Construction, method for manufacturing construction and use of construction Download PDF

Info

Publication number
EP2292304A1
EP2292304A1 EP10172722A EP10172722A EP2292304A1 EP 2292304 A1 EP2292304 A1 EP 2292304A1 EP 10172722 A EP10172722 A EP 10172722A EP 10172722 A EP10172722 A EP 10172722A EP 2292304 A1 EP2292304 A1 EP 2292304A1
Authority
EP
European Patent Office
Prior art keywords
construction
frame
meshwork
pieces
subframe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP10172722A
Other languages
German (de)
French (fr)
Inventor
Tero Saarinen
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lujitusteknllkka Oy
Original Assignee
Lujitusteknllkka Oy
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lujitusteknllkka Oy filed Critical Lujitusteknllkka Oy
Publication of EP2292304A1 publication Critical patent/EP2292304A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • AHUMAN NECESSITIES
    • A63SPORTS; GAMES; AMUSEMENTS
    • A63BAPPARATUS FOR PHYSICAL TRAINING, GYMNASTICS, SWIMMING, CLIMBING, OR FENCING; BALL GAMES; TRAINING EQUIPMENT
    • A63B69/00Training appliances or apparatus for special sports
    • A63B69/0048Training appliances or apparatus for special sports for mountaineering, e.g. climbing-walls, grip elements for climbing-walls
    • AHUMAN NECESSITIES
    • A63SPORTS; GAMES; AMUSEMENTS
    • A63BAPPARATUS FOR PHYSICAL TRAINING, GYMNASTICS, SWIMMING, CLIMBING, OR FENCING; BALL GAMES; TRAINING EQUIPMENT
    • A63B9/00Climbing poles, frames, or stages
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • AHUMAN NECESSITIES
    • A63SPORTS; GAMES; AMUSEMENTS
    • A63BAPPARATUS FOR PHYSICAL TRAINING, GYMNASTICS, SWIMMING, CLIMBING, OR FENCING; BALL GAMES; TRAINING EQUIPMENT
    • A63B2209/00Characteristics of used materials

Abstract

The invention relates to a construction (1), which is lattice-like, and which construction includes a frame, which frame comprises several tubular and/or beam-like support pieces (6, 7, 11) which are directly or indirectly fitted in an elongated frame piece (2), and the frame is fitted with a support structure (15), such as support reinforcement, and which construction (1) is fitted with a meshwork (10), such as a steel meshwork, such that the meshwork is fastened in a subframe (14) and/or the frame and/or the support structure (15), and which subframe comprises at least one tubular and/or beam-like piece (5) which is fitted in the support pieces (6, 7, 11) and/or the frame piece, and which meshwork is coated with sprayed concrete. The invention also relates to a use and a method of the construction.

Description

    Background of invention
  • The invention relates to a construction according to the preamble of claim 1. The invention also relates to a method for manufacturing the construction according to the preamble of claim 6. The invention further relates to using the construction according to the invention and the construction manufactured with the method according to the invention.
  • Of prior art, several different constructions are known which can be employed e.g. as climbing constructions or support constructions or for some other use.
  • A construction is described e.g. in an arrangement presented by specification FR2837397 which depicts a construction, and in more detail a climbing construction, which consists of several laminar parts which are connected with connecting parts to each other, and of which laminar parts are thus formed box-like pieces, and which box-like pieces are then set one on the other. In the arrangement according to the specification, the box-like pieces are coated with concrete the purpose of which is to 'imitate' a rock face.
  • Arrangements according to known prior art include some disadvantages. A disadvantage of constructions according to known arrangements is that the coating of the constructions with concrete occurs by means of forms, whereby manufacturing costs rise high and no individual, cost-effective arrangements are provided.
  • The object of this invention is to provide a novel kind of an arrangement by means of which it is possible in a simple and effective way to form a construction to be used e.g. as a climbing construction, and which construction can be easily coated with sprayed concrete at the manufacturing site of the construction, without inconvenient joints.
  • Brief description of invention
  • The construction according to the invention is characterised by what is stated in the characterising part of claim 1. The arrangement according to the invention is further characterised by what is stated in claims 2-5. The method according to the invention is characterised by what is stated in the characterising part of method claim 6. The method according to the invention is also characterised by what is stated in the characterising part of method claims 7-10. Using the construction according to the invention and the construction manufactured with the method according to the invention are described in claims 11 and 12.
  • The now described arrangement according to the invention provides some considerable advantages when compared to known arrangements. This presented invention accomplishes a novel kind of an arrangement by means of which the disadvantages of known arrangements can be diminished or eliminated, and it provides a construction simple of its structure and easily manufacturable which can be effortlessly installed and coated with sprayed concrete at the desired manufacturing site, and the arrangement according to the invention avoids joints and expensive forms.
  • Brief description of figures
  • The invention will next be described in more detail by means of examples with reference to drawings 1a-3c in which
  • Fig. 1a
    shows a front view of a construction according to the invention;
    Fig. 1b
    shows a top view of the construction according to the invention;
    Figs. 2a-2c
    show a top view of some possible different shapes for the construction according to the invention;
    Fig. 3a
    shows the construction according to the invention which can be rotated in a rotating frame 12; shows the spraying of concrete in the construction, i.e. a meshwork 10;
    Fig. 3c
    shows a top view of the rotating frame.
    Detailed description of invention
  • Fig. 1a shows a front view of a construction according to the invention, and the construction 1, which is lattice-like, comprises several tubular and/or beam- like support pieces 6, 7, 11 which are directly or indirectly fitted in an elongated frame piece 2 (which elongated piece can be e.g. a steel pipe or a steel bar), and further the frame is fitted with a support structure 15, such as support reinforcement of steel. The construction 1 is fitted with a meshwork 10, such as a steel meshwork, such that the meshwork is fastened in a subframe 14 and/or the frame and/or the support structure 15, which subframe comprises at least one tubular and/or beam-like piece 5 being substantially elongated, and which tubular and/or beam-like pieces 5 are fitted in the support pieces 6, 7, 11 and/or the frame piece. The support structure 15 is fastened in the invention on top of the meshwork 10, but the support structure can also be fastened beneath the meshwork.
  • The purpose of the subframe, i.e. the tubular and/or beam-like pieces 5, is to enable various appearances for the construction, such as shown in Figs. 2a-2c. The tubular and/or beam-like pieces of the subframe can be of different lengths, and they can be fastened at desired points of the construction, and the tubular and/or beam-like pieces forming the subframe can be straight, curved etc.
  • In the construction according to the invention, the meshwork 10 is coated with sprayed concrete. The sprayed concrete is supplied on the surface of the meshwork either with dry or wet spraying technique.
  • The meshwork 10, the mesh size of which is 1-18 mm, is fastened in the subframe 14 and/or the frame and/or the support structure with suitable fastening pieces 16, but the meshwork can alternatively be fastened by welding or in some other suitable way. The fastening pieces can be e.g. steel nails (e.g. driven by a nail gun), screws or bolts, but the fastening pieces can also be quick-fastening pieces, such as cable ties of metal or some other material.
  • The ends of the frame piece 2 include a rotation support, such as a pivot, a shaft or a projection 13, where the frame piece can be supported in order to rotate the frame piece around its longitudinal axis. A foot part, such as a foot ledge, by means of which the construction is supported and fastened in a substantially vertical position, is designated with reference number 9. Reference number 8 designates a topmost support pipe/support bar of the construction which is fastened at the ends of the support pieces 11.
    • Fig. 1b shows a top view of the construction of Fig. 1a. The support pieces in Fig. 1b are of the same length and symmetrically fitted in the frame piece 2, but the support pieces can also be of different lengths and unsymmetrically fitted in the frame piece 2. In the support pieces 11 is fastened the subframe, i.e. the tubular and/or beam-like pieces 5. The meshwork 10 is fitted on top of the subframe, i.e. the tubular and/or beam-like pieces, and the meshwork is coated with concrete (not shown in the figure). The tubular and/or beam-like pieces can be in a desired way and of desired length fastened in the support pieces 11 or the other parts of the construction, and thus they provide a desired shape for the meshwork when the meshwork is fastened in the subframe, i.e. the tubular and/or beam-like pieces.
    • Figs. 2a-2c show a top view of some possible different shapes for the construction according to the invention. However, the shapes of the construction are not solely limited to the ones shown in the figure, because it is possible to form the construction of a desired shape, depending on the number and length of the tubular and beam-like pieces and on how they are fastened in the support pieces 11. The tubular and/or beam-like pieces operating as the subframe can also be e.g. of curved, angular etc. shape and their number is not limited, i.e. a desired number of them can be fitted in the support pieces 11 and at desired points of the support pieces.
    • Fig. 3a shows the construction according to the invention which can be rotated in a rotating frame 12 around the longitudinal axis of the construction, because the ends of the construction include the rotating support 13 where it can be supported on the rotating frame when manufacturing the construction, when e.g. the support reinforcement is fastened in the construction being manufactured, and the meshwork, and when spraying concrete in the meshwork.
    • Fig. 3b shows the spraying of concrete in the construction, i.e. the meshwork 10. The concrete spray is designated with reference number 16. The spraying of concrete on different sides of the construction 1, in the meshwork 10, is easy to perform as the construction is thus rotatable in the rotating frame. The rotating frame 12 can include a drive, such as e.g. an electric drive or a hydraulic drive, or it is possible to operate it manually e.g. by means of a hoist with which the construction is rotated when it is in the rotating frame. This is not yet shown in the figure.
    • Fig. 3c shows a top view of the rotating frame.
  • The method according to the invention for manufacturing the construction 1 will be described next, with reference to Figs. 1a, 1b and 3b.
  • In the method according to the invention, a lattice-like frame is formed of several tubular and/or beam- like support pieces 6, 7 and 11 which are directly or indirectly fitted i.e. fastened in an elongated frame piece 2, which support pieces and/or the frame piece are fitted with a support structure 15, such as support reinforcement. In the frame piece and/or the support pieces is fastened a subframe 14, which subframe comprises at least one tubular and/or beam-like piece 5, and in the subframe 14 and/or the frame and/or the support structure 15 is fastened a meshwork 10, such as a steel meshwork, which meshwork is coated with concrete by spraying concrete in it as dry or wet spraying.
  • The construction according to the invention can be rotated in a rotating frame 12 around the longitudinal axis of the construction when manufacturing the construction, when e.g. the support reinforcement is fastened in the construction being manufactured, and the meshwork, and when further spraying concrete in the meshwork.
  • The meshwork is fastened in the subframe and/or the frame and/or the support structure with nails, screws or bolts, but it can also be fastened in the subframe and/or the frame and/or the support structure with quick-fastening pieces, such as e.g. cable ties made of metal or some other material. The meshwork can alternatively be fastened in the subframe and/or the frame and/or the support structure by welding.
  • It is well known by those skilled in the art that the different embodiments of the invention are not solely limited to the examples described above, and thus they can vary within the scope of the appended claims.
  • In the arrangement according to the invention, the different parts of the construction, such as the elongated frame piece or the support pieces, can each consist of one or several pieces, e.g. such that several metal profiles, such as steel bars or steel pipes, are welded or fastened in some other way, e.g. by bolts, together.
  • The construction according to the invention can also be fitted with fixed or detachable climbing holds for climbing e.g. such that the climbing holds are fastened in the concrete (sprayed in the meshwork) with bolts, screws or other fastening means. The fastening of the climbing holds can also occur e.g. such that the climbing holds are first fastened in the meshwork or at some other point, such as the support parts, in the construction, and only then the concrete is supplied on the surface of the meshwork.

Claims (12)

  1. A construction (1), which is lattice-like, and which construction includes a frame, which frame comprises several tubular and/or beam-like support pieces (6, 7, 11) which are directly or indirectly fitted in an elongated frame piece (2), and the frame is fitted with a support structure (15), such as support reinforcement, characterised in that the construction (1) is fitted with a meshwork (10), such as a steel meshwork, such that the meshwork is fastened in a subframe (14) and/or the frame and/or the support structure (15), and which subframe comprises at least one tubular and/or beam-like piece (5) which is fitted in the support pieces (6, 7, 11) and/or the frame piece, and which meshwork, the mesh size of which is 1-18 mm, is coated with sprayed concrete.
  2. A construction according to claim 1, characterised in that the meshwork (10) is fastened in the subframe (14) and/or the frame and/or the support structure with fastening pieces (16).
  3. A construction according to claim 2, characterised in that the fastening pieces are nails, screws or bolts.
  4. A construction according to claim 2, characterised in that the fastening pieces are quick-fastening pieces, such as cable ties.
  5. A construction according to claim 1, characterised in that the ends of the frame piece (2) include a pivot, a shaft or a projection (13) where the frame piece can be supported in order to rotate the frame piece around its longitudinal axis.
  6. A method for manufacturing a construction (1), in which method, forming a lattice-like frame of several tubular and/or beam-like support pieces (6, 7, 11) which are directly or indirectly fitted in an elongated frame piece (2), which support pieces and/or the frame piece are fitted with a support structure (15), such as support reinforcement, characterised by fastening in the frame piece and/or the support pieces a subframe (14) which subframe comprises at least one tubular and/or beam-like piece (5), and fastening in the subframe (14) and/or the frame and/or the support structure (15) a meshwork (10), such as a steel meshwork, and coating which meshwork, the mesh size of which is 1-18 mm, with concrete by spraying concrete in it as dry or wet spraying.
  7. A method for manufacturing a construction according to claim 6, characterised by fastening the meshwork in the subframe and/or the frame and/or the support structure with nails, screws or bolts.
  8. A method for manufacturing a construction according to claim 6, characterised by fastening the meshwork in the subframe and/or the frame and/or the support structure with quick-fastening pieces, such as cable ties.
  9. A method for manufacturing a construction according to claim 6, characterised by fastening the meshwork in the subframe and/or the frame and/or the support structure by welding.
  10. A method for manufacturing a construction according to claim 6, characterised by rotating the construction in order to coat the meshwork (10) with concrete around its longitudinal axis during the spraying of concrete.
  11. Using a construction according to any one of claims 1-5 as a climbing construction.
  12. Using a construction manufactured with a method according to any one of claims 6-10 as a climbing construction.
EP10172722A 2009-08-17 2010-08-13 Construction, method for manufacturing construction and use of construction Withdrawn EP2292304A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
FI20095850A FI20095850A (en) 2009-08-17 2009-08-17 Design and method of manufacture thereof, and use of the structure

Publications (1)

Publication Number Publication Date
EP2292304A1 true EP2292304A1 (en) 2011-03-09

Family

ID=41050678

Family Applications (1)

Application Number Title Priority Date Filing Date
EP10172722A Withdrawn EP2292304A1 (en) 2009-08-17 2010-08-13 Construction, method for manufacturing construction and use of construction

Country Status (2)

Country Link
EP (1) EP2292304A1 (en)
FI (1) FI20095850A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103157218A (en) * 2013-01-17 2013-06-19 河北科技师范学院 Indoor foldable stall bar frame

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29801221U1 (en) * 1998-01-21 1998-04-09 Brand & Schluttig Gmbh Sports and leisure facility
FR2837397A1 (en) 2002-03-22 2003-09-26 Adrien Bercher Portable climbing wall is made up of boxes with at least three walls and optionally base and top which are held together by clips and are coated with cement
US20060258511A1 (en) * 2005-05-10 2006-11-16 Nicros, Inc. Climbing wall structure and method of construction

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29801221U1 (en) * 1998-01-21 1998-04-09 Brand & Schluttig Gmbh Sports and leisure facility
FR2837397A1 (en) 2002-03-22 2003-09-26 Adrien Bercher Portable climbing wall is made up of boxes with at least three walls and optionally base and top which are held together by clips and are coated with cement
US20060258511A1 (en) * 2005-05-10 2006-11-16 Nicros, Inc. Climbing wall structure and method of construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103157218A (en) * 2013-01-17 2013-06-19 河北科技师范学院 Indoor foldable stall bar frame

Also Published As

Publication number Publication date
FI20095850A (en) 2011-02-18
FI20095850A0 (en) 2009-08-17

Similar Documents

Publication Publication Date Title
US7464512B1 (en) Hollow structural member
JP2012527549A5 (en)
CN208543333U (en) A kind of adjustable surface derusting device for steel tubes for building
CN106049766A (en) Combined eave system with large-span steel structure and bracket system wood structure and construction method of combined eave structure
EP2292304A1 (en) Construction, method for manufacturing construction and use of construction
KR20090007927A (en) Machinery for processing rebar cage
JP3207708U (en) Building structure fixing device
CN211701325U (en) Bridge mounting and fixing device
CN211850953U (en) Wire arranging device for pavement construction
CN209293455U (en) A kind of security component for assembled architecture installation
JP4078173B2 (en) Work unit
JP4459790B2 (en) Prop for installing fall prevention material
JP3125281U (en) Tile leakage check device
RU220381U1 (en) BRACKET FOR VENTILATED FACADE SYSTEM
CN204434055U (en) A kind of adjustable clamp for lifting in airduct
JP3372431B2 (en) Construction support device for curved architectural plate and its construction method
CN203654753U (en) Dabbing device for concrete
CN210909761U (en) Fastening wrench
CN218415688U (en) Left-right adjustable cable bridge elbow
FI127264B (en) Staircase elements and procedure for building stairwells
CN216789436U (en) Crane span structure monofilament pole gallows
CN216553105U (en) Simple sand-free concrete vibrating device
CN113322773B (en) Steel structure beam for municipal road and bridge building construction and construction method thereof
CN207633238U (en) A kind of reinforced isolated gate column
JPH11200615A (en) Detachable ladder

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME RS

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20110910