ITPD20120146A1 - PLANT FOR THE OPTIMIZATION OF THE EXPLOITATION OF ELECTRIC ENERGY AVAILABLE TO A BUILDING, AND PROCEDURE FOR THE USE OF SUCH SYSTEM. - Google Patents

PLANT FOR THE OPTIMIZATION OF THE EXPLOITATION OF ELECTRIC ENERGY AVAILABLE TO A BUILDING, AND PROCEDURE FOR THE USE OF SUCH SYSTEM. Download PDF

Info

Publication number
ITPD20120146A1
ITPD20120146A1 IT000146A ITPD20120146A ITPD20120146A1 IT PD20120146 A1 ITPD20120146 A1 IT PD20120146A1 IT 000146 A IT000146 A IT 000146A IT PD20120146 A ITPD20120146 A IT PD20120146A IT PD20120146 A1 ITPD20120146 A1 IT PD20120146A1
Authority
IT
Italy
Prior art keywords
tank
temperature
power
heat pump
water
Prior art date
Application number
IT000146A
Other languages
Italian (it)
Inventor
Tiziano Meneghetti
Original Assignee
Espe S R L
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Espe S R L filed Critical Espe S R L
Priority to IT000146A priority Critical patent/ITPD20120146A1/en
Publication of ITPD20120146A1 publication Critical patent/ITPD20120146A1/en

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/08Hot-water central heating systems in combination with systems for domestic hot-water supply
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D11/00Central heating systems using heat accumulated in storage masses
    • F24D11/02Central heating systems using heat accumulated in storage masses using heat pumps
    • F24D11/0214Central heating systems using heat accumulated in storage masses using heat pumps water heating system
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D19/00Details
    • F24D19/10Arrangement or mounting of control or safety devices
    • F24D19/1006Arrangement or mounting of control or safety devices for water heating systems
    • F24D19/1066Arrangement or mounting of control or safety devices for water heating systems for the combination of central heating and domestic hot water
    • F24D19/1072Arrangement or mounting of control or safety devices for water heating systems for the combination of central heating and domestic hot water the system uses a heat pump
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/381Dispersed generators
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D2200/00Heat sources or energy sources
    • F24D2200/02Photovoltaic energy
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D2200/00Heat sources or energy sources
    • F24D2200/12Heat pump
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2300/00Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
    • H02J2300/20The dispersed energy generation being of renewable origin
    • H02J2300/22The renewable source being solar energy
    • H02J2300/24The renewable source being solar energy of photovoltaic origin
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy
    • Y02E10/56Power conversion systems, e.g. maximum power point trackers

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Water Supply & Treatment (AREA)
  • Power Engineering (AREA)
  • Feedback Control In General (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Description

IMPIANTO PER L'OTTIMIZZAZIONE DELLO SFRUTTAMENTO DELL'ENERGIA ELETTRICA A DISPOSIZIONE DI UN EDIFICIO, E PROCEDIMENTO PER L'IMPIEGO DI TALE IMPIANTO PLANT FOR THE OPTIMIZATION OF THE EXPLOITATION OF ELECTRICITY AVAILABLE TO A BUILDING, AND PROCEDURE FOR THE USE OF THIS PLANT

DESCRIZIONE DESCRIPTION

Il presente trovato ha per oggetto un impianto per l'ottimizzazione dello sfruttamento dell'energia elettrica a disposizione di un edificio . The present invention relates to a plant for optimizing the exploitation of the electrical energy available to a building.

Forma oggetto del trovato anche un procedimento per l'impiego di tale impianto di ottimizzazione. E' oggigiorno sempre più sentita l'esigenza, sia per motivi di congiuntura economica, sia per motivi ecologici, di razionalizzare il consumo energetico degli edifici, sia adibiti ad abitazione, sia ambienti industriali, ancor più nel caso di edifici dotati di impianti capaci di sfruttare le cosiddette energie alternative, quali ad esempio gli impianti fotovoltaici. The invention also relates to a method for using this optimization system. Nowadays the need is increasingly felt, both for economic reasons and for ecological reasons, to rationalize the energy consumption of buildings, both used as homes and industrial environments, even more so in the case of buildings equipped with systems capable of exploit the so-called alternative energies, such as photovoltaic systems.

Infatti se da un lato gli impianti fotovoltaici soffrono dell'ineludibile inconveniente di non produrre energia elettrica nelle ore di buio, dall'altra è frequente che i gestori delle reti locali o nazionali di energia elettrica mettano a disposizione della clientela due o più tariffe di costo dell'energia elettrica, stabilendo fasce orarie in cui l'energia costa di più, generalmente di giorno, e fasce orarie in cui l'energia costa di meno, generalmente le ore notturne. In fact, if on the one hand photovoltaic systems suffer from the unavoidable disadvantage of not producing electricity in the hours of darkness, on the other hand it is common for operators of local or national electricity grids to make two or more cost rates available to customers. electricity, establishing time slots in which energy costs more, generally during the day, and time slots in which energy costs less, usually at night.

Sebbene i due citati fattori sembrino completarsi consentendo all'utenza un vantaggioso uso dell'energia elettrica prodotta dal fotovoltaico di giorno e un altrettanto conveniente uso dell'energia elettrica a basso costo da rete nelle ore serali e notturne, la realtà si propone spesso in modo più complesso e problematico, come nel caso della gestione del picco di domanda di energia elettrica. Although the two aforementioned factors seem to complement each other, allowing users an advantageous use of the electricity produced by photovoltaics during the day and an equally convenient use of low-cost electricity from the grid in the evening and at night, the reality is often proposed in a way more complex and problematic, as in the case of managing the peak of electricity demand.

Infatti ad oggi il picco di domanda energetica è gestito generalmente diminuendo la fornitura alle utenze, o interrompendo alternativamente la fornitura temporaneamente ad alcune utenze per fornirne altre. In fact, today the peak of energy demand is generally managed by decreasing the supply to the users, or alternatively interrupting the supply temporarily to some users to supply others.

Simili eventi sono ad esempio estremamente frequenti in estate, quando nelle ore diurne la richiesta energetica per il funzionamento dei condizionatori è elevatissima, ma la rete non è in grado di assicurare a tutte le utenze la corretta fornitura, e per contro nelle ore serali e notturne, pur essendo l'energia elettrica ad un prezzo più conveniente, la richiesta cala drasticamente per il naturale raffrescamente ambientale . Such events are, for example, extremely frequent in summer, when during the day the energy demand for the operation of the air conditioners is very high, but the network is not able to ensure the correct supply to all users, and on the other hand in the evening and night hours. , despite being electricity at a cheaper price, the demand drops drastically for natural environmental cooling.

Un altro inconveniente tipico degli impianti fotovoltaici è la gestione dei picchi di produzione di energia da parte dell'impianto fotovoltaico stesso, ad esempio in caso di giornata di forte insolazione; tale energia prodotta dall'impianto fotovoltaico sovente non è sfruttata localmente, nè la si riesce a convogliare ed erogare alla rete locale, venendo così dissipata ed inutilizzata. Another typical drawback of photovoltaic systems is the management of energy production peaks by the photovoltaic system itself, for example in the event of a day of strong insolation; this energy produced by the photovoltaic system is often not exploited locally, nor can it be conveyed and delivered to the local network, thus being dissipated and unused.

Il compito del presente trovato è quello di realizzare un impianto per l'ottimizzazione dello sfruttamento dell'energia elettrica a disposizione di un edificio, capace di favorire il migliore sfruttamento possibile delle fonti di energia elettrica a disposizione, razionalizzandone lo sfruttamento e diminuendo i costi per l'edificio o per il processo industriale a cui è associato. The object of the present invention is to provide a plant for optimizing the exploitation of the electrical energy available to a building, capable of favoring the best possible exploitation of the available electrical energy sources, rationalizing their exploitation and reducing costs for the building or the industrial process to which it is associated.

Nell'ambito di tale compito, uno scopo del trovato è quello di mettere a punto un impianto che cooperi ad ovviare ai problemi di gestione dei picchi di domanda energetica locali. Within the scope of this aim, an object of the invention is to provide a plant which cooperates in obviating the problems of managing local energy demand peaks.

Un altro scopo del trovato è quello di mettere a punto un impianto allestitile senza difficoltà particolari anche presso edifici già in essere. Un ulteriore scopo del trovato è quello di mettere a punto un procedimento per l'impiego di un simile impianto di ottimizzazione dello sfruttamento dell'energia elettrica a disposizione di un edificio . Another object of the invention is to provide a plant that can be fitted out without particular difficulties even in existing buildings. A further object of the invention is to provide a method for using a similar plant for optimizing the exploitation of the electrical energy available to a building.

Non ultimo scopo del trovato è quello di mettere a punto un impianto di ottimizzazione dello sfruttamento dell'energia elettrica a disposizione di un edificio, nonché un procedimento per il suo impiego, realizzabili con tecnologie note. Not least object of the invention is to provide a plant for optimizing the exploitation of electrical energy available to a building, as well as a method for its use, which can be produced with known technologies.

Questo compito, nonché questi ed altri scopi che meglio appariranno in seguito, sono raggiunti da un impianto per l'ottimizzazione dello sfruttamento dell'energia elettrica a disposizione di un edificio, comprendente This task, as well as these and other purposes which will appear better later, are achieved by a plant for the optimization of the exploitation of the electrical energy available to a building, comprising

- almeno un impianto generatore di energia alternativa, per la fornitura di energia elettrica - un primo serbatoio coibentato di accumulo (13), o boiler, per accumulo di acqua calda sanitaria, caratterizzato dal fatto di comprendere - at least one alternative energy generator system, for the supply of electricity - a first insulated storage tank (13), or boiler, for the storage of domestic hot water, characterized in that it comprises

- un secondo serbatoio, ad elevata inerzia termica, per accumulo di acqua per la fornitura ausiliaria dell'impianto di riscaldamento/ raff rescamento degli ambienti dell'edificio, o dell'impianto di preriscaldamento/ preraffreddamento di un processo industriale, - a second tank, with high thermal inertia, for accumulation of water for the auxiliary supply of the heating / cooling system of the building environments, or of the pre-heating / pre-cooling system of an industrial process,

- una pompa di calore ad acqua, atta alternativamente a fornire acqua all'impianto di riscaldamento/ raf frescamento di un edificio, o ad un impianto di preriscaldamento/ preraffreddamento di un processo industriale, o a rifornire di acqua calda il primo serbatoio, o a rifornire di acqua calda o fredda il secondo serbatoio, - a water-based heat pump, which can alternatively supply water to the heating / cooling system of a building, or to a pre-heating / pre-cooling system of an industrial process, or to supply the first tank with hot water, or to supply water hot or cold water the second tank,

- una prima sonda per la misurazione della temperatura dell'acqua nel primo serbatoio - a first probe for measuring the temperature of the water in the first tank

- una seconda sonda per la misurazione della temperatura dell'acqua nel secondo serbatoio - a second probe for measuring the water temperature in the second tank

- una terza sonda per la misurazione della temperatura dell'ambiente esterno - a third probe for measuring the temperature of the external environment

- una unità elettronica di controllo e di gestione per razionalizzare l'impiego di energia elettrica per l'alimentazione della pompa di calore, per la fornitura dell'impianto elettrico dell'edificio e per l'accumulo d'energia in forma d'acqua termicamente trattata in detti serbatoio primo e secondo, in base alle esigenze termiche dell'edificio o dei processi industriali in esso realizzati, alla produzione di energia elettrica dell 'almeno un impianto di energia alternativa e alle fasce orarie di basso costo dell'energia da rete elettrica locale. - an electronic control and management unit to rationalize the use of electricity to power the heat pump, to supply the building's electrical system and to store energy in the form of water thermally treated in said first and second tanks, according to the thermal needs of the building or the industrial processes carried out therein, to the production of electricity by at least one alternative energy plant and to the time bands of low cost of electricity from the electricity grid local.

Ulteriori caratteristiche e vantaggi del trovato risulteranno maggiormente dalla descrizione di una forma di esecuzione preferita, ma non esclusiva, dell'impianto secondo il trovato, illustrato, a titolo indicativo e non limitativo, negli uniti disegni, in cui: Further characteristics and advantages of the invention will become clearer from the description of a preferred, but not exclusive, embodiment of the system according to the invention, illustrated, by way of non-limiting example, in the accompanying drawings, in which:

—la figura 1 rappresenta schematicamente un impianto secondo il trovato; Figure 1 schematically represents a plant according to the invention;

—la figura 2 rappresenta uno schema a blocchi relativo ad un procedimento d'impiego dell'impianto secondo il trovato. Figure 2 is a block diagram relating to a method for using the plant according to the invention.

Con riferimento alle figure citate, un impianto per l'ottimizzazione dello sfruttamento dell'energia elettrica a disposizione di un edificio, è indicato nel suo complesso con il numero 10. With reference to the aforementioned figures, a plant for optimizing the exploitation of electricity available to a building is indicated as a whole with the number 10.

Tale impianto 10 comprende Such plant 10 comprises

- un impianto fotovoltaico 11 con inverter 12, per la fornitura di energia elettrica, - a photovoltaic system 11 with inverter 12, for the supply of electricity,

- un primo serbatoio di accumulo 13, o boiler, ad elevata inerzia termica, per accumulo di acqua calda sanitaria, - a first storage tank 13, or boiler, with high thermal inertia, for accumulation of domestic hot water,

- un secondo serbatoio di accumulo 14, ad elevata inerzia termica, ausiliario, per accumulo di acqua per la fornitura ausiliaria dell'impianto di riscaldamento/ raf frescamente IRR degli ambienti dell'edificio E, o per la fornitura di un impianto di preriscaldamento/preraffreddamento (o di riscaldamento/raffreddamento) di un processo industriale, - a second storage tank 14, with high thermal inertia, auxiliary, for water accumulation for the auxiliary supply of the heating / cooling system IRR of the rooms of building E, or for the supply of a pre-heating / pre-cooling system (or heating / cooling) of an industrial process,

- una pompa di calore ad acqua 15, atta alternativamente a fornire acqua all'impianto di riscaldamento/ raf frescamente IRR di un edificio E, o ad un impianto di preriscaldamento/ preraffreddamento (o di riscaldamento/ raffreddamento) di un processo industriale, o a rifornire di acqua calda il primo serbatoio d'accumulo 13, per acqua calda sanitaria, o a rifornire di acqua calda o fredda il secondo serbatoio d'accumulo 14, acqua destinata all'impianto di riscaldamento/raf frescamento o ad un impianto di un processo industriale, - a water-based heat pump 15, suitable alternatively to supply water to the heating / cooling system IRR of a building E, or to a pre-heating / pre-cooling (or heating / cooling) system of an industrial process, or to supply the first storage tank 13 with hot water, for domestic hot water, or to supply the second storage tank 14 with hot or cold water, water intended for the heating / cooling system or for an industrial process plant,

- una prima sonda 16 per la misurazione della temperatura dell'acqua nel primo serbatoio 13, - una seconda sonda 17 per la misurazione della temperatura dell'acqua nel secondo serbatoio 14, - una terza sonda 18 per la misurazione della temperatura dell'ambiente esterno, - a first probe 16 for measuring the temperature of the water in the first tank 13, - a second probe 17 for measuring the temperature of the water in the second tank 14, - a third probe 18 for measuring the temperature of the external environment ,

—una unità elettronica di controllo e di qestione 19, interconnessa con la pompa di calore 15, con l'impianto fotovoltaico 11, con l'impianto elettrico IE dell'edificio E a cui tale impianto di ottimizzazione 10 è associato, e con dette sonde 16, 17, 18 - an electronic control and management unit 19, interconnected with the heat pump 15, with the photovoltaic system 11, with the electrical system IE of building E to which this optimization system 10 is associated, and with said probes 16, 17, 18

Tale unità elettronica di controllo e qestione 19 è atta a razionalizzare 1 'impieqo di enerqia elettrica per l'alimentazione della pompa di calore 15, per la fornitura dell'impianto elettrico IE dell'edificio E, e per l'accumulo d' enerqia in forma d'acqua termicamente trattata nei serbatoi di accumulo primo 13 e secondo 14, in base alle esigenze termiche dell'edificio E, o alle esigenze termiche dell'impianto di preriscaldamento/ preraffreddamento (o di riscaldamento/ raffreddamento) di un processo industriale, alla produzione di energia elettrica dell'impianto fotovoltaico 11, e alle eventuali fasce orarie di basso costo dell'energia elettrica da rete elettrica locale RE. This electronic control and management unit 19 is adapted to rationalize the use of electrical energy for the power supply of the heat pump 15, for the supply of the electrical system IE of building E, and for the accumulation of energy in form of water thermally treated in the first 13 and second 14 storage tanks, according to the thermal needs of the building E, or to the thermal needs of the preheating / pre-cooling (or heating / cooling) system of an industrial process, to production of electricity from the photovoltaic system 11, and at any time bands of low cost of electricity from the local electricity grid RE.

L'impianto 10 comprende un multimetro 20, o altro dispositivo simile ed equivalente, in corrispondenza dei punti di connessione tra impianto fotovoltaico 11 e rete elettrica RE, per controllare se l'impianto fotovoltaico 11 sta cedendo potenza alla rete elettrica RE o se invece l'edificio E sta assorbendo energia dalla rete elettrica RE, ovvero se la potenza assorbita dall'impianto di ottimizzazione 10 stesso proviene dalla rete elettrica. The system 10 comprises a multimeter 20, or other similar and equivalent device, at the connection points between the photovoltaic system 11 and the RE electrical network, to check whether the photovoltaic system 11 is giving power to the RE electrical network or if the building E is absorbing energy from the electricity grid RE, that is, if the power absorbed by the optimization plant 10 itself comes from the electricity grid.

Le componenti dell'impianto connesse con detta unità elettronica di controllo e gestione 19 comunicano mediante protocollo Modbus RTU, o mediante un altro protocollo simile ed equivalente . The system components connected to said electronic control and management unit 19 communicate by means of the Modbus RTU protocol, or by means of another similar and equivalent protocol.

L'impianto 10 secondo il trovato può inoltre comprendere un multimetro secondario, o altro dispositivo equivalente, non illustrato per semplicità, da collegare all'inverter 12, nel caso in cui lo stesso inverter 12 non sia in grado di dialogare con protocollo Modbus RTU o altro protocollo simile. The system 10 according to the invention can also comprise a secondary multimeter, or other equivalent device, not illustrated for simplicity, to be connected to the inverter 12, in the event that the inverter 12 itself is unable to communicate with the Modbus RTU protocol or other similar protocol.

E' allestitile anche un ulteriore multimetro dedicato, o altro dispositivo equivalente, qualora si voglia tenere sotto controllo la potenza assorbita da un singolo carico, ad esempio la pompa di calore 15. An additional dedicated multimeter, or other equivalent device, is also set up if you want to keep the power absorbed by a single load under control, for example the heat pump 15.

Un simile impianto 10 secondo il trovato è in grado di abbinare la produzione di energia elettrica da un impianto fotovoltaico 11 alla produzione di energia termica e frigorifera della pompa di calore 15, utilizzando i serbatoi di accumulo primo 13 e secondo 14 per impiegare in modo più continuativo ed efficiente la pompa di calore 15, riducendone i continui passaggi di accensione e spegnimento. A similar system 10 according to the invention is capable of combining the production of electrical energy from a photovoltaic system 11 with the production of thermal and cooling energy of the heat pump 15, using the first storage tanks 13 and second 14 to use more the heat pump 15 is continuous and efficient, reducing the continuous switch-on and switch-off steps.

Infatti l'unità elettronica di controllo 19 è programmata per far funzionare la pompa di calore 15 sempre quando vi sia la possibilità accumulare energia termica nei serbatoi 13 e 14 sotto forma di acqua trattata termicamente, ovvero riscaldata o raffreddata, dando priorità al funzionamento della pompa di calore 15 nei periodi di fornitura di energia elettrica più vantaggiosi economicamente . In fact, the electronic control unit 19 is programmed to operate the heat pump 15 whenever there is the possibility of accumulating thermal energy in the tanks 13 and 14 in the form of heat-treated, or heated or cooled water, giving priority to the operation of the pump. heat 15 in the most economically advantageous periods of electricity supply.

Quindi l'unità elettronica 19 è programmata per far funzionare la pompa di calore 15 Then the electronic unit 19 is programmed to operate the heat pump 15

- o quando vi è una parte di potenza prodotta dall'impianto fotovoltaico 11 che è eccedente alla potenza fornita all'impianto elettrico IE dell'edificio E, e che quindi può essere destinata alla pompa di calore 15 anziché essere erogata alla rete elettrica RE a cui l'impianto fotovoltaico 11 è connesso, - or when there is a part of power produced by the photovoltaic system 11 which is in excess of the power supplied to the electrical system IE of building E, and which therefore can be destined for the heat pump 15 instead of being supplied to the electrical network RE a to which the photovoltaic system 11 is connected,

- o nel caso di sovraproduzione di energia da parte dell'impianto fotovoltaico 11, nei giorni particolarmente assolati, - or in the case of overproduction of energy by the photovoltaic system 11, on particularly sunny days,

- o in una fascia oraria di costo ridotto dell'energia da rete elettrica RE, qualora non sia disponibile potenza dall'impianto fotovoltaico 11, come nelle ore notturne. - or in a time slot with a reduced cost of energy from the RE electricity grid, if power is not available from the photovoltaic system 11, such as at night.

Sia l'acqua sanitaria nel primo serbatoio 13 che l'acqua di condizionamento nel secondo serbatoio 14, vengono portate e mantenute in temperatura mediante l'impiego della pompa di calore 15 nei momenti della giornata piu energeticamente convenienti . Both the sanitary water in the first tank 13 and the conditioning water in the second tank 14 are brought and maintained at temperature by using the heat pump 15 at the most energetically convenient moments of the day.

Gli accumuli dei serbatoi 13 e 14 vengono quindi impiegati nei rispettivi impianti dell'edificio E, ovvero circuito d'acqua calda sanitaria CS, o impianto di ri scaldamento/ raffrescamento IRR, nei momenti in cui l'energia elettrica da rete, se assorbita, risulterebbe più costosa, e nei quali momenti, quindi, l'unità elettronica di controllo 19 è programmata per far funzionare la pompa di calore 15 il meno possibile. The accumulations of the tanks 13 and 14 are then used in the respective systems of building E, or the DHW circuit CS, or the heating / cooling system IRR, in the moments in which the electricity from the network, if absorbed, it would be more expensive, and at which times, therefore, the electronic control unit 19 is programmed to operate the heat pump 15 as little as possible.

L'impianto 10 è quindi in grado di gestire gli accumuli, dimensionati in modo da avere una autonomia opportuna, ad esempio di qualche giorno, favorendo il funzionamento della pompa di calore nelle ore tipicamente di buona insolazione o nelle fasce orarie con basso costo dell'energia elettrica . The system 10 is therefore able to manage the accumulations, sized in such a way as to have a suitable autonomy, for example of a few days, favoring the operation of the heat pump in the hours typically of good insolation or in the time bands with low cost of electric energy .

La possibilità di accumulare energia sotto forma di acqua calda o acqua fredda, oltre ad aumentare e controllare l'autoconsumo da parte dell'edificio E, o da parte del processo industriale, dell'energia elettrica prodotta dall'impianto fotovoltaico 11, risolve anche il problema del picco di richiesta energetica a livello locale, dal momento che in caso di scarsa fornitura dalla rete elettrica RE i serbatoi 13 e 14 sono sempre in grado di assicurare il regolare funzionamento del circuito d'acqua sanitaria CS e dell'impianto di riscaldamento/raffreddamento IRR, previa opportuno dimensionamento degli stessi serbatoi 13 e 14. The possibility of accumulating energy in the form of hot or cold water, in addition to increasing and controlling the self-consumption by building E, or by the industrial process, of the electricity produced by the photovoltaic system 11, also solves the problem of the peak energy demand at local level, since in the event of a poor supply from the RE electricity network, the tanks 13 and 14 are always able to ensure the regular operation of the DHW circuit CS and the heating system / IRR cooling, after appropriate sizing of the same tanks 13 and 14.

L'impianto 10 è quindi predisposto per erogare alla rete elettrica RE il minimo di potenza elettrica possibile, prediligendo l'autoconsumo di energia da parte dell'edificio E. System 10 is therefore designed to supply the minimum possible electrical power to the RE electrical network, preferring the self-consumption of energy by building E.

Forma oggetto del trovato anche un procedimento, o metodo, per l'impiego di un impianto 10 per l'ottimizzazione dello sfruttamento dell'energia elettrica a disposizione di un edificio, come sopra descritto. The invention also relates to a process, or method, for the use of a plant 10 for optimizing the exploitation of the electrical energy available to a building, as described above.

Tale procedimento, schematizzato in figura 2, comprende le seguenti operazioni: This procedure, schematized in figure 2, includes the following operations:

- impostare nell'unità elettronica di controllo 19 i seguenti valori di temperature per la pompa di calore 15: - set the following temperature values for the heat pump 15 in the electronic control unit 19:

- temperatura ideale acqua calda Tac±daccumulata nel secondo serbatoio 14 per il condizionamento - temperatura minima Tacminaccumulo acqua calda per il condizionamento nel secondo serbatoio 14 - ideal Tac hot water temperature ± d accumulated in the second tank 14 for air conditioning - Tac min minimum temperature accumulated hot water for air conditioning in the second tank 14

- temperatura massima Tacmaxaccumulo acqua calda per il condizionamento nel secondo serbatoio 14 - temperatura ideale acqua fredda Tafidaccumulata nel secondo serbatoio 14 per il condizionamento - temperatura minima Tafminaccumulo acqua fredda per il condizionamento nel secondo serbatoio 14 - temperatura massima Tafmaxaccumulo acqua fredda per il condizionamento nel secondo serbatoio 14 - temperatura ideale accumulo acqua calda sanitaria Tb±din detto primo serbatoio 13 - maximum temperature Tacmax hot water storage for conditioning in the second tank 14 - ideal temperature Tafid cold water stored in the second tank 14 for conditioning - minimum temperature Tafmin cold water storage for conditioning in the second tank 14 - maximum temperature Tafmax cold water storage for conditioning in the second tank 14 - ideal domestic hot water storage temperature Tb ± din said first tank 13

- temperatura minima accumulo acqua calda sanitaria Tbminnel primo serbatoio 13 - minimum domestic hot water storage temperature Tbmin in the first tank 13

- temperatura massima accumulo acqua calda sanitaria Tbmaxnel primo serbatoio 13, - maximum domestic hot water storage temperature Tbmax in the first tank 13,

- impostare le fasce orarie di erogazione energia elettrica da rete elettrica RE a tariffa minore - stabilire la modalità di funzionamento per la pompa di calore 15, modalità 'estiva' per la produzione di acqua fredda o modalità 'invernale' per la produzione di acqua calda, - set the time bands for electricity supply from the RE electricity network at a lower rate - establish the operating mode for the heat pump 15, 'summer' mode for the production of cold water or 'winter' mode for the production of hot water ,

- rilevare la temperatura ambiente Te, - detect the ambient temperature Te,

- rilevare la temperatura Tb dell'acqua nel primo serbatoio 13 per acqua calda sanitaria - measure the temperature Tb of the water in the first tank 13 for domestic hot water

rilevare la temperatura Ta dell'acqua nel secondo serbatoio 14 per acqua per impianto di riscaldamento / raffreddamento detect the temperature Ta of the water in the second tank 14 for water for the heating / cooling system

—rilevare la potenza prodotta dall'impianto fotovoltaico Ptot.iFv, - detect the power produced by the Ptot.iFv photovoltaic system,

—verificare se l'impianto elettrico IE sta assorbendo potenza Ρass.ΙΕ dalla rete elettrica RE, o se l'impianto fotovoltaico 11 sta erogando potenza all'impianto elettrico IE e alla rete elettrica - check if the IE electrical system is absorbing Ρass.ΙΕ power from the RE electrical network, or if the photovoltaic system 11 is supplying power to the IE electrical system and to the electrical network

RE, ovvero se una parte Pecc della potenza Ptot.iFv prodotta dall'impianto fotovoltaico 11 è eccedente rispetto alla potenza assorbita Pass.iE dall'impianto elettrico IE dell'edificio E, RE, i.e. if a Pecc part of the Ptot.iFv power produced by the photovoltaic system 11 exceeds the absorbed power Pass.iE by the electrical system IE of building E,

—se l'impianto elettrico IE sta assorbendo potenza dalla rete elettrica Ρass.ΙΕ verificare se rispetto alla potenza assorbibile contrattuale Pass.cont vi è una parte di potenza Pass.pc disponibile sufficiente ad alimentare la pompa di calore 15, - if the IE electrical system is absorbing power from the electrical network Ρass.ΙΕ check if compared to the contractual absorbable power Pass.cont there is a part of Pass.pc power available sufficient to power the heat pump 15,

—se la parte di potenza eccedente disponibile Pece è sufficiente ad alimentare detta pompa di calore 15, se si rileva di essere in una fascia oraria di costo elevato, e se una delle temperature Ta, Tb rilevate nei serbatoi primo 13 e secondo 14 è inferiore alla corrispondente temperatura minima Tacmin, Tbmin, o superiore alla temperatura massima Tafmax nel caso in cui la pompa di calore 15 sia in modalità 'estate' e il secondo serbatoio 14 accumuli acqua fredda, allora avviare la pompa di calore 15 per portare o detto primo serbatoio 13 alla corrispondente temperatura minima Tbmin, o detto secondo serbatoio 14 alla temperatura minima Tacmin, in regime invernale, o massima Tafmax in regime estivo, - if the part of excess power available Pece is sufficient to power said heat pump 15, if it is found to be in a time band of high cost, and if one of the temperatures Ta, Tb detected in the first 13 and second 14 tanks is lower at the corresponding minimum temperature Tacmin, Tbmin, or higher than the maximum temperature Tafmax if the heat pump 15 is in 'summer' mode and the second tank 14 stores cold water, then start the heat pump 15 to bring or said first tank 13 at the corresponding minimum temperature Tbmin, or said second tank 14 at minimum Tacmin temperature, in winter mode, or maximum Tafmax in summer mode,

—se una parte Pece della potenza prodotta dall'impianto fotovoltaico Ptot.iFv è eccedente rispetto alla potenza assorbita Pass.iE dall'impianto elettrico IE dell'edificio E, e se tale potenza eccedente Pece è sufficiente ad alimentare detta pompa di calore 15, allora si alimenta la pompa di calore per portare o l'acqua in detto primo serbatoio alla sua temperatura ideale Tbid, o l'acqua in detto secondo serbatoio alla temperatura massima Tacmax o minima Tafmin, a seconda che la modalità d'uso della pompa di calore 15 sia 'invernale' o 'estiva'. - if a pitch part of the power produced by the photovoltaic system Ptot.iFv exceeds the power absorbed Pass.iE by the electrical system IE of building E, and if this excess power is sufficient to power said heat pump 15, then the heat pump is fed to bring either the water in said first tank to its ideal temperature Tbid, or the water in said second tank to the maximum temperature Tacmax or minimum Tafmin, depending on whether the mode of use of the heat 15 either 'winter' or 'summer'.

Tale procedimento secondo il trovato prevede inoltre che This method according to the invention further provides that

se detta parte di potenza disponibile PassPC è sufficiente ad alimentare detta pompa di calore 15, se si rileva di essere in una fascia oraria di costo ridotto, e se una delle temperature Ta, Tb rilevate nei serbatoi primo 13 e secondo 14 è minore alla corrispondente temperatura ideale Tacid, Tbid, o superiore alla temperatura ideale Tafid nel caso in cui la pompa di calore 15 sia in modalità 'estate' e il secondo serbatoio 14 accumuli acqua fredda, if said part of available power PassPC is sufficient to power said heat pump 15, if it is found to be in a time band of reduced cost, and if one of the temperatures Ta, Tb detected in the first 13 and second 14 tanks is lower than the corresponding ideal temperature Tacid, Tbid, or higher than the ideal Tafid temperature if the heat pump 15 is in 'summer' mode and the second tank 14 is storing cold water,

- allora avviare la pompa di calore 15 per portare o detto primo serbatoio 13 alla corrispondente temperatura ideale Tbid, o detto secondo serbatoio 14 alla temperatura ideale Tacid o Tafid. - then starting the heat pump 15 to bring either said first tank 13 to the corresponding ideal temperature Tbid, or said second tank 14 to the ideal Tacid or Tafid temperature.

Il procedimento secondo il trovato prevede inoltre che The method according to the invention further provides that

- se vi è una parte Pecc della potenza prodotta dall'impianto fotovoltaico PtotlFV che è eccedente rispetto alla potenza assorbita PassIE e sufficiente ad alimentare detta pompa di calore 15, l'alimentazione di detta pompa di calore per portare o l'acqua in detto primo serbatoio alla sua temperatura ideale Tbid, o l'acqua in detto secondo serbatoio alla temperatura massima Tacmax o minima Tafmin, avviene per cicli successivi, atti ad elevare la temperatura di un prestabilito intervallo di temperatura Itemp, ad esempio di 2°C, fino al raggiungimento delle temperature preimpostate Tacmax, Tafmin o Tbid. - if there is a Pecc part of the power produced by the photovoltaic system PtotlFV which is in excess of the absorbed power PassIE and sufficient to power said heat pump 15, the power supply of said heat pump to bring either the water into said first tank at its ideal temperature Tbid, or the water in said second tank at maximum Tacmax or minimum Tafmin temperature, occurs in successive cycles, designed to raise the temperature by a predetermined Itemp temperature range, for example by 2 ° C, up to reaching the preset temperatures Tacmax, Tafmin or Tbid.

Durante ogni ciclo, ad intervalli di tempo ITC prestabiliti, si verifica se vi è una parte Pecc della potenza prodotta dall'impianto fotovoltaico PtotlFP che è eccedente rispetto alla potenza assorbita PassIE e sufficiente ad alimentare detta pompa di calore 15, o se l'alimentazione della pompa di calore provenga dalla rete elettrica RE, e non più dall'impianto fotovoltaico. During each cycle, at pre-established ITC time intervals, it is checked whether there is a Pecc part of the power produced by the PtotlFP photovoltaic system which is in excess of the absorbed power PassIE and sufficient to power said heat pump 15, or if the power supply of the heat pump comes from the RE electrical network, and no longer from the photovoltaic system.

In figura 2 lo schema a blocchi 100 rappresenta schematicamente la serie di operazioni sopra descritte . In Figure 2 the block diagram 100 schematically represents the series of operations described above.

Il primo blocco 101 rappresenta l'assunzione da parte dell'unità elettronica di controllo 19 dei dati di temperatura, con impostazione della data corrente, e delle date di passaggio dalla modalità estate alla modalità inverno per la pompa di calore 15. The first block 101 represents the assumption by the electronic control unit 19 of the temperature data, with setting of the current date, and of the dates for the passage from summer to winter mode for the heat pump 15.

Eventualmente il passaggio di modalità da estate a inverno e viceversa può essere realizzata manualmente, in modo da poter applicare impianto e procedimento anche al semplice riscaldamento, o prer iscaldamento/ raffreddamente, o preraffreddamento, di un processo industriale. If necessary, the change of mode from summer to winter and vice versa can be carried out manually, so as to be able to apply the system and procedure even to the simple heating, or pre-heating / cooling, or pre-cooling, of an industrial process.

I blocchi 102 e 103 indicano rispettivamente il caricamento, da parte dell'unità elettronica di controllo 19, delle temperature Tacid, Tafid e Tbid, a seconda della temperatura ambiente Te ed in base a curve di temperatura predefinite e corrispondenti o alla modalità di funzionamento estiva o alla modalità di funzionamento imnvernale della pompa di calore 15. Blocks 102 and 103 indicate respectively the loading, by the electronic control unit 19, of the Tacid, Tafid and Tbid temperatures, depending on the ambient temperature Te and on the basis of predefined and corresponding temperature curves or the summer operating mode or to the winter operating mode of the heat pump 15.

II blocco 104 stabilisce l'avvio o il non avvio in automatico della sequenza di operazioni sopra descritte . Block 104 establishes the automatic start or non-start of the sequence of operations described above.

In caso di avvio automatico, il blocco 105 schematizza la verifica se l'impianto elettrico IE sta assorbendo potenza dalla rete elettrica Pass.IE e se rispetto alla potenza assorbibile contrattuale In the event of automatic start-up, block 105 schematically checks whether the IE electrical system is absorbing power from the Pass.IE electrical network and whether compared to the contractual absorbable power

Pass.cont vi è una parte di potenza disponibile sufficiente ad alimentare la pompa di calore Pass.cont there is enough power available to power the heat pump

Pass.PC. Pass.PC.

In caso affermativo, ovvero l'impianto elettrico IE sta assorbendo energia dalla rete RE, e quindi sta impiegando energia elettrica costosa, e vi è una potenza disponibile per la pompa di calore, allora la pompa di calore 15 viene attivata solo per mantenere le temperature Ta e Tb nei serbatoi primo e secondo ai valori minimi Tacmin, Tbmin, o massimo Tafmax in caso di modalità estiva, con conseguente minor impiego possibile di energia elettrica costosa dalla rete RE. If so, i.e. the electrical system IE is absorbing energy from the RE network, and therefore is using expensive electricity, and there is power available for the heat pump, then the heat pump 15 is activated only to maintain temperatures Ta and Tb in the first and second tanks at the minimum values Tacmin, Tbmin, or maximum Tafmax in the case of summer mode, resulting in the lowest possible use of expensive electricity from the RE network.

In caso negativo, ovvero non vi è potenza disponibile per alimentare la pompa di calore 15, allora, blocco 108, si valuta se Tac, Taf o Tb siano minori, o maggiore nel caso di Taf, delle rispettive Tacmin, Tafmax, Tbmin. In the negative case, i.e. there is no power available to feed the heat pump 15, then, block 108, it is evaluated whether Tac, Taf or Tb are lower, or higher in the case of Taf, than the respective Tacmin, Tafmax, Tbmin.

Se si, si va ai blocchi 106 e 107, se no, si passa al blocco 109, secondo cui l'unità di controllo 19 verifica se l'impianto fotovoltaico 11 sta cedendo corrente alla rete RE oppure no. If yes, go to blocks 106 and 107, if not, go to block 109, according to which the control unit 19 checks whether the photovoltaic system 11 is transferring current to the grid RE or not.

Se no, cioè se l'impianto fotovoltaico non sta cedendo potenza alla rete, e quindi la pompa di calore 15 per funzionare ha bisogno dell'energia della rete RE, l'unità di controllo 19 valuta, blocco 110, se si è in corrispondenza di una fascia oraria a basso costo per l'energia elettrica da rete RE. If not, that is, if the photovoltaic system is not yielding power to the grid, and therefore the heat pump 15 needs the energy of the RE grid to function, the control unit 19 evaluates, block 110, if it is in correspondence a low-cost time slot for electricity from the RE network.

Se si, blocco 111, la pompa di calore 15 viene settata per funzionare fino a portare le temperature Ta e Tb ai valori ideali, funzionando quindi vantaggiosamente nell'orario di costo ridotto dell'energia. If yes, block 111, the heat pump 15 is set to operate until the temperatures Ta and Tb are brought to the ideal values, thus operating advantageously in the time of reduced energy cost.

Se no, l'unità di controllo 19 torna all'operazione del blocco 108. If not, the control unit 19 returns to the operation of block 108.

Se invece la verifica al blocco 109, se l'impianto fotovoltaico 11 sta cedendo corrente alla rete RE oppure no, ha risposta affermativa, ovvero è disponibile una potenza eccedente Pecc utile ad alimentare la pompa di calore 15 sfruttando l'energia prodotto dall'impianto fotovoltaico 11 che non viene assorbita dall'impianto elettrico IE dell'edificio E, allora dal blocco 110, parte la serie di cicli 112 per portare la temperatura Ta ai suoi valori minimo d'estate e massimo d'inverno, e Tb al suo valore ideale. If, on the other hand, it checks it in block 109, whether the photovoltaic system 11 is yielding current to the RE network or not, it has an affirmative answer, i.e. an excess power is available Pecc useful to power the heat pump 15 by exploiting the energy produced by the system photovoltaic 11 which is not absorbed by the electrical system IE of building E, then from block 110, the series of cycles 112 starts to bring the temperature Ta to its minimum values in summer and maximum in winter, and Tb to its value ideal.

Il blocco 113 schematizza il periodico controllo che l'impianto fotovoltaico 11 stia sempre cedendo potenza alla rete RE. Block 113 schematises the periodic check that the photovoltaic system 11 is always giving power to the grid RE.

Se non vi è più potenza ceduta alla rete, allora si torna ai blocchi 106 e 107, secondo cui la pompa di calore 15 assorbe corrente da rete RE e quindi viene fatta funzionare solo per mantenere Ta e Tb ai valori minimi al di sotto dei quali gli impianti serviti darebbero un disservizio. If there is no more power transferred to the network, then we return to blocks 106 and 107, according to which the heat pump 15 draws current from the network RE and is therefore operated only to keep Ta and Tb at the minimum values below which the plants served would give a disservice.

L'unità elettronica di controllo 19 è facilmente gestibile mediante un pannello operatore, ad esempio di tipo Touch Screen, il quale raccoglie tutti i dati, e tramite la logica PLC in dotazione all'unità 19 elabora tutte le informazioni secondo il procedimento e l'algoritmo sopra descritti. The electronic control unit 19 can be easily managed by means of an operator panel, for example of the Touch Screen type, which collects all the data, and through the PLC logic supplied with the unit 19 processes all the information according to the procedure and algorithm described above.

Il pannello operatore inoltre visualizza i dati dell'impianto fotovoltaico 11, il bilancio di carico, gli allarmi dello stesso impianto fotovoltaico 11 e gli allarmi della pompa di calore 15. The operator panel also displays the data of the photovoltaic system 11, the load balance, the alarms of the same photovoltaic system 11 and the alarms of the heat pump 15.

Dal pannello di controllo è inoltre possibile settare tutti i parametri sensibili dell'impianto 10 secondo quanto richiesto dall'algoritmo. From the control panel it is also possible to set all the sensitive parameters of the system 10 as required by the algorithm.

Nel caso ci fossero le esigenze di integrazione del sistema con un sistema di supervisione e telecont rollo remoto, sono disponibili varie soluzioni a seconda della disponibilità e degli obiettivi: è possibile la visualizzazione solo in rete locale, oppure tramite router è possibile leggere tutti i dati dal pannello operatore e ospitare una pagina web grafica visualizzabile da remoto ad esempio utilizzando una opportuna SIM dati e relativo hardware per poter visualizzare i dati su PC collegato ad internet o tramite smartphone . Should there be the need to integrate the system with a remote supervision and telecontrol system, various solutions are available depending on availability and objectives: it is possible to view only in the local network, or through a router it is possible to read all the data from the operator panel and host a graphic web page that can be viewed remotely, for example by using a suitable data SIM and relative hardware to be able to view the data on a PC connected to the internet or via smartphone.

L'impianto 10 può essere dotato di UPS, gruppo di continuità, per poter garantire un minimo di servizio di controllo anche in caso di interruzioni brevi dell'alimentazione elettrica. Si è in pratica constatato come il trovato raggiunga il compito e gli scopi preposti. The system 10 can be equipped with a UPS, an uninterruptible power supply, in order to guarantee a minimum of control service even in the event of short interruptions in the power supply. In practice it has been found that the invention achieves the intended aim and objects.

In particolare, con il trovato si è messo a punto un impianto per l'ottimizzazione dello sfruttamento dell'energia elettrica a disposizione di un edificio, capace di favorire il migliore sfruttamento possibile delle fonti di energia elettrica a disposizione, razionalizzandone lo sfruttamento e diminuendo i costi per l'edificio. Quindi, con il trovato si è messo a punto un impianto che coopera ad ovviare ai problemi di gestione dei picchi di domanda energetica locali, come anche coopera alla soluzione dei problemi di picco di produzione di energia da parte dell'impianto fotovoltaico. In particular, the invention has developed a plant for the optimization of the exploitation of the electricity available to a building, capable of favoring the best possible exploitation of the available electrical energy sources, rationalizing their exploitation and decreasing the costs for the building. Therefore, with the invention, a plant has been developed which cooperates in obviating the problems of managing local energy demand peaks, as well as cooperating in solving the problems of peak production of energy by the photovoltaic plant.

In più, con il trovato si è messo a punto un impianto allestitile senza difficolatà particolari anche presso edifici già in essere. In addition, the invention has developed a system that can be set up without particular difficulties even in existing buildings.

Non ultimo, con il trovato si è messo a punto un impianto di ottimizzazione dello sfruttamento dell'energia elettrica a disposizione di un edificio, nonché un procedimento per il suo impiego, realizzabili con tecnologie note. Last but not least, the invention provides a plant for optimizing the exploitation of the electrical energy available to a building, as well as a method for its use, which can be produced with known technologies.

Il trovato, così concepito, è suscettibile di numerose modifiche e varianti, tutte rientranti nell'ambito del concetto inventivo; inoltre, tutti i dettagli potranno essere sostituiti da altri elementi tecnicamente equivalenti. The invention thus conceived is susceptible of numerous modifications and variations, all of which are within the scope of the inventive concept; moreover, all the details can be replaced by other technically equivalent elements.

In pratica, i materiali impiegati, nonché le dimensioni e le forme contingenti, potranno essere qualsiasi a seconda delle esigenze e dello stato della tecnica. In practice, the materials used, as well as the contingent shapes and dimensions, may be any according to requirements and to the state of the art.

Ove le caratteristiche e le tecniche menzionate in qualsiasi rivendicazione siano seguite da segni di riferimento, tali segni sono stati apposti al solo scopo di aumentare l'intelligibilità delle rivendicazioni e di conseguenza tali segni di riferimento non hanno alcun effetto limitante sull'interpretazione di ciascun elemento identificato a titolo di esempio da tali segni di riferimento . Where the features and techniques mentioned in any claim are followed by reference marks, these marks have been affixed for the sole purpose of increasing the intelligibility of the claims and consequently such reference marks have no limiting effect on the interpretation of each element. identified by way of example by these reference signs.

Claims (2)

RIVENDICAZIONI 1) Impianto (10) per l'ottimizzazione dello sfruttamento dell'energia elettrica a disposizione di un edificio, comprendente - almeno un impianto generatore di energia alternativa, per la fornitura di energia elettrica - un primo serbatoio coibentato di accumulo (13), o boiler, per accumulo di acqua calda sanitaria, caratterizzato dal fatto di comprendere - un secondo serbatoio coibentato di accumulo (14), ausiliario, per accumulo di acqua per la fornitura ausiliaria dell'impianto di riscaldamento/ raf frescamente (IRR) degli ambienti dell'edificio (E), o di un impianto di riscaldamento o preriscaldamento/ raffreddamento o preraffreddamento di un processo industriale, - una pompa di calore ad acqua (15), atta alternativamente a fornire acqua all'impianto di riscaldamento/ raf frescamente (IRR) di un edificio, o ad un impianto di preriscaldamento/ preraffreddamento di un processo industriale, o a rifornire di acqua calda il primo serbatoio (13), o a rifornire di acqua calda o fredda il secondo serbatoio (14), - una prima sonda (16) per la misurazione della temperatura dell'acqua nel primo serbatoio (13) - una seconda sonda (17) per la misurazione della temperatura dell'acqua nel secondo serbatoio (14) - una terza sonda (18) per la misurazione della temperatura dell'ambiente esterno - una unità elettronica di controllo e di qestione (19) per razionalizzare l'impiego di energia elettrica per l'alimentazione della pompa di calore (15), per la fornitura dell'impianto elettrico (IE) dell'edificio (E) e per l'accumulo d'energia in forma d'acqua termicamente trattata in detti serbatoio primo (13) e secondo (14), in base alle esigenze termiche dell'edificio (E) o dei processi industriali in esso realizzati, alla produzione di energia elettrica dell 'almeno un impianto generatore di energia alternativa, e alle eventuali fasce orarie di basso costo dell'energia elettrica da rete elettrica locale (RE). CLAIMS 1) Plant (10) for the optimization of the exploitation of the electrical energy available to a building, comprising - at least one alternative energy generator system, for the supply of electricity - a first insulated storage tank (13), or boiler, for the storage of domestic hot water, characterized by the fact that it comprises - a second insulated storage tank (14), auxiliary, for water accumulation for the auxiliary supply of the heating / cooling system (IRR) of the rooms of the building (E), or of a heating or preheating system / cooling or pre-cooling of an industrial process, - a water-based heat pump (15), which can alternatively supply water to the heating / cooling system (IRR) of a building, or to a pre-heating / pre-cooling system of an industrial process, or to supply hot water to the first tank (13), or to supply the second tank (14) with hot or cold water, - a first probe (16) for measuring the temperature of the water in the first tank (13) - a second probe (17) for measuring the water temperature in the second tank (14) - a third probe (18) for measuring the temperature of the external environment - an electronic control and management unit (19) to rationalize the use of electricity to power the heat pump (15), to supply the electrical system (IE) of the building (E) and to the accumulation of energy in the form of thermally treated water in said first (13) and second (14) tanks, based on the thermal requirements of the building (E) or of the industrial processes carried out therein, for the production of electricity of at least one alternative energy generating plant, and to any time bands of low cost of electricity from the local electricity grid (RE). 2) Impianto secondo la rivendicazione 1, che si caratterizza per il fatto che detto almeno un impianto generatore di energia alternativa è dato da un impianto fotovoltaico (11) con inverter (12). 3)Impianto secondo le rivendicazioni precedenti, caratterizzato dal fatto di comprendere un multimetro (20), o altro dispositivo simile ed equivalente, in corrispondenza dei punti di connessione tra impianto fotovoltaico e rete elettrica per controllare se impianto fotovoltaico sta cedendo potenza alla rete elettrica o se l'edificio (E) sta assorbendo energia dalla rete elettrica (RE), ovvero se la potenza assorbita dall'impianto di ottimizzazione (10) stesso proviene dalla rete elettrica. 4) Impianto secondo le rivendicazioni precedenti, che si caratterizza per il fatto che le componenti dell'impianto connesse con detta unità elettronica di controllo e gestione (19) comunicano mediante protocollo Modbus RTU, o altro protocollo simile ed equivalente. 5) Procedimento per l'impiego di un impianto per l'ottimizzazione dello sfruttamento dell'energia elettrica a disposizione di un edificio, secondo una o più delle rivendicazioni precedenti, caratterizzato dal fatto di comprendere le seguenti operazioni: - impostare nell'unità elettronica di controllo (19) i seguenti valori di temperature per la pompa di calore (15) - temperatura ideale acqua calda (Tacid) accumulata nel secondo serbatoio (14) per il condizionamento - temperatura minima (TaCmin) accumulo acqua calda per il condizionamento nel secondo serbatoio - temperatura massima (Tacmx) accumulo acqua calda per il condizionamento nel secondo serbatoio - temperatura ideale acqua fredda (Tafid) accumulata nel secondo serbatoio per il condizionamento - temperatura minima (Tafmin) accumulo acqua fredda per il condizionamento nel secondo serbatoio - temperatura massima (Tafmax) accumulo acqua fredda per il condizionamento nel secondo serbatoio - temperatura ideale accumulo acqua calda sanitaria (Tbid) in detto primo serbatoio (13) - temperatura minima accumulo acqua calda sanitaria (Tbmin) nel primo serbatoio (13) - temperatura massima accumulo acqua calda sanitaria (Tbmax) nel primo serbatoio, - impostare le fasce orarie di erogazione energia elettrica da rete elettrica (RE) a tariffa minore - stabilire la modalità di funzionamento per la pompa di calore (15), modalità estiva per la produzione di acqua fredda o modalità invernale per la produzione di acqua calda, - rilevare la temperatura ambiente (Te), - rilevare la temperatura (Tb) dell'acqua nel primo serbatoio (13) per acqua calda sanitaria - rilevare la temperatura dell'acqua (Ta) nel secondo serbatoio per acqua per impianto di riscaldamento / raffreddamento —rilevare la potenza prodotta dall'impianto fotovoltaico (PtotlFV), —verificare se l'impianto elettrico (IE) sta assorbendo potenza (PassIE) dalla rete elettrica (RE), o se una parte (Pecc) della potenza prodotta dall'impianto fotovoltaico (PtotlFV) è eccedente rispetto alla potenza assorbita (PassIE) dall'impianto elettrico dell'edificio, —se l'impianto elettrico (IE) sta assorbendo potenza dalla rete elettrica (PassIE) verificare se rispetto alla potenza assorbibile contrattuale (Pass.cont) vi è una parte di potenza disponibile sufficiente ad alimentare la pompa di calore (PassPC) —se la parte di potenza disponibile (PassPC) è sufficiente ad alimentare detta pompa di calore (15), se si rileva di essere in una fascia oraria di costo elevato, e se una delle temperature (Ta, Tb) rilevate nei serbatoi primo (13) e secondo (14) è inferiore alla corrispondente temperatura minima (Tacmin, Tbmin) , o superiore alla temperatura massima (Tafmax) nel caso in cui la pompa di calore (15) sia in modalità 'estate' e il secondo serbatoio (14) accumuli acqua fredda, allora avviare la pompa di calore per portare o detto primo serbatoio alla corrispondente temperatura minima, o detto secondo serbatoio alla temperatura minima, in regime invernale, o massima in regime estivo, —se una parte (Pecc) della potenza prodotta dall'impianto fotovoltaico (PtotlFV) è eccedente rispetto alla potenza assorbita (PassIE) dall'impianto elettrico dell'edificio, e se tale potenza eccedente (Pecc) è sufficiente ad alimentare detta pompa di calore (15), allora si alimenta la pompa di calore per portare o l'acqua in detto primo serbatoio alla sua temperatura ideale (Tbid), o 1 'acqua in detto secondo serbatoio alla temperatura massima (Tacmax) o minima (Tafmin) , a seconda se la modalità d'uso è inverno o estate. 6) Procedimento secondo la rivendicazione precedente, che si caratterizza per il fatto che - se detta parte di potenza disponibile (PassPC) è sufficiente ad alimentare detta pompa di calore (15), se si rileva di essere in una fascia oraria di costo ridotto, e se una delle temperature (Ta, Tb) rilevate nei serbatoi primo (13) e secondo (14) è minore alla corrispondente temperatura ideale (Tacid, Tbid), o superiore alla temperatura ideale (Tafid) nel caso in cui la pompa di calore (15) sia in modalità 'estate' e il secondo serbatoio (14) accumuli acqua fredda, allora avviare la pompa di calore per portare o detto primo serbatoio alla corrispondente temperatura ideale, o detto secondo serbatoio alla temperatura ideale . 7) Procedimento secondo le rivendicazioni precedenti, che si caratterizza per il fatto che - se vi è una parte (Pecc) della potenza prodotta dall'impianto fotovoltaico (PtotlFP) che è eccedente rispetto alla potenza assorbita (PassIE) e sufficiente ad alimentare detta pompa di calore (15), l'alimentazione di detta pompa di calore per portare o l'acqua in detto primo serbatoio alla sua temperatura ideale (Tbid), o l'acqua in detto secondo serbatoio alla temperatura massima (Tacmax) o minima (Tafmin) , avviene per cicli successivi , atti ad elevare la temperatura di un prestabilito intervallo di temperatura (Itemp) fino al raqqiunqiment o delle temperature preimpostate Tacmax, Tafmin o Tbid. 8) Procedimento secondo la rivendicazione precedente, che si caratterizza per il fatto che durante oqni ciclo, ad intervalli di tempo (ITC) prestabiliti, si verifica se vi è una parte (Pecc) della potenza prodotta dall'impianto fotovoltaico (PtotlFP) che è eccedente rispetto alla potenza assorbita (PassIE) e sufficiente ad alimentare detta pompa di calore (15), o se l'alimentazione della pompa di calore provenga dalla rete elettrica (RE), e non più dall'impianto fotovoltaico .2) Plant according to claim 1, which is characterized by the fact that said at least one alternative energy generating plant is given by a photovoltaic plant (11) with inverter (12). 3) System according to the preceding claims, characterized by the fact that it comprises a multimeter (20), or other similar and equivalent device, at the connection points between the photovoltaic system and the electricity grid to check whether the photovoltaic system is giving up power to the electricity grid or if the building (E) is absorbing energy from the electricity grid (RE), or if the power absorbed by the optimization plant (10) itself comes from the electricity grid. 4) Plant according to the preceding claims, which is characterized by the fact that the components of the plant connected to said electronic control and management unit (19) communicate by means of Modbus RTU protocol, or other similar and equivalent protocol. 5) Process for the use of a plant for the optimization of the exploitation of the electrical energy available to a building, according to one or more of the preceding claims, characterized in that it comprises the following operations: - set the following temperature values for the heat pump (15) in the electronic control unit (19) - ideal hot water temperature (Tacid) accumulated in the second tank (14) for conditioning - minimum temperature (TaCmin) hot water storage for conditioning in the second tank - maximum temperature (Tacmx) hot water storage for conditioning in the second tank - ideal cold water temperature (Tafid) accumulated in the second tank for conditioning - minimum temperature (Tafmin) cold water storage for conditioning in the second tank - maximum temperature (Tafmax) cold water storage for conditioning in the second tank - ideal domestic hot water storage temperature (Tbid) in said first tank (13) - minimum domestic hot water storage temperature (Tbmin) in the first tank (13) - maximum domestic hot water storage temperature (Tbmax) in the first tank, - set the time bands for electricity supply from the electricity network (RE) at a lower rate - set the operating mode for the heat pump (15), summer mode for the production of cold water or winter mode for the production of hot water , - measure the ambient temperature (Te), - measure the water temperature (Tb) in the first tank (13) for domestic hot water - measure the water temperature (Ta) in the second water tank for the heating / cooling system - detect the power produced by the photovoltaic system (PtotlFV), - check if the electrical system (IE) is absorbing power (PassIE) from the electricity grid (RE), or if a part (Pecc) of the power produced by the photovoltaic system (PtotlFV) is in excess of the power absorbed (PassIE) by the '' electrical system of the building, - if the electrical system (IE) is absorbing power from the electrical network (PassIE), check whether compared to the contractual absorbable power (Pass.cont) there is sufficient power available to power the heat pump (PassPC) - if the available power part (PassPC) is sufficient to power said heat pump (15), if it is found to be in a time band of high cost, and if one of the temperatures (Ta, Tb) detected in the first tanks ( 13) and second (14) is lower than the corresponding minimum temperature (Tacmin, Tbmin), or higher than the maximum temperature (Tafmax) if the heat pump (15) is in 'summer' mode and the second tank (14 ) accumulate cold water, then start the heat pump to bring either said first tank to the corresponding minimum temperature, or said second tank to the minimum temperature, in winter mode, or maximum in summer mode, - if a part (Pecc) of the power produced by the photovoltaic system (PtotlFV) exceeds the power absorbed (PassIE) by the electrical system of the building, and if this excess power (Pecc) is sufficient to power said heat pump (15), then the heat pump is fed to bring either the water in said first tank to its ideal temperature (Tbid), or the water in said second tank at the maximum (Tacmax) or minimum (Tafmin) temperature, to depending on whether the mode of use is winter or summer. 6) Process according to the preceding claim, which is characterized in that - if said part of available power (PassPC) is sufficient to power said heat pump (15), if it is found to be in a time band of reduced cost, and if one of the temperatures (Ta, Tb) detected in the first (13) and second (14) tanks is lower than the corresponding ideal temperature (Tacid, Tbid), or higher than the ideal temperature (Tafid) if the heat pump (15) both in 'summer' mode and the second tank (14) stores cold water, then start the heat pump to bring either said first tank to the corresponding ideal temperature, or said second tank to the ideal temperature. 7) Process according to the preceding claims, which is characterized by the fact that - if there is a part (Pecc) of the power produced by the photovoltaic system (PtotlFP) which is in excess of the absorbed power (PassIE) and sufficient to power said pump (15), the supply of said heat pump to bring either the water in said first tank to its ideal temperature (Tbid), or the water in said second tank at the maximum (Tacmax) or minimum (Tafmin) temperature ), takes place in successive cycles, designed to raise the temperature by a predetermined temperature interval (Itemp) up to the raqqiunqiment or the preset temperatures Tacmax, Tafmin or Tbid. 8) Process according to the preceding claim, which is characterized by the fact that during each cycle, at predetermined time intervals (ITC), it is checked whether there is a part (Pecc) of the power produced by the photovoltaic system (PtotlFP) which is exceeding the absorbed power (PassIE) and sufficient to power said heat pump (15), or if the heat pump power supply comes from the electrical network (RE), and no longer from the photovoltaic system.
IT000146A 2012-05-09 2012-05-09 PLANT FOR THE OPTIMIZATION OF THE EXPLOITATION OF ELECTRIC ENERGY AVAILABLE TO A BUILDING, AND PROCEDURE FOR THE USE OF SUCH SYSTEM. ITPD20120146A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
IT000146A ITPD20120146A1 (en) 2012-05-09 2012-05-09 PLANT FOR THE OPTIMIZATION OF THE EXPLOITATION OF ELECTRIC ENERGY AVAILABLE TO A BUILDING, AND PROCEDURE FOR THE USE OF SUCH SYSTEM.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
IT000146A ITPD20120146A1 (en) 2012-05-09 2012-05-09 PLANT FOR THE OPTIMIZATION OF THE EXPLOITATION OF ELECTRIC ENERGY AVAILABLE TO A BUILDING, AND PROCEDURE FOR THE USE OF SUCH SYSTEM.

Publications (1)

Publication Number Publication Date
ITPD20120146A1 true ITPD20120146A1 (en) 2013-11-10

Family

ID=46466714

Family Applications (1)

Application Number Title Priority Date Filing Date
IT000146A ITPD20120146A1 (en) 2012-05-09 2012-05-09 PLANT FOR THE OPTIMIZATION OF THE EXPLOITATION OF ELECTRIC ENERGY AVAILABLE TO A BUILDING, AND PROCEDURE FOR THE USE OF SUCH SYSTEM.

Country Status (1)

Country Link
IT (1) ITPD20120146A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022168044A1 (en) * 2021-02-07 2022-08-11 Octopus Energy Group Limited Methods and systems for modulating energy usage

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10048035A1 (en) * 2000-09-26 2002-05-08 Zenit Energietechnik Gmbh Use of solar energy for building heating, lighting and power, employs combined solar heat and solar cell modules, with heat pump and earth storage system
EP1450110A2 (en) * 2003-02-20 2004-08-25 Denso Corporation Hot water supply system with storing tank
EP2141419A1 (en) * 2008-07-04 2010-01-06 Roth Werke GmbH Building heating and/or cooling device
EP2249090A2 (en) * 2009-05-06 2010-11-10 Costruzioni Solari S.R.L. Thermal system
EP2442424A1 (en) * 2009-06-11 2012-04-18 Panasonic Corporation Utility interconnection system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10048035A1 (en) * 2000-09-26 2002-05-08 Zenit Energietechnik Gmbh Use of solar energy for building heating, lighting and power, employs combined solar heat and solar cell modules, with heat pump and earth storage system
EP1450110A2 (en) * 2003-02-20 2004-08-25 Denso Corporation Hot water supply system with storing tank
EP2141419A1 (en) * 2008-07-04 2010-01-06 Roth Werke GmbH Building heating and/or cooling device
EP2249090A2 (en) * 2009-05-06 2010-11-10 Costruzioni Solari S.R.L. Thermal system
EP2442424A1 (en) * 2009-06-11 2012-04-18 Panasonic Corporation Utility interconnection system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022168044A1 (en) * 2021-02-07 2022-08-11 Octopus Energy Group Limited Methods and systems for modulating energy usage

Similar Documents

Publication Publication Date Title
US8141791B2 (en) Energy management improvement for a heating system with reduced setpoint temperature during no occupancy based upon historical sampling of room thermal response with highest power heat applied
JP2013198197A (en) Output stabilization system
JP2011083086A (en) Electric power distribution system
US10054319B2 (en) System for producing hot water
BR112013019784A2 (en) system and method for estimating and providing reserve energy capacity for dispatchable operation through the use of active load management
US9927131B2 (en) Electric water heater systems for power grids with distributed generation
JP7013812B2 (en) Hot water storage type hot water supply device
JP5143209B2 (en) Middle water use management system
JP2012060878A (en) Apparatus and method for controlling power
GB201210104D0 (en) Controlling the heating of rooms
Puchegger Electric load behaviour and DSM potential of office buildings
KR20130031515A (en) A control method for the regulating energy and system for that
JP2017089970A (en) Electrically-driven water heater and boiling-up method
Niederhäuser et al. Novel approach for heating/cooling systems for buildings based on photovoltaic-heat pump: concept and evaluation
JP6719669B2 (en) Control device, power management system, device control method and program
ITPD20120146A1 (en) PLANT FOR THE OPTIMIZATION OF THE EXPLOITATION OF ELECTRIC ENERGY AVAILABLE TO A BUILDING, AND PROCEDURE FOR THE USE OF SUCH SYSTEM.
JP6657004B2 (en) Power management apparatus and control method thereof
CN111656098B (en) Method for improved utilization of an energy grid
US9879867B2 (en) Hot water supply system
Chandla Ellis et al. An IoT based system for improving the solar water heater
CN104808712A (en) Multi-power ground heating system
KR200447172Y1 (en) Power management system by indoor / outdoor temperature / humidity difference
JP2008000113A (en) Water supply quantity controlling system of self power feeding type
JP7267149B2 (en) Control device, hot water system, hot water heater control method and program
DE102012017631A1 (en) Method for controlling power consumption network, involves controlling loads, and executing prioritization and component-regulating algorithms for maintaining target-criterion of power balance of network in different operating conditions