GB1592591A - Piles - Google Patents
Piles Download PDFInfo
- Publication number
- GB1592591A GB1592591A GB135477A GB135477A GB1592591A GB 1592591 A GB1592591 A GB 1592591A GB 135477 A GB135477 A GB 135477A GB 135477 A GB135477 A GB 135477A GB 1592591 A GB1592591 A GB 1592591A
- Authority
- GB
- United Kingdom
- Prior art keywords
- pile
- segments
- segment
- driving
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000000034 method Methods 0.000 claims description 30
- 238000006243 chemical reaction Methods 0.000 claims description 22
- 229910000831 Steel Inorganic materials 0.000 claims description 6
- 230000002787 reinforcement Effects 0.000 claims description 6
- 239000010959 steel Substances 0.000 claims description 6
- 238000009424 underpinning Methods 0.000 claims description 6
- 239000000463 material Substances 0.000 claims description 5
- 230000000295 complement effect Effects 0.000 claims description 4
- 239000011178 precast concrete Substances 0.000 claims description 4
- 230000003014 reinforcing effect Effects 0.000 claims description 4
- 238000003780 insertion Methods 0.000 claims description 3
- 230000037431 insertion Effects 0.000 claims description 3
- 101150116749 chuk gene Proteins 0.000 claims description 2
- 239000011440 grout Substances 0.000 claims description 2
- 230000004048 modification Effects 0.000 claims description 2
- 238000012986 modification Methods 0.000 claims description 2
- 239000002689 soil Substances 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 238000011065 in-situ storage Methods 0.000 description 3
- 239000002184 metal Substances 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 230000004323 axial length Effects 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 239000004567 concrete Substances 0.000 description 1
- 239000004794 expanded polystyrene Substances 0.000 description 1
- 239000000835 fiber Substances 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 238000005755 formation reaction Methods 0.000 description 1
- 239000002783 friction material Substances 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 230000013011 mating Effects 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 239000004810 polytetrafluoroethylene Substances 0.000 description 1
- 229920001343 polytetrafluoroethylene Polymers 0.000 description 1
- 230000000063 preceeding effect Effects 0.000 description 1
- 239000011443 resin grout Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/52—Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
- E02D5/523—Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Description
(54) IMPROVEMENTS RELATING TO PILES
(71) We, PYNFORD LIMITED, a British company, of 74 Lancaster Road, Stroud Green
London, N.4., do hereby declare the invention, for which we pray that a patent may be granted to us, and the method by which it is to be performed, to be particularly described in and by the following statement:- The invention is concerned with the driving of columnar friction piles end first into the ground.
In the driving of such piles, it is known to provide the pile in the form of a number of separate segments which are assembled end to end to form the pile. The leading segment is first thrust into the ground whereafter successive segments are successively fitted to the end of the previously driven segment or segments and in turn driven into the ground pushing the previous segments in front.
Although this has the advantage that the whole length of the pile does not have to be handled and supported when its leading end is first thrust into the ground, the reaction required becomes greater as more and more segments are fitted and pushed into the ground, owing primarily to the frictional resistance between the sides of the segments in the ground and the surrounding earth. During the driving operation, the frictional resistance steadily increases and large heavy structures are required to develop the necessary driving reaction. For example, in the case of a pile which is put down adjacent to a building to provide a new foundation for underpinning the building, the reaction necessary to thrust the pile down into the ground during the latter part of the driving operation may be three or four times the maximum safe load bearing capacity which the pile will eventually provide.Since this maximum driving reaction on the pile may be some six times as great as the dead weight of the part of the building to be supported by that pile, it is clearly impossible to develop the necessary driving reaction by taking an abutment from the part of building, unless piles are jacked in in groups, which is unpracticable and uneconomic under light buildings such as houses.
An alternative is to use heavy machinery or large quantities of kentledge and this is both laborious and expensive.
It is also known to provide a thin casing for a cast in situ pile in the form of a number of telescopic segments. The telescopically retracted segments are first pushed into the ground to the depth of the outer segment, whereafter the inner telescopic segments are successively extended into the ground from within the outer segment. Although this has the advantage that at any time the driving reaction only has to overcome the frictional resistance between the periphery of one of the casing segments and surrounding earth, it is an expensive technique involving smooth telescopic sliding between a number of accurately nested segments and in practice it is only useful for cast in situ piles and not for piles which are built up from preformed segments.
In accordance with the present invention in a method of inserting a columnar pile in the ground, the pile is formed by a plurality of segments each of which contributes only a part of the area of contact between the surface of the pile and the surrounding earth, the method being characterised in that, at least following initial stages of segment insertion, the segments at any time forming that part of the pile in the ground are advanced individually or in groups in turn a little way further into the ground and the cycle is repeated until the pile is in its fully driven position.
With this arrangement it is only ncessary to provide the maximum reaction required for advancing through the ground a single segment. As the force required to drive one segment will usually increase with depth, it may be possible to drive two or more segments simultaneously at shallower depths during the initial stages in the pile driving sequence of operation. The necessary reaction may reaaily be developed by simple jacking devices, from comparatively small and lightweight abutment adjacent at ground level, or possibly via a group of segments in the gr ound, which are not at that moment being driven, from their frictional resistance with the ground.
The driven segments are preferably arranged to form a hollow pile body which is subsequently filled with cement or resin grout, if necessary after reinforcement has been inserted, to interconnect the segments rigidly together. The pile may also be prestressed if a prestressing wire is anchored to a segment at the leading end, that is the foot, of the pile.
The pile may have any of a possible wide range of external cross sectional shapes, ranging from a simple circle, to a star or cruciform shape. The use of a non-circular external cross section not only enables differential bending resistance to be produced in different directions, but maximizes the peripheral area of frictional contact between the friction pile and the surrounding earth, for a given volume and cross sectional area of the pile. When the pile is to support an offset load, for example when put down adjacent to an underpining beam, the cross section is preferably elongate in a direction perpendicular to the length of the beam.
The pile may be divided longitudinally into a plurality of side by side segments each providing a fraction of the circumference of the pile. Thus if the cross section of the pile is circular or annular, the segments will be sector-shaped.
When the pile is divided longitudinally, it may be necessary to provide some means for keying or holding together adjacent segments so that they may slide longitudinally relatively to one another without splaying apart. Mating keying formations may be formed in the adjacent surfaces of adjacent segments or a keying member, for example of dumbell shape, may bridge between undercut grooves in the adjacent segment surfaces. Alternatively, the segments may be surrounded by a retaining band or bands. To reduce sliding friction between the non-external surfaces of the segments and the adjacent surfaces of adjacent segments, one or both of the contact ing surfaces may be coated with a low friction material such as PTFE.
Preferably, however, the pile is divided transversely to its length into a number of abutting segments arranged end to end, each contributing only a part of the length of the pile. It might be possible to divide the pile both longitudinally and transversely but this is more complex.
When the segments are arranged end to end along the pile, the segments above the leading segment will preferably be tubular and the segments are repeatedly driven a little way into the ground in cycles beginning from the leading segment at the bottom of the pile and working successively up the pile by means of driving means extending down through the tubular segments. Each cycle will advance the whole pile by the small amount by which each segment is moved and in a typical case, say, 100 cycles would be required to drive the pile fully to the working depth.
The driving means may be a reciprocating driving member which is repeatedly brought into driving engagement with successive segments. Thus the driving member may be a mandrel which is operated from above ground level and which incorporates a ratchet mechanism for repeated engagement with successive segments. Alternatively, the driving member may be a chuck which is driven up and down a guide rod extending down through the segments, the chuck being expandible into engagement with successive segments in turn.
Preferably, however, the driving means presently considered most suitable for driving 5 or 6 m, deep piles for use in underpinning houses on stiff shrinkabe clays comprises a central driving member surrounded by a number of concentric tubular driving members, the lower ends of successive ones of the driving members in the radial outward direction abutting against respective successive ones of the pile segments in the direction from the bottom of the pile upwards, and the driving members are repeatedly advanced a little way downwards working successively radially outwardly from the central driving member.
The concentric tubular driving members can themselves be made in axial segments which are added to as the pile is advanced into the ground. The driving members may be advanced successively down the pile by means of a common driving head incorporating a number of reaction members which successively act on individual cross heads connected to the upper ends of respective ones of the driving members. Alternatively the concentric driving members may have at their upper ends angularly offset axial projections and the driving head may have a radial bar which is reciprocated axially and rotated through a small angle between each working stroke so that by engagement of the bar with successive projections the members are successively driven downwards in a driving cycle. Yet a further driving means for the concentric tubes might involve a nesting set of hydraulic rams.
It is not necessary for the leading segment, and successive segments, to be advanced at each stage by a distance equal to the axial length of the segment and the segments may be advanced at each stage by a matter of only a few mm. This minimises the gap which appears between a segment being advanced at any time and the succeeding segment and hence reduces the danger of spoil entering the gap and interfering with the subsequent end to end abutting engagement of the adjacent segments when the succeeding segment is subsequently advanced. This danger may be eliminated entirely by providing each segment with a trailing skirt into which the nose of the succeeding segment fits. The segments will then only be advanced by a distance no greater than the overlap between a complementary skirt and nose.Alterntively it may be sufficient if the nose of each segment is chamfered to provide a sharp taper for pushing radially outwardly again any spoil tending to move into the gap.
If the pile is of constant cross section, the reaction required to drive the leading segment will normally be greater then that required to drive the succeeding segments, because the advancement of the leading segment has to displace soil necessary to accommodate the cross section of the element.
This end reaction, which will usually increase as the leading segment of the element is forced further into the ground, may be at least twenty times as large per unit area of bearing surface than the frictional reaction between the side of the segment and the surrounding earth. This problem can be met in a number of ways. For example the leading segment might be subjected to a vibration, for example by a pair of side by side vibratory hammers. Alternatively, the leading segment may be formed around its periphery with a cutting shoe, the spoil cut out being withdrawn to ground level through for example a rotating auger extending up a tube through the pile from the cutting tube to ground level or above.Yet again the leading segment may be formed itself into a number of side by side sections, for example a central and one or more sections alongside or surrounding the central section, which can be successively driven into the ground. The reaction required to drive any one section of the leading segment into the ground may then be comparable with that required to drive any other segment into the ground. Also, in order to reduce the friction required to drive the leading segement into the ground, and also to assist in guiding the leading segment along a straight line, A pilot hole, smaller than the cross section of the pile, may be prebored at least partway into the ground. Furthermore, the leading segment and/or successive segments may have an appreciable taper towards its leading tip.
If the external cross section of the pile is increased either gradually or in stepwise fashion from the leading segment to the upper end of the pile, the pile may be designed such that substantially the same reaction is required to drive each segment into the ground. This minimizes the cross section of the leading segment which experiences the greatest resistance to its being advanced into the ground; ensures that the upper segments of the pile are in firm frictional contact with the ground through which the preceeding segments have already passed; and thus prov idesfor the most efficient driving machine by utilising the full capacity of every segment and minimises the number of segments for a given reaction to working load ratio.
If the upper soil strata are unstable, an upper portion of the pile may be surrounded by a fluent, resilient or crushable material to isolate the top of the pile against a reaction resulting from horizontal movement of the surrounding earth. This may involve making one or more segments at the upper portion of the pile smaller in plan area than that of the uppermost load bearing segment.
The segments may be of any appropriate load bearing material. Thus the leading segment may be made of steel or reinforced concrete and the succeeding segments may be made for example of fibre and/or metal reinforced concrete. When the pile segments are made of precast concrete, each segment may have a cast-in reinforcing member against which the respective driving member engages, thereby protecting the concrete against the liability to crumble under extreme local pressure. The reinforcing member may itself be connected with metal reinforcement embedded within the concret segment.
The use of piles constructed in accordance with the invention for use in supporting an underpining beam of a building, is illustrated by way of example in the accompanying drawings, in which: Figure 1 is a diagrammatic plan of the building;
Figure 2 is a diagrammatic section taken on the line II--II in Figure 1;
Figure 3 is a diagrammatic axial sectional view showing the driving of one pile;
Figure 4 is a sectional detail showing part of the driving head of Figure 3;
Figure 5 is a diagram showing successive stages in driving the pile of Figure 3;
Figure 6 is a sectional diagram showing the driving of another pile; and
Figure 7 is a perspective diagram illustrating the driving of a further pile.
Figures 1 and 2 show the walls 10 of a building which is underpinned. A "Pynford" (Registered Trade Mark) beam 11 is provided in the plane of each wall 10 adjacent to the bottom of the wall. The Pynford beam is constructed by cutting a horizontal slot along and through the wall, pinning the wall above up at intervals by means of stools, inserting reinforcement, and casting an in situ beam encapsulating the reinforcement and stools.
The old foundations for the walls 10 are shown at 12.
The weight of the building is carreid through the Pynford beams 11 down to new foundations provided by piles 13 of square or rectangular section.
Each pile may be put down utilizing a support structure 14 which is erected on a stiff horizontal member 15 one end of which is located beneath the Pynford beam 11 and the other end is held down to the ground by means of a ground anchor 16. The support 14 acts as a guide for the pile segments before they are pushed down into the ground 17, as a support for a driving head for the pile segments, and for transmitting the driving reaction to the pile segments from a winch 18.
As shown in Figures 2 and 3, the pile is made up from a number of segments 19A, 19B and 19C. In Figure 2 for simplicity of illustration, the pile segments 19 are shown with a smaller length to width ratio than they would have in practice and the segments l9B shown in Figure 3 are more realistically proportioned. However, as shown in Figure 2, the segments taper towards the bottom of the pile. The segments 19C at the top of the pile are narrower than the segments 19B and are surrounded by a crushable material 2, such as expanded polystyrene, which also extends under the beam 11, to isolate the building from possibly unstable upper strata of earth which might move.
The leading segment 19A may be a precast concrete element, or a steel element.
As shown particularly in Figure 3, each segment 19B is a tubular precast concrete element having a central passageway 21. The diameter of the central passageway of each segment is approximatley 15 mm. less in diameter than that of the segment above. At its trailing end each segment has integrally cast a trailing skirt 22 which receives the nose of the segment above. Internally each segment has a cast-in steel ring 23 the upper edge of which projects as an abutment shoulder into the passageway 21, for use in driving the segment. Each ring 23 is also rigid with a ring
of splayed reinforcing legs 24 which are useful for sprcading the load into the segment.
The segments 19C are constructed similarly to the segments 19B except that their external cross section is reduced to accommodate the
material 20.
In a typical underpinning pile of the kind illustrated, for use in clay soil, it is envisaged
that the pile might be up to 5 m. long, and
there would be up to 10 segments each up to
500 mm. long. The width or breadth of the
leading segment 19A of a pile of square or
rectangular cross section might be about 75
mm., and the width and breadth of the widest
segment 19B of a pile of rectangular cross
section might be of the order of 250 mm. and
400 mm. respectively.
Before putting down the pile, a narrower
pilot hole may be drilled partway into the
ground. First of all the segment 19A is
pushed a little way into the ground, and the
first segment l9B is pushed after it until it
abuts the first segment. The leading segment
19A is then advanced a few say 50 mm. further
into the ground and the second segment is
closed up behind it again. This is repeated until there is room for the second segment l9B to be inserted into the ground and the three segments then in the ground are repeatedly advanced little by little. The cycle is repeated until all the segments are in the ground.
Each segment is only advanced by an amount to close up the gap between itself and the preceding segment and to open up a gap ahead of the succeeding segment. Such a gap 25 is illustrted in Figure 3 and it will be seen that this gap is less than the length of the trailing skirt 22 so that the gap is always shielded from the surrounding soil.
A suitable means for driving the segments successively and repetitively into the ground is illustrated in Figures 3 and 4. The driving means comprises a number of concentric steel tubes 26, with a wall thickness of about 6 mm., which slide closely within one another and within the tubular passageways 21. The lower end of each tube 26 abuts against a respective one of the rings 23. The tubes 26 may themselves be formed in a number of end to end segments which abut against one another, the junctions between adjacent segments in adjacent tubes being axially offset from one another. The upper ends of the tubes 26 are connected to a pile head 27 having upper and lower members 28 which are vertically slidable in channels 29 forming part of the support 14.The sides of the head 27 themselves form guides for a series of cross heads 30 which are in vertical alignment and are movable upwards and downwards relatively to one another. The upper end of the largest one of the tubes 26 is connected to the lower member 28. The next smaller diameter tube 26 passes through the member 28 and is connected to the lowest cross head 30A. The tube 26 with the next smallest diameter passes up through the lower member 28, the cross head 30A, and is connected to the cross head 30B, and so on.
The lower member 28 and each of the cross heads 30 has extending upwards from it a pair of sliding rods 31. These rods slide through holes in all the cross heads 30 above and terminate adjacent to a driving head 32. This driving head 32 is also slidable in the channels 29 and incorporates a number of horizontal bars 33, one for each rod 31. Each of the bars 33 is pivotally mounted on the driving head 32 and can be held in its horizontal position by a respective pawl 34 operated by a fluid cylinder 35.
At the beginning of a driving cycle, the rods 31 are staggered as shown in Figure 3 and Figure 5a. The central tube 26 has to be forced downwards first and this is achieved by operating the winch 18 so that, through cables
36 the driving head 32 is pulled downwards and the two central bars 33 force the two central rods 31, and hence the top cross head
30E downwards by about 50 mm. This movement is transmitted through the central rod to the leading pile segment 19A. The cylinders 35 for the two central bars 33 are then operated to release the bars so that they can swing upwards. The winch 18 is again operated to pull the driving head down through a further distance so that the next two bars 33 engage the next two rods 31 and force the cross head 30D and the corresponding tube 26 downwards to advance the first segment 19B downwards again by about 50 mm.This is repeated as shown in sequence in Figure 5 whereafter the driving head 32 is raised again by means of cables 37 connected to another winch and the bars 33 relatched in their driving positions. The cycle is then repeated over and over again.
When a new segment or sections of the tube are to be inserted, the pile head 27 is raised by operation of a further winch acting through a cable 38.
When the pile has been fully driven into the ground, the pile head is removed together with the tubes 26. Reinforcement 39 is inserted down the hollow core of the pile formed by the passageways 21, and the core is grouted up, the pile core being united with the beams 10 in conventional fashion. As suggested in Figure 2, the reinforcment 39 in the pile core is offset from the centre ofthe pile to compensate for the offset load.
The illustrated pile with the above mentioned diemsnions, can be driven in by a reaction of three or four tons, which is readily available using a simple hydraulic jack taking its reaction from the underpinning beam 11. The resulting pile can provide a safe load of up to 10 tons.
Figure 6 shows a modification of Figure 3 in which the segments 19 are driven by a reciprocating mandrel 40 which is guided on a rod 41 and carries an expanding chuck 42.
The inner surfaces of the segments 19 taper in the upwards direction frusto-conically to provide their inner upper edges with a shoulder reinforced by a steel ring 43. The rod 41 at all times extends down to the bottom segment 19A and the mandrel 40 and chuck 42 are controlled from above ground level. When a segment is to be pushed down, the chuck 42 is expanded immediately above the corresponding shoulder 43 and the mandrel 40 is then driven down by a short distance. The chuk 42 is contracted and raised prior to expansion above the shoulder of the segment above and the driving of that segment.
The Figure 6 technique could be modified by causing the chuck 42 to be expanded into internal gripping engagement with a segment 19 to be driven, rather than into a position overlying the reinforced shoulder 43.
Figure 7 shows an alternative pile which is divided by axial planes into a ring of annular sector shaped segments 44 which extend the full length of the pile. The segments 44 are shown held together by an encircling band 45 which is seated in complementary grooves 46 in the outer surfaces of the segments 44.
The segments 44 are driven into the ground successively in diametrically opposed pairs by means of a reciprocating mandrel 47 carrying a pair of wings 48 which engage the tops of a pair of the segments. Thus a pair of the segments are driven a few millimetres into the ground, to an extent allowed by the cooperation of the band 45 and grooves 46, whereafter the mandrel 47 is raised, turned through a small angle to bring the wings 48 into engagement with the next pair of segments 44, and the mandrel is driven down once again.
Figure 7 shows one segment 44A which has been advanced relatively to the adjacent segments.
WHAT WE CLAIM IS:
1. A method of inserting a columnar pile in the ground, wherein the pile is formed by a plurality of segments each of which contributes only a part of the area of contact between the surface of the pile and the surrounding earth, the method being characterised in that, at least following initial stages of segment insertion, the segments at any time forming that part of the pile in the ground are advanced individually or in groups in turn a little way further into the ground and the cycle is repeated until the pile is in its fully driven position.
2. A method according to claim 1, in which the driven segments form a hollow pile body which is substantially filled with grout to interconnect the segments rigidly together.
3. A method according to claim 1 or claim 2, in which the pile is divided transversely to its length into the segments.
4. A method according to claim 3, in which the external cross sectional dimensions of the segments increase from the bottom of the pile upwards.
5. A method according to claim 3 or claim 4, in which the segments above the leading segment are tubular and the segments are repeatedly driven a little way into the ground beginning from the leading segment at the bottom of the pile and working successively up the pile by means of driving means extending down through the tubular segments.
6. A method according to claim 5, in which the driving means is a reciprocating driving member which is repeatedly brought into driving engagement with successive segments.
7. A method according to claim 5, in which the driving means comprises a central driving member surrounded by a number of concentric tubular driving members, the lower ends of successive ones of the driving members in the radial outward direction abutting against respective successive ones of the
**WARNING** end of DESC field may overlap start of CLMS **.
Claims (16)
1. A method of inserting a columnar pile in the ground, wherein the pile is formed by a plurality of segments each of which contributes only a part of the area of contact between the surface of the pile and the surrounding earth, the method being characterised in that, at least following initial stages of segment insertion, the segments at any time forming that part of the pile in the ground are advanced individually or in groups in turn a little way further into the ground and the cycle is repeated until the pile is in its fully driven position.
2. A method according to claim 1, in which the driven segments form a hollow pile body which is substantially filled with grout to interconnect the segments rigidly together.
3. A method according to claim 1 or claim 2, in which the pile is divided transversely to its length into the segments.
4. A method according to claim 3, in which the external cross sectional dimensions of the segments increase from the bottom of the pile upwards.
5. A method according to claim 3 or claim 4, in which the segments above the leading segment are tubular and the segments are repeatedly driven a little way into the ground beginning from the leading segment at the bottom of the pile and working successively up the pile by means of driving means extending down through the tubular segments.
6. A method according to claim 5, in which the driving means is a reciprocating driving member which is repeatedly brought into driving engagement with successive segments.
7. A method according to claim 5, in which the driving means comprises a central driving member surrounded by a number of concentric tubular driving members, the lower ends of successive ones of the driving members in the radial outward direction abutting against respective successive ones of the
pile segments in the direction from the bottom of the pile upwards, and the driving members are repeatedly advanced a little way downwards working successively radially outwardly from the central driving member.
8. A method according to claim 6 or claim 7, in which the pile segments are made of precast concrete and each segment has a cast in reinforcing member against which the respective driving member engages.
9. A method according to any one of claims 5 to 8, in which each pile segment is provided with a trailing skirt into which the nose of the succeeding segment fits, the segments being advanced by a distance no greater than the overlap between a complementary skirt and nose.
10. A method according to claim 1 or claim 2, in which the pile is divided along its length into the segments.
11. A method according to claim 10, in which means are provided for preventing the segments from moving laterally apart when they are separately driven into the ground.
12. A method according to claim 10 or claim 11, in which the segments form a ring of sector shaped segments and the segments are successively driven into the ground by an axially reciprocating driving member which is rotated through an angle into alignment with another segment or segments between each working stroke.
13. A method according to any one of the preceding claims, in which the top of the pile is surrounded by a fluent, resilient or crushable material to isolate the upper portion of the pile against a reaction resulting from horizontal movement of the surrounding earth.
14. A method according to claim 1, substantially as described with reference to any one of the examples illustrated in the accompanying drawings.
15. A pile which has been inserted by a method according to any one of the preceding claims.
16. A building having an underpinning beam which is at least artially supported by a pile according to claim 15.
Priority Applications (8)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB135477A GB1592591A (en) | 1977-01-13 | 1977-01-13 | Piles |
DE19782800971 DE2800971A1 (en) | 1977-01-13 | 1978-01-11 | DEVICE AND METHOD FOR INSERTING MULTIPARTIC OBJECTS INTO THE SOIL |
US05/868,529 US4190383A (en) | 1977-01-13 | 1978-01-11 | Structural element |
MX78172014A MX145227A (en) | 1977-01-13 | 1978-01-12 | IMPROVED METHOD FOR HINDING COLUMN PILES IN THE FLOOR |
NL7800389A NL7800389A (en) | 1977-01-13 | 1978-01-12 | METHOD OF INSTALLING A COLUMN SHAPED POLE IN THE GROUND. |
IT67054/78A IT1106526B (en) | 1977-01-13 | 1978-01-12 | PROCEDURE FOR OBTAINING COLUMN POLES STUCK IN THE SOIL |
BE184263A BE862848A (en) | 1977-01-13 | 1978-01-12 | PROCESS FOR CREATING A COLUMN-SHAPED PILE IN THE SOIL |
FR7800842A FR2377485A1 (en) | 1977-01-13 | 1978-01-12 | PILE AND PILE DRIVING PROCESS DESIGNED FOR THE IMPLEMENTATION OF THIS PROCESS |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB135477A GB1592591A (en) | 1977-01-13 | 1977-01-13 | Piles |
Publications (1)
Publication Number | Publication Date |
---|---|
GB1592591A true GB1592591A (en) | 1981-07-08 |
Family
ID=9720557
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
GB135477A Expired GB1592591A (en) | 1977-01-13 | 1977-01-13 | Piles |
Country Status (2)
Country | Link |
---|---|
BE (1) | BE862848A (en) |
GB (1) | GB1592591A (en) |
-
1977
- 1977-01-13 GB GB135477A patent/GB1592591A/en not_active Expired
-
1978
- 1978-01-12 BE BE184263A patent/BE862848A/en not_active IP Right Cessation
Also Published As
Publication number | Publication date |
---|---|
BE862848A (en) | 1978-07-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4190383A (en) | Structural element | |
EP1673509B1 (en) | Method of constructing a pile foundation | |
US6718707B2 (en) | Cable end wedge lock | |
CN109778851B (en) | Construction method for multistage expandable supporting body bag grouting prestressed anchor rod | |
US3568452A (en) | Method and apparatus for forming bulbular base piles | |
EP0820550B1 (en) | Method and tool for performing ground anchorage | |
US4040260A (en) | Pile with downwardly extending elongated elements | |
US4038827A (en) | Pile | |
CN111827280B (en) | Ex-situ pouring, jacking and in-place hole digging pile retaining wall device and construction method thereof | |
US6948885B2 (en) | Method for constructing foundation | |
US1164085A (en) | Method or process of anchoring steel piles. | |
US4619558A (en) | Apparatus for producing in-situ concreted piles with enlarged bases | |
JP4115095B2 (en) | Reverse strike method | |
GB1592591A (en) | Piles | |
EP0413422B1 (en) | Foundation construction method | |
EP0084921B1 (en) | Piles | |
GB2218722A (en) | Pile pressing | |
GB2067623A (en) | Method for supporting buildings | |
US2274082A (en) | Method for construction of marine foundations | |
GB2085950A (en) | Driven composite piles | |
SU1677180A1 (en) | Method of manufacturing reinforced cast-in-place pile | |
CN219240516U (en) | Isolation pile structure for limiting soil displacement | |
CN111779018B (en) | Mechanical construction method for embedded anchor rod composite foundation of power transmission line | |
JPH0960311A (en) | Lift-up demolition method | |
SU863868A1 (en) | Method and unit for pressing-through tunnel sections |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PS | Patent sealed | ||
PCNP | Patent ceased through non-payment of renewal fee |