GB2563424A - Soil treatment - Google Patents

Soil treatment Download PDF

Info

Publication number
GB2563424A
GB2563424A GB1709532.4A GB201709532A GB2563424A GB 2563424 A GB2563424 A GB 2563424A GB 201709532 A GB201709532 A GB 201709532A GB 2563424 A GB2563424 A GB 2563424A
Authority
GB
United Kingdom
Prior art keywords
soil
stabiliser
treatment
foundation
ionic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
GB1709532.4A
Other versions
GB201709532D0 (en
Inventor
Mark Davies Richard
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to GB1709532.4A priority Critical patent/GB2563424A/en
Publication of GB201709532D0 publication Critical patent/GB201709532D0/en
Priority to AU2018204136A priority patent/AU2018204136A1/en
Priority to GB1809694.1A priority patent/GB2565414A/en
Priority to US16/008,943 priority patent/US20180363265A1/en
Publication of GB2563424A publication Critical patent/GB2563424A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • CCHEMISTRY; METALLURGY
    • C09DYES; PAINTS; POLISHES; NATURAL RESINS; ADHESIVES; COMPOSITIONS NOT OTHERWISE PROVIDED FOR; APPLICATIONS OF MATERIALS NOT OTHERWISE PROVIDED FOR
    • C09KMATERIALS FOR MISCELLANEOUS APPLICATIONS, NOT PROVIDED FOR ELSEWHERE
    • C09K17/00Soil-conditioning materials or soil-stabilising materials
    • C09K17/14Soil-conditioning materials or soil-stabilising materials containing organic compounds only
    • CCHEMISTRY; METALLURGY
    • C09DYES; PAINTS; POLISHES; NATURAL RESINS; ADHESIVES; COMPOSITIONS NOT OTHERWISE PROVIDED FOR; APPLICATIONS OF MATERIALS NOT OTHERWISE PROVIDED FOR
    • C09KMATERIALS FOR MISCELLANEOUS APPLICATIONS, NOT PROVIDED FOR ELSEWHERE
    • C09K17/00Soil-conditioning materials or soil-stabilising materials
    • C09K17/40Soil-conditioning materials or soil-stabilising materials containing mixtures of inorganic and organic compounds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • E02D3/123Consolidating by placing solidifying or pore-filling substances in the soil and compacting the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0006Plastics
    • E02D2300/0014PU
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0051Including fibers

Abstract

A method of treatment of foundation soil beneath a structure, comprising treating the foundation soil with an ionic treatment agent (ionic stabiliser), and treating the foundation soil with a soil stabiliser (e.g. polyurethane, acrylic, silicate, urea) to stabilize the foundation soil. The respective treatments may be carried out sequentially or simultaneously and may be injected into the foundation soil.

Description

Soil treatment
The invention relates to a method of treatment of foundation soil beneath a structure.
Structures such as buildings and areas of fiat concrete are prone to movement if buiit on reactive soil. Changes in moisture content cause these soils to swell or shrink. An increase in moisture causes the soil to swell (increase in volume) and a reduction in moisture causes the soil to shrink (decrease in volume).
If a structure that is built on reactive soil is not heavy enough to resist the forces of swelling, or its footings do not extend down to a moisture stable stratum of soil, it will be lifted/moved through a process known as clay heave. Similarly, shrinkage of the foundation soil will result in the structure being unsupported and potentially dropping. Causes of change in moisture content may be cyclical (seasonal temperature and precipitation), the result of an event (leaking pipework or flooding),, or, a change in long term equilibrium (e.g., growing/removal of trees, new construction that affects water catchment, or variance between moisture content immediately pre-construction and the established long term equilibrium).
As the extent of shrink/swell is unlikely to be uniform across a foundation it causes differential movement that damages the structure above.
Regarding cyclical changes, because reactive soils swell with equal pressure in all directions but tend to only shrink vertically, cyclical changes commonly result in a long term reduction in foundation soil volume as the soil moves laterally with each cycle. The lateral movement occurs because the weight of the footing and vertical outer face of the footing offer resistance to the swell and provide a more stable mass off which to push. The path of least resistance and the predominant direction of swell is therefore lateral. Similarly, clays on grade/slopes tend to move laterally in the direction of fall. The movement cycle causes damage to the structure that is greater than would be expected if the structure had moved just once to a new level (e.g., through settlement or subsidence).
Long term reduction in equilibrium moisture content is typically associated with tree growth or the result of the soil’s pre-construction moisture content being particularly high, for example because the foundations were excavated and the footings poured during a wet period. Over time the foundation soil will reduce in moisture content and volume, i.e. shrink. The structure above will lose support and drop. In addition to such a tong term effect on the structure, cyclical changes in
-2moisture content may still occur. If shrinkage is caused by tree growth, removal of trees in future will cause the soil to rehydrate and regain some, or all, of its original volume.
In many parts of the world, subsidence caused by foundation soil shrinkage 5 is a major problem, requiring remedial action which can be extensive and expensive.
Various remedial systems involve the use of a stabiliser to stabilise the soil.
One such system involves the injection of a stabiliser comprising a fast reacting two component polyurethane into the soil underneath a structure. The 10 system is designed to increase the volume of settled and subsided soil and can also be used to lift structures that have dropped as a result of the change to the soil. Once injected, the polyurethane rapidly expands with great force. The force of the expansion consolidates the soil and causes the structure above to be lifted.
The first system works well in non-cohesive soil where the polyurethane can 15 expand uniformly through the soil and the soil above is more easily compressible (i.e., the soil can be compacted, and water expelled, at a pressure lower than that required to effect lift), in cohesive (less permeable) soil, however, the polyurethane tends to expand only through existing cracks and fissures in the soil. As a result of this confinement, the cell structure of the polyurethane may be damaged and 20 weakened, although generally the strength of the polyurethane is sufficient to support most structures.
The soil is usually injected through tubes at a depth leaving an untreated portion of soil above the injected portion and below the base of the structure. In reactive soils, the system generally relies on vertical cracks remaining in the 25 untreated portion which will provide pressure relief to accommodate future swelling
i.e. the soil will swell to fill these cracks rather than over lift the structure. However, we have realised that although vertical cracks may frequently be evident at the surface they may not be present below the structure and consequently continued movement can be expected with this system. Moreover, if the soil is already in a 30 swoilen state at the time of injection, future shrinkage is probable.
A second remedial system for dealing with shrinkage of reactive soil involves two stages, using two types of soil stabiliser. Cracks in the upper levels of the clay soil are first injected at low pressure with a non-foaming polymer, which is intended to fill the cracks and prevent future swell potential by limiting the ability of 35 water to enter the soil. Second, a slow foaming polymer is injected into the soil
-3beneath the crack filled section at high pressure through tubes. The structure is lifted by the high injection pressures. As with the first system, if the soil is in a swollen state at the time of injection, future shrinkage is probable.
However, by filling cracks in the upper levels of the soil, the system actually confines the swelling process and increases the potential for future over lift. If the clay cannot expand into these cracks then upward pressure will increase. The suppliers of this system therefore emphasise the importance of controlling the moisture content of the soil after the system is installed.
A third system for dealing with soil shrinkage, known as slab jacking, involves the use of a stabiliser in the form of a fast expanding two component polyurethane (as used by the first system described above) which is injected directly beneath the concrete footing/siab. The expanding foam takes the path of least resistance, initially filling voids, then filling cracks and consolidating weak soil until the expansive pressure is sufficient to lift the structure.
The system is effective at consolidating weak soils directly below the slab or footing and providing lift but will not prevent future shrink/swell, particularly of the soil below the treated region, because the stabiliser has limited downward penetration.
In one aspect, the invention provides a method of treatment of foundation soil beneath a structure, comprising treating the foundation soil with an ionic treatment agent, and treating the foundation soil with a soil stabiliser to stabilise the foundation soil.
The method can advantageously be used for the treatment of the foundation soil beneath any existing (i.e. already built) structure that is founded on, or set within, reactive (typically clay) soils. Examples include:
- buildings, whether dwellings or commercial or industrial or civil
- culverts
- sewers, pipes and manholes
- junction and service boxes
- paths & roads
- silos
- equipment & tank baseplates or plinths
- retaining walls (below and preferably also behind them, providing excellent resistance to lateral pressures.
The ionic treatment agent can serve to limit, or remove, the capacity of the foundation soil to shrink or swell. Ionic treatment agents, also referred to as ionic stabilisers, are known. They use cation exchange to alter the shrink/swell property of the soil. The effect is usually permanent. Ionic stabilisation is used pre5 construction on roads, flat areas of concrete, and buildings. In these applications it is sprayed and mixed into the foundation soii and then compacted. In remedial applications it has only been used to a limited extent, to alleviate swell and to relax existing heaving. Once treated the soil no longer attracts and holds onto moisture, becoming free draining as well as compressible/compactable at lower pressure.
Treated soils are therefore prevented from lifting further and will relax, often dropping as the weight of a structure above compresses and compacts the soil.
Examples of ionic treatment agents are “AGSS-ICS” (Ionic Ciay Stabiliser as supplied by Advanced Geotechnical Soil Stabilization), “Condor SS” as supplied by Earth Science Products, and “EcSS 3000” as supplied by ESSL Environmental Soil 15 Stabilization.
The treatment with the ionic treatment agent and the soil stabiliser may be carried out on different portions of the foundation soil (as discussed further below), or may be carried out on the same portion of the foundation soil.
The soil stabiliser may stabilise the soil by increasing its strength. The soil stabiliser may stabilise the soil by increasing its compressive strength. The soil stabiliser may stabilise the soil by increasing its weight bearing capacity.
The soil stabiliser may stabilise the soil by increasing its shear strength.
The soil stabiliser may bind with soil particles to create a cohesive mass.
The soil stabiliser may swell during curing.
The soil stabiliser may be hydrophobic, or it may be hydrophilic.
The soil stabiliser may expand to compact and compress the foundation soil, expelling and displacing water as it does so.
The soil stabiliser may occupy at least some pore spaces in the soil. Such pore spaces may include interstitial spaces between soil particles, and/or cracks in 30 the soil, and/or fissures in the soil. In embodiments where the ionic treatment agent and the soii stabiliser are applied to the same portion of the foundation soil, the soil stabiliser may occupy the volume in the soii previously occupied by water and then vacated as the soil becomes free draining as a result of treatment with the ionic treatment agent. Thus, the soil stabiliser may displace the water. Depending on the sizes and spatial distribution of the soil particles and the pore spaces, the travel
-5of the soil stabiliser may be limited to filling cracks, fissures, and interconnected voids with a throat size which permits entry of the stabiliser, as determined by the viscosity, injection pressure, and cure time of the stabiliser.
The soil stabiliser may form a solid or a gel in the foundation soil and thereby stabilise it. In practice, the solid or gel may be injected as a low viscosity resin, aqueous solution, or be a suspension in water, and will spread through pores in the foundation soil. The solid or gel may at least partially occupy interstitial spaces between soil particles.
The soil stabiliser may comprise a material which expands in the foundation soil. For example the stabiliser may comprise two components which react to create foam, or may comprise a material which reacts with water and/or with minerals in the soil to create foam. The expansion may lift the structure above the foundation soil or it may be more modest and only occupy pores in the soil without causing lift.
The plural component example usually expands with great force. Adjacent soil is displaced and compacted by the expansive force and the soil above, being confined by the weight of the structure, is compacted. A single component example generally has a week expansive force and will self-inject through the surrounding soil as it expands.
The soil stabiliser may comprise a non-expanding material· Such a material may be a single or plural component material.
The soil stabiliser may comprise a soil stabilising polymer.
The soil stabiliser may comprise polyurethane.
The polyurethane may be a plural component polyurethane which foams and provides lift through chemical reaction between the components. Examples are Tam Geotek HS as supplied by Normet Singapore Pte Ltd, Cormix’s “Contite” range of plural component polyurethanes, and Puri SJ-64” and “Puri SJ-90” as supplied by Liquimix Australia. These plural component polyurethanes each form a rigid foam.
The polyurethane may be a single component polyurethane which foams by reacting with water and/or minerals in the soil. Such a product may not provide lift. An example is Tam Geotek LV as supplied by Normet Singapore Pte Ltd. This reacts when it comes into contact with water, forming a rigid foam.
The polyurethane may be a non-foaming polyurethane. This may be a plural component product. An example of a non-foaming polyurethane is TamPur
-6116 as supplied by Normet Singapore Pte Ltd. This is a two component product which sets to form a semi-flexible solid.
The soil stabiliser may comprise a colloidal silica. An example is Tam Geo Tek CS as supplied by Normet Singapore Pte Ltd. This is a single component material, which when set forms a gel.
The soil stabiliser may comprise an acrylic (acrylate). The acrylate stabiliser may be soluble. Examples of acrylate stabilisers are Tam Geo Tek AC as supplied by Normet Singapore Pte Ltd, and “lniectPro-PM3811 -SoilStabiliser” as supplied by Aquafin. These are acrylic grouts, which when set form a resilient gel.
The soil stabiliser may comprise a cementitious material.
The soil stabiliser may comprise a microfine cement. An example is Tam Geo Tek MFC as supplied by Normet Singapore Pte Ltd. This sets into a solid form.
The soil stabiliser may comprise silica (silicate). The silicate stabiliser may be soluble. An example of a silicate stabiliser is Tam Geo Tek SS as supplied by Normet Singapore Pte Ltd. This is a sodium silicate, which sets into a solid form. Another example is Tam Geo Tek CS, which is a colloidal silicate, as supplied by Normet Singapore Pte Ltd. This is a single component material, which when set forms a gel.
The soil stabiliser may comprise an organic monomer.
The soil stabiliser may comprise a vinyl acetate.
The soil stabiliser may comprise a urea.
The soil stabiliser may comprise an epoxy.
At least in the preferred methods of the invention, the soil stabiliser comprises grouts, which may be cementitious grouts, or chemical grouts or polymer grouts.
The characteristics of the soil stabilisers of the embodiments of the invention in terms of the interaction of the soil stabilisers with the foundation soil may be summarised as follows:
1. Non-expanding soil stabilisers are typically low viscosity and are generally pumped at low pressure. The stabilisers move into the available pore spaces without pushing the particles about too much.
2. Single component polyurethane soil stabilisers react with water in the soil to create a foam. The expansion force of the foam is quite weak, but sufficient that the foam self-injects into the soil. There is some movement of particles within the soil.
3. Plural component polyurethanes create a foam ball within the soil, creating high expansive forces which move and compacted the surrounding soil. The foam remains localised and is not intended to fill in situ pore spaces.
The soil may be treated with the ionic treatment agent and the soil stabiliser at the same time. Thus the ionic treatment agent and the soil stabiliser may be simultaneously discharged into the foundation soil, as a single “shot”. The ionic treatment agent and the soil stabiliser may be mixed together before being discharged into the foundation soil. Simultaneous application of the two treatment components may be helpful in providing an efficient and quick method of treatment of the foundation soil.
However, it will often be convenient to carry out the treatment steps sequentially. This may then allow the same injection tubes to be used for each treatment step. The treatment steps may be commenced within 6 months or 4 months or 2 months or 1 month of each other, if for example the foundation soil is swollen, it may be beneficial to treat it with the ionic treatment agent and then allow time for shrinkage before carrying out the treatment with the soil stabiliser. The treatment steps may be commenced within 30 days of each other, such as within days, 7 days, or 5 or 4 or 3 or 2 days. The treatments may be commenced on the same day.
The treatment with the soil stabiliser may be carried out before the treatment with the ionic treatment agent. In most cases, however, the treatment with the ionic 25 treatment agent will be carried out before the treatment with the soil stabiliser. This is particularly effective if the same portion of the foundation soil is subjected to the two treatments. The portion of the foundation soil may effectively be conditioned by the ionic treatment agent, ready for treatment with the soil stabiliser.
The method may comprise injecting the ionic treatment agent into the foundation soil and injecting the soil stabiliser into the foundation soil.
Tubes may be used to inject the ionic treatment agent and the soil stabiliser into the foundation soil. The same tubes may be used for both injections. Such a method is ποη-disruptive, In that both materials are installed through the same tubes.
-8At least some of the tubes may be left in place after the respective treatments have been carried out. This could provide sheer strengthening of the soil, in addition to that which may be provided by the treatment 'with the soil stabiliser.
Foundation soil is considered to extend both beneath a structure and outwardly at an angle from the perimeter of the structure, referred to as the angle of repose. The method involves treatment of at least the foundation soil beneath the structure, and may additionally involve treatment of the foundation soil situated outwardly of the perimeter of the structure.
The foundation soil extends in a depth direction beneath the structure. In some methods the treatment with an ionic treatment agent may be carried out on a first portion of the soil above a second portion of the soil, and the treatment with soil stabiliser may be carried out on the second portion. The first portion would then have a reduced shrink/swell capacity and it may not be necessary to treat the first portion with the soil stabiliser. If an expanding soil stabiliser is used, the first portion and the structure above would be lifted by expansion of the second portion. For exampie, the upward force of a strongly expanding plural component polyurethane would compress and compact the first portion that has only been treated with the ionic treatment agent.
It is expected however that in most cases, in particular where lift is not required, both the ionic treatment agent and the soil stabiliser would be carried out on the same portion of the foundation soil. This would allow the use of the same treatment equipment to be used for both operations, for example the same injection tubes and the connectors to those tubes.
By combining treatment of the foundation soil with an ionic treatment agent and with a soil stabiliser, it is possible effectively to remediate shrinkage of the foundation soil, whether existing or potential. There is a benefit not just for structures which have subsided, but the treated foundation soil will also no longer be subject to swelling in the case of increasing moisture content. Therefore if surrounding conditions are changed in a way which would increase moisture content, such as with tree removal, heaving of the structure can be mitigated.
The treatment may be used to bring a structure back to a level condition. The treatment may be used to lock in the foundation soil, i.e. to avoid the long-term reduction in foundation soil volume as the soil moves laterally with each wetting and drying cycle.
-9The major direction of shrinkage under a structure is downwards rather than lateral, hence there can be a problem with soil swell beneath an adjacent structure such as a path. The footing of a structure such as a building may prevent swell beneath and in the direction of the footing and consequently increase its impact on 5 a path. These paths are commonly caused to lift at the edge furthest from the building and as a result water starts to run off towards the building, where it is channelled through a newly developed gap between the path and the building. The extent of swell outwardly adjacent to the footing, owing to moisture changes, therefore increases with each cycle and the extent of shrink diminishes. Thus by using the treatment to reduce or avoid long-term reduction in foundation soil volume beneath a first structure, such as a building, the problem of swelling beneath an adjacent second structure, such as a path, may be mitigated. In this example, application of the ionic treatment agent beneath the path and outward of its perimeter would also be beneficial.
The use of the ionic treatment agent can create a homogeneous and porous, i.e. free draining, soil, which can then be stabilised by the soil stabiliser.
When the method is carried out along the length of a footing, changes in the moisture level of the soil below the structure inwardly of the footing can be minimised. The treated soil below the footing can effectively create a curtain which protects the soil inwardly thereof against moisture ingress or egress.
The treatment with the ionic treatment agent may be carried out directly under a central region of a slab of the structure. This can be of assistance where the foundation soil has heaved. Differential moisture content between the soil beneath the slab and the surrounding area promotes the suction of water towards 25 equilibrium, causing the slab itself to “dome” or “dish. If this problem is not addressed in its early stages and soil beneath the slab heaves, then usually the only repair option is to remove and replace the entire floor slab. Installation of the ionic treatment agent directly under the central region of the slab can alleviate an existing heave problem.
The method may further comprise treating soil around a perimeter of the structure with the ionic treatment agent. This would be done in addition to treating the soil beneath the structure with the ionic treatment agent. The soil may be treated around the perimeter of the structure with the ionic treatment agent over a region extending up to 1 rn or 2 rn or 3 m from the structure. By treating soil around the perimeter of the structure, suction by the soil in this region of moisture away
- 10from the soil under the structure, and conversely, suction by the soil under the structure of moisture away from this region, is avoided, helping to ensure that the soil beneath the structure is further protected from the effect of moisture changes. Since the moisture content of the soil beneath a structure usually changes in response to moisture changes in the soil around its perimeter (because the structure itself prevents rainfall onto the soil beneath it), treatment of the soil around the perimeter of the structure with the ionic treatment agent can provide a major benefit.
In the above method, a soil stabiliser which is impervious to water may be 10 used beneath the structure, inwardly of its periphery, such as beneath a footing.
There is then a double barrier to water ingress to, and egress from, the region beneath the structure, comprising the soil in the perimeter region which provides good drainage due to its treatment with the ionic treatment agent, and the soil beneath the structure treated so as to become a curtain impervious to water.
Because the ionic stabiliser changes the characteristics of the soil, it can also allow for the soil stabiliser to move more freely through the soil, enabling the creation of a homogenous, stabilised and strengthened section of foundation soil.
After treatment, the foundation soil may have the following advantages: resistance to volume change as a result of moisture variation, being resilient to cyclical changes as well as long term equilibrium moisture content changes (both wetting and drying);
reduced reliance on surface water control and soil moisture content management (e.g., removing trees, hard standing around buildings etc.);
the creation of a homogenous foundation soil in which differential movement 25 is prevented and even footing support is provided;
increased strength;
permanent results; and measurable outcomes, in that penetrometer and reactivity testing can be carried out.
The method can be carried out as a remedial or a preventative method. The method is carried out as a remedial method if a problem already exists in the foundation soil of a structure. The method is carried out as a preventative method to avert or mitigate a problem in future.
-11 The method may be used as a preventative method to prevent movement in known problem areas or to mitigate against future moisture changes (e.g., trees being planted or cut down).
When a new structure is to be built adjacent to an existing structure, it is common that excavation causes the foundation soil of the existing structure to dry out quickly, resulting in shrinkage, cracking, and crumbling. Therefore the method may be used on an existing structure when a new structure is to be built nearby.
In one possible preventative method, the soil may first be injected with the ionic treatment agent, before being injected with either a silicate or acrylic (acrylate) 10 based stabiliser (no lift required). The best stabiliser to use will partly depend on the particle size and void factor of the existing soil and its moisture content.
In situations where there has been a long-term reduction in equilibrium moisture content, with resulting shrinkage of the foundation soil, the method may comprise treating the foundation soil by adding water. This may at least partially lift 15 the structure using the swell potential of the foundation soil, e.g. reactive clay. The water may be injected. Injection may be carried out using the same tubes as are used for the other treatments.
In situations where there has been a long-term increase in equilibrium moisture content, after treatment of the foundation soil with the ionic treatment 20 agent, the treated region may be allowed to relax, and therefore shrink, before treatment with the soli stabiliser is carried out.
In some methods, the foundation soil may be artificially dried before the treatment with the ionic treatment agent is carried out.
Thus, the method may involve managing the moisture content of the foundation soil. This can be done by the addition of water or by drying out. In the former case, the expansive force of the reactive soil is used to increase volume and provide uplift. Water can be added beneath a footing for a slab using a soaker hose or by deep injection through tubes.
In an exemplary method, a plurality of tubes may be spaced apart at approximately 500 mm to 1.5 m centres and be positioned in a row. More than one row with tubes spaced apart along the row may be employed, with the rows spaced apart by between 500 mm and 1.5 m. The row closest to the structure may pass (be drilled) through the footing of the structure and into the soil below. An area up to e.g. approximately 2rn outside the perimeter of the structure may be treated in its entirety. The depth of treatment may be up to between 1 m and 3 m, but may be
-12deeper, for example up to 5 m, depending on the structure whose foundation soil is being treated and site conditions. By the depth of treatment, it is meant the deepest point at which the treatment material is discharged into the foundation soil. Some tubes used for injection have won the directional valve outlets distributed over a length of the tube and can be sleeved or contain expandable packers, which enable control over the pressure and volume of treatment over a range of depths. The most distal outlet will be located at the deepest point of discharge.
The tube locations discussed above are applicable to treatment steps with both the ionic treatment agent and the soil stabiliser. Unless an unusually substantial water barrier is required, application of the soil stabiliser will in most cases be limited to beneath a footing of the structure and may extend to include the angle of repose. The same or different tubes may be used for the respective treatment steps.
Example
The foundation soil is treated using “AGSS-ICS” as an ionic treatment agent. Through cation exchange the ionic treatment agent removes the ability of clay particles to attract and hold on to water. The soil will now become less cohesive and this makes the soil free draining and allows the soil stabiliser to pass 20 more freely through the soil into pores between the particles.
The foundation soil is injected with the soil stabiliser. Depending on the strength requirement of the foundation and characteristics of the soil, the stabiliser may be a single component moisture activated foaming polyurethane, a plural component foaming or non-foaming polyurethane, a colloidal silica, acrylic, etc. The 25 stabiliser will create a homogenous, strong and water resistant foundation/underpin.
If additional lift is required, this can be achieved through:
1. Slab jacking - injecting plural component polyurethane foam through holes drilled directly into the footing. The foam is injected into the region above the newly stabilised foundation soil and uses it as a base on which to push. The slab jacking is used as a final step to fine tune the lift and ensure continuous support of the structure. Slab jacking can alternatively or additionally be carried out at any stage in the process (e.g., to fill voids beneath a raft footing) prior to the treatment with the ionic treatment agent or after that treatment and prior to the treatment with the soil stabilise.
- 132. Deep injection of a plural component polyurethane, in accordance with the first known remedial system discussed above. This would be installed to raise the structure.
in some embodiments, the deep injection of a plural component polyurethane may negate the need to stabilise the portion of the soil which has been treated with the ionic treatment agent. In other words, a first portion of the soil below the structure may be treated with ionic treatment agent, and then lower down, at the base level of that first portion, a second portion of the soil below the structure may be treated with the soil stabiliser.

Claims (20)

Claims
1. A method of treatment of foundation soil beneath a structure, comprising treating the foundation soil with an ionic treatment agent, and treating the
5 foundation soil with a soil stabiliser to stabilise the foundation soil.
2. A method as claimed in claim 1, wherein the respective treatments are carried out sequentially.
10
3. A method as claimed in claim 2, wherein the treatment with the ionic treatment agent is carried out before the treatment with the soil stabiliser.
4. A method as claimed in claim 2, wherein the treatment with the soil stabiliser is carried out before the treatment with the ionic treatment agent.
5. A method as claimed in claim 1, wherein the respective treatments are carried out simultaneously.
6. A method as claimed in any of claims 1 to 5, wherein the respective
20 treatments are carried out on the same portion of the foundation soil.
7. A method as claimed in any of claims 1 to 5, wherein the treatment with the ionic treatment agent is carried out on a first portion of the foundation soil above a second portion of the foundation soil, and the treatment with the soil stabiliser is
25 carried out on the second portion.
8. A method as claimed in claim 7, wherein the soil stabiliser in the second portion expands to cause compression of the first portion.
30
9. A method as claimed in claim 7, wherein the soil stabiliser is discharged into the second portion at a pressure which causes compression of the first portion.
10. A method as claimed in any preceding claim, comprising injecting the ionic treatment agent into the foundation soil and injecting the soil stabiliser into the
35 foundation soil.
11. A method as claimed in claim 10, wherein tubes are used to inject the ionic treatment agent and the soil stabiliser into the foundation soil.
5
12. A method as claimed in claim 11, wherein the same tubes are used for both injections.
13. A method as claimed in claim 11 or 12, wherein at least some of the tubes are left in place after the respective treatments have been carried out
14. A method as claimed in any preceding claim, wherein the treatment with the ionic treatment agent is carried out directly under a central region of a slab of the structure.
15 15. A method as claimed in any preceding claim, further comprising treating soil around a perimeter of the structure with the ionic treatment agent.
16. A method as claimed in any preceding claim, wherein the soil stabiliser comprises polyurethane.
17. A method as claimed in any preceding claim, wherein the soil stabiliser comprises acrylic.
18. A method as claimed in any preceding claim, wherein the soil stabiliser
25 comprises silicate.
19. A method as claimed in any preceding claim, wherein the soil stabiliser comprises a material which expands in the foundation soil.
30
20. A method as claimed in any preceding claim, wherein the soil stabiliser fills at least some pore spaces in the foundation soil.
GB1709532.4A 2017-06-15 2017-06-15 Soil treatment Withdrawn GB2563424A (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
GB1709532.4A GB2563424A (en) 2017-06-15 2017-06-15 Soil treatment
AU2018204136A AU2018204136A1 (en) 2017-06-15 2018-06-08 Soil treatment
GB1809694.1A GB2565414A (en) 2017-06-15 2018-06-13 Soil treatment
US16/008,943 US20180363265A1 (en) 2017-06-15 2018-06-14 Soil treatment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB1709532.4A GB2563424A (en) 2017-06-15 2017-06-15 Soil treatment

Publications (2)

Publication Number Publication Date
GB201709532D0 GB201709532D0 (en) 2017-08-02
GB2563424A true GB2563424A (en) 2018-12-19

Family

ID=59462326

Family Applications (2)

Application Number Title Priority Date Filing Date
GB1709532.4A Withdrawn GB2563424A (en) 2017-06-15 2017-06-15 Soil treatment
GB1809694.1A Withdrawn GB2565414A (en) 2017-06-15 2018-06-13 Soil treatment

Family Applications After (1)

Application Number Title Priority Date Filing Date
GB1809694.1A Withdrawn GB2565414A (en) 2017-06-15 2018-06-13 Soil treatment

Country Status (3)

Country Link
US (1) US20180363265A1 (en)
AU (1) AU2018204136A1 (en)
GB (2) GB2563424A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2000008114A1 (en) * 1998-07-31 2000-02-17 Ciba Specialty Chemicals Water Treatments Limited Soil treatment compositions and their use
CA2281164A1 (en) * 1999-08-27 2001-02-27 Zhihong Zhou Method for stabilizing soil using a cationic surfactant, soil stabilizing agent and stabilized soil
WO2008072964A1 (en) * 2006-12-13 2008-06-19 Stichting Deltares Soil strengthening composition
CN102676176A (en) * 2012-03-19 2012-09-19 尚路 Composite ionic soil curing agent and manufacturing method thereof
US20120288335A1 (en) * 2011-05-11 2012-11-15 Rodney Green Soil Stabilization Composition and Methods for Use

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2437387A (en) * 1945-07-11 1948-03-09 Hodgson Ronald Mortimer Process for the hardening of soil and the like
US3959975A (en) * 1970-09-25 1976-06-01 Graf Edward D Soil stabilization by ion diffusion
IT1286418B1 (en) * 1996-12-02 1998-07-08 Uretek Srl PROCEDURE TO INCREASE THE WEIGHT OF FOUNDATION LANDS FOR BUILDING CONSTRUCTIONS
IL210999A0 (en) * 2010-02-06 2011-04-28 Asher Vitner Methods for the separation of hcl from a chloride salt and compositions produced thereby
GB201213003D0 (en) * 2012-07-20 2012-09-05 Collis Simon P A ground stabilisation system and related method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2000008114A1 (en) * 1998-07-31 2000-02-17 Ciba Specialty Chemicals Water Treatments Limited Soil treatment compositions and their use
CA2281164A1 (en) * 1999-08-27 2001-02-27 Zhihong Zhou Method for stabilizing soil using a cationic surfactant, soil stabilizing agent and stabilized soil
WO2008072964A1 (en) * 2006-12-13 2008-06-19 Stichting Deltares Soil strengthening composition
US20120288335A1 (en) * 2011-05-11 2012-11-15 Rodney Green Soil Stabilization Composition and Methods for Use
CN102676176A (en) * 2012-03-19 2012-09-19 尚路 Composite ionic soil curing agent and manufacturing method thereof

Also Published As

Publication number Publication date
AU2018204136A1 (en) 2019-01-17
US20180363265A1 (en) 2018-12-20
GB201809694D0 (en) 2018-08-01
GB2565414A (en) 2019-02-13
GB201709532D0 (en) 2017-08-02

Similar Documents

Publication Publication Date Title
EP0851064B1 (en) Method for increasing the bearing capacity of foundation soils for buildings
US3626702A (en) Floating foundation and process therefor
CA2831956C (en) Method for treating soil
CA2965132C (en) Method for forming a stable foundation ground
KR101907141B1 (en) Sealing composition for umbrella arch method and process for preparing the same
CN108547336B (en) Sedimentation, reinforcement, jacking and leveling method suitable for independent pile foundation of industrial plant
AU2010246376B2 (en) Environmentally degradable void former
US4508472A (en) Method for controlling moisture-expansive clay supporting building foundations
CN104674842B (en) Solidified earth barricade and constructional method thereof
US4124982A (en) Method of stabilizing soil in pile bearing regions
GB2563424A (en) Soil treatment
JP3653305B2 (en) Restoration method for uneven settlement
WO2011021985A1 (en) Structure supporting system
RU2572477C1 (en) Method to recover contact layer "foundation - soil base"
CN107100216B (en) The unilateral basic pile foundation of monolithic wall overhangs underpinning construction method
KR100554364B1 (en) Method for increasing the bearing capacity of foundation soils for buildings
JP4927113B2 (en) Ground stabilization method
Lanka et al. Rectification of settled Foundations
Greenwood Speculations on methods of stabilizing slopes
JP2832204B2 (en) Liquefaction prevention method and liquefaction prevention structure
AU2007203032A1 (en) Void forming and suspension system for a structural concrete slab
JP2777625B2 (en) Liquefaction prevention structure
Skinner Construction on fill
US6508609B2 (en) Method of forming an in-situ void system
JP2023176278A (en) Underfloor reinforcement method and underfloor reinforcement structure