JP6658064B2 - Power management device and power management program - Google Patents

Power management device and power management program Download PDF

Info

Publication number
JP6658064B2
JP6658064B2 JP2016030173A JP2016030173A JP6658064B2 JP 6658064 B2 JP6658064 B2 JP 6658064B2 JP 2016030173 A JP2016030173 A JP 2016030173A JP 2016030173 A JP2016030173 A JP 2016030173A JP 6658064 B2 JP6658064 B2 JP 6658064B2
Authority
JP
Japan
Prior art keywords
power
customer
amount
schedule
power management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2016030173A
Other languages
Japanese (ja)
Other versions
JP2017146921A (en
Inventor
勲 後藤
勲 後藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Electric Industries Ltd
Original Assignee
Sumitomo Electric Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Electric Industries Ltd filed Critical Sumitomo Electric Industries Ltd
Priority to JP2016030173A priority Critical patent/JP6658064B2/en
Publication of JP2017146921A publication Critical patent/JP2017146921A/en
Application granted granted Critical
Publication of JP6658064B2 publication Critical patent/JP6658064B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、電力管理装置および電力管理プログラムに関し、特に、複数の需要家の電力消費を管理する電力管理装置および電力管理プログラムに関する。   The present invention relates to a power management device and a power management program, and more particularly to a power management device and a power management program that manage power consumption of a plurality of consumers.

電力の小売全面自由化により、たとえば小売事業者が、卸電力市場において電力量を予め調達し、調達した電力量を対象期間において一般家庭等の需要家に供給することができるようになる。   The full liberalization of electric power retailing allows, for example, a retailer to procure the electric energy in advance in the wholesale electric power market and supply the proceded electric energy to consumers such as ordinary households in the target period.

小売事業者には、たとえば、卸電力市場において調達した電力量と、各需要家へ供給する電力量すなわち各需要家の施設において使用される電力量とをほぼ一致させること、すなわちインバランスを回避することが求められる。   For example, the retailer is required to substantially match the amount of power procured in the wholesale power market with the amount of power supplied to each customer, that is, the amount of power used in each customer's facilities, that is, to avoid imbalance Is required.

たとえば、米国のある州では、インバランスが発生した場合にインバランス電力を市場にて手取引き可能なシステムが構築されている。たとえば、特許文献1(特許第3883498号公報)には、当該システムにおいて適用可能な以下のような技術が開示されている。すなわち、電力取引支援システムは、供給部から需要部へ電力を託送する電気事業において、前記需要部の受電量に対する前記供給部の給電量の過不足分に相当するインバランス電力についての電力市場との間で行われる電力取引を支援するインバランス電力取引支援システムであって、前記需要部の検針期間毎の受電量に関する検針データから、前記需要部の価格設定期間毎の受電量に関する清算用受電量データを導出する清算用受電量データ導出手段と、前記清算用受電量データ導出手段で導出した清算用受電量データと、前記供給部の価格設定期間毎の給電量に関する清算用給電量データとから、前記価格設定期間毎のインバランス電力の取引量に関する取引量データを導出する取引量データ導出手段と、を備えると共に、前記清算用受電量データ導出手段が、前記価格設定期間よりも長い前記検針期間毎に検針データが取得された特定需要部に対して、前記特定需要部の検針データと、前記特定需要部の需要部属性区分に対応する標準的な前記価格設定期間毎の受電量に関する清算用プロファイルデータとから、前記特定需要部の清算用受電量データを推定するプロファイリング処理手段を具備する。   For example, in a U.S. state, a system has been constructed that can manually trade imbalanced power in the market when imbalance occurs. For example, Patent Document 1 (Japanese Patent No. 3883498) discloses the following technology applicable to the system. That is, the power trading support system, in the electric power business to transfer power from the supply unit to the demand unit, the power market for imbalanced power corresponding to the excess or deficiency of the supply amount of the supply unit with respect to the amount of power received by the demand unit. An imbalanced power trading support system for supporting power trading performed between the power demanding unit, comprising: a metering data relating to a power receiving amount of the demand unit for each metering period; Clearing power receiving amount data deriving means for deriving the amount data, clearing power receiving amount data derived by the clearing power receiving amount data deriving means, and clearing power supply amount data relating to the power supply amount for each price setting period of the supply unit. And a transaction volume data deriving means for deriving transaction volume data relating to the transaction volume of the imbalanced power for each of the price setting periods. The electric energy data deriving means, for a specific demand unit for which meter reading data is acquired for each meter reading period longer than the price setting period, for the meter reading data of the specific demand unit and the demand unit attribute classification of the specific demand unit. And a profiling processing unit for estimating the received power data for clearing of the specific demand unit from the corresponding standard profile data for clearing related to the received power for each pricing period.

ところで、わが国において導入される電力システムでは、卸電力市場において調達した電力量が、各需要家が使用した電力量と比べて少なすぎた場合、小売事業者には、ペナルティーとしてインバランス料金を支払う義務が発生する予定である。また、小売事業者が卸電力市場において調達した電力量が、各需要家が使用した電力量と比べて多すぎた場合、余剰となった電力量は没収される予定である。   By the way, in the electric power system introduced in Japan, if the amount of electric power procured in the wholesale electric power market is too small compared with the amount of electric power used by each customer, the retailer is paid an imbalance fee as a penalty. Obligations will occur. If the amount of power procured by the retailer in the wholesale power market is too large compared to the amount of power used by each customer, the surplus power will be confiscated.

このような場合、小売事業者は、対象期間において需要家が使用する電力量を正確に予測し、予測結果に基づく電力量の調達を行う必要がある。   In such a case, the retailer needs to accurately predict the amount of power used by the customer during the target period and procure the amount of power based on the prediction result.

特許第3883498号公報Japanese Patent No. 3883498

しかしながら、小売事業者による電力量の供給先は、比較的少数の一般家庭等であるため、工場等の大口需要家に比べて、使用される電力量を正確に予測することは困難である。   However, since the supply destination of the electric energy by the retailer is a relatively small number of ordinary households, it is more difficult to accurately predict the electric energy to be used as compared with large customers such as factories.

この発明は、上述の課題を解決するためになされたもので、その目的は、調達した電力量と供給する電力量との不一致を抑えることが可能な電力管理装置および電力管理プログラムを提供することである。   The present invention has been made to solve the above-described problem, and an object of the present invention is to provide a power management device and a power management program capable of suppressing a mismatch between a procured power amount and a supplied power amount. It is.

(1)上記課題を解決するために、この発明のある局面に係る電力管理装置は、対象期間において使用するために調達する予定の電力量である第1の電力量または前記対象期間において使用するために調達された電力量である第2の電力量に基づいて、前記対象期間における複数の需要家の電力消費に関するスケジュールを作成する作成部と、前記作成部によって作成された前記スケジュールに関する情報を各前記需要家に対応する需要家装置へ送信する送信部とを備える。   (1) In order to solve the above-described problem, a power management device according to an aspect of the present invention uses a first power amount, which is a power amount to be procured for use in a target period, or uses the power amount in the target period. A creating unit that creates a schedule related to the power consumption of the plurality of customers in the target period based on the second amount of power that is the amount of power procured for the second unit; and information about the schedule created by the creating unit. A transmission unit for transmitting to a customer device corresponding to each customer.

(12)上記課題を解決するために、この発明のある局面に係る電力管理プログラムは、電力管理装置において用いられる電力管理プログラムであって、コンピュータを、対象期間において使用するために調達する予定の電力量である第1の電力量または前記対象期間において使用するために調達された電力量である第2の電力量に基づいて、前記対象期間における複数の需要家の電力消費に関するスケジュールを作成する作成部と、前記作成部によって作成された前記スケジュールに関する情報を各前記需要家に対応する需要家装置へ送信する送信部として機能させるためのプログラムである。   (12) In order to solve the above problem, a power management program according to an aspect of the present invention is a power management program used in a power management device, and is intended to procure a computer for use in a target period. Based on the first electric energy that is the electric energy or the second electric energy that is the electric energy procured for use in the target period, a schedule related to the power consumption of the plurality of consumers in the target period is created. It is a program for functioning as a creating unit and a transmitting unit that transmits information on the schedule created by the creating unit to a customer device corresponding to each customer.

本発明は、このような特徴的な処理部を備える電力管理装置として実現することができるだけでなく、かかる特徴的な処理をステップとする方法として実現することができる。また、電力管理装置の一部または全部を実現する半導体集積回路として実現したり、電力管理装置を含むシステムとして実現したりすることができる。   The present invention can be realized not only as a power management apparatus having such a characteristic processing unit, but also as a method having such characteristic processing as steps. Further, it can be realized as a semiconductor integrated circuit that realizes part or all of the power management device, or as a system including the power management device.

本発明によれば、調達した電力量と供給する電力量との不一致を抑えることができる。   According to the present invention, it is possible to suppress a mismatch between the amount of electric power and the amount of electric power to be supplied.

図1は、本発明の第1の実施の形態に係る電力管理システムが適用される電力システムの一例について説明するための図である。FIG. 1 is a diagram for describing an example of a power system to which the power management system according to the first embodiment of the present invention is applied. 図2は、本発明の第1の実施の形態に係る電力管理システムが適用される電力システムの一例について説明するための図である。FIG. 2 is a diagram for describing an example of a power system to which the power management system according to the first embodiment of the present invention is applied. 図3は、本発明の第1の実施の形態に係る電力管理システムが適用される電力システムの一例について説明するための図である。FIG. 3 is a diagram for describing an example of a power system to which the power management system according to the first embodiment of the present invention is applied. 図4は、本発明の第1の実施の形態に係る電力管理システムが適用される電力システムの一例について説明するための図である。FIG. 4 is a diagram for describing an example of a power system to which the power management system according to the first embodiment of the present invention is applied. 図5は、本発明の第1の実施の形態に係る電力管理システムが適用される電力システムの一例について説明するための図である。FIG. 5 is a diagram for describing an example of a power system to which the power management system according to the first embodiment of the present invention is applied. 図6は、本発明の第1の実施の形態に係る電力管理システムの構成を示す図である。FIG. 6 is a diagram illustrating a configuration of the power management system according to the first embodiment of the present invention. 図7は、本発明の第1の実施の形態に係る電力管理システムにおいて電力管理装置が作成するスケジュールYについて説明するための図である。FIG. 7 is a diagram illustrating a schedule Y created by the power management device in the power management system according to the first embodiment of the present invention. 図8は、本発明の第1の実施の形態に係る電力管理システムにおいて電力管理装置が作成するスケジュールYについて説明するための図である。FIG. 8 is a diagram illustrating a schedule Y created by the power management device in the power management system according to the first embodiment of the present invention. 図9は、本発明の第1の実施の形態に係る電力管理システムにおいて電力管理装置が作成するスケジュールYについて説明するための図である。FIG. 9 is a diagram illustrating a schedule Y created by the power management device in the power management system according to the first embodiment of the present invention. 図10は、本発明の第1の実施の形態に係る電力管理システムにおける、参加需要家Pの数とインバランスのリスクとの関係を示す図である。FIG. 10 is a diagram illustrating a relationship between the number of participating customers P and imbalance risk in the power management system according to the first embodiment of the present invention. 図11は、本発明の第1の実施の形態に係る電力管理システムにおける、インバランスのリスクについて説明するための図である。FIG. 11 is a diagram for describing an imbalance risk in the power management system according to the first embodiment of the present invention. 図12は、本発明の第1の実施の形態に係る電力管理システムにおける電力管理処理を示すシーケンス図である。FIG. 12 is a sequence diagram illustrating power management processing in the power management system according to the first embodiment of the present invention. 図13は、本発明の第1の実施の形態に係る電力管理システムにおけるキャンセル時処理を示すシーケンス図である。FIG. 13 is a sequence diagram showing a process at the time of cancellation in the power management system according to the first embodiment of the present invention. 図14は、本発明の第1の実施の形態に係る電力管理装置の構成を示す図である。FIG. 14 is a diagram illustrating a configuration of the power management device according to the first embodiment of the present invention. 図15は、本発明の第2の実施の形態に係る電力管理システムにおける電力管理処理を示すシーケンス図である。FIG. 15 is a sequence diagram illustrating a power management process in the power management system according to the second embodiment of the present invention. 図16は、本発明の第2の実施の形態に係る電力管理装置の構成を示す図である。FIG. 16 is a diagram illustrating a configuration of a power management device according to the second embodiment of the present invention.

最初に、本発明の実施の形態の内容を列記して説明する。   First, the contents of the embodiment of the present invention will be listed and described.

(1)本発明の実施の形態に係る電力管理装置は、対象期間において使用するために調達する予定の電力量である第1の電力量または前記対象期間において使用するために調達された電力量である第2の電力量に基づいて、前記対象期間における複数の需要家の電力消費に関するスケジュールを作成する作成部と、前記作成部によって作成された前記スケジュールに関する情報を各前記需要家に対応する需要家装置へ送信する送信部とを備える。   (1) The power management apparatus according to the embodiment of the present invention provides a first power amount that is a power amount to be procured for use in a target period or a power amount procured for use in the target period. A creating unit that creates a schedule related to the power consumption of a plurality of consumers in the target period based on the second amount of power that is, and information about the schedule created by the creating unit corresponding to each of the consumers. A transmission unit for transmitting to the customer device.

このような構成により、たとえば、調達済みの電力量または調達予定の電力量と、需要家に供給する電力量とが一致するように、電力消費に関するスケジュールを作成し、作成したスケジュールに従った電力消費を行うように各需要家に要求することができる。したがって、調達した電力量と供給する電力量との不一致を抑えることができる。   With such a configuration, for example, a schedule related to power consumption is created so that the amount of electric power that has already been procured or to be procured matches the amount of electric power to be supplied to the customer, and the power according to the created schedule is generated. Each consumer can be required to consume. Therefore, it is possible to suppress a mismatch between the amount of power that is procured and the amount of power that is supplied.

(2)好ましくは、前記電力管理装置は、さらに、前記送信部によって送信された前記情報に対する応答を取得する取得部と、前記取得部によって取得された前記応答に基づいて、前記第1の電力量を補正するか、または前記対象期間において使用するために調達する電力量を前記第2の電力量から補正する補正処理を行う補正処理部とを備える。   (2) Preferably, the power management device further includes: an acquisition unit that acquires a response to the information transmitted by the transmission unit; and the first power based on the response acquired by the acquisition unit. A correction processing unit that corrects the amount or corrects the amount of power to be procured for use in the target period from the second amount of power.

このような構成により、たとえば、需要家が上記スケジュールに従った電力消費を行う予定であるか否かがわかるので、当該需要家において消費される電力量を正確に把握することができる。そして、把握した電力量に基づいて、調達予定の電力量の補正、または、調達済みの電力量の一部売却もしくは電力量の追加調達を行うことができるため、調達した電力量と供給する電力量との不一致をより効果的に抑えることができる。   With such a configuration, for example, it is possible to know whether or not the customer is going to consume power according to the above schedule, so that the amount of power consumed by the customer can be accurately grasped. Then, based on the grasped electric energy, it is possible to correct the electric energy to be procured, or to sell a part of the electric energy already procured or to additionally procure the electric energy. The discrepancy with the amount can be suppressed more effectively.

(3)好ましくは、前記スケジュールは、前記需要家の施設における機器の動作内容を含み、前記需要家装置は、前記送信部から受信した前記情報に基づいて、前記機器を制御可能である。   (3) Preferably, the schedule includes an operation content of a device in the facility of the customer, and the customer device can control the device based on the information received from the transmission unit.

このような構成により、たとえば、需要家の施設における機器をスケジュールに沿って確実に動作させることができる。   With such a configuration, for example, the equipment in the facility of the customer can be reliably operated according to the schedule.

(4)好ましくは、各前記需要家は、複数のグループに分類されており、前記作成部は、前記グループごとに前記スケジュールを作成し、前記送信部は、同じ前記グループに属する前記需要家に対応する前記需要家装置へ同じ前記スケジュールに関する前記情報を送信する。   (4) Preferably, each of the customers is classified into a plurality of groups, the creating unit creates the schedule for each of the groups, and the transmitting unit sends the schedule to the customers belonging to the same group. Transmitting the information about the same schedule to the corresponding consumer device;

このような構成により、各需要家が分類されたグループごとに、適切なスケジュールを作成し、実行させることができる。   With such a configuration, an appropriate schedule can be created and executed for each group into which each customer is classified.

(5)より好ましくは、前記複数のグループは、電力からエネルギーを蓄積可能な蓄積装置を有する前記需要家の1または複数のグループと、前記蓄積装置を有しない前記需要家の1または複数のグループとを含む。   (5) More preferably, the plurality of groups are one or more groups of the customers having storage devices capable of storing energy from electric power, and one or more groups of the customers not having the storage devices. And

このような構成により、たとえば、蓄積装置の動作内容を示すスケジュールを作成することができる。   With such a configuration, for example, a schedule indicating the operation content of the storage device can be created.

(6)好ましくは、前記電力管理装置の管理対象となる前記需要家には、前記電力管理装置が作成する前記スケジュールに従うことが要求される契約を結んでいる第1の需要家と、前記スケジュールに従うことが要求される契約を結んでいない第2の需要家とが含まれる。   (6) Preferably, the customer to be managed by the power management device includes a first customer who has a contract required to follow the schedule created by the power management device, And a second customer who does not have a contract required to comply with the above.

このような構成により、たとえば、スケジュールに従うことが要求される需要家に選択的に上記スケジュールを送信することができる。   With such a configuration, for example, the schedule can be selectively transmitted to a customer who is required to follow the schedule.

(7)より好ましくは、前記電力管理装置は、さらに、前記第1の需要家および前記第2の需要家の別に基づいて、対象期間において使用するために調達する電力量を算出する電力量算出部を備える。   (7) More preferably, the power management device further calculates an electric energy to be procured for use in a target period based on the first customer and the second consumer separately. It has a unit.

このような構成により、たとえば、第1の需要家と第2の需要家とで、通常使用する電力量が異なるような場合に、消費される電力量をより正確に把握することができる。   With such a configuration, for example, in the case where the first consumer and the second consumer use different amounts of power, the amount of power consumed can be more accurately grasped.

(8)より好ましくは、前記電力管理装置の管理対象となる前記需要家には、前記電力管理装置が作成する前記スケジュールに従うことが要求される契約を結んでいる第1の需要家と、前記スケジュールに従うことが要求されない契約を結んでいる第2の需要家とが含まれ、前記補正部は、前記スケジュールに従わない旨を応答した前記第1の需要家を、前記第2の需要家とみなして前記補正処理を行う。   (8) More preferably, the customer to be managed by the power management device includes a first customer who has a contract required to follow the schedule created by the power management device, A second customer who has a contract that is not required to follow the schedule is included, and the correction unit associates the first customer who has responded that the schedule is not to be followed with the second customer. The above-described correction processing is performed assuming that the correction processing is performed.

このような構成により、たとえば、単に契約の有無に基づいて上記補正処理を行う場合に比べて、より適切な上記補正処理を行うことができる。   With such a configuration, for example, it is possible to perform the above-described correction process more appropriately than in a case where the above-described correction process is simply performed based on whether or not there is a contract.

(9)より好ましくは、前記第2の電力量の取引単価と、前記補正処理の対象となる電力の取引単価とが異なる、請求項8に記載の電力管理装置。   (9) More preferably, the power management device according to claim 8, wherein a transaction unit price of the second power amount and a transaction unit price of power to be corrected are different.

このような構成により、たとえば、取引単位が変動する市場環境において電力量の取引を行うことができる。   With such a configuration, for example, it is possible to trade electric energy in a market environment in which the transaction unit changes.

(10)好ましくは、前記第1の電力量または前記第2の電力量は、少なくとも前記各需要家の消費電力の統計値に基づいて設定される。   (10) Preferably, the first power amount or the second power amount is set based on at least a statistical value of power consumption of each of the consumers.

このような構成により、各需要家の過去の電力消費の傾向等に基づいて、各需要家において消費される電力量をより正確に把握することができる。   With such a configuration, it is possible to more accurately grasp the amount of power consumed by each customer based on, for example, past power consumption trends of each customer.

(11)好ましくは、前記スケジュールは、前記需要家の施設における機器の動作内容を含み、前記電力管理装置は、さらに、前記スケジュールが含む前記動作内容に沿って前記機器を動作させなかった前記需要家をペナルティーの対象として選択する選択部を備える。   (11) Preferably, the schedule includes an operation content of equipment in the facility of the customer, and the power management apparatus further includes the demand that does not operate the equipment according to the operation content included in the schedule. A selection unit is provided for selecting a house as a penalty target.

このように、スケジュールに沿って機器を動作させなかった需要家にペナルティーを与えることが可能な構成により、スケジュールに従う需要家を増やすことができる。   As described above, with a configuration capable of giving a penalty to a customer who did not operate the device according to the schedule, it is possible to increase the number of customers according to the schedule.

(12)本発明の実施の形態に係る電力管理プログラムは、電力管理装置において用いられる電力管理プログラムであって、コンピュータを、対象期間において使用するために調達する予定の電力量である第1の電力量または前記対象期間において使用するために調達された電力量である第2の電力量に基づいて、前記対象期間における複数の需要家の電力消費に関するスケジュールを作成する作成部と、前記作成部によって作成された前記スケジュールに関する情報を各前記需要家に対応する需要家装置へ送信する送信部として機能させるためのプログラムである。   (12) A power management program according to an embodiment of the present invention is a power management program used in a power management apparatus, and is a first power amount that is to be procured for using a computer in a target period. A creating unit that creates a schedule related to power consumption of a plurality of consumers in the target period based on the amount of power or a second amount of power that is procured for use in the target period; A program for causing the information on the schedule created by the above to function as a transmission unit that transmits the information to the customer device corresponding to each customer.

このような構成により、たとえば、調達済みの電力量または調達予定の電力量と、需要家に供給する電力量とが一致するように、電力消費に関するスケジュールを作成し、作成したスケジュールに従った電力消費を行うように各需要家に要求することができる。したがって、調達した電力量と供給する電力量との不一致を抑えることができる。   With such a configuration, for example, a schedule related to power consumption is created so that the amount of electric power that has already been procured or to be procured matches the amount of electric power to be supplied to the customer, and the power according to the created schedule is generated. Each consumer can be required to consume. Therefore, it is possible to suppress a mismatch between the amount of power that is procured and the amount of power that is supplied.

以下、本発明の実施の形態について図面を用いて説明する。なお、図中同一または相当部分には同一符号を付してその説明は繰り返さない。また、以下に記載する実施形態の少なくとも一部を任意に組み合わせてもよい。   Hereinafter, embodiments of the present invention will be described with reference to the drawings. In the drawings, the same or corresponding portions have the same reference characters allotted, and description thereof will not be repeated. Further, at least some of the embodiments described below may be arbitrarily combined.

<第1の実施の形態>
図1〜図5は、本発明の第1の実施の形態に係る電力管理システムが適用される電力システムの一例について説明するための図である。
<First embodiment>
FIGS. 1 to 5 are diagrams for explaining an example of a power system to which the power management system according to the first embodiment of the present invention is applied.

図1を参照して、電力システム100において、小売事業者3は、発電事業者1が発電した電力を送配電事業者2経由で調達する。小売事業者3は、調達した電力を自己と契約した需要家4へ供給する。小売事業者3が調達する電力の量は、たとえば、図示しない卸電力市場において購入した量である。   Referring to FIG. 1, in power system 100, retailer 3 procures power generated by power generator 1 via power transmission and distribution provider 2. The retailer 3 supplies the procured power to the customer 4 who has contracted with the retailer. The amount of power procured by the retailer 3 is, for example, the amount purchased in a wholesale power market (not shown).

図2を参照して、たとえば、小売事業者3が、対象期間において需要家4へ供給する予定で100の電力量を調達していたとする。この場合において、需要家4の対象期間における消費電力量が100であったとき、小売事業者3は事前に調達した100の電力量を需要家4へ供給する。   Referring to FIG. 2, for example, it is assumed that retailer 3 has procured 100 electric energy to supply to customer 4 in the target period. In this case, when the power consumption of the customer 4 in the target period is 100, the retailer 3 supplies the customer 4 with 100 power amounts procured in advance.

ここで、需要家4の対象期間における消費電力量が100を上回った場合、送配電事業者2が不足分の電力量を需要家4へ供給する。具体的には、図3を参照して、小売事業者3が調達していた100の電力量を上回る120の電力量を需要家4が消費した場合、送配電事業者2が不足分の20の電力量を需要家4へ供給する。   Here, when the power consumption of the customer 4 in the target period exceeds 100, the power transmission and distribution company 2 supplies the insufficient power to the customer 4. Specifically, referring to FIG. 3, when the consumer 4 consumes 120 electric powers, which exceeds the 100 electric powers that the retailer 3 has procured, the power transmission and distribution operator 2 has a shortage of 20%. Is supplied to the customer 4.

たとえば、小売事業者3が対象期間において計画値同時同量を達成できなかった場合、当該小売事業者3にはペナルティーが与えられる。ここで、計画値同時同量とは、たとえば、小売事業者3が調達した電力量と、需要家4において消費される電力量つまり小売事業者3が需要家4へ供給する電力量とを一致させることである。以下、小売事業者3が調達した電力量と、需要家4において消費される電力量とが一致しない状態をインバランスとも称する。   For example, if the retailer 3 has failed to achieve the same planned amount during the target period, the retailer 3 is given a penalty. Here, the “simultaneous planned value amount” means, for example, that the amount of power procured by the retailer 3 and the amount of power consumed by the customer 4, that is, the amount of power supplied by the retailer 3 to the customer 4 are the same. It is to make it. Hereinafter, a state in which the amount of power procured by the retailer 3 and the amount of power consumed by the customer 4 do not match is also referred to as imbalance.

計画値同時同量を達成できなかった場合のペナルティーについて、以下に説明する。図4を参照して、小売事業者3が調達した電力量より需要家4の消費電力量が少なかった場合、つまり小売事業者3において電力量が余剰となった場合、小売事業者3は、余剰となった電力量を所定価格で売却することができる。ただし、余剰となった電力のうち、調達した電力量の3%を上回った分については、たとえば送配電事業者2に無料で引き取られる。   The penalty for failing to achieve the same planned amount is described below. Referring to FIG. 4, when the power consumption of the customer 4 is smaller than the power amount procured by the retailer 3, that is, when the power amount becomes surplus in the retailer 3, the retailer 3 The surplus electric energy can be sold at a predetermined price. However, of the surplus power, the power exceeding 3% of the procured power is taken free of charge by, for example, the power transmission and distribution company 2.

一方、小売事業者3が調達した電力量より需要家4の消費電力量が多かった場合、つまり需要家4に供給する電力量が不足した場合、上述のように、不足分の電力量は送配電事業者2が需要家4へ供給する。そして、小売事業者3は、送配電事業者2にインバランス料金を支払う。ここで、電力量の不足分が、小売事業者3が事前に調達した電力量の3%以下である場合、インバランス料金は比較的安価である。これに対して、電力量の不足分が、小売事業者3が事前に調達した電力量の3%を上回る場合、インバランス料金は高額となる。   On the other hand, when the power consumption of the customer 4 is larger than the power procured by the retailer 3, that is, when the power supplied to the customer 4 is insufficient, the insufficient power is transmitted as described above. The power distribution company 2 supplies the customer 4. Then, the retailer 3 pays the imbalance fee to the power transmission and distribution company 2. Here, when the shortage of the electric energy is 3% or less of the electric energy procured in advance by the retailer 3, the imbalance fee is relatively low. On the other hand, when the shortage of the electric energy exceeds 3% of the electric energy previously procured by the retailer 3, the imbalance fee becomes high.

また、小売事業者3は、卸電力市場における取引によって、対象期間に需要家4へ供給するための電力を調達する。卸電力市場には、翌日に使用される電力の取引を行うスポット市場、および約1時間後に使用される電力の取引を行う1時間前市場等、複数種類の市場が存在する。   In addition, the retailer 3 procures electric power to be supplied to the customer 4 during the target period by a transaction in the wholesale electric power market. In the wholesale power market, there are a plurality of types of markets, such as a spot market for trading electric power used the next day and a market one hour before trading electric power used about one hour later.

小売事業者3は、たとえば、需要家4への電力量の供給計画を所定のタイミングで送配電事業者2へ提出する。具体的には、図5を参照して、たとえば、小売事業者3は、スポット市場の閉場後、対象期間における電力量の供給計画である1日前計画を送配電事業者2へ提出する。また、小売事業者3は、1時間前市場の閉場後、対象期間における電力量の供給計画である1時間前計画を送配電事業者2へ提出する。   The retailer 3 submits a power supply plan to the customer 4 to the power transmission and distribution company 2 at a predetermined timing, for example. Specifically, referring to FIG. 5, for example, after closing of the spot market, the retailer 3 submits a one-day plan, which is a power supply plan in the target period, to the power transmission and distribution company 2. Further, after the market closes one hour ago, the retailer 3 submits the one-hour plan, which is the power supply plan for the target period, to the power transmission and distribution company 2.

図6は、本発明の第1の実施の形態に係る電力管理システムの構成を示す図である。   FIG. 6 is a diagram illustrating a configuration of the power management system according to the first embodiment of the present invention.

図6を参照して、電力管理システム101は、複数の需要家装置11と、複数の機器14と、発電事業サーバ21と、送配電事業サーバ22と、電力管理装置23と、市場サーバ25とを備える。   Referring to FIG. 6, power management system 101 includes a plurality of customer devices 11, a plurality of devices 14, a power generation business server 21, a power transmission and distribution business server 22, a power management device 23, and a market server 25. Is provided.

1つの需要家装置11および複数の機器14が、一般家庭等の需要施設10において設置される。需要施設10は、需要家4によって使用される。   One customer device 11 and a plurality of devices 14 are installed in a demand facility 10 such as a general home. The demand facility 10 is used by the customer 4.

需要家装置11および各機器14は、電力管理装置23の管理対象である複数の需要施設10においてそれぞれ設置される。たとえば、需要家装置11は、HEMS(Home Energy Management System)におけるゲートウェイ装置であり、機器14は、空調機器、照明機器または給湯器等である。   The customer device 11 and each device 14 are installed in a plurality of demand facilities 10 that are managed by the power management device 23, respectively. For example, the customer device 11 is a gateway device in a HEMS (Home Energy Management System), and the device 14 is an air conditioner, a lighting device, a water heater, or the like.

発電事業サーバ21は、たとえば発電事業者1によって運用され、ネットワーク8経由で他の装置と接続される。   The power generation business server 21 is operated by, for example, the power generation company 1 and is connected to another device via the network 8.

送配電事業サーバ22は、たとえば送配電事業者2によって運用され、ネットワーク8経由で他の装置と接続される。   The power transmission and distribution business server 22 is operated by, for example, the power transmission and distribution business operator 2 and is connected to other devices via the network 8.

電力管理装置23は、たとえば発電事業者1によって運用され、ネットワーク8経由で他の装置と接続される。   The power management apparatus 23 is operated by, for example, the power generation company 1 and is connected to another apparatus via the network 8.

市場サーバ25は、たとえば卸電力市場5の管理者によって運用され、ネットワーク8経由で他の装置と接続される。   Market server 25 is operated, for example, by the administrator of wholesale power market 5, and is connected to other devices via network 8.

たとえば、発電事業サーバ21および電力管理装置23は、市場サーバ25と通信することにより、発電事業者1および小売事業者3の卸電力市場5における電力量の取引に関する処理を行う。   For example, the power generation business server 21 and the power management apparatus 23 communicate with the market server 25 to perform processing relating to the transaction of the amount of power in the wholesale power market 5 of the power generation business 1 and the retail business 3.

電力管理装置23は、各需要家4の電力消費のパターンおよび電力消費に関する統計値、ならびに気象予報情報に基づいて、各需要施設10の全体の1時間毎の消費電力量を予測する。以下、対象期間における1時間毎の、各需要施設10の全体の消費電力量を時間毎総量Ttとも称する。   The power management apparatus 23 predicts the hourly power consumption of the entire demand facility 10 based on the power consumption pattern and the statistical value related to the power consumption of each customer 4 and the weather forecast information. Hereinafter, the total power consumption of each demand facility 10 for each hour in the target period is also referred to as a total amount per hour Tt.

卸電力市場5においては、たとえば、未来において消費される予定の1時間毎の電力量を取引することが可能である。電力管理装置23は、予測した時間毎総量Ttに基づいて、対象期間における1時間毎の電力量を卸電力市場5において調達する。   In the wholesale power market 5, for example, it is possible to trade an hourly power amount scheduled to be consumed in the future. The power management apparatus 23 procures the hourly power amount in the wholesale power market 5 in the target period based on the predicted hourly total amount Tt.

以下、卸電力市場5において調達する予定の1時間ごとの電力量を時間毎調達予定量Ctとも称する。   Hereinafter, the hourly power amount scheduled to be procured in the wholesale power market 5 is also referred to as an hourly procured scheduled amount Ct.

たとえば、時間毎調達予定量Ctは、以下の式(1)で表される。ただし、Tatは上述の時間毎総量Ttの予測値であり、Btは卸電力市場5における電力量の単価に応じて決定される電力量の追加購入分である。たとえば、電力管理装置23は、卸電力市場5における電力量の単価が安いほど、追加購入分Btを大きく設定する。
Ct=Tat+Bt ・・・(1)
For example, the scheduled procurement amount Ct per hour is represented by the following equation (1). Here, Tat is a predicted value of the above-mentioned total amount per hour Tt, and Bt is an additional purchase of the electric energy determined according to the unit price of the electric energy in the wholesale electric power market 5. For example, the power management apparatus 23 sets the additional purchase Bt to be larger as the unit price of the electric energy in the wholesale power market 5 is lower.
Ct = Tat + Bt (1)

具体的には、電力管理装置23は、市場サーバ25と通信することにより、卸電力市場5におけるスポット市場において、時間毎調達予定量Ctと等しい電力量を調達する。   Specifically, the power management apparatus 23 communicates with the market server 25 to procure a power amount equal to the scheduled procurement amount per hour Ct in the spot market in the wholesale power market 5.

以下、卸電力市場5において調達した1時間毎の電力量を時間毎調達量Ptとも称する。   Hereinafter, the hourly power amount procured in the wholesale power market 5 is also referred to as hourly procured amount Pt.

電力管理装置23は、対象期間における時間毎調達量Ptに基づいて、需要施設10における各機器14の動作内容を規定するスケジュールYを作成する。スケジュールYについては後述する。   The power management apparatus 23 creates a schedule Y that specifies the operation of each device 14 in the demand facility 10 based on the hourly procured amount Pt in the target period. Schedule Y will be described later.

電力管理装置23は、作成したスケジュールYを各需要施設10における需要家装置11に通知することにより、スケジュールYに従うこと、すなわち各機器14をスケジュールYに従って動作させることを需要家4に要求する。   The power management apparatus 23 notifies the customer apparatus 11 in each demand facility 10 of the created schedule Y, thereby requesting the customer 4 to follow the schedule Y, that is, to operate each device 14 according to the schedule Y.

需要家4は、需要家装置11が通知された当該スケジュールYを確認し、当該スケジュールYに従うか否かを判断する。需要家4は、電力管理装置23からの要求に対する応答として、当該スケジュールYに従うか否かの判断結果を需要家装置11から電力管理装置23に通知する。   The customer 4 checks the schedule Y notified by the customer device 11 and determines whether or not to follow the schedule Y. The customer 4 notifies the power management apparatus 23 of the result of the determination as to whether or not to comply with the schedule Y in response to the request from the power management apparatus 23.

以下、スケジュールYに従う旨の応答を行った需要家4を参加需要家Pとも称し、スケジュールYに従わない旨の応答を行った需要家4を不参加需要家Nとも称する。   Hereinafter, the customer 4 that has responded to the schedule Y is also referred to as a participating customer P, and the customer 4 that has responded not to the schedule Y is also referred to as a non-participating customer N.

参加需要家Pの需要施設10においては、たとえば、需要家装置11が各機器14をスケジュールYに沿って自動制御する。そして、たとえば後日、スケジュールYに従ったことに対する対価が参加需要家Pに与えられる。   In the demand facility 10 of the participating customer P, for example, the customer device 11 automatically controls each device 14 according to the schedule Y. Then, for example, at a later date, a price for following the schedule Y is given to the participating customers P.

ここで、電力管理装置23が需要家4にスケジュールYに従うことを要求し、スケジュールYに従った需要家4が対価を取得する仕組みをDRプログラムとも称する。   Here, a mechanism in which the power management apparatus 23 requests the customer 4 to follow the schedule Y, and the customer 4 according to the schedule Y acquires the price is also referred to as a DR program.

需要家4は、たとえば、小売事業者3と所定の契約を結んだ場合に、DRプログラムの適用を受けることが可能となる。以下、小売事業者3と当該契約を結んだ需要家4を契約需要家Kとも称し、当該契約を結んでいない需要家4を未契約需要家Mとも称する。   The customer 4 can receive the DR program when, for example, a predetermined contract is made with the retailer 3. Hereinafter, the customer 4 that has made the contract with the retailer 3 is also referred to as a contract customer K, and the customer 4 that has not made the contract is also referred to as an uncontracted customer M.

すなわち、電力管理装置23の管理対象となる需要家4には、スケジュールYに従うことが要求される契約を結んでいる契約需要家Kと、スケジュールYに従うことが要求される契約を結んでいない未契約需要家Mとが含まれる。   That is, the customer 4 to be managed by the power management apparatus 23 has a contract customer K who has a contract that is required to follow the schedule Y and a customer who has not made a contract that is required to follow the schedule Y. Contract customer M is included.

図7〜図9は、本発明の第1の実施の形態に係る電力管理システムにおいて電力管理装置が作成するスケジュールYについて説明するための図である。   FIGS. 7 to 9 are diagrams for explaining the schedule Y created by the power management device in the power management system according to the first embodiment of the present invention.

図7を参照して、電力管理装置23は、各契約需要家Kをグループg1、グループg2およびグループg3のいずれか1つに予め分類する。   Referring to FIG. 7, power management apparatus 23 classifies each contract customer K into any one of group g1, group g2, and group g3 in advance.

具体的には、電力管理装置23は、需要施設10において設置された機器14の種類に基づいて、各契約需要家Kをグループg1〜g3のいずれかに分類する。   Specifically, the power management apparatus 23 classifies each contract customer K into one of the groups g1 to g3 based on the type of the device 14 installed in the demand facility 10.

たとえば、電力管理装置23は、需要施設10において電力貯蔵用の蓄電装置を備え、かつ給湯器を備えない契約需要家Kをグループg1に分類する。また、たとえば、電力管理装置23は、需要施設10において電力貯蔵用の蓄電装置および給湯器の両方を備える契約需要家Kをグループg2に分類する。また、たとえば、電力管理装置23は、需要施設10において電力貯蔵用の蓄電装置、および給湯器のいずれも備えない需要家4をグループg3に分類する。   For example, the power management apparatus 23 classifies the contract customer K that includes the power storage device for storing power in the demand facility 10 and does not include the water heater into the group g1. Further, for example, the power management apparatus 23 classifies the contract customer K including both the power storage device for storing power and the water heater in the demand facility 10 into the group g2. Further, for example, the power management apparatus 23 classifies the customers 4 that do not include any of the power storage device for storing power and the water heater in the demand facility 10 into the group g3.

すなわち、グループg1〜g3は、電力貯蔵用の蓄電装置すなわち電力からエネルギーを蓄積可能な蓄積装置を有する契約需要家Kのグループと、当該蓄電装置を有しない契約需要家Kのグループとを含む。なお、電力管理装置23は、各契約需要家Kを3つのグループのいずれかに分類する構成に限らず、2つのグループのいずれかに分類する構成であってもよいし、4つ以上のグループのいずれかに分類する構成であってもよい。具体的には、たとえば、電力管理装置23は、電力貯蔵用の蓄電装置および給湯器のいずれも備えない需要家4をより細かくグループ分けしてもよい。   That is, the groups g1 to g3 include a group of contract customers K having a power storage device for storing power, that is, a storage device capable of storing energy from electric power, and a group of contract customers K not having the power storage device. Note that the power management apparatus 23 is not limited to a configuration in which each contract customer K is classified into any one of the three groups, and may be a configuration in which each contract customer K is classified into any one of the two groups. May be adopted. Specifically, for example, the power management apparatus 23 may further subdivide the customers 4 that do not include any of the power storage device for storing power and the water heater.

次に、図8を参照して、電力管理装置23は、スケジュールYを作成する際、まず、時間毎調達量Ptを契約需要家K全体および未契約需要家M全体に割り当てる。具体的には、たとえば、電力管理装置23は、契約需要家Kの数および未契約需要家Mの数の割合に基づいて、時間毎調達量Ptのうちの契約需要家K全体に割り当てる量と未契約需要家M全体に割り当てる量とを決定する。   Next, with reference to FIG. 8, when creating the schedule Y, the power management apparatus 23 first allocates the hourly procured amount Pt to the entire contract customer K and the entire non-contract customer M. Specifically, for example, the power management apparatus 23 determines, based on the ratio of the number of contract customers K and the number of uncontract customers M, the amount to be allocated to the entire contract customer K in the hourly procured amount Pt. The amount to be assigned to the entire uncontracted customer M is determined.

以下、時間毎調達量Ptのうち、契約需要家K全体に割り当てた分を時間毎割当量Akとも称し、未契約需要家M全体に割り当てた分を時間毎割当量Amとも称する。   Hereinafter, of the hourly procured amount Pt, the amount allocated to the entire contract customer K is also referred to as the hourly allocated amount Ak, and the amount allocated to the entire uncontracted customer M is also referred to as the hourly allocated amount Am.

電力管理装置23は、時間毎割当量Akに基づいて、グループg1〜g3の各々についてのスケジュールYを作成する。   The power management apparatus 23 creates a schedule Y for each of the groups g1 to g3 based on the hourly allocated amount Ak.

図9は、グループg1〜g3の各々についてのスケジュールYの一例を示している。たとえば、スケジュールYは、需要施設10における1時間刻みの機器14の動作内容を規定している。ここでは、スケジュールYは、各機器14の動作の有無を規定している。   FIG. 9 shows an example of the schedule Y for each of the groups g1 to g3. For example, the schedule Y specifies the operation contents of the device 14 in the demand facility 10 at one-hour intervals. Here, the schedule Y defines whether or not each device 14 operates.

電力管理装置23は、たとえば、時間毎割当量Akが、各契約需要家Kの全体において過不足なく消費されるように、グループg1〜g3のそれぞれに対応するスケジュールYを作成する。たとえば、電力管理装置23は、線形計画法等の最適化手法を用いて各スケジュールYを作成する。   The power management apparatus 23 creates a schedule Y corresponding to each of the groups g1 to g3 so that, for example, the hourly allocated amount Ak is consumed by the contract customers K as a whole without excess or deficiency. For example, the power management apparatus 23 creates each schedule Y using an optimization method such as a linear programming method.

スケジュールYに従う旨の応答を行った契約需要家Kすなわち参加需要家Pの需要施設10においては、たとえば、上述のように、需要家装置11が各機器14をスケジュールYに沿って自動制御する。   In the demand facility 10 of the contract customer K who has responded to the schedule Y, that is, the demand facility 10 of the participant customer P, for example, the customer device 11 automatically controls each device 14 according to the schedule Y as described above.

したがって、参加需要家Pの需要施設10においては、スケジュールYに沿った電力消費が行われる。つまり、参加需要家Pの需要施設10においては、対象期間の到来より前に、対象期間における1時間毎の消費電力量が確定する。以下、消費されることが確定した、1時間ごとの電力量を時間毎確定量Dtとも称する。   Therefore, in the demand facility 10 of the participating customer P, power consumption is performed according to the schedule Y. That is, in the demand facility 10 of the participating customer P, the power consumption for each hour in the target period is determined before the arrival of the target period. Hereinafter, the amount of electric power for each hour, which is determined to be consumed, is also referred to as a fixed amount per hour Dt.

再び図6を参照して、電力管理装置23は、各契約需要家Kに提示したスケジュールYおよび各契約需要家Kの応答に基づいて、時間毎確定量Dtを算出する。   Referring to FIG. 6 again, power management device 23 calculates hourly determined amount Dt based on schedule Y presented to each contract customer K and a response from each contract customer K.

次に、電力管理装置23は、たとえば、各需要家4の電力消費のパターンおよび電力消費に関する統計値、ならびに気象予報情報に基づいて、対象期間における、各未契約需要家Mおよび各不参加需要家Nの全体の1時間毎の消費電力量を予測する。以下、予測された、1時間毎の当該消費電力量を時間毎予測量Otとも称する。   Next, the power management apparatus 23, for example, based on the power consumption pattern and the statistical value of the power consumption of each customer 4 and the weather forecast information, each uncontracted customer M and each non-participating customer in the target period. The power consumption per hour for the entire N is predicted. Hereinafter, the estimated power consumption per hour is also referred to as an hourly predicted amount Ot.

そして、電力管理装置23は、対象期間における時間毎予測量Otに、対応する時間の時間毎確定量Dtを加えることにより、時間毎総量Ttの予測値を算出し直す。以下、算出し直した時間毎総量Ttの予測値を時間毎総予測量Rtとも称する。   Then, the power management apparatus 23 recalculates the predicted value of the hourly total amount Tt by adding the hourly determined amount Dt of the corresponding time to the hourly predicted amount Ot in the target period. Hereinafter, the predicted value of the recalculated total amount per hour Tt is also referred to as a total predicted amount per hour Rt.

すなわち、時間毎総予測量Rtは、以下の式(2)で表される。だたし、Dtは時間毎確定量Dtであり、Otは時間毎予測量Otである。
Rt=Dt+Ot ・・・(2)
That is, the hourly total predicted amount Rt is represented by the following equation (2). However, Dt is the hourly determined amount Dt, and Ot is the hourly predicted amount Ot.
Rt = Dt + Ot (2)

スケジュールYに従う旨の応答をした契約需要家Kすなわち参加需要家Pが多いほど時間毎総予測量Rtにおける時間毎確定量Dtの割合が大きくなる。したがって、電力管理装置23は、参加需要家Pが多いほど、正確な時間毎総予測量Rtを算出することができる。   The greater the number of contract customers K that respond to the schedule Y, that is, the number of participating customers P, the greater the proportion of the hourly confirmed amount Dt in the hourly total predicted amount Rt. Therefore, the power management apparatus 23 can calculate the accurate hourly total predicted amount Rt as the number of participating customers P increases.

図10は、本発明の第1の実施の形態に係る電力管理システムにおける、参加需要家Pの数とインバランスのリスクとの関係を示す図である。   FIG. 10 is a diagram illustrating a relationship between the number of participating customers P and imbalance risk in the power management system according to the first embodiment of the present invention.

図10を参照して、参加需要家Pが多いほど、すなわち契約需要家Kにおける参加需要家Pの割合が大きいほど、正確な時間毎総予測量Rtを算出することができるため、インバランスのリスクを抑えることができる。具体的には、状態1から状態3のうち、最も参加需要家Pの少ない状態1が最もインバランスのリスクが高く、次に参加需要家Pが少ない状態2が次にインバランスのリスクが高く、最も参加需要家Pの多い状態3が最もインバランスのリスクが低い。   Referring to FIG. 10, as the number of participating customers P increases, that is, as the ratio of participating customers P in contract customers K increases, accurate hourly total predicted amount Rt can be calculated. Risk can be reduced. Specifically, among the states 1 to 3, the state 1 with the least participating customers P has the highest imbalance risk, and the state 2 with the next least participating customers P has the next highest imbalance risk. State 3 with the largest number of participating consumers P has the lowest imbalance risk.

図11は、本発明の第1の実施の形態に係る電力管理システムにおける、インバランスのリスクについて説明するための図である。   FIG. 11 is a diagram for describing an imbalance risk in the power management system according to the first embodiment of the present invention.

図11は、調達済みの電力量である時間毎調達量Ptと時間毎総予測量Rtとを比較して示している。   FIG. 11 shows a comparison between the hourly procured amount Pt, which is the amount of power that has been procured, and the hourly total predicted amount Rt.

図11を参照して、時間毎総予測量Rtより時間毎調達量Ptの方が大きい場合、対象の時間において、供給可能な電力が余剰となる可能性が高い。したがって、電力管理装置23は、時間毎調達量Ptおよび時間毎総予測量Rtの差分である電力量SAを卸電力市場5において売却する。   Referring to FIG. 11, when the hourly procured amount Pt is larger than the hourly total predicted amount Rt, there is a high possibility that the power that can be supplied becomes excessive at the target time. Therefore, the power management apparatus 23 sells the power amount SA, which is the difference between the hourly procured amount Pt and the hourly total predicted amount Rt, in the wholesale power market 5.

具体的には、電力管理装置23は、スポット市場で調達した時間毎調達量Ptのうち、電力量SAを売却することにより、時間毎調達量Ptの補正処理H1を行う。   Specifically, the power management apparatus 23 performs the correction process H1 of the hourly procured amount Pt by selling the electric energy SA among the hourly procured amount Pt procured in the spot market.

また、たとえば、時間毎総予測量Rtより時間毎調達量Ptの方が少ない場合、対象の時間において供給可能な電力が不足する可能性が高い。したがって、電力管理装置23は、時間毎調達量Ptに対する時間毎総予測量Rtの不足分を卸電力市場5において購入する。   Further, for example, when the hourly procured amount Pt is smaller than the hourly total predicted amount Rt, there is a high possibility that the power that can be supplied at the target time is insufficient. Therefore, the power management apparatus 23 purchases the shortage of the hourly total predicted amount Rt with respect to the hourly procured amount Pt in the wholesale power market 5.

具体的には、電力管理装置23は、時間毎調達量Ptに追加して、不足することが予想される分の電力量を購入することにより、時間毎調達量Ptの補正処理H1を行う。   Specifically, the power management apparatus 23 performs the correction process H1 of the hourly procurement amount Pt by purchasing an amount of power that is expected to be insufficient in addition to the hourly procurement amount Pt.

このように、電力管理装置23は、補正処理H1を行うことで、インバランスの発生を抑えることができる。なお、電力管理装置23は、補正処理H1を行うことによって、時間毎総予測量Rtと時間毎調達量Ptとを一致させる構成に限らず、時間毎総予測量Rtと時間毎調達量Ptとを同等にする構成であればよい。   As described above, the power management device 23 can suppress the occurrence of imbalance by performing the correction process H1. Note that the power management apparatus 23 is not limited to the configuration in which the hourly total predicted amount Rt and the hourly procurement amount Pt are made to match by performing the correction process H1. Any configuration may be used as long as they are equal.

図12は、本発明の第1の実施の形態に係る電力管理システムにおける電力管理処理を示すシーケンス図である。   FIG. 12 is a sequence diagram illustrating power management processing in the power management system according to the first embodiment of the present invention.

電力管理システムにおける各装置は、コンピュータを備え、当該コンピュータにおけるCPU等の演算処理部は、以下のシーケンスの各ステップの一部または全部を含むプログラムを図示しないメモリから読み出して実行する。これら複数の装置のプログラムは、それぞれ、外部からインストールすることができる。これら複数の装置のプログラムは、それぞれ、記録媒体に格納された状態で流通する。   Each device in the power management system includes a computer, and an arithmetic processing unit such as a CPU in the computer reads a program including a part or all of each step of the following sequence from a memory (not shown) and executes the program. Each of the programs of the plurality of devices can be externally installed. The programs of the plurality of devices are distributed while being stored in a recording medium.

電力管理システム101は、たとえば複数の需要家装置11を備えるが、ここでは、代表的に1個の需要家装置11について示す。   The power management system 101 includes, for example, a plurality of customer devices 11. Here, one customer device 11 is representatively shown.

図12を参照して、まず、電力管理装置23は、各需要家4の電力消費のパターンおよび電力消費に関する統計値、ならびに気象予報情報等に基づいて、時間毎総量Ttを予測する(ステップS11)。なお、電力管理装置23は、たとえば、契約需要家Kの数および未契約需要家Mの数の割合等にさらに基づいて、時間毎総量Ttを予測する構成であってもよい。   Referring to FIG. 12, first, power management device 23 predicts hourly total amount Tt based on a pattern of power consumption of each customer 4, a statistical value related to power consumption, weather forecast information, and the like (step S <b> 11). ). In addition, the power management apparatus 23 may be configured to predict the total amount per time Tt further based on, for example, the ratio of the number of contract customers K and the number of uncontract customers M.

次に、電力管理装置23は、市場サーバ25と通信を行うことにより、対象期間に需要施設10において使用される予定の電力量を卸電力市場5において調達する(ステップS12)。具体的には、電力管理装置23は、卸電力市場5のスポット市場において、対象期間における1時間毎の電力量を調達する。   Next, the power management apparatus 23 communicates with the market server 25 to procure the amount of power to be used in the demand facility 10 in the target period in the wholesale power market 5 (step S12). Specifically, the power management apparatus 23 procures an hourly power amount in the target period in the spot market of the wholesale power market 5.

次に、電力管理装置23は、スポット市場の閉場後、対象期間における電力量の供給計画を示す1日前計画情報を送配電事業サーバ22へ送信する。   Next, after the closing of the spot market, the power management apparatus 23 transmits, to the power transmission and distribution business server 22, one-day plan information indicating a power supply plan in the target period.

次に、電力管理装置23は、スポット市場において調達した1時間ごとの電力量すなわち時間毎調達量Ptに基づいて、需要施設10における各機器14の動作内容を規定するスケジュールYを作成する(ステップS14)。具体的には、電力管理装置23は、事前に分類されたグループg1〜g3の各々についてのスケジュールYを作成する。   Next, the power management apparatus 23 creates a schedule Y that specifies the operation of each device 14 in the demand facility 10 based on the hourly power amount procured in the spot market, that is, the hourly procured amount Pt (step). S14). Specifically, the power management apparatus 23 creates a schedule Y for each of the groups g1 to g3 classified in advance.

次に、電力管理装置23は、スケジュールYに関する情報であるスケジュール情報を対応の需要家装置11へ送信する(ステップS15)。たとえば、スケジュール情報は、送信先の需要家装置11に対応するスケジュールYを含み、当該スケジュールYに従うことを要求する情報である。   Next, the power management apparatus 23 transmits schedule information, which is information on the schedule Y, to the corresponding customer apparatus 11 (Step S15). For example, the schedule information includes schedule Y corresponding to the customer device 11 of the transmission destination, and is information that requests that the schedule device Y be followed.

次に、需要家装置11は、電力管理装置23からスケジュール情報を受信して、受信したスケジュール情報が示すスケジュールYをディスプレイ等に表示する。需要家4は、当該ディスプレイに表示されたスケジュールYを確認し、需要家装置11を操作してスケジュールYに従うか否かを当該需要家装置11に入力する。   Next, the consumer device 11 receives the schedule information from the power management device 23, and displays the schedule Y indicated by the received schedule information on a display or the like. The customer 4 confirms the schedule Y displayed on the display and operates the customer device 11 to input into the customer device 11 whether or not to follow the schedule Y.

次に、需要家装置11は、需要家4による操作を受付け(ステップS16)、受け付けた操作内容に基づいて、スケジュールYに従うか否かを示すスケジュール応答を電力管理装置23へ送信する(ステップS17)。   Next, the customer device 11 receives the operation by the customer 4 (step S16), and transmits a schedule response indicating whether or not to follow the schedule Y to the power management device 23 based on the received operation content (step S17). ).

次に、電力管理装置23は、需要家装置11から受信したスケジュール応答に基づいて、時間毎総予測量Rtを算出する(ステップS18)。   Next, the power management apparatus 23 calculates the hourly total predicted amount Rt based on the schedule response received from the customer apparatus 11 (Step S18).

次に、電力管理装置23は、算出した時間毎総予測量Rtに基づいて、時間毎調達量Ptの補正処理H1を行う(ステップS19)。具体的には、電力管理装置23は、市場サーバ25と通信することにより、1時間前市場において、時間毎調達量Ptの一部を売却するか、または時間毎調達量Ptに追加して電力量を購入する。ここで、スポット市場における電力量の取引単価と1時間前市場における電力量の取引単価とは異なることがある。   Next, the power management apparatus 23 performs a correction process H1 of the hourly procured amount Pt based on the calculated hourly total estimated amount Rt (step S19). Specifically, the power management apparatus 23 communicates with the market server 25 to sell a part of the hourly procured amount Pt or add to the hourly procured amount Pt to Buy quantity. Here, the transaction unit price of the electric energy in the spot market may be different from the transaction unit price of the electric energy in the market one hour ago.

次に、電力管理装置23は、卸電力市場5における1時間前市場の閉場後、対象期間における電力量の供給計画を示す1時間前計画情報を送配電事業サーバ22へ送信する(ステップS20)。   Next, after the market closes one hour ago in the wholesale power market 5, the power management apparatus 23 transmits one-hour-before-plan information indicating the power supply plan in the target period to the power transmission and distribution business server 22 (step S <b> 20). .

なお、電力管理装置23は、たとえば、卸電力市場5における1時間前市場の閉場前に、時間毎総予測量Rtに基づいて再度スケジュールYを作成し、作成したスケジュールYに関するスケジュール情報を需要家装置11へ送信する構成であってもよい。この場合も、同様に、需要家装置11は、電力管理装置23からスケジュール情報を受信して表示した後、需要家4の操作を受付け、需要家4の操作に応じた内容のスケジュール応答を電力管理装置23へ送信する。電力管理装置23は、需要家装置11から受信したスケジュール応答に基づいて、時間毎総予測量Rtを再度算出する。そして、電力管理装置23は、算出した時間毎総予測量Rtに基づいて、時間毎調達量Ptの補正処理H1を行う。   Note that the power management apparatus 23 creates the schedule Y again based on the hourly total predicted amount Rt before closing the market one hour before in the wholesale power market 5, and transmits the schedule information on the created schedule Y to the customer. It may be configured to transmit to the device 11. Also in this case, similarly, after receiving and displaying the schedule information from the power management device 23, the customer device 11 accepts the operation of the customer 4, and transmits the schedule response having the content corresponding to the operation of the customer 4 to the power device. It is transmitted to the management device 23. The power management device 23 calculates the hourly total predicted amount Rt again based on the schedule response received from the customer device 11. Then, the power management apparatus 23 performs a correction process H1 of the hourly procured amount Pt based on the calculated hourly total predicted amount Rt.

次に、電力管理装置23は、スケジュールYに従う旨のスケジュール応答を自己へ送信した需要家装置11、すなわち参加需要家Pの需要家装置11に対応する制御情報を作成する。具体的には、電力管理装置23は、当該需要家装置11へ送信したスケジュール情報(ステップS15)の内容に基づいて、各機器14を動作させるための制御情報を作成する。そして、電力管理装置23は、たとえば対象期間になると、作成した制御情報を需要家装置11へ送信する(ステップS21)。   Next, the power management apparatus 23 creates control information corresponding to the customer apparatus 11 that has transmitted a schedule response indicating that it follows the schedule Y to itself, that is, the customer apparatus 11 of the participating customer P. Specifically, the power management apparatus 23 creates control information for operating each device 14 based on the contents of the schedule information (step S15) transmitted to the customer apparatus 11. Then, for example, in the target period, the power management apparatus 23 transmits the created control information to the customer apparatus 11 (Step S21).

次に、需要家装置11は、電力管理装置23から制御情報を受信して、受信した制御情報に基づいて、自己の需要施設10における機器14を制御する(ステップS22)。   Next, the customer device 11 receives the control information from the power management device 23, and controls the devices 14 in its own demand facility 10 based on the received control information (step S22).

次に、需要家装置11は、たとえば対象期間の終了後、各機器14がスケジュールYに沿って動作したか否かを示す報告情報を電力管理装置23へ送信する(ステップS23)。たとえば、機器14がスケジュールYに沿った動作を行っている最中に、需要家4が当該機器14を手動で停止した等の場合、報告情報は、当該機器14がスケジュールYに沿った動作を行わなかった旨を示す。   Next, for example, after the end of the target period, the customer device 11 transmits report information indicating whether each device 14 has operated according to the schedule Y to the power management device 23 (Step S23). For example, if the customer 4 manually stops the device 14 while the device 14 is performing the operation according to the schedule Y, the report information indicates that the device 14 has performed the operation according to the schedule Y. Indicates not performed.

次に、電力管理装置23は、需要家装置11から報告情報を受信して、受信した報告情報に基づいて、対価が与えられるべき需要家4を選択する選択処理を行う(ステップS24)。具体的には、たとえば、電力管理装置23は、各機器14がスケジュールYに沿った動作を行った需要施設10の需要家4を、対価が与えられるべき需要家4として選択する。電力管理装置23が選択した需要家4には、後日、発電事業者1から対価が与えられる。   Next, the power management apparatus 23 receives the report information from the customer apparatus 11, and performs a selection process of selecting the customer 4 to be given a fee based on the received report information (Step S24). Specifically, for example, the power management apparatus 23 selects the customer 4 of the demand facility 10 in which each device 14 has performed the operation in accordance with the schedule Y as the customer 4 to whom the consideration should be given. The customer 4 selected by the power management apparatus 23 is given a fee from the power generation company 1 at a later date.

なお、電力管理装置23は、受信した報告情報に基づいて、ペナルティーを与えるべき需要家4を選択する選択処理を行う構成であってもよい。具体的には、たとえば、電力管理装置23は、少なくとも一部の機器14がスケジュールYに沿った動作を行わなかった需要施設10の需要家4を、ペナルティーが与えられるべき需要家4として選択する。   In addition, the power management apparatus 23 may be configured to perform a selection process of selecting a customer 4 to whom a penalty should be given based on the received report information. Specifically, for example, the power management apparatus 23 selects the customer 4 of the demand facility 10 in which at least some of the devices 14 did not perform the operation according to the schedule Y as the customer 4 to be given a penalty. .

また、電力管理装置23は、制御情報(ステップS21)を需要家装置11へ送信しない構成であってもよい。この場合、たとえば、参加需要家Pの需要家装置11は、対象期間になると、電力管理装置23から受信したスケジュール情報(ステップS15)に基づいて、自己の需要施設10における機器14を自発的に制御する。   Further, the power management apparatus 23 may be configured not to transmit the control information (step S21) to the customer apparatus 11. In this case, for example, in the target period, the customer device 11 of the participating customer P voluntarily activates the device 14 in its own demand facility 10 based on the schedule information (step S15) received from the power management device 23. Control.

図13は、本発明の第1の実施の形態に係る電力管理システムにおけるキャンセル時処理を示すシーケンス図である。   FIG. 13 is a sequence diagram showing a process at the time of cancellation in the power management system according to the first embodiment of the present invention.

図13は、需要家4が、スケジュールYに従う旨の応答を行った後に当該応答を取り消す処理を行う場合、すなわち、参加需要家Pが予定を変更し、スケジュールYに従わない旨の意思表示を行う場合について示している。   FIG. 13 shows a case where the customer 4 performs a process of canceling the response after responding to the schedule Y, that is, indicating that the participating customers P change the schedule and do not follow the schedule Y. It shows the case of performing.

図13を参照して、ステップS111〜S119の動作は、図12におけるステップS11〜S19の動作と同様である。   Referring to FIG. 13, the operations of steps S111 to S119 are the same as the operations of steps S11 to S19 in FIG.

次に、需要家4は、スケジュールYに従う旨の応答を取り消すための操作を需要家装置11に対して行う。   Next, the customer 4 performs an operation for canceling the response indicating that the customer follows the schedule Y on the customer device 11.

次に、需要家装置11は、需要家4による操作を受け付け(ステップS120)、受け付けた操作内容に基づいて、スケジュールYに従う旨の応答を取り消すためのキャンセル情報を電力管理装置23へ送信する(ステップS121)。   Next, the customer device 11 receives an operation by the customer 4 (step S120), and transmits cancellation information for canceling a response to the schedule Y to the power management device 23 based on the received operation content (step S120). Step S121).

次に、電力管理装置23は、需要家装置11からキャンセル情報を受信すると、時間毎総予測量Rtを再度算出する(ステップS122)。具体的には、電力管理装置23は、キャンセル情報の送信元の需要家装置11に対応する需要家4を不参加需要家Nとみなして、時間毎確定量Dtと時間毎予測量Otとを再度算出する。そして、電力管理装置23は、算出した時間毎確定量Dtと時間毎予測量Otとに基づいて、時間毎総予測量Rtを算出する。   Next, upon receiving the cancellation information from the customer device 11, the power management device 23 calculates the hourly total predicted amount Rt again (Step S122). Specifically, the power management apparatus 23 regards the customer 4 corresponding to the customer apparatus 11 that is the transmission source of the cancellation information as the non-participating customer N, and again determines the hourly confirmed amount Dt and the hourly predicted amount Ot again. calculate. Then, the power management apparatus 23 calculates the hourly total predicted amount Rt based on the calculated hourly determined amount Dt and the hourly predicted amount Ot.

次に、電力管理装置23は、時間毎総予測量Rtに基づいて、時間毎調達量Ptに対する再度の補正処理H1を行う(ステップS123)。   Next, the power management apparatus 23 performs another correction process H1 on the hourly procurement amount Pt based on the hourly total predicted amount Rt (step S123).

具体的には、たとえば、電力管理装置23は、時間毎調達量Ptおよび時間毎総予測量Rtの差分である電力量SAを1時間前市場において売却する。あるいは、電力管理装置23は、時間毎調達量Ptに対する時間毎総予測量Rtの不足分を1時間前市場において購入する。   Specifically, for example, the power management apparatus 23 sells the power amount SA that is the difference between the hourly procured amount Pt and the hourly total predicted amount Rt in the market one hour before. Alternatively, the power management apparatus 23 purchases a shortage of the hourly total predicted amount Rt with respect to the hourly procured amount Pt in the market one hour before.

ステップS124〜S128の動作は、図12に示すステップS20〜S24の動作と同様である。   The operations in steps S124 to S128 are the same as the operations in steps S20 to S24 shown in FIG.

なお、電力管理装置23は、たとえば、需要家装置11からキャンセル情報を受信した時点で既に1時間前市場が閉場している場合、補正処理H1を行わない。   Note that the power management apparatus 23 does not perform the correction processing H1 if, for example, the market is closed one hour ago when the cancellation information is received from the customer apparatus 11.

図14は、本発明の第1の実施の形態に係る電力管理装置の構成を示す図である。   FIG. 14 is a diagram illustrating a configuration of the power management device according to the first embodiment of the present invention.

図14を参照して、電力管理装置23は、取得部30と、作成部31と、補正処理部32と、電力量算出部33と、記憶部34と、送信部35と、処理部(選択部)36とを備える。   Referring to FIG. 14, power management device 23 includes acquisition unit 30, creation unit 31, correction processing unit 32, power amount calculation unit 33, storage unit 34, transmission unit 35, and processing unit (selection unit). ) 36.

記憶部34は、たとえば、各需要家4の電力消費のパターンを示す情報、電力消費に関する統計値を示す情報、気象予報情報、および需要家4が契約需要家Kであるか未契約需要家Mであるか等の情報を記憶している。また、記憶部34は、各契約需要家Kがグループg1〜g3のいずれに属するのかを示す情報を記憶している。   The storage unit 34 stores, for example, information indicating a pattern of power consumption of each customer 4, information indicating a statistical value related to power consumption, weather forecast information, and whether the customer 4 is a contract customer K or an uncontracted customer M Is stored. The storage unit 34 stores information indicating which of the groups g1 to g3 each contract customer K belongs to.

電力量算出部33は、たとえば、各需要家4の電力消費のパターンおよび電力消費に関する統計値、ならびに気象予報情報に基づいて、スポット市場において調達すべき、対象期間において使用するための電力量を算出する。   The power amount calculation unit 33 calculates, for example, the power amount to be procured in the spot market and used in the target period based on the statistical pattern of the power consumption pattern and the power consumption of each customer 4 and the weather forecast information. calculate.

なお、電力量算出部33は、契約需要家Kおよび未契約需要家Mの別に基づいて、対象期間において使用するために調達する電力量を算出する構成であってもよい。具体的には、たとえば、電力量算出部33は、契約需要家Kの電力消費に関する統計値、および未契約需要家Mの電力消費に関する統計値に基づいて、スポット市場において調達する電力量を算出する。   Note that the power amount calculation unit 33 may be configured to calculate the amount of power to be procured for use in the target period based on each of the contract customer K and the uncontracted customer M. Specifically, for example, the power amount calculation unit 33 calculates the power amount to be procured in the spot market based on the statistical value regarding the power consumption of the contract customer K and the statistical value regarding the power consumption of the uncontracted customer M. I do.

処理部36は、送信部35経由で市場サーバ25へ情報を送信し、取得部30経由で市場サーバ25から情報を取得することにより、電力量算出部33によって算出された、対象期間において使用するための電力量を調達するための処理を行う。   The processing unit 36 transmits the information to the market server 25 via the transmission unit 35 and acquires the information from the market server 25 via the acquisition unit 30 to use the information in the target period calculated by the power amount calculation unit 33. To procure the required power.

作成部31は、対象期間において使用するために調達された電力量である時間毎調達量Ptに基づいて、複数の需要家4、具体的には、複数の契約需要家Kの対象期間における電力消費に関するスケジュールであるスケジュールYを作成する。   The creating unit 31 determines the power consumption of the plurality of customers 4, specifically, the plurality of contract customers K in the target period based on the hourly procured amount Pt which is the amount of power procured for use in the target period. A schedule Y, which is a schedule related to consumption, is created.

具体的には、作成部31は、時間毎調達量Ptを契約需要家K全体および未契約需要家M全体に割り当てる。そして、作成部31は、時間毎調達量Ptのうち、契約需要家Kに割り当てた分である時間毎割当量Akに基づいて、グループg1〜g3の各々についてのスケジュールYを作成する。   Specifically, the creating unit 31 allocates the hourly procured amount Pt to the entire contract customer K and the entire non-contract customer M. Then, the creating unit 31 creates a schedule Y for each of the groups g1 to g3 based on the hourly allocated amount Ak that is allocated to the contract customer K in the hourly procured amount Pt.

より具体的には、たとえば、作成部31は、時間毎割当量Akが、各契約需要家Kの全体において過不足なく消費されるように、グループg1〜g3の各々についてのスケジュールYを作成する。たとえば、同じグループに属する需要家4に対応するスケジュールYは同じ内容である。   More specifically, for example, the creating unit 31 creates a schedule Y for each of the groups g1 to g3 such that the hourly assigned amount Ak is consumed by the contract customers K as a whole without excess or deficiency. . For example, the schedule Y corresponding to the customers 4 belonging to the same group has the same contents.

処理部36は、作成部31によって作成されたスケジュールYに関するスケジュール情報を作成する。送信部35は、処理部36が作成したスケジュール情報を、対応の需要家装置11へ送信する。   The processing unit 36 creates schedule information on the schedule Y created by the creating unit 31. The transmitting unit 35 transmits the schedule information created by the processing unit 36 to the corresponding customer device 11.

具体的には、送信部35は、同じグループに属する各需要家4に対応する需要家装置11へ同じスケジュールYに関するスケジュール情報を送信する。   Specifically, the transmitting unit 35 transmits the schedule information on the same schedule Y to the customer devices 11 corresponding to the customers 4 belonging to the same group.

取得部30は、スケジュール情報に対する応答を示すスケジュール応答を各需要家装置11から取得し、取得したスケジュール応答を処理部36へ出力する。   The acquiring unit 30 acquires a schedule response indicating a response to the schedule information from each customer device 11, and outputs the acquired schedule response to the processing unit 36.

補正処理部32は、処理部36が受けたスケジュール応答に基づいて、対象期間において使用するために調達する電力量を調達済みの電力量つまり現在の時間毎調達量Ptから補正する補正処理H1を行う。   Based on the schedule response received by the processing unit 36, the correction processing unit 32 performs a correction process H1 for correcting the amount of power to be procured for use in the target period from the already obtained power amount, that is, the current hourly procured amount Pt. Do.

具体的には、補正処理部32は、処理部36が受けたスケジュール応答および作成部31が作成したスケジュールYに基づいて、時間毎確定量Dtを算出する。また、補正処理部32は、各未契約需要家Mならびに各不参加需要家Nの全体における1時間毎の総消費電力量の予測値である時間毎予測量Otを算出する。このとき、たとえば、補正処理部32は、不参加需要家Nを、元々スケジュール情報の送信対象でない未契約需要家Mとみなして時間毎予測量Otを算出する。   Specifically, the correction processing unit 32 calculates the hourly fixed amount Dt based on the schedule response received by the processing unit 36 and the schedule Y created by the creation unit 31. In addition, the correction processing unit 32 calculates an hourly predicted amount Ot, which is a predicted value of the hourly total power consumption in each of the uncontracted customers M and the non-participating customers N as a whole. At this time, for example, the correction processing unit 32 regards the non-participating customer N as an uncontracted customer M that is not originally a schedule information transmission target and calculates the hourly predicted amount Ot.

補正処理部32は、時間毎確定量Dtおよび時間毎予測量Otに基づいて時間毎総予測量Rtを算出し、算出した時間毎総予測量Rtと時間毎調達量Ptとの比較結果に基づいて、時間毎調達量Ptの補正処理H1を行う。より具体的には、補正処理部32は、当該比較結果に基づいて、1時間前市場において売却する電力量または追加購入する電力量を決定し、決定した電力量を処理部36に通知する。   The correction processing unit 32 calculates the hourly total predicted amount Rt based on the hourly determined amount Dt and the hourly predicted amount Ot, and based on a comparison result between the calculated hourly total predicted amount Rt and the hourly procured amount Pt. Then, the correction processing H1 of the hourly procurement amount Pt is performed. More specifically, the correction processing unit 32 determines the amount of power to be sold or additionally purchased in the market one hour ago based on the comparison result, and notifies the processing unit 36 of the determined amount of power.

処理部36は、補正処理部32からの通知に基づいて、送信部35経由で市場サーバ25へ情報を送信し、取得部30経由で市場サーバ25から情報を取得することにより、1時間前市場において電力量を売却する処理または追加購入する売買処理を行う。   The processing unit 36 transmits the information to the market server 25 via the transmission unit 35 based on the notification from the correction processing unit 32, and acquires the information from the market server 25 via the acquisition unit 30 so that the market Performs a process of selling the amount of power or a process of buying and selling additionally.

処理部36は、たとえば、各参加需要家Pの需要家装置11に対応する制御情報を作成し、作成した制御情報を送信部35経由で対応の需要家装置11へ送信する。   The processing unit 36 creates control information corresponding to the customer device 11 of each participating customer P, for example, and transmits the created control information to the corresponding customer device 11 via the transmission unit 35.

具体的には、処理部36は、需要家装置11へ送信したスケジュール情報の内容に基づいて、当該需要家装置11に対応する各機器14を動作させるための制御情報を作成し、作成した制御情報を送信部35経由で当該需要家装置11へ送信する。   Specifically, the processing unit 36 creates control information for operating each device 14 corresponding to the customer device 11 based on the contents of the schedule information transmitted to the customer device 11, and creates the created control information. The information is transmitted to the customer device 11 via the transmission unit 35.

また、処理部36は、各需要家装置11から送信された報告情報を取得部30経由で取得し、取得した各報告情報に基づいて、対価が与えられるべき需要家4を選択する選択処理を行う。なお、処理部36は、スケジュールYに沿って機器14を動作させなかった需要家4をペナルティーの対象として選択する選択処理を行う構成であってもよい。   In addition, the processing unit 36 acquires the report information transmitted from each customer device 11 via the acquisition unit 30, and performs a selection process of selecting the customer 4 to whom the compensation should be given based on each acquired report information. Do. Note that the processing unit 36 may be configured to perform a selection process of selecting a consumer 4 who has not operated the device 14 according to the schedule Y as a penalty target.

なお、本発明の第1の実施の形態に係る電力管理システム101では、電力管理装置23は、対象期間における1時間毎の、各需要施設10の全体の消費電力量を予測し、予測結果に基づいて各種処理を行う構成であるとしたが、これ限定するものはない。たとえば、電力管理装置23は、対象期間における30分ごとの各需要施設10の全体の消費電力量を予測し、予測結果に基づいて各種処理を行う構成であってもよい。   In the power management system 101 according to the first embodiment of the present invention, the power management device 23 predicts the entire power consumption of each demand facility 10 every hour in the target period, and outputs Although it is described that various processes are performed based on this, there is no limitation. For example, the power management apparatus 23 may be configured to predict the overall power consumption of each demand facility 10 every 30 minutes in the target period and perform various processes based on the prediction result.

また、本発明の第1の実施の形態に係る電力管理システム101では、需要施設10における機器14の動作内容を1時間刻みで規定する構成であるとしたが、これに限定するものではない。具体的には、たとえば、スケジュールYは、機器14の動作内容を2時間刻みで規定する構成であってもよい。   Further, in the power management system 101 according to the first embodiment of the present invention, the operation content of the device 14 in the demand facility 10 is defined in one-hour steps, but the present invention is not limited to this. Specifically, for example, the schedule Y may have a configuration in which the operation content of the device 14 is specified in units of two hours.

また、本発明の第1の実施の形態に係る電力管理システム101では、需要家装置11は、HEMSにおけるゲートウェイ装置であるとしたが、これに限定するものではない。具体的には、たとえば、需要家装置11は、参加需要家Pが使用する携帯端末装置等であってもよい。この場合、たとえば、参加需要家Pは、対象期間においてスケジュールYに沿って機器14の制御を手動で行う。   In the power management system 101 according to the first embodiment of the present invention, the customer device 11 is a gateway device in the HEMS, but the present invention is not limited to this. Specifically, for example, the customer device 11 may be a portable terminal device or the like used by the participating customer P. In this case, for example, the participating customers P manually control the devices 14 along the schedule Y in the target period.

また、本発明の第1の実施の形態に係る電力管理システム101では、電力管理装置23は、補正処理H1を行う構成であるとしたが、これに限定するものではなく、補正処理H1を行わない構成であってもよい。この場合、たとえば、電力管理装置23は、補正処理部32を備えない。   Further, in the power management system 101 according to the first embodiment of the present invention, the power management device 23 is configured to perform the correction process H1, but the configuration is not limited to this, and the power management device 23 performs the correction process H1. There may be no configuration. In this case, for example, the power management apparatus 23 does not include the correction processing unit 32.

また、本発明の第1の実施の形態に係る電力管理システム101では、電力管理装置23は、対象期間において使用するための電力量を算出する構成であるとしたが、これに限定するものではなく、当該電力量を他の装置から通知される構成であってもよい。この場合、たとえば、電力管理装置23は、電力量算出部33を備えない。   Further, in the power management system 101 according to the first embodiment of the present invention, the power management device 23 is configured to calculate the amount of power to be used in the target period, but the configuration is not limited to this. Instead, the configuration may be such that the power amount is notified from another device. In this case, for example, the power management apparatus 23 does not include the power amount calculation unit 33.

ところで、小売事業者による電力量の供給先は、比較的少数の一般家庭等であるため、工場等の大口需要家に比べて、使用される電力量を正確に予測することは困難である。   By the way, since the supply destination of the electric energy by the retailer is a relatively small number of ordinary households, it is more difficult to accurately predict the electric energy to be used as compared with large customers such as factories.

これに対して、本発明の第1の実施の形態に係る電力管理装置では、作成部31は、対象期間において使用するために調達された電力量である時間毎調達量Ptに基づいて、対象期間における複数の需要家4の電力消費に関するスケジュールであるスケジュールYを作成する。送信部35は、作成部31によって作成されたスケジュールYに関する情報を各需要家4に対応する需要家装置11へ送信する。   On the other hand, in the power management apparatus according to the first embodiment of the present invention, the creating unit 31 determines the target amount based on the hourly procured amount Pt that is the amount of power procured for use in the target period. A schedule Y, which is a schedule related to the power consumption of the plurality of consumers 4 during the period, is created. The transmitting unit 35 transmits the information on the schedule Y created by the creating unit 31 to the customer device 11 corresponding to each customer 4.

このような構成により、たとえば、調達済みの電力量と需要家4に供給する電力量とが一致するように、電力消費に関するスケジュールYを作成し、作成したスケジュールYに従った電力消費を行うように各需要家4に要求することができる。   With such a configuration, for example, a schedule Y relating to power consumption is created such that the amount of power that has been procured and the amount of power supplied to the customer 4 match, and power consumption is performed according to the created schedule Y. Can be requested from each customer 4.

したがって、本発明の第1の実施の形態に係る電力管理装置では、調達した電力量と供給する電力量との不一致を抑えることができる。   Therefore, in the power management device according to the first embodiment of the present invention, it is possible to suppress a mismatch between the amount of power procured and the amount of power to be supplied.

また、本発明の第1の実施の形態に係る電力管理装置では、取得部30は、送信部35によって送信された情報に対する応答を取得する。補正処理部32は、取得部30によって取得された応答に基づいて、対象期間において使用するために調達する電力量を上記時間毎調達量Ptから補正する補正処理H1を行う。   Further, in the power management device according to the first embodiment of the present invention, the obtaining unit 30 obtains a response to the information transmitted by the transmitting unit 35. The correction processing unit 32 performs a correction process H1 for correcting the amount of power to be procured for use in the target period from the above-mentioned hourly procured amount Pt based on the response obtained by the obtaining unit 30.

このような構成により、たとえば、需要家4がスケジュールYに従った電力消費を行う予定であるか否かがわかるので、当該需要家4において消費される電力量を正確に把握することができる。そして、把握した電力量に基づいて、調達済みの電力量の一部売却もしくは電力量の追加調達を行うことができるため、調達した電力量と供給する電力量との不一致をより効果的に抑えることができる。   With such a configuration, for example, since it is known whether or not the customer 4 is going to consume power according to the schedule Y, the amount of power consumed in the customer 4 can be accurately grasped. Then, based on the grasped electric energy, it is possible to sell a part of the electric energy that has already been procured or to additionally procure the electric energy, so that the mismatch between the amount of electric power and the amount of electric power to be supplied can be suppressed more effectively. be able to.

また、本発明の第1の実施の形態に係る電力管理システムにおいて、スケジュールYは、需要家4の施設における機器14の動作内容を含む。需要家装置11は、送信部35から受信したスケジュールYに関する情報に基づいて、機器14を制御可能である。   Further, in the power management system according to the first embodiment of the present invention, the schedule Y includes the operation content of the device 14 in the facility of the customer 4. The customer device 11 can control the device 14 based on the information on the schedule Y received from the transmission unit 35.

このような構成により、たとえば、需要家4の施設における機器14をスケジュールYに沿って確実に動作させることができる。   With such a configuration, for example, the equipment 14 in the facility of the customer 4 can be reliably operated according to the schedule Y.

また、本発明の第1の実施の形態に係る電力管理システムにおいて、各需要家4は、複数のグループに分類されている。作成部31は、このグループごとにスケジュールYを作成する。送信部35は、同じグループに属する需要家4に対応する需要家装置11へ同じスケジュールYに関する情報を送信する。   Further, in the power management system according to the first embodiment of the present invention, each customer 4 is classified into a plurality of groups. The creating unit 31 creates a schedule Y for each group. The transmitting unit 35 transmits information on the same schedule Y to the customer devices 11 corresponding to the customers 4 belonging to the same group.

このような構成により、各需要家4が分類されたグループごとに、適切なスケジュールYを作成し、実行させることができる。   With such a configuration, an appropriate schedule Y can be created and executed for each group into which each customer 4 is classified.

また、本発明の第1の実施の形態に係る電力管理システムおいて、上記複数のグループは、電力からエネルギーを蓄積可能な蓄積装置を有する需要家4の1または複数のグループと、当該蓄積装置を有しない需要家4の1または複数のグループとを含む。   In the power management system according to the first embodiment of the present invention, the plurality of groups include one or more groups of consumers 4 having storage devices capable of storing energy from electric power, and the storage devices. And one or more groups of customers 4 that do not have

このような構成により、たとえば、蓄積装置の動作内容を示すスケジュールYを作成することができる。   With such a configuration, for example, a schedule Y indicating the operation content of the storage device can be created.

また、本発明の第1の実施の形態に係る電力管理システムでは、需要家4には、電力管理装置23が作成するスケジュールYに従うことが要求される契約を結んでいる契約需要家Kと、スケジュールYに従うことが要求される契約を結んでいない未契約需要家Mとが含まれる。   Further, in the power management system according to the first embodiment of the present invention, the customer 4 has a contract customer K who has a contract required to follow the schedule Y created by the power management apparatus 23, An uncontracted customer M who has not made a contract required to follow the schedule Y is included.

このような構成により、たとえば、スケジュールYに従うことが要求される需要家4に選択的にスケジュールYを送信することができる。   With such a configuration, for example, the schedule Y can be selectively transmitted to the customer 4 who is required to follow the schedule Y.

また、本発明の第1の実施の形態に係る電力管理装置では、電力量算出部33は、契約需要家Kおよび未契約需要家Mの別に基づいて、対象期間において使用するために調達する電力量を算出する。   Further, in the power management device according to the first embodiment of the present invention, the power amount calculation unit 33 determines the amount of power to be procured for use in the target period based on the contract customers K and the uncontract customers M. Calculate the amount.

このような構成により、たとえば、契約需要家Kと未契約需要家Mとで、通常使用する電力量が異なるような場合に、消費される電力量をより正確に把握することができる。   With such a configuration, for example, in the case where the amount of power normally used differs between the contract customer K and the non-contract customer M, the amount of power consumed can be more accurately grasped.

また、本発明の第1の実施の形態に係る電力管理装置では、補正処理部32は、スケジュールYに従わない旨を応答した契約需要家Kを、未契約需要家Mとみなして補正処理H1を行う。   Further, in the power management apparatus according to the first embodiment of the present invention, the correction processing unit 32 regards the contract customer K responding that the schedule Y is not obeyed as the uncontracted customer M and performs the correction processing H1. I do.

このような構成により、たとえば、単に契約の有無に基づいて補正処理H1を行う場合に比べて、より適切な補正処理H1を行うことができる。   With such a configuration, for example, a more appropriate correction process H1 can be performed as compared with a case where the correction process H1 is simply performed based on the presence or absence of a contract.

また、本発明の第1の実施の形態に係る電力管理システムでは、時間毎調達量Ptを確保した際の取引単価と、補正処理の対象となる電力の取引単価とが異なる。   Moreover, in the power management system according to the first embodiment of the present invention, the transaction unit price when the hourly procurement amount Pt is secured is different from the transaction unit price of the power to be corrected.

このような構成により、たとえば、取引単位が変動する市場環境において電力量の取引を行うことができる。   With such a configuration, for example, it is possible to trade electric energy in a market environment in which the transaction unit changes.

また、本発明の第1の実施の形態に係る電力管理システムでは、時間毎調達量Ptは、少なくとも各需要家4の消費電力の統計値に基づいて設定される。   In the power management system according to the first embodiment of the present invention, the hourly procurement amount Pt is set based on at least a statistical value of the power consumption of each customer 4.

このような構成により、各需要家4の過去の電力消費の傾向等に基づいて、各需要家4において消費される電力量をより正確に把握することができる。   With such a configuration, it is possible to more accurately grasp the amount of power consumed in each customer 4 based on the past power consumption tendency of each customer 4 and the like.

また、本発明の第1の実施の形態に係る電力管理装置では、処理部36は、スケジュールYが含む動作内容に沿って機器14を動作させなかった需要家4をペナルティーの対象として選択する。   Further, in the power management apparatus according to the first embodiment of the present invention, the processing unit 36 selects the customer 4 who did not operate the device 14 according to the operation content included in the schedule Y as a penalty target.

このように、スケジュールYに沿って機器14を動作させなかった需要家4にペナルティーを与えることが可能な構成により、スケジュールYに従う需要家4を増やすことができる。   As described above, with the configuration that can give a penalty to the customers 4 who did not operate the device 14 according to the schedule Y, it is possible to increase the number of customers 4 according to the schedule Y.

次に、本発明の他の実施の形態について図面を用いて説明する。なお、図中同一または相当部分には同一符号を付してその説明は繰り返さない。   Next, another embodiment of the present invention will be described with reference to the drawings. In the drawings, the same or corresponding portions have the same reference characters allotted, and description thereof will not be repeated.

<第2の実施の形態>
本実施の形態は、第1の実施の形態に係る電力管理システムと比べて、電力量の調達前に調達予定の電力量を補正する電力管理システムに関する。以下で説明する内容以外は第1の実施の形態に係る電力管理システムと同様である。
<Second embodiment>
The present embodiment relates to a power management system that corrects the amount of power to be procured before the procurement of power, as compared with the power management system according to the first embodiment. The contents other than those described below are the same as those of the power management system according to the first embodiment.

図15は、本発明の第2の実施の形態に係る電力管理システムにおける電力管理処理を示すシーケンス図である。   FIG. 15 is a sequence diagram illustrating a power management process in the power management system according to the second embodiment of the present invention.

電力管理システム101は、たとえば複数の需要家装置11を備えるが、ここでは、代表的に1個の需要家装置11について示す。   The power management system 101 includes, for example, a plurality of customer devices 11. Here, one customer device 11 is representatively shown.

図15を参照して、まず、電力管理装置23は、各需要家4の電力消費のパターンおよび電力消費に関する統計値、ならびに気象予報情報に基づいて、時間毎総量Ttを予測する(ステップS31)。   Referring to FIG. 15, first, power management device 23 predicts hourly total amount Tt based on a pattern of power consumption of each customer 4, a statistical value related to power consumption, and weather forecast information (step S <b> 31). .

次に、電力管理装置23は、予測した時間毎総量Ttに基づいて、対象期間において使用するために調達する予定の電力量である時間毎調達予定量Ctを決定する(ステップS32)。   Next, the power management apparatus 23 determines an estimated hourly procurement amount Ct, which is an estimated amount of power to be procured for use in the target period, based on the predicted hourly total amount Tt (step S32).

次に、電力管理装置23は、時間毎調達予定量Ctに基づいて、グループg1〜g3のそれぞれに対応するスケジュールYを作成する(ステップS33)。具体的には、電力管理装置23は、時間毎調達予定量Ctを契約需要家K全体および未契約需要家M全体に割り当てる。そして、電力管理装置23は、時間毎調達予定量Ctのうち、契約需要家K全体に割り当てた分が各契約需要家Kの需要施設10の全体において過不足なく消費されるように、グループg1〜g3のそれぞれに対応するスケジュールYを作成する。   Next, the power management apparatus 23 creates a schedule Y corresponding to each of the groups g1 to g3 based on the scheduled procurement amount Ct for each hour (step S33). Specifically, the power management apparatus 23 allocates the scheduled procurement amount Ct per hour to the entire contract customer K and the entire non-contract customer M. Then, the power management apparatus 23 sets the group g1 such that the portion allocated to the entire contract customer K in the scheduled procurement amount Ct per hour is consumed in the entire demand facility 10 of each contract customer K without excess or shortage. The schedule Y corresponding to each of ~ g3 is created.

次に、電力管理装置23は、スケジュールYに関する情報であるスケジュール情報を対応の需要家装置11へ送信する(ステップS34)。具体的には、たとえば、スケジュール情報は、送信先の需要家装置11に対応するスケジュールYを含み、当該スケジュールYに従うことを要求する情報である。   Next, the power management apparatus 23 transmits schedule information, which is information about the schedule Y, to the corresponding customer apparatus 11 (Step S34). Specifically, for example, the schedule information includes schedule Y corresponding to the customer device 11 of the transmission destination, and is information requesting to follow the schedule Y.

次に、需要家装置11は、電力管理装置23からスケジュール情報を受信して、受信したスケジュール情報が示すスケジュールYをディスプレイ等に表示する。需要家4は、当該ディスプレイに表示されたスケジュールYを確認し、需要家装置11を操作してスケジュールYに従うか否かを当該需要家装置11に入力する。   Next, the consumer device 11 receives the schedule information from the power management device 23, and displays the schedule Y indicated by the received schedule information on a display or the like. The customer 4 confirms the schedule Y displayed on the display and operates the customer device 11 to input into the customer device 11 whether or not to follow the schedule Y.

次に、需要家装置11は、需要家4による操作を受付け(ステップS35)、受け付けた操作内容に基づいて、スケジュールYに従うか否かを示すスケジュール応答を電力管理装置23へ送信する(ステップS36)。   Next, the customer device 11 receives the operation by the customer 4 (Step S35), and transmits a schedule response indicating whether or not to follow the schedule Y to the power management device 23 based on the received operation content (Step S36). ).

次に、電力管理装置23は、需要家装置11から受信したスケジュール応答に基づいて、時間毎総予測量Rtを算出する(ステップS37)。具体的には、電力管理装置23は、消費されることが確定した1時間ごとの電力量である時間毎確定量Dtと、各未契約需要家Mならびに各不参加需要家N全体における、1時間毎の総消費電力量の予測値である時間毎予測量Otとに基づいて、時間毎総量Ttを予測し直す。   Next, the power management apparatus 23 calculates the hourly total predicted amount Rt based on the schedule response received from the customer apparatus 11 (Step S37). Specifically, the power management apparatus 23 determines the hourly determined amount Dt, which is the hourly power amount determined to be consumed, and the hourly total amount for each uncontracted customer M and each non-participating customer N. The hourly total amount Tt is re-estimated based on the hourly predicted amount Ot, which is a predicted value of the total power consumption for each.

次に、電力管理装置23は、需要家装置11から受信したスケジュール応答に基づいて、時間毎調達予定量Ctを補正する補正処理H2を行う(ステップS38)。具体的には、電力管理装置23は、算出し直した時間毎総予測量Rtに基づいて、時間毎調達予定量Ctを補正する。   Next, based on the schedule response received from the customer device 11, the power management device 23 performs a correction process H2 for correcting the scheduled procurement amount Ct per hour (step S38). Specifically, the power management apparatus 23 corrects the hourly scheduled procurement amount Ct based on the recalculated hourly total estimated amount Rt.

次に、電力管理装置23は、時間毎調達予定量Ctと等しい電力量をスポット市場において調達する(ステップS39)。   Next, the power management apparatus 23 procures an amount of power equal to the scheduled procurement amount Ct in the spot market (step S39).

次に、電力管理装置23は、スポット市場の閉場後、対象期間における電力量の供給計画を示す1日前計画情報を送配電事業サーバ22へ送信する。   Next, after the closing of the spot market, the power management apparatus 23 transmits, to the power transmission and distribution business server 22, one-day plan information indicating a power supply plan in the target period.

なお、電力管理装置23は、スポット市場において対象期間における1時間毎の電力量を調達する構成に限らず、たとえば、1時間前市場において当該電力量を調達する構成であってもよい。この場合、電力管理装置23は、1時間前市場の閉場後、対象期間における電力量の供給計画を示す1時間前計画情報を送配電事業サーバ22へ送信する。   In addition, the power management apparatus 23 is not limited to the configuration in which the power amount is procured every hour in the target period in the spot market, but may be, for example, a configuration in which the power amount is procured in the market one hour before. In this case, after the market is closed one hour ago, the power management apparatus 23 transmits the one-hour-before-plan information indicating the power supply plan in the target period to the power transmission and distribution business server 22.

次に、電力管理装置23は、スケジュールYに従う旨のスケジュール応答を自己へ送信した需要家装置11、すなわち参加需要家Pの需要家装置11に対応する制御情報を作成する。そして、電力管理装置23は、たとえば対象期間になると、作成した制御情報を需要家装置11へ送信する(ステップS41)。   Next, the power management apparatus 23 creates control information corresponding to the customer apparatus 11 that has transmitted a schedule response indicating that it follows the schedule Y to itself, that is, the customer apparatus 11 of the participating customer P. Then, for example, in the target period, the power management apparatus 23 transmits the created control information to the customer apparatus 11 (Step S41).

次に、需要家装置11は、電力管理装置23から制御情報を受信して、受信した制御情報に基づいて、自己の需要施設10における機器14を制御する(ステップS42)。   Next, the customer device 11 receives the control information from the power management device 23, and controls the devices 14 in its own demand facility 10 based on the received control information (Step S42).

次に、需要家装置11は、たとえば対象期間の終了後、各機器14がスケジュールYに沿って動作したか否かを示す報告情報を電力管理装置23へ送信する(ステップS43)。   Next, for example, after the end of the target period, the customer device 11 transmits report information indicating whether each device 14 has operated according to the schedule Y to the power management device 23 (Step S43).

次に、電力管理装置23は、需要家装置11から報告情報を受信して、たとえば、対価が与えられるべき需要家4を選択する選択処理を行う(ステップS44)。   Next, the power management apparatus 23 receives the report information from the customer apparatus 11, and performs, for example, a selection process of selecting the customer 4 to be paid (step S44).

図16は、本発明の第2の実施の形態に係る電力管理装置の構成を示す図である。   FIG. 16 is a diagram illustrating a configuration of a power management device according to the second embodiment of the present invention.

図16を参照して、電力量算出部33は、記憶部34の記憶する各種情報に基づいて、対象期間において使用するために調達する予定の電力量である時間毎調達予定量Ctを算出する。   Referring to FIG. 16, power amount calculation unit 33 calculates a scheduled procurement amount per hour Ct, which is a power amount scheduled to be procured for use in the target period, based on various types of information stored in storage unit 34. .

作成部31は、電力量算出部33が算出した時間毎調達予定量Ctに基づいて、複数の契約需要家Kの対象期間における電力消費に関するスケジュールであるスケジュールYを作成する。   The creating unit 31 creates a schedule Y, which is a schedule related to power consumption in the target period of the plurality of contract customers K, based on the scheduled procurement amount Ct per hour calculated by the power amount calculating unit 33.

具体的には、作成部31は、時間毎調達予定量Ctを契約需要家K全体および未契約需要家M全体に割り当てる。そして、作成部31は、時間毎調達予定量Ctのうち、契約需要家Kに割り当てた分である時間毎割当量Akに基づいて、グループg1〜g3の各々についてのスケジュールYを作成する。   Specifically, the creating unit 31 allocates the scheduled procurement amount Ct per hour to the entire contract customer K and the entire uncontracted customer M. Then, the creating unit 31 creates a schedule Y for each of the groups g1 to g3 based on the hourly allocation amount Ak that is allocated to the contract customer K in the hourly procurement schedule amount Ct.

より具体的には、たとえば、作成部31は、時間毎割当量Akが、各契約需要家Kの需要施設10の全体において過不足なく消費されるように、グループg1〜g3の各々についてのスケジュールYを作成する。   More specifically, for example, the creating unit 31 determines the schedule for each of the groups g1 to g3 so that the hourly allocated amount Ak is consumed in the entire demand facility 10 of each contract customer K without excess or shortage. Create Y.

処理部36は、作成部31によって作成されたスケジュールYに関するスケジュール情報を作成する。送信部35は、処理部36が作成したスケジュール情報を、対応の需要家装置11へ送信する。   The processing unit 36 creates schedule information on the schedule Y created by the creating unit 31. The transmitting unit 35 transmits the schedule information created by the processing unit 36 to the corresponding customer device 11.

具体的には、送信部35は、同じグループに属する各需要家4に対応する需要家装置11へ同じスケジュールYに関するスケジュール情報を送信する。   Specifically, the transmitting unit 35 transmits the schedule information on the same schedule Y to the customer devices 11 corresponding to the customers 4 belonging to the same group.

取得部30は、スケジュール情報に対する応答を示すスケジュール応答を各需要家装置11から取得し、取得したスケジュール応答を処理部36へ出力する。   The acquiring unit 30 acquires a schedule response indicating a response to the schedule information from each customer device 11, and outputs the acquired schedule response to the processing unit 36.

補正処理部32は、処理部36が受けたスケジュール応答に基づいて、時間毎調達予定量Ctを補正する補正処理H2を行う。   The correction processing unit 32 performs a correction process H2 for correcting the scheduled procurement amount Ct per hour based on the schedule response received by the processing unit 36.

具体的には、補正処理部32は、処理部36が受けたスケジュール応答および作成部31が作成したスケジュールYに基づいて、時間毎確定量Dtを算出する。また、補正処理部32は、各未契約需要家Mならびに各不参加需要家Nの全体における1時間毎の総消費電力量の予測値である時間毎予測量Otを算出する。   Specifically, the correction processing unit 32 calculates the hourly fixed amount Dt based on the schedule response received by the processing unit 36 and the schedule Y created by the creation unit 31. In addition, the correction processing unit 32 calculates an hourly predicted amount Ot, which is a predicted value of the hourly total power consumption in each of the uncontracted customers M and the non-participating customers N as a whole.

補正処理部32は、時間毎確定量Dtおよび時間毎予測量Otに基づいて時間毎総予測量Rtを算出し、算出した時間毎総予測量Rtと時間毎調達予定量Ctとの比較結果に基づいて、時間毎調達予定量Ctの補正処理H2を行う。   The correction processing unit 32 calculates an hourly total predicted amount Rt based on the hourly confirmed amount Dt and the hourly predicted amount Ot, and calculates a comparison result between the calculated hourly total predicted amount Rt and the estimated hourly procurement amount Ct. Based on this, a correction process H2 for the scheduled procurement amount Ct for each hour is performed.

具体的には、補正処理部32は、時間毎調達予定量Ctが時間毎総予測量Rtより大きい場合、時間毎調達予定量Ctが時間毎総予測量Rtと同等になるように時間毎調達予定量Ctを増加させる。また、補正処理部32は、時間毎調達予定量Ctが時間毎総予測量Rtより小さい場合、時間毎調達予定量Ctが時間毎総予測量Rtと同等になるように時間毎調達予定量Ctを減少させる。補正処理部32は、たとえば、補正処理H2を行った後の時間毎調達予定量Ctを処理部36に通知する。   Specifically, when the scheduled procurement amount per hour Ct is larger than the total predicted amount per hour Rt, the correction processing unit 32 procures the hourly procured amount so that the scheduled procured amount per hour Ct becomes equal to the total predicted amount per hour Rt. The planned amount Ct is increased. Further, when the scheduled procured amount Ct per hour is smaller than the total predicted amount Rt per hour, the correction processing unit 32 determines that the planned procured hourly amount Ct is equal to the planned hourly procured amount Rt. Decrease. The correction processing unit 32 notifies the processing unit 36 of the scheduled procurement amount Ct per hour after performing the correction process H2, for example.

処理部36は、補正処理部32からの通知に基づいて、送信部35経由で市場サーバ25へ情報を送信し、取得部30経由で市場サーバ25から情報を取得することにより、スポット市場において時間毎調達予定量Ctと等しい電力量を調達する売買処理を行う。   The processing unit 36 transmits information to the market server 25 via the transmission unit 35 based on the notification from the correction processing unit 32 and acquires information from the market server 25 via the acquisition unit 30 to thereby save time in the spot market. A trading process is performed to procure an amount of power equal to the scheduled amount of procurement Ct.

処理部36は、たとえば、参加需要家Pの需要家装置11に対応する制御情報を作成し、作成した制御情報を送信部35経由で需要家装置11へ送信する。具体的には、処理部36は、当該需要家装置11へ送信したスケジュール情報の内容に基づいて、各機器14を動作させるための制御情報を作成し、作成した制御情報を送信部35経由で需要家装置11へ送信する。   The processing unit 36 creates control information corresponding to the customer device 11 of the participating customer P, for example, and transmits the created control information to the customer device 11 via the transmission unit 35. Specifically, the processing unit 36 creates control information for operating each device 14 based on the contents of the schedule information transmitted to the customer device 11, and transmits the created control information via the transmission unit 35. The data is transmitted to the customer device 11.

以上のように、本発明の第2の実施の形態に係る電力管理装置では、作成部31は、対象期間において使用するために調達する予定の電力量である時間毎調達予定量Ctに基づいて、対象期間における複数の需要家4の電力消費に関するスケジュールYを作成する。送信部35は、作成部31によって作成されたスケジュールYに関する情報を各需要家4に対応する需要家装置11へ送信する。   As described above, in the power management device according to the second embodiment of the present invention, the creation unit 31 performs the process based on the scheduled hourly procurement amount Ct, which is the power amount to be procured for use in the target period. , A schedule Y relating to power consumption of the plurality of consumers 4 in the target period is created. The transmitting unit 35 transmits the information on the schedule Y created by the creating unit 31 to the customer device 11 corresponding to each customer 4.

このような構成により、たとえば、調達予定の電力量と、需要家4に供給する電力量とが一致するように、電力消費に関するスケジュールYを作成し、作成したスケジュールYに従った電力消費を行うように各需要家4に要求することができる。   With such a configuration, for example, a schedule Y relating to power consumption is created such that the amount of power to be procured matches the amount of power supplied to the customer 4, and power consumption is performed according to the created schedule Y. Request to each customer 4 as described above.

したがって、本発明の第2の実施の形態に係る電力管理装置では、調達した電力量と供給する電力量との不一致を抑えることができる。   Therefore, in the power management apparatus according to the second embodiment of the present invention, it is possible to suppress the mismatch between the amount of power that is procured and the amount of power that is supplied.

また、本発明の第2の実施の形態に係る電力管理装置では、取得部30は、送信部35によって送信された情報に対する応答を取得する。補正処理部32は、取得部30によって取得された応答に基づいて、時間毎調達予定量Ctを補正する補正処理H2を行う。   Further, in the power management device according to the second embodiment of the present invention, the obtaining unit 30 obtains a response to the information transmitted by the transmitting unit 35. The correction processing unit 32 performs a correction process H2 for correcting the scheduled procurement amount Ct per hour based on the response acquired by the acquisition unit 30.

このような構成により、たとえば、需要家4がスケジュールYに従った電力消費を行う予定であるか否かがわかるので、当該需要家4において消費される電力量を正確に把握することができる。そして、把握した電力量に基づいて、調達予定の電力量の補正を行うことができるため、調達した電力量と供給する電力量との不一致をより効果的に抑えることができる。   With such a configuration, for example, since it is known whether or not the customer 4 is going to consume power according to the schedule Y, the amount of power consumed in the customer 4 can be accurately grasped. Then, the power amount to be procured can be corrected based on the grasped power amount, so that the mismatch between the procured power amount and the supplied power amount can be suppressed more effectively.

また、本発明の第2の実施の形態に係る電力管理システムでは、時間毎調達予定量Ctは、少なくとも各需要家4の消費電力の統計値に基づいて設定される。   In the power management system according to the second embodiment of the present invention, the scheduled procurement amount Ct per hour is set based on at least the statistical value of the power consumption of each customer 4.

このような構成により、各需要家4の過去の電力消費の傾向等に基づいて、各需要家4において消費される電力量をより正確に把握することができる。   With such a configuration, it is possible to more accurately grasp the amount of power consumed in each customer 4 based on the past power consumption tendency of each customer 4 and the like.

その他の構成および動作は第1の実施の形態に係る電力管理装置と同様であるため、ここでは詳細な説明を繰り返さない。   Other configurations and operations are the same as those of the power management apparatus according to the first embodiment, and thus detailed description will not be repeated here.

上記実施の形態は、すべての点で例示であって制限的なものではないと考えられるべきである。本発明の範囲は、上記説明ではなく特許請求の範囲によって示され、特許請求の範囲と均等の意味および範囲内でのすべての変更が含まれることが意図される。   The above embodiment is to be considered in all respects as illustrative and not restrictive. The scope of the present invention is defined by the terms of the claims, rather than the description above, and is intended to include any modifications within the scope and meaning equivalent to the terms of the claims.

以上の説明は、以下に付記する特徴を含む。   The above description includes the features described below.

[付記1]
対象期間において使用するために調達する予定の電力量である第1の電力量または前記対象期間において使用するために調達された電力量である第2の電力量に基づいて、前記対象期間における複数の需要家の電力消費に関するスケジュールを作成する作成部と、
前記作成部によって作成された前記スケジュールに関する情報を各前記需要家に対応する需要家装置へ送信する送信部とを備え、
卸電力市場における電力量の取引を管理する市場サーバと通信することによって電力量の調達を行うことが可能な、電力管理装置。
[Appendix 1]
Based on a first power amount that is a power amount to be procured for use in the target period or a second power amount that is a power amount procured for use in the target period, a plurality of A creating unit that creates a schedule for power consumption of consumers in
A transmitting unit that transmits information on the schedule created by the creating unit to a customer device corresponding to each customer,
An electric power management device capable of procuring electric energy by communicating with a market server that manages transactions of electric energy in a wholesale electric power market.

1 発電事業者
2 送配電事業者
3 小売事業者
4 需要家
5 卸電力市場
8 ネットワーク
10 需要施設
11 需要家装置
14 機器
21 発電事業サーバ
22 送配電事業サーバ
23 電力管理装置
25 市場サーバ
30 取得部
31 作成部
32 補正処理部
33 電力量算出部
34 記憶部
35 送信部
36 処理部
100 電力システム
101 電力管理システム
DESCRIPTION OF SYMBOLS 1 Power generation company 2 Power transmission and distribution company 3 Retail business operator 4 Customer 5 Wholesale power market 8 Network 10 Demand facilities 11 Customer equipment 14 Equipment 21 Power generation business server 22 Power transmission and distribution business server 23 Power management device 25 Market server 30 Acquisition part 31 creation unit 32 correction processing unit 33 power amount calculation unit 34 storage unit 35 transmission unit 36 processing unit 100 power system 101 power management system

Claims (11)

対象期間において使用するために調達する予定の電力量である第1の電力量または前記対象期間において使用するために調達された電力量である第2の電力量に基づいて、前記対象期間における複数の需要家の電力消費に関するスケジュールを作成する作成部と、
前記作成部によって作成された前記スケジュールに関する情報を各前記需要家に対応する需要家装置へ送信する送信部と、
前記送信部によって送信された前記情報の示す前記スケジュールに従うか否かの応答を前記対象期間に先立ち取得する取得部と、
前記取得部によって取得された前記応答に基づいて、前記第1の電力量を補正するか、または前記対象期間において使用するために調達する電力量を前記第2の電力量から補正する補正処理を行う補正処理部と、
前記対象期間の到来より前において、前記補正処理後の前記第1の電力量または前記補正処理後の前記第2の電力量に基づいて、市場において電力を取引する処理を行う処理部とを備える、電力管理装置。
Based on a first power amount that is a power amount to be procured for use in the target period or a second power amount that is a power amount procured for use in the target period, a plurality of A creating unit that creates a schedule for power consumption of consumers in
A transmitting unit that transmits information on the schedule created by the creating unit to a customer device corresponding to each customer,
An acquisition unit that acquires a response as to whether to follow the schedule indicated by the information transmitted by the transmission unit prior to the target period ,
Based on the response obtained by the obtaining unit, a correction process of correcting the first power amount or correcting a power amount to be procured for use in the target period from the second power amount. A correction processing unit to be performed;
A processing unit that performs a process of trading power in a market based on the first power amount after the correction process or the second power amount after the correction process before the arrival of the target period. , Power management equipment.
前記スケジュールは、前記需要家の施設における機器の動作内容を含み、
前記需要家装置は、前記送信部から受信した前記情報に基づいて、前記機器を制御可能である、請求項1に記載の電力管理装置。
The schedule includes operation contents of equipment in the facility of the customer,
The power management device according to claim 1, wherein the customer device is capable of controlling the device based on the information received from the transmission unit.
各前記需要家は、複数のグループに分類されており、
前記作成部は、前記グループごとに前記スケジュールを作成し、
前記送信部は、同じ前記グループに属する前記需要家に対応する前記需要家装置へ同じ前記スケジュールに関する前記情報を送信する、請求項1または請求項2に記載の電力管理装置。
Each customer is classified into a plurality of groups,
The creating unit creates the schedule for each group,
The power management device according to claim 1, wherein the transmission unit transmits the information on the same schedule to the customer devices corresponding to the customers belonging to the same group.
前記複数のグループは、電力からエネルギーを蓄積可能な蓄積装置を有する前記需要家の1または複数のグループと、前記蓄積装置を有しない前記需要家の1または複数のグループとを含む、請求項3に記載の電力管理装置。   The plurality of groups includes one or more groups of the customers having storage devices capable of storing energy from electric power, and one or more groups of the customers not having the storage devices. The power management device according to claim 1. 前記電力管理装置の管理対象となる前記需要家には、前記電力管理装置が作成する前記スケジュールに従うことが要求される契約を結んでいる第1の需要家と、前記スケジュールに従うことが要求される契約を結んでいない第2の需要家とが含まれる、請求項1から請求項4のいずれか1項に記載の電力管理装置。   The customer to be managed by the power management device is required to have a first customer who has a contract required to follow the schedule created by the power management device and to comply with the schedule. The power management apparatus according to any one of claims 1 to 4, wherein the power management apparatus includes a second customer who has not made a contract. 前記電力管理装置は、さらに、
前記第1の需要家および前記第2の需要家の別に基づいて、対象期間において使用するために調達する電力量を算出する電力量算出部を備える、請求項5に記載の電力管理装置。
The power management device further includes:
The power management device according to claim 5, further comprising: a power amount calculation unit that calculates an amount of power to be procured for use in a target period based on the first customer and the second customer.
前記電力管理装置の管理対象となる前記需要家には、前記電力管理装置が作成する前記スケジュールに従うことが要求される契約を結んでいる第1の需要家と、前記スケジュールに従うことが要求されない契約を結んでいる第2の需要家とが含まれ、
前記補正処理部は、前記スケジュールに従わない旨を応答した前記第1の需要家を、前記第2の需要家とみなして前記補正処理を行う、請求項1に記載の電力管理装置
The customer to be managed by the power management device has a first customer who has a contract that is required to follow the schedule created by the power management device, and a contract that is not required to follow the schedule. And a second customer connecting
2. The power management apparatus according to claim 1, wherein the correction processing unit performs the correction processing by regarding the first customer who has responded that the schedule does not comply with the schedule as the second customer. 3.
前記第2の電力量の取引単価と、前記補正処理の対象となる電力の取引単価とが異なる、請求項7に記載の電力管理装置。   The power management device according to claim 7, wherein a transaction unit price of the second power amount and a transaction unit price of power to be corrected are different. 前記第1の電力量または前記第2の電力量は、少なくとも前記各需要家の消費電力の統計値に基づいて設定される、請求項1から請求項8のいずれか1項に記載の電力管理装置。   The power management according to any one of claims 1 to 8, wherein the first power amount or the second power amount is set based on at least a statistical value of power consumption of each customer. apparatus. 前記スケジュールは、前記需要家の施設における機器の動作内容を含み、
前記電力管理装置は、さらに、
前記スケジュールが含む前記動作内容に沿って前記機器を動作させなかった前記需要家をペナルティーの対象として選択する選択部を備える、請求項1から請求項9のいずれか1項に記載の電力管理装置。
The schedule includes operation contents of equipment in the facility of the customer,
The power management device further includes:
The power management device according to any one of claims 1 to 9, further comprising a selection unit that selects, as a penalty target, the customer who has not operated the device according to the operation content included in the schedule. .
電力管理装置において用いられる電力管理プログラムであって、コンピュータを、
対象期間において使用するために調達する予定の電力量である第1の電力量または前記対象期間において使用するために調達された電力量である第2の電力量に基づいて、前記対象期間における複数の需要家の電力消費に関するスケジュールを作成する作成部と、
前記作成部によって作成された前記スケジュールに関する情報を各前記需要家に対応する需要家装置へ送信する送信部と、
前記送信部によって送信された前記情報の示す前記スケジュールに従うか否かの応答を前記対象期間に先立ち取得する取得部と、
前記取得部によって取得された前記応答に基づいて、前記第1の電力量を補正するか、または前記対象期間において使用するために調達する電力量を前記第2の電力量から補正する補正処理を行う補正処理部と、
前記対象期間の到来より前において、前記補正処理後の前記第1の電力量または前記補正処理後の前記第2の電力量に基づいて、市場において電力を取引する処理を行う処理部、
として機能させるための、電力管理プログラム。
A power management program used in a power management device, comprising:
Based on a first power amount that is a power amount to be procured for use in the target period or a second power amount that is a power amount procured for use in the target period, a plurality of A creating unit that creates a schedule for power consumption of consumers in
A transmitting unit that transmits information on the schedule created by the creating unit to a customer device corresponding to each customer,
An acquisition unit that acquires a response as to whether to follow the schedule indicated by the information transmitted by the transmission unit prior to the target period ,
Based on the response obtained by the obtaining unit, a correction process of correcting the first power amount or correcting a power amount to be procured for use in the target period from the second power amount. A correction processing unit to be performed;
Before the arrival of the target period, a processing unit that performs a process of trading power in a market based on the first power amount after the correction process or the second power amount after the correction process,
Power management program to function as
JP2016030173A 2016-02-19 2016-02-19 Power management device and power management program Active JP6658064B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016030173A JP6658064B2 (en) 2016-02-19 2016-02-19 Power management device and power management program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016030173A JP6658064B2 (en) 2016-02-19 2016-02-19 Power management device and power management program

Publications (2)

Publication Number Publication Date
JP2017146921A JP2017146921A (en) 2017-08-24
JP6658064B2 true JP6658064B2 (en) 2020-03-04

Family

ID=59682220

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016030173A Active JP6658064B2 (en) 2016-02-19 2016-02-19 Power management device and power management program

Country Status (1)

Country Link
JP (1) JP6658064B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6803596B1 (en) * 2020-10-15 2020-12-23 デジタルグリッド株式会社 Power trading system, power trading method and power trading program

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5899830B2 (en) * 2011-11-09 2016-04-06 ソニー株式会社 Power management apparatus, power management method, and demand notification apparatus
JP5643791B2 (en) * 2012-07-23 2014-12-17 株式会社東芝 Electric power supply and demand control device and electric power supply and demand control method
JP5951399B2 (en) * 2012-08-06 2016-07-13 株式会社東芝 Monitoring control method and monitoring control apparatus
JP6079215B2 (en) * 2012-12-21 2017-02-15 富士電機株式会社 Power demand forecasting device, program
JP6118136B2 (en) * 2013-02-27 2017-04-19 株式会社日立製作所 Power supply adjustment device and power supply adjustment method
JP5664726B1 (en) * 2013-08-28 2015-02-04 ダイキン工業株式会社 Control device
JP6194101B2 (en) * 2014-04-04 2017-09-06 株式会社日立製作所 Power transaction planning support system and power transaction planning support method
CN105048447B (en) * 2014-04-24 2017-09-22 松下知识产权经营株式会社 integration demand control method and integration demand control device
JP2016001951A (en) * 2014-06-11 2016-01-07 富士電機株式会社 Power demand prediction apparatus and program

Also Published As

Publication number Publication date
JP2017146921A (en) 2017-08-24

Similar Documents

Publication Publication Date Title
Lezama et al. Local energy markets: Paving the path toward fully transactive energy systems
Rashidizadeh-Kermani et al. A regret-based stochastic bi-level framework for scheduling of DR aggregator under uncertainties
Carreiro et al. Energy management systems aggregators: A literature survey
Lampropoulos et al. A framework for the provision of flexibility services at the transmission and distribution levels through aggregator companies
Ausubel et al. Using forward markets to improve electricity market design
Vahedipour-Dahraie et al. Peer-to-peer energy trading between wind power producer and demand response aggregators for scheduling joint energy and reserve
US20160275630A1 (en) Decision support system based on energy markets
US10447035B2 (en) Electric power creation control system and method
JP6512503B2 (en) Power adjustment device, power adjustment method, program
Ali et al. A market-oriented hierarchical framework for residential demand response
US20090319415A1 (en) Momentary Power Market
Greve et al. A system operator’s utility function for the frequency response market
Rashidizadeh‐Kermani et al. A stochastic bi‐level decision‐making framework for a load‐serving entity in day‐ahead and balancing markets
Salah et al. Morphological analysis of energy services: Paving the way to quality differentiation in the power sector
JP2006158189A (en) Cost minimization power control system using combination of electric power transaction and distributed power supply
JP2017182698A (en) Power demand management supporting system, power demand management supporting method, and power demand management supporting program
JP6915233B2 (en) Power management equipment, power systems, consumer equipment, power management methods and power management programs
JP6411247B2 (en) Power aggregator system, power trading method, and power trading program
Rashidizadeh‐Kermani et al. Stochastic risk‐constrained decision‐making approach for a retailer in a competitive environment with flexible demand side resources
JP6803596B1 (en) Power trading system, power trading method and power trading program
JP4799517B2 (en) Power supply service provision system
JP2021149282A (en) Electric power trading assistance device, electric power trading assistance method and program
JP6554785B2 (en) Power management apparatus, power system, customer apparatus, power management method, and power management program
You et al. Leveraging flexibility of residential heat pumps through local energy markets
JP7470832B2 (en) Demand adjustment system, demand adjustment method and program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180921

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190726

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190806

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190930

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20191023

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20191212

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200107

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200120

R150 Certificate of patent or registration of utility model

Ref document number: 6658064

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250