FR2774967A1 - Barge for the development and exploitation of an oilfield at sea - Google Patents
Barge for the development and exploitation of an oilfield at sea Download PDFInfo
- Publication number
- FR2774967A1 FR2774967A1 FR9801765A FR9801765A FR2774967A1 FR 2774967 A1 FR2774967 A1 FR 2774967A1 FR 9801765 A FR9801765 A FR 9801765A FR 9801765 A FR9801765 A FR 9801765A FR 2774967 A1 FR2774967 A1 FR 2774967A1
- Authority
- FR
- France
- Prior art keywords
- columns
- bridge
- substructure
- bridges
- barge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/44—Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
- B63B35/4413—Floating drilling platforms, e.g. carrying water-oil separating devices
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Earth Drilling (AREA)
Abstract
Description
La présente invention est relative à une barge pour le développement et l'exploitation d'un champ pétrolier en mer et à un procédé pour l'installation d'une telle barge sur un tel champ. The present invention relates to a barge for the development and exploitation of an oil field at sea and to a method for the installation of such a barge on such a field.
On décrit dans la demande de brevet français n" 97 15774, déposée le 12 décembre 1997 par la demanderesse, une plate-forme semi-submersible d'exploitation d'un champ pétrolier en mer et un procédé d'installation de cette plate-forme. Il s'agit d'une plate-forme conçue pour des champs pétroliers situés sur des fonds marins de grande profondeur, de plusieurs centaines de mètres à 1500 m ou plus, par exemple. Elle comprend une sous-structure flottable constituée d'une embase de plan sensiblement carré et de plusieurs colonnes débordant vers le haut de cette embase et portant, au-dessus de la surface de l'eau, un pont-coque flottable, propriété qui est exploitée pour monter ledit pont sur la sous-structure suivant le procédé d'installation décrit dans cette demande de brevet. Cette plate-forme présente un fort tirant d'eau et des moyens de stockage de produits pétroliers dans son embase immergée. En combinaison avec un ancrage adapté, cette disposition minimise les mouvements de pilonnement de la plate-forme sous l'effet de la houle, ce qui facilite l'installation de têtes de puits sur le pont-coque. There is described in French patent application No. 97 15774, filed on December 12, 1997 by the applicant, a semi-submersible platform for the exploitation of an oil field at sea and a method of installing this platform. It is a platform designed for oil fields located on very deep seabed, several hundreds of meters to 1500 m or more, for example. It includes a buoyant substructure consisting of a base of substantially square plan and of several columns projecting upwards from this base and carrying, above the water surface, a buoyant hull, property which is used to mount said bridge on the following substructure the installation process described in this patent application. This platform has a deep draft and means for storing petroleum products in its submerged base. In combination with an adapted anchoring, this arrangement minimizes the s pounding movements of the platform under the effect of the swell, which facilitates the installation of well heads on the hull deck.
Lorsqu'elle doit présenter des dimensions importantes, une telle plate-forme de plan sensiblement carré ne peut être construite dans les installations de constructions navales actuelles, conçues pour des navires de forme allongée. Il faut alors les construire dans des cales sèches spécialement aménagées, ce qui alourdit les coûts de fabrication. En outre, la capacité de stockage d'une telle plate-forme est, compte tenu de l'état actuel de la technique, limitée à quelques centaines de milliers de barils. When it must have large dimensions, such a substantially square plane platform cannot be built in current shipbuilding installations designed for elongated ships. They must then be built in specially fitted dry docks, which increases manufacturing costs. In addition, the storage capacity of such a platform is, given the current state of the art, limited to a few hundred thousand barrels.
En outre, une telle plate-forme sensiblement carrée ou circulaire n'offre pas une stabilité hydrodynamique optimale dans les environnements marins où la houle se développe suivant une direction préférentielle. Dans ce cas, on optimise la stabilité d'un navire en l'orientant face à la houle, sa longueur étant alors alignée avec la direction de celle-ci. In addition, such a substantially square or circular platform does not offer optimal hydrodynamic stability in marine environments where the swell develops in a preferred direction. In this case, the stability of a ship is optimized by orienting it facing the swell, its length then being aligned with the direction of the latter.
Par ailleurs, le développement et l'exploitation d'un champ pétrolier en mer s'opère en plusieurs phases successives, notamment une première phase d'exploration et de forage, suivie par une deuxième phase de production exigeant des installations de surface plus importantes que la phase d'exploration et de forage. In addition, the development and exploitation of an offshore oil field takes place in several successive phases, notably a first phase of exploration and drilling, followed by a second phase of production requiring larger surface facilities than the exploration and drilling phase.
L'installation, ab initio, d'une plate-forme d'une surface convenant aussi bien à la phase initiale de forage qu'à la phase ultérieure de production, conduit à un investissement initial très important. The installation, ab initio, of a platform with a surface suitable for both the initial drilling phase and the subsequent production phase, leads to a very significant initial investment.
La présente invention a donc pour but de réaliser une structure semi-submersible pour l'exploitation de tels champs, de moyenne ou grande profondeur, susceptible d'être construite notamment dans des installations existantes de chantiers navals, offrant une capacité de stockage de produits pétroliers de un à plusieurs millions de barils et présentant une bonne stabilité hydrodynamique vis-à-vis d'un site à houle de direction préférentielle. The present invention therefore aims to achieve a semi-submersible structure for the exploitation of such fields, of medium or great depth, capable of being built in particular in existing installations of shipyards, offering a storage capacity for petroleum products. from one to several million barrels and having good hydrodynamic stability with respect to a swell site of preferential direction.
La présente invention a aussi pour but de réaliser une telle structure conçue pour assurer une adaptation optimale des moyens à installer sur site aux opérations exécutées sur celui-ci, lors des diverses phases successives de l'exploitation, de manière à réduire les coûts par un échelonnement rationnel des investissements nécessaires. The present invention also aims to achieve such a structure designed to ensure optimal adaptation of the means to be installed on site to the operations carried out on it, during the various successive phases of operation, so as to reduce costs by rational spreading of the necessary investments.
On atteint ces buts de l'invention, ainsi que d'autres qui apparaîtront à la lecture de la description qui va suivre, avec une barge pour le développement et l'exploitation de champs pétroliers en mer, cette barge étant remarquable en ce qu'elle comprend a) une sousstructure flottable constituée d'une embase entièrement immergée comportant des compartiments de stockage de produits pétroliers extraits d'un champ pétrolier, et d'une pluralité de colonnes débordant vers le haut de ladite embase jusqu'au-dessus de la surface de l'eau et, b) une pluralité de ponts, au moins deux desdits ponts étant séparément montables sur lesdites colonnes, audessus de la surface de l'eau. These objects of the invention are achieved, as well as others which will appear on reading the description which follows, with a barge for the development and exploitation of oil fields at sea, this barge being remarkable in that it comprises a) a buoyant substructure consisting of a fully submerged base comprising compartments for storing petroleum products extracted from an oil field, and a plurality of columns projecting upwards from said base to above the water surface and, b) a plurality of bridges, at least two of said bridges being separately mountable on said columns, above the water surface.
Avantageusement, suivant l'invention, lesdits ponts sont installés en fonction des équipements utilisés lors de phases successives du développement et de l'exploitation d'un champ pétrolier. Advantageously, according to the invention, said bridges are installed according to the equipment used during successive phases of the development and exploitation of an oil field.
Suivant un mode de réalisation préféré de l'invention, au moins un des ponts est chargé avec des équipements utilisés en phase de forage de puits et au moins un autre pont est chargé avec des équipements et autres installations utilisés seulement en phase de production de produits pétroliers. According to a preferred embodiment of the invention, at least one of the bridges is loaded with equipment used in the well drilling phase and at least one other bridge is loaded with equipment and other installations used only in the product production phase tankers.
Comme on le verra plus loin, en montant successivement ces ponts, et les équipements associés, sur la sous-structure de la barge, on ajuste le coût des équipements installés sur celle-ci aux besoins réels, tout au long des phases successives de développement et de production d'un champ pétrolier. As will be seen below, by successively mounting these bridges, and the associated equipment, on the barge substructure, the cost of the equipment installed on it is adjusted to actual needs, throughout the successive phases of development and production of an oil field.
Suivant une caractéristique avantageuse de la barge selon l'invention, celle-ci présente, en plan, une forme allongée. Cette forme allongée, analogue à celle d'un navire, autorise la construction de la barge dans des installations existantes de chantiers navals, améliore la stabilité hydrodynamique de la barge pour les directions de houle préférentielles, et permet de ménager dans la sous-structure des compartiments de stockage de produits pétroliers d'une capacité de un à plusieurs millions de barils. According to an advantageous characteristic of the barge according to the invention, it has, in plan, an elongated shape. This elongated shape, analogous to that of a ship, allows the construction of the barge in existing shipyard installations, improves the hydrodynamic stability of the barge for preferential swell directions, and makes it possible to spare in the substructure of the petroleum product storage compartments with a capacity of one to several million barrels.
Suivant l'invention, pour installer une telle barge sur un champ pétrolier en mer, a) on installe sur ce champ la sous-structure équipée d'au moins un pont supportant les équipements utilisés pendant une première phase du développement et de l'exploitation dudit champ et b) à la fin de ladite première phase, on installe sur ladite structure au moins un autre pont supportant des équipements et autres installations utilisés pendant une deuxième phase de développement et de l'exploitation du champ. According to the invention, to install such a barge on an oil field at sea, a) the substructure fitted with at least one bridge supporting the equipment used during a first phase of development and operation is installed on this field of said field and b) at the end of said first phase, at least one other bridge supporting said equipment and other installations used during a second phase of development and operation of the field is installed on said structure.
D'autres caractéristiques et avantages de la présente invention apparaîtront à la lecture de la description qui va suivre et à l'examen du dessin annexé dans lequel
- les figures 1 et 2 sont des vues en élévation et en plan, respectivement, d'un premier mode de réalisation de la barge suivant l'invention,
- la figure 3 est une vue en élévation d'une variante de la barge des figures 1 et 2,
- les figures 4A à 4H illustrent diverses étapes successives d'un mode de mise en oeuvre du procédé d'installation de la plate-forme des figures 1 et 2,
- les figures 5A à 5G illustrent diverses étapes successives d'un autre mode de mise en oeuvre de ce procédé, convenant à l'installation de la plate-forme en vue d'une phase de forage,
- les figures 6A à 6D illustrent diverses étapes successives de la conversion de la plate-forme suivant l'invention, d'une phase de forage à une phase de production, et
- les figures A à 7E illustrent une variante de la conversion illustrée à la figure 6. Other characteristics and advantages of the present invention will appear on reading the description which follows and on examining the appended drawing in which
FIGS. 1 and 2 are views in elevation and in plan, respectively, of a first embodiment of the barge according to the invention,
FIG. 3 is an elevation view of a variant of the barge of FIGS. 1 and 2,
FIGS. 4A to 4H illustrate various successive stages of an embodiment of the method for installing the platform of FIGS. 1 and 2,
FIGS. 5A to 5G illustrate various successive stages of another embodiment of this method, suitable for installing the platform for a drilling phase,
FIGS. 6A to 6D illustrate various successive stages of the conversion of the platform according to the invention, from a drilling phase to a production phase, and
- Figures A to 7E illustrate a variant of the conversion illustrated in Figure 6.
On se réfère aux figures 1 et 2 du dessin annexé où il apparaît que la barge représentée comprend une sousstructure 1 semi-submersible, en béton ou en acier par exemple, constituée d'une embase 2 entièrement immergée et d'une pluralité de colonnes 3i (i de 1 à 8) débordant vers le haut de l'embase 2, jusqu'au-dessus de la surface 4 de l'eau. La barge se distingue de la plate-forme semisubmersible décrite dans la demande de brevet précitée d'abord en ce qu'elle comporte, non pas un pont unique monté sur les colonnes 3i, mais une pluralité de ponts 51,52,53 susceptibles d'être assemblés de manière variable pour constituer, éventuellement avec les faces supérieures des colonnes 3i (voir figure 1), une surface d'exploitation modulable en fonction des besoins, tout au long des diverses phases successives de forage et de production d'un champ pétrolier sous-marin sur lequel la barge est installée. L'intérêt de cette caractéristique de la barge suivant l'invention sera détaillé plus loin, en liaison avec les figures 5A à 7E, lors de la description du procédé d'installation de celle-ci. Referring to Figures 1 and 2 of the accompanying drawing where it appears that the barge shown comprises a semi-submersible substructure 1, concrete or steel for example, consisting of a base 2 fully submerged and a plurality of columns 3i (i from 1 to 8) projecting upwards from the base 2, up to the surface 4 of the water. The barge differs from the semi-submersible platform described in the aforementioned patent application first in that it comprises, not a single bridge mounted on the columns 3i, but a plurality of bridges 51,52,53 capable of '' be assembled in a variable manner to constitute, possibly with the upper faces of the columns 3i (see Figure 1), a modular operating surface according to needs, throughout the various successive phases of drilling and production of a field submarine tanker on which the barge is installed. The advantage of this characteristic of the barge according to the invention will be detailed below, in connection with FIGS. 5A to 7E, during the description of the method for installing the latter.
Les ponts 51,2,53 sont du type "pont-coque" flottable susceptible de glisser le long des colonnes, jusqu'en haut de celles-ci où des moyens de verrouillage (non représentés) fixent les ponts sur ces colonnes, de manière qu'après une séquence de ballastage/déballastage convenable de la sous-structure 1, ces ponts soient fixés chacun sur quatre colonnes au-dessus de la surface 4 de l'eau, avec un franc bord prédéterminé convenable. Une telle séquence est décrite dans la demande de brevet français précitée. Elle sera rappelée plus loin en liaison avec l'examen des figures 4 à 7. The bridges 51, 2, 53 are of the buoyant "hull-bridge" type capable of sliding along the columns, to the top of the latter where locking means (not shown) fix the bridges to these columns, so that after a suitable ballasting / deballasting sequence of the substructure 1, these bridges are each fixed on four columns above the surface 4 of the water, with a suitable predetermined freeboard. Such a sequence is described in the aforementioned French patent application. It will be recalled later in connection with the examination of FIGS. 4 to 7.
Les colonnes 3i sont régulièrement réparties sur la périphérie de l'embase 2, aux extrémités de celle-ci ainsi qu'au tiers et au deux tiers de sa longueur. C'est ainsi que les colonnes 31,32,37 et 38 supportent le pont 51, les colonnes 32,33,36,37 supportent le pont central 52, et les colonnes 33,34,35,36 supportent le pont 53. The columns 3i are regularly distributed over the periphery of the base 2, at the ends of the latter as well as one third and two thirds of its length. This is how the columns 31, 32, 37 and 38 support the bridge 51, the columns 32, 33, 36, 37 support the central bridge 52, and the columns 33, 34, 35, 36 support the bridge 53.
Le pont de la barge suivant l'invention supporte les divers équipements nécessaires lors des phases successives de forage du champ pétrolier de production des produits extraits de celui-ci. Ces équipements sont classiques et comportent ainsi, à titre d'exemple illustratif et non limitatif, un derrick 6 placé audessus d'un groupe 7 de puits s'étendant jusqu'au fond marin, ces équipements étant installés sur le pont 52 central avec les têtes de puits et un système 8 de déchargement de produits pétroliers. The deck of the barge according to the invention supports the various equipment necessary during the successive phases of drilling the oil field for the production of products extracted from it. These pieces of equipment are conventional and thus comprise, by way of non-limiting example, a derrick 6 placed above a group 7 of wells extending to the seabed, these pieces of equipment being installed on the central deck 52 with the well heads and a system 8 for discharging petroleum products.
Le pont 53 peut porter, comme représenté, des moyens utilisés en phase de production : moyens d'injection d'eau, moyens de séparation, etc... ainsi qu'une grue de manutention 9. The bridge 53 can carry, as shown, means used in the production phase: water injection means, separation means, etc., as well as a handling crane 9.
Le pont 51 peut recevoir divers équipements électriques 10, un générateur d'énergie électrique 11, une autre grue de manutention 9', etc... The bridge 51 can receive various electrical equipment 10, an electrical energy generator 11, another handling crane 9 ', etc.
D'autres équipements peuvent être montés sur les colonnes 3i elles-mêmes, par exemple un pont d'atterrissage d'hélicoptère 12, des quartiers d'habitation 13 sur la colonne 38, une aire de stockage sur la colonne 37, une torchère 14 sur la colonne 34, etc., etc... Other equipment can be mounted on the columns 3i themselves, for example a helicopter landing deck 12, living quarters 13 on the column 38, a storage area on the column 37, a flare 14 on column 34, etc., etc.
Tous les équipements cités ci-dessus sont classiques et n'exigent pas une description détaillée. All the equipment mentioned above is conventional and does not require a detailed description.
Des passerelles (non représentées) autorisent la circulation du personnel entre différents équipements portés par les colonnes 3i et les ponts 51,52,53. Footbridges (not shown) allow the movement of personnel between different equipment carried by columns 3i and bridges 51,52,53.
La sous-structure 1 de la barge suivant l'invention, constituée par l'embase 2 et les colonnes 3i, assure la flottaison et le ballastage de la barge, le stockage des produits pétroliers et autres et accueille divers équipements auxiliaires. The substructure 1 of the barge according to the invention, constituted by the base 2 and the columns 3i, ensures the flotation and ballasting of the barge, the storage of petroleum products and the like and accommodates various auxiliary equipment.
Des lignes de mouillage 15j (j de 1 à 12) assurent l'ancrage de la barge sur le fond marin. Mooring lines 15d (d from 1 to 12) anchor the barge on the seabed.
Le stockage des produits pétroliers s'opère suivant le principe du déplacement eau-huile qui est connu dans l'art et notamment utilisé pour les structures de stockage des produits pétroliers sous l'eau, de manière à éliminer le différentiel des pressions hydrostatiques et effectuer ainsi une économie de matériaux. The storage of petroleum products operates according to the principle of water-oil displacement which is known in the art and in particular used for structures for the storage of petroleum products under water, so as to eliminate the differential in hydrostatic pressures and perform thus saving materials.
La flottaison de la barge est assurée par des compartiments de flottabilité (non représentés) remplis d'air, distribués dans les diverses colonnes 3i. Ces colonnes peuvent accueillir aussi des compartiments de ballastage (non représentés) chargés en eau de mer. Ceci permet d'assurer notamment, en coopération avec des pompes et systèmes de commande appropriés, le ballastage "dynamique" de la barge, de manière à maintenir le francbord du pont à une valeur prédéterminée quand les quantités d'eau et de produits pétroliers contenues dans l'embase varient, afin de prendre en compte la différence de densité des liquides stockés. The flotation of the barge is ensured by buoyancy compartments (not shown) filled with air, distributed in the various columns 3i. These columns can also accommodate ballast compartments (not shown) loaded with seawater. This makes it possible, in particular, in cooperation with appropriate pumps and control systems, to ensure "dynamic" ballasting of the barge, so as to maintain the freeboard of the deck at a predetermined value when the quantities of water and petroleum products contained in the base vary, in order to take into account the difference in density of the liquids stored.
Les colonnes 3i peuvent accueillir également, dans des compartiments particuliers, une partie de la production de la barge. Cependant, cette production est stockée, pour l'essentiel, dans l'embase 2. On comprend que celle-ci peut atteindre un très grand volume propre à stocker de grandes quantités de produits pétroliers, un ou deux millions de barils ou plus par exemple, ceci en conformité avec l'un des buts de la présente invention. Columns 3i can also accommodate, in special compartments, part of the production of the barge. However, this production is stored, essentially, in the base 2. It is understood that this can reach a very large volume suitable for storing large quantities of petroleum products, one or two million barrels or more for example , this in accordance with one of the aims of the present invention.
De surcroît, cette grande quantité de produits pétroliers peut être stockée à une profondeur assez importante pour une structure flottante, à 40 m ou plus par exemple, ce qui est très favorable à la stabilité de la barge. In addition, this large quantity of petroleum products can be stored at a sufficient depth for a floating structure, at 40 m or more for example, which is very favorable to the stability of the barge.
A cet égard, la vue en plan de la figure 2 fait apparaître que la barge suivant l'invention présente une forme rectangulaire allongée, grâce à l'agencement en ligne des ponts 51,52,3 A titre d'exemple illustratif et non limitatif, la barge peut présenter une longueur de 250 m et une largeur de 60 m, avec un tirant d'eau de l'ordre de 40 m. Il est alors possible d'orienter l'axe longitudinal de la barge parallèlement à la direction préférentielle de la houle, la forme allongée de la barge donnant à celle-ci des caractéristiques de comportement hydrodynamique très supérieures à celles d'une plateforme de plan carré ou circulaire par exemple, ceci conformément à un autre but de la présente invention. In this respect, the plan view of FIG. 2 shows that the barge according to the invention has an elongated rectangular shape, by virtue of the on-line arrangement of the bridges 51,52,3 By way of illustrative and nonlimiting example , the barge can have a length of 250 m and a width of 60 m, with a draft of around 40 m. It is then possible to orient the longitudinal axis of the barge parallel to the preferential direction of the swell, the elongated shape of the barge giving it characteristics of hydrodynamic behavior much superior to those of a platform with a square plane. or circular for example, this in accordance with another object of the present invention.
On remarquera en outre que la forme allongée de la barge suivant l'invention permet de construire celle-ci dans des bassins existants conçus pour des navires classiques de même forme allongée, contrairement à une plate-forme carrée ou circulaire de grande capacité dont l'encombrement dépasserait alors la largeur du bassin, ceci conformément à encore un autre but de l'invention. It will also be noted that the elongated shape of the barge according to the invention makes it possible to build it in existing basins designed for conventional ships of the same elongated shape, unlike a square or circular platform of large capacity whose space would then exceed the width of the basin, this in accordance with yet another object of the invention.
Bien entendu, l'invention n' est pas limitée à une barge comportant trois ponts. Elle pourrait, en fonction des besoins d'un champ pétrolier particulier, comporter un nombre différent de ponts, agencés en une ou plusieurs lignes parallèles. C'est ainsi que la figure 3 représente un autre mode de réalisation de la présente invention, comportant deux ponts flottables 5'1,5'2 seulement, montés sur une structure 1' à embase 2' et six colonnes 3'1 à 3'6 Ici encore, comme on le verra plus loin, des équipements utilisés en phase de forage sont avantageusement réunis sur un pont et des équipements de production sur un autre. Ces équipements sont par ailleurs classiques et sont référencés sur la figure 3 comme les équipements du même type portés par la barge de la figure 1. On remarquera cependant qu'il est possible alors de faire passer le groupe de puits 7 dans une colonne 3'2 de la sous-structure 1', ceci pour réduire les efforts d'environnement sur les puits. Of course, the invention is not limited to a barge comprising three bridges. It could, depending on the needs of a particular oil field, include a different number of bridges, arranged in one or more parallel lines. Thus, FIG. 3 represents another embodiment of the present invention, comprising two buoyant bridges only 5'1.5'2, mounted on a structure 1 'with base 2' and six columns 3'1 to 3 Here again, as will be seen below, equipment used during the drilling phase is advantageously combined on one bridge and production equipment on another. This equipment is moreover conventional and is referenced in FIG. 3 as the equipment of the same type carried by the barge of FIG. 1. It will however be noted that it is then possible to pass the group of wells 7 into a column 3 ' 2 of the substructure 1 ′, this to reduce the environmental stresses on the wells.
On se réfère maintenant aux figures 4A à 4G du dessin annexé pour décrire un mode de mise en oeuvre du procédé d'installation de la barge suivant l'invention. Reference is now made to FIGS. 4A to 4G of the appended drawing to describe an embodiment of the method for installing the barge according to the invention.
Celui-ci est analogue au procédé d'installation de la plate-forme décrite dans la demande de brevet français précitée, à laquelle on pourra se reporter pour plus de détails.This is analogous to the method of installing the platform described in the aforementioned French patent application, to which reference may be made for more details.
Après construction de la sous-structure 1 dans un bassin à sec (figure 4A), celui-ci est mis en eau et l'embase est remorquée (figure 4B) jusqu'à un site ou on la charge avec les ponts 51, 52, 53, déchargés sur l'embase 2 par ripage, à partir de barges de transport telles que celle référencée 20 à la figure 4C. After construction of the substructure 1 in a dry basin (FIG. 4A), it is put in water and the base is towed (FIG. 4B) to a site where it is loaded with the bridges 51, 52 , 53, unloaded on the base 2 by shifting, from transport barges such as that referenced 20 in FIG. 4C.
Les ponts 51, 52, 53 reposant ainsi sur l'embase (figure 4D), on remorque la barge jusqu'à son site final d'installation (figure 4E). Un ballastage de la sousstructure fait alors descendre celle-ci dans l'eau tandis que les ponts, grâce à leur flottabilité, restent à la surface de l'eau, les colonnes 3i de la sous-structure glissant le long des ponts 51r52r53 grâce à des moyens de guidage latéral (non représentés) tels que ceux décrits dans la demande de brevet français précitée. Cette dernière décrit aussi des moyens de verrouillage propres à fixer temporairement les ponts en haut des colonnes, dans la position représentée à la figure 4F. On procède alors en tant que besoin au levage et à l'installation des équipements et autres installations complémentaires sur les ponts aménagés. La sous-structure est ensuite déballastée pour relever les ponts 51,52,53 au-dessus de la surface de l'eau (figure 4G) avec un franc-bord prédéterminé. The bridges 51, 52, 53 thus resting on the base (FIG. 4D), the barge is towed to its final installation site (FIG. 4E). Ballasting of the substructure then makes it descend into the water while the bridges, thanks to their buoyancy, remain on the surface of the water, the columns 3i of the substructure sliding along the bridges 51r52r53 thanks to lateral guide means (not shown) such as those described in the aforementioned French patent application. The latter also describes specific locking means for temporarily fixing the bridges at the top of the columns, in the position shown in FIG. 4F. We then proceed as necessary to the lifting and installation of equipment and other additional installations on the fitted bridges. The substructure is then deballasted to raise the bridges 51, 52, 53 above the surface of the water (FIG. 4G) with a predetermined freeboard.
Selon un autre mode de réalisation, on procède à l'installation des ponts et d'autres équipements dans un site abrité et on remorque la barge complètement équipée jusqu'à son site final d'exploitation. According to another embodiment, the bridges and other equipment are installed in a sheltered site and the fully equipped barge is towed to its final operating site.
Après la pose des lignes de mouillage, on procède au forage des puits du groupe 7 (figure 4H). Les équipements installés sur le pont 53 et destinés à la phase de production seulement sont partiellement utilisés, certains restant inactifs jusqu'à la fin de la phase de forage. After laying the mooring lines, the wells of group 7 are drilled (Figure 4H). The equipment installed on deck 53 and intended for the production phase only is partially used, some remaining inactive until the end of the drilling phase.
On conçoit que l'immobilisation du capital nécessaire à la réalisation de ces équipements de production inactifs, pendant toute la durée de la phase de forage, est désavantageuse du point de vue économique. It is understood that the immobilization of the capital necessary for the production of this inactive production equipment, throughout the duration of the drilling phase, is disadvantageous from the economic point of view.
De plus, les temps d'approvisionnement de ces équipements retardent la mise en fonctionnement de la plate-forme.In addition, the supply times for this equipment delay the start-up of the platform.
Suivant une mise en oeuvre du procédé d'installation de la barge selon la présente invention, que l'on va décrire en liaison avec l'examen des figures 5A à 7E, on supprime cet inconvénient en étalant dans le temps l'installation des divers ponts sur leur site final. According to an implementation of the method of installing the barge according to the present invention, which will be described in connection with the examination of FIGS. 5A to 7E, this drawback is eliminated by spreading out over time the installation of the various bridges on their final site.
Les figures 5A à 5G, qui correspondent sensiblement aux figures 4A à 4G , illustrent la construction et l'installation d'une barge équipée du seul pont 52 portant les matériels nécessaires dans la phase de forage par laquelle débute le développement et l'exploitation du champ pétrolier situé sur ce site final. FIGS. 5A to 5G, which correspond substantially to FIGS. 4A to 4G, illustrate the construction and installation of a barge equipped with the only bridge 52 carrying the materials necessary in the drilling phase by which the development and operation of the oil field located on this final site.
C'est seulement après le forage des puits qui, éventuellement, peut se faire depuis plusieurs positions sur le champ pétrolier, que la barge reçoit les ponts 51 et 53, sur le site final où elle est installée. Deux procédures alternatives, illustrées respectivement aux figures 6A à 6D et aux figures 7A à 7E sont utilisables, suivant la présente invention, pour monter et fixer les ponts 51 et 53 sur la barge. It is only after the drilling of the wells which, possibly, can be done from several positions on the oil field, that the barge receives the bridges 51 and 53, on the final site where it is installed. Two alternative procedures, illustrated respectively in FIGS. 6A to 6D and in FIGS. 7A to 7E can be used, according to the present invention, for mounting and fixing the bridges 51 and 53 on the barge.
Suivant la procédure représentée aux figures 6A à 6D, celle-ci consiste à reballaster la barge pour ramener le haut des colonnes prés de la surface 4 de l'eau. Deux barges de transport telles que celles référencées 21 à la figure 6A apportent les ponts 51 et 53 contre la barge. According to the procedure shown in FIGS. 6A to 6D, this consists in reballasting the barge to bring the top of the columns close to the surface 4 of the water. Two transport barges such as those referenced 21 in FIG. 6A bring the bridges 51 and 53 against the barge.
Ces barges de transport sont alors engagées entre les colonnes destinées à supporter les ponts. Les barges 21 sont ballastées, ce qui permet de poser les ponts sur les colonnes (figure 6B) . La barge 1 est déballastée pour reprendre la charge des ponts et pour relever l'ensemble des ponts au-dessus de l'eau, avec un franc bord prédéterminé (figure 6C) . Les lignes d'ancrage et les puits de forage, qui avaient été déconnectés avant l'étape illustrée la figure 6A, sont alors reconnectés à la barge.These transport barges are then engaged between the columns intended to support the bridges. The barges 21 are ballasted, which makes it possible to place the bridges on the columns (FIG. 6B). The barge 1 is deballasted to take up the load on the bridges and to raise all of the bridges above the water, with a predetermined freeboard (FIG. 6C). The anchor lines and the wells, which had been disconnected before the step illustrated in FIG. 6A, are then reconnected to the barge.
Suivant la procédure alternative décrite aux figures 7A à 7E, la barge portant le pont 52 est déballastée de manière à amener la surface supérieure de l'embase 2 de la sous-structure 1 au voisinage de la surface 4 de l'eau, à un niveau permettant de transférer par ripage les ponts 51,53 sur cette surface supérieure à partir de barges, telles que la barge de transport 21, amenées à proximité de cette surface (figure 7A). According to the alternative procedure described in FIGS. 7A to 7E, the barge carrying the bridge 52 is deballasted so as to bring the upper surface of the base 2 of the substructure 1 in the vicinity of the surface 4 of the water, to a level making it possible to transfer by bridging the bridges 51, 53 to this upper surface from barges, such as the transport barge 21, brought near this surface (FIG. 7A).
La sous-structure est alors reballastée pour mettre les ponts 51,53 en flottaison (figure 7B), ceux-ci remontant ensuite progressivement au niveau du pont 52 pendant la descente de la sous-structure 1 (figure 7C). The substructure is then reballasted to put the bridges 51, 53 in waterline (FIG. 7B), these then progressively rise to the level of the bridge 52 during the descent of the substructure 1 (FIG. 7C).
Les moyens de verrouillage des ponts 51, 53 sont alors actionnés, pour les fixer sur leurs colonnes 3i respectives, au même niveau.The locking means of the bridges 51, 53 are then actuated, to fix them on their respective columns 3i, at the same level.
La sous-structure 1 est ensuite déballastée pour remonter l'ensemble des ponts au-dessus de la surface de l'eau, avec un franc bord prédéterminé (figure 7D). Les lignes d'ancrage 15j et les puits du groupe 7 sont ensuite reconnectés (figure 7E). The substructure 1 is then deballasted to raise all of the bridges above the surface of the water, with a predetermined freeboard (FIG. 7D). The anchor lines 15j and the wells of group 7 are then reconnected (Figure 7E).
Quelle que soit la procédure employée pour monter séparément les ponts 51,53 sur la sous-structure, on comprend que ces ponts peuvent être livrés après la phase de forage. Leur construction peut donc être retardée par rapport à celle des ponts installés suivant la procédure illustrée par les figures 4A à 4H, procédure qui exige que les trois ponts soient disponibles avant même le début de la phase de forage. Les investissements ainsi retardés assurent aux procédures décrites en liaison avec les figures 5A à 7E un avantage économique important. Whatever the procedure used to separately mount the bridges 51,53 on the substructure, it is understood that these bridges can be delivered after the drilling phase. Their construction can therefore be delayed compared to that of the bridges installed according to the procedure illustrated in FIGS. 4A to 4H, a procedure which requires that the three bridges be available even before the start of the drilling phase. The investments thus delayed provide the procedures described in connection with FIGS. 5A to 7E with a significant economic advantage.
Bien entendu, l'invention n'est pas limitée aux procédés d'installation décrits ci-dessus qui ne sont donnés qu'à titre d'exemple. La flexibilité de l'invention permet l'installation des équipements suivant les utilisations les plus diverses dans un ordre qui correspond au mieux aux besoins des utilisateurs. En particulier, il est parfaitement possible d'utiliser la solution des ponts interchangeables, suivant laquelle on remplace, par exemple, un pont de production par un autre équipé différemment. Of course, the invention is not limited to the installation methods described above which are given only by way of example. The flexibility of the invention allows the installation of the equipment according to the most diverse uses in an order which best corresponds to the needs of the users. In particular, it is perfectly possible to use the solution of interchangeable bridges, according to which one replaces, for example, a production bridge by another differently equipped.
Claims (14)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
FR9801765A FR2774967B1 (en) | 1998-02-13 | 1998-02-13 | BARGE FOR THE DEVELOPMENT AND EXPLOITATION OF AN OIL FIELD AT SEA AND ITS INSTALLATION METHOD |
OA9900032A OA11103A (en) | 1998-02-13 | 1999-02-12 | Barge for the development and exploitation of an oilfield em mer and its installation process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
FR9801765A FR2774967B1 (en) | 1998-02-13 | 1998-02-13 | BARGE FOR THE DEVELOPMENT AND EXPLOITATION OF AN OIL FIELD AT SEA AND ITS INSTALLATION METHOD |
Publications (2)
Publication Number | Publication Date |
---|---|
FR2774967A1 true FR2774967A1 (en) | 1999-08-20 |
FR2774967B1 FR2774967B1 (en) | 2000-04-28 |
Family
ID=9522953
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
FR9801765A Expired - Fee Related FR2774967B1 (en) | 1998-02-13 | 1998-02-13 | BARGE FOR THE DEVELOPMENT AND EXPLOITATION OF AN OIL FIELD AT SEA AND ITS INSTALLATION METHOD |
Country Status (2)
Country | Link |
---|---|
FR (1) | FR2774967B1 (en) |
OA (1) | OA11103A (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3507238A (en) * | 1968-03-26 | 1970-04-21 | Santa Fe Int Corp | Semisubmersible oil storage vessel |
GB1527759A (en) * | 1975-12-11 | 1978-10-11 | Mitsui Shipbuilding Eng | Semi-submersible structures and method of manufacture thereof |
US4167148A (en) * | 1976-09-13 | 1979-09-11 | Fayren Jose M | Floating apparatus and method of assembling the same |
EP0832817A2 (en) * | 1996-09-27 | 1998-04-01 | Deep Oil Technology, Incorporated | Shallow draft floating offshore drilling/producing structures |
-
1998
- 1998-02-13 FR FR9801765A patent/FR2774967B1/en not_active Expired - Fee Related
-
1999
- 1999-02-12 OA OA9900032A patent/OA11103A/en unknown
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3507238A (en) * | 1968-03-26 | 1970-04-21 | Santa Fe Int Corp | Semisubmersible oil storage vessel |
GB1527759A (en) * | 1975-12-11 | 1978-10-11 | Mitsui Shipbuilding Eng | Semi-submersible structures and method of manufacture thereof |
US4167148A (en) * | 1976-09-13 | 1979-09-11 | Fayren Jose M | Floating apparatus and method of assembling the same |
EP0832817A2 (en) * | 1996-09-27 | 1998-04-01 | Deep Oil Technology, Incorporated | Shallow draft floating offshore drilling/producing structures |
Also Published As
Publication number | Publication date |
---|---|
OA11103A (en) | 2003-03-17 |
FR2774967B1 (en) | 2000-04-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3717343B1 (en) | Floating support structure for offshore wind turbine and method for installing a wind turbine provided with such a support structure | |
EP1716293B1 (en) | Method and Device for dismanteling an oil platform | |
CA1305370C (en) | Modular system for the production, storage and loading of hydrocarbons at sea | |
US7281881B1 (en) | Column-stabilized platform with water-entrapment plate | |
AU701557B2 (en) | Offshore apparatus and method for oil operations | |
EP2454149B1 (en) | Catamaran ship used for assembling, transporting and installing a marine wind turbine on the seafloor | |
RU2141427C1 (en) | Low-draft floating drilling and oil production off-shore platform (versions) | |
FR2772336A1 (en) | SEMI-SUBMERSIBLE PLATFORM FOR OPERATING AN OIL FIELD AT SEA AND METHOD FOR INSTALLING SUCH A PLATFORM | |
RU2145289C1 (en) | Method and system of mooring tank ship | |
EP3322635B1 (en) | Floating production unit and method of installing a floating production unit | |
WO2002092425A1 (en) | Floating multipurpose platform structure and method for constructing same | |
EP3286069B1 (en) | Floating mounting having a depth-variable horizontal cross-section | |
FR2540065A1 (en) | Floating and ballasted structure, held in its place in the open sea | |
FR2525176A1 (en) | HALF-IMMEREDE SEA DRILLING STRUCTURE | |
FR2774967A1 (en) | Barge for the development and exploitation of an oilfield at sea | |
GB2301800A (en) | Buoyant Platform | |
FR2576577A1 (en) | Semi-submersible platform for deep-water oil production, storage and loading | |
FR2833922A1 (en) | Mounting heavy equipment onto floating vessel hull comprises fixing lifting units designed to work from seabed to ends of hanging equipment | |
EP0963906B1 (en) | Method for the installation of a gravity, self-elevating oil production platform at sea | |
FR2581362A1 (en) | Semi-submersible platform, in particular for exploration and/or working underwater deposits in cold seas | |
FR2645827A1 (en) | Marine platform formed of a plurality of modular elements for storing products and for direct anchoring and loading of ships, and method for installing, dismantling and reinstalling this platform at another location | |
EP0097069B1 (en) | Method for the installation of a platform in the sea, platform superstructure for carrying out this method | |
WO2024121687A1 (en) | Floating intervention vessel for temporarily docking on an offshore wind turbine platform and associated intervention assembly and system | |
FR2859698A1 (en) | Floating unit e.g. platform, mooring device for use in offshore oil industry, has set of connection points maintained at equal depth under water surface and connected under water to anchors by mooring lines | |
WO2024184604A1 (en) | Counterweight for semi-submersible float of offshore wind turbine and installation method therefor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PLFP | Fee payment |
Year of fee payment: 19 |
|
ST | Notification of lapse |
Effective date: 20171031 |