一方、大梁1には柱21のジャッキアップに
よって反力としての柱21の軸力が作用するため、大梁1
は(b) に示すように下向きに撓もうとする。図6−(a)
のときは上部架構2の梁22と、大梁1の両端が接続する
柱の上部架構2部分が大梁1上に接続する柱21の軸力の
一部を負担した状態にあり、(b) のときにジャッキアッ
プ時の反力により柱21の軸力の多くを大梁1が負担し、
大梁1からその両端の柱に伝達された状態になる。大梁
1が柱21の軸力の多くを負担することにより上部架構2
の梁22の負担が解除、もしくは軽減される。
On the other hand, the axial force of the column 21 as a reaction force acts on the girder 1 by jacking up the column 21.
Tries to bend downward as shown in (b). Fig. 6- (a)
In the case of (b), the beam 22 of the upper frame 2 and the upper frame 2 of the column to which both ends of the girder 1 are connected bear part of the axial force of the column 21 connected to the girder 1, and Sometimes the girder 1 bears much of the axial force of the column 21 due to the reaction force when jacking up,
The state is transmitted from the girder 1 to the pillars at both ends. The girder 1 bears much of the axial force of the column 21 so that the upper frame 2
The load on the beam 22 is released or reduced.

【0012】図6では軸線が直線となるように大梁1を
製作しておき、大梁1が上部架構2の荷重を負担したと
きに下向きに撓みを生ずる場合を示しているが、軸線を
湾曲させ、予めむくりのある形で大梁1を製作してお
き、大梁1が上部架構2の荷重を負担したときに軸線が
水平となるようにする場合もある。最終的な大梁1の撓
み量が外壁等の仕上げに影響が出ない程度の大きさに納
まる場合は、前者の方法でも対応できる。
FIG. 6 shows a case where the girder 1 is manufactured so that the axis is straight, and the girder 1 bends downward when the load of the upper frame 2 is loaded. In some cases, the girder 1 may be manufactured in advance in a shape having a peeling so that the axis becomes horizontal when the girder 1 bears the load of the upper frame 2. If the final deflection of the girder 1 is small enough not to affect the finish of the outer wall or the like, the former method can be used.

【0013】大梁の撓み量は上部架構が上階に向かって
順次構築され、柱がジャッキアップされる毎に加算さ
れ、最終的にはケーブルを用いて大梁を変形させた状態
で上部架構を構築する場合と同様に、大梁にその合計の
撓み量を生じさせるだけの上部架構の荷重を大梁に負担
させることになる。
The amount of deflection of the girder is sequentially added to the upper frame toward the upper floor, and is added each time a pillar is jacked up. Finally, the upper frame is constructed in a state where the girder is deformed using a cable. In the same manner as in the above case, the load on the upper frame that causes the total deflection of the girder is applied to the girder.

【0014】この結果、上部架構の梁が柱の軸力の一部
を負担することがなくなる、あるいは梁の負担が軽減さ
れるため、上部架構の梁の負担を小さくし、また柱に鉛
直荷重により曲げモーメントを作用させない設計意図が
反映される。
As a result, the beam of the upper frame does not bear a part of the axial force of the column, or the load of the beam is reduced, so that the load of the beam of the upper frame is reduced and the vertical load is applied to the column. This reflects the design intent that no bending moment is applied.

【0015】大梁に上部架構全体の荷重を負担させる作
業が大梁上に設置されるジャッキのみによって行えるこ
とで、ケーブルを用いる場合より設備数が少なくて済
み、経費が削減される。
Since the work of applying the load of the entire upper frame to the girder can be performed only by the jacks installed on the girder, the number of facilities can be reduced as compared with the case of using cables, and the cost can be reduced.

【0016】またジャッキの設置によって吹抜けが塞が
れることがないため、中間階以下での施工の障害がなく
なり、施工性が向上する。上部架構の階数が多く、上部
架構の柱の軸方向の変形量が大きくなる場合は、請求項
2に記載のようにジャッキアップをする階を複数に分散
させることで、柱の圧縮変形分の上部架構への影響を小
さくすることができ、ジャッキの能力も軽減される。
[0016] Further, since the installation of the jack does not block the atrium, there is no obstruction to the construction at the middle floor or lower, and the workability is improved. When the number of floors of the upper frame is large and the amount of deformation of the columns of the upper frame in the axial direction is large, the number of floors to be jacked up is dispersed into a plurality of floors as described in claim 2, so that the compression deformation of the columns is reduced. The effect on the upper frame can be reduced, and the ability of the jack is also reduced.

【0017】この場合、1層分、もしくは複数層分の上
部架構の構築と共に、上部架構のいずれかの梁とその上
に立設される柱との間にジャッキを設置し、柱をジャッ
キに支持させた状態で前記梁上の1層分以上の架構の全
体、もしくは架構の一部を構築する毎に、柱をジャッキ
アップする作業が繰り返される。この上部架構の梁上で
のジャッキアップは大梁上でのジャッキアップと並行し
て行われる。
In this case, together with the construction of the upper frame for one layer or a plurality of layers, a jack is installed between any of the beams of the upper frame and the pillar erected thereon, and the pillar is connected to the jack. The operation of jacking up the pillars is repeated every time the whole frame or a part of the frame of one or more layers on the beam is constructed while being supported. The jack-up on the beam of the upper frame is performed in parallel with the jack-up on the girder.

【0018】構造物の架構が鉄骨造や鉄骨鉄筋コンクリ
ート造の場合で、上部架構全体の鉄骨の建方を先行させ
る場合は、請求項3に記載のように大梁の架設後、上部
架構全体の構築と共に、大梁とそれに接続する柱との間
にジャッキを設置し、柱をジャッキに支持させた状態
で、上部架構の床版を下層側から敷設する、あるいはス
ラブのコンクリートを下層側から打設する等、スラブを
下層側から構築する毎に、柱をジャッキアップする作業
が繰り返される。
In the case where the frame of the structure is a steel frame or a steel reinforced concrete structure, and when the construction of the steel frame of the entire upper frame is to be preceded, the entire upper frame is constructed after the erection of the girder. At the same time, a jack is installed between the girder and the pillar connected to it, and with the pillar supported by the jack, the floor slab of the upper frame is laid from the lower side, or concrete of the slab is poured from the lower side Each time a slab is constructed from the lower side, the operation of jacking up the pillar is repeated.

【0019】この場合も上部架構の階数が多く、上部架
構の柱の軸方向の変形量が大きくなる場合は、請求項4
に記載のように大梁上のジャッキに加え、上部架構全体
の構築と共に、上部架構のいずれかの梁とそれに接続す
る柱との間にジャッキを設置し、柱をジャッキに支持さ
せた状態で、梁上のスラブを下層側から構築する毎に、
柱をジャッキアップする作業が繰り返される。
Also in this case, in the case where the number of floors of the upper frame is large and the amount of deformation of the columns of the upper frame in the axial direction is large, claim 4
In addition to the jack on the girder as described in the above, with the construction of the entire upper frame, with a jack installed between any of the beams of the upper frame and the pillar connected to it, the jack was supported by the jack, Each time the slab on the beam is built from the bottom,
The work of jacking up the pillar is repeated.

【0020】[0020]

【発明の実施の形態】この発明は図7に示すような、中
間階に架設される大スパンの大梁1の下に吹抜けが形成
される構造物において、大梁1より上方に構築される上
部架構2を、大梁1上に設置されるジャッキ4を用いて
上部架構2の鉛直荷重を大梁1に負担させるように施工
する方法である。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an upper frame constructed above a girder 1 in a structure as shown in FIG. 2 is a method in which a vertical load of the upper frame 2 is applied to the girder 1 by using a jack 4 installed on the girder 1.

【0021】図面では大梁1が架設される中間階までの
下部架構3が鉄骨鉄筋コンクリート造で、大梁1と上部
架構2が鉄骨造である場合を示すが、下部架構3と上部
架構2及び大梁1の構造種別は問われない。
The drawing shows a case where the lower frame 3 up to the intermediate floor where the girder 1 is installed is made of steel-framed reinforced concrete, and the girder 1 and the upper frame 2 are made of steel, but the lower frame 3, the upper frame 2 and the girder 1 Does not matter.

【0022】図7、及びその詳細図である図2では下部
架構3全体の構築と下部架構3へのコンクリートの打設
と、大梁1の架設が終了し、上部架構2全体の柱21と梁
22の構築が終了した段階で、コンクリートの打設等によ
り上部架構2の下層側からスラブ24を構築する毎に、柱
21をジャッキアップする場合を示しているが、下部架構
3全体の構築、及び下部架構3へのコンクリートの打設
と、大梁1の架設が終了した後に、上部架構2の柱21と
梁22を下層側から構築すると共に、コンクリートの打設
等によりスラブ24を構築する毎に、柱21をジャッキアッ
プする場合もある。
In FIG. 7 and FIG. 2 which is a detailed view thereof, the construction of the entire lower frame 3, the casting of concrete on the lower frame 3, and the erection of the girder 1 are completed, and the columns 21 and beams of the entire upper frame 2 are completed.
When the construction of the slab 24 is completed, every time the slab 24 is constructed from the lower layer side of the upper frame 2 by casting concrete,
The case where the jack 21 is jacked up is shown. After the construction of the lower frame 3 as a whole, the casting of concrete into the lower frame 3 and the erection of the girder 1 are completed, the columns 21 and beams 22 of the upper frame 2 are The column 21 may be jacked up each time the slab 24 is constructed by casting concrete or the like while being constructed from the lower layer side.

【0023】構造物の架構が鉄骨造の場合は、下部架構
3全体の構築と大梁1の架設が終了した後、上部架構2
の柱21と梁22を下層側から構築すると共に、床版を敷設
する毎に、柱21をジャッキアップするか、図7と同様に
上部架構2全体の柱21と梁22の構築まで終了した後、下
層側から床版を敷設する毎に、柱21をジャッキアップす
ることになる。
When the frame of the structure is a steel frame, after the construction of the entire lower frame 3 and the erection of the girder 1 are completed, the upper frame 2
The columns 21 and beams 22 were constructed from the lower layer side, and every time the floor slab was laid, the columns 21 were jacked up or the construction of the columns 21 and beams 22 of the entire upper frame 2 was completed as in FIG. Thereafter, every time a floor slab is laid from the lower side, the pillar 21 is jacked up.

【0024】鉄筋コンクリート造の場合も、下部架構3
全体の構築と大梁1の架設が終了した後、上部架構2の
柱21と梁22の構築と共に、床版の敷設やコンクリートの
打設によりスラブ24を下層側から構築する毎に、柱21を
ジャッキアップするか、下部架構3全体の構築と大梁1
の架設、及び上部架構2全体の柱21と梁22の構築が終了
した後に、床版の敷設やコンクリートの打設によりスラ
ブ24を下層側から構築する毎に、柱21をジャッキアップ
することになる。
In the case of reinforced concrete, the lower frame 3
After the entire construction and the erection of the girder 1 are completed, each time the slab 24 is constructed from the lower side by laying the floor slab or casting concrete together with the construction of the columns 21 and the beams 22 of the upper frame 2, Jack up or build the entire lower frame 3 and girder 1
After the completion of the erection and the construction of the pillars 21 and the beams 22 of the entire upper frame 2, the pillars 21 are jacked up every time the slab 24 is constructed from the lower layer side by laying a floor slab or placing concrete. Become.

【0025】図1,図2,図7は前記の通り、大梁1が
架設される中間階までの鉄骨鉄筋コンクリート造躯体が
完成し、上部架構2全体の柱21と梁22の建方が完了した
状態を示すが、上部架構2は大梁1とその上に接続する
柱21との間にジャッキ4を設置した状態で構築される。
FIGS. 1, 2 and 7 show that, as described above, the steel reinforced concrete frame up to the intermediate floor where the girder 1 is erected is completed, and the columns 21 and beams 22 of the entire upper frame 2 have been erected. As shown, the upper frame 2 is constructed with a jack 4 installed between the girder 1 and a pillar 21 connected thereto.

【0026】この場合、柱21をジャッキ4に支持させた
状態で、上部架構2のスラブ24のコンクリートを下層側
から打設する毎に、柱21をジャッキアップする作業が繰
り返される。ジャッキアップは下端が大梁1に接続し、
下部架構3の柱31に接続しない柱21に対して行われる。
In this case, the operation of jacking up the column 21 is repeated every time the concrete of the slab 24 of the upper frame 2 is driven from the lower side while the column 21 is supported by the jack 4. The jack up is connected to the girder 1 at the lower end,
This is performed for the pillar 21 that is not connected to the pillar 31 of the lower frame 3.

【0027】ジャッキ4は図1〜図3に示すように大梁
1の架設後、上部架構2の柱21の立設位置の脇に設置さ
れる。図4、図5は図2のそれぞれA部、B部の詳細を
示す。図3では各柱21の軸力に応じて大荷重用のジャッ
キ4と小荷重用のジャッキ4を交互に配列させている。
図3〜図5中、5は大梁1が鉄骨である場合のフランジ
を補剛するスチフナを示す。
As shown in FIGS. 1 to 3, the jack 4 is installed beside the column 21 of the upper frame 2 after the bridge 1 is erected. FIGS. 4 and 5 show the details of the portions A and B in FIG. 2, respectively. In FIG. 3, jacks 4 for large loads and jacks 4 for small loads are alternately arranged according to the axial force of each column 21.
3 to 5, reference numeral 5 denotes a stiffener for stiffening the flange when the girder 1 is a steel frame.

【0028】ジャッキ4で直接支持される柱21の下端部
の側面にはジャッキ4の軸力を受ける反力受けブラケッ
ト6が突設され、この反力受けブラケット6と大梁1と
の間にジャッキ4が設置される。ジャッキ4は大梁1上
に設置される束柱25の上に設置される。
A reaction force receiving bracket 6 for receiving the axial force of the jack 4 protrudes from a side surface of a lower end portion of the column 21 directly supported by the jack 4, and a jack is provided between the reaction force receiving bracket 6 and the beam 1. 4 is installed. The jack 4 is installed on a bundle 25 installed on the girder 1.

【0029】柱21の下端と大梁1との間には柱21をジャ
ッキアップし終えるまでの間、柱21を支持する調整柱23
が設置され、施工中の安全性確保のために、調整柱23は
スプライスプレート7によって柱21に接続される。スプ
ライスプレート7の、柱21に接合される側、もしくは調
整柱23に接合される側のいずれかのボルト孔7aは柱21の
全ジャッキアップ量を見込み、長孔状に形成される。長
孔状のボルト孔7aを挿通しているボルト8は柱21の最終
のジャッキアップ後に本締めされるか、またはスプライ
スプレート7を、ボルト孔が長孔でないスプライスプレ
ートに交換した後に本締めされる。
An adjusting column 23 for supporting the column 21 between the lower end of the column 21 and the girder 1 until the column 21 is completely jacked up.
Is installed, and the adjustment column 23 is connected to the column 21 by the splice plate 7 to ensure safety during construction. The bolt hole 7a on either side of the splice plate 7 that is joined to the column 21 or the side that is joined to the adjustment column 23 is formed in a long hole shape in consideration of the total jack-up amount of the column 21. The bolt 8 inserted through the elongated bolt hole 7a is fully tightened after the final jack-up of the column 21, or after the splice plate 7 is replaced with a splice plate having a bolt hole that is not an elongated hole. You.

【0030】柱21が鉄骨造の場合と鉄筋コンクリート造
の場合にも柱21の側面に反力受けブラケット6が突設さ
れ、大梁1と柱21との間に調整柱23が設置される。鉄筋
コンクリート造の場合には柱21の最終のジャッキアップ
後、調整柱23は撤去され、その部分では柱21の主筋と大
梁1から突出する鉄筋の継手が行われ、コンクリートが
打設される。調整柱23を設置した部分における柱21と大
梁1の接続方法は柱21と大梁1の構造種別に応じて任意
に選択される。
When the column 21 is made of steel frame or reinforced concrete, the reaction force receiving bracket 6 protrudes from the side surface of the column 21, and the adjusting column 23 is installed between the girder 1 and the column 21. In the case of the reinforced concrete structure, after the final jack-up of the column 21, the adjusting column 23 is removed, and at that portion, the joint between the main reinforcing bar of the column 21 and the reinforcing bar projecting from the girder 1 is performed, and concrete is poured. The connection method between the column 21 and the girder 1 in the portion where the adjustment column 23 is installed is arbitrarily selected according to the structural type of the column 21 and the girder 1.

【0031】調整柱23は柱21の最終のジャッキアップが
終了した後に柱21の下に設置される場合もあり、その場
合、柱21のジャッキアップ後、その下に調整柱23を差し
込み、両者間にスプライスプレート7を渡し、ボルト8
の本締めを行った後、ジャッキ4の軸力が解除される。
The adjusting column 23 may be installed below the column 21 after the final jack-up of the column 21 is completed. In this case, after the column 21 is jacked up, the adjusting column 23 is inserted under the column, and the adjusting column 23 is inserted. Pass the splice plate 7 between the bolts 8
After the final tightening, the axial force of the jack 4 is released.

【0032】上部架構2全体の柱21と梁22の建方が完了
した後、大梁1の直上階のスラブ24のコンクリート、ま
たはスラブ24と共に柱21の、もしくは柱21と梁22等のコ
ンクリートが打設される。大梁1の直上階のコンクリー
トの打設によってスラブ24や梁22に鉛直変位が生ずるこ
とになるが、変位の発生後、鉛直変位が0となるように
柱21がジャッキアップされる。ジャッキアップはスプラ
イスプレート7の柱21側と調整柱23側のいずれかの、長
孔状のボルト孔7aを挿通しているボルト8を緩めた状態
で行われる。
After the construction of the columns 21 and the beams 22 of the entire upper frame 2 is completed, the concrete of the slab 24 immediately above the girder 1 or the concrete of the columns 21 or the columns 21 and the beams 22 together with the slab 24 is removed. It is cast. Vertical displacement of the slab 24 and the beam 22 is caused by placing concrete on the floor directly above the girder 1. After the displacement occurs, the column 21 is jacked up so that the vertical displacement becomes zero. The jack-up is performed in a state where the bolt 8 inserted into the elongated bolt hole 7a on either the column 21 side or the adjustment column 23 side of the splice plate 7 is loosened.

【0033】続いて更にその上の階のコンクリートを打
設した後、その階のコンクリートの打設によって大梁1
の直上階のスラブ24や梁22に生じた鉛直変位が0になる
まで柱21がジャッキアップされる。
Subsequently, after the concrete on the upper floor is further poured, the girders 1 are cast by the concrete on the floor.
The column 21 is jacked up until the vertical displacement generated in the slab 24 and the beam 22 immediately above the floor becomes zero.

【0034】以下同様に各階のコンクリートを打設する
毎に、大梁1の直上階のスラブ24や梁22に生じた鉛直変
位が0になるまで柱21をジャッキアップする作業が最上
階のコンクリートの打設後まで繰り返される。
Similarly, every time concrete on each floor is cast, the work of jacking up the column 21 until the vertical displacement generated on the slab 24 or the beam 22 immediately above the girder 1 becomes zero is performed on the concrete on the top floor. It is repeated until after casting.

【0035】最上階のコンクリートの打設後のジャッキ
アップが終了した後、大梁1上の調整柱23とその直上の
柱21を接合するスプライスプレート7の長孔状のボルト
孔7aを挿通しているボルト8を本締めし、柱21が負担し
ている荷重を調整柱23を通じて大梁1に負担させた後、
ジャッキ4の軸力を解除し、施工が終了する。
After the jacking-up after the concrete on the top floor has been completed, the adjusting column 23 on the girder 1 and the column 21 immediately above the adjusting column 23 are inserted through the elongated bolt holes 7a of the splice plate 7 to join them. After the bolts 8 are fully tightened and the load borne by the column 21 is borne by the girder 1 through the adjustment columns 23,
The axial force of the jack 4 is released, and the construction is completed.

【0036】上部架構2の階数が多い場合は、上部架構
2全体の構築と共に、上部架構2のいずれかの梁22とそ
れに接続する柱21との間にジャッキ4を設置し、柱21を
ジャッキ4に支持させた状態で、梁22上のスラブ24を下
層側から構築する毎に、柱21をジャッキアップする作業
が大梁1上でのジャッキアップと並行して繰り返され
る。
When the number of floors of the upper frame 2 is large, the jack 4 is installed between any of the beams 22 of the upper frame 2 and the pillars 21 connected thereto, and the pillars 21 are jacked. When the slab 24 on the beam 22 is constructed from the lower layer while being supported by the beam 4, the operation of jacking up the column 21 is repeated in parallel with the jacking up on the girder 1.

【0037】その場合はジャッキ4に支持される柱21に
反力受けブラケット6が突設され、柱21と梁22間に調整
柱23が設置される。
In this case, the reaction force receiving bracket 6 is protruded from the column 21 supported by the jack 4, and the adjusting column 23 is installed between the column 21 and the beam 22.

【0038】[0038]

【発明の効果】請求項1では大梁上に立設される上部架
構の柱と大梁との間にジャッキを設置し、柱をジャッキ
に支持させた状態で大梁上の上部架構を構築する毎に、
柱のジャッキアップを繰り返すことで、請求項3では上
部架構の構築後、上部架構のスラブを構築する毎に、柱
のジャッキアップを繰り返すことで、ジャッキアップ時
の反力としての柱の軸力を大梁に作用させ、大梁に撓み
を生じさせるため、最終的に大梁にその合計の撓み量を
生じさせるだけの上部架構の荷重を大梁に負担させるこ
とができる。
According to the first aspect of the present invention, a jack is installed between the pillar of the upper frame standing on the girder and the girder, and each time the upper frame on the girder is constructed with the column supported by the jack. ,
The axial force of the pillar as a reaction force at the time of jacking-up by repeating jacking-up of the pillar and repeating the jacking-up of the pillar every time the slab of the upper frame is constructed after the construction of the upper frame according to claim 3, by repeating the jacking-up of the pillar. Is applied to the girder to cause the girder to bend, so that the girder can bear the load of the upper frame that finally causes the girder to have the total amount of bending.

【0039】この結果、上部架構の梁が柱の軸力の一部
を負担することがなくなる、あるいは梁の負担が軽減さ
れ、上部架構の梁の負担を小さくし、フィーレンディー
ル効果を期待しないという設計意図が反映される。
As a result, the beam of the upper frame does not bear a part of the axial force of the column, or the load on the beam is reduced, the load on the beam of the upper frame is reduced, and no expectation of the Feerendiel effect is expected. Is reflected.

【0040】大梁に上部架構全体の荷重を負担させる作
業が大梁上に設置されるジャッキのみによって行えるこ
とで、ケーブルを用いる場合より設備数が少なくて済
み、経費が削減される。
Since the work of applying the load of the entire upper frame to the girder can be performed only by the jacks installed on the girder, the number of facilities can be reduced as compared with the case of using cables, and the cost can be reduced.

【0041】またジャッキの設置によって吹抜けが塞が
れることがないため、中間階以下での施工の障害がなく
なり、施工性が向上する。請求項2、請求項4ではジャ
ッキアップをする階を複数に分散させるため、上部架構
の階数が多く、上部架構の柱の軸方向の変形量が大きく
なる場合にも、柱の圧縮変形分の上部架構の上昇を容易
に行うことができ、ジャッキの能力も軽減される。
Also, since the installation of the jack does not block the stairwell, there is no obstacle to the construction at the middle floor or lower, and the workability is improved. In claim 2 and claim 4, since the floors for jacking up are dispersed into a plurality of floors, even when the number of floors of the upper frame is large and the amount of deformation of the columns of the upper frame in the axial direction is large, the compression deformation of the columns is also small. The upper frame can be easily raised, and the capacity of the jack is reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】大梁と上部架構の柱間にジャッキを設置した様
子を示した立面図である。
FIG. 1 is an elevational view showing a state where a jack is installed between a girder and a column of an upper frame.

【図2】図7の構造物の大梁上にジャッキを設置した様
子を示した立面図である。
FIG. 2 is an elevational view showing a state where a jack is installed on a girder of the structure of FIG. 7;

【図3】図2の平面図である。FIG. 3 is a plan view of FIG. 2;

【図4】(a) は図2のA部の詳細図、(b) は(a) のx−
x線断面図である。
4 (a) is a detailed view of a part A in FIG. 2, and FIG. 4 (b) is an x-
It is an x-ray sectional view.

【図5】(a) は図2のB部の詳細図、(b) は(a) のy−
y線断面図である。
5 (a) is a detailed view of a portion B in FIG. 2, and FIG.
FIG. 3 is a sectional view taken along line y.

【図6】(a) は上部架構の梁が柱の軸力を負担している
ときの様子を示した概略図、(b) は柱の軸力を大梁が負
担したときの様子を示した概略図である。
FIG. 6 (a) is a schematic diagram showing a state in which the beam of the upper frame bears the axial force of the column, and FIG. 6 (b) shows a state in which the girder bears the axial force of the column. It is a schematic diagram.

【図7】大梁の下に吹抜けが形成される構造物を示した
立面図である。
FIG. 7 is an elevation view showing a structure in which a stairwell is formed under a girder.

【図8】ケーブルを用いて大梁に強制変形を加える従来
方法を示した立面図である。
FIG. 8 is an elevation view showing a conventional method of forcibly deforming a girder using a cable.

【符号の説明】[Explanation of symbols]

1……大梁、2……上部架構、21……柱、22……梁、23
……調整柱、24……スラブ、25……束柱、3……下部架
構、31……柱、4……ジャッキ、5……スチフナ、6…
…反力受けブラケット、7……スプライスプレート、7a
……ボルト孔、8……ボルト、9……ケーブル。
1 ... giant beam, 2 ... upper frame, 21 ... pillar, 22 ... beam, 23
...... Adjustment column, 24 ... Slab, 25 ... Bundle column, 3 ... Lower frame, 31 ... Column, 4 ... Jack, 5 ... Stiffener, 6 ...
… Reaction force receiving bracket, 7 …… Splice plate, 7a
... bolt holes, 8 ... bolts, 9 ... cables.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 角田 光正 神奈川県横浜市中区太田町4丁目51番地 鹿島建設株式会社横浜支店内 (72)発明者 平野 勇 神奈川県横浜市中区太田町4丁目51番地 鹿島建設株式会社横浜支店内 (72)発明者 三ノ輪 幸平 神奈川県横浜市中区太田町4丁目51番地 鹿島建設株式会社横浜支店内 (72)発明者 田中 久雄 神奈川県横浜市中区太田町4丁目51番地 鹿島建設株式会社横浜支店内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Mitsumasa Tsunoda 4-51 Otacho, Naka-ku, Yokohama-shi, Kanagawa Prefecture Within the Yokohama Branch of Kashima Construction Co., Ltd. (72) Isamu Hirano 4-chome Otacho, Naka-ku, Yokohama-shi, Kanagawa Prefecture 51 Kashima Construction Co., Ltd. in Yokohama Branch (72) Inventor Kohei Minowa 4-51 Otacho, Naka-ku, Yokohama-shi, Kanagawa Prefecture Kashima Construction Co., Ltd. in Yokohama Branch (72) Inventor Hisao Tanaka Otacho, Naka-ku, Yokohama-shi, Kanagawa 4-51, Kashima Construction Co., Ltd. Yokohama Branch

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 中間階に架設される大スパンの大梁の下
に吹抜けが形成される構造物において、前記大梁より上
方に構築される上部架構を施工する方法であり、大梁の
架設後、大梁上に立設される上部架構の柱と大梁との間
にジャッキを設置し、柱をジャッキに支持させた状態で
大梁上の1層分以上の架構の全体、もしくは架構の一部
を構築する毎に、柱をジャッキアップする作業を繰り返
す大スパン大梁上部架構の施工方法。
1. A method for constructing an upper frame constructed above a girder in a structure in which a stairwell is formed below a girder of a large span installed on an intermediate floor, comprising: A jack is installed between the pillar and the girder of the upper frame that is erected on the top, and the entire frame or a part of the frame of at least one layer on the girder is constructed with the pillar supported by the jack. A method of constructing a large span large beam upper frame that repeats jacking up columns every time.
【請求項2】 1層分、もしくは複数層分の上部架構の
構築と共に、上部架構のいずれかの梁とその上に立設さ
れる柱との間にジャッキを設置し、柱をジャッキに支持
させた状態で前記梁上の1層分以上の架構の全体、もし
くは架構の一部を構築する毎に、柱をジャッキアップす
る作業を繰り返す請求項1記載の大スパン大梁上部架構
の施工方法。
2. A single-layer or multiple-layer upper frame is constructed, and a jack is installed between any of the beams of the upper frame and a column erected thereon, and the column is supported by the jack. 2. The method for constructing a large span large beam upper frame according to claim 1, wherein the work of jacking up the pillars is repeated every time the entire frame of one or more layers on the beam or a part of the frame is constructed in the state in which the beams are made.
【請求項3】 中間階に架設される大スパンの大梁の下
に吹抜けが形成される構造物において、前記大梁より上
方に構築される上部架構を施工する方法であり、大梁の
架設後、上部架構全体の構築と共に、大梁とその上に接
続する上部架構の柱との間にジャッキを設置し、柱をジ
ャッキに支持させた状態で、上部架構のスラブを下層側
から構築する毎に、柱をジャッキアップする作業を繰り
返す大スパン大梁上部架構の施工方法。
3. A method for constructing an upper frame constructed above a girder in a structure in which a stairwell is formed under a large span girder constructed on an intermediate floor. With the construction of the entire frame, a jack was installed between the girder and the pillar of the upper frame connected to it, and with the pillar supported by the jack, every time the slab of the upper frame was constructed from the lower layer, Construction method of large span large beam upper frame that repeats jacking up work.
【請求項4】 上部架構全体の構築と共に、上部架構の
いずれかの梁とそれに接続する柱との間にジャッキを設
置し、柱をジャッキに支持させた状態で、前記梁上のス
ラブを下層側から構築する毎に、柱をジャッキアップす
る作業を繰り返す請求項3記載の大スパン大梁上部架構
の施工方法。
4. When the entire upper frame is constructed, a jack is installed between one of the beams of the upper frame and a column connected to the beam, and the slab on the beam is placed in a lower layer while the column is supported by the jack. The method according to claim 3, wherein the work of jacking up the columns is repeated every time the building is constructed from the side.
JP31855798A 1998-11-10 1998-11-10 Construction method of large span large beam upper frame Expired - Fee Related JP2974025B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP31855798A JP2974025B1 (en) 1998-11-10 1998-11-10 Construction method of large span large beam upper frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP31855798A JP2974025B1 (en) 1998-11-10 1998-11-10 Construction method of large span large beam upper frame

Publications (2)

Publication Number Publication Date
JP2974025B1 JP2974025B1 (en) 1999-11-08
JP2000144892A true JP2000144892A (en) 2000-05-26

Family

ID=18100468

Family Applications (1)

Application Number Title Priority Date Filing Date
JP31855798A Expired - Fee Related JP2974025B1 (en) 1998-11-10 1998-11-10 Construction method of large span large beam upper frame

Country Status (1)

Country Link
JP (1) JP2974025B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019190073A (en) * 2018-04-20 2019-10-31 大成建設株式会社 Construction method of structure
JP2021063354A (en) * 2019-10-11 2021-04-22 株式会社日立プラントサービス Dust remover and installation method thereof

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7005262B2 (en) * 2017-10-11 2022-02-10 大成建設株式会社 How to build a building
CN112267556B (en) * 2020-10-10 2022-05-17 广东省构建工程建设有限公司 Large-span steel structure corridor assembling construction process for narrow space

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019190073A (en) * 2018-04-20 2019-10-31 大成建設株式会社 Construction method of structure
JP7169765B2 (en) 2018-04-20 2022-11-11 大成建設株式会社 How to build structures
JP2021063354A (en) * 2019-10-11 2021-04-22 株式会社日立プラントサービス Dust remover and installation method thereof

Also Published As

Publication number Publication date
JP2974025B1 (en) 1999-11-08

Similar Documents

Publication Publication Date Title
AU2015246120B2 (en) Open web composite shear connector construction
CN100365229C (en) Constructing the large-span self-braced buildings of composite load-bearing wall-panels and floors
US8161691B2 (en) Precast composite structural floor system
US6298617B1 (en) High rise building system using steel wall panels
US8234827B1 (en) Express framing building construction system
CA2358747C (en) Ring beam/lintel system
JP2001525022A (en) Composite column of steel and concrete
CN102619331B (en) Once molding construction method of beam-type conversion layer of high-rise building by steel pipe supporting and laminated pouring
CN107882328B (en) Construction method of large-span steel truss suspension structure
JP3638571B2 (en) Support load transfer method for existing buildings
JP2974025B1 (en) Construction method of large span large beam upper frame
JP3877995B2 (en) How to build a string string bridge
JPS63147032A (en) Construction having tensile string beam floor structure
EP1181423B1 (en) Inner stairs for building and method of constructing it
JP2934668B2 (en) Beam structure
JP7169765B2 (en) How to build structures
JP3116767B2 (en) Existing building seismic isolation structuring method
JP2852626B2 (en) Construction method of slab using arch slab plate
JP3407164B2 (en) Frame structure
JP2916585B2 (en) Construction method of building
JP3020343B2 (en) Column base structure using hollow tube and method of constructing the same
CN114703986B (en) Casting method of shear wall of high-rise stairwell
JP2004270377A (en) Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same
CN216713527U (en) Assembled plane superstructure
JP3187618B2 (en) How to assemble beam reinforcement

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990803

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110903

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110903

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140903

Year of fee payment: 15

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees