EP3396069B1 - Anchoring head for an anchoring rod - Google Patents

Anchoring head for an anchoring rod Download PDF

Info

Publication number
EP3396069B1
EP3396069B1 EP18169034.8A EP18169034A EP3396069B1 EP 3396069 B1 EP3396069 B1 EP 3396069B1 EP 18169034 A EP18169034 A EP 18169034A EP 3396069 B1 EP3396069 B1 EP 3396069B1
Authority
EP
European Patent Office
Prior art keywords
plate
anchoring head
anchoring
connection member
head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP18169034.8A
Other languages
German (de)
French (fr)
Other versions
EP3396069A1 (en
Inventor
Alfredo FICHERA
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Prometec SRL
Original Assignee
Prometec SRL
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Prometec SRL filed Critical Prometec SRL
Publication of EP3396069A1 publication Critical patent/EP3396069A1/en
Application granted granted Critical
Publication of EP3396069B1 publication Critical patent/EP3396069B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors

Definitions

  • the present description relates to the technical field of anchoring systems for geotechnical use, and more in particular it relates to an anchoring head for an anchoring rod as defined in the preamble of claim 1.
  • anchoring rods provided with a plurality of longitudinal reinforcement elements, which are made, for example, by means of steel strands. Such rods are commonly used to stabilize rocky walls, making supporting walls and bulkheads, consolidating excavation walls and tunnels, etc.
  • the known anchoring rods made with steel strand reinforcement consist of three main elements: the anchoring head, the unbonded length and the anchor length (the latter also called bonded length or foundation bulb).
  • the anchoring head consists of a steel plate which is shaped and sized so as to allow the transfer of forces onto a contrast structure (reinforced concrete wall, bulkhead, support wall etc.).
  • the anchoring head must allow pulling the reinforcement made with strands and blocking them, as well as pulling them again in the event of load losses if this is required during the working life of the works.
  • the unbonded length which is the stretch measured from the head of the rod to beyond the slide line of the ground, constitutes the part of the rod not constrained to the ground, in which the reinforcement, generally protected by a smooth sheath, can freely extend.
  • the anchor length is the part of the rod in which the reinforcement is anchored to the ground, typically by injecting cementitious mortar into the final stretch of the borehole. Having injected the cementitious material and after it has hardened, the strands of the rod are pulled with jacks and hydraulic power units and the head reinforcement is fixed with appropriate clamps.
  • the anchor length transfers the applied load to the ground by virtue of the friction resistance of the mortar-ground adherence.
  • the anchoring head is protected with a protective cap filled with grease at the end of the operations.
  • This grease has an anti-corrosive and lubrication function.
  • Such cap must be removable so as to allow re-tensioning strands, which operation must always be performed using hydraulic jacks, once or more often during the working life of the rod.
  • the protective cap is removed, the head is cleaned removing all the grease and then the strands are pulled again with the hydraulic jacks.
  • the strands In order to allow the new pulling of the strands by means of the hydraulic jacks, the strands have protruding portions which must protrude for a relatively long stretch beyond the anchoring head in order to allow an adequate grip by the hydraulic jacks. Consequently, the known protective caps are relatively long (typically they have a length of 40-60 cm) in order to be able to receive the aforesaid protruding portions of the strands inside them. Once the strands have been pulled again, the protective cap, filled again with grease, is replaced. It is worth noting that these operations, arduous in themselves, are often performed at great heights, where workers are exposed to the risk of falling.
  • an object of the present description to make available an anchoring head for an anchoring rod which that is particularly simple, effective, small in size and easily manageable in re-tensioning operations.
  • FIG. 8 the figure partially shows an anchoring rod 1, 10 for geotechnical use.
  • the anchoring rod 1, 10 is used, by way of non-limiting example, to stabilize rocky walls, make supporting walls and bulkheads, to consolidate excavation walls and tunnels, etc.
  • the anchoring rod 1, 10 is shown in the respective final installation configuration in which is installed inside a borehole P1.
  • Fig. 8 partially shows the borehole P1 and some longitudinal reinforcing elements 10 of the rod 1, 10. Indeed, the parts of the borehole P1, of the unbonded length and of the anchor length of the longitudinal elements 10 which are not shown are widely known to a person skilled in the art.
  • the longitudinal elements 10 are strands 10, and more preferably steel strands 10.
  • the anchoring rod 1, 10 comprises a plurality of longitudinal reinforcing elements 10, preferably from two to eight longitudinal elements 10.
  • the rod 1, 10 comprises in particular four longitudinal elements 10, only two of which are diagrammatically shown in Fig. 8 .
  • the anchoring rod 1, 10 comprises a anchoring head according to a presently preferred embodiment, which is globally indicated by reference numeral 1. The anchoring head 1 makes it possible to pull the longitudinal elements 10 and to block them so as to allow the transfer of load onto a contrast wall CW1.
  • the contrast wall CW1 is a wall of a contrast structure CS1 suited to be coupled to a wall to be consolidated.
  • the contrast structure CS1 may comprise, for example, a reinforced concrete slab, a bulkhead, a supporting wall etc.
  • the anchoring head 1 comprises a first plate 20 having a central axis X1 perpendicular to the first plate 20.
  • the plate 20 comprises a first face 210 and an opposite second face 220, which are preferably planar faces, and the axis X1 is perpendicular to the faces 210, 220.
  • the first plate 20 comprises first holes 201 configured to be each crossed by a respective longitudinal reinforcing element 10.
  • the rod 1, 10 comprises four longitudinal elements 10. Consequently, the plate 20 comprises four first holes 201, as can be seen in Fig. 10 .
  • the anchoring head 1 comprises a second plate 40, which is smaller than the first plate 20.
  • the plates 20, 40 are circular plates, as in the example shown in the accompanying figures, the diameter of the plate 40 is smaller than the diameter of the first plate 20.
  • the diameter of the first plate 20 is greater than the diameter of the borehole P1 so as to be able to rest on the contrast wall CW1.
  • the diameter of the second plate 40 is smaller than the diameter of the borehole P1 so that it can be received inside the contrast wall P1.
  • the shape of the plates 20, 40 is not limited to a circular shape.
  • the second plate 40 comprises a first face 410 and an opposite second face 420.
  • the second plate 40 is arranged facing the first plate 20, preferably so that the second face 220 of the first plate 20 faces the first face 410 of the second plate 40.
  • the second plate 40 comprises a plurality of second holes 401 aligned with said first holes 201.
  • the second holes 401 are provided to be each crossed by a respective longitudinal reinforcing element 10.
  • the rod 1, 10 comprises four longitudinal elements 10, as can be seen also in Fig. 11
  • the second plate 40 comprises four second holes 401.
  • each hole 201 is aligned with a respective hole 401 along an axis which is inclined with respect to the central axis X1.
  • each of the inclined axes Y1 and Y2 and the central axis X1 converge in the direction which goes from the first plate 20 to the second plate 40.
  • each of the axes Y1, Y2 forms an angle of about 3 degrees with the central axis X1.
  • the anchoring head 1 is suitable for taking on a first configuration, wherein the first and the second plate 20, 40 are spaced apart from each other by a first axial distance D1.
  • the distance D1 is a distance between the second face 220 of the first plate 20 and the first face 410 of the second plate 40.
  • the configuration in Fig. 1 is an initial configuration of the anchoring head 1, i.e. the configuration assumed by the head 1 before it is coupled to the longitudinal elements 10.
  • the distance D1 is equal to about 7 cm.
  • the anchoring head 1 comprises a connection member 50 which crosses the first plate 20 and is connected to the second plate 40.
  • the connection member 50 is connected to the second plate 40 so as to be integral in translation with the second plate 40 in the direction of said middle axis X1.
  • the connection member 50 is suitable to be moved axially, i.e. in the direction of the central axis X1, in a first direction T1 ( Fig. 1 or Fig. 6 ) so that the anchoring head 1 takes on a second configuration (not shown), wherein the first and the second plate 20, 40 are spaced apart from each other by a second axial distance which is smaller than said first axial distance D1.
  • the connection member 50 is suitable to be moved axially so as to approach the second plate 40 to the first plate 20.
  • the anchoring head 1 conveniently also comprises a stop element 60 operatively connected to the connection member 50.
  • the stop element 60 is suitable for engaging the first plate 20 so as to prevent a translation of the connection member 50 and accordingly of the second plate 40 in a second direction T2 ( Fig. 1 or Fig. 6 ) opposite to said first direction T1.
  • the actuating element 60 is accessible from the side of first face 210 of the first plate 20.
  • the stop element 60 is suitable for axially moving said connection member 50 and accordingly the second plate 40 so as to axially move the first and the second plate 20, 40 close to each other with respect to the aforesaid first axial distance D1.
  • connection member 50 comprises a threaded bar 50
  • said stop element 60 comprises a stop nut 60 coupled to the threaded bar 50.
  • threaded bar is to be understood in a general manner so as to include not only a threaded bar for its entire length of the bar, as shown in the example illustrated in the appended figures, but also in general a pin, which can be threaded for only part of the respective length so as to make it possible to screw the stop nut 60 to the pin.
  • the first plate 20 comprises a central hole 205 ( Fig. 1 and Fig.
  • the second plate 40 comprises a central hole 405 ( Fig. 1 and Fig. 11 ).
  • the central hole 205 is a smooth hole, i.e. a non-threaded hole, in which a portion 61 of the stop nut 60 operatively suitable to rotate around the central axis X1 is preferably received.
  • the central hole 405 is preferably a threaded hole into which a portion 51 of the threaded bar 50 is screwed to make the second plate 40 integral with the threaded bar 50.
  • the anchoring head 1 comprises a plurality of locking elements 30.
  • Each locking element 30 is suitable for being coupled to a respective longitudinal reinforcing element 10 and to engage a respective part 402 of the second plate 40 to make the respective longitudinal reinforcing element 10 integral with the anchoring head 40 and transfer a load from said respective longitudinal reinforcing element 10 to the anchoring head 1.
  • the part 402 of the second plate 40 engaged by each locking element 30 comprises a side wall 402 of each second hole 401.
  • the anchoring head 1 comprises in non-limiting manner four clamping elements 30, each of which is suited to engage the side wall 402 of a respective second hole 401.
  • the anchoring head 1 comprises a plurality of supporting tubes 80 for the locking elements 30.
  • the supporting tubes are preferably rigid tubes, preferably metal tubes.
  • each supporting tube 80 crosses a respective pair of holes comprising one of the first holes 201 and one of the second holes 401 aligned with one another.
  • Each supporting tube 80 is suitable to be crossed by a respective longitudinal reinforcing element 10.
  • the locking elements 30 comprise a plurality of self-tightening clamps 30, each of which is coupled to a respective supporting tube 80 so as to be crossed by the respective supporting tube 80.
  • the plurality of self-tightening clamps 30 is interposed between the first and the second plate 20, 40.
  • the self-tightening clamps 30 and the second holes 401 are shaped so that said clamps 30 may be coupled with said second holes 401 so as to interlock in the second plate 40.
  • the clamps 30 act in practice as locking wedges suitable to interlock in the second holes 401.
  • the self-tightening clamps 30 are sized to be able to entirely cross neither the first holes 201 nor the second holes 401.
  • the self-tightening clamps 30 and the second holes 401 have a tapered shape, preferably a generally frustoconical shape.
  • the self-tightening clamps 30 comprise a plurality of clamp portions 301, preferably three portions 301, which extend about a clamp axis M1 (axis M1 is shown in Fig. 12 and is orthogonal to the plane of the figure) and are elastically connected to one another so as to be subject to an elastic return force which tends to return the portions 301 towards the axis M1 when they are moved away from such axis M1.
  • the anchoring head 1 comprises an elastic spacer element 70 to keep the first and second plate 20, 40 mutually spaced apart.
  • the elastic spacer element 70 is operatively interposed between the first and the second plate 20, 40.
  • the elastic spacer element 70 comprises a helical spring 70 fitted on said connection member 50.
  • the anchoring head 1 comprises a plurality of sleeves 90.
  • the sleeves 90 are preferably rigid sleeves, preferably metal sleeves.
  • Each sleeve 90 is fixed to the second plate 40, preferably welded to the second plate 40, so as to protrude from the second face 420 of the second plate 40.
  • each of the sleeves 90 is suitable to be crossed by a respective supporting tube 80 ( Fig. 1 ).
  • the sleeves 90 make it possible to receive inside a sheathed portion of the longitudinal reinforcing elements 10. In this manner, it is advantageously possible to obtain a better protection of the longitudinal elements 10 because it avoids the remaining exposed to corrosion, humidity, etc., of a bare, i.e.
  • the longitudinal elements 10 must each display in general a respective bare end portion which extends from the end of each longitudinal element 10 located outside the borehole P1 to a stretch of the elements 10 which extends near the second face 420 of the second plate 40 on the side of the second face 420.
  • the anchoring head 1 comprises an outer protective casing 100 suitable for containing therein the first and the second plate 20, 40, the connection member 50, the stop element 60 and the locking elements 30.
  • the outer protective casing 100 is made of an electrically insulating material, preferably polyethylene.
  • the outer protective casing 100 comprises a first casing part 1010 and a cap 1020, 1030, which can be removably coupled, preferably screwed, to the first casing part 1010.
  • the first part 1010 of the outer casing 100 is arranged so as to close laterally a space 2 or gap 2 comprised between the first and the second plate 20, 40.
  • the first part 1010 of casing 100 substantially forms a container which, as will be described in greater detail below in the present description, is suitable to be filled with a substance G1 having a lubricating and corrosion inhibiting function (shown by dotted lines in Fig. 8 ) which is used to protect some components of the anchoring head 1 and of the rod 1, 10.
  • the substance G1 either comprises or consists of grease G1.
  • the first part 1010 has a tubular shape and preferably has an annular edge 1011 ( Fig. 1 ) on which a peripheral edge portion 421 of the second face 420 of the second plate 40 rests.
  • the plate 40 forms a movable bottom of a container defined by the second plate 40 and by the first part 1010 of casing, wherein such movable bottom in the configuration of Fig. 1 rests on the annular edge 1011 of the first part 1010 of casing.
  • the cap 1020, 1030 protrudes beyond the first face 210 of the first plate 20 when it is coupled to the first portion 1010 of the casing 100.
  • the connection member 50 comprises a protruding portion 501, which protrudes beyond the first face 201 of the first plate 20 on the side opposite to the second plate 40, and said cap 1020, 1030 is shaped so as to cover the protruding portion 501 of the connection member 50.
  • the cap 1020, 1030 comprises a first part 1020 of cap comprising an access opening 1021 and a second part 1030 of cap which can be removably coupled, preferably screwed, to the first part 1020 of cap.
  • the second part 1030 of the cap 1020, 1030 acts as a plug for closing the access opening 1021.
  • the anchoring head 1 is shown in the respective initial configuration.
  • the anchoring head 1 preferably arrives already assembled to the construction site in the configuration of Fig. 1 or possibly also provided with the cap 1020, 1030 which must be removed before installing the head 1, ready to be installed.
  • the threaded bar 50 is screwed into the central hole 405 of the second plate 40 and to the internal threading of the stop nut 60.
  • the nut 60 is in turn inserted in the central hole 205 of the first plate 20.
  • the spring 70 initially keeps the plates 20, 40 at the predetermined distance D1, which is preferably equal to about 7 cm.
  • the sleeves 90 are preferably fixed to the second face 420 of the second plate 40.
  • the supporting tubes 80 the number of which is also equal to the number of strands 10 of rod 1,10 on which they must engage, pass through the first holes 201 of the plate 20, cross the clamps 30 placed in the space 2 between the plates 20 and 40 and finally cross the sleeves 90, whereby protruding from them.
  • Fig. 2 shows the anchoring head 1 just inserted on the strands 10.
  • the installation which is very simple and fast, consists in approaching the head 1 to the contrast structure CS1 and threading it onto the strands 10 leading out from borehole P1.
  • the strands 10 are inserted through the supporting tubes 80 from the side of the second plate 40 until the first plate 20 abuts against the contrast structure CS1.
  • the supporting tubes 80 also act as guiding elements, which make it possible to facilitate the positioning of the head on the contrast structure CS1.
  • the strands 10 cross, in this order, the tubes 80, the sleeves 90, the second plate 40, the clamps 30, the first plate 20 to then protrude from the supporting tubes 80 from the side of the first plate 20 by a length sufficient to allow the gripping by hydraulic jacks (not shown) for pulling the strands 10.
  • the second plate 40 is also inserted inside the borehole P1.
  • the method proceeds by pulling out the supporting tubes 80.
  • Fig. 3 shows the anchoring head 1, while the supporting tubes 80 are being pulled out in the senses indicated by the arrows F1, F2, an operation which is performed manually by an operator.
  • Fig. 4 shows the anchoring head in the configuration after having pulled out of the supporting tubes 80 completely. Having pulled off the last tubes 80, the clamps 30 tighten automatically about the strands 10.
  • the strands 10 can be tensioned, preferably by using hydraulic jacks 1500.
  • Fig. 5 shows the pulling operation of the strands 10 by means of hydraulic jacks 1500.
  • the hydraulic jacks generally available on the market are provided with inner pistons flush with one end of the jacks themselves.
  • the hydraulic jacks 1500 are jacks provided with modified pistons 1510.
  • the pistons 1510 are elongated pistons of a predetermined length with respect to the pistons of a traditional jack so they can reach the clamps 30 and push them into the respective holes 401 of the plate 40.
  • the pistons 1520 protrude with respect to an end 1520 of the respective jack 1500 by a length equal to about 11cm.
  • the pistons 1510 are then inserted in the holes 201 of the plate 20 so as to push the clamps 30 into the holes 401 of the plate 40.
  • the pulling operation with multiple hydraulic jacks 1500 (jack applied to each strand 10 with simultaneous tensioning of the strands 10) ends when each strand 10 is stretched by the predetermined load.
  • the clamps 30, pushed by the aforesaid pistons 1510 constrain the strands 10 to the plate 40 and consequently implement the transfer of load from the strands 10 to the plate 40 itself.
  • the latter being rigidly coupled to the first plate 20 by means of the threaded bar 50 and the stop nut 60, in turn transfers the load to the plate 20 itself, which goes into contrast with the contrast structure CS1.
  • Fig. 6 shows the anchoring head 1 after tensioning and with the clamps 30 wedged into the holes 401 of the plate 40.
  • the method proceeds with the cutting of the strands 10, preferably flush or substantially flush with the first face 210 of the first plate 20.
  • Fig. 7 shows the step in which the strands 10 are cut by means of the cutting tools L1, L2 diagrammatically shown by means of scissors L1, L2 in Fig. 7 . Once having cut the strands 10, the final process of protecting the anchoring head 1 from the atmospheric elements begins.
  • Fig. 8 shows the anchoring head 1 in its final configuration.
  • grease G1 is introduced and penetrates through the holes 201 of the first plate 20 into the space 2 between the plates 20 and 40, whereby saturating almost all spaces.
  • the grease G1 is introduced through the access opening 1021 of the cap 1020, 1030.
  • the grease G1 thus penetrates even through the clamps 30 until it reaches sheathed part of the strands 10.
  • the first part 1010 of the casing 100 filled with the grease G1 substantially seals the space 2, whereby creating a saturated volume of grease G1.
  • the grease G1 comes out of the holes 201 of the first plate 20.
  • the method then proceeds introducing grease G1 until the entire segment 501 ( Fig. 1 ) of the threaded bar 50 is covered.
  • the second part 1030 of the cap 1020, 1030 is coupled to the first part 1020 of it so as to close the access opening 1021.
  • the outer protective casing 100 together with the grease G1, guarantees an optimal protection with compact dimensions, whereby ensuring preservation, e.g. from water infiltrations and corrosion of the metal elements, preferably made of steel, of the head 1.
  • Fig. 9 shows the anchoring head 1 upon re-tensioning which will be performed either with a simple torque wrench K1 by applying an appropriate tightening torque on the stop nut 60 or by a single jack 1600 for bars (said jack 1600 is partially and diagrammatically shown in Fig. 9 ), unlike the traditional anchoring systems, which are performed with a plurality of hydraulic jacks of the type used for the tensioning the strands 10.
  • the jack 1600 acts only on the threaded bar 50 so as to pull the bar 50 and the second plate 40 in sense T1 ( Fig. 1 or Fig.
  • an ordinary strand rod may typically be subjected at most to a load loss of 3-4 tons and that, for the purposes of load recovery, 1 cm of elongation during re-tensioning corresponds to about 3-4 tons recovered by the rod itself. So, in order to recover the lost load, which obviously will also depend on the length of the rod itself, a re-tensioning of about 3-4 centimeters will be generally required.
  • An initial distance D1 between the plates 20 and 40 equal to about 7 centimeters can satisfy the aforesaid geometric requirements. Indeed, by applying the tightening torque on the stop nut 60, or by pulling the bar 50 by means of the bar jack 1600, plate 40 approaches the plate 20, which instead remains motionless, pulling the strands 10 and following their elongation.
  • the re-tensioning operation is fundamentally very simple and easily manageable on the construction site. Having removed the cap 1020, 1030 of the outer protective casing 100, the size of which is very small compared to the traditional protective caps (according with an embodiment, the length of the cap 1020, 1030 in the direction of axis X1 is equal to about 10 cm), it will be necessary to remove only a small amount of grease G1 and, for example, use a common and manageable torque wrench to tighten the stop nut 60, whereby determining the translation of the plate 40 towards the plate 20 with the torque applied and the concurrent elongation of the strands 10 which will thus re-acquire the lost load. As mentioned above, as previously mentioned, the re-tensioning may be performed alternatively with the bar jack 1600. Finally, after re-tensioning, the cap 1020, 1030 is repositioned and the small quantity of grease G1 which was previously removed is introduced again.
  • an anchoring head for an anchoring rod for geotechnical use is globally indicated by reference numeral 1A.
  • the anchoring head 1A differs from the anchoring head 1 described above, exclusively in that it is provided with a key 230 in addition to a first plate 20a and to a connection member 50A, which are slightly modified with respect to the first plate 20 and the connection member 50 of the head 1.
  • the first plate 20A differs from the first plate 20 in that a housing seat 231 is provided for the key 230.
  • a housing seat 231 is provided for the key 230.
  • connection member 50A differs from the connection member 50 in that is provided on a respective side wall 52a with rectilinear longitudinal groove 53A extending parallel to said central axis X1.
  • the groove 53a extends from at least one end face 54a of the connection member 50A.
  • the rectilinear longitudinal groove 53A is coupled to the key 230 in such a way that during an axial sliding (axis X1) of the connection member 50A, the key 230 is at least partly received in the longitudinal groove 53A.
  • the key 230 and the groove 53a make it possible to either avoid or reduce the negative effects due to possible torsional stresses on the first plate 20A.

Description

  • The present description relates to the technical field of anchoring systems for geotechnical use, and more in particular it relates to an anchoring head for an anchoring rod as defined in the preamble of claim 1.
  • In anchoring systems for geotechnical use, see for example US 6 283 451 B1 , it is known to use anchoring rods provided with a plurality of longitudinal reinforcement elements, which are made, for example, by means of steel strands. Such rods are commonly used to stabilize rocky walls, making supporting walls and bulkheads, consolidating excavation walls and tunnels, etc. In broad terms, the known anchoring rods made with steel strand reinforcement consist of three main elements: the anchoring head, the unbonded length and the anchor length (the latter also called bonded length or foundation bulb). The anchoring head consists of a steel plate which is shaped and sized so as to allow the transfer of forces onto a contrast structure (reinforced concrete wall, bulkhead, support wall etc.). The anchoring head must allow pulling the reinforcement made with strands and blocking them, as well as pulling them again in the event of load losses if this is required during the working life of the works. The unbonded length, which is the stretch measured from the head of the rod to beyond the slide line of the ground, constitutes the part of the rod not constrained to the ground, in which the reinforcement, generally protected by a smooth sheath, can freely extend. The anchor length is the part of the rod in which the reinforcement is anchored to the ground, typically by injecting cementitious mortar into the final stretch of the borehole. Having injected the cementitious material and after it has hardened, the strands of the rod are pulled with jacks and hydraulic power units and the head reinforcement is fixed with appropriate clamps. In this manner, the anchor length transfers the applied load to the ground by virtue of the friction resistance of the mortar-ground adherence. In the case of rods for geotechnical use of the permanent type (typically rods designed for a working life longer than two years), the anchoring head is protected with a protective cap filled with grease at the end of the operations. This grease has an anti-corrosive and lubrication function. Such cap must be removable so as to allow re-tensioning strands, which operation must always be performed using hydraulic jacks, once or more often during the working life of the rod. In particular, in this case, the protective cap is removed, the head is cleaned removing all the grease and then the strands are pulled again with the hydraulic jacks. In order to allow the new pulling of the strands by means of the hydraulic jacks, the strands have protruding portions which must protrude for a relatively long stretch beyond the anchoring head in order to allow an adequate grip by the hydraulic jacks. Consequently, the known protective caps are relatively long (typically they have a length of 40-60 cm) in order to be able to receive the aforesaid protruding portions of the strands inside them. Once the strands have been pulled again, the protective cap, filled again with grease, is replaced. It is worth noting that these operations, arduous in themselves, are often performed at great heights, where workers are exposed to the risk of falling.
  • There are many difficulties related to the above operations, because in addition to being performed at height, the works imply, for example, the following drawbacks:
    • the disassembly of a cap, placed in an inclined or perpendicular position with respect to the consolidated wall (which is typically either vertical or substantially vertical), inside which a conspicuous amount of liquefied grease is usually contained, which can drip and fall by gravity, invading the work platform and/or the underlying areas;
    • the collection and disposal of the removed grease, the amount of which may be considerable in the case of works having a large number of rods;
    • the use of a plurality of hydraulic jacks at a height for re-tensioning the rod, which is difficult for both logistical problems and because, considering their weight and size, the presence of at least 2 workers is normally necessary;
    • the restoration of the cap with a quantity of grease similar to that previously removed.
    In addition to the aforesaid construction site difficulties, there is also the impact of unpleasant appearance, which often contrasts with the requirements of constraints in places of scenic beauty, when observing a wall from which a series of 40-60-cm-long caps emerge in a direction inclined to the wall itself.
  • It is a general object of the present description to provide an anchoring head for an anchoring rod which can solve or reduce at least in part the problems described above with reference to the prior art.
  • This and other objects are achieved by means of an anchoring head for an anchoring rod as defined in claim 1 in its most general form, and in some particular embodiments of it in the dependent claims.
  • According to an aspect of the present invention, it is an object of the present description to make available an anchoring head for an anchoring rod which that is particularly simple, effective, small in size and easily manageable in re-tensioning operations.
  • It is a further object of the present invention an anchoring rod as described in claim 15.
  • The invention will be better understood from the following detailed description of its embodiments, made by way of example and consequently not limiting in any way with reference to the accompanying drawings, in which:
    • Fig. 1 is a plan, partial section view of an anchoring head for an anchoring rod according to a presently preferred embodiment;
    • Figs. 2-7 are plan, partial section views anchoring head in Fig. 1 showing the steps of installing of the anchoring head, where the head is coupled with longitudinal reinforcement elements of an anchoring rod arranged inside a borehole;
    • Fig. 8 is a plan, section view of the anchoring head in Fig. 1 in the final installation configuration;
    • Fig. 9 is a plan, section view of the anchoring head in Fig. 1 during a step of re-tensioning of the longitudinal reinforcement elements in Fig. 2;
    • Figure 10 is a top plan view of a first component of the anchoring head in Fig. 1;
    • Fig. 11 is a top plan view of a second component of the anchoring head in Fig. 1;
    • Fig. 12 is a top plan view of a third component of the anchoring head in Fig. 1;
    • Fig. 13 is a plan, section view of an anchoring head according to a second embodiment shown in the respective final installation configuration;
    • Fig. 14 is a top plan view of two components of the anchoring head in Fig. 13; and
    • Fig. 15 is a plan, side elevation view of a further component of the anchoring head in Fig. 13.
  • Similar or equivalent elements in the accompanying figures are indicated by means of the same reference numerals.
  • It is worth noting that in the following description and in the claims, the words "axial" and "radial" are to be understood as referring to the direction of axis X1 which will be described later. Furthermore, in the following description and in the claims, the words "inner" and "outer" are referred to the center of the anchoring head.
  • With initial reference to Fig. 8, the figure partially shows an anchoring rod 1, 10 for geotechnical use. In manner known in itself, the anchoring rod 1, 10 is used, by way of non-limiting example, to stabilize rocky walls, make supporting walls and bulkheads, to consolidate excavation walls and tunnels, etc. In Fig. 8, the anchoring rod 1, 10 is shown in the respective final installation configuration in which is installed inside a borehole P1. In particular, Fig. 8 partially shows the borehole P1 and some longitudinal reinforcing elements 10 of the rod 1, 10. Indeed, the parts of the borehole P1, of the unbonded length and of the anchor length of the longitudinal elements 10 which are not shown are widely known to a person skilled in the art. Preferably, the longitudinal elements 10 are strands 10, and more preferably steel strands 10. In general, the anchoring rod 1, 10 comprises a plurality of longitudinal reinforcing elements 10, preferably from two to eight longitudinal elements 10. In the example shown in the accompanying figures, the rod 1, 10 comprises in particular four longitudinal elements 10, only two of which are diagrammatically shown in Fig. 8. Again with reference to Fig. 8, the anchoring rod 1, 10 comprises a anchoring head according to a presently preferred embodiment, which is globally indicated by reference numeral 1. The anchoring head 1 makes it possible to pull the longitudinal elements 10 and to block them so as to allow the transfer of load onto a contrast wall CW1. Preferably, the contrast wall CW1 is a wall of a contrast structure CS1 suited to be coupled to a wall to be consolidated. The contrast structure CS1 may comprise, for example, a reinforced concrete slab, a bulkhead, a supporting wall etc.
  • Again with reference to Fig. 8, the anchoring head 1 comprises a first plate 20 having a central axis X1 perpendicular to the first plate 20. In other words, the plate 20 comprises a first face 210 and an opposite second face 220, which are preferably planar faces, and the axis X1 is perpendicular to the faces 210, 220. The first plate 20 comprises first holes 201 configured to be each crossed by a respective longitudinal reinforcing element 10. In the example, the rod 1, 10 comprises four longitudinal elements 10. Consequently, the plate 20 comprises four first holes 201, as can be seen in Fig. 10.
  • The anchoring head 1 comprises a second plate 40, which is smaller than the first plate 20. In other words, if the plates 20, 40 are circular plates, as in the example shown in the accompanying figures, the diameter of the plate 40 is smaller than the diameter of the first plate 20. In particular, it is worth noting that the diameter of the first plate 20 is greater than the diameter of the borehole P1 so as to be able to rest on the contrast wall CW1. Conversely, the diameter of the second plate 40 is smaller than the diameter of the borehole P1 so that it can be received inside the contrast wall P1. However, it is worth noting that, in general, the shape of the plates 20, 40 is not limited to a circular shape. The second plate 40 comprises a first face 410 and an opposite second face 420. The second plate 40 is arranged facing the first plate 20, preferably so that the second face 220 of the first plate 20 faces the first face 410 of the second plate 40. The second plate 40 comprises a plurality of second holes 401 aligned with said first holes 201. The second holes 401 are provided to be each crossed by a respective longitudinal reinforcing element 10. In the example, in which the rod 1, 10 comprises four longitudinal elements 10, as can be seen also in Fig. 11, the second plate 40 comprises four second holes 401. With reference to Fig. 1, according to a preferred embodiment, each hole 201 is aligned with a respective hole 401 along an axis which is inclined with respect to the central axis X1. In particular, Fig. 1 shows an inclined axis Y1 along which a hole 201 and a hole 401 are aligned and a further inclined axis Y2 along which a further hole 201 and a further hole 401 are aligned. As shown, for example in Fig. 1, each of the inclined axes Y1 and Y2 and the central axis X1 converge in the direction which goes from the first plate 20 to the second plate 40. Preferably, each of the axes Y1, Y2 forms an angle of about 3 degrees with the central axis X1.
    Again with reference to Fig. 1, the anchoring head 1 is suitable for taking on a first configuration, wherein the first and the second plate 20, 40 are spaced apart from each other by a first axial distance D1. The distance D1 is a distance between the second face 220 of the first plate 20 and the first face 410 of the second plate 40. Preferably, the configuration in Fig. 1 is an initial configuration of the anchoring head 1, i.e. the configuration assumed by the head 1 before it is coupled to the longitudinal elements 10. According to a preferred embodiment, the distance D1 is equal to about 7 cm.
  • Turning back to Fig. 8, the anchoring head 1 comprises a connection member 50 which crosses the first plate 20 and is connected to the second plate 40. In particular, the connection member 50 is connected to the second plate 40 so as to be integral in translation with the second plate 40 in the direction of said middle axis X1. The connection member 50 is suitable to be moved axially, i.e. in the direction of the central axis X1, in a first direction T1 (Fig. 1 or Fig. 6) so that the anchoring head 1 takes on a second configuration (not shown), wherein the first and the second plate 20, 40 are spaced apart from each other by a second axial distance which is smaller than said first axial distance D1. In other words, the connection member 50 is suitable to be moved axially so as to approach the second plate 40 to the first plate 20.
  • The anchoring head 1 conveniently also comprises a stop element 60 operatively connected to the connection member 50. The stop element 60 is suitable for engaging the first plate 20 so as to prevent a translation of the connection member 50 and accordingly of the second plate 40 in a second direction T2 (Fig. 1 or Fig. 6) opposite to said first direction T1. According to a convenient embodiment, the actuating element 60 is accessible from the side of first face 210 of the first plate 20. According to a preferred embodiment, the stop element 60 is suitable for axially moving said connection member 50 and accordingly the second plate 40 so as to axially move the first and the second plate 20, 40 close to each other with respect to the aforesaid first axial distance D1. According to a preferred embodiment, the connection member 50 comprises a threaded bar 50, and wherein said stop element 60 comprises a stop nut 60 coupled to the threaded bar 50. With this regard, it is worth noting that for the purposes of the present description the expression "threaded bar" is to be understood in a general manner so as to include not only a threaded bar for its entire length of the bar, as shown in the example illustrated in the appended figures, but also in general a pin, which can be threaded for only part of the respective length so as to make it possible to screw the stop nut 60 to the pin. According to a preferred embodiment, the first plate 20 comprises a central hole 205 (Fig. 1 and Fig. 10) crossed by the threaded bar 50, while the second plate 40 comprises a central hole 405 (Fig. 1 and Fig. 11). In particular, the central hole 205 is a smooth hole, i.e. a non-threaded hole, in which a portion 61 of the stop nut 60 operatively suitable to rotate around the central axis X1 is preferably received. The central hole 405 is preferably a threaded hole into which a portion 51 of the threaded bar 50 is screwed to make the second plate 40 integral with the threaded bar 50.
  • Turning back to Fig. 8, the anchoring head 1 comprises a plurality of locking elements 30. Each locking element 30 is suitable for being coupled to a respective longitudinal reinforcing element 10 and to engage a respective part 402 of the second plate 40 to make the respective longitudinal reinforcing element 10 integral with the anchoring head 40 and transfer a load from said respective longitudinal reinforcing element 10 to the anchoring head 1.
  • According to a preferred embodiment, the part 402 of the second plate 40 engaged by each locking element 30 comprises a side wall 402 of each second hole 401. In the example, the anchoring head 1 comprises in non-limiting manner four clamping elements 30, each of which is suited to engage the side wall 402 of a respective second hole 401.
  • With reference to Fig. 1, according to a convenient embodiment, the anchoring head 1 comprises a plurality of supporting tubes 80 for the locking elements 30. The supporting tubes are preferably rigid tubes, preferably metal tubes. In particular, each supporting tube 80 crosses a respective pair of holes comprising one of the first holes 201 and one of the second holes 401 aligned with one another. Each supporting tube 80 is suitable to be crossed by a respective longitudinal reinforcing element 10. Preferably, the locking elements 30 comprise a plurality of self-tightening clamps 30, each of which is coupled to a respective supporting tube 80 so as to be crossed by the respective supporting tube 80. The plurality of self-tightening clamps 30 is interposed between the first and the second plate 20, 40. According to a convenient embodiment, the self-tightening clamps 30 and the second holes 401 are shaped so that said clamps 30 may be coupled with said second holes 401 so as to interlock in the second plate 40. According to a preferred embodiment, shown in the accompanying figures, the clamps 30 act in practice as locking wedges suitable to interlock in the second holes 401. In particular, according to a convenient embodiment, the self-tightening clamps 30 are sized to be able to entirely cross neither the first holes 201 nor the second holes 401. According to a preferred embodiment, as can be seen for example in Fig. 1, the self-tightening clamps 30 and the second holes 401 have a tapered shape, preferably a generally frustoconical shape. With reference to Fig. 12, according to a preferred embodiment the self-tightening clamps 30 comprise a plurality of clamp portions 301, preferably three portions 301, which extend about a clamp axis M1 (axis M1 is shown in Fig. 12 and is orthogonal to the plane of the figure) and are elastically connected to one another so as to be subject to an elastic return force which tends to return the portions 301 towards the axis M1 when they are moved away from such axis M1.
  • With reference to Fig. 8, the anchoring head 1 comprises an elastic spacer element 70 to keep the first and second plate 20, 40 mutually spaced apart. The elastic spacer element 70 is operatively interposed between the first and the second plate 20, 40. According to a preferred embodiment, the elastic spacer element 70 comprises a helical spring 70 fitted on said connection member 50.
  • Again with reference to Fig. 1, according to a convenient embodiment, the anchoring head 1 comprises a plurality of sleeves 90. The sleeves 90 are preferably rigid sleeves, preferably metal sleeves. Each sleeve 90 is fixed to the second plate 40, preferably welded to the second plate 40, so as to protrude from the second face 420 of the second plate 40. Furthermore, each of the sleeves 90 is suitable to be crossed by a respective supporting tube 80 (Fig. 1). Conveniently, the sleeves 90 make it possible to receive inside a sheathed portion of the longitudinal reinforcing elements 10. In this manner, it is advantageously possible to obtain a better protection of the longitudinal elements 10 because it avoids the remaining exposed to corrosion, humidity, etc., of a bare, i.e. not sheathed, portion of the elements 10 at the stretches of the elements 10 which extend near the second plate 40 from the side of the second face 420 of the second plate 40. Indeed, the longitudinal elements 10 must each display in general a respective bare end portion which extends from the end of each longitudinal element 10 located outside the borehole P1 to a stretch of the elements 10 which extends near the second face 420 of the second plate 40 on the side of the second face 420.
  • Again with reference to Fig. 8, according to a convenient embodiment, the anchoring head 1 comprises an outer protective casing 100 suitable for containing therein the first and the second plate 20, 40, the connection member 50, the stop element 60 and the locking elements 30. According to a convenient embodiment, the outer protective casing 100 is made of an electrically insulating material, preferably polyethylene. The outer protective casing 100 comprises a first casing part 1010 and a cap 1020, 1030, which can be removably coupled, preferably screwed, to the first casing part 1010. The first part 1010 of the outer casing 100 is arranged so as to close laterally a space 2 or gap 2 comprised between the first and the second plate 20, 40. In this manner, the first part 1010 of casing 100, preferably together with the second plate 40, substantially forms a container which, as will be described in greater detail below in the present description, is suitable to be filled with a substance G1 having a lubricating and corrosion inhibiting function (shown by dotted lines in Fig. 8) which is used to protect some components of the anchoring head 1 and of the rod 1, 10. Preferably, the substance G1 either comprises or consists of grease G1. According to a preferred embodiment, the first part 1010 has a tubular shape and preferably has an annular edge 1011 (Fig. 1) on which a peripheral edge portion 421 of the second face 420 of the second plate 40 rests. In other words, according to a preferred embodiment, the plate 40 forms a movable bottom of a container defined by the second plate 40 and by the first part 1010 of casing, wherein such movable bottom in the configuration of Fig. 1 rests on the annular edge 1011 of the first part 1010 of casing.
  • According to a convenient embodiment, the cap 1020, 1030 protrudes beyond the first face 210 of the first plate 20 when it is coupled to the first portion 1010 of the casing 100. In particular, with reference to Fig. 1, according to a preferred embodiment, the connection member 50 comprises a protruding portion 501, which protrudes beyond the first face 201 of the first plate 20 on the side opposite to the second plate 40, and said cap 1020, 1030 is shaped so as to cover the protruding portion 501 of the connection member 50. Turning back to Fig. 8, according to a convenient embodiment, the cap 1020, 1030 comprises a first part 1020 of cap comprising an access opening 1021 and a second part 1030 of cap which can be removably coupled, preferably screwed, to the first part 1020 of cap. In practice, the second part 1030 of the cap 1020, 1030 acts as a plug for closing the access opening 1021.
  • Having described the structure of the anchoring head 1, a coupling method of the anchoring head 1 to the longitudinal reinforcing elements 10 anchored inside the borehole P1 will now be described by way of non-limiting example with reference to the embodiment of the anchoring head 1 shown in the accompanying figures.
  • With reference to Fig. 1, in this figure the anchoring head 1 is shown in the respective initial configuration. In practice, the anchoring head 1 preferably arrives already assembled to the construction site in the configuration of Fig. 1 or possibly also provided with the cap 1020, 1030 which must be removed before installing the head 1, ready to be installed. The threaded bar 50 is screwed into the central hole 405 of the second plate 40 and to the internal threading of the stop nut 60. The nut 60 is in turn inserted in the central hole 205 of the first plate 20. In Fig. 1, the spring 70 initially keeps the plates 20, 40 at the predetermined distance D1, which is preferably equal to about 7 cm. The sleeves 90, the number of which is equal to the number of strands 10 of rod 1,10, are preferably fixed to the second face 420 of the second plate 40. The supporting tubes 80, the number of which is also equal to the number of strands 10 of rod 1,10 on which they must engage, pass through the first holes 201 of the plate 20, cross the clamps 30 placed in the space 2 between the plates 20 and 40 and finally cross the sleeves 90, whereby protruding from them.
  • Fig. 2 shows the anchoring head 1 just inserted on the strands 10. The installation, which is very simple and fast, consists in approaching the head 1 to the contrast structure CS1 and threading it onto the strands 10 leading out from borehole P1. In particular, in the inserting operation, the strands 10 are inserted through the supporting tubes 80 from the side of the second plate 40 until the first plate 20 abuts against the contrast structure CS1. Conveniently, it is worth noting that the supporting tubes 80 also act as guiding elements, which make it possible to facilitate the positioning of the head on the contrast structure CS1. During the insertion of the strands in the supporting tubes 80, the strands 10 cross, in this order, the tubes 80, the sleeves 90, the second plate 40, the clamps 30, the first plate 20 to then protrude from the supporting tubes 80 from the side of the first plate 20 by a length sufficient to allow the gripping by hydraulic jacks (not shown) for pulling the strands 10. During such insertion operation of the strands 10 in the tubes 80, the second plate 40 is also inserted inside the borehole P1. After having ended the insertion of the strands 10 with the concurrently resting and placement of the first plate 20 on the contrast structure CS1, the method proceeds by pulling out the supporting tubes 80. Fig. 3 shows the anchoring head 1, while the supporting tubes 80 are being pulled out in the senses indicated by the arrows F1, F2, an operation which is performed manually by an operator.
  • Fig. 4 shows the anchoring head in the configuration after having pulled out of the supporting tubes 80 completely. Having pulled off the last tubes 80, the clamps 30 tighten automatically about the strands 10. At this point, with reference to Fig. 5, the strands 10 can be tensioned, preferably by using hydraulic jacks 1500. In particular, Fig. 5 shows the pulling operation of the strands 10 by means of hydraulic jacks 1500. In this regard, it is worth noting that the hydraulic jacks generally available on the market are provided with inner pistons flush with one end of the jacks themselves. In this case, since the clamps 30 must be coupled with the second plate 40, the hydraulic jacks 1500 are jacks provided with modified pistons 1510. In particular, the pistons 1510 are elongated pistons of a predetermined length with respect to the pistons of a traditional jack so they can reach the clamps 30 and push them into the respective holes 401 of the plate 40. According to a preferred embodiment, the pistons 1520 protrude with respect to an end 1520 of the respective jack 1500 by a length equal to about 11cm. In order to couple the clamps 30 with the second plate 40, the pistons 1510 are then inserted in the holes 201 of the plate 20 so as to push the clamps 30 into the holes 401 of the plate 40. The pulling operation with multiple hydraulic jacks 1500 (jack applied to each strand 10 with simultaneous tensioning of the strands 10) ends when each strand 10 is stretched by the predetermined load. During the step of unloading, the clamps 30, pushed by the aforesaid pistons 1510, constrain the strands 10 to the plate 40 and consequently implement the transfer of load from the strands 10 to the plate 40 itself. The latter, being rigidly coupled to the first plate 20 by means of the threaded bar 50 and the stop nut 60, in turn transfers the load to the plate 20 itself, which goes into contrast with the contrast structure CS1.
  • Fig. 6 shows the anchoring head 1 after tensioning and with the clamps 30 wedged into the holes 401 of the plate 40. At this point, the method proceeds with the cutting of the strands 10, preferably flush or substantially flush with the first face 210 of the first plate 20. Fig. 7 shows the step in which the strands 10 are cut by means of the cutting tools L1, L2 diagrammatically shown by means of scissors L1, L2 in Fig. 7. Once having cut the strands 10, the final process of protecting the anchoring head 1 from the atmospheric elements begins.
  • Fig. 8 shows the anchoring head 1 in its final configuration. Having cut the strands 10, in the example substantially flush with plate 20 and coupled the cap 1020, 1030 with the first part 1010 of the outer casing 100, grease G1 is introduced and penetrates through the holes 201 of the first plate 20 into the space 2 between the plates 20 and 40, whereby saturating almost all spaces. Preferably, the grease G1 is introduced through the access opening 1021 of the cap 1020, 1030. The grease G1 thus penetrates even through the clamps 30 until it reaches sheathed part of the strands 10. The first part 1010 of the casing 100 filled with the grease G1 substantially seals the space 2, whereby creating a saturated volume of grease G1. Having filled the space 2, the grease G1 comes out of the holes 201 of the first plate 20. The method then proceeds introducing grease G1 until the entire segment 501 (Fig. 1) of the threaded bar 50 is covered. Finally, the second part 1030 of the cap 1020, 1030 is coupled to the first part 1020 of it so as to close the access opening 1021.
  • It is worth noting that the outer protective casing 100, together with the grease G1, guarantees an optimal protection with compact dimensions, whereby ensuring preservation, e.g. from water infiltrations and corrosion of the metal elements, preferably made of steel, of the head 1.
  • Having described an example of installation method of the anchoring head 1, we will now describe by way of non-limiting example an example of re-tensioning procedure of the strands 10, which as described above may be required in one or more occasions during the working life of the rod 1,10 due to losses of load. From the description that follows it can be readily understood that an anchoring head according to the present description makes it possible to easily manage this requirement.
  • Fig. 9 shows the anchoring head 1 upon re-tensioning which will be performed either with a simple torque wrench K1 by applying an appropriate tightening torque on the stop nut 60 or by a single jack 1600 for bars (said jack 1600 is partially and diagrammatically shown in Fig. 9), unlike the traditional anchoring systems, which are performed with a plurality of hydraulic jacks of the type used for the tensioning the strands 10. In this case, the jack 1600 acts only on the threaded bar 50 so as to pull the bar 50 and the second plate 40 in sense T1 (Fig. 1 or Fig. 6), while the stop nut 60 is engaged to block the bar 50 in the position defined by the jack 1600 by screwing the stop nut 60 onto the bar 50 until the nut 60 engages the first plate 20. With this regard, it is worth noting that an ordinary strand rod may typically be subjected at most to a load loss of 3-4 tons and that, for the purposes of load recovery, 1 cm of elongation during re-tensioning corresponds to about 3-4 tons recovered by the rod itself. So, in order to recover the lost load, which obviously will also depend on the length of the rod itself, a re-tensioning of about 3-4 centimeters will be generally required. An initial distance D1 between the plates 20 and 40 equal to about 7 centimeters can satisfy the aforesaid geometric requirements. Indeed, by applying the tightening torque on the stop nut 60, or by pulling the bar 50 by means of the bar jack 1600, plate 40 approaches the plate 20, which instead remains motionless, pulling the strands 10 and following their elongation.
  • The re-tensioning operation is fundamentally very simple and easily manageable on the construction site. Having removed the cap 1020, 1030 of the outer protective casing 100, the size of which is very small compared to the traditional protective caps (according with an embodiment, the length of the cap 1020, 1030 in the direction of axis X1 is equal to about 10 cm), it will be necessary to remove only a small amount of grease G1 and, for example, use a common and manageable torque wrench to tighten the stop nut 60, whereby determining the translation of the plate 40 towards the plate 20 with the torque applied and the concurrent elongation of the strands 10 which will thus re-acquire the lost load. As mentioned above, as previously mentioned, the re-tensioning may be performed alternatively with the bar jack 1600. Finally, after re-tensioning, the cap 1020, 1030 is repositioned and the small quantity of grease G1 which was previously removed is introduced again.
  • In Fig. 13, an anchoring head for an anchoring rod for geotechnical use according to a further embodiment is globally indicated by reference numeral 1A. The anchoring head 1A differs from the anchoring head 1 described above, exclusively in that it is provided with a key 230 in addition to a first plate 20a and to a connection member 50A, which are slightly modified with respect to the first plate 20 and the connection member 50 of the head 1. In particular, as can be seen in Fig. 13 and Fig. 14, the first plate 20A differs from the first plate 20 in that a housing seat 231 is provided for the key 230. Furthermore, as shown in Fig. 13 and Fig. 15, the connection member 50A differs from the connection member 50 in that is provided on a respective side wall 52a with rectilinear longitudinal groove 53A extending parallel to said central axis X1. Preferably, the groove 53a extends from at least one end face 54a of the connection member 50A. With reference to Fig. 13, the rectilinear longitudinal groove 53A is coupled to the key 230 in such a way that during an axial sliding (axis X1) of the connection member 50A, the key 230 is at least partly received in the longitudinal groove 53A. Conveniently, the key 230 and the groove 53a make it possible to either avoid or reduce the negative effects due to possible torsional stresses on the first plate 20A. Except for the differences discussed above, the structure and the operation of head 1 and of head 1A are substantially and mutually identical. For this reason, for the sake of brevity of description, the structure and the operation of the head 1A will not be described here in further detail.
    On the basis of the above, it is thus possible to understand how an anchoring head according to the present invention makes it possible to achieve the purposes indicated above with reference to the prior art.
  • Indeed, with an anchoring head according to the present description, all the longitudinal reinforcing elements of the rod can be re-tensioned simultaneously simply and quickly either by using a torque wrench or by using alternatively a bar jack. Furthermore, since with an anchoring head according to the present description for re-tensioning the rod it is not necessary to act directly on the longitudinal reinforcing elements by means of hydraulic jacks for the pulling them, the longitudinal reinforcing elements can be cut preferably flush with the plate of the head which rests on the contrast structure, advantageously allowing a significant reduction in the protrusion of the protective cap with respect to the solutions of the prior art. It is apparent that the use of an anchoring head according to the present description implies many advantages in terms of economy, execution time, safety, environment and practice, such as for example:
    • anchoring head with a top protection system of much smaller geometric size, which forms a protrusion, e.g. of about 10 cm, compared to the caps commonly in use, which typically have a height of about 40-60 cm;
    • the disassembly and reassembly of a cap of about 40-60 cm is avoided, the cap being located in an inclined or perpendicular position with to the consolidated wall, inside which a conspicuous amount of liquefied grease is usually contained which can drip and fall by gravity, invading the work platform and/or the underlying areas;
    • the problem of collecting and disposing of the removed grease, the amount of which may be considerable in the case of works having a large number of rods, is reduced;
    • greater guarantees in terms of protection from corrosion and from the infiltration of water with respect to the known anchoring heads;
    • use of a plurality of hydraulic jacks at a height, which is difficult for logistical problems and because, since they are accompanied by bulky and heavy equipment, the presence of at least 2 workers is normally necessary during the steps of re-tensioning;
    • simplicity and speed in the re-tensioning operation of the rod, which can be performed with a common and manageable torque wrench by a single worker;
    • the use of a torque wrench does not presuppose particular technical preparation, which instead may be necessary for the use of hydraulic jacks;
    • modern torque wrenches, in addition to being easy to use, provide the reading in a few seconds and have a more precise reading accuracy than that of the hydraulic jacks;
    • lower environmental impact, because there is less grease to be disposed of;
    • improved appearance (especially on sites of scenic beauty and/or with environmental constraints) due to the small size of the protection system at the top of the heads;
    • shorter on-site execution times with advantages in economic terms and in terms of safety at the workplace.
  • Notwithstanding the principle of the invention, embodiments and details may be greatly varied with respect to that described and illustrated herein exclusively by way of non-limiting example without because of this departing from the scope of protection of the invention as defined in the appended claims.

Claims (15)

  1. An anchoring head (1) for an anchoring rod (1, 10) for geotechnical use, the anchoring rod (1, 10) comprising a plurality of longitudinal reinforcing elements (10) and said head (1) comprising:
    - a first plate (20) having a middle axis (X1) orthogonal to the first plate (20) and first holes (201) configured to be crossed each by a respective longitudinal reinforcing element (10) of said longitudinal reinforcing elements (10);
    - a plurality of locking elements (30), each suitable for being coupled to a respective longitudinal reinforcing element (10) of said longitudinal reinforcing elements (10) and for engaging a respective part (402) of the anchoring head (1) to make said respective longitudinal reinforcing element (10) integral with the anchoring head (1) and transfer a load from said respective longitudinal reinforcing element (10) to the anchoring head (1);
    the anchoring head (1) being characterized in that it comprises:
    - a second plate (40) which is smaller than the first plate (20), the second plate (40) being arranged facing the first plate (20) and comprising a plurality of second holes (401) aligned with said first holes (201), said second holes (401) being provided to be crossed each by a respective longitudinal reinforcing element (10) of said longitudinal reinforcing elements (10);
    - a connection member (50) which crosses the first plate (20) and is connected to the second plate (40) so as to be integral in translation with the second plate (40) in the direction of said middle axis (X1); and
    - a stop element (60) operatively connected to the connection member (50);
    wherein said respective part (402) of the anchoring head (1) suitable for being engaged by a respective locking element (30) of said locking elements (30) is a part (402) of the second plate (40),
    wherein the anchoring head (1) is suitable for taking on a first configuration wherein the first and the second plate (20, 40) are spaced apart from each other by a first axial distance (D1);
    wherein said connection member (50) is suitable for being axially moved in a first direction (T1) so that the anchoring head (1) takes on a second configuration wherein the first and the second plate (20, 40) are spaced apart from each other by a second axial distance which is smaller than said first axial distance (D1);
    said stop element (60) being suitable for engaging the first plate (20) so as to prevent a translation of the connection member (50) and accordingly of the second plate (40) in a second direction (T2) opposite to said first direction (T1).
  2. An anchoring head (1) according to claim 1, wherein said stop element (60) is suitable for axially moving said connection member (50) and accordingly the second plate (40) so as to axially move the first and the second plate (20, 40) close to each other with respect to the first axial distance (D1).
  3. An anchoring head (1) according to claim 1 or 2, wherein the first plate (20) and the second plate (40) comprise each a first face (210, 410) and an opposite second face (220, 420), the second face (220) of the first plate (20) facing the first face (410) of the second plate (40), wherein said stop element (60) is accessible from the side of the first face (210) of the first plate (20).
  4. An anchoring head (1) according to any one of the preceding claims, wherein said connection member (50) comprises a threaded bar (50) and wherein said stop element (60) comprises a stop nut (60) coupled to the threaded bar (50).
  5. An anchoring head (1) according to any one of the preceding claims, comprising an elastic spacer element (70) for keeping the first and the second plate (20, 40) spaced apart from each other, said elastic spacer element (70) being operatively interposed between the first and the second plate (20, 40).
  6. An anchoring head (1) according to claim 5, wherein said elastic spacer element (70) comprises a helical spring (70) fitted on said connection member (50).
  7. An anchoring head (1) according to any one of claims 3 to 6, comprising a plurality of supporting tubes (80) for said locking elements (30), each supporting tube (80) crossing a pair of holes comprising one of said first holes (201) and one of said second holes (401) aligned with each other, each of said supporting tubes (80) being suitable for being crossed by a respective longitudinal reinforcing element (10) of said longitudinal reinforcing elements (10), said locking elements (30) comprising a plurality of self-tightening clamps (30), each of which is coupled to a respective supporting tube (80) of said supporting tubes (80) so as to be crossed by the respective supporting tube (80), said plurality of self-tightening clamps (30) being interposed between the first and the second plate (20, 40).
  8. An anchoring head (1) according to claim 7, wherein said self-tightening clamps (30) and said second holes (401) are shaped so that said clamps (30) may be coupled with said second holes (401) so as to interlock in the second plate (40).
  9. An anchoring head (1) according to claim 7 or 8, comprising a plurality of sleeves (90), each sleeve being fixed to the second plate (40) so as to project from the second face (420) of the second plate (40), each of said sleeves (90) being suitable for being crossed by a respective supporting tube (80) of said supporting tubes (80) .
  10. An anchoring head (1) according to any one of the preceding claims, comprising an outer protective casing (100) suitable for containing therein the first and the second plate (20, 40), the connection member (50), the stop element (60) and the locking elements (30), said outer protective casing (100) comprising a first part (1010) of casing and a cap (1020, 1030) which can be removably coupled to the first part (1010) of casing, said first part (1010) of casing being arranged so as to laterally close a space (2) comprised between the first and the second plate (20, 40).
  11. An anchoring head (1) according to claim 10, wherein said connection member (50) comprises a protruding portion (501) which protrudes past the first face (201) of the first plate (20) on the side opposite to the second plate (40), wherein said cap (1020, 1030) is shaped so as to cover said protruding portion (501) of the connection member (50).
  12. An anchoring head (1) according to claim 11, wherein said cap (1020, 1030) comprises a first part (1020) of cap comprising an access opening (1021) and a second part (1030) of cap which can be removably coupled to the first part (1020) of cap and which serves as plug for closing said access opening (1021).
  13. An anchoring head (1) according to claim 12, wherein said outer protective casing (100) is made of an electrically insulated material.
  14. An anchoring head (1A) according to any one of the preceding claims, comprising a key (230) accommodated in a housing seat (231) provided in the first plate (20A) and wherein the connection member (50A) comprises a side wall (52A) on which there is provided a straight longitudinal groove (53A) extending parallel to said middle axis (X1), said straight longitudinal groove (53A) being coupled to said key (230) so that the key (230) is at least partly received in said longitudinal groove (53A) during an axial sliding of the connection member (50A) .
  15. An anchoring rod (1, 10) comprising an anchoring head (1) as defined in any one of the preceding claims.
EP18169034.8A 2017-04-28 2018-04-24 Anchoring head for an anchoring rod Active EP3396069B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
IT102017000046356A IT201700046356A1 (en) 2017-04-28 2017-04-28 Anchor head for an anchor rod

Publications (2)

Publication Number Publication Date
EP3396069A1 EP3396069A1 (en) 2018-10-31
EP3396069B1 true EP3396069B1 (en) 2020-04-22

Family

ID=60294009

Family Applications (1)

Application Number Title Priority Date Filing Date
EP18169034.8A Active EP3396069B1 (en) 2017-04-28 2018-04-24 Anchoring head for an anchoring rod

Country Status (2)

Country Link
EP (1) EP3396069B1 (en)
IT (1) IT201700046356A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102577895B1 (en) * 2022-08-16 2023-09-13 주식회사 제이제이건설 multipurpose load dispersion style ground anchor assembly

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7244833B2 (en) * 2019-04-26 2023-03-23 国立大学法人 琉球大学 ground anchor head structure
CN115492096A (en) * 2022-09-01 2022-12-20 广西集益建筑科技有限公司 Anchoring rod body mechanism and anchoring structure

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5622015A (en) * 1995-04-12 1997-04-22 Collins; James S. Method and apparatus for consolidating earth and anchor setting device
US6283451B1 (en) * 1998-06-05 2001-09-04 Jennmar Corporation Hydraulic tensioner for mine roof support cables

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
None *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102577895B1 (en) * 2022-08-16 2023-09-13 주식회사 제이제이건설 multipurpose load dispersion style ground anchor assembly

Also Published As

Publication number Publication date
EP3396069A1 (en) 2018-10-31
IT201700046356A1 (en) 2018-10-28

Similar Documents

Publication Publication Date Title
EP3396069B1 (en) Anchoring head for an anchoring rod
US9062457B2 (en) Assembly and method for anchoring rebar to a mass
EP2409001B1 (en) Friction bolt
EP3146122B1 (en) Cap for anchor of post-tension anchorage system
US20060201083A1 (en) Tensioning anchor suitable for blind-hole tendon anchoring and tendon repair
US3632089A (en) Safety barrier post
EA027072B1 (en) Lifting device
KR101852082B1 (en) Re-tensioning anchorage device
US20020098054A1 (en) Expansion bolt
US6634830B1 (en) Method and apparatus for post-tensioning segmented concrete pilings
RU2352720C1 (en) Injection soil threaded anchor with withdrawn bar of screw profile
US7351013B2 (en) Unitary pile jacking sleeve for installing and compressively loading piling without overhead access and without disrupting a super-structure
KR101588860B1 (en) dismantling method of tension member for anchor and apparatus thereof
KR101367640B1 (en) Soil-nailing method for elimination of tension member using manual tension device and fixing unit
EP0545471B1 (en) Method for fixing an anchor for anchoring earth-retaining walls, buildings, bank sheet-pilings, quay walls and the like
JP4253016B2 (en) Tightening method of concrete box in open shield method
EP3309316B1 (en) Sheathing puller
CA1059351A (en) Cable bolt
KR20070068991A (en) Bar type anchor
RU70902U1 (en) INJECTION SOIL ROD ANCHOR WITH REMOVABLE SCREW SCREW PROFILE
KR200277684Y1 (en) anchor for removable anchor
US11174651B1 (en) Tensioning system and method
KR102591042B1 (en) A temporary or permanent anchor capable of tensile and compression and complex of grout materials and of removing tension materials, and its construction method
RU2492295C2 (en) Device to fix building structure in soil and method of fixation and withdrawal of device traction rod from soil
KR101368055B1 (en) Anchor head device

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

RIN1 Information on inventor provided before grant (corrected)

Inventor name: FICHERA, ALFREDO

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20190417

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20191118

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602018003888

Country of ref document: DE

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 1260212

Country of ref document: AT

Kind code of ref document: T

Effective date: 20200515

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: TR-IP CONSULTING LLC, CH

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG4D

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20200422

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200824

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200822

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200723

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200722

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 1260212

Country of ref document: AT

Kind code of ref document: T

Effective date: 20200422

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200722

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602018003888

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200424

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

REG Reference to a national code

Ref country code: BE

Ref legal event code: MM

Effective date: 20200430

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200430

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20210125

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200424

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

REG Reference to a national code

Ref country code: DE

Ref legal event code: R081

Ref document number: 602018003888

Country of ref document: DE

Owner name: COMPONENTI PER GESTIONI INDUSTRIALI SOCIETA' A, IT

Free format text: FORMER OWNER: PROMETEC S.R.L., MARANO DI NAPOLI (NA), IT

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: MT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20200422

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20220424

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20220424

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: SM

Payment date: 20230405

Year of fee payment: 6

Ref country code: FR

Payment date: 20230428

Year of fee payment: 6

Ref country code: DE

Payment date: 20230420

Year of fee payment: 6

Ref country code: CH

Payment date: 20230502

Year of fee payment: 6