EP2642025A1 - Recoverable temporary traverse - Google Patents

Recoverable temporary traverse Download PDF

Info

Publication number
EP2642025A1
EP2642025A1 EP11841208.9A EP11841208A EP2642025A1 EP 2642025 A1 EP2642025 A1 EP 2642025A1 EP 11841208 A EP11841208 A EP 11841208A EP 2642025 A1 EP2642025 A1 EP 2642025A1
Authority
EP
European Patent Office
Prior art keywords
rails
track
main structure
rail
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP11841208.9A
Other languages
German (de)
French (fr)
Other versions
EP2642025B1 (en
EP2642025A4 (en
Inventor
Alejandro Oscar Alvarez-Stein Maso
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of EP2642025A1 publication Critical patent/EP2642025A1/en
Publication of EP2642025A4 publication Critical patent/EP2642025A4/en
Application granted granted Critical
Publication of EP2642025B1 publication Critical patent/EP2642025B1/en
Not-in-force legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • E01B1/004Ballastless track, e.g. concrete slab trackway, or with asphalt layers with prefabricated elements embedded in fresh concrete or asphalt
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/005Making of concrete parts of the track in situ
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B5/00Rails; Guard rails; Distance-keeping means for them
    • E01B5/16Distance keepers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/06Height or lateral adjustment means or positioning means for slabs, sleepers or rails

Definitions

  • the present invention relates to a recoverable temporary traverse applicable in the construction of railway tracks consisting of plates with rails that are not interconnected, and that are anchored by means of block or plate supports with inserts.
  • the rails are held by fixing means that are part of block-shaped supports or plates with inserts that are independent for each rail, which are anchored in place by a setting concrete slab where they are embedded and that holds them when the concrete is set, so in this type of railway it is the setting concrete slab, when hardened, what determines the track gauge, the inclination of the rails, and their position in the space, so that the track and their fittings must be perfectly mounted and positioned before pouring the concrete that will form the slab.
  • a concrete base is firstly poured, on which, once set, the track is assembled by using temporary traverses that are placed every 1.5 to 2 metres away and which are responsible for maintaining the track gauge and the inclination of the rails with respect to the running surface.
  • the track is lifted by jacks, the block supports or plates with insert are hanged to the rails and topographers position the track in that space by making all the necessary corrections.
  • the track is perfectly aligned and levelled, it is maintained in position by means of shims placed under the rails or the supports, or using threaded levelling rods incorporated to the temporary traverses and that maintain the track in place while the concrete, which will form the setting slab, is poured. Once it has set, the temporary traverses are removed.
  • topographic carts used for the track positioning which were created afterwards and that are cars with three support points equipped with rollers that allow for its circulation by the track by taking data along the entire path instead on a point to point basis as it was previously done. This enables topographers to do their job quickly and accurately.
  • the reduced space between the rail foot and the setting slab raise serious challenges, because if the temporary traverses are built in a single piece, then it is necessary to loosen all the rail fixing means in order to lift them and remove the traverses with the aim of recovering them; on the other hand, if they are built divided so they can be removed without having to raise the track just assembled, then they lose stiffness and precision.
  • the attachment of the rails at the rail foot which is the farthest part from the running surface and the active side of the rail, which is where the track parameters must apply, causes the occurrence of deformations that affect the slope of the track and the track gauge, thus complicating the topographer's work and reducing the accuracy of the track.
  • the recoverable temporary traverse of the present invention is characterized in that it comprises a main supporting structure to be placed on the inside of the track between the rails, perpendicularly to the axis thereof, and intended to set the track gauge, the inclination of the rails with respect to the running surface and to maintain the rails and stands in the proper position while the setting concrete, which forms the slab, hardens, and at least one pair of secondary elements to be placed from each of the outer faces of the track by passing beneath the rails in order to be temporarily attached to the main structure and intended to press the rails against the main structure by fixing them to it, thus ensuring their correct position.
  • the main supporting structure is formed by at least one piece where their vertices form a rectangle perpendicularly oriented to the ground, and in the two upper corners of which are angular shaped housings in which a portion of the inner lower corners of the rail head is inserted and supported, and in the two lower corners of which are other angular shaped housings in which a portion of the inner upper corners of the rail foot is inserted and supported.
  • this main structure has two main anchoring systems located at its bottom and intended for the temporary attachment of the secondary parts.
  • This main structure may also have at least two mechanisms for regulating the height of the structure with respect to the concrete base on which the track is assembled.
  • This arrangement allows for the rails to rest against the main structure at two points, one located at the rail head just below the point where the track gauge is measured thus ensuring this, the other located at the corner of the rail foot, that is, the point situated on the same side of the farthest rail from the previous one and therefore ensuring as greater accurately as possible in the inclination angle of the rails. Furthermore, as the rail is engaged by the upper and lower housings of the main structure, it is impossible that a vertical sliding occurs between the main structure and the track in case the track were maintained in an elevated position through temporary traverses provided with mechanism for adjusting the height of the structure.
  • This arrangement also allows for the main support structure to be extracted from the recently assembled track by turning and rotating it, thus making unnecessary to remove any element in the track to facilitate the removal thereof and decreasing the work, increasing the accuracy of the track parameters, while allowing, if desired, the main structure for being made in a single piece, what eliminates potential errors in manufacturing and in the assembly of the joints, increasing the accuracy of the track and making cheaper the manufacture of both, the temporary traverse and the track.
  • the supporting substructure of the height adjusting mechanisms has been provided with at least one sliding mechanism of the main supporting structure and at least a mechanism for adjusting and fixing the position thereof on the substructure.
  • Secondary angle parts whose wings form an angle of about 90 degrees are also provided. These pieces have, at the end of the lower wing, an anchoring element which allows to temporarily fixing them to the anchors provided for this purpose on the main frame passing beneath the rail through the space existing between the setting concrete and the bottom face of the rail foot. They also have, at the end of the vertical wing, a tightening mechanism intended to push the rail from the outside of the track by supporting it at its ends against the housings of the main structure. Furthermore, this wing includes at least one projection, situated under the tightening mechanism and intended to rest on the upper and outer face of the rail foot and to prevent the secondary part from sliding from the anchoring element of the main structure because of the pressure mechanism action on the rail by pushing it against the main structure.
  • This arrangement allows to attach the rails to the main support structure in a solid and accurate way as it allows for the rails to be pressured against the angular housings of the main supporting structure, but without interfering in any way with the running surface, thereby enabling the use of topography carts, what facilitates the work of topographers and increases the accuracy of the track parameters. Additionally, as they are separate pieces that can be easily assembled and disassembled, they allow the main structure to be extracted from the recently assembled track by turning and rotating it without the need to disassemble any of its parts.
  • the recoverable temporary traverse comprises: a main supporting structure (1), secondary pieces (2) intended to hook onto the opposite ends of the main structure (1) and a tightening mechanism (10), made of screws mounted on said secondary parts and laterally pushing the rails (12) of the track against the opposite ends of the main structure by establishing a fixed separation and inclination of said rails (12).
  • the main supporting structure (1) located on the inside of the track between the rails (12) is intended to maintain the track gauge and inclination of the rails (12) while the setting concrete (21), which will definitely attach the track to said concrete base (22), hardens.
  • the main supporting structure (1) is formed by a flattened piece, in this case, a cast piece, perpendicularly oriented to the ground and having, at its opposite ends, upper housings (3), of angular shape, into which a portion of the inner lower corners of the heads (13) of the rails (12) are inserted and supported, and other lower housings (4), of angular shape, into which a portion of the inner upper corners of the foot (14) of the rails (12) are inserted and supported.
  • this main structure (1) has two hook-shaped anchoring systems (5) located at its bottom and intended for the temporary attachment of the secondary parts (2).
  • This main structure (1) also have two height adjusting mechanisms (6) for adjusting the height of the structure with respect to the concrete base (22) on which the track is mounted.
  • the secondary parts (2) have two wings (7, 9) which, in the example shown, form an angle of about 90 degrees.
  • These secondary parts (2) have, at the end of the lower wing (7), a housing (8) which allows to temporarily attach them to the hook-like anchoring elements (5) of the main structure (1); said lower wings (7) passing beneath the rails (12) without interfering in the running surface (23).
  • Said secondary parts (2) also have, at the end of the wing vertically located (9), a tightening mechanism (10), represented in this case by a screw, intended to push the rail (12) from the outside of the track by supporting it at its ends against the housings (3, 4) of the main structure (1).
  • a tightening mechanism (10) represented in this case by a screw, intended to push the rail (12) from the outside of the track by supporting it at its ends against the housings (3, 4) of the main structure (1).
  • this vertically positioned wing (9) includes a projection (11) intended to rest on the upper and outer face of the rail foot (14) and prevent that the secondary piece (2) swing from the anchoring element (5) of the main structure (1) upon actuation of the tightening mechanism (10) on the rail (12) when pushing it against the main structure (1).
  • Figures 5 and 6 represent a schematic elevation ( Fig. 5 ) and plan ( Fig. 6 ) view of the turning (15) and rotation (16) movements to be performed by the traverse of the invention in order to be removed from the rails once its task has finished, in case its main supporting structure (1) is made in a single piece without detachable joints.
  • the height adjusting mechanisms (6) can have different configurations.
  • said height adjusting mechanisms (6) are constituted by threaded rods mounted on two drilled and threaded housings that vertically pass through the axis of the main structure (1), so that they allow for the regulation of the height of the main structure and of the track on the concrete base (22).
  • the height adjusting mechanisms (6) are integrated in a substructure (17) situated between the rails and independent from the main supporting structure (1). These height adjusting means allow for keeping the rails (12) and their supporting elements (20) elevated and in position on the concrete base (22) while the setting concrete (21), which is intended to definitely attach the track, hardens.
  • This substructure (17) also incorporates sliding mechanisms (18) and a position locking mechanism (19) allowing the cross movement of the main supporting structure (1) and of the track, thus facilitating the alignment of the latter.
  • the sliding mechanism in the cross direction and the locking mechanism of the substructure (17), which has the height adjusting mechanism are constituted by an adjustable tensioner (24) that is attached at one of its ends to said substructure (17) and at its opposite end to the main structure (1).
  • the vertical wing (9) does not have the projection intended to rest on the upper and outer surface of the rail foot (14), having, however, the lower wing (7) of each of the secondary parts (2) two housings (8) for being hooked onto the respective pairs of anchoring elements (5) defined at the lower areas of the respective ends of the main structure.
  • This double anchor prevents the swinging of the secondary parts (2) with respect to the main structure (1) during the pushing of the rails (12) against said main structure by means of the tightening mechanisms (10).

Abstract

The invention is applicable in the construction of tracks consisting of plates with rails that are not interconnected, in order to fix the geometry of the track while the concrete hardens, which maintains the track in its definitive position, without interfering in the running surface. The invention comprises at least. A main structure (1) arranged between the rails (12) and provided with housings (3) and (4) into which part of the rails (12) is introduced, and anchoring elements (5) for fixing secondary parts (2) the pass beneath the rail, tightening said rail against the main structure (1). In addition, the main structure can comprise height adjusting mechanisms (6). The main structure (1) is designed in such a way that it can be turned and rotated in order to be extracted from between the rails (12). Furthermore, the height adjusting mechanisms (6) are independent from the main structure (1) and are built into a supporting substructure (17) arranged between the rails (12), enabling the displacement of the track.

Description

    Object of the invention
  • The present invention relates to a recoverable temporary traverse applicable in the construction of railway tracks consisting of plates with rails that are not interconnected, and that are anchored by means of block or plate supports with inserts.
  • State of the art
  • Currently, the construction of railways by means of the so-called plate tracks with rails that are not interconnected and that are anchored by means of block or plate supports with inserts is becoming more common.
  • In this type of railway, the rails are held by fixing means that are part of block-shaped supports or plates with inserts that are independent for each rail, which are anchored in place by a setting concrete slab where they are embedded and that holds them when the concrete is set, so in this type of railway it is the setting concrete slab, when hardened, what determines the track gauge, the inclination of the rails, and their position in the space, so that the track and their fittings must be perfectly mounted and positioned before pouring the concrete that will form the slab. To do this, generally a concrete base is firstly poured, on which, once set, the track is assembled by using temporary traverses that are placed every 1.5 to 2 metres away and which are responsible for maintaining the track gauge and the inclination of the rails with respect to the running surface. Then, the track is lifted by jacks, the block supports or plates with insert are hanged to the rails and topographers position the track in that space by making all the necessary corrections. When the track is perfectly aligned and levelled, it is maintained in position by means of shims placed under the rails or the supports, or using threaded levelling rods incorporated to the temporary traverses and that maintain the track in place while the concrete, which will form the setting slab, is poured. Once it has set, the temporary traverses are removed.
  • When this type of tracks began to be used, temporary traverse were built lying on the running surface and covering the rail above its head and which, by means of screw, tightly pressed the active side of the rail head and the internal end of the rail foot against the central part of the traverse, thus keeping the rail in the suitable position and preventing it from sliding in case the track were held high by temporary traverses provided with levelling rods. These traverses, being constructed by forming a single piece, were solid and precise, and, as they were removed upwards, they were easy to disassemble. However, as they interfere with the running surface, they prevent the circulation and therefore the use of topographic carts used for the track positioning, which were created afterwards and that are cars with three support points equipped with rollers that allow for its circulation by the track by taking data along the entire path instead on a point to point basis as it was previously done. This enables topographers to do their job quickly and accurately.
  • To solve this problem other temporary traverses were designed that position each rail by holding it from the rail foot and allow for the circulation of topography carts but causing other problems. This type of traverses has lost much of its rigidity in the vertical direction because, in most rail tracks of this kind, there are only 25 or 30 millimetres between the setting concrete and the rail foot, which has forced to construct them very thin in the direction where they have to perform a greater effort. Furthermore, the reduced space between the rail foot and the setting slab raise serious challenges, because if the temporary traverses are built in a single piece, then it is necessary to loosen all the rail fixing means in order to lift them and remove the traverses with the aim of recovering them; on the other hand, if they are built divided so they can be removed without having to raise the track just assembled, then they lose stiffness and precision. Moreover, the attachment of the rails at the rail foot, which is the farthest part from the running surface and the active side of the rail, which is where the track parameters must apply, causes the occurrence of deformations that affect the slope of the track and the track gauge, thus complicating the topographer's work and reducing the accuracy of the track.
  • It would be therefore desirable to conceive a new kind of recoverable temporary traverse that does not interfere in the circulation of topography carts, ensures the track gauge and the inclination of the rails with respect to the running surface and allows for an easy disassembly without having to move the rails for removal.
  • Description of the invention
  • In order to offer a solution to the above problems presented by the hitherto known temporary traverses, a recoverable temporary traverse having a new structure and functionality is provided.
  • The recoverable temporary traverse of the present invention is characterized in that it comprises a main supporting structure to be placed on the inside of the track between the rails, perpendicularly to the axis thereof, and intended to set the track gauge, the inclination of the rails with respect to the running surface and to maintain the rails and stands in the proper position while the setting concrete, which forms the slab, hardens, and at least one pair of secondary elements to be placed from each of the outer faces of the track by passing beneath the rails in order to be temporarily attached to the main structure and intended to press the rails against the main structure by fixing them to it, thus ensuring their correct position.
  • The main supporting structure is formed by at least one piece where their vertices form a rectangle perpendicularly oriented to the ground, and in the two upper corners of which are angular shaped housings in which a portion of the inner lower corners of the rail head is inserted and supported, and in the two lower corners of which are other angular shaped housings in which a portion of the inner upper corners of the rail foot is inserted and supported. Moreover, this main structure has two main anchoring systems located at its bottom and intended for the temporary attachment of the secondary parts. This main structure may also have at least two mechanisms for regulating the height of the structure with respect to the concrete base on which the track is assembled.
  • This arrangement allows for the rails to rest against the main structure at two points, one located at the rail head just below the point where the track gauge is measured thus ensuring this, the other located at the corner of the rail foot, that is, the point situated on the same side of the farthest rail from the previous one and therefore ensuring as greater accurately as possible in the inclination angle of the rails. Furthermore, as the rail is engaged by the upper and lower housings of the main structure, it is impossible that a vertical sliding occurs between the main structure and the track in case the track were maintained in an elevated position through temporary traverses provided with mechanism for adjusting the height of the structure. This arrangement also allows for the main support structure to be extracted from the recently assembled track by turning and rotating it, thus making unnecessary to remove any element in the track to facilitate the removal thereof and decreasing the work, increasing the accuracy of the track parameters, while allowing, if desired, the main structure for being made in a single piece, what eliminates potential errors in manufacturing and in the assembly of the joints, increasing the accuracy of the track and making cheaper the manufacture of both, the temporary traverse and the track.
  • It should be noted that, in some cases, in order to facilitate the alignment of the track, it may be interesting to separate the height adjusting mechanisms and to integrate them into a substructure independent from the main structure in order to allow that said main structure and the track supported by it to move transversely without the need to move said adjusting mechanisms. For this purpose, the supporting substructure of the height adjusting mechanisms has been provided with at least one sliding mechanism of the main supporting structure and at least a mechanism for adjusting and fixing the position thereof on the substructure.
  • Secondary angle parts whose wings form an angle of about 90 degrees are also provided. These pieces have, at the end of the lower wing, an anchoring element which allows to temporarily fixing them to the anchors provided for this purpose on the main frame passing beneath the rail through the space existing between the setting concrete and the bottom face of the rail foot. They also have, at the end of the vertical wing, a tightening mechanism intended to push the rail from the outside of the track by supporting it at its ends against the housings of the main structure. Furthermore, this wing includes at least one projection, situated under the tightening mechanism and intended to rest on the upper and outer face of the rail foot and to prevent the secondary part from sliding from the anchoring element of the main structure because of the pressure mechanism action on the rail by pushing it against the main structure.
  • This arrangement allows to attach the rails to the main support structure in a solid and accurate way as it allows for the rails to be pressured against the angular housings of the main supporting structure, but without interfering in any way with the running surface, thereby enabling the use of topography carts, what facilitates the work of topographers and increases the accuracy of the track parameters. Additionally, as they are separate pieces that can be easily assembled and disassembled, they allow the main structure to be extracted from the recently assembled track by turning and rotating it without the need to disassemble any of its parts.
  • The features disclosed in the recoverable temporary traverse for tracks in plates with anchoring by means of blocks or plates with inserts provide a solution to the drawbacks described above presented by the temporary traverses previously known.
  • Description of the drawings
  • With the aim of facilitating the understanding of the invention described herein some explanatory drawings have been included.
  • These drawings represent an embodiment schematic example of the recoverable temporary traverse object of the present invention.
    • Figures 1, 2, and 3 represent the temporary traverse according to the present invention, seen respectively in a front elevation (Fig. 1), side elevation (Fig. 2) and plan (Fig. 3) view.
    • Figure 4 represents an enlarged detail of the attachment of the rail to the temporary traverse.
    • Figures 5 and 6 represent, respectively, a schematic elevation and plan view of the turning and rotation movements to be performed by the traverse of the invention in order to be removed from the rails.
    • Figures 7 and 8 are respective front elevation (Fig. 7) and plan (Fig. 8) views of an alternative embodiment of the temporary traverse of the invention in which the height adjusting mechanisms (6) have been integrated on a substructure (17) independent of the main support structure (1).
    • Figures 9 and 10 show elevation (Fig. 9) and top plan (Fig. 10) views of an embodiment variant of the temporary traverse in which the height adjusting mechanisms are integrated into one independent substructure of the main supporting structure and connected with it by means of a regulating and locking system, in this case a tensioner for the relative attachment in the cross direction.
    Preferred embodiment of the invention
  • In the example shown in the accompanying figures, the recoverable temporary traverse comprises: a main supporting structure (1), secondary pieces (2) intended to hook onto the opposite ends of the main structure (1) and a tightening mechanism (10), made of screws mounted on said secondary parts and laterally pushing the rails (12) of the track against the opposite ends of the main structure by establishing a fixed separation and inclination of said rails (12).
  • The main supporting structure (1) located on the inside of the track between the rails (12) is intended to maintain the track gauge and inclination of the rails (12) while the setting concrete (21), which will definitely attach the track to said concrete base (22), hardens.
  • The main supporting structure (1) is formed by a flattened piece, in this case, a cast piece, perpendicularly oriented to the ground and having, at its opposite ends, upper housings (3), of angular shape, into which a portion of the inner lower corners of the heads (13) of the rails (12) are inserted and supported, and other lower housings (4), of angular shape, into which a portion of the inner upper corners of the foot (14) of the rails (12) are inserted and supported.
  • Furthermore, this main structure (1) has two hook-shaped anchoring systems (5) located at its bottom and intended for the temporary attachment of the secondary parts (2).
  • This main structure (1) also have two height adjusting mechanisms (6) for adjusting the height of the structure with respect to the concrete base (22) on which the track is mounted.
  • The secondary parts (2) have two wings (7, 9) which, in the example shown, form an angle of about 90 degrees.
  • These secondary parts (2) have, at the end of the lower wing (7), a housing (8) which allows to temporarily attach them to the hook-like anchoring elements (5) of the main structure (1); said lower wings (7) passing beneath the rails (12) without interfering in the running surface (23).
  • Said secondary parts (2) also have, at the end of the wing vertically located (9), a tightening mechanism (10), represented in this case by a screw, intended to push the rail (12) from the outside of the track by supporting it at its ends against the housings (3, 4) of the main structure (1).
  • Furthermore, in the exemplary embodiments shown in Figures 1 to 8, this vertically positioned wing (9) includes a projection (11) intended to rest on the upper and outer face of the rail foot (14) and prevent that the secondary piece (2) swing from the anchoring element (5) of the main structure (1) upon actuation of the tightening mechanism (10) on the rail (12) when pushing it against the main structure (1).
  • Figures 5 and 6 represent a schematic elevation (Fig. 5) and plan (Fig. 6) view of the turning (15) and rotation (16) movements to be performed by the traverse of the invention in order to be removed from the rails once its task has finished, in case its main supporting structure (1) is made in a single piece without detachable joints.
  • As can be seen in the accompanying figures, the height adjusting mechanisms (6) can have different configurations.
  • Specifically, in the embodiments shown in Figures 1 to 6, said height adjusting mechanisms (6) are constituted by threaded rods mounted on two drilled and threaded housings that vertically pass through the axis of the main structure (1), so that they allow for the regulation of the height of the main structure and of the track on the concrete base (22).
  • In Figures 7 and 8, the height adjusting mechanisms (6) are integrated in a substructure (17) situated between the rails and independent from the main supporting structure (1). These height adjusting means allow for keeping the rails (12) and their supporting elements (20) elevated and in position on the concrete base (22) while the setting concrete (21), which is intended to definitely attach the track, hardens.
  • This substructure (17) also incorporates sliding mechanisms (18) and a position locking mechanism (19) allowing the cross movement of the main supporting structure (1) and of the track, thus facilitating the alignment of the latter.
  • In the illustrative embodiment shown in Figures 9 and 10, the sliding mechanism in the cross direction and the locking mechanism of the substructure (17), which has the height adjusting mechanism, are constituted by an adjustable tensioner (24) that is attached at one of its ends to said substructure (17) and at its opposite end to the main structure (1).
  • In said Figures 9 and 10, the vertical wing (9) does not have the projection intended to rest on the upper and outer surface of the rail foot (14), having, however, the lower wing (7) of each of the secondary parts (2) two housings (8) for being hooked onto the respective pairs of anchoring elements (5) defined at the lower areas of the respective ends of the main structure. This double anchor prevents the swinging of the secondary parts (2) with respect to the main structure (1) during the pushing of the rails (12) against said main structure by means of the tightening mechanisms (10).

Claims (6)

  1. Recoverable temporary traverse applicable in the construction of railway tracks on plates with rails that are not interconnected and anchored by means of block or plate supports with inserts, and intended to attach and position in a given space rails (12) provided with a head (13) and a foot (14) defining a running surface and forming a track and anchoring supports (20) thereof while performing a mounting, levelling and alignment process of the track and pouring and hardening on a concrete base (22) a setting concrete (21) that will definitively secure said track in a position, characterized in that it comprises:
    - a main supporting structure (1) intended to be placed between the rails (12) perpendicularly to the axis of the track, said main structure having, at its opposite ends, upper housings (3) wherein at least one portion of the heads (13) of the rails (12) are inserted and are laterally and vertically supported, and lower housings (4) wherein at least one portion of the feet (14) of the respective rails (12) are laterally and vertically supported in a given position, said main structure (1) having at least two anchoring systems (5) for temporary attaching secondary parts (2);
    - at least two secondary parts (2) having: a lower wing (7) provided with a housing (8) or the like for temporary attachment to at least one anchoring system (5) of respective lateral end of the main structure (1) and intended to be positioned beneath the corresponding rail (12) without interference with a running surface (23) of the track, and an vertical wing (9) arranged on the outer side of the corresponding rail (12),
    - tightening mechanisms (10) mounted on the vertical wings (9) of the secondary parts (2) and intended to push the rails (12) from the outer side of the track against the housings (3, 4) of the main structure (1); said main structure (1) determining, in the pushing operating position of the tightening mechanisms (10), the track gauge and the inclination of the rails (12) with respect to the running surface (23).
  2. Recoverable temporary traverse, according to claim 1, characterized in that it comprises at least two main structure (1) height adjusting mechanisms (6) for keeping the rails (12) and supports (20) thereof at a suitable height and position relative to the concrete base (22) during hardening of the setting concrete (21) that definitely secures the supports (20) on said concrete base (22).
  3. Recoverable temporary traverse according to claim 2, characterized in that the height adjusting mechanisms (6) are located at the ends of the main structure (1).
  4. Recoverable temporary traverse according to any of the preceding claims, characterized in that the vertical wing (9) of the secondary parts has at least one projection (11) located beneath the tightening mechanism (10) and intended to rest on an upper face of the rail foot (14) and prevent the secondary part (2) from swinging from the anchoring system (5) of the main structure (1) while the tightening mechanism (10) actuates sidewards against the rail (12) and pushes against the main structure (1).
  5. Recoverable temporary traverse according to claim 1, characterized in that the main supporting structure (1) is formed by a single part without detachable attachments, wherein the housings (3, 4) for lateral support of the heads (13) and feet (14) of the respective rails (12) have vertical faces arranged parallel to one another, so as to allow to turn (15) the main structure (1) over in the same direction as the axis of the rails (12) and then rotate it (16) to be removed from between the rails of the track.
  6. Recoverable temporary traverse according to any of claims 1 and 2, characterized in that the height adjusting mechanisms (6) are independent from the main structure (1) and are incorporated into a supporting substructure (17) located between the rails and equipped with a sliding and guiding mechanism (18) and a position locking mechanism (19) allowing the main structure (1) to be moved transversally relative to the height adjusting mechanisms and the track to be alligned without having to move the supporting substructure (17).
EP11841208.9A 2010-11-16 2011-11-14 Recoverable temporary traverse Not-in-force EP2642025B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
ES201001489A ES2387965B1 (en) 2010-11-16 2010-11-16 RECOVERY PROVISIONAL TRAVIESA.
PCT/ES2011/000336 WO2012066163A1 (en) 2010-11-16 2011-11-14 Recoverable temporary traverse

Publications (3)

Publication Number Publication Date
EP2642025A1 true EP2642025A1 (en) 2013-09-25
EP2642025A4 EP2642025A4 (en) 2014-09-10
EP2642025B1 EP2642025B1 (en) 2015-08-26

Family

ID=46083517

Family Applications (1)

Application Number Title Priority Date Filing Date
EP11841208.9A Not-in-force EP2642025B1 (en) 2010-11-16 2011-11-14 Recoverable temporary traverse

Country Status (4)

Country Link
EP (1) EP2642025B1 (en)
AR (1) AR083890A1 (en)
ES (2) ES2387965B1 (en)
WO (1) WO2012066163A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104594143A (en) * 2014-12-03 2015-05-06 西南交通大学 Inner supporting type screw adjuster and track skeleton positioning method
CN109183522A (en) * 2018-10-12 2019-01-11 株洲时代新材料科技股份有限公司 A kind of floating board connecting equipment of prefabricated and its construction method

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2499862C2 (en) * 2012-01-30 2013-11-27 Открытое акционерное общество Научно-внедренческий центр "Путевые машины" Device to lay rail lengths
CN103410060B (en) * 2013-08-15 2016-01-20 中铁四局集团有限公司 A kind of emergency hand turn-out track equipment for city rail track switch
CN105442399B (en) * 2015-12-28 2017-07-04 上海市安装工程集团有限公司 Track assembles supporting trolley and track assemble method
CN106436499B (en) * 2016-11-01 2019-01-22 五冶集团上海有限公司 A kind of streetcar track mounting device and its installation and application
CN111395055A (en) * 2020-03-16 2020-07-10 中铁上海工程局集团有限公司 Construction method of track integral ballast bed
CN114541198B (en) * 2022-01-29 2024-01-16 陈福杰 Battery car track displacement adjusting device in subway tunnel
CN115467200B (en) * 2022-08-16 2024-02-02 中铁四局集团第五工程有限公司 Power track panel adjusting device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2000044987A1 (en) * 1999-01-30 2000-08-03 Bahnbau Wels Gmbh Device for the height and lateral alignment and/or support of the rails of a railway track
WO2003066964A1 (en) * 2002-02-02 2003-08-14 Rte Technologie Gmbh Device for adjusting the width of a track
WO2004065692A1 (en) * 2003-01-21 2004-08-05 Pfleiderer Infrastrukturtechnik Gmbh & Co. Kg Screw device for high-adjusting a track span
JP2007132043A (en) * 2005-11-09 2007-05-31 Hosen Kiki Seibi Kk Rail jacking-up device
CN201151857Y (en) * 2007-12-29 2008-11-19 南车洛阳机车有限公司 Manual adjustment crossbeam of double block type ballastless track construction equipment

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2258804T3 (en) * 1997-09-18 2006-09-01 PFLEIDERER INFRASTRUKTURTECHNIK GMBH & CO. KG PROCEDURE FOR THE CONSTRUCTION OF A FIXED ROAD BANK FOR GUIDED TRAFFICKING ON RAILS, AS WELL AS A FIXED VIA BANK TO CARRY OUT THE PROCEDURE.
DE102004019275B4 (en) * 2004-04-21 2006-09-07 Pfleiderer Infrastrukturtechnik Gmbh & Co. Kg System formwork for transverse joints on fixed carriageways

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2000044987A1 (en) * 1999-01-30 2000-08-03 Bahnbau Wels Gmbh Device for the height and lateral alignment and/or support of the rails of a railway track
WO2003066964A1 (en) * 2002-02-02 2003-08-14 Rte Technologie Gmbh Device for adjusting the width of a track
WO2004065692A1 (en) * 2003-01-21 2004-08-05 Pfleiderer Infrastrukturtechnik Gmbh & Co. Kg Screw device for high-adjusting a track span
JP2007132043A (en) * 2005-11-09 2007-05-31 Hosen Kiki Seibi Kk Rail jacking-up device
CN201151857Y (en) * 2007-12-29 2008-11-19 南车洛阳机车有限公司 Manual adjustment crossbeam of double block type ballastless track construction equipment

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of WO2012066163A1 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104594143A (en) * 2014-12-03 2015-05-06 西南交通大学 Inner supporting type screw adjuster and track skeleton positioning method
CN109183522A (en) * 2018-10-12 2019-01-11 株洲时代新材料科技股份有限公司 A kind of floating board connecting equipment of prefabricated and its construction method

Also Published As

Publication number Publication date
ES2387965A1 (en) 2012-10-04
EP2642025B1 (en) 2015-08-26
EP2642025A4 (en) 2014-09-10
WO2012066163A1 (en) 2012-05-24
ES2553614T3 (en) 2015-12-10
AR083890A1 (en) 2013-03-27
ES2387965B1 (en) 2013-08-09

Similar Documents

Publication Publication Date Title
EP2642025B1 (en) Recoverable temporary traverse
KR101052906B1 (en) Precast slab track system and method constructing the same
CN202170456U (en) Construction device of ballastless track
CN106758879B (en) A method of for runing the correction of high-speed railway bridge ballastless track structure
CA3065809A1 (en) Support head having a lowerable mounting height for a formwork support
ES2912777T3 (en) Alignment device for aligning rails in track construction
CN204151820U (en) Stone bolt location and installation support
CN108708292A (en) A kind of I-shaped steel reinforced concrete combination beam concrete folding constructing device and construction method
EP1441066B1 (en) Support device for prefabricated concrete slabs of a track for magnetically levitated trains
CN207047889U (en) A kind of device for installing forging machine main frame embedded part
EP4182504A1 (en) Slab track adjustment plate and method of installation
CA2564931C (en) Device for adjusting a track structure and switches
CN110900820B (en) Construction device and construction method for self-adaptive post-tensioning prefabricated box girder
CN100547161C (en) The bearing calibration of concrete prefabricated structural board and position thereof and adjuster
KR101493313B1 (en) A form for 3D precast slab track manufacturing device
CN220767629U (en) Adjustable anti-collision wall and flower groove synchronous cast-in-situ template
JP3315101B2 (en) Track measuring instrument for track laying and track slab measuring instrument
CN220266319U (en) Four-corner leveling bolt shaping steel mould
CN212176531U (en) Building engineering concatenation construction templates
CN216992380U (en) Embedded steel plate sand pit gradient adjusting mechanism for box girder prefabricating pedestal
JP2518797B2 (en) Construction method of labor-saving track using standard device for track alignment and measuring device
CN209892229U (en) Widened steel frame device of strip steel mold trolley
EP3305984B1 (en) Device for positioning rails
US20230323608A1 (en) Bridge for a Rail Vehicle and Method for Assembling a Bridge Beam on Such a Bridge
CN217378417U (en) Track fixing device

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20130611

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

DAX Request for extension of the european patent (deleted)
A4 Supplementary search report drawn up and despatched

Effective date: 20140812

RIC1 Information provided on ipc code assigned before grant

Ipc: E01B 5/16 20060101ALI20140806BHEP

Ipc: E01B 29/02 20060101ALI20140806BHEP

Ipc: E01B 29/24 20060101ALI20140806BHEP

Ipc: E01B 29/00 20060101ALI20140806BHEP

Ipc: E01B 1/00 20060101AFI20140806BHEP

Ipc: E01B 29/04 20060101ALI20140806BHEP

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

INTG Intention to grant announced

Effective date: 20150330

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 745255

Country of ref document: AT

Kind code of ref document: T

Effective date: 20150915

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602011019277

Country of ref document: DE

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: RECHTSANWALT DR. ALEXANDER MILLER, LL.M, CH

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 5

REG Reference to a national code

Ref country code: ES

Ref legal event code: FG2A

Ref document number: 2553614

Country of ref document: ES

Kind code of ref document: T3

Effective date: 20151210

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 745255

Country of ref document: AT

Kind code of ref document: T

Effective date: 20150826

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG4D

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20151126

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20150826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20151226

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20151228

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602011019277

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: LU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20151114

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20160406

Year of fee payment: 5

26N No opposition filed

Effective date: 20160530

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20151114

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 6

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20111114

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161130

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 7

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150826

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20181113

Year of fee payment: 8

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: ES

Payment date: 20181203

Year of fee payment: 8

Ref country code: GB

Payment date: 20181121

Year of fee payment: 8

Ref country code: FR

Payment date: 20181120

Year of fee payment: 8

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 602011019277

Country of ref document: DE

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20191114

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191114

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200603

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191130

REG Reference to a national code

Ref country code: ES

Ref legal event code: FD2A

Effective date: 20210528

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191115