ES2493722A1 - Procedure of execution of a wind turbine to repower an existing wind farm and wind turbine obtained (Machine-translation by Google Translate, not legally binding) - Google Patents
Procedure of execution of a wind turbine to repower an existing wind farm and wind turbine obtained (Machine-translation by Google Translate, not legally binding) Download PDFInfo
- Publication number
- ES2493722A1 ES2493722A1 ES201330349A ES201330349A ES2493722A1 ES 2493722 A1 ES2493722 A1 ES 2493722A1 ES 201330349 A ES201330349 A ES 201330349A ES 201330349 A ES201330349 A ES 201330349A ES 2493722 A1 ES2493722 A1 ES 2493722A1
- Authority
- ES
- Spain
- Prior art keywords
- wind turbine
- foundation
- procedure
- repower
- translation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/22—Sockets or holders for poles or posts
- E04H12/2292—Holders used for protection, repair or reinforcement of the post or pole
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Wind Motors (AREA)
Abstract
Description
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
ES201330349A ES2493722B1 (en) | 2013-03-12 | 2013-03-12 | Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
ES201330349A ES2493722B1 (en) | 2013-03-12 | 2013-03-12 | Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained |
Publications (2)
Publication Number | Publication Date |
---|---|
ES2493722A1 true ES2493722A1 (en) | 2014-09-12 |
ES2493722B1 ES2493722B1 (en) | 2015-07-20 |
Family
ID=51492699
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
ES201330349A Expired - Fee Related ES2493722B1 (en) | 2013-03-12 | 2013-03-12 | Wind turbine execution procedure to upgrade an existing wind farm and wind turbine obtained |
Country Status (1)
Country | Link |
---|---|
ES (1) | ES2493722B1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2016001455A1 (en) * | 2014-07-03 | 2016-01-07 | Iconkrete 2012, S.L. | Method for installing a wind turbine to upgrade an existing wind farm and wind turbine obtained |
WO2022029355A1 (en) | 2020-08-07 | 2022-02-10 | Hws Concrete Towers, S.L. | Method for the extension of foundations in the upsizing of wind farms |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6453636B1 (en) * | 2000-04-24 | 2002-09-24 | Charles D. Ritz | Method and apparatus for increasing the capacity and stability of a single-pole tower |
US20050183364A1 (en) * | 2000-04-24 | 2005-08-25 | Cash David W. | Method and apparatus for increasing the capacity and stability of a single-pole tower |
EP1936071A1 (en) * | 2006-12-18 | 2008-06-25 | Transel etude de construction de lignes de transport d'energie electrique | Method of replacing a post and installation comprising a post |
US20090307998A1 (en) * | 2008-06-13 | 2009-12-17 | Tindall Corporation | Base support for wind-driven power generators |
-
2013
- 2013-03-12 ES ES201330349A patent/ES2493722B1/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6453636B1 (en) * | 2000-04-24 | 2002-09-24 | Charles D. Ritz | Method and apparatus for increasing the capacity and stability of a single-pole tower |
US20050183364A1 (en) * | 2000-04-24 | 2005-08-25 | Cash David W. | Method and apparatus for increasing the capacity and stability of a single-pole tower |
EP1936071A1 (en) * | 2006-12-18 | 2008-06-25 | Transel etude de construction de lignes de transport d'energie electrique | Method of replacing a post and installation comprising a post |
US20090307998A1 (en) * | 2008-06-13 | 2009-12-17 | Tindall Corporation | Base support for wind-driven power generators |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2016001455A1 (en) * | 2014-07-03 | 2016-01-07 | Iconkrete 2012, S.L. | Method for installing a wind turbine to upgrade an existing wind farm and wind turbine obtained |
WO2022029355A1 (en) | 2020-08-07 | 2022-02-10 | Hws Concrete Towers, S.L. | Method for the extension of foundations in the upsizing of wind farms |
ES2894337A1 (en) * | 2020-08-07 | 2022-02-14 | Hws Concrete Towers S L | Foundation and use extension procedure (Machine-translation by Google Translate, not legally binding) |
Also Published As
Publication number | Publication date |
---|---|
ES2493722B1 (en) | 2015-07-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DK3060385T3 (en) | WIND TURBINE BLADES | |
DK2889473T3 (en) | System and method for managing wind turbines in wind farms | |
DK3004637T4 (en) | METHODS FOR OPERATING WIND TURBINE SYSTEM WITH DYNAMIC BRAKE | |
DK3450752T3 (en) | Wind turbine with an access device to a nacelle | |
DK2855924T3 (en) | METHOD AND MEANS FOR ESTABLISHING ACCESS TO THE MAIN PARTS IN THE NACELLE ON A WIND TURBINE. | |
DK2934857T3 (en) | A wind turbine blade comprising an aerodynamic shell with recess and prefabricated beam flange | |
DK2929182T3 (en) | The wind turbine tower assembly | |
CL2015001561A1 (en) | Procedure for calculating a rear edge to be manufactured for an aerodynamic rotor blade of a wind power installation, where the blade shows radial positions referred to the rotor and has a local blade profile, the edge has a dentate development with several peaks; later song; rotor blade; and wind installation. | |
DK2795107T3 (en) | Noise reduction device for rotor blade in wind turbine | |
BR112012027846A2 (en) | unidirectional hydraulic turbine with improved duct, blades and generator | |
DK2286084T3 (en) | Wind turbine blade with an extra carrier profile | |
DK2053239T3 (en) | Method for managing wind turbines in a wind farm | |
DK2108826T3 (en) | Measurement procedure for brakes in wind turbines | |
BR112015003374A2 (en) | wind farm, and method for injecting electricity generated in a wind farm. | |
DK3568589T3 (en) | PROCEDURE FOR LOAD REDUCTION ON WIND TURBINE BLADE PITCH BEARINGS | |
AR096550A1 (en) | ROTOR SHOVEL FOR A WIND ENERGY INSTALLATION AND WIND ENERGY INSTALLATION | |
BR112015029316A2 (en) | Concrete foundation and method for producing a concrete foundation for a wind power tower as well as positioning device for positioning casing pipes in a concrete foundation | |
NZ720568A (en) | Wind turbine comprising a segmented tower and foundation | |
DK3039285T3 (en) | Rotor blade element for a wind power plant, rotor blade and its manufacturing method and wind power plant with rotor blade | |
NZ714902A (en) | Wind turbine foundation | |
DK3077666T3 (en) | INTERNAL TOWER STRUCTURE FOR A WINDMILL GENERATOR | |
GB201109897D0 (en) | A method for managing wind farms | |
CL2016001581A1 (en) | A method of managing a hydroelectric turbine array. | |
DK2595308T3 (en) | SYSTEM FOR IMPROVED WIND TURBINES GENERATION PERFORMANCE | |
DK2159414T3 (en) | Wind turbine blade with cross ribs |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
FG2A | Definitive protection |
Ref document number: 2493722 Country of ref document: ES Kind code of ref document: B1 Effective date: 20150720 |
|
PC2A | Transfer of patent |
Owner name: GRI RENEWABLE INDUSTRIES, S.L. Effective date: 20170605 |
|
FD2A | Announcement of lapse in spain |
Effective date: 20211004 |