ES2493722B1 - Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained - Google Patents

Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained Download PDF

Info

Publication number
ES2493722B1
ES2493722B1 ES201330349A ES201330349A ES2493722B1 ES 2493722 B1 ES2493722 B1 ES 2493722B1 ES 201330349 A ES201330349 A ES 201330349A ES 201330349 A ES201330349 A ES 201330349A ES 2493722 B1 ES2493722 B1 ES 2493722B1
Authority
ES
Spain
Prior art keywords
wind turbine
foundation
wind
upgrade
execution procedure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
ES201330349A
Other languages
Spanish (es)
Other versions
ES2493722A1 (en
Inventor
César ABAD HUBER
Jorge Franco Rey
Javier CARPINTERO GRANDE
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GRI Renewable Industries SL
Original Assignee
Iconkrete 2012 SL
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Iconkrete 2012 SL filed Critical Iconkrete 2012 SL
Priority to ES201330349A priority Critical patent/ES2493722B1/en
Publication of ES2493722A1 publication Critical patent/ES2493722A1/en
Application granted granted Critical
Publication of ES2493722B1 publication Critical patent/ES2493722B1/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/22Sockets or holders for poles or posts
    • E04H12/2292Holders used for protection, repair or reinforcement of the post or pole
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Wind Motors (AREA)

Abstract

Procedimiento de ejecución de un aerogenerador para repotenciar un parque eólico existente y aerogenerador obtenido, donde el procedimiento comprende:#- desmontar las palas, la turbina y la torre del aerogenerador a reemplazar, conservando la primera cimentación (1) y los elementos de cimentación (6) embebidos en ella,#- ejecutar una segunda cimentación (2) circunscrita y en contacto con la primera cimentación (1),#- proporcionar elementos de anclaje (3) en la segunda cimentación (2),#- fijar la primera cimentación (1) a la segunda cimentación (2) mediante unos medios de fijación,#- anclar un primer tramo (9) de la torre del nuevo aerogenerador a los elementos de anclaje (3) provistos en la segunda cimentación (2),#- instalar una turbina y unas palas y el resto de la torre sobre el primer tramo (9) de la misma para obtener un nuevo aerogenerador funcional.Execution procedure of a wind turbine to repower an existing wind farm and wind turbine obtained, where the procedure includes: # - disassemble the blades, the turbine and the wind turbine tower to be replaced, keeping the first foundation (1) and the foundation elements ( 6) embedded in it, # - execute a second foundation (2) circumscribed and in contact with the first foundation (1), # - provide anchoring elements (3) in the second foundation (2), # - fix the first foundation (1) to the second foundation (2) by means of fixing means, # - anchor a first section (9) of the new wind turbine tower to the anchoring elements (3) provided in the second foundation (2), # - install a turbine and some blades and the rest of the tower on the first section (9) of the same to obtain a new functional wind turbine.

Description



imagen1image 1

imagen2image2

imagen3image3

imagen4image4

imagen5image5

imagen6image6

imagen7image7

imagen8image8

imagen9image9

imagen10image10

imagen11image11

imagen12image12

imagen13image13

imagen14image14

imagen15image15

imagen16image16

imagen17image17

imagen18image18

imagen19image19

imagen20image20

imagen21image21

imagen22image22

imagen23image23

imagen24image24

imagen25image25

Claims (1)



imagen1image 1 imagen2image2 imagen3image3 imagen4image4 imagen5image5 imagen6image6 imagen7image7
ES201330349A 2013-03-12 2013-03-12 Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained Expired - Fee Related ES2493722B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
ES201330349A ES2493722B1 (en) 2013-03-12 2013-03-12 Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
ES201330349A ES2493722B1 (en) 2013-03-12 2013-03-12 Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained

Publications (2)

Publication Number Publication Date
ES2493722A1 ES2493722A1 (en) 2014-09-12
ES2493722B1 true ES2493722B1 (en) 2015-07-20

Family

ID=51492699

Family Applications (1)

Application Number Title Priority Date Filing Date
ES201330349A Expired - Fee Related ES2493722B1 (en) 2013-03-12 2013-03-12 Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained

Country Status (1)

Country Link
ES (1) ES2493722B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016001455A1 (en) * 2014-07-03 2016-01-07 Iconkrete 2012, S.L. Method for installing a wind turbine to upgrade an existing wind farm and wind turbine obtained
ES2894337B2 (en) * 2020-08-07 2022-08-19 Hws Concrete Towers S L FOUNDATION EXTENSION PROCEDURE IN WIND FARMS

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6453636B1 (en) * 2000-04-24 2002-09-24 Charles D. Ritz Method and apparatus for increasing the capacity and stability of a single-pole tower
US20020056250A1 (en) * 2000-04-24 2002-05-16 Cash David W. Method and apparatus for increasing the capacity and stability of a single-pole tower
FR2910038B1 (en) * 2006-12-18 2009-03-06 Transel Etude De Construction METHOD FOR REPLACING A POST AND INSTALLATION COMPRISING A POST
US8734705B2 (en) * 2008-06-13 2014-05-27 Tindall Corporation Method for fabrication of structures used in construction of tower base supports

Also Published As

Publication number Publication date
ES2493722A1 (en) 2014-09-12

Similar Documents

Publication Publication Date Title
ES2533230B1 (en) Lightning protection system with integrated anti-freeze system for wind turbine blades
CL2018000551A1 (en) Tower segment and method using a segmented bearing plate
ES2472306B1 (en) Mold for the manufacture of precast concrete
DK3060385T3 (en) WIND TURBINE BLADES
DK3049668T3 (en) Liquid wind turbine carrier system.
DK2929182T3 (en) The wind turbine tower assembly
DK2841766T3 (en) WIND TURBLE PARK WITH FIXED LOCAL REACTIVE POWER MANAGEMENT
ES2573525T3 (en) Tower crane
ES2401648R1 (en) PROCEDURE FOR ACCESS TO THE OUTSIDE SURFACE OF AEROGENERATOR TOWERS AND USE DEVICE WITH THE SAME
DK2934857T3 (en) A wind turbine blade comprising an aerodynamic shell with recess and prefabricated beam flange
DK2889473T3 (en) System and method for managing wind turbines in wind farms
BR112015002954A2 (en) integrated cooling system for a wind turbine nacelle
DK2354541T3 (en) Wind park power management based on a matrix showing a power load distribution between individual wind turbines
DK3450752T3 (en) Wind turbine with an access device to a nacelle
CL2016001325A1 (en) Wind power installation comprising a foundation that has a tower socket and a tower with a plurality of tower segments; the base has at least two segments and a tower segment is specially braced on the base by means of tensioning elements
DK3021393T3 (en) FUEL CELL, PROCEDURE FOR PREPARING THE SAME, FUEL CELL STAKE AND FUEL CELL DEVICE
DK2855924T3 (en) METHOD AND MEANS FOR ESTABLISHING ACCESS TO THE MAIN PARTS IN THE NACELLE ON A WIND TURBINE.
DK3527820T3 (en) Wind turbine cooling device
ES2549586T3 (en) Solar energy system with weather vane
ITUA20163710A1 (en) WIND TURBINE WITH VERTICAL AXIS WITH MOBILE BLADES
AR086347A1 (en) ROTOR BLADES CONTROL
ES2567082T9 (en) Wind turbine transformer
DK3690234T3 (en) Wind turbine management
CL2015003094A1 (en) Wind farm and procedure to control a wind farm
ES2414581B1 (en) INTELLIGENT DEVICE, SYSTEM AND PROCEDURE FOR OPTIMIZATION OF ELECTRICAL ENERGY CONSUMPTION

Legal Events

Date Code Title Description
FG2A Definitive protection

Ref document number: 2493722

Country of ref document: ES

Kind code of ref document: B1

Effective date: 20150720

PC2A Transfer of patent

Owner name: GRI RENEWABLE INDUSTRIES, S.L.

Effective date: 20170605

FD2A Announcement of lapse in spain

Effective date: 20211004