EP3914850B1 EP20744266.6A EP20744266A EP3914850B1 EP 3914850 B1 EP3914850 B1 EP 3914850B1 EP 20744266 A EP20744266 A EP 20744266A EP 3914850 B1 EP3914850 B1 EP 3914850B1
Authority
EP
European Patent Office
Prior art keywords
bladder
aperture
pulling
vessel
resistance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP20744266.6A
Other languages
English (en)
French (fr)
Other versions
EP3914850A4 (de
EP3914850A1 (de
Inventor
Ola Ravndal
Egil SÆL
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sael Consulting AS
Original Assignee
Sael Consulting AS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sael Consulting AS filed Critical Sael Consulting AS
Publication of EP3914850A1 publication Critical patent/EP3914850A1/de
Publication of EP3914850A4 publication Critical patent/EP3914850A4/de
Application granted granted Critical
Publication of EP3914850B1 publication Critical patent/EP3914850B1/de
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C3/00Vessels not under pressure
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C9/00Methods or apparatus for discharging liquefied or solidified gases from vessels not under pressure
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65DCONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
    • B65D90/00Component parts, details or accessories for large containers
    • B65D90/22Safety features
    • B65D90/38Means for reducing the vapour space or for reducing the formation of vapour within containers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65DCONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
    • B65D2231/00Means for facilitating the complete expelling of the contents
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65DCONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
    • B65D90/00Component parts, details or accessories for large containers
    • B65D90/0093Devices for cleaning the internal surfaces of the container and forming part of the container
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2201/00Vessel construction, in particular geometry, arrangement or size
    • F17C2201/01Shape
    • F17C2201/0176Shape variable
    • F17C2201/018Shape variable with bladders
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2201/00Vessel construction, in particular geometry, arrangement or size
    • F17C2201/03Orientation
    • F17C2201/035Orientation with substantially horizontal main axis
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2201/00Vessel construction, in particular geometry, arrangement or size
    • F17C2201/05Size
    • F17C2201/052Size large (>1000 m3)
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2203/00Vessel construction, in particular walls or details thereof
    • F17C2203/06Materials for walls or layers thereof; Properties or structures of walls or their materials
    • F17C2203/0602Wall structures; Special features thereof
    • F17C2203/0612Wall structures
    • F17C2203/0614Single wall
    • F17C2203/0619Single wall with two layers
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2203/00Vessel construction, in particular walls or details thereof
    • F17C2203/06Materials for walls or layers thereof; Properties or structures of walls or their materials
    • F17C2203/068Special properties of materials for vessel walls
    • F17C2203/0685Special properties of materials for vessel walls flexible
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2221/00Handled fluid, in particular type of fluid
    • F17C2221/03Mixtures
    • F17C2221/032Hydrocarbons
    • F17C2221/035Propane butane, e.g. LPG, GPL
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2223/00Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
    • F17C2223/01Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the phase
    • F17C2223/0146Two-phase
    • F17C2223/0153Liquefied gas, e.g. LPG, GPL
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2223/00Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
    • F17C2223/03Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the pressure level
    • F17C2223/033Small pressure, e.g. for liquefied gas
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2250/00Accessories; Control means; Indicating, measuring or monitoring of parameters
    • F17C2250/04Indicating or measuring of parameters as input values
    • F17C2250/0404Parameters indicated or measured
    • F17C2250/0421Mass or weight of the content of the vessel
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2250/00Accessories; Control means; Indicating, measuring or monitoring of parameters
    • F17C2250/04Indicating or measuring of parameters as input values
    • F17C2250/0404Parameters indicated or measured
    • F17C2250/0469Constraints, e.g. by gauges
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2260/00Purposes of gas storage and gas handling
    • F17C2260/01Improving mechanical properties or manufacturing
    • F17C2260/015Facilitating maintenance
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2260/00Purposes of gas storage and gas handling
    • F17C2260/04Reducing risks and environmental impact
    • F17C2260/048Refurbishing
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17CVESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
    • F17C2270/00Applications
    • F17C2270/01Applications for fluid transport or storage
    • F17C2270/0102Applications for fluid transport or storage on or in the water
    • F17C2270/0105Ships

Definitions

  • the present invention is related to removal of a flexible bellows or bladder that has been inflated inside a chamber. More particularly, the present invention is related to an apparatus and a method for controlling a pulling of an inflatable bladder through an aperture in a wall between a chamber and a structure arranged on an outside of the chamber.
  • the bladder may be elastic or substantially inelastic of a type suitable for use as a volume-displacing device in a chamber such as for example an LPG-tank in an LPG transport ship.
  • a bladder or bellows intended for this purpose is disclosed in publication WO 2006/033577 A1 which discloses i.a. a method related to change of cargo of a transport vessel having at least one fluid container containing a first fluid comprising a liquid phase and a gas phase. A second fluid is introduced into a bladder which is situated inside the fluid container. The expansion or filling of the bladder reduces the internal volume of the fluid container which is available for said gas phase.
  • the method comprises inter alia the following steps:
  • WO 2006/033577 A1 discloses an efficient manner in which a gas is ventilated from an enclosure such as a tank. Once the bladder is inflated using said gas, a gas on the outside of the bellows is allowed to escape through at least one aperture and into another area for safe keeping and/or processing. Once the bladder has been completely or nearly completely inflated, all the gas on the outside of the bladder is thus displaced though said apertures.
  • Publication WO 2014/070021 A1 discloses an apparatus and a method for facilitating purging a vessel by means of an inflatable bellows or bladder.
  • the bladder is connected to a conduit for communicating a fluid into or out of the bladder.
  • the bladder is initially arranged in a fluid tight compartment outside the vessel.
  • the compartment is provided with a closable sealing means adapted for selectively bringing the compartment in fluid communication with the internal of the vessel via an aperture in a portion of the vessel.
  • the aperture may typically, but not exclusively, be a so-called manhole.
  • At least a portion of the bladder is then brought into the vessel. Thereafter, the bladder is inflated by means of a fluid provided from a fluid source.
  • the vessel When the bladder has been inflated, the vessel is cleaned by purging a space which is defined by an internal surface of the vessel and an external surface of the inflated bladder. When the cleaning process has been completed, the bladder is deflated and thereafter brought out of the vessel and back into the compartment.
  • the bladder used for insertion into a first tank such as described in WO 2014/070021 A1 , is typically folded inside a cartridge when it is inserted into the second adjacent tank prior to use.
  • the bellows or bladder Upon deployment, the bellows or bladder is typically falling from its cartridge in the second, adjacent tank into the first tank such that the filling end of the bladder is retained inside the second, adjacent tank.
  • the filling end is a narrow portion of the bladder extending from its termination point inside the second, adjacent tank into the main tank so that it forms a "neck" on the main bladder, which is intended to inflate in the first tank.
  • the bladder is folded in so a manner so as to avoid twist, which would impede the flow of gas into the bladder once it is dropped into the first tank.
  • the "neck" of the bladder is typically made in a somewhat stiffer material than that of the main portion of the bladder so that it does not successively collapse and re-inflate in dynamically unstable manner during inflation and deflation.
  • the bladder Once the bladder has served its purpose, it is typically deflated as much as is possible through the filling of gas on the outside of the bladder inside the first tank in which it has been deployed.
  • This deflation method although reliable, is not guaranteed to expel all the gas from the bladder.
  • the remaining gas inside the bladder must be allowed to escape prior to the bladder entering a collection means inside the compartment.
  • This inflated portion being upstream of the aperture in the vessel will tend to fully block the aperture between the vessel and the compartment. If the pulling operation continues, the gas pressure within the inflated portion of the bladder being upstream of the aperture will increase and represent a high risk of rupture. If, or rather when, such a rupture occurs, the gas from inside the bladder will blend with that of the gas on the outside of bladder inside vessel. A person skilled in the art will appreciate that such a blend of gases is highly undesirable.
  • the invention has for its object to remedy or to reduce at least one of the drawbacks of the prior art, or at least provide a useful alternative to prior art.
  • an apparatus for controlling a pulling of an inflatable bladder through an aperture in a wall between a chamber and a structure arranged on an outside of the chamber comprises:
  • the structure may be configured for carrying the pulling mechanism and the cutting device.
  • the structure may be a housing.
  • slit any passage through a wall of the bladder allowing gas to flow out of the bladder.
  • the slit may for example be one or a plurality of circular holes, or one or more rifts in the wall of the bladder.
  • the evacuating rate of gas out of the bladder and into the structure, such as a housing can be controlled.
  • the evacuation rate of gas out of the bladder it is possible to use the portion of bladder still being upstream of the aperture, i.e. the portion of the bladder still being on the inside of the chamber, as a sealing means against the aperture.
  • the evacuation rate of gas out of the bladder two different situations may arise. If the evacuation rate of gas is too large, the gas pressure within the portion of the bladder still being upstream of the aperture, will be too small to abut the periphery of the aperture and an open space will arise between the bladder and the periphery of the aperture.
  • the gas pressure within the portion of the bladder still being upstream of the aperture may increase to a pressure exceeding the capacity of the bladder while the bladder is pulled out.
  • a pressure exceeding the capacity of the bladder will result in rupture of the bladder and mixing of the gas within the bladder with the gas within the chamber.
  • the resistance is measured by measuring a load on the pulling mechanism.
  • the load on the pulling mechanism may be measured for example by means of power consumption of the pulling mechanism, a torque, a "weight" of the device detected by means of a load cell, etc.
  • the resistance is measured by means of a pressure sensing mechanism arranged in or at a periphery of the aperture, the pressure sensing mechanism configured for measuring a pressure exerted by the bladder.
  • a pressure sensing mechanism may give signals to a control device operating the cutting device; the higher pressure sensed by the sensing mechanism, the higher number of and/or larger size of slits in the bladder is made by the cutting mechanism.
  • the apparatus may further comprise a control device for controlling a pulling rate of the pulling mechanism, the control device being responsive to a resistance of the bladder from passing through the aperture so that the pulling rate is increased if the resistance is reduced, and vice versa; i.e. the pulling rate is reduced if the resistance is increased.
  • the control device may form part of a common control device for controlling other components of the apparatus.
  • the cutting device may be configured for providing one or more slits along an axis being substantially in parallel with a moving direction of the bladder through the aperture. This has the effect that the bladder even after being provided with slits, is continuous in said moving direction and thus being spoolable onto a drum.
  • the pulling mechanism may be configured for puckering the bladder so that a volume of the bladder at the pulling mechanism is smaller than an area defined by a periphery of the aperture.
  • a method for pulling an inflatable bladder through an aperture in a wall between a chamber and a structure arranged on an outside of the chamber comprising:
  • the method may further comprise, after activating the cutting device, controlling a pulling rate so that the resistance of the bladder against passing through the aperture is within a predetermined range.
  • Position indications such as for example, upper, lower, upstream and downstream refers to a typical position of use of the apparatus, and as shown in the figures.
  • the figures are principle drawings, and that relative proportions between individual elements may be distorted.
  • the volume of the chamber and the volume defined by the structure are for illustrative purposes substantially the same.
  • the volume of the chamber will typically be much larger, for example 100 times or more, than the volume defined by the structure.
  • reference numeral 1 denotes an apparatus for controlling a pulling of an inflatable bladder B through an aperture 3 in a wall between a chamber 5, here in the form of a vessel, and a structure 7, here in the form of a bladder housing compartment which is desired if the gas within the bladder B is to be collected for example for future use and/or discharged distant from the structure 7. It should be noted that all required or desired piping and instrumentation of i.a. the vessel 5 and the bladder housing compartment 7 will be obvious to a person skilled in the art and are thus not shown in figures 1-9 .
  • the bladder housing compartment 7 is connected to the vessel 5 via a conduit 9 extending from the aperture 3.
  • the conduit 9 is similar to a so-called manhole. Typically, a diameter of the conduit 9 is 600 mm.
  • the purpose of the bladder housing compartment 7 is to store the bladder B prior to insertion into the vessel 5 as shown in fig. 1 , and to receive the bladder B as shown in figures 4-5 and 7-9 when it has served its purpose, i.e. when the vessel 5 has been purged, as discussed above in relation to WO 2014/070021 A1 .
  • the bladder housing compartment 7 is provided with an internal partition 21 having a central opening therein for receiving a top portion of the bladder B.
  • the partition 21 extends radially inwards from an internal wall of the bladder housing compartment 7. Prior to commencing the pulling operation of the bladder B, the bladder B and the partition 21 serve to divide the bladder housing compartment 7 into an upper portion 22 and a lower portion 23, as will be understood from the discussion below.
  • the apparatus 1 comprises a pulling mechanism 11, 11', here in the form of a pair of oblong rollers 11 abutting each other, and a rotatable drum 11'.
  • the rotatable drum 11' is rotated by means of a driving device such as for example an electric, pneumatic or hydraulic motor (not shown).
  • the rollers 11 are traction rollers 11 configured for rotating in opposite directions as indicated by arrows R in figures 4-5 and 7-8 .
  • the rotation is provided by means of a driving device (not shown) such as for example electric, pneumatic or hydraulic motors.
  • the rotatable drum 11' is configured for winding the bladder B onto the drum 11' after having passed the traction rollers 11.
  • the rotatable drum 11' is configured for operating synchronous with the traction rollers 11 by means of a control device 15 operatively connected i.a. thereto.
  • the control device 15 is typically operated from a remote location on for example a ship. For the sake of clarity, communication lines/signals to and from the control device 15 are not shown.
  • the rotatable drum 11' is configured for pulling the bladder B out of the vessel 5.
  • the rollers 11 may be passive rollers configured for being rotated by means of the bladder B passing the rollers 11 while the bladder B is pulled by the rotatable drum 11'.
  • the passive rollers 11 serve as a guidance means.
  • the bladder B is pulled out of the vessel 5 by means of both the traction rollers 11 and the rotatable drum 11'.
  • the rotatable drum 11' is configured for operating synchronous with the traction rollers 11 by means of the control device 15.
  • rollers 11 independent of being traction rollers or rollers serving as guidance means, may in one embodiment (not shown) be provided with serrated surfaces configured for cutting the bladder B into a plurality of elongate strips when passing the rollers 11.
  • the elongate strips are wound onto the drum 11'.
  • the rotatable drum 11' is configured for being removed from the upper portion 22 of the bladder housing compartment 7 in a manner disclosed in WO 2014/070021 A1 .
  • the apparatus 1 further comprises a cutting device 13 for providing a slit in a portion of the bladder B after said portion having passed the aperture 3 in the wall of the vessel 5 during the pulling operation, i.e. in a "downstream" side of the aperture 3. Providing the slit in the downstream side of the aperture 3 will substantially prevent that the gas within the bladder B mixes with the gas within the vessel 5.
  • the cutting device 13 is movable from a passive position as shown in figures 1 - 4 wherein the cutting device 13 is not in contact with the bladder B, to an active position as shown in figures 5-8 wherein the cutting device penetrates the bladder B. It should be noted that the cutting device shown in fig. 7 is shown both in the passive position (indicated by dotted lines) and in the active position.
  • the movement of the cutting device 13 both ways between its passive position and its active position is controlled by the control device 15 being further configured for measuring a resistance of the bladder B from passing through the relatively small diameter of the aperture 3 in the vessel 5.
  • the bladder B is folded and packed in a storage device 17 such as a cartridge, canister or other types of container or box having a size and a shape suitable for efficient storage and transport and thereafter easy handling and installation within the lower portion 23 of the bladder housing compartment 7.
  • a storage device 17 such as a cartridge, canister or other types of container or box having a size and a shape suitable for efficient storage and transport and thereafter easy handling and installation within the lower portion 23 of the bladder housing compartment 7.
  • Several storage devices 17 are typically stored for example on board a ship for easy use and installation within the bladder housing compartment 7, when needed.
  • a rim BR forming a top portion of a nozzle BN (see for example fig. 2 ) of the bladder B is connected to the rotatable drum 11' by means of for example a rope 18 attached to the rim BR of the bladder B and the rotatable drum 11'.
  • the rim BR of the bladder B abuts an upper surface portion of the partition 21 at the periphery of the central opening in the partition 21.
  • the partition 21 may support at least some of the weight of the bladder B. More importantly, when the rim BR abuts the partition 21, a sufficient seal is provided for inflating the bladder B by means of a gas, for example N 2 , supplied to the upper portion 22 of the bladder housing compartment 7 via a gas supply pipe 8.
  • a gas for example N 2
  • the bladder housing compartment 7 is connected to the vessel 5 by a closable sealing means 19 adapted for controllable opening and closing for communication between the bladder housing compartment 7 and the internal of the vessel 5.
  • a closable sealing means 19 adapted for controllable opening and closing for communication between the bladder housing compartment 7 and the internal of the vessel 5.
  • the closable sealing means 19 are shown in fig. 1 only wherein it is indicated as a gate valve 19 being in its closed position.
  • the gate valve 19 has been opened and a major portion of the bladder B has been inserted, or allowed to "drop", into the vessel 5 and subsequently fully inflated (as indicated by arrows Fi) within the vessel 5.
  • the bladder B occupies substantially the entire internal volume of the vessel 5.
  • a fluid within the lower portion 23 of the bladder housing compartment 7 may mix with the fluid within the vessel 5.
  • the fluid within the vessel 5 is substantially prevented from mixing with the fluid within the upper portion 23 of the bladder housing compartment 7.
  • the bladder B At least after being fully inflated, the bladder B abuts the aperture 3 in the wall of the vessel 5 and thus substantially prevents fluid communication between the bladder housing compartment 7, including its lower portion 23, and the internal volume of the vessel 5 defined by an inner surface of the vessel 5 and outer surface of the bladder B.
  • a vessel purging operation as discussed in WO 2014/070021 A1 may now commence.
  • Fig. 3 shows a situation prior to commencing the pulling operation of the bladder B out of the vessel 5.
  • the bladder B is in the process of being compressed by means of filling a fluid, preferably a gas having a pressure being higher than the pressure within the bladder B, into the space defined by the inner surface of the vessel 5 and the outer surface of the bladder B.
  • the fluid is supplied into the vessel 5 via vessel supply pipe 6.
  • the bladder B is compressed and most of the gas within the bladder is urged into the upper portion 22 of the bladder housing compartment 7 and out via a conduit 8' for storage in another vessel (not shown) for later use or, depending on the type of gas, ventilated to atmosphere.
  • the fluid flow into the vessel 5 is in fig. 3 indicated by arrow Fi and the gas flow out of the bladder B is indicated by arrow Fo.
  • Fig. 4 shows a situation wherein the bladder B has been substantially deflated by means of the pressure within the vessel 5, and the pulling process has commenced by activating the pulling mechanism 11, 11' as indicated by arrows R.
  • the pair of oblong rollers 11, independent of being traction rollers or guidance means as discussed above, will pucker the bladder B so that a volume of the bladder B at the rollers 11 is smaller than an area defined by the periphery of the aperture 3 in the vessel 5.
  • the gas will accumulate in the portion of the bladder B still being within the vessel 5, i.e. upstream of the aperture 3. Due to the pulling of the bladder B, the volume available for housing the gas within the bladder B will diminish and the pressure within the bladder B will increase. This increased pressure will result in an increased resistance against the pulling of the bladder B through the aperture 3.
  • the apparatus 1 is provided with a measuring device (not shown) for measuring a load on the relevant pulling mechanism 11, 11'.
  • the measuring device may be a pressure sensing mechanism arranged in or at a periphery of the aperture 3 in the wall of the vessel 5.
  • the pressure sensing mechanism is responsive to a pressure or load exerted by the bladder B while passing the aperture 3.
  • the control device 15 will activate a driving device of the cutting device 13 and move the cutting device 13 from an initial passive position as shown for example in fig. 4 , to an active position as shown for example in fig. 5 wherein the cutting device 13 penetrates the bladder B in the portion being downstream of the aperture 3, i.e. within the lower portion 23 of the bladder housing compartment 7.
  • the cutting device 13 comprises a sharp object, such as a knife extending from a piston movable within a cylinder (best seen in fig. 6 ).
  • the driving device comprises a fluid pump, for example a hydraulic pump connected to a hydraulic source.
  • the cutting device may for example comprise a rod configured for being heated at least in its active position so that the rod penetrates the bladder B by melting through the wall thereof.
  • a cutting device in the form of a sharp object is preferred.
  • the cutting device 13 may be controlled both ways between its active and passive positions so that a desired resistance against the pulling is achieved.
  • the control device 15 controls the control device 15 in such a manner that if the resistance against pulling of the bladder B is below a predetermined level, the cutting device 13 is retracted to its initial passive position. If the resistance thereafter increases to a level above the predetermined level, the cutting device 13 is again moved to its active position. This process continues until the bladder B is completely pulled out of the vessel 5 and the valve 19 at the aperture 3 is closed.
  • Fig. 6 shows an example of a configuration of the cutting device 13 comprising eight cutting elements 14 extending radially towards a centerline of the aperture 3 of the vessel and the conduit 9.
  • the cutting device 13 in an alternative embodiment may comprise at least one cutting element.
  • each cutting element 14 is connected to a piston of a piston-cylinder arrangement 14' as discussed above.
  • the piston-cylinder arrangements 14' are arranged at the interface between the conduit 9 and a wall of the bladder housing compartment 7.
  • all eight cutting elements 14 are in their active position penetrating the bladder B.
  • each of or at least opposite pairs of the cutting elements 14 are configured to be controlled individually by means of the control device 15 operatively connected to the means for measuring resistance of the bladder B through the aperture 3.
  • the cutting device 13 comprises rolling knives 14.
  • Each rolling knife 14 is arranged at an end portion of a pivot arm 14' connected to the wall of the lower portion 23 of the bladder housing compartment 7.
  • the arm 14' is configured for movement between a passive position (shown by dotted lines), and an active position wherein the rolling knives penetrates the wall of the bladder B.
  • the movement is provided by means of a hydraulic or pneumatic cylinder controlled by means of the control device 15 as discussed above.
  • the cutting device 13 shown in fig. 8 is similar to cutting device 13 shown in fig. 5 , but inclined downwardly with respect to a pulling direction of the bladder B instead of being substantially perpendicular thereto as indicated in fig. 5 .
  • the cutting devices 13 shown in figures 7 and 8 may be arranged and operated in a similar way as discussed with regards to the embodiment shown in fig. 5 and fig. 6 .
  • the bladder B has been pulled out of the vessel 5 and fully wound onto the drum 11' which can then be removed from the upper portion 22 of the bladder housing compartment 7 for example via an openable top portion (not shown) thereof.
  • the gate valve 19 has been activated to its closed position so that bladder housing compartment 7 is fluidly isolated from the internal of the vessel 5.
  • the rate of gas release from the bladder attained through such controlled slit or cut is not significantly greater than that of the pulling rate of the bladder so that the bladder inside the vessel 5 is sufficiently inflated to form an effective seal against leakage from the bladder housing compartment 7 into the vessel 5 through the aperture 3. If the gas release rate is too high compared with the pulling rate of the bladder B, the bladder B may deflate more rapidly than its volumetric removal rate from vessel 5, resulting in loss of sealing of the bladder B against the aperture 3 resulting of gas leakage from the bladder housing compartment 7 into vessel 5.
  • volumetric removal rate is meant the rate at which the remaining volume of the bladder B is reduced inside the vessel 5 as a result of the bladder B being pulled through the aperture 3 and into bladder housing compartment 7.
  • the gas release rate from the bladder can be controlled by at least three different methods.
  • a first method of controlling the gas release rate from the bladder B in the lower portion 23 of the bladder housing compartment 7, is through monitoring the torque applied to the pulling mechanism 11, 11' and thus apply a selective degree of cut of the bladder B in the lower portion 23 of the bladder housing compartment 7 as a function of required torque above a certain threshold level. Once the required gas release rate is achieved the required torque is reduced and thus the degree of selective cut is similarly reduced.
  • a second method of controlling the gas release rate from the bladder B in the lower portion 23 of the bladder housing compartment 7 is through maintaining a certain degree torque applied to the pulling mechanism 11, 11'. Once a certain torque level is exceeded, the selective cut is applied in increasing degree until the torque level is reduced to within acceptable or desired limits.
  • the torque level of the pulling mechanism 11, 11' will be a proxy for the degree of sealing pressure from the bladder B against the aperture 3 on the inside of vessel 5.
  • the degree of selective cut of the bladder B in the lower portion 23 of the bladder housing compartment 7 is successively reduced in line with reduced degree of torque requirements.
  • a third method of controlling the gas release rate from the bladder B in the lower portion 23 of the bladder housing compartment 7 is through maintaining a constant volumetric extraction rate of the bladder B through controlling the speed of the rollers 11 and/or the rotatable drum 11' whilst monitoring the required torque applied thereto. Once a certain torque level is exceeded, selective slit(s) is/are applied in the lower portion 23 of the bladder housing compartment 7 whilst maintaining the applied torque of the rollers 11 and/or rotatable drum 11' below a predetermined limit. The torque is maintained by varying the rotational speed thereof such that neither the extraction rate of the bladder B nor the upper torque level is exceeded. Once the torque level is below a predetermined level and the maximum predetermined rotational speed of the rollers 11 and/or rotatable drum 11' is achieved, the degree of selective cut through the wall of the bladder B is reduced or withdrawn.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)
  • Massaging Devices (AREA)
  • Mattresses And Other Support Structures For Chairs And Beds (AREA)
  • Earth Drilling (AREA)
  • Supply Devices, Intensifiers, Converters, And Telemotors (AREA)

Claims (8)

  1. Vorrichtung (1) zum Steuern eines Hindurchziehens einer aufblasbaren Blase (B) durch eine Öffnung (3) in einer Wand zwischen einer Kammer (5) und einer an einer Aussenseite der Kammer (5) angeordneten Struktur (7), wobei die Vorrichtung (1) aufweist:
    - einen Zugmechanismus (11, 11'), um die Blase (B) durch die Öffnung (3) zu ziehen;
    - eine Schneidevorrichtung (13), um einen Schlitz in einem Abschnitt der Blase (B) anzufertigen, nachdem der besagte Abschnitt die Öffnung (3) passiert hat, wobei die Schneidevorrichtung (13) reagieren kann auf einen Widerstand der Blase (B) gegen das Passieren der Öffnung (3), sodass die Schneidevorrichtung (13) aktiviert ist und den Schlitz anfertigt, wenn der Widerstand ein vorbestimmtes Niveau übersteigt.
  2. Vorrichtung (1) gemäss Anspruch 1, wobei der Widerstand gemessen wird, indem eine auf den Zugmechanismus wirkende Belastung gemessen wird.
  3. Vorrichtung (1) gemäss Anspruch 1, wobei der Widerstand mittels eines Druckmesssystems gemessen wird, welches in oder an einer Peripherie der Öffnung (3) angeordnet ist, wobei das Druckmesssystem ausgebildet ist, um einen von der Blase (B) ausgeübten Druck zu messen.
  4. Vorrichtung (1) gemäss einem der Ansprüche 1 bis 3, aufweisend eine Steuervorrichtung (15) zur weiteren Steuerung einer Zuggeschwindigkeit des Zugmechanismus' (11, 11'), wobei die Steuervorrichtung (15) auf einen Widerstand der Blase (B) gegen das Passieren der Öffnung (3) reagieren kann, sodass die Zuggeschwindigkeit erhöht wird, wenn der Widerstand verringert wird, und umgekehrt.
  5. Vorrichtung (1) gemäss einem der Ansprüche 1 bis 4, wobei die Schneidevorrichtung (13) ausgebildet ist, um einen oder mehrere Schlitze entlang einer Achse anzufertigen, welche im Wesentlichen parallel zu einer Bewegungsrichtung der Blase (B) durch die Öffnung (3) ist.
  6. Vorrichtung (1) gemäss einem der Ansprüche 1 bis 5, wobei der Zugmechanismus (11, 11') ausgebildet ist, um die Blase (B) zu fälteln, sodass ein Volumen der Blase (B) am Zugmechanismus (11) kleiner ist als eine von einer Peripherie der Öffnung (3) definierte Fläche.
  7. Verfahren zum Ziehen einer aufblasbaren Blase (B) durch eine Öffnung (3) in einer Wand zwischen einer Kammer (5) und einer Struktur (7), wobei das Verfahren beinhaltet:
    - in-Eingriff-Bringen der Blase (B) mit einer Zugvorrichtung (11, 11'), welche ausgebildet ist, um die Blase (B) durch die Öffnung (3) zwischen der Kammer (5) und der an einer Aussenseite der Kammer (5) angeordneten Struktur (7) zu ziehen;
    - Aktivieren der Zugvorrichtung (11, 11') und Messen eines Widerstands der Blase (B), die Öffnung (3) zu passieren, mittels einer Messvorrichtung (15); und
    - wenn der gemessene Widerstand ein vorbestimmtes Niveau übersteigt, Aktivieren einer Schneidevorrichtung (13), welche ausgebildet ist, um einen Schlitz in einem durch die Öffnung hindurch gezogenen Abschnitt der Blase (B) anzufertigen.
  8. Verfahren gemäss Anspruch 7, wobei nach dem Aktivieren der Schneidevorrichtung (13) das Verfahren femer beinhaltet, eine Zuggeschwindigkeit zu steuern, sodass der Widerstand der Blase (B), die Öffnung (3) zu passieren, innerhalb eines vorbestimmten Bereichs liegt.
EP20744266.6A 2019-01-25 2020-01-23 Vorrichtung und verfahren zum steuern eines ziehens einer aufblasbaren blase durch eine öffnung Active EP3914850B1 (de)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NO20190096A NO345292B1 (en) 2019-01-25 2019-01-25 An apparatus and a method for controlling a pulling of an inflatable bladder through an aperture
PCT/NO2020/050011 WO2020153852A1 (en) 2019-01-25 2020-01-23 An apparatus and a method for controlling a pulling of an inflatable bladder through an aperture

Publications (3)

Publication Number Publication Date
EP3914850A1 EP3914850A1 (de) 2021-12-01
EP3914850A4 EP3914850A4 (de) 2022-10-26
EP3914850B1 true EP3914850B1 (de) 2023-08-02

Family

ID=71736483

Family Applications (1)

Application Number Title Priority Date Filing Date
EP20744266.6A Active EP3914850B1 (de) 2019-01-25 2020-01-23 Vorrichtung und verfahren zum steuern eines ziehens einer aufblasbaren blase durch eine öffnung

Country Status (3)

Country Link
EP (1) EP3914850B1 (de)
NO (1) NO345292B1 (de)
WO (1) WO2020153852A1 (de)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NO346713B1 (en) * 2021-05-20 2022-12-05 Ravndal & Moore Projects As An apparatus and a method for extracting a bladder through a constriction

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE542014A (de) * 1954-10-18
JPS51150551A (en) * 1975-06-19 1976-12-24 Nittetsu Kaatenoole Kk An electro deposition method of aluminium or aluminium alloys by alter nating current
GB1543579A (en) * 1975-07-02 1979-04-04 British Petroleum Co Storage tank
JPS58180897A (ja) * 1982-04-19 1983-10-22 Kawasaki Steel Corp ガスホルダ内の残留気体除去方法
US7021488B2 (en) * 2003-03-31 2006-04-04 Matheson Tri-Gas, Inc. Pressure vessel for compressed gases utilizing a replaceable and flexible liner
DE102004043380A1 (de) * 2004-09-03 2006-03-09 SCHÄFER, Friedrich Flüssigkeitsvorrichtung zum Schutz von eingelagerten Stoffen bzw. deren Oberflächen vor Reaktionen mit anderen Medien
NO322558B1 (no) * 2004-09-21 2006-10-23 Ola Ravndal Fremgangsmate ved bruk av volumfortrengende innretning ved skifte av last i et transportmiddel
EP2914893B1 (de) * 2012-11-05 2019-03-13 Environgas AS Verfahren und vorrichtung für den einsatz einer blase in und aus einem behälter
FR2998268B1 (fr) * 2012-11-19 2015-07-17 Eurocopter France Dispositif de stockage de carburant, aeronef et procede

Also Published As

Publication number Publication date
EP3914850A4 (de) 2022-10-26
EP3914850A1 (de) 2021-12-01
NO345292B1 (en) 2020-11-30
NO20190096A1 (en) 2020-07-27
WO2020153852A1 (en) 2020-07-30

Similar Documents

Publication Publication Date Title
EP3170755B1 (de) Düse zum aufblasen und gaseinbringvorrichtung für gastaschen
CN107406185B (zh) 空气缓冲体的充气方法及其充气系统和充气装置
EP3914850B1 (de) Vorrichtung und verfahren zum steuern eines ziehens einer aufblasbaren blase durch eine öffnung
AU606127B2 (en) Method and apparatus for making gas flushed packages
MX2012008056A (es) Sistemas y metodos para limpiar cavidades corporales.
ES2402979T3 (es) Dispositivo para la extracción de líquidos de un envase
US9067378B2 (en) Inflation and sealing device with rotary cutter
US3971437A (en) Apparatus for dewatering boreholes
US4548321A (en) Foil bag
EP3290091B1 (de) Kugelbadvorrichtung
CA2641774A1 (en) Inflation valve assembly
WO2013074782A1 (en) Apparatus and method for displacing air from wine containers
CN2344433Y (zh) 堵漏气囊
GB2506651A (en) A scoring balloon with a balloon body folded over scoring blades
US4666413A (en) Life-saving appliance with a gas-tight covering
WO2016195742A1 (en) On-board re-inflatable containment boom and control system
EP2948536B1 (de) Vorrichtung zum schutz einer flüssigkeit vor oxidation
US20180016762A1 (en) On-board spool-able re-useable containment boom and control system
NO346713B1 (en) An apparatus and a method for extracting a bladder through a constriction
EP3261932B1 (de) Verpackungsvorrichtung mit evakuierungs- und verpackungsverfahren
CN202911164U (zh) 用于堵塞隔膜中的孔的装置
GB2064703A (en) Unblocking and repairing conduits
CN208071018U (zh) 一种pvc篷布的张力调节装置
KR102182480B1 (ko) 정제 및/또는 석유화학 반응기에 고체입자를 장입하기 위한 분배기구 시스템
US4079856A (en) Storage tank seal

Legal Events

Date Code Title Description
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE

PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20210810

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

DAV Request for validation of the european patent (deleted)
DAX Request for extension of the european patent (deleted)
A4 Supplementary search report drawn up and despatched

Effective date: 20220926

RIC1 Information provided on ipc code assigned before grant

Ipc: F17C 3/00 20060101ALI20220920BHEP

Ipc: F17C 1/02 20060101ALI20220920BHEP

Ipc: B65D 90/22 20060101ALI20220920BHEP

Ipc: F17C 7/00 20060101AFI20220920BHEP

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20230327

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602020015049

Country of ref document: DE

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: NL

Ref legal event code: FP

P01 Opt-out of the competence of the unified patent court (upc) registered

Effective date: 20230821

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG9D

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 1595135

Country of ref document: AT

Kind code of ref document: T

Effective date: 20230802

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231103

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231202

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231204

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231102

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231202

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20231103

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20240119

Year of fee payment: 5

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20240118

Year of fee payment: 5

Ref country code: GB

Payment date: 20240118

Year of fee payment: 5

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602020015049

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20240115

Year of fee payment: 5

Ref country code: BE

Payment date: 20240126

Year of fee payment: 5

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20240503

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20230802

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20240123

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20240123