EP3535460A1 - Reinforcing framework and slab design - Google Patents
Reinforcing framework and slab designInfo
- Publication number
- EP3535460A1 EP3535460A1 EP17793664.8A EP17793664A EP3535460A1 EP 3535460 A1 EP3535460 A1 EP 3535460A1 EP 17793664 A EP17793664 A EP 17793664A EP 3535460 A1 EP3535460 A1 EP 3535460A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- reinforcing
- cross member
- framework
- reinforcing framework
- elongate members
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000003014 reinforcing effect Effects 0.000 title claims abstract description 164
- 238000010276 construction Methods 0.000 claims abstract description 37
- 125000006850 spacer group Chemical group 0.000 claims abstract description 32
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 5
- 230000008901 benefit Effects 0.000 description 26
- 239000004567 concrete Substances 0.000 description 22
- 238000004519 manufacturing process Methods 0.000 description 17
- 238000000034 method Methods 0.000 description 11
- 239000000463 material Substances 0.000 description 10
- 238000009434 installation Methods 0.000 description 9
- 238000013459 approach Methods 0.000 description 7
- 229910000831 Steel Inorganic materials 0.000 description 6
- 239000010959 steel Substances 0.000 description 6
- 238000003466 welding Methods 0.000 description 6
- 239000012779 reinforcing material Substances 0.000 description 5
- 238000009417 prefabrication Methods 0.000 description 4
- 230000002787 reinforcement Effects 0.000 description 4
- 239000002131 composite material Substances 0.000 description 3
- 238000001035 drying Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 238000011065 in-situ storage Methods 0.000 description 3
- 239000007795 chemical reaction product Substances 0.000 description 2
- 239000011152 fibreglass Substances 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000000704 physical effect Effects 0.000 description 2
- 229920000642 polymer Polymers 0.000 description 2
- 238000009416 shuttering Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 230000036541 health Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000009940 knitting Methods 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 230000000284 resting effect Effects 0.000 description 1
- 230000036642 wellbeing Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/01—Reinforcing elements of metal, e.g. with non-structural coatings
- E04C5/06—Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
- E04C5/0627—Three-dimensional reinforcements composed of a prefabricated reinforcing mat combined with reinforcing elements protruding out of the plane of the mat
- E04C5/0631—Reinforcing mats combined with separate prefabricated reinforcement cages or girders
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/01—Reinforcing elements of metal, e.g. with non-structural coatings
- E04C5/06—Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
- E04C5/0604—Prismatic or cylindrical reinforcement cages composed of longitudinal bars and open or closed stirrup rods
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/01—Reinforcing elements of metal, e.g. with non-structural coatings
- E04C5/06—Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
- E04C5/0636—Three-dimensional reinforcing mats composed of reinforcing elements laying in two or more parallel planes and connected by separate reinforcing parts
- E04C5/064—Three-dimensional reinforcing mats composed of reinforcing elements laying in two or more parallel planes and connected by separate reinforcing parts the reinforcing elements in each plane being formed by, or forming a, mat of longitunal and transverse bars
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/16—Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
- E04C5/18—Spacers of metal or substantially of metal
Definitions
- This invention relates to a reinforcing framework capable of prefabrication in an off- site location.
- the reinforcing framework can be subsequently transported to a building site location for instalment and use in the formation of reinforced concrete slabs in the construction of a building.
- Composite materials are widely used in the construction industry to form reinforced structures, for many reasons including durability, strength, tensile and thermal properties as well as flexibility in construction of various components and structures. It is to be appreciated that while concrete is an often used and popular choice for use in reinforced structures, other materials with similar physical properties, such as tensile strength and ductility, may be substituted.
- Reinforcement of concrete or similar material is often achieved by embedding a skeletal framework formed of reinforcing materials made of steel, polymers, fibre glass, or alternate composite material into the concrete or similar material.
- reinforcing materials made of steel, polymers, fibre glass, or alternate composite material.
- rebar steel reinforcing bars
- Shear reinforcement is required to resist the effects of sheer or diagonal stress on a material, such as concrete.
- shear links are often added to reinforcing frame work to counter shear stress.
- the length of the reinforcing materials used in skeletal frameworks can be adjusted by splicing two reinforcing materials, such as rebar, together. Splicing allows for shear stress to be transferred from one rebar to another. Splicing can be achieved by lapping the bars, using a mechanical joint, or welding the bars together where they join or overlap. Preferably splicing of bars is performed on alternate bars with up to 50% of reinforcement bars spliced in any given section of a reinforcing structure. Reinforoed concrete is used to build many different types of structures and components of structures including, slabs, walls, floors, beams, columns, foundations and frames.
- Reinforced concrete can be classified as precast or cast-in-place concrete.
- the loose rebar takes time to be loaded and unloaded from the vehicular transportation, meaning that there is increased disturbance at the offsite and onsite locations, as greater time is needed to complete the loading or offloading task. This issue is even more evident at onsite locations positioned on a busy road.
- fixers require substantial crane time to complete the manual fixation of bars in place meaning that there is increased downtime in construction, particularly for other build projects that require a crane to complete.
- a standard 1000 square foot reinforcing framework will require around 8 to 9 fixers and will take the 8 to 9 fixers about 5 to 6 working days to complete the reinforcing framework ready for concrete to be poured over the framework.
- the buildings and construction industry is under pressure to deliver faster, more cost- effective builds and . build designs without compromising the quality, strength and durability of the end product.
- a reinforcing framework for the construction of reinforced concrete structures including: at least two mesh layers, namely, a first mesh layer and a second mesh layer, a plurality of spaced-apart spacers mounted between the first layer and the second layer to support the two mesh layers spaced-apart in substantially parallel planes, each spacer having a cross member with a leg extending outwardly at each end of the cross member, said legs being substantially parallel to each other and substantially perpendicular to the cross member, each leg having a foot at an outer end of the leg remote from the cross member, the foot being substantially perpendicular to the leg and substantially perpendicular to the cross member, and the cross member being bent inwardly between the legs.
- the length of the cross member is sufficient to support a plurality of reinforcing bars.
- the spacing between the legs is greater than the spacing between adjacent parallel spaced-apart reinforcing bars of the mesh layer which engages the cross member.
- the cross member is curved inwardly between the legs. In another embodiment, the cross member is V-shaped.
- each spacer has feet which project outwardly from the legs in opposite directions.
- a spacer is mounted at a lifting point for the reinforcing framework.
- a plurality of spaced-apart splice bars project outwardly at one or both sides of the frame.
- the splice bars form an extension of one or both of the mesh layers. This arrangement facilitates automatic splicing of adjacent reinforcing frameworks during construction.
- One advantage of the new reinforcing framework of the present invention is that reinforcing frameworks comprising elongate members with a diameter of 10mm or more can now be prefabricated in an offsite location.
- Another advantage of the new reinforcing framework is that the design can be pre- approved by an engineer who has greater access for inspection.
- a further advantage of the new reinforcing framework of the present invention is that is capable of being produced in a controlled factory environment with standardised equipment set up and standardised methods and approach to construction.
- Another advantage of the new reinforcing framework is that build time onsite is greatly reduced with typical installation time taking minutes to hours to complete compared with the days to weeks' timeframe endured using traditional designs and manual assembly and installation techniques. Delivery and installation time is reduced by around 70% with no onsite labour required for fixing thereby increasing labour efficiency and decreasing labour costs associated with this task.
- a further advantage of the new reinforcing framework of the present invention is that there are fewer disturbances to other onsite activities and to the surrounding area affected by the building project, as the fully assembled reinforcing framework of the present invention can be loaded and unloaded from the vehicular transportation swiftly.
- a further advantage of the new reinforcing framework of the present invention is that monopoly of a crane for the purpose of assembling a reinforcing framework onsite by traditional fixing means is mitigated as the new reinforcing framework of the present invention arrives at the onsite location, fully assembled and ready to install and use.
- a further advantage of the new reinforcing framework of the present invention is that monopoly of the crane for the purpose of loading and unloading the reinforcing framework and placing the reinforcing framework into the desired location for installation and use, is reduced.
- a further advantage of the new reinforcing framework of the present invention is that the monopoly of skilled labour or manpower as traditionally required in assembling a reinforcing framework onsite by traditional fixing means, is mitigated as the new reinforcing framework of the present invention arrives at the onsite location, fully assembled and ready to install and use.
- a further advantage of the new reinforcing framework of the present invention is that the health safety and wellbeing of onsite labour is improved.
- a further advantage of the new reinforcing framework of the present invention is that productivity of the reinforcing framework made in factory environments is increased.
- a further advantage of the new reinforcing framework is that it provides a standardised construction approach with improved accuracy and consistency in building the reinforcing framework on which the completed reinforcing structure such as, but not limited to, a slab design, is made.
- a further advantage to the new reinforcing framework of the present invention is that by combining more than one mesh layer together, separated by a spacer, enables larger reinforcing structures to be constructed with rebar elements having diameters of up to 40mm.
- the cross member is curved such as to allow a gap to be formed between the cross member and the mesh layer engaged therewith.
- the gap formed between the cross member and the first mesh layer is generally positioned at a substantially midway point along the cross member and between proximal and distal ends of the cross member.
- curve in the cross member allows for ease of access through the gap positioned between the cross member and to the two sets of elongate members present in the first mesh layer such that it allows at least one bar to be placed between the two sets of elongate members present in the first mesh layer.
- a further advantage of the curve in the cross member is that the curve allows for additional reinforcing bars to be added once the reinforcing framework has been fully assembled.
- a further advantage of the curve in the cross member is that the curve allows for ease of access to enable the additional bars to be spliced together with the existing elongate members of the first mesh layer once the reinforcing framework has been fully assembled.
- any and all details pertaining to the second set of elongate members may also equally be applied to the first set of elongate members.
- any and all details pertaining to the first mesh layer may equally be applied to the second mesh layer.
- the mesh layers are interchangeable in this regard.
- the at least one bar may be placed evenly throughout the first mesh layer and adjacent to one or more elongate member.
- more than one bar is placed, namely a first bar and a second bar, such that the first bar is placed at a distance of approx. 500mm c ⁇ c from the second bar.
- the curve of the cross member is any angle from 1° to 45°.
- the curve of the cross member is any angle from 5° to 30°. In a most preferred embodiment the curve of the cross member is any angle from 8° to 15°.
- a further advantage of the curve in the cross member is that splicing together the two sets of elongate members, present in the first mesh layer, where the first set of elongate members engage the second sets of elongate members, can be performed easily. Such positions, where the first set of elongate members engage the second set of elongate members, as spliced together may further be referred to as joints.
- the at least one contact point is substantially adjacent to the distal or proximal ends of the cross member.
- the cross member comprises at least two contact points.
- One advantage of the contact points is that the contact points provides clearly defined positions on the first mesh layer that provide improved purchase, such that the fully assembled reinforcing framework may be lifted about the contact points from the vehicular transportation to the desired position for final instalment and use. Such contact points may also be referred to as lifting points.
- a further advantage of the contact points is that the contact points enable multiple fully assembled reinforcing frameworks to be lifted from the vehicular transportation to the desired position for instalment and use. Being able to lift multiple fully assembled reinforcing frameworks in a single lift means that the time taken to load and unload the reinforcing framework is greatly reduced and less disturbance of other onsrte activities.
- a further advantage of the contact points is that, due to the reduced number of lifts required to load or unload the fully assembled reinforcing frameworks, the crane time needed is significantly reduced freeing up the crane for other onsite jobs or projects. This has a positive impact on overall build time meaning that the construction project can be completed in a shorter time period.
- One advantage of having each foot portion extending in the opposite direction to one another is that stability of the overall spacer is improved.
- each of the first mesh layer and second mesh layer comprise at least two sets of elongated members, namely a first set and a second set
- One advantage of the present invention is that the diameters of the elongate members, used in constructing the mesh layers, namely the first mesh layer and the second mesh layer, can range from 10mm to 100mm.
- the diameters of the elongate members, used in constructing the mesh layers, namely the first mesh layer and the second mesh layer range between 10mm to 70mm.
- the diameters of the elongate members, used in constructing the mesh layers, namely the first mesh layer and the second mesh layer range between 10mm to 50mm.
- the diameters of the elongate members, used in constructing the mesh layers, namely the first mesh layer and the second mesh layer range between 10mm to 40mm.
- first set of elongated members and the second set of elongate members are positioned substantially perpendicular to one another.
- first set of elongate members are arranged in pairs, each pair of elongate members being positioned substantially in parallel to the next pair of elongate members.
- each elongate member differs in length.
- One advantage to having differing lengths of elongate members is that it allows for greater flexibility in the design of different types of reinforcing structures.
- a further advantage to having differing lengths of elongate members is that it allows for designs to be adjusted to fit onsite dimensions. ln a most preferred embodiment in each pair of elongate members one elongate member is substantially shorter than the other elongate member that makes up the pair. In a further embodiment at least a proportion of the individual components that make up the reinforcing framework are made from one or more of steel, rebar, polymers, fibre glass and alternate composite material or any combination thereof.
- the present invention is further directed towards a method of fabricating and installing the reinforcing framework in the construction of reinforcing structures comprising prefabricate of the reinforcing framework in an off-site location; transporting and delivering a complete assembly of the fabricated reinforcing framework to the site; instalment of the reinforcing framework by lifting the complete assembly into the desired position; and, applying concrete to the reinforcing framework.
- One advantage of the method of fabricating and installing reinforcing framework of the present invention is that production in a controlled factory environment with standardised equipment set up and standardised methods and approach to construction enables a fast and efficient turnaround of production of individual components and the fully assembled reinforcing structure.
- the method of fabricating and installing reinforcing framework with standardised equipment set up can speed up production of the fully assembled reinforcing structure by being continually present and in the desired position ready for assembly purposes. It is to be appreciated that during onsite fabrication of similar reinforcing frameworks the equipment is often moved and repositioned for the purpose of other onsite jobs, meaning mat the fabrication is slowed as the equipment needs to be returned to the desired position for the purpose of fabricating reinforcing frameworks.
- a further advantage of the method of fabricating and installing reinforcing framework of the present invention is that mass production is enabled.
- the reinforcing framework of the present invention may be transportable at any length and width, and in particular any wide-load width or parameters as may be required or imposed by vehicular transportation.
- the method comprises a drying step following the application of concrete, in particular when the concrete is cast-in-place.
- the advantage of having a drying step is to set the concrete, or other similar material, hard and in place against the reinforcing framework to form a strong and robust reinforcing structure.
- reinforcing frameworks of the present invention are for use in the construction of one or more reinforcing structures including, but not limited to, slabs, walls, floors, beams, columns, foundations and frames.
- reinforcing framework for use in constructing reinforcing structures, can be arranged in a variety of sequences in conjunction with other reinforcing frameworks including, but not limited to, in series and in parallel.
- Figure 1 shows a perspective view of a portion of a reinforcing framework in accordance with the present invention
- Figure 2 shows a front view of the reinforcing framework of Figure 1 ;
- Figure 3 shows a side sectional view of the reinforcing framework of Figure 1 ;
- Figure 4 shows a further side sectional view of the reinforcing framework of Figure
- Figures 5a to 5g show a series of fabrication steps for constructing the reinforcing framework of Figure 1 and a resulting reinforcing structure
- Figure 6 is a plan view of another reinforcing framework according to another embodiment of the invention.
- Figure 7 is a side sectional elevational view showing the reinforcing framework of Figure 6 in use
- Figure 8 is a plan view of a further reinforcing framework according to another embodiment of the invention.
- Figure 9 is a side sectional elevational view of the reinforcing framework of Figure 8, shown in use;
- Figure 10 is a detail perspective view showing the reinforcing framework of the invention in use
- Figure 11 is another detail perspective view showing the reinforcing framework in use
- Figure 12 is a perspective view showing a reinforcing framework of the invention in use.
- Figure 13 is a detail perspective view showing portion of the arrangement in Fig. 12.
- a prefabricated reinforcing skeletal framework according to the invention indicated generally by reference numeral 100 for use in the construction of reinforced structures such as floor slabs and wall slabs in buildings.
- the reinforcing skeletal framework 100 is shown without a set of elongate members of a first top mesh layer, in order to improve the understandability of the drawing.
- the reinforcing skeletal framework comprises at least two mesh layers, namely a first mesh layer and a second mesh layer, indicated generally by reference numerals 202 and 204 respectively; and, a plurality of spacers, generally indicated by reference numeral 206.
- the first mesh layer 202 and the second mesh layer 204 are substantially adjacent from one another and, when fully constructed for use, are held separate by the plurality of spacers 206.
- a plurality of spaced-part spacers 206 support the two mesh layers spaced-apart in substantially parallel planes in a double skin construction.
- Each of the plurality of spacers 206 is formed of a cross member 302, leg portions 304 and foot portions 306.
- Each leg portion 304 has a top and a bottom and is connected, at the top of the leg portion 304, to a distal or proximal end of the cross member 302.
- the leg portion 304 is positioned substantially perpendicular to the cross member 302.
- Each leg portion 304 is also connected to at least one foot portion 306 at the bottom end of the leg portion 304 remote from the cross member 302.
- the foot portion 306 extends substantially perpendicular to the leg portion 304. In this way, the cross member 302, the leg portion 304 and the foot portion 306 may be mutually orthogonal to each other.
- foot portions 306 project outwardly from the legs 304 in opposite directions as shown in the drawings.
- the first mesh layer 202 and second mesh layer 204 independently comprise of at least two sets of elongated reinforcing bar members, namely a transverse first set 308 and a longitudinal second set 310 of spaced-apart reinforcing bars in parallel alignment, positioned substantially perpendicular to one another, so as to form a grid-like structure for the mesh layer 202, 204.
- the second set of elongate members 310 Is arranged in pairs 312 of reinforcing bars, comprising a first elongate reinforcing bar member 312a and a second elongate reinforcing bar member 312b, each pair of elongate members 312 being positioned substantially parallel to and spaced-apart from the next pair of elongate members 312 within the second set of elongate members 310.
- the first elongate member 312a making up each pair of elongate members 312 may independently be of different length to the second elongate member 312b making up each pair of elongate members 312.
- the second elongate member 312b which forms one of the pair of elongate members 312 may be substantially shorter than the first elongate member 312a that forms the other of the pair of elongate members 312.
- Each of the pairs of elongate members 312 may be of different lengths independently of each other pair in the second set of elongate members 310.
- any and all details pertaining to the second set of elongate members 310 may also equally be applied to the first set of elongate members 308.
- any and all details pertaining to the first mesh layer 202 may equally be applied to the second mesh layer 204.
- the mesh layers 202, 204 are interchangeable in this regard.
- the cross member 302 has a distal and proximal end, with a portion of the cross member 302 curved intermediate the ends such as to allow at least one contact point 402 between the cross member 302 and the first mesh layer 202, wherein the contact point 402 is located towards one of the distal and proximal ends of the cross member 302. Said portion of the cross member 302 being curved intermediate the ends also allows for a gap 404 to be formed between the cross member 302 of the spacer 206 and the first mesh layer 202.
- An example of a fabrication method of the reinforcing framework of the present invention will now be described. It will be appreciated that alternative methods of fabrication may be used.
- the reinforcing framework 100 is fabricated firstly by laying out the first set of elongate members 308, spaced-apart and substantially in parallel to one another. This is followed by the second elongate members 312b of the second set of elongate members 310 positioned spaced-apart and mutually orthogonal to the first set of elongate members 308 as shown in Figure 5b.
- the spacers 206 are positioned substantially adjacent to and resting on the first set of elongate members 308, such that the foot portions 306 of the spacer 206 are positioned substantially adjacent to the second elongate member 312b of the second set of elongate members 310.
- the foot portions 306 of the spacer 206 are then secured to the second elongate member 312b of the second set of elongate members 310 and the second elongate members 312b are secured to the elongate members 308.
- the first elongate member 312a is positioned substantially adjacent to the second elongate member 312b to form a pair of elongate members 312 within the second set of elongate members 310.
- the first elongate member 312a is then secured to the second elongate member 312b to complete the second mesh layer 204.
- first elongate member 312a may be positioned substantially adjacent to the foot portions 306 of the spacer 206, such that the foot portions 306 of the spacer 206 are positioned between the first elongate member 312a and the second elongate member 312b.
- some further second elongate members 312b are arranged substantially in parallel and over the cross members 302 of the plurality of spacers 206.
- first elongate members 312a are laid out substantially adjacent to the further second elongate members 312b so as to be substantially adjacent the cross member 302 of the spacer 206 as can be seen in Figure 5e.
- the first elongate members 312a and second elongate members 312b are secured together to form a pair of elongate members 312 and forming a further second set of elongate members 310.
- a further first set of elongate members 308 are positioned mutually orthogonal to the further second set of elongate members 310.
- the further first set of elongate members 308 and the further second set of elongate members 310 are secured together to form the first mesh layer 202.
- the first mesh layer 202 is then secured to the cross member 302 of the spacers 206.
- the prefabricated mesh cage construction thus formed can be transported to a building site and lifted into position.
- construction of the reinforcing structure comprising the reinforcing framework 100 is completed in situ at an onsite location; concrete, or other material, is applied to the reinforcing framework 100, such that only a portion of the first mesh layer 202 and the second mesh layer 204 remain visible, namely the ends of the pair of elongate members 312 that make up the second set of elongate members 310 present in both the first mesh layer 202 and the second mesh layer 204.
- Figures 5a to 5g show the method for fabrication of the reinforcing framework 100 of the present invention as following a certain series of steps as outlined above, the method of fabrication may comprise similar steps conducted in alternative orders, such as may be considered more efficient or otherwise beneficial, without being considered to substantially deviate from the present invention.
- Figures 5a to 5g show the first mesh layer 202 and second mesh layer 204 to be constructed in situ in connection with the spacer 206, that each of the mesh layers, namely the first mesh layer 202 and the second mesh layer 204 may be fabricated independently and separately from each other and the reinforcing framework 100. The complete assembly of the first mesh layer 202 and the complete assembly of the second mesh layer 204 are then incorporated into the fabrication of the reinforcing framework 100 of the present invention.
- Such method of fabricating the reinforcing framework 100 of the present invention may comprise firstly laying out the second mesh layer 204 before placing the spacers 206 positioned substantially adjacent to the first set of elongate members 308, such that the foot portions 306 are positioned substantially adjacent to the second elongate member 312b of the second set of elongate members 310 present in the second mesh layer 204.
- the foot portions 306 of the spacer 206 are then secured to the second elongate member 312b of the second set of elongate members 310 present in the second mesh layer 204;
- the first mesh layer 202 is placed such as to position the first mesh layer 202 substantially adjacent to the cross member 302 of the spacer 206.
- the first mesh layer 202 is placed, such that shear links contained within the first mesh layer 202 are positioned substantially adjacent to the lifting points.
- the first set of elongate members 308 are then spliced to the second set of elongate members 310, where the first set of elongate members 308 and the second set of elongate members 310 fall within the curve area of the cross member 302 of the spacer 206.
- the first mesh layer 202 is then secured to the cross member 302 of the spacer 206 about the contact points.
- securing of elongate members and the spacer may include, but is not limited to, splicing and fixers made of steel or other material as may be deemed appropriate in the industry for use as a fixer, and welding.
- Splicing may include, but is not limited to, half lap splice, bevel lap splice and tabled splice joints as may be deemed appropriate.
- Welding may include any form of welding technique, as may be deemed appropriate, including, but not limited to spot welding, bottom welding,
- Example 1 Method of constructing and installing a reinforcing framework for a slab design in accordance with the present invention.
- the reinforcing framework 100 is firstly designed and approved by engineers. Prefabrication in an offsite location is achieved by fixing the components of the reinforcing framework 100 using standard steel fixers according to a slab format design, as pre-approved by an engineer. The assembled reinforcing framework 100 is then transported and delivered, in one piece, to the site of instalment. Instalment involves lifting the assembled reinforcing framework 100, in one piece, into the desired position and cast-in-place concrete applied to the reinforcing framework 100. The concrete is then allowed to dry before use of the fully formed slab.
- FIG. 6 and Fig. 7 there is shown another reinforcing framework according to the invention, indicated generally by the reference numeral 400. Parts similar to those described previously are assigned the same reference numerals. In this case, splice bars 401 project outwardly at one side of the reinforcing framework 400 in a single fly arrangement.
- Fig. 7 shows a concrete slab 402 cast about the reinforcing framework 400 in use.
- FIG. 8 and Fig. 9 there is shown another reinforcing framework according to another embodiment of the invention, indicated generally by the reference numeral 500. Parts similar to those described previously are assigned the same reference numerals.
- sets of splice bars 401 project outwardly at both sides of the reinforcing framework 500. It will be noted that this has a double fly construction with the splice bars 401 projecting out at opposite sides of the reinforcing framework 500 and forming an extension of the first mesh layer 202 and second mesh layer 204.
- the arrangements in Figures 6 to 9 advantageously provide for automatic splicing of the reinforcing frameworks 400, 500 during construction of a building.
- the reinforcing framework 400 is inserted first.
- reinforcing framework 500 are dropped into place in alignment with the first reinforcing framework 400 with the splice bars 401 overlapping with the adjacent framework. It will be appreciated that the reinforcing frameworks 400, 500 facilitate automatic splicing of the reinforcing frameworks 400, 500 which greatly speeds up the construction process.
- FIG. 10 this shows the knitting together of a vertical wall panel 600 and a reinforcing framework 400.
- Fig. 11 shows this from another angle. It will be noted that U-bar ends 410 on the reinforcing framework 400 accommodate varying dimensions. It will be appreciated that the wall panel reinforcement may be formed by any of the reinforcing frameworks of the invention previously described.
- this shows a reinforcing framework 500 mounted at a column 700. It will be noted in Fig. 13, a cutaway portion 502 is provided in the reinforcing framework 500 to accommodate the column 700. Shear links 503 are incorporated into the steelwork of the reinforcing frame 500 around the opening 502. It is to be appreciated that while the present example demonstrates a slab design the reinforcing framework may also be used to construct and install other reinforcing structures such as, but not limited to, walls, floors, beams, columns, foundations and frames.
- frame refers to a structure, or structures, for supporting or enclosing a reinforcing structure or prefabricated concrete, such as reinforcing slab designs, and as such are to be considered as interchangeable and accorded the widest possible interpretation. Said terms should not be confused with “forrnwork” or “shuttering” as further defined below.
- forrnwork or “shuttering, refer to temporary or permanent moulds into which cement , or other material, may be poured and allowed to dry, and as such may be formed of "framework”, “skeletal framework”, “frame” and “skeleton”.
- double skin and double skin mats are well known industry terms to mean a set of skins, panels or rebar mats or mesh layers and as such are to be considered as interchangeable and accorded the widest possible interpretation.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Reinforcement Elements For Buildings (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Working Measures On Existing Buildindgs (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
- Rod-Shaped Construction Members (AREA)
- Panels For Use In Building Construction (AREA)
Abstract
Description
Claims
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP23192510.8A EP4273344A3 (en) | 2016-11-03 | 2017-11-03 | Reinforcing framework and slab design |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB201618561 | 2016-11-03 | ||
PCT/EP2017/078244 WO2018083272A1 (en) | 2016-11-03 | 2017-11-03 | Reinforcing framework and slab design |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP23192510.8A Division EP4273344A3 (en) | 2016-11-03 | 2017-11-03 | Reinforcing framework and slab design |
Publications (2)
Publication Number | Publication Date |
---|---|
EP3535460A1 true EP3535460A1 (en) | 2019-09-11 |
EP3535460B1 EP3535460B1 (en) | 2023-08-23 |
Family
ID=60202059
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP23192510.8A Pending EP4273344A3 (en) | 2016-11-03 | 2017-11-03 | Reinforcing framework and slab design |
EP17793664.8A Active EP3535460B1 (en) | 2016-11-03 | 2017-11-03 | Reinforcing framework and slab design |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP23192510.8A Pending EP4273344A3 (en) | 2016-11-03 | 2017-11-03 | Reinforcing framework and slab design |
Country Status (11)
Country | Link |
---|---|
US (1) | US20190277031A1 (en) |
EP (2) | EP4273344A3 (en) |
AU (2) | AU2017353537A1 (en) |
CA (1) | CA3081118A1 (en) |
DK (1) | DK3535460T3 (en) |
ES (1) | ES2962654T3 (en) |
FI (1) | FI3535460T3 (en) |
LT (1) | LT3535460T (en) |
PL (1) | PL3535460T3 (en) |
PT (1) | PT3535460T (en) |
WO (1) | WO2018083272A1 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU2020354492A1 (en) | 2019-09-23 | 2022-04-28 | Midland Steel Reinforcement Supplies Limited | Reinforcing steel skeletal framework |
US20240254769A1 (en) * | 2022-03-25 | 2024-08-01 | Shahn Christian Andersen | Modular Prefabricated Rebar Component |
Family Cites Families (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1735592A (en) * | 1929-06-08 | 1929-11-12 | Kalman Steel Co | Mat chair |
US3132448A (en) * | 1958-05-08 | 1964-05-12 | Colorado Builders Supply Co | Chair for concrete reinforcing rods |
SE321334B (en) * | 1966-12-16 | 1970-03-02 | A Aberg | |
US3512331A (en) * | 1969-02-17 | 1970-05-19 | Hull Metal & Supply Corp | Rod chair |
SE351003B (en) * | 1970-08-11 | 1972-11-13 | Europ Eng Establishment | |
US4084916A (en) * | 1976-12-22 | 1978-04-18 | Charles Senn | Steel mesh system and brackets |
US5287672A (en) * | 1991-04-16 | 1994-02-22 | Oklahoma Steel & Wire Co. | Reinforcement bar trussing structure and method of making the same |
JP3236839B2 (en) * | 1999-07-22 | 2001-12-10 | 株式会社高橋製作所 | Rebar spacer |
US20060059804A1 (en) * | 2004-08-20 | 2006-03-23 | Brown William G | Components for use in large-scale concrete slab constructions |
AU2006252206A1 (en) * | 2006-12-21 | 2008-07-10 | Onesteel Reinforcing Pty Ltd | Bar chairs |
JP4898875B2 (en) * | 2009-08-03 | 2012-03-21 | 三和線材株式会社 | Bar arrangement spacer |
US20120227350A1 (en) * | 2011-03-08 | 2012-09-13 | Beaver Plastics Ltd. | Rebar support for use when forming concrete structures |
USD651066S1 (en) * | 2011-06-06 | 2011-12-27 | Masonry Reinforcing Corporation Of America | Rebar positioner |
US8448404B2 (en) * | 2011-06-06 | 2013-05-28 | Masonry Reinforcing Corporation Of America | Bond beam rebar positioner |
WO2016020932A2 (en) * | 2014-08-04 | 2016-02-11 | Srinidhi Anantharaman | Deployable pre-fabricated reinforcement cage system |
-
2017
- 2017-11-03 WO PCT/EP2017/078244 patent/WO2018083272A1/en unknown
- 2017-11-03 LT LTEPPCT/EP2017/078244T patent/LT3535460T/en unknown
- 2017-11-03 EP EP23192510.8A patent/EP4273344A3/en active Pending
- 2017-11-03 PT PT177936648T patent/PT3535460T/en unknown
- 2017-11-03 DK DK17793664.8T patent/DK3535460T3/en active
- 2017-11-03 ES ES17793664T patent/ES2962654T3/en active Active
- 2017-11-03 FI FIEP17793664.8T patent/FI3535460T3/en active
- 2017-11-03 CA CA3081118A patent/CA3081118A1/en active Pending
- 2017-11-03 US US16/347,271 patent/US20190277031A1/en active Pending
- 2017-11-03 PL PL17793664.8T patent/PL3535460T3/en unknown
- 2017-11-03 AU AU2017353537A patent/AU2017353537A1/en not_active Abandoned
- 2017-11-03 EP EP17793664.8A patent/EP3535460B1/en active Active
-
2023
- 2023-08-22 AU AU2023219854A patent/AU2023219854A1/en active Pending
Also Published As
Publication number | Publication date |
---|---|
PT3535460T (en) | 2023-11-20 |
WO2018083272A1 (en) | 2018-05-11 |
AU2017353537A1 (en) | 2019-06-20 |
DK3535460T3 (en) | 2023-11-06 |
PL3535460T3 (en) | 2024-03-18 |
EP4273344A3 (en) | 2023-12-06 |
FI3535460T3 (en) | 2023-11-09 |
EP4273344A2 (en) | 2023-11-08 |
ES2962654T3 (en) | 2024-03-20 |
EP3535460B1 (en) | 2023-08-23 |
CA3081118A1 (en) | 2018-05-11 |
LT3535460T (en) | 2023-12-11 |
AU2023219854A1 (en) | 2023-09-28 |
US20190277031A1 (en) | 2019-09-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2892837C (en) | Prefabricated modular rebar modules and methods of using the same | |
AU2023219854A1 (en) | Reinforcing framework and slab design | |
JP6004353B2 (en) | Replacement method of concrete floor slab for elevated road | |
US9683361B2 (en) | Method and system for rapid construction of structurally reinforced concrete structures using prefabricated assemblies and method of making the same | |
US20160108618A1 (en) | Prefabricated modular rebar modules and methods of using the same | |
US20120210669A1 (en) | Method of constructing prefabricated steel reinforced concrete (psrc) column using angle steels and psrc column using angle steels | |
JP5937898B2 (en) | Construction method of box girder bridge | |
JP2019526004A (en) | Precast concrete formwork, floor system, and construction method | |
EP3176325A1 (en) | Process for the construction of structures with void segments and system for construction with void segments | |
CN112681511B (en) | Reinforced concrete structure construction method using section steel to replace part of reinforcing steel bars | |
CN112814163B (en) | Construction method of building without template | |
JP2002089043A (en) | Reinforced concrete structure and construction method for steel framed reinforced concrete, structure | |
JP2017096057A (en) | Bridge construction method | |
US20220356706A1 (en) | Reinforcing Steel Skeletal Framework | |
JP6012353B2 (en) | Composite column structure and composite column construction method | |
KR20200113901A (en) | Method for constructing flat slab structure with drop panel | |
RU126738U1 (en) | VALVE FORMWORK BLOCK | |
JP6842351B2 (en) | Culvert construction method | |
JPH05148817A (en) | Construction of pc bridge | |
Hertz et al. | Pearl-Chain Structures | |
RU2617813C2 (en) | The method of erection of prefabricated multi-storey reinforced concrete frame of a building | |
NL2006456C2 (en) | METHOD FOR BUILDING A BUILDING, PREFAB SANDWICH PANEL AND FORMWORK. | |
WO2020222630A1 (en) | Hollow core slab manufactured by vibration casting without formwork | |
JP2010144388A (en) | Method for constructing skeleton of steel-reinforced concrete structure | |
CZ20013613A3 (en) | Permanent formwork prefabricated element and method for making a panel-like construction from permanent formwork prefabricated elements |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: UNKNOWN |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE |
|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20190531 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
DAV | Request for validation of the european patent (deleted) | ||
DAX | Request for extension of the european patent (deleted) | ||
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
17Q | First examination report despatched |
Effective date: 20220421 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20230302 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602017073145 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IE Payment date: 20230911 Year of fee payment: 7 |
|
REG | Reference to a national code |
Ref country code: DK Ref legal event code: T3 Effective date: 20231103 |
|
REG | Reference to a national code |
Ref country code: RO Ref legal event code: EPE |
|
REG | Reference to a national code |
Ref country code: PT Ref legal event code: SC4A Ref document number: 3535460 Country of ref document: PT Date of ref document: 20231120 Kind code of ref document: T Free format text: AVAILABILITY OF NATIONAL TRANSLATION Effective date: 20231115 |
|
REG | Reference to a national code |
Ref country code: SE Ref legal event code: TRGR |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: FP |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 20231116 Year of fee payment: 7 Ref country code: LU Payment date: 20231116 Year of fee payment: 7 |
|
REG | Reference to a national code |
Ref country code: NO Ref legal event code: T2 Effective date: 20230823 Ref country code: AT Ref legal event code: MK05 Ref document number: 1602760 Country of ref document: AT Kind code of ref document: T Effective date: 20230823 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231124 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20231107 Year of fee payment: 7 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: ES Payment date: 20231205 Year of fee payment: 7 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231223 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231223 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231124 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: SE Payment date: 20231107 Year of fee payment: 7 Ref country code: RO Payment date: 20231102 Year of fee payment: 7 Ref country code: PT Payment date: 20231122 Year of fee payment: 7 Ref country code: NO Payment date: 20231108 Year of fee payment: 7 Ref country code: LT Payment date: 20231103 Year of fee payment: 7 Ref country code: FR Payment date: 20231107 Year of fee payment: 7 Ref country code: FI Payment date: 20231107 Year of fee payment: 7 Ref country code: DK Payment date: 20231107 Year of fee payment: 7 Ref country code: DE Payment date: 20231030 Year of fee payment: 7 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: BE Payment date: 20231116 Year of fee payment: 7 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FG2A Ref document number: 2962654 Country of ref document: ES Kind code of ref document: T3 Effective date: 20240320 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602017073145 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AL Payment date: 20231218 Year of fee payment: 7 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20231130 |
|
26N | No opposition filed |
Effective date: 20240524 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20231130 Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230823 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: PL Payment date: 20231103 Year of fee payment: 7 |