A procedure for construction of floors and roofs of armed, or mixed armed and pretensed concrete. (Machine-translation by Google Translate, not legally binding)
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Forjados De Tenerife S A
Original Assignee
Forjados De Tenerife S A
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Forjados De Tenerife S AfiledCriticalForjados De Tenerife S A
Priority to ES0332278ApriorityCriticalpatent/ES332278A2/en
Publication of ES332278A2publicationCriticalpatent/ES332278A2/en
Improvements introduced in the object of the main patent no. 278,000 for: A procedure for the construction of floors and roofs of reinforced concrete, or mixed reinforcing and prestressing, in which prefabricated ribs or joists are used, as stated in the claims of the main patent, essentially characterized by placing the extension reinforcement, that is to say the one placed in the lower part, a third round iron higher than the two normally provided, so that its axes form a triangle, which allows reducing the concrete height of those beams provided or nerves, the armor being almost uncovered in order to weld short pieces of round iron that are interspersed with variable spaces between the two lower irons and the third superimposed on them. (Machine-translation by Google Translate, not legally binding)
ES0332278A1966-10-141966-10-14A procedure for construction of floors and roofs of armed, or mixed armed and pretensed concrete. (Machine-translation by Google Translate, not legally binding)
ExpiredES332278A2
(en)
A procedure for construction of floors and roofs of armed, or mixed armed and pretensed concrete. (Machine-translation by Google Translate, not legally binding)
A procedure for construction of floors and roofs of armed, or mixed armed and pretensed concrete. (Machine-translation by Google Translate, not legally binding)
A procedure for construction of floors and roofs of armed, or mixed armed and pretensed concrete. (Machine-translation by Google Translate, not legally binding)
A procedure for construction of floors and roofs of armed, or mixed armed and pretensed concrete. (Machine-translation by Google Translate, not legally binding)
Improvements introduced in the construction of beams with metal reinforcement or other material for covered or forged (Machine-translation by Google Translate, not legally binding)
Procedure for the construction of sustainable structures in armed cement with pillars and prefabricated beams (Machine-translation by Google Translate, not legally binding)