EP3628794A1 - Stair railing, frame system and method for mounting a stair railing - Google Patents

Stair railing, frame system and method for mounting a stair railing Download PDF

Info

Publication number
EP3628794A1
EP3628794A1 EP19197945.9A EP19197945A EP3628794A1 EP 3628794 A1 EP3628794 A1 EP 3628794A1 EP 19197945 A EP19197945 A EP 19197945A EP 3628794 A1 EP3628794 A1 EP 3628794A1
Authority
EP
European Patent Office
Prior art keywords
railing
end section
coupling element
scaffolding system
rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP19197945.9A
Other languages
German (de)
French (fr)
Other versions
EP3628794B1 (en
Inventor
André GAISER
Thomas Buffler
Dr. Tobias SCHMIDT
Julian Hellenschmidt
Tobias Danner
Christian Leder
Franz Winter
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Peri SE
Original Assignee
Peri GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Peri GmbH filed Critical Peri GmbH
Publication of EP3628794A1 publication Critical patent/EP3628794A1/en
Application granted granted Critical
Publication of EP3628794B1 publication Critical patent/EP3628794B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/10Steps or ladders specially adapted for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G27/00Temporary arrangements for giving access from one level to another for men or vehicles, e.g. steps, ramps
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings
    • E04G5/147Railings specially adapted for mounting prior to the mounting of the platform
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/30Scaffolding bars or members with non-detachably fixed coupling elements
    • E04G7/302Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members
    • E04G7/306Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members the added coupling elements are fixed at several bars or members to connect
    • E04G7/308Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members the added coupling elements are fixed at several bars or members to connect without tying means for connecting the bars or members

Abstract

Die Erfindung betrifft ein Treppengeländer (1) für ein Gerüstsystem (2), insbesondere für einen vorgesetzten Treppenaufstieg an einem Fassadengerüst oder einen gleichläufigen Treppenturm, wobei ein erstes Kupplungselement (12, 38) und ein zweites Kupplungselement (14) des zumindest einen Geländerholms (10, 20) durch einen Benutzer aus einer gesicherten Position benachbart zu dem in Einbauposition unteren Endabschnitt (18b) einer Treppe (18) des Gerüstsystems (2) an den Kupplungselementen (14, 24) der Vertikalstützen (16, 26) des Gerüstsystems (2) befestigbar sind. Die Erfindung betrifft des Weiteren ein Gerüstsystem (2) und ein Verfahren zur Montage eines Treppengeländers (1) für das Gerüstsystem (2).The invention relates to a banister (1) for a scaffolding system (2), in particular for an upstairs staircase on a facade scaffolding or a stair tower in the same direction, a first coupling element (12, 38) and a second coupling element (14) of the at least one railing spar (10 , 20) by a user from a secured position adjacent to the lower end section (18b) in the installed position of a staircase (18) of the scaffolding system (2) on the coupling elements (14, 24) of the vertical supports (16, 26) of the scaffolding system (2) are attachable. The invention further relates to a scaffolding system (2) and a method for assembling a banister (1) for the scaffolding system (2).

Description

Hintergrundbackground

Die vorliegende Erfindung betrifft ein Treppengeländer für ein Gerüstsystem. Die Erfindung betrifft des Weiteren ein Gerüstsystem. Die Erfindung betrifft überdies ein Verfahren zur Montage eines Treppengeländers für ein Gerüstsystem.The present invention relates to a banister for a scaffolding system. The invention further relates to a scaffolding system. The invention also relates to a method for assembling a banister for a scaffolding system.

Treppenaufstiege lösen bei Gerüstsystemen mehr und mehr Durchstiegsbeläge ab. Bei einem mit einer oder mehreren Treppen versehenen Gerüstsystem ist es erforderlich, einen Treppenaufgang durch ein entsprechendes Treppengeländer abzusichern.Stairways are increasingly replacing access platforms with scaffolding systems. In the case of a scaffolding system provided with one or more stairs, it is necessary to secure a staircase by means of an appropriate stair railing.

Bestehende Treppengeländer für Gerüstsysteme weisen jedoch den Nachteil auf, dass ein sicherer Auf- und Abbau der Treppengeländer nur dann möglich ist, wenn ein Benutzer eine persönliche Schutzausrüstung gegen Absturz anlegt. Der Aufbau des Treppengeländers für das Gerüstsystem bei Verwendung der persönlichen Schutzausrüstung gegen Absturz ist jedoch komplexer und nimmt mehr Zeit in Anspruch.Existing stair railings for scaffolding systems have the disadvantage, however, that the stair railings can only be assembled and disassembled safely if a user puts on personal protective equipment against falling. However, the construction of the stair railing for the scaffolding system when using personal protective equipment against falling is more complex and takes more time.

Ohne diese entsprechende Schutzausrüstung lassen sich existierende Treppengeländer nicht aus einer sicheren Position heraus montieren, da ein Arbeiter sich hierfür auf die ungesicherte Treppe begeben müsste.Without the appropriate protective equipment, existing stair rails cannot be installed from a safe position, since a worker would have to climb the unsecured staircase for this.

DE 10 2005 028 885 A1 offenbart eine Gerüsttreppe mit zwei separaten Seitenwangen und mehreren separaten Treppenstufenelementen, die sowohl miteinander als auch mit den Seitenwangen lösbar koppelbar sind. Des Weiteren ist ein an entsprechenden Rosetten der Vertikalstützen eingehängtes Treppengeländer vorgesehen. Auch hier muss das Treppengeländer am oberen Bereich der Treppe aus einer ungesicherten Position heraus am oberen Treppenende eingehängt werden, da dies bauartbedingt nicht anders möglich ist. DE 10 2005 028 885 A1 discloses a scaffolding staircase with two separate side walls and a plurality of separate stair tread elements, which can be detachably coupled both to one another and to the side walls. Furthermore, a stair railing is attached to the corresponding rosettes of the vertical supports. Here, too, the stair railing at the top of the staircase must be hung from an unsecured position at the top of the stair, as this cannot be done otherwise due to the design.

Offenbarung der ErfindungDisclosure of the invention

Die vorliegende Erfindung betrifft ein Treppengeländer für ein Gerüstsystem nach Anspruch 1, ein Gerüstsystem nach Anspruch 12 und ein Verfahren zur Montage eines Treppengeländers für ein Gerüstsystem nach Anspruch 16.The present invention relates to a banister for a scaffolding system according to claim 1, a scaffolding system according to claim 12 and a method for assembling a banister for a scaffolding system according to claim 16.

Weitere Ausführungsformen der vorliegenden Erfindung sind Gegenstand der weiteren Unteransprüche und der nachfolgenden Beschreibung unter Bezugnahme auf die Figuren.Further embodiments of the present invention are the subject of the further subclaims and the following description with reference to the figures.

Ein Aspekt der vorliegenden Erfindung bezieht sich auf ein Treppengeländer für ein Gerüstsystem, insbesondere für einen vorgesetzten Treppenaufstieg an einem Fassadengerüst oder einen gleichläufigen Treppenturm, mit zumindest einem Geländerholm, welcher einen ersten Endabschnitt aufweist, an dem ein erstes Kupplungselement angeordnet ist, wobei das erste Kupplungselement dazu ausgebildet ist, an einem zweiten Kupplungselement einer Vertikalstütze des Gerüstsystems benachbart zu einem in Einbauposition oberen Endabschnitt einer Treppe des Gerüstsystems befestigt zu werden, wobei der zumindest eine Geländerholm einen zweiten Endabschnitt aufweist, an dem ein drittes Kupplungselement angeordnet ist, wobei das dritte Kupplungselement dazu ausgebildet ist, an einem vierten Kupplungselement einer weiteren Vertikalstütze des Gerüstsystems benachbart zu einem in Einbauposition unteren Endabschnitt der Treppe des Gerüstsystems befestigt zu werden, und wobei das erste Kupplungselement und das dritte Kupplungselement des zumindest einen Geländerholms dazu ausgebildet sind, durch einen Benutzer aus einer gesicherten Position benachbart zu dem in Einbauposition unteren Endabschnitt der Treppe des Gerüstsystems an den Kupplungselementen der Vertikalstützen des Gerüstsystems befestigt zu werden.One aspect of the present invention relates to a stair railing for a scaffolding system, in particular for a front staircase on a facade scaffolding or a co-rotating stair tower, with at least one railing rail which has a first end section on which a first coupling element is arranged, the first coupling element is designed, on a second coupling element, of a vertical support of the scaffolding system adjacent to an in Installation position to be attached to the upper end section of a staircase of the scaffolding system, the at least one railing rail having a second end section on which a third coupling element is arranged, the third coupling element being designed to adjoin a fourth vertical coupling element of a further vertical support of the scaffolding system Installation position to be fixed lower end portion of the stairs of the scaffolding system, and wherein the first coupling element and the third coupling element of the at least one railing spar are designed by a user from a secured position adjacent to the lower end portion of the stairs of the scaffolding system in the installation position on the coupling elements of the Vertical supports to be attached to the scaffolding system.

Ein weiterer Aspekt bezieht sich auf ein Gerüstsystem, insbesondere einen vorgesetzten Treppenaufstieg an einem Fassadengerüst oder ein gleichläufiger Treppenturm mit dem erfindungsgemäßen Treppengeländer.Another aspect relates to a scaffolding system, in particular a front staircase on a facade scaffolding or a co-rotating stair tower with the stair railing according to the invention.

Ein weiterer Aspekt bezieht sich auf ein Verfahren zur Montage eines Treppengeländers für ein Gerüstsystem, insbesondere für einen vorgesetzten Treppenaufstieg an einem Fassadengerüst oder einen gleichläufigen Treppenturm. Das Verfahren umfasst ein Bereitstellen zumindest eines Geländerholms mit einem ersten Endabschnitt, an dem ein erstes Kupplungselement angeordnet ist, und mit einem zweiten Endabschnitt, an dem ein drittes Kupplungselement angeordnet ist.Another aspect relates to a method for assembling a banister for a scaffolding system, in particular for an upstairs staircase on a facade scaffolding or a co-rotating stair tower. The method comprises providing at least one railing rail with a first end section on which a first coupling element is arranged and with a second end section on which a third coupling element is arranged.

Das Verfahren umfasst des Weiteren ein Befestigen des ersten Kupplungselements an einem zweiten Kupplungselement einer Vertikalstütze des Gerüstsystems benachbart zu einem in Einbauposition oberen Endabschnitt einer Treppe des Gerüstsystems.The method further comprises fastening the first coupling element to a second coupling element of a vertical support of the scaffolding system adjacent to an upper end section of a staircase of the scaffolding system in the installed position.

Das Verfahren umfasst ferner ein Befestigen des dritten Kupplungselements an einem vierten Kupplungselement einer weiteren Vertikalstütze des Gerüstsystems benachbart zu einem in Einbauposition unteren Endabschnitt der Treppe des Gerüstsystems, wobei das erste Kupplungselement und das dritte Kupplungselement des zumindest einen Geländerholms durch einen Benutzer aus einer gesicherten Position benachbart zu dem in Einbauposition unteren Endabschnitt der Treppe des Gerüstsystems an den Kupplungselementen der Vertikalstützen des Gerüstsystems befestigt werden.The method further comprises fastening the third coupling element to a fourth coupling element of a further vertical support of the scaffolding system adjacent to a lower end section of the stairs of the scaffolding system in the installation position, the first coupling element and the third coupling element of the at least one railing rail being adjacent by a user from a secured position to the lower end section of the stairs of the scaffolding system in the installed position on the coupling elements of the vertical supports of the scaffolding system.

Die Idee der vorliegenden Erfindung besteht darin, durch Vorsehen des zumindest einen Geländerholms des Treppengeländers derart, dass das Treppengeländer durch einen Benutzer aus einer gesicherten Position benachbart zu dem in Einbauposition unteren Endabschnitt der Treppe des Gerüstsystems an den Kupplungselementen der Vertikalstützen des Gerüstsystems befestigbar ist, eine verbesserte Montagesicherheit des Treppengeländers zu ermöglichen.The idea of the present invention is to provide the at least one railing spar of the stair railing in such a way that the stair railing can be fastened to the coupling elements of the vertical supports of the scaffolding system by a user from a secured position adjacent to the lower end section of the stairs of the scaffolding system in the installed position to enable improved assembly safety of the banister.

Dadurch kann ein sicherer Auf- und Abbau des Treppengeländers bei sowohl einem vorgesetzten Treppenaufstieg an einem Fassadengerüst als auch einem gleichläufigen Treppenturm, ohne das Anlegen der persönlichen Schutzausrüstung gegen Absturz durch den Benutzer ermöglicht werden.As a result, the stair railing can be safely assembled and dismantled with both an upstairs staircase on a facade scaffold and a co-rotating stair tower, without having to put on the personal protective equipment against falls by the user.

Gemäß einer bevorzugten Weiterbildung ist vorgesehen, dass der zumindest eine Geländerholm einen sich axial erstreckenden, rohrförmig ausgebildeten Mittenabschnitt, den sich an einen ersten axialen Endabschnitt des Mittenabschnitts anschließenden ersten Endabschnitt des zumindest einen Geländerholms, und den sich an einen zweiten axialen Endabschnitt des Mittenabschnitts anschließenden zweiten Endabschnitt des zumindest einen Geländerholms aufweist, wobei der erste Endabschnitt und der zweite Endabschnitt des zumindest einen Geländerholms in einem vorgegebenen Winkel zu dem Mittenabschnitt geneigt sind.According to a preferred development, it is provided that the at least one railing spar has an axially extending, tubular center section, the first end section of the at least one railing spar adjoining a first axial end section of the center section, and the second one adjoining a second axial end section of the center section End portion of the at least one railing spar, wherein the first end portion and the second end portion of the at least one railing spar are inclined at a predetermined angle to the central portion.

Somit kann der Geländerholm durch entsprechende Bestimmung der Winkel an jeweilige Voraussetzungen bzw. Gegebenheiten des Gerüstsystems angepasst werden.The railing spar can thus be adapted to the respective requirements or conditions of the scaffolding system by determining the angles accordingly.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass der Mittenabschnitt des zumindest einen Geländerholms dazu ausgebildet ist, in Einbauposition des zumindest einen Geländerholms parallel zu der benachbarten Treppe angeordnet zu werden, und wobei der erste Endabschnitt und der zweite Endabschnitt des zumindest einen Geländerholms dazu ausgebildet sind, in Einbauposition des zumindest einen Geländerholms parallel zu einem Boden, auf dem das Gerüstsystem errichtet ist, angeordnet zu werden.According to a further preferred development, it is provided that the central section of the at least one railing spar is designed to be arranged parallel to the adjacent staircase in the installation position of the at least one railing spar, and the first end section and the second end section of the at least one railing spar are designed for this purpose , to be arranged in the installation position of the at least one railing spar parallel to a floor on which the scaffolding system is erected.

Somit passt sich der Geländerholm in vorteilhafter Weise optimal an eine Einbaugeometrie der Treppe in das Gerüstsystem an.The railing rail therefore advantageously adapts optimally to an installation geometry of the stairs in the scaffolding system.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass sich das erste Kupplungselement an den ersten Endabschnitt des zumindest einen Geländerholms anschließt, wobei das erste Kupplungselement an einem zu dem ersten Endabschnitt des zumindest einen Geländerholms benachbarten ersten Endabschnitt rohrförmig ausgebildet und an einem zweiten Endabschnitt im Wesentlichen flach ausgebildet ist.According to a further preferred development, it is provided that the first coupling element adjoins the first end section of the at least one railing rail, the first coupling element being tubular at a first end section adjacent to the first end section of the at least one railing rail and essentially flat at a second end section is trained.

Somit kann der Geländerholm in vorteilhafter Weise einfach an entsprechenden Kupplungselementen des Gerüstsystems befestigt werden.Thus, the railing rail can advantageously be easily attached to corresponding coupling elements of the scaffolding system.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass das erste Kupplungselement an dem zweiten Endabschnitt eine Öffnung aufweist, welche in Einbauposition des ersten Kupplungselements einen an einer Unterseite des im Wesentlichen flach ausgebildeten zweiten Endabschnitts im Wesentlichen vertikalen Abschnitt und einen sich an den vertikalen Abschnitt anschließenden, durch einen bogenförmigen Verbindungsabschnitt mit dem vertikalen Abschnitt verbundenen, horizontalen Abschnitt aufweist.According to a further preferred development, it is provided that the first coupling element has an opening on the second end section, which in the installed position of the first coupling element has a section which is essentially vertical on an underside of the essentially flat second section and a section which adjoins the vertical section. has a horizontal portion connected to the vertical portion by an arcuate connecting portion.

Das erste Kupplungselement ist somit in vorteilhafter Weise derart ausgebildet, dass dieses in einfacher und sicherer Art und Weise an einem entsprechenden Kupplungselement des Gerüstsystems befestigbar ist. Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass das erste Kupplungselement dazu ausgebildet ist, mit der Öffnung in das an der Vertikalstütze des Gerüstsystems angeordnete, insbesondere stiftförmig ausgebildete, zweite Kupplungselement eingehängt zu werden.The first coupling element is thus advantageously designed such that it can be fastened to a corresponding coupling element of the scaffolding system in a simple and secure manner. According to a further preferred development, it is provided that the first coupling element is designed to be hung with the opening in the second coupling element which is arranged on the vertical support of the scaffolding system, in particular in the form of a pin.

Aufgrund der einfachen Einhängbarkeit des ersten Kupplungselements in das stiftförmig ausgebildete zweite Kupplungselement kann das Einhängen des zumindest einen Geländerholms durch den Benutzer aus einer gesicherten Position heraus erfolgen.Because the first coupling element can be easily hooked into the pin-shaped second coupling element, the at least one railing rail can be hooked in by the user from a secured position.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass sich das dritte Kupplungselement an den zweiten Endabschnitt des zumindest einen Geländerholms anschließt, wobei das dritte Kupplungselement an einem zu dem zweiten Endabschnitt des zumindest einen Geländerholms benachbarten ersten Endabschnitt rohrförmig ausgebildet und an einem zweiten Endabschnitt im Wesentlichen flach ausgebildet ist.According to a further preferred development, it is provided that the third coupling element adjoins the second end section of the at least one railing spar, the third coupling element being tubular on a first end section adjacent to the second end section of the at least one railing spar and essentially flat on a second end section is trained.

Somit kann der Geländerholm in vorteilhafter Weise einfach an entsprechenden Kupplungselementen des Gerüstsystems befestigt werden.Thus, the railing rail can advantageously be easily attached to corresponding coupling elements of the scaffolding system.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass das dritte Kupplungselement an dem zweiten Endabschnitt eine Öffnung aufweist, an welcher das dritte Kupplungselement in das, an der weiteren Vertikalstütze des Gerüstsystems angeordnete, insbesondere stiftförmig ausgebildete, vierte Kupplungselement einhängbar ist. Aufgrund der einfachen Einhängbarkeit des dritten Kupplungselements in das stiftförmig ausgebildete vierte Kupplungselement kann das Einhängen des zumindest einen Geländerholms durch den Benutzer aus einer gesicherten Position heraus erfolgen.According to a further preferred development, it is provided that the third coupling element has an opening at the second end section, at which the third coupling element into the fourth, in particular pin-shaped, arranged on the further vertical support of the scaffolding system Coupling element can be hooked. Because the third coupling element can be easily hooked into the fourth coupling element designed in the form of a pin, the at least one railing rail can be hooked in by the user from a secured position.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass das Treppengeländer einen ersten Geländerholm, insbesondere einen Knieholm, und einen von dem ersten Geländerholm getrennt ausgebildeten zweiten Geländerholm, insbesondere einen Handlaufholm, aufweist, wobei der erste Geländerholm und der zweite Geländerholm identisch ausgebildet sind.According to a further preferred development, it is provided that the stair railing has a first railing rail, in particular a knee rail, and a second railing rail, in particular a handrail rail, which is separate from the first railing rail, the first railing rail and the second railing rail being configured identically.

Die identische Ausbildung der jeweiligen Geländerholme ermöglicht eine einfache und zeitsparende Montierbarkeit, da es nicht zu einer Verwechslung unterschiedlicher Geländerholme kommen kann. Des Weiteren bringt die voneinander getrennte Ausbildung der Geländerholme den Vorteil mit sich, dass diese ein geringeres Gewicht und dadurch bedingt eine einfachere Montierbarkeit durch den Benutzer ermöglichen.The identical design of the respective railing spars enables simple and time-saving assembly, since there can be no confusion between different railing spars. Furthermore, the separate design of the railing rails has the advantage that they are lighter in weight and therefore easier to install by the user.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass der erste Geländerholm und der zweite Geländerholm im Bereich des ersten Endabschnitts durch ein stiftförmig ausgebildetes erstes Verbindungselement, insbesondere einen Steckbolzen, verbunden sind, und wobei der erste Geländerholm und der zweite Geländerholm im Bereich des zweiten Endabschnitts durch ein stiftförmig ausgebildetes zweites Verbindungselement, insbesondere einen Steckbolzen, verbunden sind. Das Vorsehen des Steckbolzens erhöht in vorteilhafter Weise die Stabilität des Treppengeländers.According to a further preferred development, it is provided that the first railing rail and the second railing rail are connected in the region of the first end section by a pin-shaped first connecting element, in particular a plug pin, and the first railing rail and the second railing rail are connected in the region of the second end section a pin-shaped second connecting element, in particular a socket pin, are connected. The provision of the Pin bolt increases the stability of the banister in an advantageous manner.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass das erste Verbindungselement und das zweite Verbindungselement im Bereich des zweiten Geländerholms eine Federklammer aufweisen, welche dazu ausgebildet ist, das erste Verbindungselement und das zweite Verbindungselement an dem zweiten Geländerholm zu sichern. Somit können die Verbindungselemente in einfacher Art und Weise an den Geländerholmen gesichert werden.According to a further preferred development, it is provided that the first connecting element and the second connecting element have a spring clip in the region of the second railing spar which is designed to secure the first connecting element and the second connecting element to the second railing spar. Thus, the connecting elements can be secured to the railing rails in a simple manner.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass das Treppengeländer am Gerüstsystem vorlaufend, insbesondere an einer von einer zu dem Gerüstsystem benachbarten Fassade abgewandten Seite des Gerüstsystems, angeordnet ist. Somit kann in vorteilhafter Weise ein sicherer Treppenaufgang am Gerüstsystem bereitgestellt werden.According to a further preferred development, it is provided that the stair railing is arranged in advance on the scaffolding system, in particular on a side of the scaffolding system facing away from a facade adjacent to the scaffolding system. Thus, a safe staircase can advantageously be provided on the scaffolding system.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass das Gerüstsystem an einem unteren Endabschnitt einer Treppe ein Podest und in derselben horizontalen Ebene als das Podest einen benachbart zu dem Podest angeordneten Belag aufweist, wobei ein weiterer Geländerholm an einem ersten axialen Endabschnitt mit einer ersten Vertikalstütze lösbar verbunden ist, an welcher das Podest und der Belag befestigt sind, wobei der weitere Geländerholm an einem zweiten axialen Endabschnitt mit einer zweiten Vertikalstütze lösbar verbunden ist, an welcher das Podest und der Belag befestigt sind, und wobei der weitere Geländerholm dazu ausgebildet ist, durch räumliche Trennung der Ebene des Podests und des Belags eine gesicherte Position des Benutzers zur Montage des Treppengeländers für das Gerüstsystem bereitzustellen. Somit kann durch Vorsehen des weiteren Geländerholms in vorteilhafter Weise eine abgesicherte Arbeitsposition des Benutzers zur Montage des Treppengeländers bereitgestellt werden.According to a further preferred development, it is provided that the scaffolding system has a pedestal on a lower end section of a staircase and, in the same horizontal plane as the pedestal, a covering arranged adjacent to the pedestal, a further railing rail being releasable at a first axial end section with a first vertical support is connected to which the pedestal and the covering are fastened, the further railing rail being detachably connected at a second axial end section to a second vertical support on which the pedestal and the covering are fixed, and wherein the further railing spar is designed to provide a secure position of the user for mounting the stair railing for the scaffolding system by spatial separation of the level of the platform and the covering. Thus, by providing the additional railing spar, a secured working position of the user for mounting the stair railing can advantageously be provided.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass die Vertikalstütze als ein erstes Teil und ein mit dem ersten Teil durch eine Steckverbindung verbindbares zweites Teil ausgebildet ist, wobei im Montagezustand der Vertikalstütze das zweite Teil durch die Steckverbindung auf das erste Teil aufgesetzt ist, wobei das zweite Teil ein daran montiertes oder integral mit diesem ausgebildetes Stirngeländer aufweist.According to a further preferred development, it is provided that the vertical support is designed as a first part and a second part which can be connected to the first part by a plug connection, the second part being placed on the first part by the plug connection in the assembled state of the vertical support, the second part has an end railing mounted thereon or integrally formed therewith.

Somit kann das Stirngeländer einer nächsten Etage bereits bei Montage der Vertikalstütze, d.h. vor Montage der Treppe und der Geländerholme des Treppengeländers aus einer sicheren Position heraus montiert werden. Die sichere Position liegt hierbei eine Etage unter dem zu montierenden Stirngeländer.Thus, the front railing of a next floor can already be installed when the vertical support, i.e. before installing the stairs and the railing rails of the banister from a safe position. The safe position is one floor below the front railing to be installed.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass das Gerüstsystem an einem unteren Endabschnitt einer Treppe mit einem Podest und in derselben horizontalen Ebene als das Podest mit einem benachbart zu dem Podest angeordneten Belag bereitgestellt wird, wobei ein weiterer Geländerholm an einem ersten axialen Endabschnitt mit einer ersten Vertikalstütze lösbar verbunden wird, an welcher das Podest und der Belag befestigt sind, wobei der weitere Geländerholm an einem zweiten axialen Endabschnitt mit einer zweiten Vertikalstütze lösbar verbunden wird, an welcher das Podest und der Belag befestigt sind, und wobei der weitere Geländerholm durch räumliche Trennung der Ebene des Podests und des Belags eine gesicherte Position des Benutzers zur Montage des Treppengeländers für das Gerüstsystem bereitstellt.According to a further preferred development, it is provided that the scaffolding system is provided at a lower end section of a staircase with a platform and in the same horizontal plane as the platform with a covering arranged adjacent to the platform, a further railing rail at a first axial end section with a first Vertical support is releasably connected to which the pedestal and the covering are fastened, the further railing spar being releasably connected at a second axial end section to a second vertical support to which the pedestal and the covering are fastened, and the further railing spar by spatial separation the level of the platform and the covering provides a secure position for the user to assemble the banister for the scaffolding system.

Somit kann durch Vorsehen des weiteren Geländerholms in vorteilhafter Weise eine abgesicherte Arbeitsposition des Benutzers zur Montage des Treppengeländers bereitgestellt werden.Thus, by providing the additional railing spar, a secured working position of the user for mounting the stair railing can be provided in an advantageous manner.

Gemäß einer weiteren bevorzugten Weiterbildung ist vorgesehen, dass die Vertikalstütze als ein erstes Teil und ein mit dem ersten Teil durch eine Steckverbindung verbindbares zweites Teil bereitgestellt wird, wobei zuerst das erste Teil montiert wird und anschließend das zweite Teil durch die Steckverbindung auf das erste Teil aufgesetzt wird, und wobei das zweite Teil mit einem daran vormontierten oder integral ausgebildeten Stirngeländer bereitgestellt wird.According to a further preferred development, it is provided that the vertical support is provided as a first part and a second part which can be connected to the first part by a plug connection, the first part being mounted first and then the second part being placed on the first part by the plug connection is, and wherein the second part is provided with a pre-assembled or integrally formed front railing.

Somit kann das Stirngeländer einer nächsten Etage bereits bei Montage der Vertikalstütze, d.h. vor Montage der Treppe und der Geländerholme des Treppengeländers aus einer sicheren Position heraus montiert werden. Die sichere Position liegt hierbei eine Etage unter dem zu montierenden Stirngeländer.Thus, the front railing of a next floor can already be installed from a safe position when installing the vertical support, ie before installing the stairs and the railing rails of the stair railing. The safe position is one floor below the front railing to be installed.

Die hierin beschriebenen Merkmale des Treppengeländers sind für die Verwendung mit jedem Gerüstsystem offenbart. Alternativ kann das erfindungsgemäße Treppengeländer beispielsweise in einem anderen Kontext als im Rahmen von Gerüstsystemen Anwendung finden, bei welchen es einer Sicherung des Treppenaufgangs durch Vorsehen eines Treppengeländers bedarf.The features of the banister described herein are disclosed for use with any scaffolding system. Alternatively, the banister according to the invention can be used, for example, in a different context than in the context of scaffolding systems, in which securing the stairway by providing a banister is required.

Kurze Beschreibung der ZeichnungenBrief description of the drawings

Zum besseren Verständnis der vorliegenden Erfindung und ihrer Vorteile wird nun auf die nachfolgende Beschreibung in Verbindung mit den dazugehörigen Zeichnungen verwiesen. Nachfolgend wird die Erfindung anhand exemplarischer Ausführungsformen näher erläutert, die in den schematischen Abbildungen der Zeichnungen angegeben sind. Es zeigen:

Fig. 1
eine schematische Ansicht eines gleichläufigen Treppenturms mit einem Treppengeländer gemäß einer bevorzugten Ausführungsform der Erfindung;
Fig. 1a
eine schematische Ansicht eines vorgesetzten Treppenaufstiegs an einem Fassadengerüst gemäß einer weiteren bevorzugten Ausführungsform der Erfindung;
Fig. 2
eine schematische Ansicht des Treppengeländers für ein Gerüstsystem gemäß der bevorzugten Ausführungsform der Erfindung;
Fig. 3
eine schematische Ansicht eines Verbindungselements zum Verbinden benachbarter Geländerholme des Treppengeländers gemäß der bevorzugten Ausführungsform der Erfindung;
Fig. 4
eine schematische Ansicht eines ersten Kupplungselements des Geländerholms gemäß der bevorzugten Ausführungsform der Erfindung;
Fig. 5
eine schematische Ansicht eines ersten Kupplungselements des Geländerholms gemäß der bevorzugten Ausführungsform der Erfindung;
Fig. 6
eine schematische Ansicht eines ersten Kupplungselements des Geländerholms gemäß der bevorzugten Ausführungsform der Erfindung;
Fig. 7
eine schematische Ansicht eines dritten Kupplungselements des Geländerholms gemäß der bevorzugten Ausführungsform der Erfindung;
Fig. 8
eine schematische Ansicht eines dritten Kupplungselements des Geländerholms gemäß der bevorzugten Ausführungsform der Erfindung; und
Fig. 9
ein Ablaufdiagramm eines Verfahrens zur Montage des Treppengeländers für das Gerüstsystem gemäß der bevorzugten Ausführungsform der Erfindung.
For a better understanding of the present invention and its advantages, reference is now made to the following description in conjunction with the associated drawings. The invention is explained in more detail below on the basis of exemplary embodiments which are specified in the schematic illustrations of the drawings. Show it:
Fig. 1
is a schematic view of a co-rotating stair tower with a banister according to a preferred embodiment of the invention;
Fig. 1a
a schematic view of a front staircase on a facade scaffold according to a further preferred embodiment of the invention;
Fig. 2
is a schematic view of the banister for a scaffolding system according to the preferred embodiment of the invention;
Fig. 3
is a schematic view of a connecting element for connecting adjacent railing spars of the banister according to the preferred embodiment of the invention;
Fig. 4
is a schematic view of a first coupling element of the railing spar according to the preferred embodiment of the invention;
Fig. 5
is a schematic view of a first coupling element of the railing spar according to the preferred embodiment of the invention;
Fig. 6
is a schematic view of a first coupling element of the railing spar according to the preferred embodiment of the invention;
Fig. 7
is a schematic view of a third coupling element of the railing spar according to the preferred embodiment of the invention;
Fig. 8
is a schematic view of a third coupling element of the railing spar according to the preferred embodiment of the invention; and
Fig. 9
a flowchart of a method for assembling the banister for the scaffolding system according to the preferred embodiment of the invention.

Sofern nicht anders angegeben, bezeichnen gleiche Bezugszeichen gleiche Elemente der Zeichnungen.Unless otherwise stated, the same reference symbols denote the same elements in the drawings.

Ausführliche Beschreibung der AusführungsformenDetailed description of the embodiments

Fig. 1 zeigt eine schematische Ansicht eines Gerüstsystems mit einem Treppengeländer gemäß einer bevorzugten Ausführungsform der Erfindung. Fig. 1 shows a schematic view of a scaffolding system with a banister according to a preferred embodiment of the invention.

Das Treppengeländer 1 für das Gerüstsystem 2, ist am Beispiel eines gleichläufigen Treppenturms gezeigt und weist zumindest einen Geländerholm 10, 20 auf, welcher einen ersten Endabschnitt 10a, 20a aufweist, an dem ein erstes Kupplungselement 12, 38 angeordnet ist. Das Vorsehen eines weiteren Treppenholm, der in Fig. 1 beispielhaft dargestellt ist, ist optional.The stair railing 1 for the scaffolding system 2 is shown using the example of a co-rotating stair tower and has at least one railing rail 10, 20 which has a first end section 10a, 20a on which a first coupling element 12, 38 is arranged. The provision of another stair spar, which in Fig. 1 is exemplified is optional.

Das erste Kupplungselement 12, 38 ist dazu ausgebildet, an einem zweiten Kupplungselement 14 einer Vertikalstütze 16 des Gerüstsystems 2 benachbart zu einem in Einbauposition oberen Endabschnitt 18a einer Treppe des Gerüstsystems 2 befestigt zu werden.The first coupling element 12, 38 is designed to be fastened to a second coupling element 14 of a vertical support 16 of the scaffolding system 2 adjacent to an upper end section 18a of a staircase of the scaffolding system 2 in the installed position.

Der zumindest eine Geländerholm 10, 20 weist einen zweiten Endabschnitt 10b, 20b auf, an dem ein drittes Kupplungselement 22, 40 angeordnet ist.The at least one railing rail 10, 20 has a second end section 10b, 20b, on which a third coupling element 22, 40 is arranged.

Das dritte Kupplungselement 22, 40 ist dazu ausgebildet, an einem vierten Kupplungselement 24 einer weiteren Vertikalstütze 26 des Gerüstsystems 2 benachbart zu einem in Einbauposition unteren Endabschnitt 18b der Treppe 18 des Gerüstsystems 2 befestigt zu werden.The third coupling element 22, 40 is designed to be attached to a fourth coupling element 24 of a further vertical support 26 of the scaffolding system 2 adjacent to a lower end section 18b of the stairs 18 of the scaffolding system 2 in the installed position.

Das erste Kupplungselement 12, 38 und das dritte Kupplungselement 22, 40 des zumindest einen Geländerholms 10, 20 sind dazu ausgebildet, durch einen Benutzer aus einer gesicherten Position benachbart zu dem in Einbauposition unterem Endabschnitt 18b der Treppe 18 des Gerüstsystems 2 an den Kupplungselementen 14, 24 der Vertikalstützen 16, 26 des Gerüstsystems 2 befestigt zu werden.The first coupling element 12, 38 and the third coupling element 22, 40 of the at least one railing spar 10, 20 are designed to be fastened to the coupling elements 14, 24 of the vertical supports 16, 26 of the scaffolding system 2 by a user from a secured position adjacent to the lower end section 18b of the stairs 18 of the scaffolding system 2 in the installed position.

Die gesicherte Einbauposition ist eine Position, an welcher der Benutzer ohne Verwenden einer persönlichen Schutzausrüstung gegen Absturz das Treppengeländer 1 sicher, d.h. nicht absturzgefährdet, am Gerüstsystem 2 montieren kann.The secured installation position is a position at which the user can secure the stair railing 1 without using personal protective equipment against falling, i.e. not at risk of falling, can be mounted on scaffolding system 2.

Der Mittenabschnitt 10c, 20c des zumindest einen Geländerholms 10, 20 ist vorzugsweise dazu ausgebildet, in Einbauposition des zumindest einen Geländerholms 10, 20 parallel zu der benachbarten Treppe 18 angeordnet zu werden.The central section 10c, 20c of the at least one railing spar 10, 20 is preferably designed to be arranged parallel to the adjacent staircase 18 in the installed position of the at least one railing spar 10, 20.

Der erste Endabschnitt 10a, 20a und der zweite Endabschnitt 10b, 20b des zumindest einen Geländerholms 10, 20 ist dazu ausgebildet, in Einbauposition des zumindest einen Geländerholms 10, 20 parallel zu einem Boden 28, auf dem das Gerüstsystem 2 errichtet ist, angeordnet zu werden.The first end section 10a, 20a and the second end section 10b, 20b of the at least one railing spar 10, 20 are designed to be arranged in the installed position of the at least one railing spar 10, 20 parallel to a floor 28 on which the scaffolding system 2 is erected .

Das erste Kupplungselement 12, 38 schließt sich an den ersten Endabschnitt 10a, 20a des zumindest einen Geländerholms 10, 20 an. Das erste Kupplungselement 12, 38 ist an einem zu dem ersten Endabschnitt 10a, 20a des zumindest einen Geländerholms 10, 20 benachbarten ersten Endabschnitt 12a rohrförmig ausgebildet und an einem zweiten Endabschnitt 12b im Wesentlichen flach ausgebildet.The first coupling element 12, 38 adjoins the first end section 10a, 20a of the at least one railing rail 10, 20. The first coupling element 12, 38 is tubular on a first end section 12a adjacent to the first end section 10a, 20a of the at least one railing spar 10, 20 and on one second end portion 12b formed substantially flat.

Das Treppengeländer 1 weist gemäß der gezeigten beispielhaften Ausführungsform einen ersten Geländerholm 10, insbesondere einen Knieholm, und einen von dem ersten Geländerholm 10 getrennt ausgebildeten zweiten Geländerholm 20, insbesondere einen Handlaufholm, auf.According to the exemplary embodiment shown, the stair railing 1 has a first railing rail 10, in particular a knee rail, and a second railing rail 20, in particular a handrail rail, which is separate from the first railing rail 10.

Der erste Geländerholm 10 und der zweite Geländerholm 20 sind hierbei identisch ausgebildet. Alternativ können der erste Geländerholm 10 und der zweite Geländerholm 20 beispielsweise unterschiedlich ausgebildet sein.The first railing rail 10 and the second railing rail 20 are of identical design. Alternatively, the first railing spar 10 and the second railing spar 20 can be designed differently, for example.

Das Treppengeländer 1 ist des Weiteren am Gerüstsystem 2 vorlaufend, insbesondere an einer von einer zu dem Gerüstsystem 2 benachbarten Fassade abgewandten Seite des Gerüstsystems 2, angeordnet.The stair railing 1 is also arranged in advance on the scaffolding system 2, in particular on a side of the scaffolding system 2 facing away from a facade adjacent to the scaffolding system 2.

Das Gerüstsystem 2 weist an einem unteren Endabschnitt 49a einer Treppe 49 ein Podest 45 bzw. einen Treppenauftritt und in derselben horizontalen Ebene als das Podest 45 einen benachbart zu dem Podest 45 angeordneten Belag 47 auf.The scaffolding system 2 has a platform 45 or a stair tread on a lower end section 49a of a staircase 49 and, in the same horizontal plane as the platform 45, a covering 47 arranged adjacent to the platform 45.

Ein weiterer Geländerholm 46 ist an einem ersten axialen Endabschnitt 46a mit einer ersten Vertikalstütze 48 lösbar verbunden, an welcher das Podest 45 und der Belag 47 befestigt sind.Another railing rail 46 is detachably connected at a first axial end section 46a to a first vertical support 48, to which the platform 45 and the covering 47 are fastened.

Der weitere Geländerholm 46 ist an einem zweiten axialen Endabschnitt 46b mit einer zweiten Vertikalstütze 50 lösbar verbunden, an welcher das Podest 45 und der Belag 47 befestigt sind.The further railing rail 46 is at a second axial end section 46b with a second vertical support 50 releasably connected to which the platform 45 and the covering 47 are attached.

Der weitere Geländerholm 46 ist dazu ausgebildet, durch räumliche Trennung der Ebene des Podests 45 und des Belags 47 eine gesicherte Position des Benutzers zur Montage des Treppengeländers 1 für das Gerüstsystem 2 bereitzustellen.The further railing rail 46 is designed to provide a secure position of the user for mounting the stair railing 1 for the scaffolding system 2 by spatial separation of the level of the platform 45 and the covering 47.

Die Vertikalstütze 16 ist als ein erstes Teil 16a und ein mit dem ersten Teil 16a durch eine Steckverbindung 17 verbindbares zweites Teil 16b ausgebildet.The vertical support 16 is designed as a first part 16a and a second part 16b which can be connected to the first part 16a by a plug connection 17.

Im Montagezustand der Vertikalstütze 16 ist das zweite Teil 16b durch die Steckverbindung 17 auf das erste Teil 16a aufgesetzt, wobei das zweite Teil 16b ein daran montiertes oder integral mit diesem ausgebildetes Stirngeländer 42 aufweist.In the assembled state of the vertical support 16, the second part 16b is placed on the first part 16a by the plug connection 17, the second part 16b having an end railing 42 mounted thereon or integrally formed therewith.

Fig. 1a zeigt eine schematische Ansicht eines vorgesetzten Treppenaufstiegs an einem Fassadengerüst gemäß einer weiteren bevorzugten Ausführungsform der Erfindung. Fig. 1a shows a schematic view of a front stair climb on a facade scaffold according to a further preferred embodiment of the invention.

Das Treppengeländer 1 für das Gerüstsystem 2 ist am Beispiel des vorgesetzten Treppenaufstiegs an einem Fassadengerüst dargestellt. Das Gerüstsystem 2 ist an einer Fassade 3 errichtet bzw. aufgestellt. Das Treppengeländer 1 weist zumindest einen Geländerholm 10, 20 auf.The banister 1 for the scaffolding system 2 is shown using the example of the upstairs staircase on a facade scaffolding. The scaffolding system 2 is erected or erected on a facade 3. The stair railing 1 has at least one railing rail 10, 20.

Im Gegensatz zu der in Fig. 1 gezeigten Ausführungsform ist der Treppenaufstieg dem Gerüstsystem 2 vorgesetzt, d.h. weist lediglich eine horizonale Trittebene im Bereich der Treppe 18 auf, wobei der Benutzer zum Erreichen einer weiteren Treppe 52 einen Belag 47 des Gerüstsystems 2 begeht.In contrast to that in Fig. 1 In the embodiment shown, the stair ascent is in front of the scaffolding system 2, ie only has a horizontal tread plane in the area of the stairs 18, the user walking on a covering 47 of the scaffolding system 2 in order to reach another staircase 52.

Fig. 2 zeigt eine schematische Ansicht des Treppengeländers für ein Gerüstsystem gemäß der bevorzugten Ausführungsform der Erfindung.
Der zumindest eine Geländerholm 10, 20 weist einen sich axial erstreckenden, rohrförmig ausgebildeten Mittenabschnitt 10c, 20c, den sich an einen ersten axialen Endabschnitt 10c1, 20c1 des Mittenabschnitts 10c, 20c anschließenden ersten Endabschnitt 10a, 20a des zumindest einen Geländerholms 10, 20, und den sich an einen zweiten axialen Endabschnitt 10c2, 20c2 des Mittenabschnitts 10c, 20c anschließenden zweiten Endabschnitt 10b, 20b des zumindest einen Geländerholms 10, 20 auf.
Fig. 2 shows a schematic view of the banister for a scaffolding system according to the preferred embodiment of the invention.
The at least one railing rail 10, 20 has an axially extending, tubular center section 10c, 20c, the first end section 10a, 20a of the at least one railing rail 10, 20, and adjoining a first axial end section 10c1, 20c1 of the center section 10c, 20c the second end section 10b, 20b of the at least one railing rail 10, 20 adjoining a second axial end section 10c2, 20c2 of the center section 10c, 20c.

Der erste Endabschnitt 10a, 20a und der zweite Endabschnitt 10b, 20b des zumindest einen Geländerholms 10, 20 sind in einem vorgegebenen Winkel α1, α2 zu dem Mittenabschnitt 10c, 20c geneigt. Ebenfalls in Fig. 2 ersichtlich ist die rohrförmige Ausbildung des zumindest einen Geländerholms 10, 20, wobei das erste Kupplungselement 12, 38 an einem zu dem ersten Endabschnitt 10a, 20a des zumindest einen Geländerholms 10, 20 benachbarten ersten Endabschnitt 12a rohrförmig ausgebildet und an einem zweiten Endabschnitt 12b im Wesentlichen flach ausgebildet ist.The first end section 10a, 20a and the second end section 10b, 20b of the at least one railing rail 10, 20 are inclined at a predetermined angle α1, α2 to the central section 10c, 20c. Also in Fig. 2 The tubular design of the at least one railing spar 10, 20 can be seen, the first coupling element 12, 38 being tubular in form on a first end section 12a adjacent to the first end section 10a, 20a of the at least one railing spar 10, 20 and essentially on a second end section 12b is flat.

Der erste Geländerholm 10 und der zweite Geländerholm 20 sind im Bereich des ersten Endabschnitts 10a, 20a durch ein stiftförmig ausgebildetes erstes Verbindungselement 30, insbesondere einen Steckbolzen, verbunden. Der erste Geländerholm 10 und der zweite Geländerholm 20 sind im Bereich des zweiten Endabschnitts 10b, 20b durch ein stiftförmig ausgebildetes zweites Verbindungselement 32, insbesondere einen Steckbolzen, verbunden.The first railing rail 10 and the second railing rail 20 are connected in the area of the first end section 10a, 20a by a pin-shaped first connecting element 30, in particular a plug pin. The first railing rail 10 and the second railing rail 20 are connected in the region of the second end section 10b, 20b by a pin-shaped second connecting element 32, in particular a plug pin.

Das erste Verbindungselement 30 und das zweite Verbindungselement 32 weisen an einem oberen Endabschnitt jeweils eine Federklammer 34, 36 auf, mit welcher die Verbindungselemente 30, 32 am zweiten Geländerholm 20 lösbar befestigt sind.The first connecting element 30 and the second connecting element 32 each have a spring clip 34, 36 on an upper end section, with which the connecting elements 30, 32 are detachably fastened to the second railing rail 20.

Fig. 3 zeigt ein Verbindungselement zum Verbinden benachbarter Geländerholme des Treppengeländers gemäß der bevorzugten Ausführungsform der Erfindung. Fig. 3 shows a connecting element for connecting adjacent railing spars of the stair railing according to the preferred embodiment of the invention.

Das erste Verbindungselement 30 und das (in Fig. 3 nicht gezeigte) zweite Verbindungselement sind im Wesentlichen stiftförmig ausgebildet und weisen an einem oberen Endabschnitt, die in Einbauposition in den zweiten Geländerholm eingefügt werden, die Federklammer 34 auf. Die Federklammer 34 ist dazu ausgebildet, das erste Verbindungselement 30 an dem zweiten Geländerholm 20 zu sichern.The first connecting element 30 and the (in Fig. 3 second connecting element (not shown) are essentially pin-shaped and have the spring clip 34 at an upper end section which are inserted into the second railing rail in the installation position. The spring clip 34 is designed to secure the first connecting element 30 to the second railing rail 20.

Fig. 4 zeigt eine schematische Ansicht eines ersten Kupplungselements des Geländerholms gemäß der bevorzugten Ausführungsform der Erfindung. Fig. 4 shows a schematic view of a first coupling element of the railing spar according to the preferred embodiment of the invention.

Das erste Kupplungselement 12 des ersten Geländerholms 10 weist an dem zweiten Endabschnitt 12b eine Öffnung 12c auf. Die Öffnung 12c weist in Einbauposition des ersten Kupplungselements 12 einen an einer Unterseite des im Wesentlichen flach ausgebildeten zweiten Endabschnitts 12b im Wesentlichen vertikalen Abschnitt 12d auf. Ferner weist die Öffnung 12c einen sich an den vertikalen Abschnitt 12d anschließenden, durch einen bogenförmigen Verbindungsabschnitt 12e mit dem vertikalen Abschnitt 12d verbundenen horizontalen Abschnitt 12f auf.The first coupling element 12 of the first railing spar 10 has an opening 12c at the second end section 12b. In the installed position of the first coupling element 12, the opening 12c has a substantially vertical section 12d on an underside of the essentially flat second end section 12b. Furthermore, the opening 12c has a horizontal section 12f adjoining the vertical section 12d and connected to the vertical section 12d by an arcuate connecting section 12e.

Das erste Kupplungselement 12 ist dazu ausgebildet, mit der Öffnung 12c in das an der Vertikalstütze 16 des Gerüstsystems 2 angeordnete, insbesondere stiftförmig ausgebildete, zweite Kupplungselement 14 eingehängt zu werden. In der vorliegenden Darstellung ist das erste Kupplungselement 12 derart positioniert, dass dieses unmittelbar in das zweite Kupplungselement 14 eingefügt werden kann.The first coupling element 12 is designed to be hung with the opening 12c into the second coupling element 14, which is arranged on the vertical support 16 of the scaffolding system 2, in particular in the form of a pin. In the present illustration, the first coupling element 12 is positioned such that it can be inserted directly into the second coupling element 14.

Fig. 5 zeigt eine schematische Ansicht eines ersten Kupplungselements des Geländerholms gemäß der bevorzugten Ausführungsform der Erfindung. Fig. 5 shows a schematic view of a first coupling element of the railing spar according to the preferred embodiment of the invention.

In der vorliegenden Darstellung ist das erste Kupplungselement 12 im Bereich der in diesem ausgebildeten Öffnung 12c in das zweite Kupplungselement 14 eingehängt. Sobald das erste Kupplungselement 12 in das zweite Kupplungselement 14 eingehängt ist, ist dieses aufgrund der Geometrie der Öffnung 12c gesichert und liegt an dem zweiten Kupplungselement 14 im Bereich des horizontalen Abschnitts 12f auf.In the present illustration, the first coupling element 12 is hooked into the second coupling element 14 in the region of the opening 12c formed therein. As soon as the first coupling element 12 is hooked into the second coupling element 14, this is secured due to the geometry of the opening 12c and rests on the second coupling element 14 in the region of the horizontal section 12f.

Fig. 6 zeigt eine schematische Ansicht eines ersten Kupplungselements des Geländerholms gemäß der bevorzugten Ausführungsform der Erfindung. Fig. 6 shows a schematic view of a first coupling element of the railing spar according to the preferred embodiment of the invention.

In der in Fig. 6 gezeigten Darstellung ist zudem eine weitere Vertikalstütze 42 gezeigt, welche in einem Montagezustand derart angeordnet ist, dass diese das zweite Kupplungselement 14 umfasst. Somit ist das erste Kupplungselement 12 in vorteilhafter Weise sowohl in Längsrichtung als auch in Querrichtung gesichert.In the in Fig. 6 The illustration shown also shows a further vertical support 42, which is arranged in an assembled state in such a way that it comprises the second coupling element 14. The first coupling element 12 is thus advantageously secured both in the longitudinal direction and in the transverse direction.

Fig. 7 zeigt eine schematische Ansicht eines dritten Kupplungselements des Geländerholms gemäß der bevorzugten Ausführungsform der Erfindung. Fig. 7 shows a schematic view of a third coupling element of the railing spar according to the preferred embodiment of the invention.

Das dritte Kupplungselement 22 schließt sich an den (in Fig. 7 nicht dargestellten) zweiten Endabschnitt des zumindest einen Geländerholms an. Das dritte Kupplungselement 22 ist an einem zu dem zweiten Endabschnitt des zumindest einen Geländerholms benachbarten ersten Endabschnitt 22a rohrförmig ausgebildet und an einem zweiten Endabschnitt 22b im Wesentlichen flach ausgebildet.The third coupling element 22 connects to the (in Fig. 7 not shown) second end portion of the at least one railing spar. The third coupling element 22 is tubular in form at a first end section 22a adjacent to the second end section of the at least one railing spar and is essentially flat in a second end section 22b.

Ferner weist das dritte Kupplungselement 22 an dem zweiten Endabschnitt 22b eine Öffnung 22c auf. An der Öffnung 22c ist das dritte Kupplungselement 22 in das, an der weiteren Vertikalstütze 26 des Gerüstsystems 2 angeordnete, insbesondere stiftförmig ausgebildete, vierte Kupplungselement 24 einhängbar.Furthermore, the third coupling element 22 has an opening 22c at the second end section 22b. At the opening 22c, the third coupling element 22 can be hooked into the fourth coupling element 24, which is arranged on the further vertical support 26 of the scaffolding system 2, in particular in the form of a pin.

Fig. 8 zeigt eine schematische Ansicht eines dritten Kupplungselements des Geländerholms gemäß der bevorzugten Ausführungsform der Erfindung. Fig. 8 shows a schematic view of a third coupling element of the railing spar according to the preferred embodiment of the invention.

In der in Fig. 8 gezeigten Darstellung ist des Weiteren eine weitere Vertikalstütze 44 dargestellt, die in einem Montagezustand das vierte Kupplungselement 24 umschließt. Somit ist das dritte Kupplungselement 22 derart mit dem vierten Kupplungselement 24 verbunden, dass dieses aus dem Eingriff nicht lösbar ist.In the in Fig. 8 In the illustration shown, a further vertical support 44 is also shown, which encloses the fourth coupling element 24 in an assembled state. Thus, the third coupling element 22 is connected to the fourth coupling element 24 in such a way that it cannot be released from the engagement.

Der Treppenholm 10 ist somit in einfacher Art und Weise in das Gerüstsystem einhängbar und sodann mittels der Anordnung weiterer Vertikalstützen fixierbar, nachdem das Einhängen bereits erfolgt ist.The stair spar 10 can thus be hung into the scaffolding system in a simple manner and can then be fixed by means of the arrangement of further vertical supports after the hanging has already taken place.

Fig. 9 zeigt ein Ablaufdiagramm eines Verfahrens zur Montage des Treppengeländers für das Gerüstsystem gemäß der bevorzugten Ausführungsform der Erfindung. Fig. 9 shows a flow diagram of a method for assembling the banister for the scaffolding system according to the preferred embodiment of the invention.

Das Verfahren betrifft die Montage eines Treppengeländers für ein Gerüstsystem 2, insbesondere für einen vorgesetzten Treppenaufstieg an einem Fassadengerüst oder einen gleichläufigen Treppenturm, und weist folgende Schritte auf. Das Verfahren umfasst ein Bereitstellen S1 zumindest eines Treppenholms 10 mit einem ersten Endabschnitt 10a, 20a, an dem ein erstes Kupplungselement 12, 38 angeordnet ist, und mit einem zweiten Endabschnitt 10b, 20b, an dem ein drittes Kupplungselement 22, 40 angeordnet ist.The method relates to the assembly of a banister for a scaffolding system 2, in particular for an upstairs staircase on a facade scaffolding or a stair tower in the same direction, and has the following steps. The method comprises providing S1 at least one stair spar 10 with a first end section 10a, 20a, on which a first coupling element 12, 38 is arranged, and with a second end section 10b, 20b, on which a third coupling element 22, 40 is arranged.

Das Verfahren umfasst ferner ein Befestigen S2 des ersten Kupplungselements 12, 38 an einem zweiten Kupplungselement 14 einer Vertikalstütze 16 des Gerüstsystems 2 benachbart zu einem in Einbauposition oberen Endabschnitt 18a einer Treppe 18 des Gerüstsystems 2.The method further comprises fastening S2 of the first coupling element 12, 38 to a second coupling element 14 of a vertical support 16 of the scaffolding system 2 adjacent to an upper end section 18a of a staircase 18 of the scaffolding system 2 in the installed position.

Das Verfahren umfasst überdies ein Befestigen S3 des dritten Kupplungselements 22, 40 an einem vierten Kupplungselement 24 einer weiteren Vertikalstütze 26 des Gerüstsystems 2 benachbart zu einem in Einbauposition unteren Endabschnitt 18b der Treppe 18 des Gerüstsystems 2.The method also includes fastening S3 of the third coupling element 22, 40 to a fourth coupling element 24 of a further vertical support 26 of the scaffolding system 2 adjacent to an end section 18b of the stairs 18 of the scaffolding system 2 which is lower in the installed position.

Das erste Kupplungselement 12, 38 und das zweite Kupplungselement 14 des zumindest einen Geländerholms 10, 20 werden durch einen Benutzer aus einer gesicherten Position benachbart zu dem in Einbauposition unteren Endabschnitt 18b der Treppe 18 des Gerüstsystems 2 an den Kupplungselementen 12, 14, 22, 24 der Vertikalstützen 16, 26 des Gerüstsystems 2 befestigt.The first coupling element 12, 38 and the second coupling element 14 of the at least one railing spar 10, 20 are moved by a user from a secured position adjacent to the lower end section 18b of the stairs 18 of the scaffolding system 2 in the installed position on the coupling elements 12, 14, 22, 24 the vertical supports 16, 26 of the scaffolding system 2 attached.

Das Verfahren umfasst darüber hinaus, dass das Gerüstsystem 2 an einem unteren Endabschnitt 49a einer Treppe 49 mit einem Podest 45 und einen in derselben horizontalen Ebene als das Podest 45 mit einem benachbart zu dem Podest 45 angeordneten Belag 47 bereitgestellt wird.The method also includes that the scaffolding system 2 is provided at a lower end section 49a of a staircase 49 with a platform 45 and a platform 47 in the same horizontal plane as the platform 45 with a covering 47 arranged adjacent to the platform 45.

Das Podest 45 ist vorzugsweise integral mit der Treppe 49 ausgebildet.The platform 45 is preferably formed integrally with the stairs 49.

Ein weiterer Geländerholm 46 wird an einem ersten axialen Endabschnitt 46a mit einer ersten Vertikalstütze 48 lösbar verbunden, an welcher das Podest 45 und der Belag 47 befestigt sind.Another railing rail 46 is detachably connected at a first axial end section 46a to a first vertical support 48, to which the platform 45 and the covering 47 are fastened.

Der weitere Geländerholm 46 wird an einem zweiten axialen Endabschnitt 46b mit einer zweiten Vertikalstütze 50 lösbar verbunden, an welcher das Podest 45 und der Belag 47 befestigt sind.The further railing rail 46 is detachably connected at a second axial end section 46b to a second vertical support 50, to which the platform 45 and the covering 47 are fastened.

Der weitere Geländerholm 46 stellt durch räumliche Trennung der Ebene des Podests 45 und des Belags 47 eine gesicherte Position des Benutzers zur Montage des Treppengeländers 1 für das Gerüstsystem 2 bereit.The further railing rail 46 provides a secure position of the user for the assembly of the stair railing 1 for the scaffolding system 2 by spatial separation of the level of the platform 45 and the covering 47.

Die Vertikalstütze 16 wird als ein erstes Teil 16a und ein mit dem ersten Teil 16a durch eine Steckverbindung 17 verbindbares zweites Teil 16b bereitgestellt.The vertical support 16 is provided as a first part 16a and a second part 16b which can be connected to the first part 16a by a plug connection 17.

Bei der Montage wird zuerst das erste Teil 16a montiert. Anschließend wird das zweite Teil 16b durch die Steckverbindung 17 auf das erste Teil 16a aufgesetzt. Das zweite Teil 16b wird mit einem daran vormontierten oder integral ausgebildeten Stirngeländer 42 bereitgestellt.During assembly, the first part 16a is first assembled. Subsequently, the second part 16b is placed on the first part 16a by the connector 17. The second part 16b is provided with an end railing 42 pre-assembled or integrally formed thereon.

Obwohl hierin spezifische Ausführungsformen illustriert und beschrieben wurden, ist es dem Fachmann verständlich, dass eine Vielzahl von Alternativen und/oder äquivalenten Implementierungen existieren.Although specific embodiments have been illustrated and described herein, it will be understood by those skilled in the art that a variety of alternatives and / or equivalent implementations exist.

Es sollte beachtet werden, dass die beispielhafte Ausführungsform oder beispielhaften Ausführungsformen nur Beispiele sind und nicht dazu dienen, den Umfang, die Anwendbarkeit oder die Konfiguration in irgendeiner Weise einzuschränken.It should be noted that the exemplary embodiment or exemplary embodiments are only examples and are not intended to limit the scope Limit applicability or configuration in any way.

Vielmehr liefert die vorstehend genannte Zusammenfassung und ausführliche Beschreibung dem Fachmann eine bequeme Anleitung zur Implementierung zumindest einer beispielhaften Ausführungsform, wobei verständlich ist, dass verschiedene Änderungen im Funktionsumfang und der Anordnung der Elemente vorgenommen werden können, ohne von dem Umfang der beigefügten Ansprüche und ihrer rechtlichen Äquivalente abzuweichen.Rather, the above summary and detailed description provide those skilled in the art with a convenient road map for implementing at least one exemplary embodiment, it being understood that various changes in the functionality and arrangement of the elements can be made without departing from the scope of the appended claims and their legal equivalents to deviate.

Im Allgemeinen beabsichtigt diese Anmeldung, Änderungen bzw. Anpassungen oder Variationen der hierin dargelegten Ausführungsformen abzudecken.In general, this application is intended to cover changes or adaptations or variations to the embodiments set forth herein.

BezugszeichenlisteReference list

11
TreppengeländerBanisters
22nd
GerüstsystemScaffolding system
10, 2010, 20
GeländerholmGuardrail
10a, 20a10a, 20a
erster Endabschnittfirst end section
10b, 20b10b, 20b
zweiter Endabschnittsecond end section
10c, 20c10c, 20c
MittenabschnittMiddle section
10c1, 20c110c1, 20c1
erster axialer Endabschnittfirst axial end section
10c2, 20c210c2, 20c2
zweiter axialer Endabschnittsecond axial end section
12, 3812, 38
erstes Kupplungselementfirst coupling element
12a12a
erster Endabschnittfirst end section
12b12b
zweiter Endabschnittsecond end section
12c12c
Öffnungopening
12d12d
vertikaler Abschnittvertical section
12e12e
VerbindungsabschnittConnecting section
12f12f
horizontaler Abschnitthorizontal section
1414
zweites Kupplungselementsecond coupling element
1616
VertikalstützeVertical support
16a16a
erstes Teilfirst part
16b16b
zweites Teilsecond part
1717th
SteckverbindungConnector
1818th
Treppestairway
18a18a
oberer Endabschnittupper end section
18b18b
unterer Endabschnittlower end section
22, 4022, 40
drittes Kupplungselementthird coupling element
22a22a
erster Endabschnittfirst end section
22b22b
zweiter Endabschnittsecond end section
22c22c
Öffnungopening
2424th
viertes Kupplungselementfourth coupling element
2626
weitere Vertikalstützefurther vertical support
2828
Bodenground
3030th
erstes Verbindungselementfirst connecting element
3232
zweites Verbindungselementsecond connecting element
34, 3634, 36
FederklammerSpring clip
α1, α2α1, α2
Winkelangle
42, 4442, 44
StirngeländerFront railing
4545
PodestPedestal
4646
weiterer Geländerholmanother railing spar
46a46a
erster axialer Endabschnittfirst axial end section
46b46b
zweiter axialer Endabschnittsecond axial end section
4747
zweiter Belagsecond topping
4848
erste Vertikalstützefirst vertical support
4949
Treppestairway
49a49a
unterer Endabschnittlower end section
5050
zweite Vertikalstützesecond vertical support
5252
weitere Treppefurther stairs

Claims (18)

Treppengeländer (1) für ein Gerüstsystem (2), insbesondere für einen vorgesetzten Treppenaufstieg an einem Fassadengerüst oder einen gleichläufigen Treppenturm, mit:
zumindest einem Geländerholm (10, 20), welcher einen ersten Endabschnitt (10a, 20a) aufweist, an dem ein erstes Kupplungselement (12, 38) angeordnet ist, wobei das erste Kupplungselement (12, 38) dazu ausgebildet ist, an einem zweiten Kupplungselement (14) einer Vertikalstütze (16) des Gerüstsystems (2) benachbart zu einem in Einbauposition oberen Endabschnitt (18a) einer Treppe (18) des Gerüstsystems (2) befestigt zu werden, wobei der zumindest eine Geländerholm (10, 20) einen zweiten Endabschnitt (10b, 20b) aufweist, an dem ein drittes Kupplungselement (22, 40) angeordnet ist, wobei das dritte Kupplungselement (22, 40) dazu ausgebildet ist, an einem vierten Kupplungselement (24) einer weiteren Vertikalstütze (26) des Gerüstsystems (2) benachbart zu einem in Einbauposition unteren Endabschnitt (18b) der Treppe (18) des Gerüstsystems (2) befestigt zu werden, und wobei das erste Kupplungselement (12, 38) und das dritte Kupplungselement (22, 40) des zumindest einen Geländerholms (10, 20) dazu ausgebildet sind, durch einen Benutzer aus einer gesicherten Position benachbart zu dem in Einbauposition unteren Endabschnitt (18b) der Treppe (18) des Gerüstsystems (2) an den Kupplungselementen (14, 24) der Vertikalstützen (16, 26) des Gerüstsystems (2) befestigt zu werden.
Stair railing (1) for a scaffolding system (2), in particular for an upstairs staircase on a facade scaffolding or a parallel stair tower, with:
at least one railing rail (10, 20), which has a first end section (10a, 20a), on which a first coupling element (12, 38) is arranged, the first coupling element (12, 38) being designed on a second coupling element (14) a vertical support (16) of the scaffolding system (2) to be fastened adjacent to an upper end section (18a) in the installation position of a staircase (18) of the scaffolding system (2), the at least one railing rail (10, 20) having a second end section (10b, 20b), on which a third coupling element (22, 40) is arranged, the third coupling element (22, 40) being designed to connect a further vertical support (26) of the scaffolding system (2 ) to be attached adjacent to a lower end section (18b) of the stairs (18) of the scaffolding system (2) in the installation position, and wherein the first coupling element (12, 38) and the third coupling element (22, 40) of the at least one railing rail (10, 20) are designed, by a user, from a secured position adjacent to the lower end section (18b) of the stairs (18) of the scaffolding system (2) in the installed position on the coupling elements (14, 24) of the vertical supports (16, 26 ) of the scaffolding system (2).
Treppengeländer nach Anspruch 1, dadurch gekennzeichnet, dass der zumindest eine Geländerholm (10, 20) einen sich axial erstreckenden, rohrförmig ausgebildeten Mittenabschnitt (10c, 20c), den sich an einen ersten axialen Endabschnitt (10c1, 20c1) des Mittenabschnitts (10c, 20c) anschließenden ersten Endabschnitt (10a, 20a) des zumindest einen Geländerholms (10, 20), und den sich an einen zweiten axialen Endabschnitt (10c2, 20c2) des Mittenabschnitts (10c, 20c) anschließenden zweiten Endabschnitt (10b, 20b) des zumindest einen Geländerholms (10, 20) aufweist, wobei der erste Endabschnitt (10a, 20a) und der zweite Endabschnitt (10b, 20b) des zumindest einen Geländerholms (10, 20) in einem vorgegebenen Winkel (α1, α2) zu dem Mittenabschnitt (10c, 20c) geneigt sind.Stair railing according to claim 1, characterized in that the at least one railing spar (10, 20) has an axially extending, tubular center section (10c, 20c) which is connected to a first axial end section (10c1, 20c1) of the center section (10c, 20c ) adjoining first end section (10a, 20a) of the at least one railing spar (10, 20), and the second end section (10b, 20b) of the at least one adjoining a second axial end section (10c2, 20c2) of the center section (10c, 20c) Railing spar (10, 20), the first end section (10a, 20a) and the second end section (10b, 20b) of the at least one railing spar (10, 20) at a predetermined angle (α1, α2) to the center section (10c, 20c) are inclined. Treppengeländer nach Anspruch 2, dadurch gekennzeichnet, dass der Mittenabschnitt (10c, 20c) des zumindest einen Geländerholms (10, 20) dazu ausgebildet ist, in Einbauposition des zumindest einen Geländerholms (10, 20) parallel zu der benachbarten Treppe (18) angeordnet zu werden, und wobei der erste Endabschnitt (10a, 20a) und der zweite Endabschnitt (10b, 20b) des zumindest einen Geländerholms (10, 20) dazu ausgebildet sind, in Einbauposition des zumindest einen Geländerholms (10, 20) parallel zu einem Boden (28), auf dem das Gerüstsystem (2) errichtet ist, angeordnet zu werden.Stair railing according to claim 2, characterized in that the central section (10c, 20c) of the at least one railing spar (10, 20) is designed to be arranged parallel to the adjacent staircase (18) in the installed position of the at least one railing spar (10, 20) and wherein the first end section (10a, 20a) and the second end section (10b, 20b) of the at least one railing spar (10, 20) are designed to be parallel to a floor (10) in the installed position of the at least one railing spar (10, 20) 28) on which the scaffolding system (2) is erected. Treppengeländer nach Anspruch 2 oder 3, dadurch gekennzeichnet, dass sich das erste Kupplungselement (12, 38) an den ersten Endabschnitt (10a, 20a) des zumindest einen Geländerholms (10, 20) anschließt, wobei das erste Kupplungselement (12, 38) an einem zu dem ersten Endabschnitt (10a, 20a) des zumindest einen Geländerholms (10, 20) benachbarten ersten Endabschnitt (12a) rohrförmig ausgebildet und an einem zweiten Endabschnitt (12b) im Wesentlichen flach ausgebildet ist.Stair railing according to claim 2 or 3, characterized in that the first coupling element (12, 38) adjoins the first end section (10a, 20a) of the at least one railing spar (10, 20), the first Coupling element (12, 38) on a first end section (12a) adjacent to the first end section (10a, 20a) of the at least one railing rail (10, 20) is tubular and is essentially flat on a second end section (12b). Treppengeländer nach Anspruch 4, dadurch gekennzeichnet, dass das erste Kupplungselement (12, 38) an dem zweiten Endabschnitt (12b) eine Öffnung (12c) aufweist, welche in Einbauposition des ersten Kupplungselements (12) einen an einer Unterseite des im Wesentlichen flach ausgebildeten zweiten Endabschnitts (12b) im Wesentlichen vertikalen Abschnitt (12d) und einen sich an den vertikalen Abschnitt (12d) anschließenden, durch einen bogenförmigen Verbindungsabschnitt (12e) mit dem vertikalen Abschnitt (12d) verbundenen, horizontalen Abschnitt (12f) aufweist.Stair railing according to Claim 4, characterized in that the first coupling element (12, 38) has an opening (12c) on the second end section (12b), which in the installed position of the first coupling element (12) has an opening on an underside of the substantially flat second one End section (12b) has essentially vertical section (12d) and a horizontal section (12f) adjoining the vertical section (12d) and connected to the vertical section (12d) by an arcuate connecting section (12e). Treppengeländer nach Anspruch 5, dadurch gekennzeichnet, dass das erste Kupplungselement (12, 38) dazu ausgebildet ist, mit der Öffnung (12c) in das an der Vertikalstütze (16) des Gerüstsystems (2) angeordnete, insbesondere stiftförmig ausgebildete, zweite Kupplungselement (14) eingehängt zu werden.Stair railing according to claim 5, characterized in that the first coupling element (12, 38) is designed with the opening (12c) into the second coupling element (14) which is arranged on the vertical support (16) of the scaffolding system (2), in particular in the form of a pin ) to be attached. Treppengeländer nach einem der Ansprüche 2 bis 6, dadurch gekennzeichnet, dass sich das dritte Kupplungselement (22, 40) an den zweiten Endabschnitt (10b, 20b) des zumindest einen Geländerholms (10, 20) anschließt, wobei das dritte Kupplungselement (22, 40) an einem zu dem zweiten Endabschnitt (10b, 20b) des zumindest einen Geländerholms (10, 20) benachbarten ersten Endabschnitt (22a) rohrförmig ausgebildet und an einem zweiten Endabschnitt (22b) im Wesentlichen flach ausgebildet ist.Stair railing according to one of claims 2 to 6, characterized in that the third coupling element (22, 40) adjoins the second end section (10b, 20b) of the at least one railing spar (10, 20), the third coupling element (22, 40 ) at a first end section (22a) adjacent to the second end section (10b, 20b) of the at least one railing spar (10, 20) and to be tubular a second end section (22b) is essentially flat. Treppengeländer nach Anspruch 7, dadurch gekennzeichnet, dass das dritte Kupplungselement (22, 40) an dem zweiten Endabschnitt (22b) eine Öffnung (22c) aufweist, an welcher das dritte Kupplungselement (22, 40) in das, an der weiteren Vertikalstütze (26) des Gerüstsystems (2) angeordnete, insbesondere stiftförmig ausgebildete, vierte Kupplungselement (24) einhängbar ist.Stair railing according to claim 7, characterized in that the third coupling element (22, 40) at the second end section (22b) has an opening (22c) at which the third coupling element (22, 40) into which on the further vertical support (26 ) of the scaffolding system (2) arranged, in particular pin-shaped, fourth coupling element (24) can be suspended. Treppengeländer nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass das Treppengeländer (1) einen ersten Geländerholm (10), insbesondere einen Knieholm und einen von dem ersten Geländerholm (10) getrennt ausgebildeten zweiten Geländerholm (20), insbesondere einen Handlaufholm aufweist, wobei der erste Geländerholm (10) und der zweite Geländerholm (20) identisch ausgebildet sind.Stair railing according to one of the preceding claims, characterized in that the stair railing (1) has a first railing rail (10), in particular a knee rail and a second railing rail (20), in particular a handrail rail, which is separate from the first railing rail (10) the first railing spar (10) and the second railing spar (20) are identical. Treppengeländer nach Anspruch 9, dadurch gekennzeichnet, dass der erste Geländerholm (10) und der zweite Geländerholm (20) im Bereich des ersten Endabschnitts (10a, 20a) durch ein stiftförmig ausgebildetes erstes Verbindungselement (30), insbesondere einen Steckbolzen, verbunden sind, und wobei der erste Geländerholm (10) und der zweite Geländerholm (20) im Bereich des zweiten Endabschnitts (10b, 20b) durch ein stiftförmig ausgebildetes zweites Verbindungselement (32), insbesondere einen Steckbolzen, verbunden sind.Stair railing according to claim 9, characterized in that the first railing rail (10) and the second railing rail (20) are connected in the region of the first end section (10a, 20a) by a pin-shaped first connecting element (30), in particular a plug pin, and the first railing rail (10) and the second railing rail (20) being connected in the region of the second end section (10b, 20b) by a pin-shaped second connecting element (32), in particular a plug pin. Treppengeländer nach Anspruch 10, dadurch gekennzeichnet, dass das erste Verbindungselement (30) und das zweite Verbindungselement (32) im Bereich des zweiten Geländerholms (20) eine Federklammer (34, 36) aufweisen, welche dazu ausgebildet ist, das erste Verbindungselement (30) und das zweite Verbindungselement (32) an dem zweiten Geländerholm (20) zu sichern.Stair railing according to claim 10, characterized in that the first connecting element (30) and the second connecting element (32) in the region of the second railing spar (20) have a spring clip (34, 36) which is designed to secure the first connecting element (30) and to secure the second connecting element (32) to the second railing spar (20). Gerüstsystem (2), insbesondere vorgesetzter Treppenaufstieg an einem Fassadengerüst oder gleichläufiger Treppenturm, mit einem Treppengeländer nach einem der Ansprüche 1 bis 11.Scaffolding system (2), in particular a set of stairs on a facade scaffolding or a stair tower in the same direction, with a stair railing according to one of Claims 1 to 11. Gerüstsystem nach Anspruch 12, dadurch gekennzeichnet, dass das Treppengeländer (1) am Gerüstsystem (2) vorlaufend, insbesondere an einer von einer zu dem Gerüstsystem (2) benachbarten Fassade abgewandten Seite des Gerüstsystems (2) angeordnet ist.Scaffolding system according to claim 12, characterized in that the stair railing (1) is arranged in front of the scaffolding system (2), in particular on a side of the scaffolding system (2) facing away from a facade adjacent to the scaffolding system (2). Gerüstsystem nach Anspruch 12 oder 13, dadurch gekennzeichnet, dass das Gerüstsystem (2) an einem unteren Endabschnitt (49a) einer Treppe (49) ein Podest (45) und in derselben horizontalen Ebene als das Podest (45) einen benachbart zu dem Podest (45) angeordneten Belag (47) aufweist, wobei ein weiterer Geländerholm (46) an einem ersten axialen Endabschnitt (46a) mit einer ersten Vertikalstütze (48) lösbar verbunden ist, an welcher das Podest (45) und der Belag (47) befestigt sind, wobei der weitere Geländerholm (46) an einem zweiten axialen Endabschnitt (46b) mit einer zweiten Vertikalstütze (50) lösbar verbunden ist, an welcher das Podest (45) und der Belag (47) befestigt sind, und wobei der weitere Geländerholm (46) dazu ausgebildet ist, durch räumliche Trennung der Ebene des Podests (45) und des Belags (47) eine gesicherte Position des Benutzers zur Montage des Treppengeländers (1) für das Gerüstsystem (2) bereitzustellen.Scaffolding system according to claim 12 or 13, characterized in that the scaffolding system (2) has a platform (45) at a lower end section (49a) of a staircase (49) and one adjacent to the platform (45) in the same horizontal plane as the platform (45) 45) has a covering (47), a further railing rail (46) being detachably connected at a first axial end section (46a) to a first vertical support (48) to which the platform (45) and the covering (47) are fastened , the further railing rail (46) being detachably connected at a second axial end section (46b) to a second vertical support (50) to which the platform (45) and the covering (47) are fastened, and the further railing rail (46 ) is trained to spatial separation of the level of the platform (45) and the covering (47) to provide a secure position for the user to assemble the banister (1) for the scaffolding system (2). Gerüstsystem nach einem der Ansprüche 12 bis 14, dadurch gekennzeichnet, dass die Vertikalstütze (16) als ein erstes Teil (16a) und ein mit dem ersten Teil (16a) durch eine Steckverbindung (17)v erbindbares zweites Teil (16b) ausgebildet ist, wobei im Montagezustand der Vertikalstütze (16) das zweite Teil (16b) durch die Steckverbindung (17) auf das erste Teil (16a) aufgesetzt ist, wobei das zweite Teil (16b) ein daran montiertes oder integral mit diesem ausgebildetes Stirngeländer (42) aufweist.Scaffolding system according to one of claims 12 to 14, characterized in that the vertical support (16) is designed as a first part (16a) and a second part (16b) which can be connected to the first part (16a) by a plug connection (17), wherein in the assembled state of the vertical support (16) the second part (16b) is placed on the first part (16a) by the plug connection (17), the second part (16b) having an end railing (42) mounted thereon or integrally formed therewith . Verfahren zur Montage eines Treppengeländers für ein Gerüstsystem (2), insbesondere für einen vorgesetzten Treppenaufstieg an einem Fassadengerüst oder einen gleichläufigen Treppenturm, mit den Schritten: - Bereitstellen (S1) zumindest eines Geländerholms (10) mit einem ersten Endabschnitt (10a, 20a), an dem ein erstes Kupplungselement (12, 38) angeordnet ist und mit einem zweiten Endabschnitt (10b, 20b), an dem ein drittes Kupplungselement (22, 40) angeordnet ist; - Befestigen (S2) des ersten Kupplungselements (12, 38) an einem zweiten Kupplungselement (14) einer Vertikalstütze (16) des Gerüstsystems (2) benachbart zu einem in Einbauposition oberen Endabschnitt (18a) einer Treppe (18) des Gerüstsystems (2); und - Befestigen (S3) des dritten Kupplungselements (22, 40) an einem vierten Kupplungselement (24) einer weiteren Vertikalstütze (26) des Gerüstsystems (2) benachbart zu einem in Einbauposition unteren Endabschnitt (18b) der Treppe (18) des Gerüstsystems (2), wobei das erste Kupplungselement (12, 38) und das dritte Kupplungselement (22, 40) des zumindest einen Geländerholms (10, 20) durch einen Benutzer aus einer gesicherten Position benachbart zu dem in Einbauposition unteren Endabschnitt (18b) der Treppe (18) des Gerüstsystems (2) an den Kupplungselementen (14, 24) der Vertikalstützen (16, 26) des Gerüstsystems (2) befestigt werden. Method for assembling a banister for a scaffolding system (2), in particular for an upstairs staircase on a facade scaffolding or a parallel stair tower, with the steps: - Providing (S1) at least one railing rail (10) with a first end section (10a, 20a) on which a first coupling element (12, 38) is arranged and with a second end section (10b, 20b) on which a third coupling element ( 22, 40) is arranged; - Fastening (S2) the first coupling element (12, 38) to a second coupling element (14) of a vertical support (16) of the scaffolding system (2) adjacent to an upper end section (18a) in the installation position of a staircase (18) of the scaffolding system (2) ; and - Attaching (S3) the third coupling element (22, 40) to a fourth coupling element (24) Another vertical support (26) of the scaffolding system (2) adjacent to an end section (18b) of the stairs (18) of the scaffolding system (2) which is lower in the installed position, the first coupling element (12, 38) and the third coupling element (22, 40) of the at least one railing rail (10, 20) by a user from a secured position adjacent to the lower end section (18b) of the stairs (18) of the scaffolding system (2) in the installed position on the coupling elements (14, 24) of the vertical supports (16, 26) of the scaffolding system (2). Verfahren nach Anspruch 16, dadurch gekennzeichnet, dass das Gerüstsystem (2) an einem unteren Endabschnitt (49a) einer Treppe (49) mit einem Podest (45) und in derselben horizontalen Ebene als das Podest (45) mit einem benachbart zu dem Podest (45) angeordneten Belag (47) bereitgestellt wird, wobei ein weiterer Geländerholm (46) an einem ersten axialen Endabschnitt (46a) mit einer ersten Vertikalstütze (48) lösbar verbunden wird, an welcher das Podest (45) und der Belag (47) befestigt sind, wobei der weitere Geländerholm (46) an einem zweiten axialen Endabschnitt (46b) mit einer zweiten Vertikalstütze (50) lösbar verbunden wird, an welcher das Podest (45) und der Belag (47) befestigt sind, und wobei der weitere Geländerholm (46) durch räumliche Trennung der Ebene des Podests (45) und des Belags (47) eine gesicherte Position des Benutzers zur Montage des Treppengeländers (1) für das Gerüstsystem (2) bereitstellt.A method according to claim 16, characterized in that the scaffolding system (2) at a lower end portion (49a) of a staircase (49) with a pedestal (45) and in the same horizontal plane as the pedestal (45) with an adjacent to the pedestal ( 45) arranged covering (47) is provided, a further railing rail (46) being detachably connected at a first axial end section (46a) to a first vertical support (48) to which the platform (45) and the covering (47) are fastened the further railing rail (46) is detachably connected at a second axial end section (46b) to a second vertical support (50) to which the platform (45) and the covering (47) are fastened, and the further railing rail ( 46) by spatial separation of the level of the platform (45) and the covering (47) provides a secure position for the user to assemble the banister (1) for the scaffolding system (2). Verfahren nach Anspruch 16 oder 17, dadurch gekennzeichnet, dass die Vertikalstütze (16) als ein erstes Teil (16a) und ein mit dem ersten Teil (16a) durch eine Steckverbindung (17) verbindbares zweites Teil (16b) bereitgestellt wird, wobei zuerst das erste Teil (16a) montiert wird und anschließend das zweite Teil (16b) durch die Steckverbindung (17) auf das erste Teil (16a) aufgesetzt wird, und wobei das zweite Teil (16b) mit einem daran vormontierten oder integral ausgebildeten Stirngeländer (42) bereitgestellt wird.A method according to claim 16 or 17, characterized in that the vertical support (16) is provided as a first part (16a) and a second part (16b) which can be connected to the first part (16a) by a plug connection (17), the first part first part (16a) is mounted and then the second part (16b) is placed on the first part (16a) by means of the plug connection (17), and wherein the second part (16b) with a front railing (42) pre-assembled or integrally formed thereon provided.
EP19197945.9A 2018-09-25 2019-09-18 Stair railing, frame system and method for mounting a stair railing Active EP3628794B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE102018123567.4A DE102018123567A1 (en) 2018-09-25 2018-09-25 STAIRS, SCAFFOLDING SYSTEM AND METHOD FOR ASSEMBLING A STAIRS

Publications (2)

Publication Number Publication Date
EP3628794A1 true EP3628794A1 (en) 2020-04-01
EP3628794B1 EP3628794B1 (en) 2024-02-07

Family

ID=67997433

Family Applications (1)

Application Number Title Priority Date Filing Date
EP19197945.9A Active EP3628794B1 (en) 2018-09-25 2019-09-18 Stair railing, frame system and method for mounting a stair railing

Country Status (2)

Country Link
EP (1) EP3628794B1 (en)
DE (1) DE102018123567A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112031466A (en) * 2020-08-18 2020-12-04 东莞市至简机电工程技术有限公司 Assembled building construction stair
CN113612144A (en) * 2021-07-09 2021-11-05 广东电网有限责任公司广州供电局 Substation overhaul professional training platform
EP4079991A1 (en) * 2021-04-20 2022-10-26 Peri Se Guard rail, framework, method for erecting a framework and use of a guard rail in a framework

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2516141A1 (en) * 1981-11-10 1983-05-13 Philippe Robert Scaffolding erection procedure - has two base frames braced to take next level of guard rails and decking
DE8707755U1 (en) * 1987-05-30 1988-09-29 Langer, Geb. Layher, Ruth, 7129 Gueglingen, De
DE102005028885A1 (en) 2005-06-22 2007-01-04 Peri Gmbh stairway

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1174959B (en) * 1959-02-02 1964-07-30 Up Right Inc Mast section
GB2500025B (en) * 2012-03-07 2019-02-13 Turner Access Ltd Scaffolding
US20160346570A1 (en) * 2014-07-28 2016-12-01 Andrew Philip Anson Scaffolding safety line
DE102014224002A1 (en) * 2014-11-25 2016-05-25 Peri Gmbh Railing rail and scaffolding with a railing rail

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2516141A1 (en) * 1981-11-10 1983-05-13 Philippe Robert Scaffolding erection procedure - has two base frames braced to take next level of guard rails and decking
DE8707755U1 (en) * 1987-05-30 1988-09-29 Langer, Geb. Layher, Ruth, 7129 Gueglingen, De
DE102005028885A1 (en) 2005-06-22 2007-01-04 Peri Gmbh stairway

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
G RINGSCAFF ET AL: "Technical Manual Scafom-rux products are distributed through sales and rental", 1 May 2011 (2011-05-01), XP055398839, Retrieved from the Internet <URL:https://www.scafom-rux.nl/uploads/documents/Handleidingen/2011-05-01-The-Ringscaff-erection-manual-complete.pdf> [retrieved on 20170815] *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112031466A (en) * 2020-08-18 2020-12-04 东莞市至简机电工程技术有限公司 Assembled building construction stair
EP4079991A1 (en) * 2021-04-20 2022-10-26 Peri Se Guard rail, framework, method for erecting a framework and use of a guard rail in a framework
CN113612144A (en) * 2021-07-09 2021-11-05 广东电网有限责任公司广州供电局 Substation overhaul professional training platform

Also Published As

Publication number Publication date
DE102018123567A1 (en) 2020-03-26
EP3628794B1 (en) 2024-02-07

Similar Documents

Publication Publication Date Title
EP3628794B1 (en) Stair railing, frame system and method for mounting a stair railing
EP0918912B1 (en) Dismountable facade scaffold
EP1395723B1 (en) Dismountable scaffolding
CH680810A5 (en)
EP2557252B1 (en) Work platform and method for securely setting up a support frame tower
DE19651901C2 (en) Safety guardrail element, especially for scaffolding structures that run in different directions
DE102010004807A1 (en) Lifting protection for scaffolding
DE10144218A1 (en) Protective railing for work sites on flat roofs has vertical posts between which railing bars are connected and bearing arm articulated to vertical post, located on flat roof structure
DE19527944C2 (en) Scaffold holder for step ladders or the like
DE60318350T2 (en) Guardrails device
DE102009024857A1 (en) Stair stringer for stair towers utilized as e.g. emergency stairs during renovation work on public buildings, has retainers arranged in step form, and supporting units, which are independent of height of points and distance of supports
DE10305145B4 (en) Scaffold stairway module
DE202018002270U1 (en) Toe board for scaffolding
EP1245757B1 (en) Stair tower for building shell
DE10006094C2 (en) Scaffold stairway system
DE10307087B4 (en) Stairway
EP2096235A1 (en) Console front-end railing
DE202022105807U1 (en) stair stringer
DE19811750A1 (en) Railings for staircases, galleries, balustrades, balconies etc.
DE202022105809U1 (en) topping bar
DE202022105808U1 (en) decking board
EP1209304A2 (en) Post for a fall prevention railing
DE102021129115A1 (en) Railing with a device for closing a free space
DE102018101968A1 (en) stairway
DE2852082A1 (en) SCAFFOLDING STAIRS

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20200928

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20231025

RAP3 Party data changed (applicant data changed or rights of an application transferred)

Owner name: PERI SE

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

Free format text: NOT ENGLISH

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 502019010530

Country of ref document: DE

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: LANGUAGE OF EP DOCUMENT: GERMAN

P01 Opt-out of the competence of the unified patent court (upc) registered

Effective date: 20240318

REG Reference to a national code

Ref country code: SE

Ref legal event code: TRGR