FR2675829A3 - Method for implementing pillars, the foundations for which have been laid in the ground in advance - Google Patents

Method for implementing pillars, the foundations for which have been laid in the ground in advance Download PDF

Info

Publication number
FR2675829A3
FR2675829A3 FR9205109A FR9205109A FR2675829A3 FR 2675829 A3 FR2675829 A3 FR 2675829A3 FR 9205109 A FR9205109 A FR 9205109A FR 9205109 A FR9205109 A FR 9205109A FR 2675829 A3 FR2675829 A3 FR 2675829A3
Authority
FR
France
Prior art keywords
concrete
column
ground
concreting
steel fibers
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
FR9205109A
Other languages
French (fr)
Other versions
FR2675829B3 (en
Inventor
Le Clercq Pierre
Lamotte Serge
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of FR2675829A3 publication Critical patent/FR2675829A3/en
Application granted granted Critical
Publication of FR2675829B3 publication Critical patent/FR2675829B3/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention relates to a method for laying foundations consisting of the installation of pillars placed in wells dug in the ground and anchored into concrete plinths. In accordance with the invention, a concrete filled with steel fibres is used around the lower part of the pillar in order to take up the very high loads transmitted by the reduced cross section of the pillar to the huge cross section of the foundation concrete.

Description

DESCRIPTION
Procédé de mise en oeuvre de colonnes fondées à l'avance
dans le terrain
La présente invention a pour objet un procédé de fondation qui permet de réaliser des fondations locales profondes en béton complétées à la partie supérieure par des colonnes préfabriquées, généralement en acier, qui constitueront les colonnes des sous-sols de l'ouvrage à construire sur ces fondations.
DESCRIPTION
Method for implementing columns based in advance
in the field
The subject of the present invention is a foundation process which makes it possible to produce deep local foundations in concrete supplemented at the top by prefabricated columns, generally of steel, which will constitute the columns of the basements of the structure to be built on these foundations.

Le brevet belge n0690.843 décrit un procédé de construction simultanée des étages et des sous-sols d'un bâtiment construit sur de telles colonnes préfondées dans des puits creusés dans le sol. Belgian patent n0690.843 describes a process for the simultaneous construction of the floors and basements of a building constructed on such prefabricated columns in wells dug in the ground.

Dans l'état actuel de cette technique, le béton qui entoure la partie inférieure de la colonne est renforcé par des armatures de frettage. In the current state of this technique, the concrete which surrounds the lower part of the column is reinforced by hoop reinforcements.

La mise en place de ces armatures est une opération longue et coûteuse. The installation of these frames is a long and expensive operation.

La présente invention supprime cette armature de frettage qui est remplacée par la mise en oeuvre d'un béton chargé de fibres en acier de petit diamètre et de faible longueur. Ces fibres en acier vont fretter le béton en augmentant considérablement la résistance du béton à la traction et donc à l'éclatement sous l'effet des charges verticales transmises par la section réduite de la colonne à la masse du béton fretté. The present invention eliminates this hooping reinforcement which is replaced by the use of concrete loaded with steel fibers of small diameter and short length. These steel fibers will hoop the concrete considerably increasing the concrete tensile strength and therefore the bursting under the effect of vertical loads transmitted by the reduced section of the column to the mass of hooped concrete.

Les figures 1 et 2 montrent la disposition correspondant à l'état actuel de la technique. La figure 1 est une coupe verticale dans le terrain La figure 2 est une coupe horizontale.  Figures 1 and 2 show the arrangement corresponding to the current state of the art. Figure 1 is a vertical section through the ground Figure 2 is a horizontal section.

Depuis le niveau du sol 1, un puits 2 est excavé dans le terrain, à l'aide d'une machine adéquate, généralement sous boue de bentonite 3. From ground level 1, a well 2 is excavated in the ground, using a suitable machine, generally under bentonite mud 3.

Une colonne 4 métallique ou en béton préfabriqué comporte des dispositifs d'adhérence 5 à sa partie inférieure. A metal or precast concrete column 4 has adhesion devices 5 at its lower part.

Une armature de frettage 6 est fixée à la partie inférieure de la colonne 4 avant son introduction dans le puits 2. A hooping reinforcement 6 is fixed to the lower part of the column 4 before its introduction into the well 2.

Pour réaliser cette opération, la colonne 4 est suspendue verticalement par une grue au-dessus du puits 2 permettant de souder la partie supérieure de l'armature de frettage 6 à la partie inférieure de la colonne. To carry out this operation, the column 4 is suspended vertically by a crane above the well 2 making it possible to weld the upper part of the hooping frame 6 to the lower part of the column.

La colonne 4 comporte une tête de colonne 7 qui est boulonnée à la partie supérieure de la colonne. Column 4 has a column head 7 which is bolted to the top of the column.

Cette tête de colonne est descendue sur un châssis de positionnement 8 posé au-dessus du puits. This column head is lowered onto a positioning frame 8 placed above the well.

La colonne 4 est ensuite réglée dans les trois directions à l'aide de vérins hydrauliques ou mécaniques fixés sur le châssis 8. Column 4 is then adjusted in three directions using hydraulic or mechanical jacks fixed to the chassis 8.

On introduit ensuite un ou deux tubes de bétonnage 9 comportant des éléments d'environ 3 mètres de long assemblés entre eux pour constituer un tube de bétonnage généralement de plusieurs dizaines de mètres de longueur. One or two concreting tubes 9 are then introduced, comprising elements about 3 meters long assembled together to form a concreting tube generally of several tens of meters in length.

Un entonnoir 10 est fixé à la partie supérieure de ce tube de bétonnage. A funnel 10 is fixed to the upper part of this concreting tube.

Du béton 11 est déversé dans ltentonnoir 10 et descend dans le fond du puits en refoulant la boue de bentonite 3 qui est récupérée. Concrete 11 is poured into the funnel 10 and descends into the bottom of the well by pushing back the bentonite mud 3 which is recovered.

Au fur et à mesure de ce bétonnage, les tubes de bétonnage sont remontés de manière à pénétrer dans la masse de béton frais de 2 m à 3 m environ. As this concreting progresses, the concreting tubes are reassembled so as to penetrate the mass of fresh concrete from 2 m to 3 m approximately.

Le bétonnage est ainsi effectué jusqu'au niveau 12 supérieur au niveau des armatures de frettage 6.  Concreting is thus carried out up to level 12 higher than the level of the hooping reinforcements 6.

La partie supérieure du puits est remplia ensuite d'un matériau non cohérent 13, généralement du gravier, pour s'opposer au flambage de la colonne métallique 4 lors de sa mise en charge. The upper part of the well is then filled with a non-coherent material 13, generally gravel, to oppose the buckling of the metal column 4 when it is loaded.

Les figures 3 et 4 montrent le procédé de fondation faisant l'objet de l'invention. La figure 3 est une coupe verticale dans le terrain. La figure 4 est une coupe horizontale. Figures 3 and 4 show the foundation process which is the subject of the invention. Figure 3 is a vertical section through the ground. Figure 4 is a horizontal section.

Depuis le niveau du sol 1, un puits 2 est excavé dans le terrain, à l'aide d'une machine adéquate, généralement sous boue de bentonite 3. From ground level 1, a well 2 is excavated in the ground, using a suitable machine, generally under bentonite mud 3.

Une colonne 4 métallique ou en béton préfabriqué comporte des dispositifs d'adhérence 5 à sa partie inférieure. A metal or precast concrete column 4 has adhesion devices 5 at its lower part.

Du béton normal 14 est mis en oeuvre sous boue de bentonite à l'aide d'un ou deux tubes de bétonnage 9 complété par un entonnoir 10 en refoulant la boue de bentonite 3. Normal concrete 14 is used under bentonite mud using one or two concreting tubes 9 completed by a funnel 10 by pumping out the bentonite mud 3.

Ce bétonnage est effectué jusqu'à un niveau 15 situé plus bas que le niveau inférieur de la colonne 4. This concreting is carried out up to a level 15 located lower than the lower level of column 4.

On mélange ensuite des fibres en acier au béton de manière appropriée pour s'assurer que la répartition de ces fibres se fait bien de façon homogène dans le béton. Steel fibers are then mixed with the concrete appropriately to ensure that the distribution of these fibers takes place evenly in the concrete.

Ce béton 16 chargé de fibres en acier est ensuite déversé dans le tube 9 au travers de l'entonnoir 10 de manière à atteindre un niveau supérieur 17 correspondant au niveau 12 de la figure 1. This concrete 16 loaded with steel fibers is then poured into the tube 9 through the funnel 10 so as to reach a higher level 17 corresponding to the level 12 of FIG. 1.

La colonne 4 avec sa te te de positionnement 7 est suspendue verticalement à la grue et introduite verticalement en position correcte dans le béton frais 16 chargé de fibres d'acier. The column 4 with its positioning head 7 is suspended vertically from the crane and introduced vertically in the correct position into the fresh concrete 16 loaded with steel fibers.

Elle pénètre aisément dans le béton frais par suite de l'absence d'armatures de frettage qui, si elles étaient fixées à la colonne, empecheraient la pénétration de la colonne dans le béton frais.  It easily penetrates into fresh concrete due to the absence of hooping reinforcements which, if they were fixed to the column, would prevent the column from penetrating into fresh concrete.

La te te de positionnement 7 est posée exactement à l'emplacement prévu du châssis de positionnement 8 qui a été réglé à l'avance en fonction des coordonnées précises horizontales et en altitude de la colonne 4. The positioning head 7 is placed exactly at the intended location of the positioning frame 8 which has been adjusted in advance as a function of the precise horizontal and altitude coordinates of column 4.

Après durcissement du béton, le matériau de remplissage non cohérent 13 est déversé dans la partie supérieure du puits 2. After the concrete has hardened, the non-coherent filling material 13 is poured into the upper part of the well 2.

Dans la présente invention on peut également placer la colonne 4 avant le bétonnage. In the present invention, it is also possible to place column 4 before concreting.

On peut également réaliser le béton 14 avec adjonction de fibres au meme dosage que le béton 16 ou avec un dosage inférieur. Concrete 14 can also be produced with the addition of fibers at the same dosage as concrete 16 or with a lower dosage.

A titre d'exemple, un béton normal peut avoir la compositition suivante 3
- ciment HK40 : 350 kg/m
- sable 0/5 : 840 kg/m3 3
- gravier : 930 kg/m3
- eau : 200 ka/m3
2.320 kg/m3
Un béton chargé de fibres est identique au précédent sauf qu'il comporte en plus une charge de 20 à 45 3 kg en poids de fibre d'acier par m de béton et qu'on y ajoute un fluidifiant a raison d'environ 4 kg par m de béton.
As an example, normal concrete can have the following composition 3
- HK40 cement: 350 kg / m
- sand 0/5: 840 kg / m3 3
- gravel: 930 kg / m3
- water: 200 ka / m3
2.320 kg / m3
A fiber-reinforced concrete is identical to the previous one except that it additionally contains a load of 20 to 45 3 kg by weight of steel fiber per m of concrete and that a plasticizer is added at the rate of approximately 4 kg per m of concrete.

Les fibres utilisées sont de type classique dans ce genre d'application.  The fibers used are of conventional type in this kind of application.

Claims (6)

REVENDICATIONS 1. Procédé de fondation consistant dans la mise en place de colonnes posées dans des puits creusés dans le sol et ancrées dans des socles en béton, souvent sous boue de bentonite, caractérisé en ce que du béton chargé de fibres d'acier est mis en oeuvre autour de la partie inférieure de la colonne pour reprendre les efforts très élevés transmis par la section réduite de la colonne à la section massive du béton. 1. Foundation process consisting in the installation of columns placed in wells dug in the ground and anchored in concrete bases, often under bentonite mud, characterized in that concrete loaded with steel fibers is put in works around the lower part of the column to take up the very high forces transmitted by the reduced section of the column to the massive section of the concrete. 2. Procédé suivant la revendication 1, caractérisé en ce que la colonne est mise en place après la mise en oeuvre du béton chargé de fibres en acier. 2. Method according to claim 1, characterized in that the column is put in place after the implementation of the concrete loaded with steel fibers. 3. Procédé suivant la revendication 1, caractérisé en ce que la colonne est mise en place avant le bétonnage. 3. Method according to claim 1, characterized in that the column is put in place before concreting. 4. Procédé suivant l'une quelconque des revendications I à 3, caractérisé en ce que le béton de fibres peut avoir des dosages en fibres différents suivant la profondeur. 4. Method according to any one of claims I to 3, characterized in that the fiber concrete can have different fiber dosages depending on the depth. 5. Procédé suivant l'une quelconque des revendications I à 3, caractérisé en ce que la mise en oeuvre du béton comprend une première phase au cours de laquelle un beton normal est versé jusqu'à un niveau situé plus bas que le niveau inférieur de la colonne puis une deuxième phase au cours de laquelle un béton chargé de fibres en acier est versé de manière à atteindre un niveau de bétonnage classique. 5. Method according to any one of claims I to 3, characterized in that the implementation of the concrete comprises a first phase during which a normal concrete is poured up to a level located lower than the lower level of the column then a second phase during which a concrete loaded with steel fibers is poured so as to reach a standard level of concreting. 6. Procédé suivant l'une quelconque des revendications 1 à 5 caractérisé en ce que la partie inférieure de la colonne comporte des dispositifs d'adhérence.  6. Method according to any one of claims 1 to 5 characterized in that the lower part of the column comprises adhesion devices.
FR9205109A 1991-04-26 1992-04-24 METHOD OF IMPLEMENTING COLUMNS ADVANCED IN THE FIELD. Expired - Fee Related FR2675829B3 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
BE9100389A BE1004735A5 (en) 1991-04-26 1991-04-26 Process for implementation of columns based in advance in the field.

Publications (2)

Publication Number Publication Date
FR2675829A3 true FR2675829A3 (en) 1992-10-30
FR2675829B3 FR2675829B3 (en) 1993-04-09

Family

ID=3885464

Family Applications (1)

Application Number Title Priority Date Filing Date
FR9205109A Expired - Fee Related FR2675829B3 (en) 1991-04-26 1992-04-24 METHOD OF IMPLEMENTING COLUMNS ADVANCED IN THE FIELD.

Country Status (2)

Country Link
BE (1) BE1004735A5 (en)
FR (1) FR2675829B3 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116290059A (en) * 2023-01-04 2023-06-23 江苏海洋大学 Prefabricated ultra-high performance concrete spiral pile cap and construction process

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH428148A (en) * 1965-12-07 1967-01-15 Clercq Pierre Le Method of constructing a building structure executed simultaneously in the basement and above the ground
DE3416679A1 (en) * 1984-05-05 1985-11-14 Gkn Keller Gmbh, 6050 Offenbach Method and apparatus for producing foundations by embedding precast members, in particular pillars, in the end base
DE3827703A1 (en) * 1988-08-16 1990-02-22 Bilfinger Berger Bau Supporting elements for forming foundation bodies

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116290059A (en) * 2023-01-04 2023-06-23 江苏海洋大学 Prefabricated ultra-high performance concrete spiral pile cap and construction process
CN116290059B (en) * 2023-01-04 2023-09-08 江苏海洋大学 Prefabricated ultra-high performance concrete spiral pile cap and construction process

Also Published As

Publication number Publication date
FR2675829B3 (en) 1993-04-09
BE1004735A5 (en) 1993-01-19

Similar Documents

Publication Publication Date Title
US4832535A (en) Process for compaction-reinforcement-grouting or for decompaction-drainage and for construction of linear works and plane works in the soils
CN108842791B (en) Detachable load pile anchor multistage supporting structure and construction method
US2555359A (en) Pile structure and method of making same
CN106968139A (en) The construction method of railway bed supporting in undercrossing tunnel jacking framed bridge jack-in process
CN112523215A (en) Multi-equipment efficient construction method for carrier pile
CN114215042A (en) Miniature steel pipe pile for reinforcing foundation and construction method thereof
US7025537B2 (en) Subterranean structures and methods for constructing subterranean structures
CN112681291A (en) Novel pile foundation and construction method thereof
CN210766754U (en) Recoverable prestressed anchorage cable stock supporting construction
CN111441343A (en) Mountain photovoltaic support micropore cast-in-place pile foundation system, construction method and application
CN114215090A (en) Construction method of raft and compression pile in closed space
BE1004735A5 (en) Process for implementation of columns based in advance in the field.
US6062770A (en) Method for underpinning buildings
JPH08296243A (en) Construction method for underground structure by precast concrete central pillar
CN104131562A (en) Pile-forming construction equipment for composite foundation piles
CN107059872B (en) Inclined cable pile pulling method and inclined cable pile pulling system
US11293407B1 (en) Circular can-shape foundation and construction method for onshore wind turbines
CN106988327A (en) A kind of upright controling slip casting steel floral tube pile base beam barrier wall structure and its construction method
CN113605924A (en) Combined vertical miniature steel flower pipe pile structure and construction method
CN214784152U (en) Embankment formula steel flower tubular pile foundation joist anchor beam anchor rope high retaining wall structure
CN102561360A (en) Deep foundation pit supporting method
CN217601402U (en) Miniature steel pipe pile for reinforcing foundation
RU2266368C2 (en) Method for cast-in-place pile building in collapsible ground
JPS6319648B2 (en)
CN115030155B (en) Construction method of photovoltaic support precast pile for harder stratum based on grouting process

Legal Events

Date Code Title Description
ST Notification of lapse