JP2000060031A - Supplied power leveling system - Google Patents

Supplied power leveling system

Info

Publication number
JP2000060031A
JP2000060031A JP25591898A JP25591898A JP2000060031A JP 2000060031 A JP2000060031 A JP 2000060031A JP 25591898 A JP25591898 A JP 25591898A JP 25591898 A JP25591898 A JP 25591898A JP 2000060031 A JP2000060031 A JP 2000060031A
Authority
JP
Japan
Prior art keywords
data
incentive
power
electronic
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP25591898A
Other languages
Japanese (ja)
Inventor
Takeshi Rokuroda
長支 六呂田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP25591898A priority Critical patent/JP2000060031A/en
Publication of JP2000060031A publication Critical patent/JP2000060031A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S50/00Market activities related to the operation of systems integrating technologies related to power network operation or related to communication or information technologies
    • Y04S50/12Billing, invoicing, buying or selling transactions or other related activities, e.g. cost or usage evaluation

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To level supplied power by providing a program setting section, an incentive correcting section, and an incentive data generating section on the supplier side, and a program setting section, a manual operating section, and an arithmetic and control section on the user side, and supplying the data about electric power using facilities. SOLUTION: The organization of a program setting section 12 on a supplier side 1 sets a framework for automatically generating electronic incentive data from the data 16 about electric power supplying facilities based on contract data 11 and develops software. An incentive data generating section 14 generates electronic incentive data by processing the data 16 about electric power supplying facilities in accordance with the program of the program setting section 12. An arithmetic and control section 24 generates control signals for a facility 25 using electric power by computing transmitted electronic incentive data and the data A26 about the facility 25 when the program of the program setting section 22 is installed. Therefore, the effective leveling of supplied power is instrumentally achieved.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】 本発明は、電力供給者(一
般的には電力会社をいう)と電力使用者(一般的には電
力需要家という)とが電力の供給契約に従って電力の供
給を行う(電力の供給を受ける)ことになっているシス
テム(=電力供給システム)において、電力供給者側の
電力供給設備の利用率を高めあるいは電力供給の信頼性
を高めるなどの目的で行う〔供給電力/供給設備負荷率
等〕を平準化するためのシステムに関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an electric power supplier (generally, an electric power company) and an electric power user (generally, an electric power customer) supplying electric power according to an electric power supply contract. In a system that is supposed to receive power supply (= power supply system), this is performed for the purpose of increasing the utilization rate of power supply facilities on the power supplier side or improving the reliability of power supply [supply power / Supplying equipment load factor etc.].

【0002】[0002]

【従来の技術】 日本の電力供給者が現在採用している
供給電力平準化手法は、電力使用者あてにインセンティ
ブ対象メニューを定めて、すなわち、a.特定の期間
(夏期とか夜間とか)を定めて/b.特定の電力使用設
備(蓄熱方式設備など)を定めて、メニュー個々に対す
るインセンティブ(特別単価、割引・割り増し率、報償
金、反則金等)を設定していた。(インセンティブは書
面(契約を構成する文書)の中で規定されており、イン
センティブの程度は印刷文字で表示される固定的定数的
なものであった。すなわち、従来形のインセンティブ
は、日々刻々変化する情勢に追随できるものではなかっ
た。この結果、インセンティブの与え方(インセンティ
ブ適用の時間帯及びインセンティブの程度)が適切でな
かったとしてもそのことが判明するには時間が掛かり、
インセンティブを臨機応変に変化させることはできなか
った。)
2. Description of the Related Art The power supply leveling method currently employed by Japanese power suppliers defines an incentive target menu for power users, that is, a. Define a specific period (summer or night) / b. Specific power use equipment (heat storage equipment, etc.) was defined, and incentives (special unit price, discount / surcharge rate, remuneration, penalty, etc.) for each menu were set. (The incentive was specified in a written document (the document that constitutes the contract), and the degree of incentive was a fixed and constant one displayed in printed characters. As a result, even if the method of incentive provision (time of incentive application and degree of incentive) is not appropriate, it takes time to find out,
Incentives could not be changed on the fly. )

【0003】そして、電力料金を算定するため電力使用
者側に設置の電力計量装置(本明細書では「受電電力明
細記録部」という)は、多くの場合複数個設置する必要
があった。(理由:多くの場合、契約が電力使用設備一
本としてなされるのではなく、電力使用設備を構成して
いる特定の設備(例えば、蓄熱設備)に対してもなされ
ているため、計量装置の設置個所が複数となってい
た。)
In many cases, it is necessary to install a plurality of power metering devices (hereinafter referred to as “received power detail recording unit”) installed on the power user side in order to calculate a power rate. (Reason: In many cases, contracts are not made for a single power-using facility, but for specific facilities (for example, thermal storage facilities) that make up the power-using facility. There were multiple installation locations.)

【0004】[0004]

【発明が解決しようとする課題】 経済主導型社会で
は、電力供給システム(電力供給者側の電力供給システ
ムと電力使用者側の電力使用システムとからなるシステ
ム)も経済システムの下に位置づけられている。経済は
人間心理で駆動される。そこで、課題とするところは;
「電力供給者側の意図する程度の供給電力の平準化」が
機動的に達成されるようにすることである。具体的に
は、電力供給者側が、電力供給者側と電力使用者側との
利害が一致するような働き掛け−−この働き掛けをコン
ピュータ処理できる形にデータ化したものを本明細書で
は「電子インセンティブデータ」と表現している−−を
電力供給者側であらかじめ設定してあるプログラムによ
り自動的に発生させ、これを電力使用者側に伝達するよ
うにする。電力使用者側では;〔自動モード〕の場合あ
らかじめ設定してあるプログラムに従って伝達された
「電子インセンティブデータ」を自動的に処理しかつ電
力使用設備を制御させるようにする。〔手動モード〕の
場合「電子インセンティブデータ」の内容をモニターし
手動操作により電力使用設備を制御できるようにする。
そして、付随して解決する課題は、本発明によるシステ
ムに対応する取引(電力供給)明細を明確に記録させる
ことである。
[Problems to be Solved by the Invention] In an economy-led society, a power supply system (a system including a power supply system on the power supplier side and a power use system on the power user side) is also positioned under the economic system. I have. The economy is driven by human psychology. Therefore, the tasks are:
The aim is to flexibly achieve "leveling of the supply power intended by the power supplier". Specifically, in the present specification, the power supplier side makes an action such that the interests of the power supplier side and the power user side coincide with each other. The expression "data" is automatically generated by a program preset on the power supplier side, and is transmitted to the power user side. In the case of [automatic mode], the power user automatically processes "electronic incentive data" transmitted according to a preset program and controls the power using equipment. In the case of [manual mode], the contents of the "electronic incentive data" are monitored and the power use equipment can be controlled by manual operation.
The problem to be solved subsequently is to have the transaction (power supply) statement corresponding to the system according to the invention clearly recorded.

【0005】[0005]

【課題を解決するための手段】 最小限以下の手段を準
備する。すなわち;電力供給者側には、プログラム設定
部、インセンティブ補正部及びインセンティブデータ発
生部を設ける。そして、これら三つには電力供給設備デ
ータを供給する。電力使用者側には、プログラム設定
部、手動操作部及び演算・制御部を設ける。そして、こ
れら三つには電力使用設備データを供給する。そのほ
か、電力供給者側から電力使用者側へ電子インセンティ
ブデータをオンラインリアルタイムで伝達するための通
信システムを設ける。さらに、付随課題を解決するため
に、取引(電力供給)明細を明確にするための受電電力
明細記録部を電力使用者側に設置する。
[Means for Solving the Problems] The following means are prepared. That is, a program setting unit, an incentive correction unit, and an incentive data generation unit are provided on the power supplier side. These three are supplied with power supply equipment data. On the power user side, a program setting unit, a manual operation unit, and a calculation / control unit are provided. Then, these three units are supplied with the power usage facility data. In addition, a communication system for transmitting electronic incentive data from a power supplier to a power user in real time online is provided. Further, in order to solve the incidental problem, a received power description recording unit for clarifying a transaction (power supply) specification is installed on the power user side.

【0006】[0006]

【発明の実施の形態】 システムの概要:本発明では電
力供給者側の設備、組織及び考え方(人間心理)並びに
電力使用者側の設備、組織及び考え方を含めた大きな体
系(この体系を本発明では「供給電力平準化システム」
と呼ぶ。)の中で供給電力の平準化が達成される。この
システムは全く新規の概念に基づくものである。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Outline of the system: In the present invention, a large system including facilities, organizations and ideas on the side of electric power suppliers (human psychology) and facilities, organizations and ideas on the side of electric power users (this system is referred to as the present invention) Then, "supply power leveling system"
Call. The leveling of the supply power is achieved in the above). This system is based on a completely new concept.

【0007】以下本発明で用いる用語の意味と各部の作
用を交えてシステムの構成を説明する。図1に本発明に
よる供給電力平準化システムの現実的構成を示す。本発
明によるシステムの価値は、システムの運用次第である
のでここでは運用の仕方が分かる説明としている。ただ
し、ここで述べる運用の仕方は本発明の要件とはしな
い。
Hereinafter, the configuration of the system will be described with the meaning of terms used in the present invention and the operation of each unit. FIG. 1 shows a practical configuration of a supply power leveling system according to the present invention. Since the value of the system according to the present invention depends on the operation of the system, the explanation is given here to explain how to operate the system. However, the operation method described here is not a requirement of the present invention.

【0008】「電子インセンティブデータ」とは、次に
示す「インセンティブデータ」をコンピュータ処理でき
る形にしたものをいう。
[0008] "Electronic incentive data" means the following "incentive data" in a form that can be processed by a computer.

【0009】「インセンティブデータ」とは、次に示す
「インセンティブ」の一個一個または全体がわかるデー
タで人間が書いたり内容を読み取ったりできる文書形式
のものである。
The "incentive data" is data in which the following "incentive" can be understood one by one or in whole, and has a document format which can be written and read by a human.

【0010】「インセンティブ」とは、本発明では、電
力供給者側(1)が電力使用者側(2)をして制御した
いとする物理量に対応して電力使用者側に提示するもの
で、インセンティブのメニュー個々に対して適用時間帯
ごと一対一で対応するインセンティブの程度(この「程
度」は、演算に使える数値に置き換えられる形で表現さ
れる)を示すものである。ここで;「制御したい物理
量」とは、例えば、ピーク電力〔kW〕、平均電力〔k
W〕、受電電力量〔kWh〕,規定時間当たりの電力量
(デマンド)〔kWh〕、受電無効電力量〔kvar・
h〕、受電電流の中に含まれる高調波電流〔A〕などが
該当する。
In the present invention, the "incentive" means that the power supplier (1) presents the power user (2) to the power user corresponding to a physical quantity that the user wants to control by controlling the power user (2). This indicates the degree of incentive (the "degree" is expressed in a form that can be replaced with a numerical value that can be used for calculation) corresponding to each incentive menu for each application time zone on a one-to-one basis. Here, “physical quantity to be controlled” means, for example, peak power [kW], average power [k
W], received power amount [kWh], power amount per specified time (demand) [kWh], received reactive power amount [kvar ·
h], harmonic current [A] included in the received current, and the like.

【0011】「電力供給者側(1)」とは、電力供給者
支配下にある発変電設備、送配電設備、組織・人員、運
用・活動等すべてをいう。規模の大きい電力会社では、
設備・考え方等が各支店により異なる場合があるので用
語を「電力供給者」とはせずに「電力供給者側」とし
た。
The "power supplier side (1)" refers to all power generation and transformation facilities, transmission and distribution facilities, organizations and personnel, operations and activities, etc., under the control of the power suppliers. For large power companies,
The term "power supplier" was used instead of "power supplier" because facilities and ideas may differ between branches.

【0012】「契約データ(11)」及び「契約データ
(21)」とは、電力受給に関する契約データであり電
力の取引条件を定めている。当然電力供給者側(1)が
持っている契約データ(11)と電力使用者側(2)が
持っている契約データ(21)とは同一内容である。本
明細書で扱う契約データとは、供給電力の平準化に関係
し、電力供給者側(1)が情勢に応じて可変させてよい
インセンティブについてのものである。契約の中では、
インセンティブの適用の仕方(どういう場面でどういう
インセンティブがあり、その程度=変化範囲)の大枠が
示されていなければならない。このような契約データは
すべて時間の関数であるかまたは時間に対応するもので
あり、かつ、数字に置き換えられるものである。
The "contract data (11)" and the "contract data (21)" are contract data relating to power reception and define power transaction conditions. Naturally, the contract data (11) held by the power supplier (1) and the contract data (21) held by the power user (2) have the same contents. The contract data dealt with in the present specification relates to the leveling of the supplied power and relates to an incentive that the power supplier (1) may change according to the situation. In the contract,
The outline of how the incentive is applied (what kind of incentive is in which situation, and the degree of change = range of change) must be shown. All such contract data are functions of or correspond to time and are replaced by numbers.

【0013】ここで、請求項2で定義の三つのインセン
ティブデータについて契約上の扱い方を記す。「インセ
ンティブ予報データ」は、予報データであり時間が進む
に従って正確になる。(「インセンティブ確定データ」
に近づく。) このデータは参考情報として伝達するもので電気料金算
定には用いない。「インセンティブ確定データ」は、イ
ンセンティブの程度を確定(約束)するデータである。
そして、このデータを使用する契約になっていれば、こ
のデータを用いて電気料金算定を行う。「緊急付加イン
センティブデータ」は、緊急の情況変化により既に伝達
済の「インセンティブ確定データ」に付加するかまたは
それに取って代わり採用するか
Here, the contractual treatment of the three incentive data defined in claim 2 will be described. “Incentive forecast data” is forecast data and becomes more accurate as time progresses. ("Incentive data confirmed"
Approach. This data is for reference only and is not used for calculating electricity rates. “Incentive confirmation data” is data for determining (promising) the degree of incentive.
If a contract is made to use this data, the electricity rate is calculated using this data. Should "urgent additional incentive data" be added to or replace "incentive confirmed data" already communicated due to urgent situation changes?

【0014】する。いづれにしても「緊急付加インセン
ティブデータ」を採用するかしないかは契約次第であ
る。「電力供給設備(15)」とは、電力供給者側
(1)の電力を電力使用者側(2)に届けるまでの全設
備をいう。(送配電路は図示省略。)
[0014] In any case, whether or not to use "emergency additional incentive data" depends on the contract. The “power supply facility (15)” refers to all facilities until the power of the power supplier (1) is delivered to the power user (2). (The transmission and distribution lines are not shown.)

【0015】「電力供給設備データ(16)」とは、電
力供給設備(15)の過去から現在までの電力供給に関
するデータでコンピュータ処理できる形にしたものであ
る。内容としては、設備のon−off信号、運転−停
止信号、計器の指示値、供給能力、供給余力、事故・故
障情報、事故率、設備稼働・停止計画、降水量、燃料相
場などのデータが相当する。
The "power supply equipment data (16)" is a data which can be computer-processed with data relating to the power supply of the power supply equipment (15) from the past to the present. The contents include on-off signal of equipment, run-stop signal, meter reading, supply capacity, supply capacity, accident / failure information, accident rate, equipment operation / stop plan, precipitation, fuel market data, etc. Equivalent to.

【0016】電力供給者側(1)にある「プログラム設
定部(12)」とは、電力供給者側(1)組織が契約デ
ータ(11)を基礎に、電力供給設備データ(16)を
大局的視野で読み取り、景気指標、経営方針などを加味
して、日々刻々変化する設備データから自動的に電子イ
ンセンティブデータを発生させる大枠(論理)を設定し
それをソフトウェア化する(ソフトウェアを作成す
る)。情勢変化に合わせ必要により大枠(論理)とソフ
トウェアの更新を行う。(このソフトウェアは「インセ
ンティブデータ発生部(14)」にインストールする。
また、このソフトウェアは「インセンティブ補正部(1
3)」からのインセンティブ補正データで電子インセン
ティブデータを補正できるようにする。)
The "program setting unit (12)" on the power supplier side (1) means that the organization of the power supplier side (1) collects the power supply equipment data (16) based on the contract data (11). Set a framework (logic) to automatically generate electronic incentive data from equipment data that changes every day, taking into account the business index, business index, management policy, etc., and convert it to software (create software) . Update the software (basic logic) and software as necessary according to the situation change. (This software is installed in the “incentive data generator (14)”.
In addition, this software uses the “incentive correction unit (1
3) The electronic incentive data can be corrected with the incentive correction data from "3)." )

【0017】「インセンティブ補正部(13)」とは、
「プログラム設定部(12)」で定めた大枠内で、情況
に合わせて、その場の人間の判断でそれを「インセンテ
ィブデータ発生部(14)」が発生する電子インセンテ
ィブデータに盛り込むべく人間がインセンティブ補正操
作を行う所である。(インセンティブ補正部からの出力
のことを「インセンティブ補正データ」という。) 補正操作には、直近の情勢変化が急で予想外である場合
に、その場の人間の判断で必要により「インセンティブ
データ発生部(14)」に「緊急付加インセンティブデ
ータ」を発生させることも含む。ここで;「直近の情勢
変化が急で予想外である場合」とは、電力供給者側
(1)の電力供給設備(15)に大事故が発生し電力供
給能力が急減した場合、社会的大事件が発生し国中のテ
レビ受信機が点けられると予想される場合などが相当す
る。
The "incentive correction unit (13)"
Within the framework defined by the "program setting unit (12)", the human incentive is included in the electronic incentive data generated by the "incentive data generating unit (14)" according to the situation, according to the situation of the human being. This is where the correction operation is performed. (The output from the incentive correction unit is referred to as "incentive correction data.") In the correction operation, if the latest situation change is sudden and unexpected, the "incentive data generation" (14) generating "urgent additional incentive data". Here, “when the latest situation change is sudden and unexpected” means that when a major accident occurs in the power supply facility (15) on the power supplier side (1) and the power supply capacity suddenly decreases, social This corresponds to a case where a major incident occurs and television receivers throughout the country are expected to be turned on.

【0018】「インセンティブデータ発生部」(1
4)」とは、「プログラム設定部(12)」で作成のプ
ログラムに従って「電力供給設備データ(16)」を処
理し、電子インセンティブデータを発生させる。(も
し、「インセンティブ補正部(13)」からのインセン
ティブ補正入力があれば、発生する電子インセンティブ
データはそれにより補正されたものとなる。)
"Incentive data generator" (1
"4)" means that the "power supply equipment data (16)" is processed according to the program created by the "program setting unit (12)" to generate electronic incentive data. (If there is an incentive correction input from the “incentive correction unit (13)”, the generated electronic incentive data is corrected by that.)

【0019】「電力使用者側(2)」とは、電力使用者
支配下にある受電設備、負荷設備、組織・人員、運用・
活動等すべてをいう。設備に関する責任・権限等が下部
組織に分散されている場合があるので用語を「電力使用
者」とはせずに「電力使用者側」とした。 (注)電力会社に電気を卸す電気卸業者がある場合は、
電気卸業者に対しても本発明を適用できる。
The “power user side (2)” means power receiving equipment, load equipment, organization / personnel, operation /
Refers to all activities. The term "electricity user" was used instead of "electricity user" because responsibilities and authorities related to equipment were sometimes distributed to subordinate organizations. (Note) If the electric power company has an electric wholesaler who wholesales electricity,
The present invention can be applied to electric wholesalers.

【0020】「電力使用設備(25)」とは、電力供給
者側(1)から供給される電力を受電し使用(消費)す
る全設備をいう。(受電路は図示省略。)
"Electric power using equipment (25)" means all equipment that receives and uses (consumes) electric power supplied from the electric power supplier side (1). (The power receiving path is not shown.)

【0021】「電力使用設備データA(26)」とは、
電力使用設備(25)の過去から現在までの電力使用に
関するデータでコンピュータ処理できる形にしたもので
ある。内容としては、設備のon−off信号、運転−
停止信号、計器の指示値、設備能力、設備余力、設備稼
働率、事故率、設備稼働・停止計画、操業データなどが
相当する。データには実測データのほか統計的手法を使
ったりして得られる加工データまで含まれる。ここで、
似ている二つの用語「電力使用設備データA(26)」
と「電力使用設備データB(27)」について:「電力
使用設備データA(26)」は電力使用者側(2)が使
用するデータである。一方、「電力使用設備データB
(27)」は通常電力供給者側(1)が使用するデータ
である。本明細書では、「電力使用設備データA(2
6)」と「電力使用設備データB(27)」とを厳密に
区分する必要のない場面では、ただ単に「電力使用設備
データ」と表現している。
"Electric power usage facility data A (26)"
This is in a form that can be computer-processed with data on the power usage of the power usage facility (25) from the past to the present. The contents include the on-off signal of the equipment, operation-
Stop signals, meter readings, equipment capacity, equipment reserve, equipment availability, accident rates, equipment operation / stop plans, operation data, and the like. Data includes not only measured data but also processed data obtained by using statistical methods. here,
Two similar terms, "Electricity data for power consumption A (26)"
And "Power use facility data B (27)": "Power use facility data A (26)" is data used by the power user side (2). On the other hand, "Electric power usage facility data B
(27) "is data normally used by the power supplier (1). In this specification, “power use facility data A (2
6) "and" Electric power usage equipment data B (27) "are simply expressed as" Electric power usage equipment data "when it is not necessary to strictly separate them.

【0022】「電力使用設備データB(27)」とは、
電力使用設備(25)の現時点の使用電力の電気的物理
量のデータでありコンピュータ処理できる形にしたもの
である。このデータは取引用のものである。取引に使う
電気物理量は通常は電力供給者側(1)の所有物である
計量装置で計量される。この計量装置は電力使用者側
(2)の電力使用設備(25)の中に設置されている。
"Electric power usage facility data B (27)"
This is data on the electrical physical quantity of the current power consumption of the power usage facility (25), which is in a form that can be processed by a computer. This data is for transactions. The electric physical quantity used for the transaction is usually measured by a measuring device belonging to the electric power supplier (1). This metering device is installed in a power use facility (25) on the power user side (2).

【0023】「受電電力明細記録部(28)」とは、契
約が定める料金算定方式(これは、「契約データ(2
1)」(=「契約データ(11)」)の中に含まれてい
る)に従い、電力使用設備データB(27)と電力使用
者側(2)に伝達された電子インセンティブデータを演
算し電気料金の明細データ(または電気料金確定に必須
のデータ)を作成し記録する。
The “received power statement recording unit (28)” is a fee calculation method defined by the contract (this is described in “Contract Data (2)
(1)) (= contract data (11)), calculates the electric power use facility data B (27) and the electronic incentive data transmitted to the electric power user (2), and Create and record detailed billing data (or data essential for determining electricity rates).

【0024】電力使用者側(2)の「プログラム設定部
(22)」とは、電力使用者側(2)組織が契約データ
(21)を基礎に、電力使用設備データA(26)を大
局的視野で読み取り、景気指標、経営方針などを加味し
て、電力供給者側(1)から日々刻々伝達されてくる電
子インセンティブデータに含まれるインセンティブをど
う利用するのか決め、伝達されてくる電子インセンティ
ブデータによって「電力使用設備(25)」を自動的に
(または手動で)制御させる大枠(理論)を設定しそれ
をソフトウェア化する(ソフトウェアを作成する)。情
勢変化に合わせ必要により大枠(理論)とソフトウェア
の更新を行う。(このソフトウェアは「演算・制御部
(24)」にインストールする。また、このソフトウェ
アは〔自動モード〕では、「手動操作部(23)」から
の補正データで「演算・制御部(24)」の出力である
「電力使用設備(25)」を制御させるための制御信号
を補正できるようになっている。〔手動モード〕では、
「手動操作部(23)」による「電力使用設備(2
5)」の直接制御となる制御信号を「演算・制御部」に
出させるようになっている。)
The "program setting unit (22)" of the electric power user (2) means that the organization of the electric power user (2) collects the electric power using equipment data A (26) based on the contract data (21). Electronic incentives that are read from a strategic perspective, take into account economic indicators, management policies, etc., determine how to use the incentives contained in the electronic incentive data that is transmitted from the power supplier (1) every day, and transmitted. An outline (theory) for automatically (or manually) controlling the “power use equipment (25)” is set based on the data, and the software is created (software is created). Update the framework (theory) and software as needed according to changes in the situation. (This software is installed in the "calculation / control unit (24)." In the "automatic mode," this software uses the correction data from the "manual operation unit (23)" to provide the "calculation / control unit (24)." In the [manual mode], the control signal for controlling the "power use equipment (25)" which is the output of the control unit can be corrected.
"Electricity using equipment (2
The control signal for direct control of 5)) is output to the “calculation / control section”. )

【0025】「手動操作部(23)」とは、電力使用者
側(2)の「プログラム設定部(22)」で定めた大枠
内で、〔自動モード〕の場合;情況に合わせて、その場
の人間の判断でそれを「演算・制御部(24)」が出力
する制御信号に盛り込むべく手動補正操作を行う所であ
る。また、〔手動モード〕の場合;「演算・制御部」
(24)」の出力はすべて人間の操作が優先となる手動
操作を行う所である。
The "manual operation section (23)" is within the outline defined by the "program setting section (22)" of the electric power user (2), in the case of [automatic mode]; At the discretion of the person in the field, a manual correction operation is performed so as to incorporate it into the control signal output by the "calculation / control section (24)". In the case of [manual mode]; "arithmetic / control unit"
(24) "are all places where a manual operation is performed in which human operation has priority.

【0026】「演算・制御部」(24)」とは、「プロ
グラム設定部(22)」で作成のプログラムがインスト
ールされ、それに従って、〔自動モード〕の場合;伝達
された電子インセンティブデータと「電力使用設備デー
タA(26)」とを演算し、「電力使用設備(25)」
を制御する制御信号を発生させる。もし、「手動操作部
(23)」からの補正入力があれば、発生する制御信号
はそれにより補正されたものとなる。〔手動モード〕の
場合;「手動操作部(23)」からの操作信号を受け、
人間の操作が優先する制御信号を出力する。ここで;
「電力使用設備(25)を制御する」とは、電力使用設
備(25)を構成する色々な負荷設備について、負荷設
備個々にまたはグループとして次のような操作を行うこ
とである。(該当するもの) a.電源をon−offする。b.機械を運転−停止す
る。c.機械の周波数/回転数を加減する。d.加熱装
置の設定温度を下げる。e.冷却装置の設定温度を上げ
る。f.運転時間帯を変更する。
The "arithmetic / control unit" (24) means that the program created by the "program setting unit (22)" is installed, and accordingly, in the case of [automatic mode]; the transmitted electronic incentive data and " Power usage facility data A (26) "is calculated, and" power usage facility (25) "
Generate a control signal for controlling If there is a correction input from the "manual operation unit (23)", the generated control signal is corrected by that. [Manual mode]; receives an operation signal from the "manual operation unit (23)"
It outputs a control signal that gives priority to human operation. here;
“Controlling the electric power using facility (25)” means performing the following operation on various load facilities constituting the electric power using facility (25) individually or as a group of load facilities. (Applicable) a. Turn the power on and off. b. Start / stop the machine. c. Adjust the frequency / speed of the machine. d. Lower the set temperature of the heating device. e. Increase the temperature of the cooling device. f. Change driving hours.

【0027】「通信システム(3)」とは、電力供給者
側(1)から電力使用者側(2)に電子インセンティブ
データをオンラインリアルタイムで伝達するためのシス
テムであり、電力供給者側(1)と電力使用者側(2)
とが合意のうえ選定されるものである。(通信システム
(3)の要件を定めるのは本発明の目的ではない。)こ
こで;オンラインリアルタイムとは、電子インセンティ
ブデータが次のいづれかに相当する伝達方式によるもの
をいう。 〔伝達方式1〕:電力供給者側(1)から電子インセン
ティブデータが連続的に電力使用者側(2)に伝達され
る方式。 〔伝達方式2〕:電力供給者側(1)から電子インセン
ティブデータが定期的にまたは随時に電力使用者側
(2)に伝達される方式。 〔伝達方式3〕:電力供給者側(1)から電子インセン
ティブデータが電力使用者側(2)が要求したときにそ
の都度電力使用者側(2)に伝達される方式。
The "communication system (3)" is a system for transmitting electronic incentive data online and in real time from the electric power supplier (1) to the electric power user (2). ) And the power user side (2)
Are selected upon agreement. (It is not the object of the present invention to determine the requirements of the communication system (3).) Here, online real-time means that the electronic incentive data is transmitted by any of the following transmission methods. [Transmission method 1]: A method in which electronic incentive data is continuously transmitted from the power supplier (1) to the power user (2). [Transmission method 2]: A method in which electronic incentive data is transmitted from the power supplier side (1) to the power user side (2) periodically or as needed. [Transmission method 3]: A method in which electronic incentive data is transmitted from the power supplier (1) to the power user (2) each time the power user (2) requests.

【0028】本発明の要件ではないが、人間が扱うシス
テムであるので、電力供給者側(1)には、電力使用者
側(2)に伝達したインセンティブデータが何であった
かを表示・記録する表示・記録部がある。電力使用者側
(2)にも、電力供給者側(1)から伝達されたインセ
ンティブデータをモニターし記録する表示・記録部があ
る。(これらの表示・記録部の図示省略。)
Although not a requirement of the present invention, since the system is handled by humans, the power supplier (1) displays and records what the incentive data transmitted to the power user (2) was.・ There is a recording unit. The power user (2) also has a display / recording unit that monitors and records the incentive data transmitted from the power supplier (1). (The display and recording units are not shown.)

【発明の効果】 a.従来よりもより効果的な供給電力
の平準化が機動的に達成されるようになる。とくに「自
動モード〕では、いちいち人間がこまごまと関与するこ
となしに自動的にコンピュータを用いて供給電力の平準
化が達成されるようになる。b.電力料金を算定するた
め電力使用者側に設置の電力計量装置(本明細書では
「受電電力明細記録部」という)は、原理的に一つにで
きる。(原則、一契約(一取引)一計量とすることがで
きる。)
Effect of the Invention a. A more effective leveling of the supply power than before can be achieved flexibly. In particular, in the “automatic mode”, the leveling of the supplied power is automatically achieved using a computer without human involvement.b. The installed power metering device (herein referred to as “received power detail recording unit”) can be united in principle. (In principle, one contract (one transaction) can be measured.)

【図面の簡単な説明】[Brief description of the drawings]

【図1】は、供給電力平準化システムの現実的構成を示
す図である。
FIG. 1 is a diagram showing a practical configuration of a power supply leveling system.

【符号の説明】[Explanation of symbols]

1 電力供給者側 2 電力使用者側 3 通信システム 11,21 契約データ 12,22 プログラム設定部 13 インセンティブ補正部 14 インセンティブデータ発生部 15 電力供給設備 16 電力供給設備データ 23 手動操作部 24 演算・制御部 25 電力使用設備 26 電力使用設備データA 27 電力使用設備データB 28 受電電力明細記録部 DESCRIPTION OF SYMBOLS 1 Power supplier side 2 Power user side 3 Communication system 11 and 21 Contract data 12, 22 Program setting part 13 Incentive correction part 14 Incentive data generation part 15 Power supply equipment 16 Power supply equipment data 23 Manual operation part 24 Calculation / control Part 25 Power usage facility 26 Power usage facility data A 27 Power usage facility data B 28 Received power detail recording section

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 通信システムを使って電力供給者側から
電力使用者側に電子インセンティブデータをオンライン
リアルタイムで伝達し、かつ、電力使用者側では、あら
かじめ設定してあるプログラムに従って伝達されたこの
電子インセンティブデータを処理し、この処理結果に基
づいて電力使用設備をリアルタイムで制御できることを
特徴とする供給電力平準化システム。
1. An electronic incentive data is transmitted from a power supplier side to a power user side in real time online using a communication system, and the electronic user transmits the electronic incentive data according to a preset program. A supply power leveling system that processes incentive data and controls power use equipment in real time based on the processing result.
【請求項2】 二つの入力すなわち電力供給設備データ
とインセンティブ補正部からのインセンティブ補正デー
タから、出力として次に示す「インセンティブ予報デー
タ」、「インセンティブ確定データ」及び「緊急付加イ
ンセンティブデータ」の三つのうち、一つ以上を発生さ
せるようにプログラムを組んであることを特徴とする請
求項1の電子インセンティブデータを発生させるインセ
ンティブデータ発生部。ここで; 「インセンティブ予報データ」とは;「現在から(数時
間から数週間程度の期間の)未来に亙って細分した各時
間帯ごと一対一で対応する可変予測インセンティブデー
タ」 「インセンティブ確定データ」とは;「現在から(数時
間程度の)近未来に亙って細分した各時間帯ごと一対一
で対応する確定(不変)インセンティブデータ」 「緊急付加インセンティブデータ」とは;「現在から
(数分から1時間程度)先の直近時間帯ごと一対一で対
応する緊急に設定する確定(不変)インセンティブデー
タ」
2. Based on two inputs, ie, power supply facility data and incentive correction data from the incentive correction unit, three outputs of “incentive forecast data”, “incentive confirmation data” and “emergency additional incentive data” are output as follows. 2. The incentive data generation unit for generating electronic incentive data according to claim 1, wherein a program is configured to generate at least one of the electronic incentive data. Here, "incentive forecast data" means: "variable prediction incentive data corresponding one-to-one for each time zone subdivided from the present (from several hours to several weeks) in the future""incentive confirmed data "Emergency added incentive data";"Emergency additional incentive data";"Emergency additional incentive data" which corresponds one-to-one with each time zone subdivided over the near future (about several hours from the present). (Several minutes to 1 hour) Final (invariant) incentive data to be set urgently for one-on-one correspondence in the latest time zone ahead "
【請求項3】 電子データが、請求項2に示す「インセ
ンティブ予報データ」、「インセンティブ確定データ」
及び「緊急付加インセンティブデータ」の三つのうちの
少なくとも一つ以上を含んでいることを特徴とする請求
項1の電子インセンティブデータ。
3. The electronic data includes “incentive forecast data” and “incentive confirmation data” described in claim 2.
2. The electronic incentive data according to claim 1, wherein the electronic incentive data includes at least one of the following three: "emergency additional incentive data".
【請求項4】 必須入力データが、使用者側に伝達され
た請求項1の電子インセンティブデータと電力使用設備
データの二つであり、最小限これら二つのデータを演算
し自動的に電力使用設備を制御するための制御信号を発
生する演算・制御部。
4. The indispensable input data is the electronic incentive data and the power use equipment data of claim 1 transmitted to the user side, and at least these two data are calculated and automatically used. An arithmetic and control unit that generates a control signal for controlling the operation.
【請求項5】 受電電力明細記録部が、請求項1の電子
インセンティブデータが示すインセンティブ対象メニュ
ー個々について、次に示す二つの「明細データ」を記録
するようになっている受電電力明細記録部。 「明細データ」その1:電気料金算出根拠及びその証明
に必須の伝達されたインセンティブの程度を示すデータ
(数値または数値に対応するランク区分記号) 「明細データ」その2:料金算出のための演算に使われ
る電力使用設備データ
5. A received power description recording unit, wherein the received power description recording unit records the following two “description data” for each incentive target menu indicated by the electronic incentive data of claim 1. "Detailed data" Part 1: Data indicating the basis for calculating the electricity rate and the degree of incentive transmitted to the proof (numerical value or rank classification symbol corresponding to the numerical value) "Detailed data" Part 2: Calculation for calculating the rate Power usage data used for
JP25591898A 1998-08-07 1998-08-07 Supplied power leveling system Pending JP2000060031A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP25591898A JP2000060031A (en) 1998-08-07 1998-08-07 Supplied power leveling system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP25591898A JP2000060031A (en) 1998-08-07 1998-08-07 Supplied power leveling system

Publications (1)

Publication Number Publication Date
JP2000060031A true JP2000060031A (en) 2000-02-25

Family

ID=17285385

Family Applications (1)

Application Number Title Priority Date Filing Date
JP25591898A Pending JP2000060031A (en) 1998-08-07 1998-08-07 Supplied power leveling system

Country Status (1)

Country Link
JP (1) JP2000060031A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002245306A (en) * 2001-02-15 2002-08-30 Hitachi Ltd Transaction mediating system, article transaction mediating system, power transaction mediating system and services therefor
JP2007510968A (en) * 2003-09-16 2007-04-26 イーティージー インターナショナル エルエルシー Management of wide area power demand and power supply
JP2010537622A (en) * 2007-08-28 2010-12-02 コンサート インコーポレイテッド Active power load management system and active power load management method
JP2012075246A (en) * 2010-09-28 2012-04-12 Toshiba Corp Green power demand management device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002245306A (en) * 2001-02-15 2002-08-30 Hitachi Ltd Transaction mediating system, article transaction mediating system, power transaction mediating system and services therefor
JP2007510968A (en) * 2003-09-16 2007-04-26 イーティージー インターナショナル エルエルシー Management of wide area power demand and power supply
JP2010537622A (en) * 2007-08-28 2010-12-02 コンサート インコーポレイテッド Active power load management system and active power load management method
JP2013059256A (en) * 2007-08-28 2013-03-28 Consert Inc Active power load management system and active power load management method
JP2012075246A (en) * 2010-09-28 2012-04-12 Toshiba Corp Green power demand management device

Similar Documents

Publication Publication Date Title
Zhang et al. A novel peer-to-peer local electricity market for joint trading of energy and uncertainty
Riesz et al. Frequency control ancillary service market design: Insights from the australian national electricity market
USRE46093E1 (en) Energy reduction
EP2359457B1 (en) Energy reduction
US20100145884A1 (en) Energy savings aggregation
JP6758881B2 (en) Power supply and demand management support system, power supply and demand management support method and power supply and demand management support program
CA2915961C (en) Hierarchical operational control of aggregated load management resources
Ellison et al. Project report: a survey of operating reserve markets in US ISO/RTO-managed electric energy regions.
US20160189298A1 (en) Power adjustment system, power adjustment method, and computer program
JP2002369385A (en) Power transmission control system, power reception control system and power transmission and reception control system
Tesfatsion A new swing-contract design for wholesale power markets
JP2020017030A (en) Demand response management system including scheduling function
JP2000060031A (en) Supplied power leveling system
JP6117984B1 (en) Supply and demand management device, supply and demand management method, and supply and demand management program
JP4104520B2 (en) Electricity load leveling system
Hirst Price-responsive demand in wholesale markets: Why is so little happening?
JP2002345154A (en) Power demand and supply method, and display device
Tesfatsion et al. Analytical SCUC/SCED optimization formulation for AMES V5. 0
Goodin California Independent System Operator demand response & proxy demand resources
JP6658064B2 (en) Power management device and power management program
JP5886400B1 (en) Power market pricing system and method
KR102594831B1 (en) System for renewable energy capability prediction and development plan
Susan et al. Demand response participation in organized electricity markets: A PJM case study
Zhang et al. Optimal bidding strategy for data center aggregators considering spatio-temporal transfer characteristics
JP7215013B2 (en) Supply and demand planning device