EP4248017B1 - Fundament für einen turm für eine sendeanlage oder für den freileitungsbau - Google Patents
Fundament für einen turm für eine sendeanlage oder für den freileitungsbauInfo
- Publication number
- EP4248017B1 EP4248017B1 EP21819730.9A EP21819730A EP4248017B1 EP 4248017 B1 EP4248017 B1 EP 4248017B1 EP 21819730 A EP21819730 A EP 21819730A EP 4248017 B1 EP4248017 B1 EP 4248017B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- elements
- prefabricated
- prefabricated element
- foundation
- fastening
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/22—Sockets or holders for poles or posts
- E04H12/2238—Sockets or holders for poles or posts to be placed on the ground
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/22—Sockets or holders for poles or posts
- E04H12/2253—Mounting poles or posts to the holder
- E04H12/2261—Mounting poles or posts to the holder on a flat base
Definitions
- the invention relates to a foundation according to claim 1 for a tower for a transmitter or for overhead line construction, wherein the foundation comprises at least three prefabricated elements made of reinforced concrete and an assembly area for erecting the tower, wherein at least one first and at least one second prefabricated element form a lower first section which is in contact with a ground at the erection site of the foundation, and wherein at least one third prefabricated element forms an upper section arranged on the first section, wherein the assembly area has at least one attachment point for arranging the tower on the foundation, which is provided on a top surface of the upper section.
- Foundations for transmission towers, especially for mobile communications and overhead power lines, are primarily constructed as in-situ concrete foundations. For this, a pit is excavated at the construction site and lined with a leveling layer. The formwork and reinforcement are then erected, and the entire structure is filled with concrete on-site. This results in a flat, flat structure, possibly with a base. Besides the transportation costs associated with delivering the concrete, formwork, and reinforcement, this process is very labor-intensive on-site. Quality assurance is also complex and, depending on the weather, can be problematic. Additionally, a construction site must be set up for the curing period of the cast-in-place concrete (e.g., 28 days).
- tower refers to a tower made of pipe sections, for example of concrete and/or steel, as well as a truss tower / lattice tower / mast or a combination of both.
- the invention provides that the at least one first prefabricated element and the at least one second prefabricated element of the lower section are arranged substantially parallel and spaced apart from each other, such that there is a gap between the at least two prefabricated elements, that at least one third prefabricated element of the upper section is arranged on the at least one first prefabricated element and on the at least one second prefabricated element, so that the at least one third prefabricated element bridges the gap, and that the at least one third prefabricated element has a maximum length such that the at least one third prefabricated element is substantially flush on both sides with the outer edge of the at least one first prefabricated element and the at least one second prefabricated element.
- the at least three prefabricated elements are designed in a plate-like or cuboid shape.
- the loads can be transferred accordingly even with larger connection geometries.
- the dimensions of the prefabricated elements are preferably chosen so that the assembly area of the tower extends onto the upper section of the foundation, resulting in a particularly simple and cost-effective foundation.
- Prefabricated elements can, for example, be manufactured on site and then placed at the construction site, or, for example, in a concrete plant under defined conditions.
- the components are manufactured according to the specifications and then transported to the installation site. Other options are also possible.
- the foundation is constructed primarily by excavating a depression in the ground at the construction site, for example in the form of trenches or a building pit, possibly with a leveling layer, into which the first section of the foundation is then placed. To increase the load on the foundation or its components, it can be covered with soil.
- At least one fixing point in the assembly area has at least one vertically extending opening through at least one prefabricated element for inserting at least one fastening element, wherein the fastening elements are preferably an anchor cage, vertical tensioning elements, prestressing elements, reinforcement elements, or anchor elements, preferably threaded rods.
- the openings are preferably provided in all, or at least in all but the lowest, prefabricated element in the assembly area. It is advantageous that the openings in the prefabricated elements are aligned to accommodate the fastening elements. These are used for tensioning/prestressing the foundation components and/or for securing the tower.
- a further aspect of the invention provides that at least one connection point is provided for connecting the upper section to the lower section, and that this at least one connection point has a vertically extending opening through at least one prefabricated element for inserting at least one fastening element, wherein the fastening elements are preferably an anchor cage, vertical bracing elements, prestressing elements, reinforcement elements, or anchor elements, preferably threaded rods.
- the openings are preferably provided in all, or at least in all but the lowest, prefabricated element. It is advantageous that the openings of the prefabricated elements are aligned to accommodate the fastening elements. These are used for bracing/prestressing the foundation components and/or for securing the tower.
- the fastening elements provide prestressing in a joint between at least two prefabricated elements, preferably creating a shear connection in the joint.
- a shear connection is preferably provided by prestressing the prefabricated elements in one of the joints. The load is transferred through friction in the joint via the prestressing. The fasteners are therefore free from shear stress.
- the fastening elements may be provided, particularly if the loads to be carried are lower, that the fastening elements provide clamping in an element joint between at least two prefabricated elements, which is designed in such a way that a shear hole bearing connection is given.
- the at least one third prefabricated element has a width that is less than or equal to the width of the at least one first prefabricated element and/or the at least one second prefabricated element.
- a further teaching of the invention provides that the at least one third prefabricated element is arranged essentially at right angles ( ⁇ ) to the at least one first and/or to the at least one second element.
- Figures 1 to 6 Figure 1 shows a first embodiment of a foundation 10 according to the invention, comprising a lower section 11 and an upper section 12 arranged above it.
- the lower section 11 is composed of a first element 13 and a second element 14, which are arranged parallel to each other with a distance 18 between them.
- a third element 15 and a fourth element 16 are arranged on the upper surface of the first element 13 and the second element 14 to form the upper section 12.
- the third element 15 is arranged parallel to the fourth element 16 at a distance 22 from it to form the upper section 12.
- a mounting area 17 is provided on the upper surface 23 of the third element 15 and the fourth element 16. This area has, for example, four attachment points 20 for erecting a four-column tower (not shown) on it.
- the lengths of the third element 15 and the fourth element 16 are chosen such that they correspond to the sum of the widths of the first element 13 and the fourth element 14, as well as the distance 18 between the two.
- the third element 15 and the fourth element 16 thus extend between the outer edges 19 of the first element 13 and the second element 14.
- the fastening points 20 in the mounting area 17 are provided according to the installation geometry of the tower to be erected (not shown). In the illustrated embodiment, these are offset towards the inner edges 24 of the first element 13 of the second element 14.
- connection points 25 are provided offset towards the outer edge 19 on the third element 15 and the fourth element 16. The number of connection points 25 depends on the loads to be transferred by the tower to be erected on the foundation 10.
- FIG. 3a , 4a , 5a and 6 Figure 1 shows a first embodiment for providing the fastening points 20 and the connection points 25.
- Anchor cage-like fastening elements 26 are provided at the fastening points 20.
- the fastening element 26 has a plate-shaped abutment 28 on its upper side and a plate-shaped abutment 27 on its lower side.
- Tensioning elements 29 are provided between the abutments 27 and 28.
- the tensioning element 29 projects beyond the upper abutments 28. This projection forms the connection sections 39 for connecting the tower.
- the tensioning elements 29 can be, for example, threaded rods or other anchor rods.
- the abutment elements 27 and 28 of the fastening elements 26 are designed as square plates, each connected to four tensioning elements 29. Alternative embodiments and, in particular, different numbers of tensioning elements 29 are possible.
- Connecting elements 30 are provided at connection point 25, each of which has a plate-like abutment 32 on the upper side and an abutment 31 on the lower side, which in turn are connected to a clamping element 33.
- the abutment elements 31, 32 of the connecting elements 30 are designed as square plates, each connected to a clamping element 33.
- Alternative embodiments and, in particular, different numbers of clamping elements 33 are possible.
- the first element 13 and the second element 14 show, as in Figure 4a
- the illustration shows openings 34 into which the fastening elements 26 and connecting elements 30 are arranged.
- Figure 5a in which openings 35 are provided, into which the fastening elements 26 and connecting elements 30 are arranged.
- the openings 34 and 35 are shown aligned in the assembled state.
- abutments 31 and 27 are provided on the underside 36 of the first element 13 and the second element 14.
- Abutments 28 and 32 are provided on the top side of the third element 15 and the fourth element 16.
- Tensioning elements 29 are provided in the openings 34 and 35 between abutments 27 and 28, and tensioning elements 33 are provided between abutments 31 and 32.
- a portion of the underside 37 of the third element 15 and the fourth element 16 rests on a corresponding portion of the upper side 21 of the first element 13 and the second element 14. This creates an element joint 38 between the elements 13, 14, 15, and 16.
- a shear connection is provided between the elements 13, 14, 15, and 16.
- This connection is preferably designed with a sufficiently strong prestress to ensure that no shear stress is present in the fastening elements 26 and the connecting elements 30. The friction present in the element joint 38 due to the prestress transfers the loads exerted by the tower into the foundation.
- bracing could also be designed so that only a shear hole bearing connection is provided if the loads to be carried are small.
- Figures 3b , 4b , and 5b Figure 2 shows a second embodiment for providing the fastening points 20 and the connection points 25.
- Anchor cage-like fastening elements 26 are provided at the fastening points 20 as shown in Figure 2.
- Figure 6 The fastening element 26 has a plate-shaped abutment 28 on its upper side and a plate-shaped abutment 27 on its lower side.
- Tensioning elements 29 are provided between the abutments 27 and 28.
- the tensioning element 29 projects beyond the upper abutments 28. This projection forms the connection sections 39 for attaching the tower.
- the tensioning elements 29 can be, for example, threaded rods or other anchor rods.
- the abutment elements 27 and 28 of the fastening elements 26 are designed as square plates, each connected to four tensioning elements 29. Alternative designs and, in particular, different numbers of tensioning elements 29 are possible.
- Connecting elements 30 are provided at connection point 25, as shown in Figure 6
- the figure shows a plate-like abutment 32 on the upper side and an abutment 31 on the lower side, which in turn are connected to a clamping element 33.
- the abutment elements 31, 32 of the connecting elements 30 are designed as square plates, each connected to a clamping element 33.
- Alternative designs and, in particular, different numbers of clamping elements 33 are possible.
- the first element 13 and the second element 14, as in the Figures 3b and 4b As shown, there are no openings 34, but rather the lower abutments 27, 31 and the tensioning elements 29, 33 arranged thereon are incorporated into the reinforcement and cast into the concrete during the manufacture of the elements 13, 14.
- the third element 15 and the fourth element 16 have, according to Figure 5b Openings 35 are created. During assembly, the openings 35 are placed onto the clamping elements 29, 33 protruding from the elements 13, 14.
- the upper abutments 28, 32 are inserted into recesses 40, 41 on the upper surface 23.
- the recesses can also be used in the first embodiment.
- the pre-tensioning or tensioning is carried out as described above.
- Figure 1 shows a second embodiment of a foundation 10 according to the invention, in which a third and fourth element 15, 16 are also arranged on a first and second element 13, 14.
- the second embodiment shows a foundation 10 for mounting a three-column tower. Consequently, only three fastening points 20 are provided. Two of these fastening points are located, for example, on the third element 15 such that their fastening elements 26 are arranged in the openings 34, 35 and brace the third element 15 with the first element 13 and the second element 14, as was already shown in the first embodiment.
- the connection points 25 are also provided accordingly. Only the upper abutments 28 and, correspondingly, the openings 34 and 35 are rotated to accommodate the three-column tower.
- the third fixing point 20, however, is provided only on the fourth element 16 above the distance 18 to achieve a triangular shape.
- the lower abutment 27 accordingly rests against the underside 37 of the fourth element 16.
- the clamping elements 29 are correspondingly shorter.
- additional connection points 25 with corresponding connecting elements 30 are provided. These are located on the outside.
- connection points 25 provided for the fourth element 16 further connection points 25 are provided, which are shifted accordingly oppositely towards the area of the distance 18.
- the assembly of the connecting elements 30 and the fastening elements 26 is carried out as shown in Figure 12. Alternatively, it would also be possible to partially provide the fastening elements 26 and connecting elements 25 by installing the abutments 27, 31 and the clamping elements 29, 33 in the first element 13 and the second element 14.
- the Figures 13-18 which show a third embodiment, and which Figures 19-24
- the fourth embodiment which shows a modification in which, instead of a narrow third and a narrow fourth element 15, 16, only a third element 13 is provided, but this element has a greater width.
- the width is chosen such that the mounting area 17 can be arranged entirely on the third element 15.
- the third and fourth embodiments again show the arrangement of a three-column tower. However, the embodiments are also suitable for four-column or multi-column towers. This embodiment is also suitable for a round tower, as shown in a further embodiment in Figure 25
- the third and fourth embodiments differ only in the number of connection points 25.
- the third fastening point 20 is also located within the area of the distance 18, so that it does not contribute to the connection of the third element 15 with the first element 13 and the second element 14.
- the remaining structure corresponds to the embodiments described above.
- Figure 25 shows an embodiment in which a round tower is arranged on the mounting area 17 on the upper section 12 in the form of a third element 15. Openings 35 are provided in the third element 15, some located at the distance 18 and some above the first and second elements 13, 14.
- An anchor cage (not shown) is used as a fastening element 26, which is provided in sections for assembly. Sections of the anchor cage are provided on the underside 37 of the third element 15 and further sections on the underside 36 of the first and second elements 13, 14 (both not shown), which are then arranged in openings 34 and 35 analogously to what has been previously disclosed.
- an upper abutment 28 divided into several parts or a one-piece abutment 28 can be provided on the upper side.
- connection points 25 are provided on the outer sides of the third element 15. Recesses 40, 41 can also be used here.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Foundations (AREA)
- Wind Motors (AREA)
Applications Claiming Priority (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE102020130813 | 2020-11-20 | ||
| DE102021106003 | 2021-03-11 | ||
| PCT/EP2021/081745 WO2022106371A1 (de) | 2020-11-20 | 2021-11-15 | Fundament für einen turm für eine sendeanlage oder für den freileitungsbau |
Publications (3)
| Publication Number | Publication Date |
|---|---|
| EP4248017A1 EP4248017A1 (de) | 2023-09-27 |
| EP4248017C0 EP4248017C0 (de) | 2025-12-31 |
| EP4248017B1 true EP4248017B1 (de) | 2025-12-31 |
Family
ID=78821827
Family Applications (2)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| EP21819730.9A Active EP4248017B1 (de) | 2020-11-20 | 2021-11-15 | Fundament für einen turm für eine sendeanlage oder für den freileitungsbau |
| EP21819729.1A Pending EP4248039A1 (de) | 2020-11-20 | 2021-11-15 | Fundament für einen turm für eine windkraftanlage |
Family Applications After (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| EP21819729.1A Pending EP4248039A1 (de) | 2020-11-20 | 2021-11-15 | Fundament für einen turm für eine windkraftanlage |
Country Status (6)
| Country | Link |
|---|---|
| US (1) | US20250297446A1 (pl) |
| EP (2) | EP4248017B1 (pl) |
| DE (2) | DE102021129759A1 (pl) |
| PL (1) | PL4248017T3 (pl) |
| SA (1) | SA523440855B1 (pl) |
| WO (2) | WO2022106371A1 (pl) |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5456555A (en) * | 1992-11-09 | 1995-10-10 | Boekeler; Hans-Joerg | Structural set of angle elements fitting into one another |
| FR2707313B1 (fr) * | 1993-07-08 | 1999-02-26 | Mathon Jean Claude | Structure d'ancrage et de liaison amovible et polyvalente pour ossatures pré infrastructures. |
| DE202015003668U1 (de) * | 2015-05-08 | 2015-11-05 | Cteam Consulting & Anlagenbau Gmbh | Unterbau für einen Mast und Mastsystem |
| DE202016006586U1 (de) * | 2016-10-25 | 2016-12-28 | Margit Niklas | Sonnenschirmständer |
| DE102018121024A1 (de) * | 2018-08-28 | 2020-03-05 | Universelle-Fertigteil-Fundamente GmbH | Fundament für eine Windkraftanlage |
-
2021
- 2021-11-15 WO PCT/EP2021/081745 patent/WO2022106371A1/de not_active Ceased
- 2021-11-15 US US18/038,012 patent/US20250297446A1/en active Pending
- 2021-11-15 DE DE102021129759.1A patent/DE102021129759A1/de active Pending
- 2021-11-15 DE DE102021129748.6A patent/DE102021129748A1/de active Pending
- 2021-11-15 PL PL21819730.9T patent/PL4248017T3/pl unknown
- 2021-11-15 EP EP21819730.9A patent/EP4248017B1/de active Active
- 2021-11-15 EP EP21819729.1A patent/EP4248039A1/de active Pending
- 2021-11-15 WO PCT/EP2021/081733 patent/WO2022106368A1/de not_active Ceased
-
2023
- 2023-05-21 SA SA523440855A patent/SA523440855B1/ar unknown
Also Published As
| Publication number | Publication date |
|---|---|
| EP4248039A1 (de) | 2023-09-27 |
| US20250297446A1 (en) | 2025-09-25 |
| EP4248017C0 (de) | 2025-12-31 |
| DE102021129759A1 (de) | 2022-05-25 |
| DE102021129748A1 (de) | 2022-05-25 |
| SA523440855B1 (ar) | 2024-10-02 |
| EP4248017A1 (de) | 2023-09-27 |
| WO2022106368A1 (de) | 2022-05-27 |
| WO2022106371A1 (de) | 2022-05-27 |
| PL4248017T3 (pl) | 2026-03-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP1735533B2 (de) | Verfahren zum errichten eines turmes sowie windenergieanlage | |
| EP3724407B1 (de) | Fundament für eine windkraftanlage | |
| EP3821083B1 (de) | Fundament für ein windkraftwerk | |
| EP3821084B1 (de) | Fundament für ein windkraftwerk | |
| AT519190A1 (de) | Fundament für eine Windmühle | |
| DE102018107421A1 (de) | Fundament für ein mittels einer Vielzahl von Spanngliedern vorgespanntes Bauwerk sowie mittels einer Vielzahl von Spanngliedern vorgespanntes Bauwerk | |
| DE202016009246U1 (de) | Turm für eine Windkraftanlage aus ringsegmentförmigen Betonfertigteilen | |
| EP4497945A2 (de) | Fundament für eine windkraftanlage | |
| DE102021100799B4 (de) | Turm für eine Windenergieanlage sowie Adapter | |
| DE102018121024A1 (de) | Fundament für eine Windkraftanlage | |
| WO2022069333A1 (de) | Fundament für eine windkraftanlage | |
| EP4248017B1 (de) | Fundament für einen turm für eine sendeanlage oder für den freileitungsbau | |
| EP4222321B1 (de) | Fundament für eine windkraftanlage | |
| DE102010040332B4 (de) | Gründungselement | |
| DE102021125328A1 (de) | Ankerkorb für ein Fundament für eine Windkraftanlage | |
| DE102021105960A1 (de) | Fundament für einen Turm für eine Sendeanlage oder für den Freileitungsbau | |
| LU502258B1 (de) | Verfahren zur Herstellung eines Röhrenkomplexes | |
| DE102021105955A1 (de) | Fundament für einen Turm für eine Windkraftanlage | |
| EP4248038A1 (de) | Fundament für einen turm für eine windkraftanlage | |
| DE202023102846U1 (de) | Fundament für ein Fertighaus | |
| DE102021122183A1 (de) | Fundament für einen Turm für eine Windkraftanlage | |
| DE202021105272U1 (de) | Ankerkorb für ein Fundament für eine Windkraftanlage | |
| EP4729698A1 (de) | Windenergieanlagenfundament und verfahren zum herstellen eines solchen | |
| DE202020105643U1 (de) | Fundament für eine Windkraftanlage | |
| DE202020106971U1 (de) | Fundament für eine Windkraftanlage |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: UNKNOWN |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE |
|
| PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
| 17P | Request for examination filed |
Effective date: 20230620 |
|
| AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
| DAV | Request for validation of the european patent (deleted) | ||
| DAX | Request for extension of the european patent (deleted) | ||
| GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
| INTG | Intention to grant announced |
Effective date: 20250724 |
|
| GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
| GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
| RAP1 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: NEXT FOUNDATION GMBH |
|
| AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
| REG | Reference to a national code |
Ref country code: CH Ref legal event code: F10 Free format text: ST27 STATUS EVENT CODE: U-0-0-F10-F00 (AS PROVIDED BY THE NATIONAL OFFICE) Effective date: 20251231 Ref country code: GB Ref legal event code: FG4D Free format text: NOT ENGLISH |
|
| REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 502021009559 Country of ref document: DE |
|
| REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D Free format text: LANGUAGE OF EP DOCUMENT: GERMAN |
|
| U01 | Request for unitary effect filed |
Effective date: 20260116 |
|
| U07 | Unitary effect registered |
Designated state(s): AT BE BG DE DK EE FI FR IT LT LU LV MT NL PT RO SE SI Effective date: 20260122 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20260331 |
|
| REG | Reference to a national code |
Ref country code: ES Ref legal event code: FG2A Ref document number: 3062557 Country of ref document: ES Kind code of ref document: T3 Effective date: 20260413 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20251231 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20260331 |