EP3508281A1 - Painting assembly - Google Patents

Painting assembly Download PDF

Info

Publication number
EP3508281A1
EP3508281A1 EP19150648.4A EP19150648A EP3508281A1 EP 3508281 A1 EP3508281 A1 EP 3508281A1 EP 19150648 A EP19150648 A EP 19150648A EP 3508281 A1 EP3508281 A1 EP 3508281A1
Authority
EP
European Patent Office
Prior art keywords
functional
building
media
wing
treatment areas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP19150648.4A
Other languages
German (de)
French (fr)
Inventor
Giorgio Boscarino
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Eisenmann SE
Original Assignee
Eisenmann SE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Eisenmann SE filed Critical Eisenmann SE
Publication of EP3508281A1 publication Critical patent/EP3508281A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05BSPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
    • B05B16/00Spray booths
    • B05B16/40Construction elements specially adapted therefor, e.g. floors, walls or ceilings
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05BSPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
    • B05B16/00Spray booths
    • B05B16/20Arrangements for spraying in combination with other operations, e.g. drying; Arrangements enabling a combination of spraying operations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05BSPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
    • B05B13/00Machines or plants for applying liquids or other fluent materials to surfaces of objects or other work by spraying, not covered by groups B05B1/00 - B05B11/00
    • B05B13/02Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work
    • B05B13/04Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work the spray heads being moved during spraying operation
    • B05B13/0447Installation or apparatus for applying liquid or other fluent material to conveyed separate articles
    • B05B13/0452Installation or apparatus for applying liquid or other fluent material to conveyed separate articles the conveyed articles being vehicle bodies
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05BSPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
    • B05B14/00Arrangements for collecting, re-using or eliminating excess spraying material
    • B05B14/40Arrangements for collecting, re-using or eliminating excess spraying material for use in spray booths
    • B05B14/43Arrangements for collecting, re-using or eliminating excess spraying material for use in spray booths by filtering the air charged with excess material
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B05SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
    • B05BSPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
    • B05B16/00Spray booths
    • B05B16/60Ventilation arrangements specially adapted therefor

Definitions

  • a building concept in which it is possible for the operating media to be guided in a specially designed building part, namely the functional wing, and to be removed from or from this at various points.
  • the media conduit is connectable to complementary media conduits in the building wing in at least two connection regions spaced longitudinally. In this way, a service medium with a single line can be distributed and conveyed over the length of the paint shop.
  • the functional tract comprises functional modules for technical facilities and construction modules for infrastructure and structural engineering.
  • To this Way is a modular structure of the functional tract possible, which combines the requirements of the Lackier plante on the one hand and the requirements of the building from a structural point of view on the other.
  • the functional modules and / or the design modules are oriented vertically. In this way, cross-floor building concepts are possible.
  • the functional tract comprises one or more functional modules with one or more flow channels of an air system and / or one or more functional modules in which components for powering the paint shop are accommodated, and / or one or more functional modules with one or more installation shafts for media lines.
  • the functional wing one or more construction modules for one or more staircases and / or one or more construction modules for one or more elevator systems and / or one or more design modules for the establishment of recreational and / or communication zones and / or one or several design modules to compensate for expansion variations of the building body includes.
  • the building wing has several floors, it is particularly advantageous if the floors are accessible via the functional wing and connected to each other.
  • FIGS. 1 to 3 show a plant complex 10 of a paint shop 12, in which objects are painted; in the illustrated embodiment, it is a paint shop 12, in which vehicle bodies 14 are painted, with only in FIG. 6 a vehicle body 14 is shown.
  • the plant complex 10 has a building structure 16 in and on which the plant components of the plant complex 10 are accommodated.
  • the building structure 16 defines one only in the FIGS. 1 and 2 longitudinal direction 18 denoted by an arrow and two end faces 20 and 22 opposite in the longitudinal direction 18 and comprises a central functional tract 24 which is flanked in the longitudinal direction 18 by a first building wing 26 and a second building wing 28. In the exemplary embodiment described here, the building wings 26 and 28 adjoin the functional wing 24 directly.
  • the building structure 16 is enclosed in total by a building envelope 30.
  • an intermediate storage to the building body 16 which is formed in the present embodiment as a high-bay warehouse 32 and in the FIGS. 1 and 2 schematically indicated by dashed lines and shown in phantom.
  • it can be provided as an intermediate storage and a surface storage.
  • the Governmentbaugroper 16 has a plurality of floors or floors 34, wherein viewed in the present embodiment from bottom to top four floors 34.1, 34.2, 34.3 and 34.4 are available.
  • the floor 34.1 also referred to as the ground floor
  • the floors 34.2 and 34.3 as the first and second floors
  • the floor 34.4 also referred to as a penthouse, wherein the reference numerals are retained.
  • the penthouse always refers to the top floor; There may be between ground floor 34.1 and penthouse but also only a single upper floor or more than two upper floors.
  • the floors 34 of the building structure 16 may, but need not be separated from each other by ceilings or shelves.
  • Components and components located on the upper floors 34.2, 34.3 or the penthouse 34.4 may also be supported by steel structures anchored to the floor of the ground floor 34.1.
  • the floor of the ground floor 34.1 defines a 0 m level
  • the floors of the two upper floors 34.2, 34.3 and the Penthouses 34.4 lie on this 0 m level at +5 m, +10.5 m and +16 m respectively.
  • the vehicle bodies 14 to be treated are conveyed by means of a conveyor system 38 along a conveying path 40 through the treatment areas 36, which will now be described with reference to FIG FIG. 4 in conjunction with the Figures 2 and 3 is explained.
  • the conveying path 40 of the vehicle bodies 14 through the individual treatment areas 36 can vary and depends on the treatment areas 36 to be completed and on the painting plan, ie which sequence of vehicle bodies 14 is to be painted. Processes can also be changed.
  • a vehicle body 14 Before a vehicle body 14 is painted, it passes from a paint shop 12 upstream Rohbaustrom in the high-bay warehouse 32. There, the vehicle body 14 is optionally stored.
  • the vehicle body 14 is conveyed out of the high-bay warehouse 32 into the paint shop 12 and initially conveyed to the second upper floor 34.2 in a pre-treatment dipping installation 42, which is located on the ground floor 34.1 and in the first and second floors 34.2 and 34.3.
  • the pre-treatment dip system 42 includes a pretreatment dip tank 44 in the first floor 34.2, in which the vehicle body 14 is lowered from the second floor 34.3.
  • On the ground floor 34.1 are metering stations for chemical agents and counter container 46, which in FIG. 2 can be seen.
  • the vehicle body 14 is lifted out of the pretreatment dip tank 44 and is again on the second floor 34.3.
  • KTL being the abbreviation for "cataphoretic dip painting".
  • the KTL system 48 extends over the ground floor 34.1 and the first and second floors 34.2 and 34.3.
  • the KTL system 48 includes a KTL dip tank 50 on the first floor 34.2; Again, the vehicle body 14 is lowered from the second floor 34.3 in the KTL dip tank 50.
  • On the ground floor 34.1 are located below the KTL dip tank 50 associated dosing for KTL paint, chemicals and KTL counter container 52nd
  • the conveying path 40 of the conveyor system 38 comprises return sections 54 for the conveyor technology, on the way of which they can be moved back to the dip tanks 44 and 54 to their immersion area.
  • the KTL system 48 also includes a KTL dryer 56, which is located on the first floor 34.2 and in which the vehicle body 14 passes after the cataphoretic dip painting from the second floor 34.3 via a multi-floor transition section 58 of the conveying path 40 of the conveyor system 38.
  • a vertical conveyor can be arranged for this purpose.
  • operating units 60 which in turn are housed in the second floor 34.3; please refer Figures 2 and 3 ,
  • a KTL cooling zone 62 At the end of the KTL dryer 56 is a KTL cooling zone 62, which is followed by a vertical conveyor 64, with which the vehicle body 14 is conveyed down into the ground floor 34.1, if the vehicle body 14 is to be treated immediately following the cataphoretic dip painting , Alternatively, the vehicle body 14 can also initially be conveyed back into the high-bay warehouse 32.
  • the vehicle body 14 On the ground floor 34.1, the vehicle body 14 initially comes in FIG. 3 to be recognized workstations 66, which are located below the KTL system 48 and in which the vehicle body 14 may be subjected to, for example, an audit and / or a grinding process.
  • the vehicle body 14 becomes a likewise in FIG. 3 to be recognized underbody protection cabin 68 a underbody protection system 70 promoted.
  • the underbody protection cabin 68 extends in the longitudinal direction 18 below a underbody protection dryer 72 of the underbody protection system 70 in the first floor 34.2, which runs parallel to the KTL dryer 56.
  • the underbody protection system 70 in the first floor 34.2 thus runs overall parallel to the KTL dryer 56.
  • both the application of the underbody protection and the seam sealing takes place.
  • the output of the underbody protection cabin 68 is conveyor technically linked via a further vertical conveyor 74 to the entrance of the underbody protection dryer 72, at the end of which a underbody protection cooling zone 76 is located.
  • On the second floor 34.3 operating units 78 of the underbody protection dryer 72 are arranged, which again in the Figures 2 and 3 are shown.
  • first building wing 26 is generally a basic treatment line 80 for vehicle bodies 14 housed.
  • this includes the pretreatment plant 42, the cathodic dip-painting installation 48 and the underbody protection installation 70 as well as the workstations 66.
  • the vehicle body 14 After the vehicle body 14 has completed the basic treatment line 80 and left the underbody cooling zone 76, it is conveyed on the way over the high-bay warehouse 32 on the functional wing 24 in the second building wing 28, the vehicle body 14 on the way there in the high-bay warehouse 32nd can be stored.
  • a paint line 82 is accommodated in the second building wing.
  • this coating line 82 comprises a filler application booth 84, a filler drier 86, a basecoat application booth 88, an intermediate dryer 90 for basecoat, a topcoat application booth 92, and a topcoat drier 94 disposed on the vehicle body 14 on the first floor 34.2 are passed.
  • the application booths 84, 88 and 92 are conceptually identical in principle and will be explained only by the example of the basecoat application booth 88, whose schematic section FIG. 3 shows and the in FIG. 6 shown with more details.
  • the basecoat application booth 88 extends from the ground floor 34.1 to the second floor 34.3 and comprises from top to bottom a plenum area 88.1 on the second floor 34.3, an application area 88.2 on the first floor 34.2 and a separation area 88.3 on the ground floor 34.1.
  • FIG. 6 shows only the application area 88.2 and the separation area 84.3.
  • the basecoat application booth 88 is formed in a manner known per se. Conditioned air passes down the plenum area 88.1 and flows through the application area 88.2, in which the base coat is applied to the vehicle body 14.
  • the overspray generated during application is absorbed by the air flowing through it and thus continues down into the separation area 88.3, where the overspray is separated from the cabin air.
  • application robots 96 available, as it is in itself known.
  • a separating device 98 is provided in the separating region 88.3 Filter modules 100 is arranged, in which overspray is deposited.
  • electrostatic working separator may be provided alternatively or additionally.
  • the dryers 86, 90 and 94 are also constructed conceptually identical and each extend in the first and second floors 34.2 and 34.3. In each case, associated operating units are located on the second floor 34.3, with only operating units 106 of the intermediate dryer 90 for basecoat in FIG. 3 can be seen.
  • the dryers 86, 90, and 94 like the CTL dryer 56 or underbody protection dryer 72, include respective cooling zones; however, these are not marked separately.
  • the vehicle body 14 Before the vehicle body 14 is conveyed into the base paint application cabin 88, it can be conveyed by means of the conveyor system 38 into the ground floor 34. 1 of the second building wing 28, in which Figures 2 and 3 there are workstations 108 to be recognized, which may be located, for example, under the intermediary dryer 90 for basecoat and / or the other dryers 86 and 94, respectively.
  • the workstations 108 for example, the vehicle bodies 14 may again be subjected to an audit and / or a grinding process. After that, the vehicle bodies 14 are again conveyed to the first upper floor 34. 2 and into the base paint application cabin 92.
  • the vehicle body 14 After the vehicle body 14 has left the top coat dryer 94, it is conveyed through an inspection line 110 in which a plurality of inspection booths 112 are arranged, in which the quality end of the vehicle body 14 by inspection personnel. If necessary, small paint repairs can be carried out in so-called spot repair cabins. For larger paint defects, the vehicle body 14 can be introduced as a return to the topcoat paint process. Optionally, the vehicle body 14 may also be stored in the high-bay warehouse 32 before the inspection line 110.
  • the vehicle body 14 is conveyed to a final assembly facility, not specifically shown, in which the vehicle is completed.
  • the treatment areas 36 are connected to a distributor medium 114 for operating media, by means of which operating media, which are required or accumulated in the individual treatment areas 36, can be supplied or removed to the individual treatment areas 36.
  • operating media are, for example, general operating media such as hot water, cold water, compressed air and electricity.
  • operating media may also be treatment-specific operating media, which are required for a specific treatment of a vehicle body 14 in a treatment area 36.
  • Treatment-specific operating media may include, for example, the coating materials applied in the individual application booths 84, 88, 92 or special cleaning agents or the like required in different treatment areas 36.
  • the supply of the treatment areas 36 with such treatment-specific operating media takes place via separate treatment distribution systems, which are each assigned to one or optionally a plurality of treatment areas 36.
  • the application booths 84, 88, 92 are each supplied separately with the required coating materials filler, basecoat or topcoat.
  • the functional section 24 comprises at least one installation duct 116 for media ducts 118, which extends at least in a section of the functional wing 24 in the longitudinal direction 18 and in which at least one media duct 118 is accommodated, which is connected to at least one complementary duct 120 in one of the building wings 26 or 28 is.
  • the installation channel 116 extends in the longitudinal direction 18 over the entire length of the functional section 24.
  • the media line 118 can in particular at least two connecting portions, which are spaced in the longitudinal direction 18, with complementary media lines 120 in the first building wing 26 and / or in the second building wing 28 can be connected.
  • first installation channel 116.1 on the ground floor 34.1 for power lines there is a first installation channel 116.1 on the ground floor 34.1 for power lines and a second installation channel 116.2 on the first floor 34.2 for fluid lines.
  • the media lines 118 extend in the longitudinal direction 18 through the installation channels 116, wherein they can also have an angled and / or inclined upward or downward course.
  • An angled course is in FIG. 5 to recognize, for example, is used to compensate for thermal expansion.
  • FIG. 6 illustrates a hot water line 118.1, a cold water line 118.2, a compressed air line 118.3 and a sewer line 118.4 in the first installation channel 116.1, of which FIG. 5 for the sake of clarity, only the hot water line 118.1 and the compressed air line 118.3 shows. Also, in FIG. 5 Two branch lines 118a, specifically a hot water branch line 118.1a of the hot water line 118.1 and a compressed air branch line 118.3a of the compressed air line 118 can be seen leading to an above-mentioned connection area for connecting the complementary media lines 120 in the second building wing 28, which is not here Individual is shown.
  • the branch lines 118a may be passed through vertical, cross-storey installation shafts 122 to other floors 34 so that the other floors 34 can be supplied with the required media.
  • a compressed air branch 118.3a from the second installation channel 116.2 can be led down into the ground floor 34.1 where it can be connected to a complementary compressed air line 120.3 to supply the work stations 66 or 108 with compressed air.
  • Complementary media lines 120 in the form of a complementary hot water line 120.1 and a complementary compressed air line 120.3 are only in FIG. 6 and there very schematically illustrated as dashed lines.
  • the functional wing 24 also includes integrated fresh air flow channels 124, supply air flow channels 126 and recirculation flow channels 128, and exhaust and exhaust air flow channels of an air system generally designated 130.
  • air system 130 For the operation of the air system 130 necessary components and components in individual treatment areas 36 needed or released.
  • flow paths of fresh air 132 are illustrated as dashed lines.
  • Flow paths of supply air 134 are shown as dash-dotted lines and flow paths of circulating air 136 are shown as dotted lines.
  • flow directions are illustrated by arrows.
  • the flow channels 124, 126 and 128 are connected to flow paths in the building wings 26, 28 which lead to respective treatment areas 36 in which supply air is required or exhaust air is generated, which is then forwarded as circulating air.
  • Such flow paths toward or away from the treatment areas 36 are not separately shown or designated and may be, for example be designed in the form of flow lines, flow wells or flow channels.
  • the fresh air 132 first passes to a primary conditioning device 140, in which the fresh air is conditioned in a known manner and in the Figures 3 and 7 can be seen. During conditioning, for example, the temperature and the moisture content of the fresh air 132 are set. Also, the fresh air 132 may be mixed with circulating air 136, wherein the mixing ratio can be adjusted.
  • the primary conditioning device 140 is housed in the penthouse 34.4 in the second building wing 28.
  • the conditioned incoming air 134 is distributed to the individual treatment areas 36 and the local installations or the local operating units 60, 78 and 106 as well as work stations 66 and 108.
  • all plants and workstations are fluidically connected to one of the supply air systems 142, from where the supply air 134 is passed on the way via one of the supply air flow channels 126 of the functional tract 24 to a treatment zone 36 and the local plant.
  • the filler application booth 84, the basecoat application booth 88 and the topcoat application booth 92 are also each fluidic connected to one of the recirculation systems 144, where circulating air 136 conditioned and can be recycled as a conditioned supply air 134 back to the system from which the circulating air 136 comes.
  • the recirculation systems 144 thus form secondary conditioning devices.
  • the flow path of supply air 134 to the workstations 66 and 108 is exemplary in the FIGS. 2 to 4 illustrated.
  • fresh air 132 has been aspirated through the input unit of the build-up unit 138 and conditioned in the primary conditioning device 140, it passes into the work stations 66, 108 associated Zu Kunststoffanlagen 142, from where it is routed through supply air flow channels 126 of the functional tract 24 in the ground floor 34.1 , There, the supply air 134 flows through above-mentioned, not specifically shown flow paths to the respective workstation 66, 108th
  • fresh air 134 reaches the inspection cabins 112 of the inspection line 110 on the first floor 34.2 via separately assigned supply air installations 142; this shows FIG. 3 , There it can also be seen that in the inspection cabins 112 resulting exhaust air as circulating air 136 to a circulating air flow channel 128 in the functional wing 24, in which the circulating air 136 from the first floor 34.2 upwards in the penthouse 34.4, where the circulating air 136 back in the primary conditioning device 140 is fed.
  • the cleaned exhaust air from the application booths 84, 88 or 92 passes through the respective collection channel, which accordingly forms a recirculating air flow channel 128 in functional tract 24, back up into the penthouse 34.4.
  • the circulating air from the application booths 84, 88 or 92 is supplied to the respective circulating air system 144, where a separate conditioning takes place.
  • the installation channels 116 of the functional tract 24 are oriented horizontally.
  • the functional tract 24 also oriented vertically Includes modules, functional modules for technical facilities on the one hand and design modules for infrastructure and structural engineering on the other hand are present, extending over floors 34 of the functional wing 24 away.
  • the functional modules and the design modules may extend on the ground floor 34.1 and from there to the penthouse 34.4 or run between less than the total number of floors 34.
  • One or more design modules 152 are provided for one or more staircases 154, one or more further design modules 156 for one or more elevator systems 158.
  • One or more supplemental design modules 160 are used to compensate for expansion variations of the building body 16.
  • each floor 34 the functional modules 146 to 150 and the construction modules 152 to 160 are flanked by a walk-through passage 162 which, in the exemplary embodiment described here, lies on the side of the functional wing 24, which facing the first building wing 26.
  • the installation channels 116.1 and 116.2 are housed in the upper part of the respective aisles 162. Via the passages 162, the areas of the paint shop 12 in the longitudinal direction 18 can be achieved.
  • the aisles 162 can be used for the inspection of the paint shop 12 without visitors having to enter the building wings 26, 28 with the treatment areas 36. Such visitor aisles are to the building wings 26, 28 equipped with appropriate windows.
  • penthouse 34.4 in the first building wing accommodates 26 social rooms 164.
  • Such social rooms 164 include, for example, changing rooms, sanitary facilities, a canteen, offices, and the like.
  • the paint shop 12 and the functional wing 24 are designed such that the building wings 26 and 28 can be achieved in principle for workers only on the way through the functional wing 24 and in the functional wing 24 only on the way through the social spaces 164. Exceptions to this may be additional escape routes or separate access for emergency services.
  • a person Via an entrance, a person therefore first reaches the elevator installation 158, which leads directly to the penthouse 34.4 and the social rooms 164 there. In particular, offices and an optionally existing canteen can be reached directly. From there, a person can then access the staircases 154 or possibly another elevator system in the individual projectiles 34.1 to 34.3.
  • Access doors 166 in the penthouse 34.4 and on the second floor 34.3 can be seen, via which the building wing 26 is accessible in the respective floors 34.4 and 34.3.
  • Corresponding connecting doors are also present in the other floors 34.1 and 34. 2 and also towards the second building wing 28 out. The latter are particularly present in the expansion compensation design module 160, which flanks from functional modules to the second building wing 28 adjacent to it.
  • the floors 34 of the paint shop 12 are thus accessible via the functional tract 24 and connected to each other. In normal operation of the paint shop 12, only these accessibilities and connections are used. There may be additional connection paths between the floors 34, which can be used in hazardous situations or in other special cases.
  • the functional tract 24 can in particular be made of reinforced concrete.
  • the functional tract 24 contributes significantly to the stability of the building body 16.
  • the building wings 26 and 28 can either be made in concrete construction or designed as a steel structure. A load capacity of the building wings 26, 28 between 5 to 10 KN m -2 may be sufficient to carry the system components can.
  • the functional tract 24 also separates the building wings 26, 28 from one another as separate fire sections.
  • the functional wing 24 forms a protected area with respect to the building wings 26, 28 and can be reached in case of danger from both building wings 26, 28 with short distances.
  • Function modules 146, 148, 150 and design modules 152, 156, 160, 161 may be unitary and include both media and ventilation technical facilities and infrastructures such as stairways 154, elevator installations 158, or service and sightseeing routes 162. These functional modules 146, 148, 150 and design modules 152, 156, 160, 161 are in practice load-bearing elements for building statics.

Abstract

Eine Lackieranlage zum Lackieren von Gegenständen, insbesondere von Fahrzeugkarosserien (14), umfasst einen Gebäudebaukörper (16), in dem mehrere Behandlungsbereiche (36) untergebracht sind, in denen unterschiedlichen Lackierschritte durchführbar sind, und der eine Längsrichtung (18) definiert. Es gibt ein Verteilersystem (114) mit Medienleitungen (118) für Betriebsmedien, durch welche Betriebsmedien, die in den einzelnen Behandlungsbereichen (36) benötigt werden oder dort anfallen, den einzelnen Behandlungsbereichen (36) zuführbar oder von den Behandlungsbereichen (36) abführbar sind. Der Gebäudebaukörper (16) umfasst einen Funktionstrakt (24), der in Längsrichtung (18) von wenigstens einem Gebäudeflügel (26, 28) flankiert ist, in dem einer oder mehrere der Behandlungsbereiche (36) untergebracht sind. Der Funktionstrakt (24) umfasst wenigstens einen Installationskanal (116) für Medienleitungen (118), welcher sich zumindest in einem Abschnitt des Funktionstraktes (24) in Längsrichtung (18) erstreckt, wobei in dem Abschnitt wenigstens eine der Medienleitungen (118) in Längsrichtung (18) verläuft, die mit wenigstens einer komplementären Medienleitung (120) in dem Gebäudeflügel (26, 28) verbindbar ist, die zu einem der Behandlungsbereiche (36) führt.

Figure imgaf001
A painting installation for painting objects, in particular vehicle bodies (14), comprises a building construction body (16) in which a plurality of treatment areas (36) are accommodated, in which different painting steps can be carried out, and which defines a longitudinal direction (18). There is a distribution system (114) with media lines (118) for operating media through which operating media needed or accumulated in the individual treatment areas (36) are deliverable to or dissipated from the treatment areas (36) to the individual treatment areas (36). The building structure (16) comprises a functional wing (24) which is flanked in the longitudinal direction (18) by at least one building wing (26, 28) in which one or more of the treatment areas (36) are accommodated. The functional tract (24) comprises at least one installation duct (116) for media ducts (118), which extends in the longitudinal direction (18) at least in a section of the functional wing (24), wherein in the section at least one of the medium ducts (118) is longitudinally ( 18) which is connectable to at least one complementary media conduit (120) in the building wing (26, 28) leading to one of the treatment areas (36).
Figure imgaf001

Description

Die Erfindung betrifft eine Lackieranlage zum Lackieren von Gegenständen, insbesondere von Fahrzeugkarosserien, mit

  1. a) einem Gebäudebaukörper, in dem mehrere Behandlungsbereiche untergebracht sind, in denen unterschiedlichen Lackierschritte durchführbar sind, und der eine Längsrichtung definiert;
  2. b) einem Verteilersystem mit Medienleitungen für Betriebsmedien, durch welche Betriebsmedien, die in den einzelnen Behandlungsbereichen benötigt werden oder dort anfallen, den einzelnen Behandlungsbereichen zuführbar oder von den Behandlungsbereichen (36) abführbar sind.
The invention relates to a paint shop for painting objects, in particular vehicle bodies, with
  1. a) a building structure, in which a plurality of treatment areas are housed, in which different painting steps are feasible, and which defines a longitudinal direction;
  2. b) a distribution system with media lines for operating media, through which operating media, which are required in the individual treatment areas or incurred there, the individual treatment areas supplied or discharged from the treatment areas (36).

Solche Lackieranlagen sind am Markt bekannt, wobei die Gebäudebaukörper den Anforderungen einer Lackieranlage nicht oder nur wenig Rechnung tragen. Dies kann das Fall sein, wenn bereits vorhandene Gebäudebaukörper genutzt werden.Such paint systems are known in the market, with the building structures do not or only slightly take into account the requirements of a paint shop. This may be the case if existing building structures are used.

Eine der wichtigen Anforderungen einer Lackieranlage sind die Zuführung und Abführung von Betriebsmedien, die zum Betrieb der Lackieranlage erforderlich sind. Hierzu zählen insbesondere allgemeine Betriebsmedien wie Heißwasser, Kaltwasser, Druckluft und Strom, die in fast allen Behandlungsbereichen zur Verfügung stehen müssen. Um dies zu erreichen, wird in der Praxis ein umfangreiches Leitungsnetz verlegt und auch vorab geplant, wobei der Gebäudebaukörper jeweils individuelle konzipiert wird. Der Planungs- und Installationsaufwand wird dadurch verhältnismäßig hoch.One of the important requirements of a paint shop is the supply and discharge of operating media, which are required for operation of the paint shop. These include in particular general operating media such as hot water, cold water, compressed air and electricity, which must be available in almost all treatment areas. In order to achieve this, an extensive pipeline network is laid in practice and planned in advance, whereby the building structure is designed individually. The planning and installation effort is relatively high.

Es ist Aufgabe der Erfindung, ein Konzept einer Lackieranlage bereitzustellen, welche die Planung und die Installation der Lackieranlage demgegenüber vereinfacht.It is an object of the invention to provide a concept of a paint shop, which simplifies the planning and installation of the paint shop on the other hand.

Diese Aufgabe wird bei einer Lackieranlage der eingangs genannten Art dadurch gelöst, dass

  • c) der Gebäudebaukörper einen Funktionstrakt umfasst, der in Längsrichtung von wenigstens einem Gebäudeflügel flankiert ist, in dem einer oder mehrere der Behandlungsbereiche untergebracht sind;
  • d) der Funktionstrakt wenigstens einen Installationskanal für Medienleitungen umfasst, welcher sich zumindest in einem Abschnitt des Funktionstraktes in Längsrichtung erstreckt, wobei in dem Abschnitt wenigstens eine der Medienleitungen in Längsrichtung verläuft, die mit wenigstens einer komplementären Medienleitung in dem Gebäudeflügel verbindbar ist, die zu einem der Behandlungsbereiche führt.
This object is achieved in a paint shop of the type mentioned in that
  • c) the building structure comprises a functional tract which is flanked longitudinally by at least one building wing in which one or more of the treatment areas are accommodated;
  • d) the functional tract comprises at least one installation duct for media ducts, which extends in the longitudinal direction at least in a section of the functional wing, wherein in the section at least one of the media ducts extends in the longitudinal direction, which is connectable to at least one complementary media duct in the building wing which leads to a the treatment areas leads.

Erfindungsgemäß wird ein Gebäudekonzept bereitgestellt, bei dem es möglich ist, die Betriebsmedien in einem speziell dafür ausgelegten Gebäudeteil, nämlich dem Funktionstrakt, geführt und von oder aus diesem an verschiedenen Stellen entnommen werden können.According to the invention, a building concept is provided in which it is possible for the operating media to be guided in a specially designed building part, namely the functional wing, and to be removed from or from this at various points.

Insbesondere, wenn sich der Installationskanal in Längsrichtung weitgehend über die gesamte Länge des Funktionstraktes erstreckt, sind für die Medienführung in Längsrichtung keine oder nur wenig Leitungen in dem Gebäudeflügel notwendig.In particular, when the installation channel extends in the longitudinal direction largely over the entire length of the functional tract, no or only little lines in the building wing are required for the media guide in the longitudinal direction.

Es ist effektiv, wenn die Medienleitung in wenigstens zwei Verbindungsbereichen, die in Längsrichtung beabstandet ist, mit komplementären Medienleitungen in dem Gebäudeflügel verbindbar ist. Auf diese Weise kann ein Betriebsmedium mit einer einzigen Leitung über die Länge der Lackieranlage verteilt und gefördert werden.It is effective if the media conduit is connectable to complementary media conduits in the building wing in at least two connection regions spaced longitudinally. In this way, a service medium with a single line can be distributed and conveyed over the length of the paint shop.

Es ist günstig, wenn der Funktionstrakt Funktionsmodule für technische Einrichtungen und Konstruktionsmodule für Infrastruktur und Baustatik umfasst. Auf diese Weise ist ein modulartiger Aufbau des Funktionstraktes möglich, der die Anforderungen an den Lackierbetrieb einerseits und die Anforderungen an das Gebäude aus bautechnischer Sicht andererseits vereint.It is favorable if the functional tract comprises functional modules for technical facilities and construction modules for infrastructure and structural engineering. To this Way is a modular structure of the functional tract possible, which combines the requirements of the Lackierbetrieb on the one hand and the requirements of the building from a structural point of view on the other.

Vorzugsweise sind die Funktionsmodule und/oder die Konstruktionsmodule vertikal orientiert. Auf diese Weise sind geschossübergreifende Baukonzepte möglich.Preferably, the functional modules and / or the design modules are oriented vertically. In this way, cross-floor building concepts are possible.

Vorteilhaft umfasst der Funktionstrakt ein oder mehrere Funktionsmodule mit einem oder mehreren Strömungskanälen eines Luftsystems und/oder ein oder mehrere Funktionsmodule, in denen Komponenten zur Energieversorgung der Lackieranlage untergebracht sind, und/oder ein oder mehrere Funktionsmodule mit ein oder mehreren Installationsschächten für Medienleitungen umfasst.Advantageously, the functional tract comprises one or more functional modules with one or more flow channels of an air system and / or one or more functional modules in which components for powering the paint shop are accommodated, and / or one or more functional modules with one or more installation shafts for media lines.

Außerdem ist es günstig, wenn der Funktionstrakt ein oder mehrere Konstruktionsmodule für ein oder mehrere Treppenhäuser und/oder ein oder mehrere Konstruktionsmodule für eine oder mehrere Aufzuganlagen und/oder ein oder mehrere Konstruktionsmodule zur Einrichtung von Erholungs- und/oder Kommunikationszonen und/oder ein oder mehrere Konstruktionsmodule zur Kompensation von Ausdehnungsschwankungen des Gebäudekörpers umfasst.It is also advantageous if the functional wing one or more construction modules for one or more staircases and / or one or more construction modules for one or more elevator systems and / or one or more design modules for the establishment of recreational and / or communication zones and / or one or several design modules to compensate for expansion variations of the building body includes.

Wenn der Gebäudeflügel mehrere Etagen aufweist, ist es besonders günstig, wenn die Etagen über den Funktionstrakt erreichbar und miteinander verbunden sind.If the building wing has several floors, it is particularly advantageous if the floors are accessible via the functional wing and connected to each other.

Nachfolgend wird ein Ausführungsbeispiel der Erfindung anhand der Zeichnungen näher erläutert. In diesen zeigen:

Figur 1
eine perspektivische Ansicht eines Gebäudebaukörpers eines Anlagenkomplexes einer Lackieranlage, bei dem der Gebäudebaukörper einen zentralen Funktionstrakt und zwei daran angrenzende Behandlungstrakte umfasst;
Figur 2
eine der Figur 1 entsprechende Ansicht des Gebäudebaukörpers in teilweiser Durchsicht und mit teilweise weggebrochenen Wänden;
Figur 3
einen Vertikalschnitt des Gebäudebaukörpers entlang der Schnittebene III in Figur 2 bzw. entlang der Schnittlinie III-III in Figur 4;
Figur 4
einen ersten Horizontalschnitt des Gebäudebaukörpers entlang der Schnittlinie IV-IV in Figur 3;
Figur 5
einen Abschnitt des Horizontalschnittes von Figur 4 in größerem Maßstab;
Figur 6
den in Figur 3 strichpunktiert eingefassten Ausschnitt VI;
Figur 7
einen zweiten Horizontalschnitt des Gebäudebaukörpers entlang der Schnittlinie V-V in Figur 3.
An embodiment of the invention will be explained in more detail with reference to the drawings. In these show:
FIG. 1
a perspective view of a building structure of a plant complex of a paint shop, in which the building structure comprises a central functional tract and two adjoining treatment tracts;
FIG. 2
one of the FIG. 1 corresponding view of the building structure in partial view and with partially broken walls;
FIG. 3
a vertical section of the building structure along the sectional plane III in FIG. 2 or along the section line III-III in FIG. 4 ;
FIG. 4
a first horizontal section of the building structure along the section line IV-IV in FIG. 3 ;
FIG. 5
a section of the horizontal section of FIG. 4 on a larger scale;
FIG. 6
the in FIG. 3 dash-dot framed section VI;
FIG. 7
a second horizontal section of the building structure along the section line VV in FIG. 3 ,

Die Figuren 1 bis 3 zeigen einen Anlagenkomplex 10 einer Lackieranlage 12, in welcher Gegenstände lackiert werden; bei dem erläuterten Ausführungsbeispiel handelt es sich um eine Lackieranlage 12, in welcher Fahrzeugkarosserien 14 lackiert werden, wobei lediglich in Figur 6 eine Fahrzeugkarosserie 14 gezeigt ist.The FIGS. 1 to 3 show a plant complex 10 of a paint shop 12, in which objects are painted; in the illustrated embodiment, it is a paint shop 12, in which vehicle bodies 14 are painted, with only in FIG. 6 a vehicle body 14 is shown.

Der Anlagenkomplex 10 weist einen Gebäudebaukörper 16 auf, in und an dem die Anlagenkomponenten des Anlagenkomplexes 10 untergebracht sind. Der Gebäudebaukörper 16 definiert eine nur in den Figuren 1 und 2 mit einem Pfeil bezeichnete Längsrichtung 18 sowie zwei in Längsrichtung 18 gegenüberliegende Stirnseiten 20 und 22 und umfasst einen mittleren Funktionstrakt 24, der in Längsrichtung 18 von einem ersten Gebäudeflügel 26 und einem zweiten Gebäudeflügel 28 flankiert ist. Bei dem hier beschriebenen Ausführungsbeispiel grenzen die Gebäudeflügel 26 und 28 unmittelbar an den Funktionstrakt 24 an. Der Gebäudebaukörper 16 ist insgesamt von einer Gebäudehülle 30 umschlossen.The plant complex 10 has a building structure 16 in and on which the plant components of the plant complex 10 are accommodated. The building structure 16 defines one only in the FIGS. 1 and 2 longitudinal direction 18 denoted by an arrow and two end faces 20 and 22 opposite in the longitudinal direction 18 and comprises a central functional tract 24 which is flanked in the longitudinal direction 18 by a first building wing 26 and a second building wing 28. In the exemplary embodiment described here, the building wings 26 and 28 adjoin the functional wing 24 directly. The building structure 16 is enclosed in total by a building envelope 30.

An der ersten Stirnseite 20 grenzt ein Zwischenlager an den Gebäudekörper 16 an, das beim vorliegenden Ausführungsbeispiel als Hochregallager 32 ausgebildet ist und in den Figuren 1 und 2 schematisch durch gestrichelte Linien angedeutet und in Durchsicht gezeigt ist. Alternativ kann als Zwischenlager auch ein Flächenlager vorgesehen sein.At the first end face 20 adjacent to an intermediate storage to the building body 16, which is formed in the present embodiment as a high-bay warehouse 32 and in the FIGS. 1 and 2 schematically indicated by dashed lines and shown in phantom. Alternatively it can be provided as an intermediate storage and a surface storage.

Der Gebäudebauköper 16 hat mehrere Geschosse bzw. Etagen 34, wobei beim vorliegenden Ausführungsbeispiel von unten nach oben betrachtet vier Etagen 34.1, 34.2, 34.3 und 34.4 vorhanden sind. Im Weiteren werden die Etage 34.1 auch als Erdgeschoss, die Etagen 34.2 und 34.3 auch als erstes bzw. zweites Obergeschoss und die Etage 34.4 auch als Penthouse bezeichnet, wobei die Bezugszeichen beibehalten werden. Das Penthouse bezeichnet stets die oberste Etage; es können zwischen Erdgeschoss 34.1 und Penthouse aber auch nur ein einziges Obergeschoss oder auch mehr als zwei Obergeschosse vorhanden sein. Die Etagen 34 des Gebäudebaukörpers 16 können, müssen aber nicht durch Decken bzw. Zwischenböden voneinander getrennt sein. Komponenten und Bauteile, die in den Obergeschossen 34.2, 34.3 oder dem Penthouse 34.4 angeordnet sind, können auch durch Stahlbauten getragen sein, die auf dem Boden des Erdgeschosses 34.1 verankert sind. Der Boden des Erdgeschosses 34.1 definiert eine 0 m-Ebene, die Böden der beiden Obergeschosse 34.2, 34.3 und des Penthouses 34.4 liegen bezogen auf diese 0 m-Ebene auf +5 m, +10,5 m bzw. +16 m.The Gebäudebauköper 16 has a plurality of floors or floors 34, wherein viewed in the present embodiment from bottom to top four floors 34.1, 34.2, 34.3 and 34.4 are available. In addition, the floor 34.1 also referred to as the ground floor, the floors 34.2 and 34.3 as the first and second floors and the floor 34.4 also referred to as a penthouse, wherein the reference numerals are retained. The penthouse always refers to the top floor; There may be between ground floor 34.1 and penthouse but also only a single upper floor or more than two upper floors. The floors 34 of the building structure 16 may, but need not be separated from each other by ceilings or shelves. Components and components located on the upper floors 34.2, 34.3 or the penthouse 34.4 may also be supported by steel structures anchored to the floor of the ground floor 34.1. The floor of the ground floor 34.1 defines a 0 m level, the floors of the two upper floors 34.2, 34.3 and the Penthouses 34.4 lie on this 0 m level at +5 m, +10.5 m and +16 m respectively.

In den Gebäudeflügeln 26 und 28 sind verschiedene Behandlungsbereiche 36 untergebracht, in denen unterschiedliche Lackierschritte durchgeführt werden. Bei der hier beschriebenen Lackieranlage 12 sind solche Behandlungsbereiche 36 im Erdgeschoss 34.1 und im ersten Obergeschoss 34.2 angeordnet, wogegen im zweiten Obergeschoss 34.3 und im Penthouse 34.4 technische Systemkomponenten und andere Einrichtungen untergebracht sind. Auf einzelne Etagen 34 wird weiter unten eingegangen. In dem Funktionstrakt 24 sind keine Behandlungsbereiche 36 untergebracht. Bei einer Abwandlung kann dies jedoch der Fall sein, wenn auch der Funktionstrakt im Grundsatz lediglich zur Aufnahme von technischen Einrichtungen wie beispielsweise Medienleitungen und Umluft- oder Abluftventilatoren dient.In the building wings 26 and 28 different treatment areas 36 are housed, in which different painting steps are performed. In the case of the painting installation 12 described here, such treatment areas 36 are arranged on the ground floor 34.1 and on the first floor 34.2, whereas in the second floor 34.3 and in the penthouse 34.4 technical system components and other facilities are accommodated. On individual floors 34 will be discussed below. In the functional tract 24, there are no treatment areas 36 accommodated. In a modification, however, this may be the case, although the functional section in principle only serves to accommodate technical equipment such as media lines and recirculation or exhaust fans.

Die zu behandelnden Fahrzeugkarosserien 14 werden mit Hilfe eines Fördersystems 38 entlang eines Förderweges 40 durch die Behandlungsbereiche 36 gefördert, was nun anhand der Figur 4 in Verbindung mit den Figuren 2 und 3 erläutert wird. Der Förderweg 40 der Fahrzeugkarosserien 14 durch die einzelnen Behandlungsbereiche 36 kann variieren und hängt von den zu absolvierenden Behandlungsbereichen 36 und von dem Lackierplan ab, d.h. welche Abfolge von Fahrzeugkarosserien 14 lackiert werden soll. Dabei können Abläufe auch geändert werden.The vehicle bodies 14 to be treated are conveyed by means of a conveyor system 38 along a conveying path 40 through the treatment areas 36, which will now be described with reference to FIG FIG. 4 in conjunction with the Figures 2 and 3 is explained. The conveying path 40 of the vehicle bodies 14 through the individual treatment areas 36 can vary and depends on the treatment areas 36 to be completed and on the painting plan, ie which sequence of vehicle bodies 14 is to be painted. Processes can also be changed.

Bevor eine Fahrzeugkarosserie 14 lackiert wird, gelangt sie aus einer der Lackieranlage 12 vorgelagerten Rohbauanlage in das Hochregallager 32. Dort wird die Fahrzeugkarosserie 14 gegebenenfalls zwischengelagert.Before a vehicle body 14 is painted, it passes from a paint shop 12 upstream Rohbauanlage in the high-bay warehouse 32. There, the vehicle body 14 is optionally stored.

Die Fahrzeugkarosserie 14 wird aus dem Hochregallager 32 heraus in die Lackieranlage 12 gefördert und zunächst in das zweite Obergeschoss 34.2 in eine Vorbehandlungs-Tauchanlage 42 gefördert, die im Erdgeschoss 34.1 sowie im ersten und im zweiten Obergeschoss 34.2 und 34.3 angesiedelt ist. Die Vorbehandlungs-Tauchanlage 42 umfasst ein Vorbehandlungs-Tauchbecken 44 im ersten Obergeschoss 34.2, in welches die Fahrzeugkarosserie 14 aus dem zweiten Obergeschoss 34.3 abgesenkt wird. Im Erdgeschoss 34.1 befinden sich Dosierstationen für Betriebschemikalien und Gegenbehälter 46, die in Figur 2 zu erkennen sind.The vehicle body 14 is conveyed out of the high-bay warehouse 32 into the paint shop 12 and initially conveyed to the second upper floor 34.2 in a pre-treatment dipping installation 42, which is located on the ground floor 34.1 and in the first and second floors 34.2 and 34.3. The pre-treatment dip system 42 includes a pretreatment dip tank 44 in the first floor 34.2, in which the vehicle body 14 is lowered from the second floor 34.3. On the ground floor 34.1 are metering stations for chemical agents and counter container 46, which in FIG. 2 can be seen.

Nach dem Vorbehandlungs-Tauchgang wird die Fahrzeugkarosserie 14 aus dem Vorbehandlungs-Tauchbecken 44 herausgehoben und befindet sich wieder im zweiten Obergeschoss 34.3.After the pretreatment dive, the vehicle body 14 is lifted out of the pretreatment dip tank 44 and is again on the second floor 34.3.

Hiernach gelangt die Fahrzeugkarosserie 14 in eine KTL-Anlage 48, wobei KTL die Abkürzung für "kataphoretische Tauchlackierung" ist. Auch die KTL-Anlage 48 erstreckt sich über das Erdgeschoss 34.1 sowie das erste und zweite Obergeschoss 34.2 und 34.3. Die KTL-Anlage 48 umfasst ein KTL-Tauchbecken 50 im ersten Obergeschoss 34.2; auch hier wird die Fahrzeugkarosserie 14 aus dem zweiten Obergeschoss 34.3 in das KTL-Tauchbecken 50 abgesenkt. Im Erdgeschoss 34.1 befinden sich unter dem KTL-Tauchbecken 50 zugehörige Dosierstationen für KTL-Lack, Betriebschemikalien und KTL-Gegenbehälter 52.After that, the vehicle body 14 enters a KTL installation 48, KTL being the abbreviation for "cataphoretic dip painting". Also, the KTL system 48 extends over the ground floor 34.1 and the first and second floors 34.2 and 34.3. The KTL system 48 includes a KTL dip tank 50 on the first floor 34.2; Again, the vehicle body 14 is lowered from the second floor 34.3 in the KTL dip tank 50. On the ground floor 34.1 are located below the KTL dip tank 50 associated dosing for KTL paint, chemicals and KTL counter container 52nd

Der Förderweg 40 des Fördersystems 38 umfasst Rückführabschnitte 54 für die Fördertechnik, auf deren Weg diese an den Tauchbecken 44 bzw. 54 zurück zu deren Eintauchbereich bewegt werden können.The conveying path 40 of the conveyor system 38 comprises return sections 54 for the conveyor technology, on the way of which they can be moved back to the dip tanks 44 and 54 to their immersion area.

Die KTL-Anlage 48 umfasst außerdem einen KTL-Trockner 56, der sich im ersten Obergeschoss 34.2 befindet und in welchen die Fahrzeugkarosserie 14 nach der kataphoretischen Tauchlackierung aus dem zweiten Obergeschoss 34.3 über einen etagenübergreifenden Übergangsabschnitt 58 des Förderweges 40 des Fördersystems 38 gelangt. In dem Übergangsabschnitt 58 kann hierfür beispielsweise ein Vertikalförderer angeordnet sein. Zu dem KTL-Trockner 56 gehörten Betriebsaggregate 60, die wiederum im zweiten Obergeschoss 34.3 untergebracht sind; siehe Figuren 2 und 3.The KTL system 48 also includes a KTL dryer 56, which is located on the first floor 34.2 and in which the vehicle body 14 passes after the cataphoretic dip painting from the second floor 34.3 via a multi-floor transition section 58 of the conveying path 40 of the conveyor system 38. In the transition section 58, for example, a vertical conveyor can be arranged for this purpose. To the KTL dryer 56 included operating units 60, which in turn are housed in the second floor 34.3; please refer Figures 2 and 3 ,

Am Ende des KTL-Trockners 56 befindet sich eine KTL-Kühlzone 62, auf welche ein Vertikalförderer 64 folgt, mit dem die Fahrzeugkarosserie 14 nach unten in das Erdgeschoss 34.1 gefördert wird, wenn die Fahrzeugkarosserie 14 unmittelbar im Anschluss an die kataphoretische Tauchlackierung weiterbehandelt werden soll. Alternativ kann die Fahrzeugkarosserie 14 auch zunächst wieder in das Hochregallager 32 gefördert werden.At the end of the KTL dryer 56 is a KTL cooling zone 62, which is followed by a vertical conveyor 64, with which the vehicle body 14 is conveyed down into the ground floor 34.1, if the vehicle body 14 is to be treated immediately following the cataphoretic dip painting , Alternatively, the vehicle body 14 can also initially be conveyed back into the high-bay warehouse 32.

Im Erdgeschoss 34.1 gelangt die Fahrzeugkarosserie 14 zunächst zu in Figur 3 zu erkennenden Arbeitsstationen 66, die sich unter der KTL-Anlage 48 befinden und in denen die Fahrzeugkarosserie 14 beispielsweise einem Audit und/oder einem Schleifprozess unterworfen werden kann.On the ground floor 34.1, the vehicle body 14 initially comes in FIG. 3 to be recognized workstations 66, which are located below the KTL system 48 and in which the vehicle body 14 may be subjected to, for example, an audit and / or a grinding process.

Hiernach wird die Fahrzeugkarosserie 14 zu einer ebenfalls in Figur 3 zu erkennenden Unterbodenschutz-Kabine 68 einer Unterbodenschutz-Anlage 70 gefördert. Die Unterbodenschutz-Kabine 68 erstreckt sich in Längsrichtung 18 unterhalb eines Unterbodenschutz-Trockners 72 der Unterbodenschutz-Anlage 70 im ersten Obergeschoss 34.2, der parallel zum KTL-Trockner 56 verläuft. Die Unterbodenschutz-Anlage 70 im ersten Obergeschoss 34.2 verläuft somit insgesamt parallel zum KTL-Trockner 56. In der Unterbodenschutz-Kabine 68 erfolgt sowohl die Applikation des Unterbodenschutzes als auch das Nahtabdichten. Der Ausgang der Unterbodenschutz-Kabine 68 ist fördertechnisch über einen weiteren Vertikalförderer 74 mit dem Eingang des Unterbodenschutz-Trockners 72 verknüpft, an dessen Ende sich eine Unterbodenschutz-Kühlzone 76 befindet. Im zweiten Obergeschoss 34.3 sind Betriebsaggregate 78 des Unterbodenschutz-Trockners 72 angeordnet, die wieder in den Figuren 2 und 3 gezeigt sind.After that, the vehicle body 14 becomes a likewise in FIG. 3 to be recognized underbody protection cabin 68 a underbody protection system 70 promoted. The underbody protection cabin 68 extends in the longitudinal direction 18 below a underbody protection dryer 72 of the underbody protection system 70 in the first floor 34.2, which runs parallel to the KTL dryer 56. The underbody protection system 70 in the first floor 34.2 thus runs overall parallel to the KTL dryer 56. In the underbody protection cabin 68, both the application of the underbody protection and the seam sealing takes place. The output of the underbody protection cabin 68 is conveyor technically linked via a further vertical conveyor 74 to the entrance of the underbody protection dryer 72, at the end of which a underbody protection cooling zone 76 is located. On the second floor 34.3 operating units 78 of the underbody protection dryer 72 are arranged, which again in the Figures 2 and 3 are shown.

In dem ersten Gebäudeflügel 26 ist allgemein ausgedrückt eine Grundbehandlungslinie 80 für Fahrzeugkarosserien 14 untergebracht. Diese umfasst beim hier konkret erläuterten Ausführungsbeispiel die Vorbehandlungsanlage 42, die KTL-Anlage 48 und die Unterbodenschutzanlage 70 sowie die Arbeitsstationen 66.In the first building wing 26 is generally a basic treatment line 80 for vehicle bodies 14 housed. In the exemplary embodiment explained here, this includes the pretreatment plant 42, the cathodic dip-painting installation 48 and the underbody protection installation 70 as well as the workstations 66.

Nachdem die Fahrzeugkarosserie 14 die Grundbehandlungslinie 80 absolviert und die Unterbodenschutz-Kühlzone 76 verlassen hat, wird sie auf dem Weg über das Hochregallager 32 an dem Funktionstrakt 24 vorbei in den zweiten Gebäudeflügel 28 gefördert, wobei die Fahrzeugkarosserie 14 auf dem Weg dorthin in dem Hochregallager 32 zwischengelagert werden kann.After the vehicle body 14 has completed the basic treatment line 80 and left the underbody cooling zone 76, it is conveyed on the way over the high-bay warehouse 32 on the functional wing 24 in the second building wing 28, the vehicle body 14 on the way there in the high-bay warehouse 32nd can be stored.

In dem zweiten Gebäudeflügel ist allgemein ausgedrückt eine Lackierlinie 82 untergebracht. Diese Lackierlinie 82 umfasst beim hier konkret beschriebenen Ausführungsbeispiel eine Füller-Applikationskabine 84, einen Füller-Trockner 86, eine Basislack-Applikationskabine 88, einen Zwischentrockner 90 für Basislack, eine Decklack-Applikationskabine 92 sowie einen Decklack-Trockner 94, die von der Fahrzeugkarosserie 14 im ersten Obergeschoss 34.2 durchfahren werden.In general, a paint line 82 is accommodated in the second building wing. In the exemplary embodiment described here, this coating line 82 comprises a filler application booth 84, a filler drier 86, a basecoat application booth 88, an intermediate dryer 90 for basecoat, a topcoat application booth 92, and a topcoat drier 94 disposed on the vehicle body 14 on the first floor 34.2 are passed.

Die Applikationskabinen 84, 88 und 92 sind im Grundsatz identisch konzeptioniert und werden lediglich am Beispiel der Basislack-Applikationskabine 88 erläutert, deren schematischen Schnitt Figur 3 zeigt und die in Figur 6 mit mehr Details gezeigt ist.The application booths 84, 88 and 92 are conceptually identical in principle and will be explained only by the example of the basecoat application booth 88, whose schematic section FIG. 3 shows and the in FIG. 6 shown with more details.

Die Basislack-Applikationskabine 88 erstreckt sich vom Erdgeschoss 34.1 bis in das zweite Obergeschoss 34.3 und umfasst von oben nach unten einen Plenumbereich 88.1 im zweiten Obergeschoss 34.3, einen Applikationsbereich 88.2 im ersten Obergeschoss 34.2 und einen Abscheidebereich 88.3 im Erdgeschoss 34.1. Figur 6 zeigt nur den Applikationsbereich 88.2 und den Abscheidebereich 84.3.The basecoat application booth 88 extends from the ground floor 34.1 to the second floor 34.3 and comprises from top to bottom a plenum area 88.1 on the second floor 34.3, an application area 88.2 on the first floor 34.2 and a separation area 88.3 on the ground floor 34.1. FIG. 6 shows only the application area 88.2 and the separation area 84.3.

Die Basislack-Applikationskabine 88 ist in an und für sich bekannter Art und Weise ausgebildet. Konditionierte Luft gelangt über den Plenumbereich 88.1 nach unten und durchströmt den Applikationsbereich 88.2, in dem der Basislack auf die Fahrzeugkarosserie 14 appliziert wird.The basecoat application booth 88 is formed in a manner known per se. Conditioned air passes down the plenum area 88.1 and flows through the application area 88.2, in which the base coat is applied to the vehicle body 14.

Der bei der Applikation entstehende Overspray wird von der durchströmenden Luft aufgenommen und gelangt so weiter nach unten in den Abscheidebereich 88.3, wo der Overspray von der Kabinenluft getrennt wird. Wie in Figur 6 zu erkennen ist, sind in dem Applikationsbereich 88.2 Applikationsvorrichtungen in Form von mehrachsigen, insbesondere sechs- und/oder siebenachsigen, Applikationsrobotern 96 vorhanden, wie es an und für sich bekannt ist. Außerdem veranschaulicht Figur 6, dass in dem Abscheidebereich 88.3 eine Abscheidevorrichtung 98 mit Filtermodulen 100 angeordnet ist, in denen Overspray abgeschieden wird. Auch elektrostatisch arbeitenden Abscheider können alternativ oder ergänzend vorgesehen sein. Die von Overspray befreite Kabinenluft gelangt nach Durchströmen der Abscheidevorrichtung 98 in einen Sammelkanal 102 mit einem Fördergebläse 104 und kann dann in einem Kreislauf aufbereitet und neu konditioniert wieder dem Plenumbereich 88.1 zugeführt werden bzw. anteilmäßig als Fortluft über einen Abluftventilator abgeführt werden.The overspray generated during application is absorbed by the air flowing through it and thus continues down into the separation area 88.3, where the overspray is separated from the cabin air. As in FIG. 6 can be seen, in the application area 88.2 application devices in the form of multi-axis, in particular six- and / or seven-axis, application robots 96 available, as it is in itself known. Also illustrated FIG. 6 in that a separating device 98 is provided in the separating region 88.3 Filter modules 100 is arranged, in which overspray is deposited. Also electrostatic working separator may be provided alternatively or additionally. The cabin air freed from overspray, after flowing through the separating device 98, passes into a collecting duct 102 with a conveying fan 104 and can then be recirculated and conditioned again, fed back to the plenum area 88.1 or proportionately discharged as exhaust air via an exhaust fan.

Die Trockner 86, 90 und 94 sind ebenfalls konzeptionell identisch aufgebaut und erstrecken sich jeweils im ersten und im zweiten Obergeschoss 34.2 und 34.3. Dabei sind im zweiten Obergeschoss 34.3 jeweils zugehörige Betriebsaggregate angesiedelt, wobei nur Betriebsaggregate 106 des Zwischentrockners 90 für Basislack in Figur 3 zu erkennen sind. Die Trockner 86, 90 und 94 umfassen wie der KTL-Trockner 56 oder der Unterbodenschutz-Trockner 72 jeweilige Kühlzonen; diese sind jedoch nicht gesondert gekennzeichnet.The dryers 86, 90 and 94 are also constructed conceptually identical and each extend in the first and second floors 34.2 and 34.3. In each case, associated operating units are located on the second floor 34.3, with only operating units 106 of the intermediate dryer 90 for basecoat in FIG. 3 can be seen. The dryers 86, 90, and 94, like the CTL dryer 56 or underbody protection dryer 72, include respective cooling zones; however, these are not marked separately.

Bevor die Fahrzeugkarosserie 14 in die Basislack-Applikationskabine 88 hinein gefördert wird, kann sie mittels des Fördersystems 38 in das Erdgeschoss 34.1 des zweiten Gebäudeflügels 28 gefördert werden, in dem in den Figuren 2 und 3 zu erkennende Arbeitsstationen 108 vorhanden sind, die sich beispielsweise unter dem Zwischentrockner 90 für Basislack und/oder den anderen Trocknern 86 bzw. 94 befinden können. In den Arbeitsstationen 108 können die Fahrzeugkarosserien 14 beispielsweise wieder einem Audit und/oder einem Schleifprozess unterworfen werden. Hiernach werden die Fahrzeugkarosserien 14 wieder in das erste Obergeschoss 34.2 und in die Basislack-Applikationskabine 92 hinein gefördert.Before the vehicle body 14 is conveyed into the base paint application cabin 88, it can be conveyed by means of the conveyor system 38 into the ground floor 34. 1 of the second building wing 28, in which Figures 2 and 3 there are workstations 108 to be recognized, which may be located, for example, under the intermediary dryer 90 for basecoat and / or the other dryers 86 and 94, respectively. In the workstations 108, for example, the vehicle bodies 14 may again be subjected to an audit and / or a grinding process. After that, the vehicle bodies 14 are again conveyed to the first upper floor 34. 2 and into the base paint application cabin 92.

Nachdem die Fahrzeugkarosserie 14 den Decklack-Trockner 94 verlassen haben, wird sie durch eine Inspektionslinie 110 gefördert, in welcher mehrere Inspektionskabinen 112 angeordnet sind, in denen die Qualitätsendabnahme der Fahrzeugkarosserie 14 durch Inspektionspersonal erfolgt. Im Bedarfsfall können hiernach kleinere Lackreparaturen in sogenannten "spot repair"-Kabinen durchgeführt werden. Bei größeren Lackfehlern kann die Fahrzeugkarosserie 14 als Rückläufer wieder in den Decklack-Lackierprozess eingeschleust werden. Wahlweise kann die Fahrzeugkarosserie 14 auch vor der Inspektionslinie 110 in dem Hochregallager 32 zwischengelagert werden.After the vehicle body 14 has left the top coat dryer 94, it is conveyed through an inspection line 110 in which a plurality of inspection booths 112 are arranged, in which the quality end of the vehicle body 14 by inspection personnel. If necessary, small paint repairs can be carried out in so-called spot repair cabins. For larger paint defects, the vehicle body 14 can be introduced as a return to the topcoat paint process. Optionally, the vehicle body 14 may also be stored in the high-bay warehouse 32 before the inspection line 110.

Nach der in der Inspektionslinie 110 durchgeführten finalen Qualitätskontrolle wird die Fahrzeugkarosserie 14 in eine nicht eigens gezeigte Endmontage-Anlage gefördert, in welcher das Fahrzeug fertiggestellt wird.Following the final quality control performed in the inspection line 110, the vehicle body 14 is conveyed to a final assembly facility, not specifically shown, in which the vehicle is completed.

Die Behandlungsbereiche 36 sind mit einem Verteilersystem 114 für Betriebsmedien verbunden, durch welches Betriebsmedien, die in den einzelnen Behandlungsbereichen 36 benötigt werden oder dort anfallen, den einzelnen Behandlungsbereichen 36 zugeführt bzw. abgeführt werden können. Solche Betriebsmedien sind beispielsweise allgemeine Betriebsmedien wie Heißwasser, Kaltwasser, Druckluft und Strom. Solche Betriebsmedien können aber auch behandlungsspezifische Betriebsmedien sein, die für eine bestimmte Behandlung einer Fahrzeugkarosserie 14 in einem Behandlungsbereich 36 erforderlich sind. Behandlungsspezifische Betriebsmedien können zum Beispiel die Beschichtungsmaterialien umfassen, die in den einzelnen Applikationskabinen 84, 88, 92 appliziert werden, oder auch spezielle Reinigungsmittel oder dergleichen, die in unterschiedlichen Behandlungsbereichen 36 benötigt werden.The treatment areas 36 are connected to a distributor medium 114 for operating media, by means of which operating media, which are required or accumulated in the individual treatment areas 36, can be supplied or removed to the individual treatment areas 36. Such operating media are, for example, general operating media such as hot water, cold water, compressed air and electricity. However, such operating media may also be treatment-specific operating media, which are required for a specific treatment of a vehicle body 14 in a treatment area 36. Treatment-specific operating media may include, for example, the coating materials applied in the individual application booths 84, 88, 92 or special cleaning agents or the like required in different treatment areas 36.

In der Regel erfolgt die Versorgung der Behandlungsbereiche 36 mit solchen derartigen behandlungsspezifischen Betriebsmedien jedoch über gesonderte Behandlungs-Verteilersysteme, die jeweils einem oder gegebenenfalls mehreren Behandlungsbereichen 36 zugeordnet sind. So werden die Applikationskabinen 84, 88, 92 jeweils gesondert mit den benötigten Beschichtungsmaterialien Füller, Basislack bzw. Decklack versorgt.As a rule, however, the supply of the treatment areas 36 with such treatment-specific operating media takes place via separate treatment distribution systems, which are each assigned to one or optionally a plurality of treatment areas 36. Thus, the application booths 84, 88, 92 are each supplied separately with the required coating materials filler, basecoat or topcoat.

Der Funktionstrakt 24 umfasst wenigstens einen Installationskanal 116 für Medienleitungen 118, der sich zumindest in einem Abschnitt des Funktionstraktes 24 in Längsrichtung 18 erstreckt und in welchem wenigstens eine Medienleitung 118 untergebracht ist, die mit wenigstens einer komplementären Medienleitung 120 in einem der Gebäudeflügel 26 oder 28 verbunden ist.The functional section 24 comprises at least one installation duct 116 for media ducts 118, which extends at least in a section of the functional wing 24 in the longitudinal direction 18 and in which at least one media duct 118 is accommodated, which is connected to at least one complementary duct 120 in one of the building wings 26 or 28 is.

Der Installationskanal 116 erstreckt sich in Längsrichtung 18 weitgehen über die gesamte Länge des Funktionstraktes 24. Die Medienleitung 118 kann insbesondere an wenigstens zwei Verbindungsbereichen, die in Längsrichtung 18 beabstandet sind, mit komplementären Medienleitungen 120 in dem ersten Gebäudeflügel 26 und/oder in dem zweiten Gebäudeflügel 28 verbunden werden kann.The installation channel 116 extends in the longitudinal direction 18 over the entire length of the functional section 24. The media line 118 can in particular at least two connecting portions, which are spaced in the longitudinal direction 18, with complementary media lines 120 in the first building wing 26 and / or in the second building wing 28 can be connected.

Beim hier erläuterten Ausführungsbeispiel gibt es einen ersten Installationskanal 116.1 im Erdgeschoss 34.1 für Energieleitungen und einen zweiten Installationskanal 116.2 im ersten Obergeschoss 34.2 für Fluidleitungen.In the exemplary embodiment explained here, there is a first installation channel 116.1 on the ground floor 34.1 for power lines and a second installation channel 116.2 on the first floor 34.2 for fluid lines.

Die Medienleitungen 118 erstrecken sich in Längsrichtung 18 durch die Installationskanäle 116, wobei sie auch einen gewinkelten und/oder nach oben oder unten geneigten Verlauf haben können. Ein gewinkelter Verlauf ist in Figur 5 zu erkennen, der beispielsweise zur Kompensation einer Wärmeausdehnung dient.The media lines 118 extend in the longitudinal direction 18 through the installation channels 116, wherein they can also have an angled and / or inclined upward or downward course. An angled course is in FIG. 5 to recognize, for example, is used to compensate for thermal expansion.

Figur 6 veranschaulicht eine Heißwasserleitung 118.1, eine Kaltwasserleitung 118.2, eine Druckluftleitung 118.3 und eine Abwasserleitung 118.4 in dem ersten Installationskanal 116.1, von denen Figur 5 der Übersichtlichkeit halber lediglich die Heißwasserleitung 118.1 und die Druckluftleitung 118.3 zeigt. Außerdem sind in Figur 5 zwei Zweigleitungen 118a, konkret eine Heißwasser-Zweigleitung 118.1a der Heißwasserleitung 118.1 und eine Druckluft-Zweigleitung 118.3a der Druckluftleitung 118 zu erkennen, die zu einem oben erwähnten Verbindungsbereich zum Anschluss der komplementären Medienleitungen 120 in dem zweiten Gebäudeflügel 28 führen, was hier nicht im Einzelnen gezeigt ist. Die Zweigleitungen 118a können durch vertikale, geschossübergreifende Installationsschächte 122 zu anderen Geschossen 34 geführt werden, damit auch die anderen Geschosse 34 mit den benötigten Medien versorgt werden können. Beispielsweise kann eine Druckluft-Zweigleitung 118.3a aus dem zweiten Installationskanal 116.2 nach unten in das Erdgeschoss 34.1 geführt werden, wo sie an eine komplementäre Druckluftleitung 120.3 angeschlossen werden kann, um die Arbeitsstationen 66 oder 108 mit Druckluft zu versorgen. FIG. 6 illustrates a hot water line 118.1, a cold water line 118.2, a compressed air line 118.3 and a sewer line 118.4 in the first installation channel 116.1, of which FIG. 5 for the sake of clarity, only the hot water line 118.1 and the compressed air line 118.3 shows. Also, in FIG. 5 Two branch lines 118a, specifically a hot water branch line 118.1a of the hot water line 118.1 and a compressed air branch line 118.3a of the compressed air line 118 can be seen leading to an above-mentioned connection area for connecting the complementary media lines 120 in the second building wing 28, which is not here Individual is shown. The branch lines 118a may be passed through vertical, cross-storey installation shafts 122 to other floors 34 so that the other floors 34 can be supplied with the required media. For example, a compressed air branch 118.3a from the second installation channel 116.2 can be led down into the ground floor 34.1 where it can be connected to a complementary compressed air line 120.3 to supply the work stations 66 or 108 with compressed air.

Komplementäre Medienleitungen 120 in Form einer komplementären Heißwasserleitung 120.1 und einer komplementären Druckluftleitung 120.3 sind nur in Figur 6 und dort stark schematisch als gestrichelte Linien veranschaulicht.Complementary media lines 120 in the form of a complementary hot water line 120.1 and a complementary compressed air line 120.3 are only in FIG. 6 and there very schematically illustrated as dashed lines.

Der Funktionstrakt 24 umfasst außerdem integrierte Frischluft-Strömungskanäle 124, Zuluft-Strömungskanäle 126 und Umluft-Strömungskanäle 128 sowie Abluft- und Fortluft-Strömungskanäle eines insgesamt mit 130 bezeichneten Luftsystems. Für den Betrieb des Luftsystems 130 notwendige Bauteile und Komponenten in einzelnen Behandlungsbereichen 36 benötigt oder freigesetzt werden.The functional wing 24 also includes integrated fresh air flow channels 124, supply air flow channels 126 and recirculation flow channels 128, and exhaust and exhaust air flow channels of an air system generally designated 130. For the operation of the air system 130 necessary components and components in individual treatment areas 36 needed or released.

In den Figuren sind Strömungswege von Frischluft 132 als gestrichelte Linien veranschaulicht. Strömungswege von Zuluft 134 sind als strich-doppelpunktierte Linien und Strömungswege von Umluft 136 sind als punktierte Linien dargestellt. Bei allen Strömungslinien 132, 134, 136 sind die Strömungsrichtungen jeweils durch Pfeile verdeutlicht.In the figures, flow paths of fresh air 132 are illustrated as dashed lines. Flow paths of supply air 134 are shown as dash-dotted lines and flow paths of circulating air 136 are shown as dotted lines. For all flow lines 132, 134, 136, the flow directions are illustrated by arrows.

Die Strömungskanäle 124, 126 und 128 sind mit Strömungswegen in den Gebäudeflügeln 26, 28 verbunden, die zu jeweiligen Behandlungsbereichen 36 führen, in denen Zuluft benötigt oder Abluft erzeugt wird, die dann als Umluft weitergeleitet wird. Solche Strömungswege zu den Behandlungsbereichen 36 hin oder von diesen weg sind nicht gesondert gezeigt oder bezeichnet und können beispielsweise in Form von Strömungsleitungen, Strömungsschächten oder Strömungskanälen ausgebildet sein.The flow channels 124, 126 and 128 are connected to flow paths in the building wings 26, 28 which lead to respective treatment areas 36 in which supply air is required or exhaust air is generated, which is then forwarded as circulating air. Such flow paths toward or away from the treatment areas 36 are not separately shown or designated and may be, for example be designed in the form of flow lines, flow wells or flow channels.

Auf dem Dach des Gebäudebaukörpers 16 befindet sich ein Aufbau, der als eine oder mehrere Eingangseinheiten, über welche Außenluft als Frischluft 132 in den Gebäudebaukörper 16 angesaugt wird, und ein oder mehrere Ausgangseinheiten für Fortluft ausgebildet sein kann, wobei lediglich eine einzige Aufbau-Einheit 138 gezeigt ist, welche eine solche Eingangseinheit und eine solche Ausgangseinheit zusammenfasst. In diesem Fall sind die Frischluft-Strömungskanäle 124 somit Außenluft-Strömungskanäle. Die Frischluft 132 gelangt zunächst zu einer primären Konditioniervorrichtung 140, in welchen die Frischluft in bekannter Art und Weise konditioniert wird und die in den Figuren 3 und 7 zu erkennen sind. Bei der Konditionierung werden beispielsweise die Temperatur und der Feuchtegehalt der Frischluft 132 eingestellt. Auch kann die Frischluft 132 mit Umluft 136 gemischt werden, wobei das Mischungsverhältnis eingestellt werden kann. Beim vorliegenden Ausführungsbeispiel ist die primäre Konditioniervorrichtung 140 im Penthouse 34.4 im zweiten Gebäudeflügel 28 untergebracht.On the roof of the building structure 16 is a structure which as one or more input units, via which outside air is drawn as fresh air 132 into the building structure 16, and one or more output units can be formed for exhaust air, wherein only a single assembly unit 138th which summarizes such an input unit and such an output unit. In this case, the fresh air flow channels 124 are thus outside air flow channels. The fresh air 132 first passes to a primary conditioning device 140, in which the fresh air is conditioned in a known manner and in the Figures 3 and 7 can be seen. During conditioning, for example, the temperature and the moisture content of the fresh air 132 are set. Also, the fresh air 132 may be mixed with circulating air 136, wherein the mixing ratio can be adjusted. In the present embodiment, the primary conditioning device 140 is housed in the penthouse 34.4 in the second building wing 28.

Wie in Figur 7 zu erkennen ist, befinden sich im Penthouse 34.4 im zweiten Gebäudeflügel 28 außerdem noch Zuluftanlagen 142 und Umluftanlagen 144, die nicht alle mit Bezugszeichen versehen sind. Über die Zuluftanlagen 142 wird die konditionierte Zuluft 134 zu den einzelnen Behandlungsbereichen 36 und den dortigen Anlagen bzw. den dortigen Betriebsaggregate 60, 78 und 106 sowie Arbeitsstationen 66 und 108 verteilt. Hierzu sind alle Anlagen und Arbeitsstationen strömungstechnisch mit einer der Zuluftanlagen 142 verbunden, von wo die Zuluft 134 auf dem Wege über einen der Zuluft-Strömungskanäle 126 des Funktionstraktes 24 zu einer Behandlungszone 36 bzw. der dortigen Anlage geleitet wird.As in FIG. 7 can be seen, are in the penthouse 34.4 in the second building wing 28 also still supply air systems 142 and recirculation systems 144, which are not all provided with reference numerals. Via the supply air installations 142, the conditioned incoming air 134 is distributed to the individual treatment areas 36 and the local installations or the local operating units 60, 78 and 106 as well as work stations 66 and 108. For this purpose, all plants and workstations are fluidically connected to one of the supply air systems 142, from where the supply air 134 is passed on the way via one of the supply air flow channels 126 of the functional tract 24 to a treatment zone 36 and the local plant.

Die Füller-Applikationskabine 84, die Basislack-Applikationskabine 88 und die Decklack-Applikationskabine 92 sind außerdem noch jeweils strömungstechnisch mit einer der Umluftanlagen 144 verbunden, wo Umluft 136 konditioniert und als konditionierte Zuluft 134 wieder zu der Anlage rückgeführt werden kann, aus der die Umluft 136 stammt. Die Umluftanlagen 144 bilden somit sekundäre Konditioniervorrichtungen.The filler application booth 84, the basecoat application booth 88 and the topcoat application booth 92 are also each fluidic connected to one of the recirculation systems 144, where circulating air 136 conditioned and can be recycled as a conditioned supply air 134 back to the system from which the circulating air 136 comes. The recirculation systems 144 thus form secondary conditioning devices.

Der Strömungsweg von Zuluft 134 zu den Arbeitsstationen 66 und 108 ist exemplarisch in den Figuren 2 bis 4 veranschaulicht. Nachdem Frischluft 132 durch die Eingangseinheit der Aufbau-Einheit 138 angesaugt und in der primären Konditioniervorrichtung 140 konditioniert wurde, gelangt sie in den Arbeitsstationen 66, 108 zugeordneten Zuluftanlagen 142, von wo sie über Zuluft-Strömungskanäle 126 des Funktionstraktes 24 in das Erdgeschoss 34.1 geleitet wird. Dort strömt die Zuluft 134 über oben angesprochene, nicht eigens gezeigte Strömungswege zur jeweiligen Arbeitsstation 66, 108.The flow path of supply air 134 to the workstations 66 and 108 is exemplary in the FIGS. 2 to 4 illustrated. After fresh air 132 has been aspirated through the input unit of the build-up unit 138 and conditioned in the primary conditioning device 140, it passes into the work stations 66, 108 associated Zuluftanlagen 142, from where it is routed through supply air flow channels 126 of the functional tract 24 in the ground floor 34.1 , There, the supply air 134 flows through above-mentioned, not specifically shown flow paths to the respective workstation 66, 108th

In entsprechender Weise gelangt Frischluft 134 über gesondert zugewiesene Zuluftanlagen 142 zu den Inspektionskabinen 112 der Inspektionslinie 110 im ersten Obergeschoss 34.2; dies zeigt Figur 3. Dort ist auch zu erkennen, dass in den Inspektionskabinen 112 entstehende Abluft als Umluft 136 zu einem Umluft-Strömungskanal 128 in dem Funktionstrakt 24, in welchem die Umluft 136 aus dem ersten Obergeschoss 34.2 nach oben in das Penthouse 34.4, wo die Umluft 136 wieder in die primäre Konditioniervorrichtung 140 eingespeist wird.In a corresponding manner, fresh air 134 reaches the inspection cabins 112 of the inspection line 110 on the first floor 34.2 via separately assigned supply air installations 142; this shows FIG. 3 , There it can also be seen that in the inspection cabins 112 resulting exhaust air as circulating air 136 to a circulating air flow channel 128 in the functional wing 24, in which the circulating air 136 from the first floor 34.2 upwards in the penthouse 34.4, where the circulating air 136 back in the primary conditioning device 140 is fed.

Auch die gereinigte Abluft aus den Applikationskabinen 84, 88 oder 92 gelangt über den jeweiligen Sammelkanal, der dementsprechend einen Umluft-Strömungskanal 128 im Funktionstrakt 24 bildet, wieder nach oben in das Penthouse 34.4. Die Umluft aus den Applikationskabinen 84, 88 oder 92 wird jedoch der jeweiligen Umluftanlage 144 zugeführt, wo eine gesonderte Konditionierung erfolgt.Also, the cleaned exhaust air from the application booths 84, 88 or 92 passes through the respective collection channel, which accordingly forms a recirculating air flow channel 128 in functional tract 24, back up into the penthouse 34.4. However, the circulating air from the application booths 84, 88 or 92 is supplied to the respective circulating air system 144, where a separate conditioning takes place.

Die Installationskanäle 116 des Funktionstraktes 24 sind horizontal orientiert. In Figur 5 ist zu erkennen, dass der Funktionstrakt 24 darüber hinaus vertikal orientierte Module umfasst, wobei Funktionsmodule für technische Einrichtungen einerseits und Konstruktionsmodule für Infrastruktur und Baustatik andererseits vorhanden sind, die sich über Etagen 34 des Funktionstraktes 24 hinweg erstrecken. Die Funktionsmodule und die Konstruktionsmodule können sich im Erdgeschoss 34.1 und von dort bis ins Penthouse 34.4 erstrecken oder zwischen weniger als der Gesamtzahl der Etagen 34 verlaufen.The installation channels 116 of the functional tract 24 are oriented horizontally. In Figure 5 it can be seen that the functional tract 24 also oriented vertically Includes modules, functional modules for technical facilities on the one hand and design modules for infrastructure and structural engineering on the other hand are present, extending over floors 34 of the functional wing 24 away. The functional modules and the design modules may extend on the ground floor 34.1 and from there to the penthouse 34.4 or run between less than the total number of floors 34.

Es gibt ein oder mehrere Funktionsmodule 146 mit einem oder mehreren Strömungskanälen 124, 126 oder 128 des Luftsystems 130, ein oder mehrere Funktionsmodule 148, in denen Komponenten zur Energieversorgung der Lackieranlage 12 untergebracht sind, ferner ein oder mehrere Funktionsmodule 150 mit ein oder mehreren Installationsschächten 122 für Medienleitungen 118, wie beispielsweise die oben beschriebenen Zweigleitungen 118a, die vertikal verlaufen. Ein oder mehrere Konstruktionsmodule 152 sind für ein oder mehrere Treppenhäuser 154 vorgesehen, ein oder mehrere weitere Konstruktionsmodule 156 für ein oder mehrere Aufzuganlagen 158. Ein oder mehrere ergänzende Konstruktionsmodule 160 dienen zur Kompensation von Ausdehnungsschwankungen des Gebäudekörpers 16. Darüber hinaus gibt es ein oder mehrere Konstruktionsmodule 161 für Erholungs- und/oder Kommunikationszonen, in denen sich Mitarbeiter aufhalten können und/oder in denen Kommunikationsmittel untergebracht sein können, damit die Mitarbeiter miteinander oder mit anderen Bereichen in der AnlageThere are one or more functional modules 146 with one or more flow channels 124, 126 or 128 of the air system 130, one or more functional modules 148, in which components for powering the paint shop 12 are housed, further one or more functional modules 150 with one or more installation wells 122nd for media lines 118, such as the branch lines 118a described above, which are vertical. One or more design modules 152 are provided for one or more staircases 154, one or more further design modules 156 for one or more elevator systems 158. One or more supplemental design modules 160 are used to compensate for expansion variations of the building body 16. In addition, there are one or more design modules 161 for recreation and / or communication zones in which employees may reside and / or in which means of communication may be accommodated, so that employees interact with each other or with other areas in the facility

In Figur 5 ist jeweils nur eines der Funktionsmodule 146, 148, 150 und jeweils nur eines der Konstruktionsmodule 152, 156, 160 gezeigt. Die Anzahl und Anordnung der Funktionsmodule 146, 148, 150 und der Konstruktionsmodule 152, 156, 160 hängt von der Konzeption der Lackieranlage 12 und des Funktionstraktes 24 ab.In FIG. 5 In each case, only one of the functional modules 146, 148, 150 and in each case only one of the design modules 152, 156, 160 is shown. The number and arrangement of the functional modules 146, 148, 150 and the design modules 152, 156, 160 depends on the design of the paint shop 12 and the functional wing 24.

In jeder Etage 34 sind die Funktionsmodule 146 bis 150 und die Konstruktionsmodule 152 bis 160 von einem begehbaren Gang 162 flankiert, der beim hier beschriebenen Ausführungsbeispiel auf der Seite des Funktionstraktes 24 liegt, der dem ersten Gebäudeflügel 26 zugewandt ist. Die Installationskanäle 116.1 und 116.2 sind im oberen Teil der jeweiligen Gänge 162 untergebracht. Über die Gänge 162 können die Bereiche der Lackieranlage 12 in Längsrichtung 18 erreicht werden. Darüber hinaus können die Gänge 162 für die Besichtigung der Lackieranlage 12 genutzt werden, ohne dass Besucher hierzu die Gebäudeflügel 26, 28 mit den Behandlungsbereichen 36 betreten müssen. Solche Besucher-Gänge sind zur den Gebäudeflügeln 26, 28 mit entsprechenden Fenstern ausgestattet.In each floor 34, the functional modules 146 to 150 and the construction modules 152 to 160 are flanked by a walk-through passage 162 which, in the exemplary embodiment described here, lies on the side of the functional wing 24, which facing the first building wing 26. The installation channels 116.1 and 116.2 are housed in the upper part of the respective aisles 162. Via the passages 162, the areas of the paint shop 12 in the longitudinal direction 18 can be achieved. In addition, the aisles 162 can be used for the inspection of the paint shop 12 without visitors having to enter the building wings 26, 28 with the treatment areas 36. Such visitor aisles are to the building wings 26, 28 equipped with appropriate windows.

Wie Figur 7 außerdem zeigt, sind im Penthouse 34.4 im ersten Gebäudeflügel 26 Sozialräume 164 untergebracht. Solche Sozialräume 164 umfassen beispielsweise Umkleideräume, Sanitärräume, eine Kantine, Büros und dergleichen.As FIG. 7 In addition, penthouse 34.4 in the first building wing accommodates 26 social rooms 164. Such social rooms 164 include, for example, changing rooms, sanitary facilities, a canteen, offices, and the like.

Die Lackieranlage 12 bzw. der Funktionstrakt 24 sind derart konzipiert, dass die Gebäudeflügel 26 und 28 im Grundsatz für Werker nur auf dem Wege über den Funktionstrakt 24 und in dem Funktionstrakt 24 nur auf dem Wege über die Sozialräume 164 erreicht werden können. Hiervon ausgenommen sind gegebenenfalls zusätzlich vorhandene Fluchtwege bzw. gesonderte Zugänge für Rettungskräfte.The paint shop 12 and the functional wing 24 are designed such that the building wings 26 and 28 can be achieved in principle for workers only on the way through the functional wing 24 and in the functional wing 24 only on the way through the social spaces 164. Exceptions to this may be additional escape routes or separate access for emergency services.

Über einen Eingang gelangt eine Person daher zunächst zur Aufzuganlage 158, die direkt in das Penthouse 34.4 und die dortigen Sozialräume 164 führt. Insbesondere können Büros und eine gegebenenfalls vorhandene Kantine unmittelbar erreicht werden. Von dort kann eine Person dann über das Treppenhaus 154 oder gegebenenfalls eine weitere Aufzuganlage in die einzelnen Geschosse 34.1 bis 34.3 gelangen. In Figur 2 sind Zugangstüren 166 in im Penthouse 34.4 und im zweiten Obergeschoss 34.3 zu erkennen, über welche der Gebäudeflügel 26 in den jeweiligen Etagen 34.4 und 34.3 zugänglich ist. Entsprechende Verbindungstüren sind auch in den anderen Etagen 34.1 und 34. 2 und auch in Richtung zum zweiten Gebäudeflügel 28 hin vorhanden. Letztere sind insbesondere in dem Konstruktionsmodul 160 für die Ausdehnungskompensation vorhanden, das sich von Funktionsmodulen flankiert bis an den zweiten Gebäudeflügel 28 angrenzend erstreckt.Via an entrance, a person therefore first reaches the elevator installation 158, which leads directly to the penthouse 34.4 and the social rooms 164 there. In particular, offices and an optionally existing canteen can be reached directly. From there, a person can then access the staircases 154 or possibly another elevator system in the individual projectiles 34.1 to 34.3. In FIG. 2 Access doors 166 in the penthouse 34.4 and on the second floor 34.3 can be seen, via which the building wing 26 is accessible in the respective floors 34.4 and 34.3. Corresponding connecting doors are also present in the other floors 34.1 and 34. 2 and also towards the second building wing 28 out. The latter are particularly present in the expansion compensation design module 160, which flanks from functional modules to the second building wing 28 adjacent to it.

Die Etagen 34 der Lackieranlage 12 sind somit über den Funktionstrakt 24 erreichbar und miteinander verbunden. Im Normalbetrieb der Lackieranlage 12 werden auch nur diese Erreichbarkeiten und Verbindungen genutzt. Es können noch zusätzliche Verbindungswege zwischen den Etagen 34 vorhanden sein, die in Gefahrenfällen oder in anderen Sonderfällen genutzt werden können.The floors 34 of the paint shop 12 are thus accessible via the functional tract 24 and connected to each other. In normal operation of the paint shop 12, only these accessibilities and connections are used. There may be additional connection paths between the floors 34, which can be used in hazardous situations or in other special cases.

Der Funktionstrakt 24 kann insbesondere aus Stahlbeton gefertigt sein. Der Funktionstrakt 24 trägt maßgeblich zur Stabilität des Gebäudekörpers 16 bei. Die Gebäudeflügel 26 und 28 können wahlweise in Betonbauweise gefertigt sein oder als Stahlkonstruktion konzipiert sein. Eine Belastbarkeit der Gebäudeflügel 26, 28 zwischen 5 bis 10 KN m-2 kann ausreichend sein, um die Anlagenkomponenten tragen zu können.The functional tract 24 can in particular be made of reinforced concrete. The functional tract 24 contributes significantly to the stability of the building body 16. The building wings 26 and 28 can either be made in concrete construction or designed as a steel structure. A load capacity of the building wings 26, 28 between 5 to 10 KN m -2 may be sufficient to carry the system components can.

Der Funktionstrakt 24 trennt die Gebäudeflügel 26, 28 außerdem als gesonderte Brandabschnitte voneinander. Der Funktionstrakt 24 bildet einen gegenüber den Gebäudeflügeln 26, 28 abgesicherten Bereich und ist im Gefahrenfall von beiden Gebäudeflügeln 26, 28 mit kurzen Wegen erreichbar.The functional tract 24 also separates the building wings 26, 28 from one another as separate fire sections. The functional wing 24 forms a protected area with respect to the building wings 26, 28 and can be reached in case of danger from both building wings 26, 28 with short distances.

Funktionsmodule 146, 148, 150 und Konstruktionsmodule 152, 156, 160, 161 können eine Einheit bilden und sowohl technische Einrichtungen für die Versorgung von Medien und die Lüftung als auch Infrastruktureinrichtungen wie Treppenhäuser 154, Aufzuganlagen 158 oder Bedien- und Besichtigungswege 162 umfassen. Diese Funktionsmodule 146, 148, 150 und Konstruktionsmodule 152, 156, 160, 161 sind in der Praxis tragende Elemente für die Gebäudestatik.Function modules 146, 148, 150 and design modules 152, 156, 160, 161 may be unitary and include both media and ventilation technical facilities and infrastructures such as stairways 154, elevator installations 158, or service and sightseeing routes 162. These functional modules 146, 148, 150 and design modules 152, 156, 160, 161 are in practice load-bearing elements for building statics.

Claims (8)

Lackieranlage zum Lackieren von Gegenständen, insbesondere von Fahrzeugkarosserien (14), mit a) einem Gebäudebaukörper (16), in dem mehrere Behandlungsbereiche (36) untergebracht sind, in denen unterschiedlichen Lackierschritte durchführbar sind, und der eine Längsrichtung (18) definiert; b) einem Verteilersystem (114) mit Medienleitungen (118, 120) für Betriebsmedien, durch welche Betriebsmedien, die in den einzelnen Behandlungsbereichen (36) benötigt werden oder dort anfallen, den einzelnen Behandlungsbereichen (36) zuführbar oder von den Behandlungsbereichen (36) abführbar sind; dadurch gekennzeichnet, dass c) der Gebäudebaukörper (16) einen Funktionstrakt (24) umfasst, der in Längsrichtung (18) von wenigstens einem Gebäudeflügel (26, 28) flankiert ist, in dem einer oder mehrere der Behandlungsbereiche (36) untergebracht sind; d) der Funktionstrakt (24) wenigstens einen Installationskanal (116) für Medienleitungen (118) umfasst, welcher sich zumindest in einem Abschnitt des Funktionstraktes (24) in Längsrichtung (18) erstreckt, wobei in dem Abschnitt wenigstens eine der Medienleitungen (118) in Längsrichtung (18) verläuft, die mit wenigstens einer komplementären Medienleitung (120) in dem Gebäudeflügel (26, 28) verbindbar ist, die zu einem der Behandlungsbereiche (36) führt. Painting installation for painting objects, in particular vehicle bodies (14), with a) a building structure (16) in which a plurality of treatment areas (36) are housed, in which different painting steps are feasible, and which defines a longitudinal direction (18); b) a distribution system (114) with media lines (118, 120) for operating media, through which operating media required or generated in the individual treatment areas (36) can be supplied to the individual treatment areas (36) or discharged from the treatment areas (36) are; characterized in that c) the building structure (16) comprises a functional wing (24) flanked in the longitudinal direction (18) by at least one building wing (26, 28) housing one or more of the treatment areas (36); d) the functional tract (24) comprises at least one installation duct (116) for media ducts (118) extending in at least a portion of the functional wing (24) in the longitudinal direction (18), wherein in the section at least one of the media ducts (118) in Lengthwise direction (18), which is connectable to at least one complementary media line (120) in the building wing (26, 28), which leads to one of the treatment areas (36). Lackieranlage nach Anspruch 1, dadurch gekennzeichnet, dass sich der Installationskanal (116) in Längsrichtung (18) weitgehend über die gesamte Länge des Funktionstraktes (24) erstreckt.Painting installation according to claim 1, characterized in that the installation channel (116) extends in the longitudinal direction (18) substantially over the entire length of the functional tract (24). Lackieranlage nach Anspruch 1 oder 2, dadurch gekennzeichnet, dass die Medienleitung (118) in wenigstens zwei Verbindungsbereichen, die in Längsrichtung (18) beabstandet sind, mit komplementären Medienleitungen (120) in dem Gebäudeflügel (26, 28) verbindbar ist.Painting installation according to claim 1 or 2, characterized in that the media line (118) in at least two connecting portions, which are spaced in the longitudinal direction (18), with complementary media lines (120) in the building wing (26, 28) is connectable. Lackieranlage nach einem der Ansprüche 1 bis 3, dadurch gekennzeichnet, dass der Funktionstrakt (24) Funktionsmodule (146, 148, 150) für technische Einrichtungen und Konstruktionsmodule (152, 156, 160) für Infrastruktur und Baustatik umfasst.Painting installation according to one of claims 1 to 3, characterized in that the functional tract (24) comprises functional modules (146, 148, 150) for technical facilities and construction modules (152, 156, 160) for infrastructure and structural engineering. Lackieranlage nach Anspruch 4, dadurch gekennzeichnet, dass die Funktionsmodule (146, 148, 150) und/oder die Konstruktionsmodule (152, 154, 160) vertikal orientiert sind.Painting installation according to claim 4, characterized in that the functional modules (146, 148, 150) and / or the construction modules (152, 154, 160) are vertically oriented. Lackieranlage nach Anspruch 4 oder 5, dadurch gekennzeichnet, dass der Funktionstrakt (24) ein oder mehrere Funktionsmodule (146) mit einem oder mehreren Strömungskanälen (124, 126, 128) eines Luftsystems (130) und/oder ein oder mehrere Funktionsmodule (148), in denen Komponenten zur Energieversorgung der Lackieranlage (12) untergebracht sind, und/oder ein oder mehrere Funktionsmodule (150) mit ein oder mehreren Installationsschächten (122) für Medienleitungen (118) umfasst.Painting installation according to claim 4 or 5, characterized in that the functional tract (24) one or more functional modules (146) with one or more flow channels (124, 126, 128) of an air system (130) and / or one or more functional modules (148). in which components for supplying energy to the paint shop (12) are accommodated, and / or one or more functional modules (150) with one or more installation shafts (122) for media lines (118). Lackieranlage nach Anspruch 5 oder 6, dadurch gekennzeichnet, dass der Funktionstrakt (24) ein oder mehrere Konstruktionsmodule (152) für ein oder mehrere Treppenhäuser (154) und/oder ein oder mehrere Konstruktionsmodule (156) für eine oder mehrere Aufzuganlagen (158) und/oder ein oder mehrere Konstruktionsmodule (161) zur Einrichtung von Erholungs- und/oder Kommunikationszonen und/oder ein oder mehrere Konstruktionsmodule (160) zur Kompensation von Ausdehnungsschwankungen des Gebäudekörpers (16) umfasst.Painting installation according to claim 5 or 6, characterized in that the functional tract (24) comprises one or more construction modules (152) for one or more staircases (154) and / or one or more construction modules (156) for one or more elevator installations (158) and / or one or more design modules (161) for the establishment of recreational and / or Communication zones and / or one or more construction modules (160) for compensating for expansion variations of the building body (16). Lackieranlage nach einem der Ansprüche 1 bis 7, dadurch gekennzeichnet, dass der Gebäudeflügel (26, 28) mehrere Etagen (34) aufweist, die über den Funktionstrakt (24) erreichbar und miteinander verbunden sind.Painting installation according to one of claims 1 to 7, characterized in that the building wing (26, 28) has a plurality of floors (34) which are accessible via the functional tract (24) and connected to each other.
EP19150648.4A 2018-01-08 2019-01-08 Painting assembly Withdrawn EP3508281A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE102018100266.1A DE102018100266A1 (en) 2018-01-08 2018-01-08 paint shop

Publications (1)

Publication Number Publication Date
EP3508281A1 true EP3508281A1 (en) 2019-07-10

Family

ID=65010560

Family Applications (1)

Application Number Title Priority Date Filing Date
EP19150648.4A Withdrawn EP3508281A1 (en) 2018-01-08 2019-01-08 Painting assembly

Country Status (2)

Country Link
EP (1) EP3508281A1 (en)
DE (1) DE102018100266A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110668083A (en) * 2019-11-01 2020-01-10 苏州柳溪机电工程有限公司 Multi-process efficient intelligent coating assembly line
WO2022135629A1 (en) * 2020-12-21 2022-06-30 Dürr Systems Ag Treatment plant and method for treating workpieces
WO2022135630A1 (en) * 2020-12-21 2022-06-30 Dürr Systems Ag Treatment plant and method for treating workpieces

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2844118A1 (en) * 1977-11-10 1979-06-07 Nissan Motor COATING APPLICATION booth
JP2000288442A (en) * 1999-04-08 2000-10-17 Comfort:Kk Device for supplying ionized air for coating booth
WO2006056864A2 (en) * 2004-11-24 2006-06-01 Eurosider S.A.S. Di Milli Ottavio & C. Heated spray painting system
DE102014008280A1 (en) * 2014-06-03 2015-12-03 Eisenmann Ag Plant for painting objects, in particular vehicle bodies

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4114762A1 (en) * 1991-05-06 1992-11-19 Eisenmann Kg Maschbau Paint line for car bodywork - has whole operating side area hermetically closed and formed as clean chamber accessible by personnel sluices
GB9814332D0 (en) * 1998-07-03 1998-09-02 Marsh Peter Gordon Modular buildings
GB201202065D0 (en) * 2012-02-06 2012-03-21 Pmc Repair Specialists Ltd A self contained vehicle repair shop

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2844118A1 (en) * 1977-11-10 1979-06-07 Nissan Motor COATING APPLICATION booth
JP2000288442A (en) * 1999-04-08 2000-10-17 Comfort:Kk Device for supplying ionized air for coating booth
WO2006056864A2 (en) * 2004-11-24 2006-06-01 Eurosider S.A.S. Di Milli Ottavio & C. Heated spray painting system
DE102014008280A1 (en) * 2014-06-03 2015-12-03 Eisenmann Ag Plant for painting objects, in particular vehicle bodies

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110668083A (en) * 2019-11-01 2020-01-10 苏州柳溪机电工程有限公司 Multi-process efficient intelligent coating assembly line
WO2022135629A1 (en) * 2020-12-21 2022-06-30 Dürr Systems Ag Treatment plant and method for treating workpieces
WO2022135630A1 (en) * 2020-12-21 2022-06-30 Dürr Systems Ag Treatment plant and method for treating workpieces

Also Published As

Publication number Publication date
DE102018100266A1 (en) 2019-07-11

Similar Documents

Publication Publication Date Title
EP2303468B1 (en) Painting system for painting objects to be painted
EP2303467B1 (en) Temporary storage for temporarily storing objects to be painted
EP3508281A1 (en) Painting assembly
EP3151978B1 (en) System for painting objects, in particular vehicle bodies
EP1749584B1 (en) Spray booth and installation having overhead tools
WO2008006495A1 (en) Paint shop and corresponding method of operation
DE202007008852U1 (en) Coating zone with guide rails
DE102016004484A1 (en) Process and manufacturing plant for the production of vehicles and surface treatment equipment for the surface treatment of vehicle bodies
EP3322541A1 (en) Device for depositing overspray and surface treatment installation
WO2003074348A1 (en) Assembly plant for assembling industrial products
EP2101926B1 (en) Coating system and method for the series coating of workpieces
EP2244840B2 (en) Device and method for supplying air to an application zone of a paint booth
EP3335802B1 (en) Powder coating booth, powder coating installation and method for operating the powder coating booth
DE4447818C2 (en) Process for powder coating and painting system for carrying out the process
EP2244839B2 (en) Painting system
DE102020105767A1 (en) Treatment plant and treatment method for treating workpieces
EP3712547A1 (en) Temperature control device for controlling the temperature of objects
WO2021063444A1 (en) Treatment system and treatment method
EP1166336B1 (en) Device for manufacturing semiconductor products
DE19607937C2 (en) System for the cavity preservation of workpieces, in particular vehicle bodies
WO2019052947A1 (en) Installation and method for coating objects
DE102019121346B4 (en) Ceiling module for setting up a clean room
EP1466697A2 (en) Production system
WO2024051896A1 (en) Method for setting up a treatment plant, and treatment plant
DE102018118095A1 (en) Device for producing nonwoven webs and method for assembling such a device

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

19U Interruption of proceedings before grant

Effective date: 20190731

19W Proceedings resumed before grant after interruption of proceedings

Effective date: 20200803

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20210114