EP3500078B1 - Procédé et système pour prédire l'effet d'un événement transitoire dans un centre de données - Google Patents
Procédé et système pour prédire l'effet d'un événement transitoire dans un centre de données Download PDFInfo
- Publication number
- EP3500078B1 EP3500078B1 EP18208531.6A EP18208531A EP3500078B1 EP 3500078 B1 EP3500078 B1 EP 3500078B1 EP 18208531 A EP18208531 A EP 18208531A EP 3500078 B1 EP3500078 B1 EP 3500078B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- data center
- cooling
- data
- temperature
- equipment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000001052 transient effect Effects 0.000 title claims description 38
- 238000000034 method Methods 0.000 title claims description 37
- 230000000694 effects Effects 0.000 title description 10
- 238000001816 cooling Methods 0.000 claims description 135
- 238000013461 design Methods 0.000 claims description 20
- 238000005259 measurement Methods 0.000 claims description 6
- 239000012809 cooling fluid Substances 0.000 claims description 5
- 230000020169 heat generation Effects 0.000 claims description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 88
- 238000012546 transfer Methods 0.000 description 18
- 230000008569 process Effects 0.000 description 17
- 239000012530 fluid Substances 0.000 description 12
- 230000006870 function Effects 0.000 description 12
- 230000007246 mechanism Effects 0.000 description 10
- 238000004088 simulation Methods 0.000 description 9
- 238000004364 calculation method Methods 0.000 description 8
- 238000004891 communication Methods 0.000 description 8
- 238000004458 analytical method Methods 0.000 description 7
- 230000008859 change Effects 0.000 description 6
- 238000010521 absorption reaction Methods 0.000 description 4
- 238000013459 approach Methods 0.000 description 4
- 238000012800 visualization Methods 0.000 description 4
- 239000000284 extract Substances 0.000 description 3
- 230000003993 interaction Effects 0.000 description 3
- 238000012545 processing Methods 0.000 description 3
- 239000007787 solid Substances 0.000 description 3
- 208000015778 Undifferentiated pleomorphic sarcoma Diseases 0.000 description 2
- 230000009471 action Effects 0.000 description 2
- 230000004075 alteration Effects 0.000 description 2
- 230000006399 behavior Effects 0.000 description 2
- 239000000470 constituent Substances 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 238000007726 management method Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000012544 monitoring process Methods 0.000 description 2
- 239000003507 refrigerant Substances 0.000 description 2
- 230000000153 supplemental effect Effects 0.000 description 2
- 230000007704 transition Effects 0.000 description 2
- 238000004402 ultra-violet photoelectron spectroscopy Methods 0.000 description 2
- 238000004956 CI calculation Methods 0.000 description 1
- -1 CRAC Substances 0.000 description 1
- 239000003570 air Substances 0.000 description 1
- 238000003491 array Methods 0.000 description 1
- 230000001413 cellular effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000001186 cumulative effect Effects 0.000 description 1
- 125000004122 cyclic group Chemical group 0.000 description 1
- 238000013479 data entry Methods 0.000 description 1
- 238000013523 data management Methods 0.000 description 1
- 238000013500 data storage Methods 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 238000004134 energy conservation Methods 0.000 description 1
- 238000005265 energy consumption Methods 0.000 description 1
- 230000007274 generation of a signal involved in cell-cell signaling Effects 0.000 description 1
- 238000010438 heat treatment Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 239000004973 liquid crystal related substance Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000004806 packaging method and process Methods 0.000 description 1
- 238000007639 printing Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 238000012384 transportation and delivery Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F1/00—Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
- G06F1/16—Constructional details or arrangements
- G06F1/20—Cooling means
- G06F1/206—Cooling means comprising thermal management
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05K—PRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
- H05K7/00—Constructional details common to different types of electric apparatus
- H05K7/20—Modifications to facilitate cooling, ventilating, or heating
- H05K7/20709—Modifications to facilitate cooling, ventilating, or heating for server racks or cabinets; for data centers, e.g. 19-inch computer racks
- H05K7/20836—Thermal management, e.g. server temperature control
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24F—AIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
- F24F11/00—Control or safety arrangements
- F24F11/50—Control or safety arrangements characterised by user interfaces or communication
- F24F11/52—Indication arrangements, e.g. displays
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24F—AIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
- F24F11/00—Control or safety arrangements
- F24F11/50—Control or safety arrangements characterised by user interfaces or communication
- F24F11/61—Control or safety arrangements characterised by user interfaces or communication using timers
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24F—AIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
- F24F11/00—Control or safety arrangements
- F24F11/62—Control or safety arrangements characterised by the type of control or by internal processing, e.g. using fuzzy logic, adaptive control or estimation of values
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24F—AIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
- F24F11/00—Control or safety arrangements
- F24F11/89—Arrangement or mounting of control or safety devices
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/10—Complex mathematical operations
- G06F17/11—Complex mathematical operations for solving equations, e.g. nonlinear equations, general mathematical optimization problems
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2111/00—Details relating to CAD techniques
- G06F2111/10—Numerical modelling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2119/00—Details relating to the type or aim of the analysis or the optimisation
- G06F2119/08—Thermal analysis or thermal optimisation
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2200/00—Indexing scheme relating to G06F1/04 - G06F1/32
- G06F2200/20—Indexing scheme relating to G06F1/20
- G06F2200/201—Cooling arrangements using cooling fluid
Definitions
- aspects and embodiments of the present invention are directed generally to predicting transient cooling performance for a data center.
- Data centers typically house high concentrations and densities of information technology equipment, which is collocated in a structure that provides network connectivity, electrical power, and cooling capacity.
- a raised floor having an air plenum beneath the floor may be used for providing cooling air to the racks. Cool air is distributed from the air plenum to the racks through perforated tiles having open areas.
- multiple rows of equipment are organized into hot air and cold air aisles.
- equipment racks e.g., heat producing equipment
- in-row coolers may be arranged in rows in an alternating front/back arrangement creating alternating hot air and cold air aisles with the front of each row of racks facing the cold aisle and the rear of each row or racks facing the hot aisle.
- equipment in racks, or the racks themselves may be referred to as cooling consumers
- in-row cooling units and/or computer room air conditioners (CRACs) may be referred to as cooling providers.
- CRACs computer room air conditioners
- UPS uninterruptible power supplies
- emergency generators with specified redundancy levels to ensure uninterruptible computing and data storage.
- UPS uninterruptible power supplies
- the cooling system will shut down at least for a short period of time upon power interruption, and sensitive powered electronics may become overheated. Cooling systems typically draw too much power to be supported by UPSs but are usually backed-up by one or more generators.
- cooling equipment such as chillers and Direct Expansion (DX) cooling units require a relatively long time before they can support their rated cooling load following a power interruption. Consequently, electronics may operate for many minutes or tens of minutes until normal cooling has returned.
- most data center designs utilizing "open" power paths) require that the power to cooling equipment be interrupted once again when switching back to primary (utility) power after it is restored. This causes another potentially lengthy delay until cooling equipment can once again return to their full rated cooling loads. Consequently, the timing of the "return to primary power" can also significantly affect the ultimate temperatures experienced by the electronic equipment.
- the methods and systems disclosed herein improve the prediction of air and cooling temperatures, e.g., cooling fluid, in data centers that experience a transient event, such as a utility power failure.
- Maintaining reasonable IT inlet temperatures is a critical design goal, and they are typically a function of the room design, the IT load, the cooling architecture (e.g., the type of air distribution and containment), ambient (external temperatures), as well as the presence and connectivity to UPS devices.
- the cooling runtime which refers to the time period during which critical equipment continues to receive airflow below a specified temperature threshold, is primarily determined by the system stored cooling capacity and the UPS and generator backup system design.
- transient predictions are valuable in efficiently controlling cooling and load in data centers. For instance, accurate transient temperature predictions can enable data center managers to mitigate temperature and load fluctuations with the thermal mass of the system. This aspect is especially useful when combined with the forecasting of transient changes, (e.g., weather-related power outages or cyclic load changes in the data center).
- FIGS. 1 and 2 show models of a chilled water loop and an air loop respectively, for a data center having predominantly in-room cooling architecture with a raised floor plenum.
- the model 102 of the chilled water loop shown in FIG. 1 models the interactions of water streams with a cooling coil 116 of a cooler 115 (i.e., in-room cooling equipment, which in FIG. 1 is a computer room air handler (CRAH) and includes all the coolers in the room to be cooled), a chiller 105, and a water storage tank 110.
- a cooling coil 116 of a cooler 115 i.e., in-room cooling equipment, which in FIG. 1 is a computer room air handler (CRAH) and includes all the coolers in the room to be cooled
- CRAH computer room air handler
- the chilled water is supplied from the chiller 105 by pumps that circulate water through a network of pipes.
- Chilled water 108 leaves the chiller 105 having a temperature of T ch s and enters a storage tank 110, where a certain volume of chilled water is stored to serve as a source of cooling during a transient event, such as a power failure.
- a transient event such as a power failure.
- one or more pumps that pump the chilled water can be powered by a generator or, in some instances, a UPS device (e.g., before a generator provides power).
- Chilled water 108 leaves the chiller 105 and is stored in the storage tank 110. Chilled water from the storage tank 112 having a temperature of T stor then flows through a cooling coil 116 of the cooler 115.
- the return water from the cooler 119 has a temperature of T co . At least a portion of chilled water from the storage tank 110 may also bypass the cooling coil 116 via a bypass loop 118 for control purposes. Water in the bypass loop 118 and the return water from the cooler 119 are mixed together to form the water 106 that returns to the chiller and has a temperature of T ch r .
- the model 104 of the air loop shown in FIG. 2 depicts air flow in the data center.
- the air loop in a chilled water cooling scheme in the example shown in FIG. 2 includes the interaction of air streams with the CRAH mass, the plenum 130, IT equipment 135, the room 120, walls 124, floor 126, and ceiling 122.
- Air 138 from the cooler 115 having a temperature of T s a is introduced to the plenum 130 and mixes with air in the plenum to form air having a temperature of T p .
- Air 140 from the plenum having temperature T p passes through perforated floor tiles (and various leakage paths) into the room 120 as air 140a.
- Air from the plenum 130 having temperature T p (and labeled 140b in FIG.
- Air 144 which flows through IT equipment 135 exits an outlet of the IT equipment 135 as air 146 having a temperature of T IT ex .
- Air 146 exiting the IT equipment 135 with temperature T IT ex enters the room 120 as air 146a. Air 146 exiting the IT equipment 135 with temperature T IT ex also mixes with room air 142 having temperature T rm to form mixed room air 136 having temperature T r a that returns to the cooler 115.
- the model shown in FIG. 2 also indicates that the temperature of the room air T rm is affected by heat transfer through the walls 124 and ceiling 122 to ambient (external to data center).
- the temperature of air in the plenum T p is also affected by heat transfer through the floor 126 to the plenum 130, or other external environment according to alternative configurations.
- the model presented in FIGS. 1 and 2 shows a data center cooling configuration that includes a chilled water system applied to an in-room cooling architecture with a raised floor plenum, but it is to be appreciated that the model may be applied to other configurations as well, which are also within the scope of this disclosure.
- the model may be applied to an in-row cooling architecture where the model does not include a plenum.
- the cooling system may comprise an air-cooled CRAC direct expansion (DX) system that uses a refrigerant or an air system that uses air as the heat transport fluid.
- DX air-cooled CRAC direct expansion
- one or more components of the model may be omitted (and/or different components included).
- the system may also not include a storage tank 110, and instead the water from the chiller 105 may go directly to the cooler 105 and/or bypass loop 118.
- the analysis used in the model can be applied to other applications and computing environments besides data centers (in a building), such as containers, modular systems, general IT environments, battery rooms, etc.
- FIG. 3 A combined model 103 of the air and water loops presented in FIGS. 1 and 2 is shown in FIG. 3 .
- the combined model 103 shows how a chilled-water system is modeled as a combined system of heat added (IT equipment 135), heat removed (chiller 105), fluids (air and water), masses (chiller 105, cooler 115, IT equipment 135, room 120, plenum 130, walls 124, floor 126, ceiling 122, water storage 110), and outside temperatures (applied to the walls, ceiling, and floor).
- a set of energy balance and heat transfer equations can be derived for the different components (control volumes) of the data center model, including the chiller 105, water storage tank 110, cooling coil 116, cooler 115, plenum 130, IT equipment 135, and the room 120, as well as the floor 126, ceiling 122, and walls 124 of the room 120.
- thermal mass generally describes a material's resistance to change in temperature, and is the product of its mass and specific heat. Furthermore, the "usefulness” or “availability” of the thermal mass depends on the intimacy of thermal contact the material has with its surroundings.
- the thermal mass of the cooler is accounted for and represented by the term on the right side of Equation (8) below, the thermal mass of the chiller is represented by the last term on the right side of Equation (1) below, and the thermal mass of the plenum air is represented by the last term on the right side of Equation (11) below.
- the thermal mass of other components, such as the water storage, room air, IT equipment, floor, ceiling, and walls are also included in Equations (3), (12), (14), (16), (17), and (18), respectively, below.
- Equation (1) represents an energy balance equation for the chiller 105, which indicates that the chilled water supply temperature T ch s can be expressed as a function of the energy removed by the chiller, the mass of the chiller, and the temperature of the chiller mass as indicated below:
- the chiller is the only location for heat to leave the water loop of FIG. 1 .
- the chiller may lack the ability to remove heat for multiple reasons, which include power failures, during periods of time the chiller is restarting, and during times when the chiller undergoes open starting, when the chiller switches power sources from a local power supply to utility power, which are all examples of transient events.
- the use of the term representing the heat removed by the chiller q ⁇ ch in Equation (1) allows for the ability to control the supply temperature of the chiller water as a function of the capacity of the chiller and to model power outages or restarts (i.e., transient event).
- Chiller downtime can be modeled by setting the chiller cooling power q ⁇ ch to be zero when the chiller is disconnected from primary power (i.e., off) or undergoing a restart process (which usually takes about 5-15 minutes).
- Equation (2) the thermal effectiveness of the chiller in Equation (2) below:
- the water storage tank 110 may be modeled as a well-mixed volume of water.
- the energy balance on the water storage tank 110 can be expressed as shown below in Equation (3):
- the water storage is bypassed, and water from the chiller 105 may be sent directly to the cooler 115 and/or bypass loop 118.
- a data center operator may wish to bypass the water storage tank 110 upon restart of the chiller 115 after a transient event.
- T stor of Equation (3) is replaced with T ch s .
- the cooling coil 116 of the cooler 115 controls the heat transferred from the airside to the water side by the cooler 115.
- the air ratio AR should be greater than 1.
- the thermal effectiveness of the cooling coil can be estimated using technical information from the cooler manufacturer.
- the cooler's ability to handle different cooling loads can be modeled by changing the mass flow rate of water through the cooling coil ⁇ cc within the expression c p H 2 O m ⁇ cc T co ⁇ T stor (i.e., the right side of Equation (4)).
- the mass flowrate of water through the cooling cool, ⁇ cc must be less than or equal to the flowrate through the chiller, ⁇ ch (see Equations (1) and (3)), which is utilized below when solving for the unknown terms in the system
- Equations A-C may be used in alternate embodiments to describe the heat transfer between the solid cooling coil and the two fluid streams in lieu of the approach described above, which incorporates the thermal effectiveness of the cooling coil.
- the thermal effectiveness of the cooler ⁇ CRAH is assumed to be a known constant.
- the thermal effectiveness of the cooler may have a value in a range of about 0.7 - 0.9.
- Air returns to the CRAH (cooler 115) at temperature T r a , and is expressed in Equation 10 as being a linear combination of room and IT equipment exhaust temperatures, T rm and T IT ex , respectively: T r a 1 ⁇ HACI AR T rn + HACI AR T IT ex
- the hot aisle capture index (HACI) is described in further detail below.
- Equation (12) represents the energy balance equation for the room 120, which includes the thermal mass of room air, airflow streams from the plenum and IT equipment, and heat transfer through the walls and ceiling: c p a T p AR ⁇ CACI m ⁇ IT + c p a T IT ex 1 ⁇ HA
- Equation (12) characterizes the room airflow patterns with a flow network model that includes the air ratio AR, hot aisle capture index, and cold aisle capture index.
- the cold aisle capture index (CACI) for the IT equipment is defined as the fraction of air ingested by the IT equipment which originates from local cooling sources (e.g., air from the plenum 130 through the perforated floor tiles in FIG. 2 , but in other embodiments may be a local cooler, such as a CRAC).
- the hot aisle capture index (HACI) is defined as the fraction of air exhausted by the IT equipment which is captured by local extracts (e.g., cooler 115 in FIG. 2 , or return vents in other embodiments).
- the values for the hot aisle and cold aisle capture indices may be determined based on the discussion in U.S. Patent No. 7,991,592 (referred to herein as “the '592 patent”) and U.S. Patent No. 8,972,217 (referred to herein as “the '217 patent”).
- the ⁇ 592 patent to track the airflow from each rack (IT equipment), one concentration species C i is used to individually identify the exhaust air from each rack in a detailed CFD simulation.
- the hot aisle capture index calculation depends on the rack (and cooler) airflow rates. The difference arises because while both variants of CI are defined with respect to rack airflow rates, the computed values of interest in cold-aisle analyses are rack-inlet concentrations while those in hot-aisle analyses are cooler-inlet concentrations.
- f ij and g ij may form the building blocks of HACI and CACI respectively, and they can function to characterize the multiple airflow streams which combine to make-up a rack's inlet and exhaust airflow patterns.
- HACI and CACI values for IT equipment racks e.g., as computed by detailed CFD simulation, but as noted below, IT equipment in the present model is modeled as one lumped instance of the equipment rack.
- the HACI and CACI values for the model may also reflect an aggregate value, where all of the IT equipment racks are modeled as having the same value.
- the IT equipment model exemplified in Equations (13-15) indicates that the IT equipment is modeled as one lumped instance of the equipment rack.
- the model assumes that all racks in the room may be combined into one, unified rack object having the cumulative properties of all the racks. Similarly, all cooling supplies in the room may be combined into one cooling object.
- the values of HACI and CACI may be adjusted for different data center architectures and provide the specific value for IT inlet and cooler return temperatures without having to perform a full Computational Fluid Dynamics (CFD) analysis.
- CFD can, in theory, provide a desired level of detail but it is typically extremely slow, expensive, often inaccessible, and doesn't always converge to a consistent result.
- Equation I may be used in alternate embodiments to describe the heat transfer between the IT equipment and the room air in lieu of the approach described above, which incorporates the thermal effectiveness of the IT equipment.
- Equation (16) T p ⁇ T f R ft " + R f " 2 ⁇ T f ⁇ T amb f R f 0 " + R f " 2 + M f c p f dT f dt
- Equation (17) T rm ⁇ T c R ci " + R c " 2 ⁇ T c ⁇ T amb c R co " + R c " 2 + M o c p c dT c dt
- Equations (1)-(18) completely characterize the air and water systems under transient scenarios, e.g., a power outage.
- non-linear terms e.g., Equations (1), (3), (8), (11), (14)
- Two adjustments can be made to the model to decrease the computational complexity involved with solving non-linear systems by linearizing the set of equations.
- the first adjustment makes the recognition that the flowrate through the cooling coil ⁇ cc and the capacity of the chiller q ⁇ ch do not change instantaneously, and are also generally free variables when not at their limiting values. If the simulation includes enough time steps, or the time steps are sufficiently small, then the heat removed by the chiller q ⁇ ch and the mass flowrate of water through the cooling coil ⁇ cc do not have to be solved for explicitly, and can instead be estimated using the result from the previous time step.
- the derivative terms associated with the thermal mass can thus be approximated with a forward differences discretization.
- the derivative terms may be discretized using an approximation of the form: dT dt ⁇ T ⁇ T prev ⁇ t where ⁇ t represents a finite duration of time (the "time step").
- Equations (1)-(18) can then be solved in an iterative manner.
- the second adjustment allows for the capacity of the cooler (controlled by limiting ⁇ cc ⁇ ⁇ ch in Equation (4)) and the capacity of the chiller (controlled by capping q ⁇ ch in Equation (1)), must be enforced at every time step, creating piecewise linear equations for Equations (1) and (4). Since these equations are monotonic as temperatures increase, the system temperatures can be solved by first assuming capacities are not met and then iteratively changing Equations (1) and (4) if the resulting temperatures force the chiller or cooler to reach its maximum capacity. This approach is shown in the process 400 of FIG. 4 . Implementation of process 400 avoids the use of external nonlinear solution packages, which can be slow and unstable.
- Process 400 of FIG. 4 begins at 452, where the transient equations, i.e., temperature values, are solved for time step "t." Any one of a number of different software codes may be used to solve the 18 equations simultaneously and to obtain the temperature values for that particular time step.
- a determination is made as to whether the chiller capacity has been exceeded. If no, then the process continues to 460. If yes, then q ⁇ ch of Equation (1) is replaced by the maximum capacity of the chiller q ⁇ ch max at 454 and the process continues to 460.
- a determination is made as to whether the cooler capacity has been exceeded. If no, then the process continues to 464.
- the results obtained from solving the set of energy balance and heat transfer equations associated with the model described above may be used to predict temperatures in the data center, including the inlet temperature to at least one equipment rack and/or an outlet temperature of cooling fluid (e.g., air, water), associated with the cooling equipment.
- the results may also be used to calculate a cooling runtime for the data center.
- the model may be used for optimizing the transient performance of one or more components of the data center, such as the cooler, and may be used for adjusting one or more operating parameters of equipment in the data center, such as the equipment racks and/or cooling providers. For instance, a flowrate of a fluid (water, refrigerant, air) associated with a cooler may be adjusted, or electrical power associated with at least one equipment rack may be adjusted.
- the operating parameter may include adjusting a source of electrical power provided to equipment in the data center.
- equipment can be switched from one power source (e.g., utility power, generator) to another power source (e.g., generator, UPS).
- the operating parameter may be associated with starting a generator or UPS device.
- the adjustment may be performed to ensure that sufficient cooling is provided such that the maximum temperature of the data center or its components is not exceeded.
- the adjustment may be performed for conserving energy or otherwise minimizing energy consumption.
- a design of a data center may be altered based on the results of the model, such as a predicted temperature.
- a user of the data center design and management system may change the location of coolers or the types of coolers that are used in the actual layout of equipment or the proposed layout of equipment in the data center. These alterations may be implemented to improve the cooling performance and/or may be implemented to provide cost and/or power savings when the performance is found to be within predetermined specifications.
- the results from the model may also be used to generate or otherwise provide a display or other type of visualization, such as those described herein in reference to FIG. 5 on a display device.
- the temperature prediction profiles generated from the model may be displayed to a user, and can be used for monitoring or controlling one or more components of the data center.
- temperature predictions and/or a cooling runtime can be used for controlling cooling equipment or equipment racks by a user or by a controller.
- the results from the model may be displayed as part of the implementation of a design system.
- the model may be incorporated into a data center design system, which may be a stand-alone tool or may be built into a data center design platform, including a web-based software tool.
- This design aspect may be used to guide data center personnel through activities such as designing the data center structure, positioning equipment within the data centers prior to installation and repositioning equipment after construction and installation are complete.
- the design and accompanying analysis may allow the user to create models of data center configurations from which performance metrics (e.g., inlet and outlet temperatures of equipment racks and/or coolers) may be determined. Both the system and the user may then employ these performance metrics to determine alternative systems configurations that meet various design objectives.
- performance metrics e.g., inlet and outlet temperatures of equipment racks and/or coolers
- An optimized design can thus be obtained, and the results of the model may be used as part of a system to implement the design, e.g., to order equipment, ship equipment, and/or install equipment in a data center as per the optimized designed layout.
- the design of an existing data center may also be altered based on the results of the model. For instance, a user may change the location of components and/or cooling equipment to improve the performance of the data center, such as by reducing power consumption or other cost savings when the performance is found to be within predetermined specifications.
- the results from the model may be used to provide warnings, error messages, or other information to a user (e.g., data center manager) via an interface such as a display device.
- a warning could be provided regarding the cooling runtime value or hot spots in the data center.
- assessments, suggestions or recommendations may be provided to a user, such as suggestions for improving the performance of the data center, such as by achieving additional cooling capacity (e.g., "install chilled water storage” or “power chilled-water pumps using UPS” or “power cooler fans to UPS”), or taking preventative measures before external events, such as weather forecasts, affect the power distribution.
- the system may suggest lowering the air supply temperatures, and in some instances, may take automatic action by controlling the air supply temperature in anticipation of such an external event.
- a controller may be programmed or instructed by a user to execute an automatic "power-down" protocol after a transient event such as a loss of power.
- the model may be updated in real time with this information to provide an updated cooling runtime.
- one or more sensors e.g., IT load, available cooling power, temperature data
- one or more sensors positioned in an existing data center may be used in combination with the model of the data center.
- the sensors may be used to measure operating data of the data center, such as temperature, humidity, power consumption, pressure, airflow, flowrate, etc.
- the sensors may measure the flowrate of cooling fluid (e.g., water), the temperature of air exiting the IT equipment, the temperature of air exiting the cooler and/or plenum, the IT load (e.g., power consumption), available cooling power, the room temperature, etc.
- the measurement data may be compared against predicted values output by the model to verify and calibrate the model.
- the measured values may be used to calibrate transient or steady-state physical parameters of the model, such as capture indices, thermal resistances, etc.
- the model may be calibrated via one or more calibration parameters using one or more measurements. For instance, measurement data may be obtained during transient events, such as temperature data, power consumption data, airflow data, chilled water data, etc. and then stored as historic transient event data in a database or other storage device. The model may then be calibrated based on the historic transient event data.
- a calibration parameter may be applied to one or more estimated thermal mass values (e.g., see Table 2 below) of the model. For instance, a thermal mass calibration parameter may be applied to one or more of the thermal mass of the IT equipment, cooler, water storage, room air, plenum air, floor, ceiling, and walls. In some instances a different calibration parameter may be applied to each thermal mass.
- the model may be re-calibrated as new historic transient event data is obtained.
- the rise in air temperatures will not be slowed by mass in the CRAH (cooler 115) and the cooling loop will not have any effect.
- the AR, CACI, HACI, and the mass flow rate of the chiller ⁇ ch are changed over time, such that:
- the performance of different cooling technologies will influence the values for the HACI and CACI used in Equations (10), (12), and (13).
- Table 1 below lists the coefficients for 13 different combinations of cooling and containment architectures.
- Table 1 Coefficients for Various Combinations of Cooling and Containment Architectures Air Distribution Containment f CACI f HACI (1) Raised floor none 0.7 0 (2) Raised floor hot aisle 0.7 0.9 (3) Raised floor cold aisle 0.9 0 (4) Raised floor with dropped ceiling return none 0.7 0.7 (5) Raised floor with dropped ceiling return hot aisle 0.7 0.9 (6) Raised floor with dropped ceiling return cold aisle 0.9 0.7 (7) Close-coupled none 0.8 0.8 (8) Close-coupled hot aisle 0.8 0.9 (9) Close-coupled cold aisle 0.9 0.8 (10) Flooded supply none 0.5 0 (11) Flooded supply hot aisle 0.5 0.9 (12) Flooded supply with dropped ceiling return none 0.5 0.7 (13) Flooded supply with dropped ceiling return hot aisle 0.5 0.9
- a mechanism e.g., duct, perforated tile, cooling unit placed within IT rows
- a targeted area e.g., 3 meters
- Raised floor air distribution system is a contained supply, where the IT equipment supply air flow is completely enclosed to eliminate air mixing between the supply and the return air streams. Table 1 includes different combinations of air distribution and containment.
- the transient event used as the backdrop in discussing the above model focused on a power outage that created a complete loss of cooling capacity and predicting the resulting temperatures. It is to be appreciated that other types of transient events and their effects are also within the scope of this disclosure.
- the model may be used to predict the effect of partial cooling failures, as well as the implementation of quick-starting chillers, the usage of equipment with multiple cooling mechanisms, such as indirect air economizers with supplemental direct expansion (DX), and the effect of transient IT load or battery charging/discharging losses on temperatures.
- DX direct expansion
- FIGS. 5A-5C shows the location of where heat is both released and absorbed into the data center by the IT equipment, the chilled water, the thermal mass of the chiller, and the ambient external environment, at three different time periods, and are discussed in further detail below.
- the results shown in FIGS. 5A-5C can be compiled by a computer processor and displayed to a user, and/or can be used for monitoring or controlling one or more components of the data center.
- FIG. 5A is a steady state condition where heat energy (e.g., 100 kW) is released by the IT equipment.
- heat energy e.g. 100 kW
- An equal amount of heat energy is absorbed by the chilled water of the cooler and the ambient environment through heat transfer processes.
- a larger portion of the heat is absorbed by the chilled water of the cooling system and the remaining smaller portion is absorbed by the ambient environment through the walls, floor, and ceiling of the room.
- FIG. 5B is a loss of cooling scenario, where a power outage has affected the cooling equipment.
- FIG. 5B shows the heat release and absorption data in the system 10 minutes after the power outage. 100 kW of heat energy is still being released by the IT equipment (since the IT equipment is being powered by UPS devices). An equal amount of heat energy is absorbed by the chilled water, ambient environment (i.e., through the ceiling, floor, and walls of the room), and the thermal mass of the room's floor, ceiling, walls, room air, IT equipment, plenum air, and cooling coil.
- FIG. 5C is a recovery scenario, where power has been restored to the cooling equipment.
- FIG. 5C shows the heat release and absorption data in the system 20 minutes after the power outage. 150 kW of heat energy is released, because not only is 100 kW of heat energy expended by the IT equipment, but during the power outage the thermal mass of the room's floor, ceiling, walls, and air, and the plenum air and cooler absorbed heat, which is now being released. Most of the heat is absorbed by the chilled water of the cooler and the remainder is absorbed by the ambient environment via heat transfer.
- FIGS. 5A-5C are not exhaustive.
- graphs or charts of the changes of energy flow as a function of time may be displayed, or data may be displayed with greater detail, such as by indicating the individual contributions of the ceiling, floor, and walls to ambient, or by indicating the individual contributions of each thermal mass component, e.g., plenum air, room air, IT equipment, cooler, and building components (e.g., walls, ceiling, floor, etc.).
- FIG. 6 shows a data entry and results screen 600 that may be used with one embodiment to allow a user to enter and manipulate data to obtain predicted results as part of a simulation.
- the simulation may be used for optimizing the transient performance of one or more components of the data center, such as the cooler, and may be used for adjusting one or more operating parameters of equipment in the data center, such as the equipment racks and/or cooling providers.
- the screen 600 includes an input 650 section for inputting data that describes the data center, including the type of architecture used.
- One example input subsection is for the data center architecture 652, where data regarding the cooling system (e.g., chilled water, CRAC, air system, etc.), air distribution (e.g., raised floor, close-coupled, flooded, etc.), containment (e.g., none, hot aisle, cold aisle), white space area, ceiling height, total heat load, the number of racks, the rack U space utilization (e.g., 0-100%), and the average rack density.
- Another example input subsection is for data regarding the cooling equipment 654. The example shown in FIG.
- the cooling equipment input 654 also includes an option for bypassing the storage tank during startup. In this instance, chilled water 108 from the chiller in FIG. 1 would bypass the storage tank 110, which would enter the cooler 115 and/or the bypass line 118 with a temperature of T ch s instead of T stor for a predetermined length of time.
- the equipment start time input 656 includes data regarding the generator start time (i.e., the period of time after a utility power outage is detected that the generator powers on), the chiller start time (i.e., the period of time that the chiller takes to start up once it receives power), the restart time configuration, as well as connectivity information, such as if cooling equipment including the cooler fans and chilled water pumps are connected to UPS devices.
- the restart time configuration can be open or closed (when utility power is restored).
- a "closed" or “closed transition” start configuration means that there is a mechanism (e.g., electronic) that automatically puts the generator voltage in sync with line power which allows the chiller to switch back from generator power to utility power instantaneously without having to undergo a complete restart again.
- an "open” or “open transition” start configuration means that there is no such synchronizing hardware or mechanism, and the chiller needs to be disconnected from generator power before being switched over to utility power. Thus, the chiller will have to undergo a complete restart again, which has the potential of extending the period of time that cooling power is not available (e.g., a few more minutes).
- a simulation input subsection 658 may also be used to provide parameters for the simulation, such as the simulation time, and the allowable maximum temperature of data center air (e.g., room, inlet, and return air temperatures), as well as temperature gradient options.
- parameters for the simulation such as the simulation time, and the allowable maximum temperature of data center air (e.g., room, inlet, and return air temperatures), as well as temperature gradient options.
- calculations are run in real-time as the user enters or changes data in the entry boxes of the input section 650 with results also shown in real-time.
- the ability to manipulate the data and view the results in real-time allows a user to easily consider tradeoffs when designing or upgrading a data center. This allows the user to design data infrastructures to make sure the required maximum allowable temperature of IT equipment will not be exceeded during a transient event.
- calculations may be performed in real-time as the user enters or changes data in the input section 650 and may be displayed in a results section 660.
- the example results section 660 shown in FIG. 6 includes a temperature graph that provides plots of temperature versus time for several temperature values in the data center.
- different temperature parameters or other parameters may be plotted.
- the heat flow visualization data shown in one or more of FIGS. 5A-5C may be shown.
- four temperature plots are shown on the graph, including the IT equipment inlet air temperature (e.g., T IT in of FIG. 2 ), the cooler return air temperature (e.g.,T r a of FIG. 2 ) and the cooler supply air temperature (e.g., T s a of FIG. 2 ), as well as the maximum allowable temperature for the room, which is set at 33 °C from input 658.
- the results 660 of the simulation shown in FIG. 6 indicate that the temperature of the inlet air temperature to the IT equipment and the temperature of the air supplied to the cooler both increase almost immediately after the power goes out since the IT equipment is powered by the UPS, but the power to the fans, pumps, and chillers is not enabled (for at least the first 50 seconds until the generator starts).
- the generator Once the generator is turned on, power is provided to the fans and pumps of the cooling system, which allows the thermal mass of the water in the pipes and storage tank to be utilized, and the temperatures start to decrease.
- the chiller is still powered off for the first 15 minutes, so the cooling effect created by the thermal mass of the circulating water is eventually depleted and the temperatures start to increase again.
- the cooling effect allows the temperatures to decrease again and stabilize in about 38 minutes.
- the most fluctuation in temperature is predicted for the temperature of the air supplied to the cooler, and the least fluctuation in temperature is predicted for the cooler return air temperature.
- the performance of assessments and calculations in real-time refers to processes that are completed in a matter of a few seconds or less rather than several minutes or longer as can happen with complex calculations, such as those involving typical CFD calculations.
- a design of a data center and/or actual operating parameters in a data center are altered based on predicted temperature and/or airflow and/or the change in temperature and/or airflow upon the occurrence of a transient event, such as a power failure, in a data center.
- a user of the data center design and management system may change the location of coolers or the types of coolers that are used in the actual layout of equipment or the proposed layout of equipment in the data center. These alterations may be implemented to improve the cooling performance and/or may be implemented to provide cost and/or power savings when the performance is found to be within predetermined specifications.
- a data management system in accordance with one embodiment, may control one or more cooling providers to adjust the airflow, and/or control power to reduce power to one or more equipment racks if the airflow is not adequate to provide sufficient cooling.
- tools and processes are provided for determining temperatures and airflows in a data center.
- the tools and processes may be used in other types of facilities, and may also be used in mobile applications, including mobile data centers.
- a controller or processor implemented as part of a computing system as discussed in further detail below may be located in or used as part of a mobile data center to monitor and control various aspects of the data center, such as one or more operating parameters (e.g., cooling settings, flowrates, etc.).
- the controller may be configured to predict either a transient event and/or effects of a transient event, and incorporate or otherwise implement this information with the model in managing and controlling the data center.
- one or more of the methods disclosed herein may be implemented on a computerized control system.
- Various aspects may be implemented as specialized software executing in a general-purpose or specialized computer system 700 such as that shown in FIG. 7 .
- the computer system 700 may include a processor 703 (also referred to herein as a controller) connected to one or more memory devices 717, such as a disk drive, solid state memory, or other device for storing data.
- Memory 717 is typically used for storing programs and data during operation of the computer system 700.
- the processor 703 may be any device capable of executing a set of instructions (sequential or otherwise) that specify actions to be taken by that processing device. Further, while a single processor is illustrated, the term "processor” shall also be taken to include any collection of processors that individually or jointly execute a set (or multiple sets) of instructions to perform any one or more of the methodologies discussed herein.
- Components of computer system 700 may be coupled by an interconnection mechanism 707 (also referred to herein as an interconnect system), which may include one or more busses (e.g., between components that are integrated within a same machine) and/or a network.
- the interconnection mechanism 707 enables communications (e.g., data, instructions) to be exchanged between system components of system 700.
- Computer system 700 includes one or more input devices 709, for example, a keyboard, mouse, trackball, microphone, a disk drive unit, a signal generation device (e.g., a speaker or remote control), or touch screen that functions as an interface through which a user may issue commands, data input, or programming to the system 700.
- the computer system 700 may include or be coupled to or in communication with one or more input devices 709 configured to communicate with facility systems 719 of a facility, for example, equipment associated with a data center, such as cooling equipment or IT equipment.
- Computer system 700 includes one or more output devices 721, for example, a printing device, speaker, and/or display devices, such as a display screen (e.g., a liquid crystal displays (LCD), a flat panel, a solid state display, or a cathode ray tube (CRT)).
- the computer system 700 may include or be coupled to or in communication with the interconnection mechanism 707 to provide control signals to adjust one or more operating parameters of facility systems 719 of a facility.
- One or more sensors 713 may also provide input to the computer system 700. These sensors may include, for example, sensors which are capable of or are configured to measure one or more parameters external or internal to the data center, such as temperature, humidity, flow rate, airflow, solar intensity, power, flowrate, etc.
- computer system 700 may contain one or more interfaces (not shown) that connect computer system 700 to a communication network in addition to or as an alternative to the interconnection mechanism 707. These interfaces may be utilized by the central processing unit to collect data, for example, weather or solar data, from an external source such as a weather reporting service web site on the Internet.
- the storage system 711 typically includes a computer readable and writeable nonvolatile recording medium 823 in which signals are stored that define a program to be executed by the processor or information to be processed by the program.
- the medium may include, for example, a disk or flash memory.
- the processor causes data to be read from the nonvolatile recording medium 823 into another memory 825 that allows for faster access to the information by the processor than does the medium 823.
- This memory 825 is typically a volatile, random access integrated circuit memory such as a dynamic random access memory (DRAM) or static memory (SRAM). It may be located in storage system 711, as shown, or in memory system 717.
- DRAM dynamic random access memory
- SRAM static memory
- the processor 703 generally manipulates the data within the integrated circuit memory 717 and then copies the data to the medium 723 after processing is completed.
- a variety of mechanisms are known for managing data movement between the medium 823 and the integrated circuit memory element 717, and embodiments disclosed herein are not limited to any particular data movement mechanism. Embodiments disclosed herein are not limited to a particular memory system 717 or storage system 711.
- the computer system may include specially-programmed, special-purpose hardware, for example, an application-specific integrated circuit (ASIC).
- ASIC application-specific integrated circuit
- Embodiments disclosed herein may be implemented in software, hardware or firmware, or any combination thereof. Further, such methods, acts, systems, system elements and components thereof may be implemented as part of the computer system described above or as an independent component.
- computer system 700 is shown by way of example as one type of computer system upon which various embodiments disclosed herein may be practiced, it should be appreciated that the embodiments disclosed herein are not limited to being implemented on the computer system as shown in FIG. 7 . Various embodiments disclosed herein may be practiced on one or more computers having a different architecture or components that that shown in FIG. 7 .
- Computer system 700 may be a general-purpose computer system that is programmable using a high-level computer programming language. Computer system 700 may be also implemented using specially programmed, special purpose hardware.
- processor 703 is typically a commercially available processor such as the well-known Pentium TM or Core TM class processors available from the Intel Corporation. Many other processors are available.
- Such a processor usually executes an operating system which may be, for example, the Windows 7 or Windows 8 operating system available from the Microsoft Corporation, the MAC OS System X available from Apple Computer, the Solaris Operating System available from Sun Microsystems, or UNIX available from various sources. Many other operating systems may be used.
- the processor and operating system together define a computer platform for which application programs in high-level programming languages are written. It should be understood that embodiments disclosed herein are not limited to a particular computer system platform, processor, operating system, or network. Also, it should be apparent to those skilled in the art that the embodiments disclosed herein are not limited to a specific programming language or computer system. Further, it should be appreciated that other appropriate programming languages and other appropriate computer systems could also be used.
- One or more portions of the computer system may be distributed across one or more computer systems (not shown) coupled to a communications network. These computer systems also may be general-purpose computer systems. For example, various embodiments disclosed herein may be distributed among one or more computer systems configured to provide a service (e.g., servers) to one or more client computers, or to perform an overall task as part of a distributed system. For example, various embodiments disclosed herein may be performed on a client-server system that includes components distributed among one or more server systems that perform various functions according to various embodiments.
- a service e.g., servers
- These components may be executable, intermediate (e.g., IL) or interpreted (e.g., Java) code which communicate over a communication network (e.g., the Internet) using a communication protocol (e.g., TCP/IP).
- a communication network e.g., the Internet
- a communication protocol e.g., TCP/IP
- one or more components of the computer system 700 may communicate with
- a wireless network including, for example, a cellular telephone network.
- embodiments disclosed herein are not limited to executing on any particular system or group of systems. Also, it should be appreciated that embodiments disclosed herein are not limited to any particular distributed architecture, network, or communication protocol.
- Various embodiments may be programmed using an object-oriented programming language, such as SmallTalk, Java, C++, Ada, or C# (C-Sharp). Other object-oriented programming languages may also be used. Alternatively, functional, scripting, and/or logical programming languages may be used.
- Various embodiments disclosed herein may be implemented in a non-programmed environment (e.g., documents created in HTML, XML or other format that, when viewed in a window of a browser program, render aspects of a graphical-user interface (GUI) or perform other functions).
- GUI graphical-user interface
- Various embodiments disclosed herein may be implemented as programmed or non-programmed elements, or any combination thereof.
- Dedicated hardware implementations including, but not limited to, application specific integrated circuits, programmable logic arrays and other hardware devices can likewise be constructed to implement the methods described herein.
- Applications that may include the apparatus and systems of various embodiments broadly include a variety of electronic and computer systems. Some embodiments implement functions in two or more specific interconnected hardware modules or devices with related control and data signals communicated between and through the modules, or as portions of an application-specific integrated circuit.
- example systems are applicable to software, firmware, and hardware implementations.
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Engineering & Computer Science (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Mechanical Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Mathematical Physics (AREA)
- Combustion & Propulsion (AREA)
- Geometry (AREA)
- Human Computer Interaction (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Thermal Sciences (AREA)
- Microelectronics & Electronic Packaging (AREA)
- Data Mining & Analysis (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Evolutionary Computation (AREA)
- Algebra (AREA)
- Databases & Information Systems (AREA)
- Software Systems (AREA)
- Fuzzy Systems (AREA)
- Operations Research (AREA)
- Signal Processing (AREA)
- Air Conditioning Control Device (AREA)
- Cooling Or The Like Of Electrical Apparatus (AREA)
Claims (16)
- Un procédé comprenant :le fait de recevoir des données d'entrée relatives à un centre de données qui comprend au moins un bâti d'équipement et au moins un fournisseur de refroidissement, les données d'entrée incluant des informations d'architecture de centre de données, des données de construction, des données de fonctionnement, et un temps parmi un temps de redémarrage en démarrage fermé et un temps de redémarrage en démarrage ouvert pour l'au moins un fournisseur de refroidissement, le temps de redémarrage en démarrage fermé incluant une synchronisation d'une tension de générateur avec une puissance de ligne après rétablissement de la puissance d'utilité, le temps de redémarrage en démarrage ouvert excluant la synchronisation ;le fait de générer, par un dispositif informatique, un modèle incluant les données d'entrée et un ensemble d'équations d'équilibre d'énergie et d'échange de chaleur pour le centre de données qui rendent compte de la chaleur ajoutée par l'au moins un bâti d'équipement et retirée par l'au moins un fournisseur de refroidissement, et d'une masse thermique de l'au moins un bâti d'équipement et d'une masse thermique de l'au moins un fournisseur de refroidissement, le modèle étant configuré pour prédire au moins une température dans le centre de données pendant un événement transitoire ; etle fait de commander un dispositif d'affichage pour afficher l'au moins une température prédite.
- Le procédé de la revendication 1, dans lequel l'au moins une température prédite inclut une température d'admission dans l'au moins un bâti d'équipement et une température de sortie du fluide de refroidissement associées à l'au moins un fournisseur de refroidissement.
- Le procédé de la revendication 1, dans lequel les données de construction incluent des données de résistance thermique d'un plafond, de murs et d'un plancher du centre de données, et dans lequel l'ensemble d'équations d'équilibre d'énergie et d'échange de chaleur pour le modèle rendent compte de l'échange de chaleur entre au moins un élément parmi le plafond, les murs, et le plancher du centre de données et un environnement externe au centre de données.
- Le procédé de la revendication 1, dans lequel les données d'entrées incluent une donnée parmi une efficacité thermique de l'au moins un bâti d'équipement et de l'au moins un fournisseur de refroidissement.
- Le procédé de la revendication 1, dans lequel l'ensemble d'équations d'équilibre d'énergie et d'échange de chaleur utilisent une approximation linéaire par morceaux pour prédire l'au moins une température.
- Le procédé de la revendication 1, comprenant en outre le fait de calculer un temps d'exécution de refroidissement sur la base du modèle et d'afficher le temps calculé d'exécution de refroidissement sur le dispositif d'affichage.
- Le procédé de la revendication 1, comprenant en outre le fait de collecter des données de fonctionnement à l'aide d'au moins un capteur positionné dans le centre de données, les données de fonctionnement collectées incluant au moins une mesure parmi une mesure de puissance et une mesure de débit de refroidissement.
- Le procédé de la revendication 1, comprenant en outre le fait de régler un paramètre de fonctionnement d'un équipement dans le centre de données sur la base du modèle, le paramètre de fonctionnement incluant une source de puissance électrique fournie à l'équipement dans le centre de données.
- Le procédé de la revendication 1, comprenant en outre le fait de mettre en oeuvre une conception du centre de données sur la base de l'au moins une température prédite.
- Un système, comprenant :un dispositif de stockage ;un dispositif d'affichage ;un organe de commande couplé au dispositif de stockage et au dispositif d'affichage et configuré pour :recevoir des données d'entrée en provenance du dispositif de stockage relatives à un centre de données qui inclut au moins un bâti d'équipement et au moins un fournisseur de refroidissement, les données d'entrée incluant des informations d'architecture de centre de données, des données de construction, des données de fonctionnement, et un temps parmi un temps de redémarrage en démarrage fermé et un temps de redémarrage en démarrage ouvert pour l'au moins un fournisseur de refroidissement, le temps de redémarrage en démarrage fermé incluant une synchronisation d'une tension de générateur avec une puissance de ligne après rétablissement de la puissance d'utilité, le temps de redémarrage en démarrage ouvert excluant la synchronisation ;générer un modèle incluant les données d'entrée et un ensemble d'équations d'équilibre d'énergie et d'échange de chaleur pour le centre de données qui rendent compte de la chaleur ajoutée par l'au moins un bâti d'équipement et retirée par l'au moins un fournisseur de refroidissement, et d'une masse thermique de l'au moins un bâti d'équipement et d'une masse thermique de l'au moins un fournisseur de refroidissement, le modèle étant configuré pour prédire au moins une température dans le centre de données pendant un événement transitoire ; etcommander le dispositif d'affichage pour afficher l'au moins une température prédite.
- Le système de la revendication 10, dans lequel l'au moins une température prédite inclut une température d'admission dans l'au moins un bâti d'équipement et une température de sortie de fluide de refroidissement associées à l'au moins un fournisseur de refroidissement.
- Le système de la revendication 10, dans lequel l'ensemble d'équations d'équilibre d'énergie et d'échange de chaleur pour le modèle rendent compte de l'échange de chaleur entre au moins un élément parmi le plafond, les murs, et le plancher du centre de données et un environnement externe au centre de données.
- Le système de la revendication 10, comprenant en outre une interface couplée au dispositif de stockage et configurée pour recevoir des données d'entrée.
- Le système de la revendication 10, dans lequel le dispositif de commande est en outre configuré pour générer un profil de perte de chaleur et de génération de chaleur pour un laps de temps suivant l'événement transitoire et pour commander le dispositif d'affichage afin qu'il affiche le profil généré de perte de chaleur et de génération de chaleur.
- Le système de la revendication 10, comprenant en outre au moins un capteur positionné dans le centre de données et configuré pour mesurer des données de fonctionnement qui sont incluses dans les données d'entrée stockées sur le dispositif de stockage.
- Un support lisible par ordinateur comprenant des instructions qui, lorsqu'elles sont exécutées par un ordinateur, amènent l'ordinateur à effectuer le procédé de n'importe lesquelles des revendications 1 à 9.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US15/841,599 US10817033B2 (en) | 2017-12-14 | 2017-12-14 | Method and system for predicting effect of a transient event on a data center |
Publications (2)
Publication Number | Publication Date |
---|---|
EP3500078A1 EP3500078A1 (fr) | 2019-06-19 |
EP3500078B1 true EP3500078B1 (fr) | 2023-07-26 |
Family
ID=64559443
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP18208531.6A Active EP3500078B1 (fr) | 2017-12-14 | 2018-11-27 | Procédé et système pour prédire l'effet d'un événement transitoire dans un centre de données |
Country Status (3)
Country | Link |
---|---|
US (1) | US10817033B2 (fr) |
EP (1) | EP3500078B1 (fr) |
CN (1) | CN110068105B (fr) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20200065703A (ko) * | 2018-11-30 | 2020-06-09 | 에스케이하이닉스 주식회사 | 메모리 시스템 |
CN112752327B (zh) * | 2019-10-29 | 2023-10-20 | 上海华为技术有限公司 | 功率调节方法和接入网设备 |
EP3889820A1 (fr) * | 2020-03-31 | 2021-10-06 | Schneider Electric IT Corporation | Systèmes et procédés permettant de déterminer des architectures à refroidissement liquide dans une salle informatique |
CN112800588B (zh) * | 2021-01-07 | 2022-04-01 | 吉林大学 | 一种用于瞬态行驶工况下机舱换热器进风量的仿真计算方法 |
CN114161923B (zh) * | 2021-12-03 | 2023-10-20 | 华人运通(江苏)技术有限公司 | 一种电动汽车的热管理系统 |
CN114516403B (zh) * | 2022-03-07 | 2023-05-05 | 中国空气动力研究与发展中心低速空气动力研究所 | 一种基于光纤结冰探测的电热防除冰系统功率控制方法 |
CN117684929B (zh) * | 2022-12-14 | 2024-07-23 | 中国科学院沈阳自动化研究所 | 一种基于井间连通性的油水井系统能耗全局优化控制方法 |
CN117067633B (zh) * | 2023-10-12 | 2024-03-15 | 成都飞机工业(集团)有限责任公司 | 一种基于标准冷凝曲线的冷凝系统状态监控方法 |
Family Cites Families (32)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7975156B2 (en) | 2008-10-21 | 2011-07-05 | Dell Products, Lp | System and method for adapting a power usage of a server during a data center cooling failure |
US7378165B2 (en) | 2003-04-29 | 2008-05-27 | Hewlett-Packard Development Company, L.P. | System and method for providing electrical power to an equipment rack using a fuel cell |
US7799474B2 (en) | 2003-04-29 | 2010-09-21 | Hewlett-Packard Development Company, L.P. | System and method for managing electrically isolated fuel cell powered devices within an equipment rack |
US6889908B2 (en) | 2003-06-30 | 2005-05-10 | International Business Machines Corporation | Thermal analysis in a data processing system |
US7881910B2 (en) | 2005-05-02 | 2011-02-01 | American Power Conversion Corporation | Methods and systems for managing facility power and cooling |
US7885795B2 (en) * | 2005-05-02 | 2011-02-08 | American Power Conversion Corporation | Methods and systems for managing facility power and cooling |
US7844440B2 (en) | 2006-07-07 | 2010-11-30 | Edsa Micro Corporation | Systems and methods for real-time dynamic simulation of uninterruptible power supply solutions and their control logic systems |
EP2123140B1 (fr) | 2007-01-24 | 2016-09-07 | Schneider Electric IT Corporation | Système et procédé pour l'évaluation de performance de refroidissement de support d'équipement |
CA2686564C (fr) | 2007-05-15 | 2018-04-17 | American Power Conversion Corporation | Procedes et systemes pour gerer la puissance et le refroidissement d'une installation |
CN101235822B (zh) * | 2008-02-03 | 2010-04-14 | 中兴通讯股份有限公司 | 无线基站风机控制装置及其控制方法 |
US8306794B2 (en) * | 2008-06-26 | 2012-11-06 | International Business Machines Corporation | Techniques for thermal modeling of data centers to improve energy efficiency |
US8209056B2 (en) * | 2008-11-25 | 2012-06-26 | American Power Conversion Corporation | System and method for assessing and managing data center airflow and energy usage |
US8155922B2 (en) | 2009-06-04 | 2012-04-10 | Eaton Corporation | Electrical device cooling efficiency monitoring |
US8489745B2 (en) | 2010-02-26 | 2013-07-16 | International Business Machines Corporation | Optimizing power consumption by dynamic workload adjustment |
US8972217B2 (en) * | 2010-06-08 | 2015-03-03 | Schneider Electric It Corporation | System and method for predicting temperature values in a data center |
US8509959B2 (en) * | 2010-08-12 | 2013-08-13 | Schneider Electric It Corporation | System and method for predicting transient cooling performance for a data center |
US9223905B2 (en) * | 2011-03-25 | 2015-12-29 | Schneider Electric It Corporation | Systems and methods for predicting fluid dynamics in a data center |
WO2013095516A1 (fr) * | 2011-12-22 | 2013-06-27 | Schneider Electric It Corporation | Analyse d'effet d'événements transitoires sur la température dans un centre de données |
EP2796025A4 (fr) * | 2011-12-22 | 2016-06-29 | Schneider Electric It Corp | Système et procédé de prédiction de valeurs de température dans un système électronique |
US9727064B2 (en) * | 2011-12-23 | 2017-08-08 | Schneider Electric It Corporation | Dropped ceiling system cooling prediction |
JP5788337B2 (ja) * | 2012-01-13 | 2015-09-30 | 株式会社日立製作所 | It機器と冷却機器の連係制御システムおよび連係制御方法 |
US20130204593A1 (en) * | 2012-01-31 | 2013-08-08 | Panduit Corp. | Computational Fluid Dynamics Systems and Methods of Use Thereof |
EP2898376A4 (fr) * | 2012-09-21 | 2016-05-18 | Schneider Electric It Corp | Procédé et appareil permettant de caractériser les pointes de température |
US10157245B2 (en) * | 2012-10-31 | 2018-12-18 | Schneider Electric It Corporation | System and method for fluid dynamics prediction with an enhanced potential flow model |
US8964437B2 (en) * | 2013-01-15 | 2015-02-24 | Keysight Technologies, Inc. | Energy dissipating device for DC power supplies |
WO2015134655A2 (fr) * | 2014-03-05 | 2015-09-11 | Adeptdc Co. | Systèmes et procédés de commande intelligente permettant une attribution de ressources optimale pour des opérations de centre de données |
US9814160B2 (en) * | 2015-05-01 | 2017-11-07 | Baselayer Technology, Llc | Side-cooled modular data center |
CN104158754B (zh) * | 2014-07-08 | 2017-07-11 | 上海交通大学 | 基于热负载均衡的数据中心自适应性耗能管理方法 |
CN104503403B (zh) * | 2014-12-12 | 2017-05-31 | 北京百度网讯科技有限公司 | 制冷系统运行能效的管理系统及方法 |
WO2016130453A1 (fr) * | 2015-02-09 | 2016-08-18 | Schneider Electric It Corporation | Système et procédés pour l'optimisation basée sur une simulation de matériel de refroidissement de centre de données |
CN205245470U (zh) * | 2015-12-25 | 2016-05-18 | 福建省烟草公司南平市公司 | 机房辅助降温系统 |
US10180261B1 (en) * | 2015-12-28 | 2019-01-15 | Amazon Technologies, Inc. | Model based cooling control system |
-
2017
- 2017-12-14 US US15/841,599 patent/US10817033B2/en active Active
-
2018
- 2018-11-27 EP EP18208531.6A patent/EP3500078B1/fr active Active
- 2018-12-11 CN CN201811512882.4A patent/CN110068105B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
EP3500078A1 (fr) | 2019-06-19 |
CN110068105A (zh) | 2019-07-30 |
US10817033B2 (en) | 2020-10-27 |
CN110068105B (zh) | 2022-08-05 |
US20190187764A1 (en) | 2019-06-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3500078B1 (fr) | Procédé et système pour prédire l'effet d'un événement transitoire dans un centre de données | |
US9418179B2 (en) | System and method for predicting transient cooling performance for data center | |
Nada et al. | Experimental investigations of thermal managements solutions in data centers buildings for different arrangements of cold aisles containments | |
Nada et al. | Experimental investigations of air conditioning solutions in high power density data centers using a scaled physical model | |
US8639482B2 (en) | Methods and systems for managing facility power and cooling | |
US7881910B2 (en) | Methods and systems for managing facility power and cooling | |
EP1877950B1 (fr) | Procédés et systèmes de gestion de l'alimentation électrique et du refroidissement d'installations | |
EP2580697B1 (fr) | Dispositif et procédé de determination de valeurs de température dans un centre de calcul | |
Moazamigoodarzi et al. | Modeling temperature distribution and power consumption in IT server enclosures with row-based cooling architectures | |
Nada et al. | Experimental parametric study of servers cooling management in data centers buildings | |
US8155793B2 (en) | System and method for controlling air conditioning facilities, and system and method for power management of computer room | |
US8355890B2 (en) | System and method for predicting maximum cooler and rack capacities in a data center | |
US9952103B2 (en) | Analysis of effect of transient events on temperature in a data center | |
US9295183B2 (en) | Method and system for real time monitoring, prediction, analysis and display of temperatures for effective thermal management in a data center | |
Fulpagare et al. | Experimental analysis of airflow uniformity and energy consumption in data centers | |
Phan et al. | Reduced order modeling of a data center model with multi-Parameters | |
Cho et al. | Numerical and experimental study of air containment systems in legacy data centers focusing on thermal performance and air leakage | |
Erden | Experimental and analytical investigation of the transient thermal response of air cooled data centers | |
Alkharabsheh | Experimental and analytical studies of data center thermal management under dynamic conditions | |
Singh et al. | Retrofitting HVAC systems for enhanced energy performance and resilience in university data center room | |
Türkmen et al. | Thermal Profiling of a Small Operational Data Center | |
MOSS | Assessing Power and Cooling |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20191213 |
|
RBV | Designated contracting states (corrected) |
Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
17Q | First examination report despatched |
Effective date: 20211110 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20221111 |
|
GRAJ | Information related to disapproval of communication of intention to grant by the applicant or resumption of examination proceedings by the epo deleted |
Free format text: ORIGINAL CODE: EPIDOSDIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTC | Intention to grant announced (deleted) | ||
INTG | Intention to grant announced |
Effective date: 20230109 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
RAP3 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: SCHNEIDER ELECTRIC IT CORPORATION |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602018053967 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG9D |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20230726 |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 1593485 Country of ref document: AT Kind code of ref document: T Effective date: 20230726 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231027 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20231121 Year of fee payment: 6 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231126 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231127 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231026 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231126 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231027 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20231123 Year of fee payment: 6 Ref country code: DE Payment date: 20231127 Year of fee payment: 6 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602018053967 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 |
|
26N | No opposition filed |
Effective date: 20240429 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20231127 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20231130 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20231127 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20231130 Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230726 |
|
REG | Reference to a national code |
Ref country code: BE Ref legal event code: MM Effective date: 20231130 |