FR3117243A1 - 3D visualization tool of a building coupled with a schedule - Google Patents

3D visualization tool of a building coupled with a schedule Download PDF

Info

Publication number
FR3117243A1
FR3117243A1 FR2014285A FR2014285A FR3117243A1 FR 3117243 A1 FR3117243 A1 FR 3117243A1 FR 2014285 A FR2014285 A FR 2014285A FR 2014285 A FR2014285 A FR 2014285A FR 3117243 A1 FR3117243 A1 FR 3117243A1
Authority
FR
France
Prior art keywords
building
visualization
construction
schedule
tool
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
FR2014285A
Other languages
French (fr)
Inventor
Patrick Herbault
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from FR2012938A external-priority patent/FR3117241A1/en
Application filed by Individual filed Critical Individual
Priority to PCT/FR2021/000136 priority Critical patent/WO2022123126A1/en
Publication of FR3117243A1 publication Critical patent/FR3117243A1/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F3/00Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
    • G06F3/01Input arrangements or combined input and output arrangements for interaction between user and computer
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F3/00Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
    • G06F3/01Input arrangements or combined input and output arrangements for interaction between user and computer
    • G06F3/048Interaction techniques based on graphical user interfaces [GUI]
    • G06F3/0484Interaction techniques based on graphical user interfaces [GUI] for the control of specific functions or operations, e.g. selecting or manipulating an object, an image or a displayed text element, setting a parameter value or selecting a range
    • G06F3/04845Interaction techniques based on graphical user interfaces [GUI] for the control of specific functions or operations, e.g. selecting or manipulating an object, an image or a displayed text element, setting a parameter value or selecting a range for image manipulation, e.g. dragging, rotation, expansion or change of colour
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/12Geometric CAD characterised by design entry means specially adapted for CAD, e.g. graphical user interfaces [GUI] specially adapted for CAD
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2203/00Indexing scheme relating to G06F3/00 - G06F3/048
    • G06F2203/048Indexing scheme relating to G06F3/048
    • G06F2203/04804Transparency, e.g. transparent or translucent windows

Abstract

Outil de visualisation 3D d’un bâtiment couplé à un planning L’invention concerne un outil de visualisation tridimensionnelle de la construction d’un bâtiment en fonction d’un planning. L’outil logiciel de visualisation tridimensionnelle d’un bâtiment est couplé à un planning de construction de ce bâtiment et dispose de la constitution du bâtiment sous forme de constituants en CAO ainsi que des dates associées à la présence ou l’absence de ces constituants conformément au planning de construction. De ce fait l’outil permet la visualisation virtuelle de la construction du bâtiment en faisant apparaître ou disparaitre virtuellement à un instant donné les constituants en fonction de la présence ou l’absence de chaque constituant conformément au planning. L’outil comporte une interface ligne de temps avec un début, une fin, une fonction lecture, arrêt sur image, avance rapide, retour rapide ainsi qu’un moyen d’exporter une vidéo virtuelle de la construction du bâtiment en accéléré. Figure à publier avec l’abrégé : Fig. 2.Tool for 3D visualization of a building coupled with a schedule The invention relates to a tool for three-dimensional visualization of the construction of a building according to a schedule. The software tool for three-dimensional visualization of a building is coupled with a construction schedule for this building and has the constitution of the building in the form of CAD components as well as the dates associated with the presence or absence of these components in accordance to the construction schedule. As a result, the tool allows the virtual visualization of the construction of the building by making the constituents appear or disappear virtually at a given moment according to the presence or absence of each constituent in accordance with the schedule. The tool features a timeline interface with a start, end, play, freeze frame, fast forward, fast reverse and a way to export a virtual video of the construction of the building in accelerated. Figure to be published with abstract: Fig. 2.

Description

Outil de visualisation 3D d’un bâtiment couplé à un planning3D visualization tool of a building coupled with a schedule

DOMAINE DE L'INVENTION AUQUEL SE RAPPORTE L'INVENTIONFIELD OF THE INVENTION TO WHICH THE INVENTION RELATES

L’invention concerne un outil de visualisation tridimensionnelle de la construction d’un bâtiment en fonction d’un planning.The invention relates to a tool for three-dimensional visualization of the construction of a building according to a schedule.

ART ANTERIEURPRIOR ART

Dans le domaine des outils logiciels dans le domaine du bâtiment, il existe de nombreux outils d’accompagnement tels que des outils CAO pour la construction ou des outils plus artistiques de rendu 3D pour visualiser à l’avance pour le client une vue photoréaliste du bâtiment achevé.In the area of software tools in the field of construction, there are many accompanying tools such as CAD tools for construction or more artistic 3D rendering tools to visualize in advance for the customer a photorealistic view of the building completed.

Il existe également des outils de planification, de facturation, de gestion documentaire…There are also tools for planning, invoicing, document management, etc.

A notre connaissance, il n’existe pas d’outil de visualisation en 3D d’un bâtiment qui permette de visualiser la construction d’un bâtiment en fonction d’un planning.To our knowledge, there is no 3D visualization tool for a building that allows you to visualize the construction of a building according to a schedule.

BREVE DESCRIPTION DE L'INVENTIONBRIEF DESCRIPTION OF THE INVENTION

L’outil logiciel de visualisation tridimensionnelle d’un bâtiment selon l’invention est couplé à un planning de construction de ce bâtiment et dispose de la constitution du bâtiment sous forme de constituants en CAO ainsi que des dates associées à la présence ou l’absence de ces constituants conformément au planning de construction.The software tool for three-dimensional visualization of a building according to the invention is coupled with a construction schedule for this building and has the constitution of the building in the form of CAD components as well as dates associated with the presence or absence of these constituents in accordance with the construction schedule.

De ce fait l’outil permet la visualisation virtuelle de la construction du bâtiment en faisant apparaître ou disparaitre virtuellement à un instant donné les constituants en fonction de la présence ou l’absence de chaque constituant conformément au planning.As a result, the tool allows the virtual visualization of the construction of the building by making the components appear or disappear virtually at a given moment depending on the presence or absence of each component in accordance with the schedule.

Suivant un mode réalisation, l’outil dispose d’une interface propre pour associer les données planning des constituants.According to one embodiment, the tool has its own interface for associating the planning data of the constituents.

Selon un autre mode de réalisation, l’outil dispose d’un mode d’importation des données planning d’un outil de planification.According to another embodiment, the tool has a mode for importing planning data from a planning tool.

L’outil comporte une interface pour définir l’instant donné de la visualisation.The tool includes an interface to define the given instant of visualization.

De façon avantageuse, l’outil comporte une interface ligne de temps avec un début, une fin, une fonction lecture, arrêt sur image, avance rapide, retour rapide.Advantageously, the tool includes a timeline interface with a start, an end, a playback function, freeze frame, fast forward, fast reverse.

L’outil comporte une interface pour définir l’échelle de temps pour la vitesse du défilement de la visualisation par rapport à l’échelle de temps de la construction du bâtiment.The tool has an interface to set the timescale for the visualization scroll speed relative to the building construction timescale.

Dans le cas où un constituant est prévu au planning d’être réalisé avec une date de début et une date de fin, il est de façon préférentielle visualisé pendant cette phase de réalisation avec un niveau de transparence/opacité fonction du pourcentage d’avancement théorique de la réalisation.In the event that a constituent is planned in the schedule to be produced with a start date and an end date, it is preferably viewed during this phase of production with a level of transparency / opacity depending on the theoretical percentage of progress of realization.

L’invention présente l’intérêt de pouvoir disposer d’une vidéo virtuelle de la construction d’un bâtiment produite par l’outil de visualisation tridimensionnelle.The invention has the advantage of being able to have a virtual video of the construction of a building produced by the three-dimensional visualization tool.

En termes d’utilisation, c’est effectivement une des utilisations de l’outil de visualisation tridimensionnelle d’un bâtiment quand il est utilisé pour produire une vidéo virtuelle de la construction du bâtiment.In terms of usage, this is actually one of the uses of the 3D building visualization tool when it is used to produce a virtual video of the construction of the building.

D'autres caractéristiques et avantages de l'invention apparaîtront à la lecture de la description détaillée qui suit pour la compréhension de laquelle on se reportera aux dessins annexés.Other characteristics and advantages of the invention will appear on reading the detailed description which follows for the understanding of which reference is made to the appended drawings.

montre un chantier à l’étape initiale sans bâtiment mais avec un panneau réglementaire de permis de construire, des panneaux publicitaires et un espace de vente, visualisée virtuellement. shows a construction site at the initial stage without a building but with a regulatory building permit sign, advertising panels and a sales area, visualized virtually.

montre un bâtiment en cours de construction à une étape visualisée virtuellement. shows a building under construction at one stage visualized virtually.

montre un bâtiment en cours de construction à une autre étape visualisée virtuellement. shows a building under construction at another stage visualized virtually.

montre un bâtiment finalisé visualisé virtuellement avec un rendu technique. shows a finalized building visualized virtually with a technical rendering.

montre un bâtiment finalisé visualisé virtuellement avec un rendu 3D. shows a finalized building visualized virtually with a 3D rendering.

DESCRIPTION DETAILLEE DE L'INVENTIONDETAILED DESCRIPTION OF THE INVENTION

L’outil logiciel de visualisation tridimensionnelle d’un bâtiment (B) selon l’invention est couplé à un planning de construction de ce bâtiment (B)The software tool for three-dimensional visualization of a building (B) according to the invention is coupled to a construction schedule for this building (B)

Ce planning peut macroscopique ou plus fin.This schedule can be macroscopic or finer.

La planification peut être réalisée de façon macroscopique, la construction étant organisée par lots et chacun des constituants de la définition tridimensionnelle appartient à un des lots.The planning can be carried out macroscopically, the construction being organized by lots and each of the constituents of the three-dimensional definition belongs to one of the lots.

La planification peut être réalisée de façon beaucoup plus fine, chacun des constituants faisant l’objet d’une tâche de planification individuelle.Planning can be carried out in a much finer way, with each of the constituents being the subject of an individual planning task.

L’outil logiciel de visualisation tridimensionnelle doit également disposer de la constitution du bâtiment (B) sous forme de constituants en CAO ainsi que des dates associées à la présence ou l’absence de ces constituants conformément au planning de construction.The 3D visualization software tool must also have the constitution of the building (B) in the form of CAD components as well as the dates associated with the presence or absence of these components according to the construction schedule.

De façon classique des outils CAO permettent d’élaborer la définition tridimensionnelle d’un bâtiment (B). Ces outils permettent de visualiser le bâtiment. Souvent il est décrit dans un format propriétaire de l’outil.Classically, CAD tools make it possible to develop the three-dimensional definition of a building (B). These tools allow you to visualize the building. Often it is described in a format proprietary to the tool.

Il existe également des formats standards comme IFC (Industry Foundation Classes). Ce format est un format de fichier standardisé orienté objet utilisé par l'industrie du bâtiment pour échanger et partager des informations entre logiciels.There are also standard formats like IFC (Industry Foundation Classes). This format is a standardized object-oriented file format used by the construction industry to exchange and share information between software.

Il existe des outils indépendants de visualisation de bâtiment décrits au format IFC.There are independent building visualization tools described in IFC format.

L’outil logiciel de visualisation tridimensionnelle doit également disposer des dates associées à la présence ou l’absence de ces constituants conformément au planning de construction.The 3D visualization software tool must also have the dates associated with the presence or absence of these constituents according to the construction schedule.

De ce fait l’outil permet la visualisation virtuelle de la construction du bâtiment (B) en faisant apparaître ou disparaitre virtuellement à un instant donné les constituants en fonction de la présence ou l’absence de chaque constituant conformément au planning.As a result, the tool allows the virtual visualization of the construction of the building (B) by making the components appear or disappear virtually at a given moment depending on the presence or absence of each component in accordance with the schedule.

Les éléments construits restent présents une fois apparus dans la visualisation alors que des éléments provisoires peuvent apparaître puis disparaître.Constructed elements remain present once they appear in the visualization, while temporary elements may appear and then disappear.

Avant que le bâtiment ne sorte de terre, pendant les travaux de terrassement, il est possible d’intégrer des éléments provisoires spécifiques d’un chantier tels qu’un panneau réglementaire, un panneau publicitaire, une cabine de chantier, un espace de vente présent à proximité du chantier. Pour cela, ces éléments provisoires spécifiques d’un chantier doivent être numérisés comme les constituants du bâtiment (B) pour être intégrer dans la visualisation virtuelle.Before the building rises from the ground, during the earthworks, it is possible to integrate temporary elements specific to a construction site such as a regulatory panel, an advertising panel, a site cabin, a sales area present near the construction site. For this, these specific temporary elements of a construction site must be digitized like the constituents of the building (B) to be integrated into the virtual visualization.

Ensuite, en cours de construction, au fur et à mesure que les étages se montent, il est possible également d’ajouter à la définition du bâtiment également par exemples les coffrages toujours comme éléments provisoires spécifiques d’un chantier. Pour cela, ces coffrages doivent être également numérisés pour être intégrer pour être intégrer dans la visualisation virtuelle au titre du processus de construction du bâtiment (B).Then, during construction, as the floors go up, it is also possible to add to the definition of the building also, for example, the formwork, always as temporary elements specific to a site. For this, these formworks must also be digitized to be integrated to be integrated into the virtual visualization under the building construction process (B).

La illustre l’exemple où le bâtiment (B, B0) en est à l’étape zéro c’est-à-dire où il n’est pas encore sorti de terre. Sans attendre que le bâtiment (B) du chantier sorte de terre, la définition tridimensionnelle du chantier peut déjà comporter au moins un élément provisoire (P) tels qu’un panneau réglementaire (PR), un panneau publicitaire (PP) ou un espace de vente (EV) présent à proximité du chantier.There illustrates the example where the building (B, B0) is at stage zero, that is to say where it has not yet come out of the ground. Without waiting for the site building (B) to come out of the ground, the three-dimensional definition of the site may already include at least one temporary element (P) such as a regulatory panel (PR), an advertising panel (PP) or a sale (EV) present near the site.

La illustre la visualisation obtenue à titre d’exemple d’un bâtiment (B, B1) en début de construction.There illustrates the visualization obtained as an example of a building (B, B1) at the start of construction.

La illustre la visualisation obtenue à titre d’exemple du bâtiment (B, B2) est dans une configuration intermédiaire.There illustrates the visualization obtained by way of example of the building (B, B2) is in an intermediate configuration.

La illustre la visualisation du bâtiment (B) obtenue une étape du processus de construction correspondant au bâtiment (B, B3) finalisé comme représenté en vue technique.There illustrates the visualization of the building (B) obtained one step of the construction process corresponding to the building (B, B3) finalized as represented in technical view.

De façon avantageuse, la visualisation finale de l’étape du processus de construction correspondant au bâtiment finalisé (B, B3) est faite avec rendu 3D comme illustré . En particulier notamment pour les architectes il existe des moyens de visualisation extrêmement sophistiqués qui permettent d’obtenir des vues avec un rendu photoréaliste.Advantageously, the final visualization of the stage of the construction process corresponding to the finalized building (B, B3) is made with 3D rendering as illustrated . In particular, especially for architects, there are extremely sophisticated means of visualization which make it possible to obtain views with a photorealistic rendering.

Suivant un mode réalisation, l’outil dispose d’une interface propre pour associer les données planning des constituants. Cela est le cas quand les données du planning sont intégrées manuellement dans l’outil ou dans une version plus automatisée quand l’outil intègre directement un outil de planification typiquement de type Gantt.According to one embodiment, the tool has its own interface for associating the planning data of the constituents. This is the case when the planning data is manually integrated into the tool or in a more automated version when the tool directly integrates a planning tool typically of the Gantt type.

Selon un autre mode de réalisation, l’outil dispose d’un mode d’importation des données planning d’un outil de planification externe typiquement de type Gantt par exemple sous forme d’un fichier Excel (Marque déposée) exporté d’un logiciel de planification de type MS Project (Marque déposée).According to another embodiment, the tool has a mode for importing planning data from an external planning tool typically of the Gantt type, for example in the form of an Excel file (Registered trademark) exported from software planning type MS Project (Registered trademark).

L’outil comporte une interface pour définir l’instant donné de la visualisation.The tool includes an interface to define the given instant of visualization.

De façon avantageuse, l’outil comporte de façon analogue à la lecture d’une vidéo, une interface ligne de temps avec un début, une fin, une fonction lecture, arrêt sur image, avance rapide, retour rapide.Advantageously, the tool includes, similar to video playback, a timeline interface with a start, an end, a playback function, freeze frame, fast forward, fast reverse.

Bien entendu, de préférence le début de la ligne de temps correspond au début de la construction du bâtiment (B) et la fin de l’échelle de la ligne de temps correspond à la fin de la construction du bâtiment (B). Il est possible d’ajouter en finale une séquence passant d’une vue technique à une vue photoréaliste avec rendu 3D pour illustrer la phase de finition achevant la construction du bâtiment (B).Of course, preferably the beginning of the timeline corresponds to the start of the construction of the building (B) and the end of the scale of the timeline corresponds to the end of the construction of the building (B). It is possible to add in the final a sequence going from a technical view to a photorealistic view with 3D rendering to illustrate the finishing phase completing the construction of the building (B).

L’outil comporte une interface pour définir l’échelle de temps pour la vitesse du défilement de la visualisation par rapport à l’échelle de temps de la construction du bâtiment (B).The tool has an interface to set the timescale for the visualization scroll speed relative to the building construction timescale (B).

A titre d’exemple cela peut consister à ce qu’une journée de construction soit traduite par une seconde de vidéo.For example, this may consist of a day of construction being translated into a second of video.

Cela peut consister également à définir la durée de la vidéo, à titre d’exemple une durée d’une minute et choisir l’échelle de temps pour que cela corresponde à la durée du chantier du début à la fin.This can also consist of defining the duration of the video, for example a duration of one minute and choosing the time scale so that it corresponds to the duration of the construction site from start to finish.

Il est avantageux qu’en parallèle de cette commande de l’instant observé, la commande du point de vue de la visualisation reste fonctionnelle.It is advantageous that in parallel with this control of the observed instant, the control from the point of view of visualization remains functional.

Alors il reste possible pendant la séquence de construction de changer le point de vue de la visualisation au fur et à mesure de la construction du bâtiment.So it remains possible during the construction sequence to change the point of view of the visualization as the building is constructed.

La visualisation peut être celle d’un point de vue externe au bâtiment type vue d’hélicoptère.The visualization can be that of a point of view external to the building, such as a helicopter view.

La visualisation peut être interne au bâtiment selon une vue en mode jeu, c’est-à-dire permettant de visualiser et de se promener dans un modèle 3D comme à l’intérieur d’un jeu à la première personne.The visualization can be internal to the building according to a view in game mode, that is to say allowing to visualize and walk around in a 3D model as inside a first person game.

Dans le cas où un constituant est prévu au planning d’être réalisé avec une date de début et une date de fin, il est de façon préférentielle visualisé pendant cette phase de réalisation avec un niveau de transparence/opacité fonction du pourcentage d’avancement théorique de la réalisation. Le constituant est transparent au début de la phase de réalisation, partiellement transparent/opaque pendant la phase de réalisation et opaque quand la phase théorique de réalisation est achevée.In the event that a constituent is planned in the schedule to be produced with a start date and an end date, it is preferably viewed during this phase of production with a level of transparency / opacity depending on the theoretical percentage of progress of realization. The constituent is transparent at the start of the production phase, partially transparent/opaque during the production phase and opaque when the theoretical production phase is completed.

L’invention présente l’intérêt de pouvoir disposer d’une vidéo virtuelle de la construction d’un bâtiment (B) produite par l’outil de visualisation tridimensionnelle bien entendu en vitesse accélérée.The invention has the advantage of being able to have a virtual video of the construction of a building (B) produced by the three-dimensional visualization tool of course at accelerated speed.

A cette fin, l’outil dispose d’un mode d’exportation de la vidéo ainsi élaborée.To this end, the tool has an elaborate video export mode.

Cette vidéo peut être utilisée par le constructeur du bâtiment (B) pour optimiser son processus ou pour le client final pour visualiser son projet.This video can be used by the builder of the building (B) to optimize his process or for the end customer to visualize his project.

En termes d’utilisation, c’est effectivement une des utilisations de l’outil de visualisation tridimensionnelle d’un bâtiment (B) quand il est utilisé pour produire une vidéo virtuelle de la construction du bâtiment (B).In terms of use, this is actually one of the uses of the 3D building visualization tool (B) when it is used to produce a virtual video of the construction of the building (B).

En termes d’application industrielle, l’invention concerne un outil de visualisation tridimensionnelle de la construction d’un bâtiment en fonction d’un planning.In terms of industrial application, the invention relates to a tool for three-dimensional visualization of the construction of a building according to a schedule.

La présente invention n'est nullement limitée aux modes de réalisation décrits et représentés mais l'homme du métier saura y apporter toute variante conforme à son esprit pour une gamme d’outils logiciels avec différents niveaux de sophistication.The present invention is in no way limited to the embodiments described and represented, but those skilled in the art will be able to add any variant in accordance with their spirit for a range of software tools with different levels of sophistication.

Claims (9)

Procédé mis en œuvre par ordinateur de visualisation tridimensionnelle d’un bâtiment (B) caractérisé par le fait qu’il est couplé à un planning de construction de ce bâtiment (B), qu’il dispose de la constitution du bâtiment (B) sous forme de constituants en CAO ainsi que des dates associées à la présence ou l’absence de ces constituants conformément au planning de construction et par le fait qu’il dispose d’une interface pour définir l’instant donné de la visualisation.Process implemented by computer for the three-dimensional visualization of a building (B) characterized in that it is coupled to a construction schedule for this building (B), that it has the constitution of the building (B) under form of components in CAD as well as the dates associated with the presence or absence of these components in accordance with the construction schedule and by the fact that it has an interface to define the given instant of visualization. Procédé selon la revendication 1 caractérisé par le fait que le procédé permet la visualisation virtuelle de la construction du bâtiment (B) en faisant apparaître ou disparaitre virtuellement à un instant donné de la visualisation les constituants du bâtiment (B) en regard de l’instant donné de la visualisation défini par l’interface et de la présence ou l’absence de chaque constituant conformément au planning à cet instant donné défini de la visualisation en fonction des dates associées.Process according to Claim 1, characterized in that the process allows the virtual visualization of the construction of the building (B) by causing the constituents of the building (B) to appear or disappear virtually at a given instant of the visualization opposite the instant given of the visualization defined by the interface and of the presence or the absence of each component in accordance with the planning at this given instant defined of the visualization according to the associated dates. Procédé suivant l’un quelconque des revendications 1 à 2 caractérisé par le fait qu’il dispose d’une interface pour associer les données planning des constituants.Process according to any one of Claims 1 to 2, characterized in that it has an interface for associating the planning data of the constituents. Procédé suivant l’un quelconque des revendications 1 à 2 caractérisé par le fait qu’il dispose d’un mode d’importation des données planning d’un outil de planification.Process according to any one of Claims 1 to 2, characterized in that it has a mode for importing planning data from a planning tool. Procédé suivant la revendication 1 caractérisé par le fait que l’interface pour définir l’instant donné de la visualisation comporte une interface ligne de temps avec un début, une fin, une fonction lecture, arrêt sur image, avance rapide, retour rapide.Process according to Claim 1, characterized in that the interface for defining the given instant of viewing comprises a timeline interface with a start, an end, a playback function, freeze frame, fast forward, fast reverse. Procédé suivant la revendication 5 caractérisé par le fait qu’il comporte une interface pour définir l’échelle de temps pour la vitesse du défilement de la visualisation par rapport à l’échelle de temps de la construction du bâtiment (B).Method according to Claim 5, characterized in that it includes an interface for defining the time scale for the scrolling speed of the visualization in relation to the time scale of the construction of the building (B). Procédé suivant l’une quelconque des revendications 1 à 6 caractérisée par le fait que lorsque qu’un constituant est prévu au planning d’être réalisé avec une date de début et une date de fin, il est visualisé pendant cette phase de réalisation avec un niveau de transparence/opacité fonction du pourcentage d’avancement théorique de la réalisation.Process according to any one of Claims 1 to 6, characterized in that when a component is scheduled to be produced with a start date and an end date, it is visualized during this production phase with a level of transparency/opacity depending on the percentage of theoretical advancement of the achievement. Vidéo caractérisée par le fait qu’il s’agit d’une vidéo virtuelle de la construction d’un bâtiment (B) produite par le procédé de visualisation tridimensionnelle selon l’une quelconque des revendications 1 à 7.Video characterized in that it is a virtual video of the construction of a building (B) produced by the three-dimensional visualization method according to any one of Claims 1 to 7. Utilisation du procédé de visualisation tridimensionnelle d’un bâtiment (B) selon l’une quelconque des revendications 1 à 7 caractérisée par le fait qu’il est utilisé pour produire une vidéo virtuelle de la construction du bâtiment (B).Use of the three-dimensional visualization method of a building (B) according to any one of Claims 1 to 7, characterized in that it is used to produce a virtual video of the construction of the building (B).
FR2014285A 2020-12-09 2020-12-30 3D visualization tool of a building coupled with a schedule Pending FR3117243A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/FR2021/000136 WO2022123126A1 (en) 2020-12-09 2021-11-18 Tool for viewing in 3d a building coupled with a schedule

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FR2012938A FR3117241A1 (en) 2020-12-08 2020-12-09 3D visualization tool of a building coupled with a schedule
FR2012938 2020-12-09

Publications (1)

Publication Number Publication Date
FR3117243A1 true FR3117243A1 (en) 2022-06-10

Family

ID=75690370

Family Applications (1)

Application Number Title Priority Date Filing Date
FR2014285A Pending FR3117243A1 (en) 2020-12-09 2020-12-30 3D visualization tool of a building coupled with a schedule

Country Status (1)

Country Link
FR (1) FR3117243A1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030052877A1 (en) * 2001-05-04 2003-03-20 Schwegler Benedict Richard Text overlay for multi-dimensional construction project models
US20050065951A1 (en) * 2002-08-30 2005-03-24 Kathleen Liston Visualization of commonalities in data from different sources
US20100217640A1 (en) * 2009-02-20 2010-08-26 Mark Nichols Method and system for adaptive construction sequencing
US20100241471A1 (en) * 2009-03-19 2010-09-23 Scenario Design, Llc Integration system supporting dimensioned modeling system
US20190205484A1 (en) * 2017-12-28 2019-07-04 ALICE Technologies, Inc. Systems and methods for construction planning

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030052877A1 (en) * 2001-05-04 2003-03-20 Schwegler Benedict Richard Text overlay for multi-dimensional construction project models
US20050065951A1 (en) * 2002-08-30 2005-03-24 Kathleen Liston Visualization of commonalities in data from different sources
US20100217640A1 (en) * 2009-02-20 2010-08-26 Mark Nichols Method and system for adaptive construction sequencing
US20100241471A1 (en) * 2009-03-19 2010-09-23 Scenario Design, Llc Integration system supporting dimensioned modeling system
US20190205484A1 (en) * 2017-12-28 2019-07-04 ALICE Technologies, Inc. Systems and methods for construction planning

Similar Documents

Publication Publication Date Title
US20110071798A1 (en) Cad system for assessing blank size
EP2082374B1 (en) Method and aids for modelling 3d objects
CN107516161A (en) A kind of project progress management-control method based on BIM
WO2008056055A1 (en) Method and aids for relative positioning of objects during a design phase
CN105243237B (en) A kind of construction method of assembly technology structure tree
FR2674347A1 (en) Process for creating a three-dimensional model with a computer-aided design system
CN102142152A (en) Method, apparatus, and program for displaying an object on a computer screen
JP2016126795A (en) Selection of viewpoint of set of objects
TW201828259A (en) Architectural Planning method to integrate into a 3D stereoscopic Architectural Planning image having both 3D stereoscopic image model with live scene and a 3D stereoscopic virtual building
US20120194535A1 (en) Two-dimensional vector fills using topological recipes
Alexander et al. Contestation in aesthetic fields: Legitimation and legitimacy struggles in outsider art
US8823712B1 (en) Application of bevel curves to splines
FR3117243A1 (en) 3D visualization tool of a building coupled with a schedule
FR3117241A1 (en) 3D visualization tool of a building coupled with a schedule
WO2022123126A1 (en) Tool for viewing in 3d a building coupled with a schedule
CA2502325C (en) Method and device for constructing and viewing a computer model image
FR2937770A1 (en) METHOD FOR CREATING A NON-AXISYMETRIC SURFACE
Macheret et al. Automated design systems based on the use of three-dimensional object modeling techniques
US20160291821A1 (en) Generating and displaying graphical representations of processes
Brixius Google SketchUp Workshop
Muhsin Building Information Modeling Concept And Its Application in Building Renovation Stage In Term Of Time Efficiency
De Jongh Google SketchUp for Game Design: Beginner's Guide: Create 3D Game Worlds Complete with Textures, Levels, and Props
CN117609238A (en) BIM model-based light-weight data management and digital-analog separation and combination method
Fernández-Solís et al. Structured Literature Review of Design-Build/Bridging, Design-Bid-Build & Design-Build
Subhi et al. Modelling and Project Planning Of a Two Storied Building by Implementing 5D BIM

Legal Events

Date Code Title Description
PLFP Fee payment

Year of fee payment: 2

PLSC Publication of the preliminary search report

Effective date: 20220610

PLFP Fee payment

Year of fee payment: 3

PLFP Fee payment

Year of fee payment: 4