EP1983122A1 - Brick with upright edge, and method and brickwork effected therewith - Google Patents

Brick with upright edge, and method and brickwork effected therewith Download PDF

Info

Publication number
EP1983122A1
EP1983122A1 EP08154539A EP08154539A EP1983122A1 EP 1983122 A1 EP1983122 A1 EP 1983122A1 EP 08154539 A EP08154539 A EP 08154539A EP 08154539 A EP08154539 A EP 08154539A EP 1983122 A1 EP1983122 A1 EP 1983122A1
Authority
EP
European Patent Office
Prior art keywords
brick
upstanding edge
bricks
brickwork
mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP08154539A
Other languages
German (de)
French (fr)
Inventor
Mattheus Cornelis Martinus Van Leest
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
VANDERSANDEN STEENFABRIEKEN N.V.
Original Assignee
Huwa-Vandersanden BV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huwa-Vandersanden BV filed Critical Huwa-Vandersanden BV
Publication of EP1983122A1 publication Critical patent/EP1983122A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2/04Walls having neither cavities between, nor in, the solid elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2002/0256Special features of building elements
    • E04B2002/028Spacers between building elements
    • E04B2002/0284Spacers between building elements forming a unity with the building elements

Definitions

  • the invention relates to a brick.
  • Bricks are known. They are usually laid with the aid of mortar one on top of the other. An amount of mortar is then applied to a previously laid brick, whereupon a new brick is placed thereon and is slightly pressed-on. As a result, the mortar can spread uniformly between the bricks. Excess mortar is pressed outwards and then removed by the bricklayer.
  • a drawback of the known brick is that positioning and uniformly pressing-on for obtaining straight, regular joints requires a high degree of craftsmanship. Furthermore, due to wiping away excess mortar, relatively much mortar is lost. It is further often difficult for a bricklayer to reach the side of the brickwork facing away from him, so that excess mortar can remain behind thereon. This may afterwards cause problems with, inter alia, insulation.
  • the object of the invention is to provide a brick, with which the above-mentioned drawbacks are at least partly obviated.
  • the brick according to the invention is characterized in that it is provided on one side with an upstanding edge which extends along at least a part of the circumference and is closed along at least one side and is interrupted along an opposite side.
  • the bricks are set dry, at least without joints, one onto the other.
  • This side requires, in principle, no finishing.
  • the bricks are set dry one onto the other, for correct positioning, that is, positioning the bricks at a regular mutual distance, hardly any special skill is required.
  • the fact is that the bricks can simply be laid on the upstanding edge of a previously placed brick.
  • a brick according to the invention can further help a bricklayer with application of a correct amount of mortar, as the receiving provision surrounded by the upstanding edge forms a good visual indication for the required amount of mortar.
  • the bricklayer needs only fill this receiving provision.
  • the bricks can be delivered with an associated trowel, whose dimensions are adapted to those of the receiving provision of the respective bricks, so that a user can apply the correct amount of mortar even more easily. This saves time and money as less excess mortar will need to be wiped away and less mortar will be lost.
  • the bricks may have been manufactured in a moulding tray. Owing to its withdrawable form, the upstanding edge can simply be integrally formed. Normally, such bricks manufactured in moulding trays cannot be set in a dry manner one onto the other. Thereto, they first need to be calibrated, i.e. be made level and/or right-angled. However, with a brick according to the invention this is not necessary.
  • the bricks can be placed on top of one another in the above-described manner, while any manufacturing irregularities in the bricks are smoothed out by the mortar between the bricks, as is done with conventional brickwork. This smoothening action however is largely hidden from sight due to the closed upstanding edge.
  • the sight side of the effected brickwork will give the appearance of a jointless wall, with bricks laid dry one on top of the other.
  • bricklaying without joints can be effected.
  • the bricks need not lie dry one on the other.
  • a small seam of, for instance, approximately 1 - 2 mm can be present.
  • a side of the brick located opposite the upstanding edge can be provided with bonding enhancing means, such as, for instance, grooves, projections, ridges and/or recesses.
  • bonding enhancing means such as, for instance, grooves, projections, ridges and/or recesses.
  • Such means help increase the contact surface between the brick and the mortar. As this contact surface is slightly restricted due to the upstanding edges, thus, on balance, the same, at least sufficient bonding capacity can be realised.
  • the bonding enhancing means extend on the side mentioned preferably within the area which operatively comes into contact with the mortar, which, in general, will amount to an area that extends within the (projected) inside contour of the upstanding edge.
  • the invention further relates to brickwork of bricks according to the invention, wherein the interrupted upstanding edges are located on a first side of the brickwork and the closed upstanding edges are located on an opposite side.
  • the invention further relates to a method for effecting brickwork with bricks according to the invention.
  • Fig. 1 shows, in perspective view, an embodiment of a brick 1 according to the invention, wherein the brick 1 is substantially block-shaped.
  • the brick 1 comprises, in particular, six substantially rectangular side surfaces, i.e. a bottom surface 3, a top surface 4, two end faces 5, 6 and two stretcher faces 7, 8.
  • the top surface 4 is provided along its circumference with an upstanding edge 10.
  • This edge 10 extends by respective edge parts 10A,B,C along three sides of the top surface 4, i.e. the two end faces 5, 6 and one stretcher face 8.
  • a receiving provision S for mortar 15 is formed, while this receiving provision S is open towards one side of the brick 1, in this case a longitudinal or stretcher side 7.
  • the edge 10 is completely interrupted, at least completely omitted, along the stretcher side 7.
  • the upstanding edge 10 can extend at least partly along this stretcher side 7, while at least one interruption is provided (not shown).
  • the upstanding edge parts 10A,B can comprise one or more interruptions (not shown) along the respective end faces 5, 6.
  • the brick 1 can further comprise bonding enhancing means, on a side surface 10 located opposite the upstanding edge 10, here, the bottom surface 3.
  • These bonding enhancing means can be designed as projecting parts such as ridges, projections or the like, but are preferably designed as recesses, such as grooves, notches or the like.
  • the latter embodiment causes no deviations in position when a brick 1 is accidentally placed by these means on an upstanding edge 10 of another brick 1.
  • the bonding enhancing means preferably extend only within an area which operatively extends above a receiving provision S of another brick 1.
  • the bonding enhancing means therefore preferably extend within the areas 12, 12' shown in hatchings in Figs. 3A and 3B , respectively.
  • Fig. 3A shows the bottom surface 3 of a brick 1 whose upstanding edge 10 extends along three sides 5, 6, 8 of the top surface 4 (as shown in Fig. 1 )
  • Fig. 3B shows the bottom surface 3' of a brick 1' whose upstanding edge 10 (not visible) also extends along the fourth side 7', naturally with at least one interruption.
  • the brick 1 shown in Fig. 1 has a withdrawable form and, as a result, can be manufactured in, for instance, a moulding tray from, for instance, clay.
  • the upstanding edge 10 can be integrally formed by providing the moulding tray with a suitable, complementary profile.
  • the passage between the upstanding edge 10 and the top surface 4 of the brick 1 can be somewhat rounded or bevelled.
  • the bottom surface 3 of the brick will then correspond to the top side of the clay in the filled-up moulding tray.
  • This top side can be wiped off to be smooth, but can also be provided with a profile for forming the above-mentioned bonding enhancing means.
  • Such a profile can be pressed into the clay with, for instance, a profiled tool.
  • Fig. 2 shows how a number of bricks 1 according to the invention can be laid one on top of the other.
  • a bricklayer M first lays a first row of bricks 1, preferably with their receiving provisions S turned upwards and their interrupted edges 10 facing the bricklayer M, as shown in Fig. 2 .
  • the receiving provisions S are filled with mortar 15 and a row of second bricks 1 is placed on the first bricks, for instance staggered over half a stretcher length.
  • the second bricks 1 are preferably placed on the first bricks in a position tilted slightly backward, on the completely closed edge 10C situated rearwards from the perspective of the bricklayer M, as shown in Fig. 2 .
  • the brick 1 is tilted to a horizontal position, in the direction of arrow R.
  • the mortar 15 will be spread over the receiving provision S and excess mortar 15 will be pressed outward, through the interrupted edge 10, in the direction of the bricklayer M, as indicated by arrow B.
  • the bricklayer M can then simply remove this excess mortar 15.
  • the second brick 1 always remains in contact with the edge part 10C and furthermore, this edge part 10C is completely closed, no mortar 15 can exit on this side.
  • no excess mortar 15 needs to be removed.
  • a surface is formed with an appearance that is tidy and like dry-set masonry which, in principle, needs no further finishing. As a result, the entire bricklaying process can be considerably simplified and accelerated.
  • the upstanding edge 10 can extend along other side surfaces of the brick 1.
  • Such an upstanding edge 10 can also extend along several side surfaces, in particular two opposite side surfaces of the brick 1, for instance the top surface 4 and the bottom surface 3.
  • both edges 10 are preferably provided on the same side 7 of the brick 1 with interruptions, or be completely omitted.
  • Such an embodiment can be combined with a conventional brick (without upstanding edges), while maintaining the above-described advantages of a brick according to the invention.
  • a layer of conventional bricks and a layer of bricks according to the above-mentioned embodiment can be laid on top of each other.
  • the (building) stones can also be manufactured from a different material, for instance concrete or limestone.
  • the bricks can also be placed at some distance from each other in lateral direction so that between the adjacent bricks, vertical joints are formed.
  • the edge parts 10A,B which extend along these sides can be provided with interruptions, so that mortar can be pressed out via these interruptions into the vertical joints.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The invention relates to a brick, brickwork effected therewith and a method suitable thereto. The brick comprises an upstanding edge, which extends along a side surface of the brick. The upstanding edge is at least partly interrupted on a side of this side surface and completely closed on an opposite side. The upstanding edge can be manufactured integrally with the brick, for instance in a moulding tray. With such a brick, brickwork can be effected, with one side giving the appearance of a jointless wall. Excess mortar will only exit on the opposite side and therefore needs to be removed only on this one, well accessible side.

Description

  • The invention relates to a brick.
  • Bricks are known. They are usually laid with the aid of mortar one on top of the other. An amount of mortar is then applied to a previously laid brick, whereupon a new brick is placed thereon and is slightly pressed-on. As a result, the mortar can spread uniformly between the bricks. Excess mortar is pressed outwards and then removed by the bricklayer.
  • A drawback of the known brick is that positioning and uniformly pressing-on for obtaining straight, regular joints requires a high degree of craftsmanship. Furthermore, due to wiping away excess mortar, relatively much mortar is lost. It is further often difficult for a bricklayer to reach the side of the brickwork facing away from him, so that excess mortar can remain behind thereon. This may afterwards cause problems with, inter alia, insulation.
  • The object of the invention is to provide a brick, with which the above-mentioned drawbacks are at least partly obviated. To that end, the brick according to the invention is characterized in that it is provided on one side with an upstanding edge which extends along at least a part of the circumference and is closed along at least one side and is interrupted along an opposite side.
  • With such a brick, mortar can be applied in a receiving provision formed by the upstanding edge. Then, a second brick can be placed on the above-mentioned upstanding edge. As a result, excess mortar will be pressed from the receiving provision, via the interrupted edge, therefore on a predefined first side, which, in use, preferably corresponds to the so-called 'soiled' side. The closed edge prevents mortar from exiting via an opposite, second side. As a result, this second side will remain free of mortar and preferably corresponds, in use, with the so-called 'sight-side'. Excess mortar needs only be removed on the first side. This first side will be easily accessible to the skilled person as he can position himself on this side during bricklaying. As a result, unlike with conventional bricks, no expensive scaffolding or such building equipment is required. Furthermore, as a result, the risk of excess mortar accidentally remaining behind on the brickwork will decrease. As a result, also, the problems associated therewith, such as the earlier mentioned insulation problems will be smaller.
  • On the second side, the bricks are set dry, at least without joints, one onto the other. This side requires, in principle, no finishing. Thus, with the bricks, a jointless result can be realised while the bricks are laid in a substantially traditional manner. As, at least at the location of the upstanding edge, the bricks are set dry one onto the other, for correct positioning, that is, positioning the bricks at a regular mutual distance, hardly any special skill is required. The fact is that the bricks can simply be laid on the upstanding edge of a previously placed brick.
  • A brick according to the invention can further help a bricklayer with application of a correct amount of mortar, as the receiving provision surrounded by the upstanding edge forms a good visual indication for the required amount of mortar. The bricklayer needs only fill this receiving provision. If desired, the bricks can be delivered with an associated trowel, whose dimensions are adapted to those of the receiving provision of the respective bricks, so that a user can apply the correct amount of mortar even more easily. This saves time and money as less excess mortar will need to be wiped away and less mortar will be lost.
  • According to a further aspect of the invention, the bricks may have been manufactured in a moulding tray. Owing to its withdrawable form, the upstanding edge can simply be integrally formed. Normally, such bricks manufactured in moulding trays cannot be set in a dry manner one onto the other. Thereto, they first need to be calibrated, i.e. be made level and/or right-angled. However, with a brick according to the invention this is not necessary. The bricks can be placed on top of one another in the above-described manner, while any manufacturing irregularities in the bricks are smoothed out by the mortar between the bricks, as is done with conventional brickwork. This smoothening action however is largely hidden from sight due to the closed upstanding edge. As a result, at least one side, the sight side of the effected brickwork, will give the appearance of a jointless wall, with bricks laid dry one on top of the other. Thus, with a brick according to the invention manufactured in a moulding tray, bricklaying without joints can be effected. For the sake of completeness, it is noted that on the sight side the bricks need not lie dry one on the other. In practice, a small seam of, for instance, approximately 1 - 2 mm can be present.
  • According to a further advantageous aspect of the invention, a side of the brick located opposite the upstanding edge can be provided with bonding enhancing means, such as, for instance, grooves, projections, ridges and/or recesses. Such means help increase the contact surface between the brick and the mortar. As this contact surface is slightly restricted due to the upstanding edges, thus, on balance, the same, at least sufficient bonding capacity can be realised. It is self-evident that the bonding enhancing means extend on the side mentioned preferably within the area which operatively comes into contact with the mortar, which, in general, will amount to an area that extends within the (projected) inside contour of the upstanding edge.
  • The invention further relates to brickwork of bricks according to the invention, wherein the interrupted upstanding edges are located on a first side of the brickwork and the closed upstanding edges are located on an opposite side. With such a manner of bricklaying, excess mortar will exit via the first side, not via the second side. Therefore, a bricklayer needs only strip one side (the first side) of excess mortar. The difficultly accessible other side remains clean and needs no further treatment.
  • The invention further relates to a method for effecting brickwork with bricks according to the invention.
  • In the further subclaims, further advantageous embodiments of a brick, brickwork and a method for effecting this are described. In clarification of the invention, an exemplary embodiment of a brick according to the invention, and the use thereof will be explained in further detail on the basis of the drawing. In the drawing:
    • Fig. 1 shows, in perspective view, a brick according to the invention, provided with an upstanding edge;
    • Fig. 2 shows, in cross-section, the use of a brick according to the invention, while brickwork is being effected; and
    • Figs. 3A and 3B, respectively, show a bottom surface of a brick according to Fig. 1, and an alternative brick, respectively, wherein areas suitable for applying bonding enhancing means are indicated in hatchings.
  • Fig. 1 shows, in perspective view, an embodiment of a brick 1 according to the invention, wherein the brick 1 is substantially block-shaped. The brick 1 comprises, in particular, six substantially rectangular side surfaces, i.e. a bottom surface 3, a top surface 4, two end faces 5, 6 and two stretcher faces 7, 8. The top surface 4 is provided along its circumference with an upstanding edge 10. This edge 10 extends by respective edge parts 10A,B,C along three sides of the top surface 4, i.e. the two end faces 5, 6 and one stretcher face 8. Thus, above the top surface 4 a receiving provision S for mortar 15 is formed, while this receiving provision S is open towards one side of the brick 1, in this case a longitudinal or stretcher side 7.
  • In the exemplary embodiment shown, the edge 10 is completely interrupted, at least completely omitted, along the stretcher side 7. According to an alternative embodiment (not shown) the upstanding edge 10 can extend at least partly along this stretcher side 7, while at least one interruption is provided (not shown). Further, the upstanding edge parts 10A,B can comprise one or more interruptions (not shown) along the respective end faces 5, 6.
  • The brick 1 can further comprise bonding enhancing means, on a side surface 10 located opposite the upstanding edge 10, here, the bottom surface 3. These bonding enhancing means can be designed as projecting parts such as ridges, projections or the like, but are preferably designed as recesses, such as grooves, notches or the like. The latter embodiment causes no deviations in position when a brick 1 is accidentally placed by these means on an upstanding edge 10 of another brick 1. For reducing such a risk of deviations of position even further, the bonding enhancing means preferably extend only within an area which operatively extends above a receiving provision S of another brick 1. Taking into account the fact that the bricks 1 are usually laid in stretcher bond, the bonding enhancing means therefore preferably extend within the areas 12, 12' shown in hatchings in Figs. 3A and 3B, respectively. Here, Fig. 3A shows the bottom surface 3 of a brick 1 whose upstanding edge 10 extends along three sides 5, 6, 8 of the top surface 4 (as shown in Fig. 1) and Fig. 3B shows the bottom surface 3' of a brick 1' whose upstanding edge 10 (not visible) also extends along the fourth side 7', naturally with at least one interruption.
  • The brick 1 shown in Fig. 1 has a withdrawable form and, as a result, can be manufactured in, for instance, a moulding tray from, for instance, clay. Here, the upstanding edge 10 can be integrally formed by providing the moulding tray with a suitable, complementary profile. For simplifying withdrawing, the passage between the upstanding edge 10 and the top surface 4 of the brick 1 can be somewhat rounded or bevelled. The bottom surface 3 of the brick will then correspond to the top side of the clay in the filled-up moulding tray. This top side can be wiped off to be smooth, but can also be provided with a profile for forming the above-mentioned bonding enhancing means. Such a profile can be pressed into the clay with, for instance, a profiled tool.
  • Fig. 2 shows how a number of bricks 1 according to the invention can be laid one on top of the other. To that end, a bricklayer M first lays a first row of bricks 1, preferably with their receiving provisions S turned upwards and their interrupted edges 10 facing the bricklayer M, as shown in Fig. 2. Then, the receiving provisions S are filled with mortar 15 and a row of second bricks 1 is placed on the first bricks, for instance staggered over half a stretcher length. The second bricks 1 are preferably placed on the first bricks in a position tilted slightly backward, on the completely closed edge 10C situated rearwards from the perspective of the bricklayer M, as shown in Fig. 2. Then, the brick 1 is tilted to a horizontal position, in the direction of arrow R. As a result, the mortar 15 will be spread over the receiving provision S and excess mortar 15 will be pressed outward, through the interrupted edge 10, in the direction of the bricklayer M, as indicated by arrow B. The bricklayer M can then simply remove this excess mortar 15. As, during placing and tilting, the second brick 1 always remains in contact with the edge part 10C and furthermore, this edge part 10C is completely closed, no mortar 15 can exit on this side. Thus, on the side remote from the bricklayer M, which side is normally hard to reach, no excess mortar 15 needs to be removed. Furthermore, on this side remote from the bricklayer M, a surface is formed with an appearance that is tidy and like dry-set masonry which, in principle, needs no further finishing. As a result, the entire bricklaying process can be considerably simplified and accelerated.
  • The invention is not limited in any manner to the exemplary embodiments represented in the description and the drawing. All combinations of (parts of) described and/or shown embodiments are understood to fall within the inventive concept. Furthermore, many variations thereon are possible within the framework of the invention as set forth in the following claims.
  • For instance, the upstanding edge 10 can extend along other side surfaces of the brick 1. Such an upstanding edge 10 can also extend along several side surfaces, in particular two opposite side surfaces of the brick 1, for instance the top surface 4 and the bottom surface 3. In such a case, both edges 10 are preferably provided on the same side 7 of the brick 1 with interruptions, or be completely omitted. Such an embodiment can be combined with a conventional brick (without upstanding edges), while maintaining the above-described advantages of a brick according to the invention. To that end, alternately, a layer of conventional bricks and a layer of bricks according to the above-mentioned embodiment can be laid on top of each other. The (building) stones can also be manufactured from a different material, for instance concrete or limestone. The bricks can also be placed at some distance from each other in lateral direction so that between the adjacent bricks, vertical joints are formed. In such a case, the edge parts 10A,B which extend along these sides can be provided with interruptions, so that mortar can be pressed out via these interruptions into the vertical joints.
  • These and many variants are understood to fall within the framework of the invention as outlined by the claims.

Claims (11)

  1. A brick comprising an upstanding edge, which extends along a side surface of the brick, wherein the upstanding edge is at least partly interrupted on one side of this side surface and is completely closed on an opposite side.
  2. A brick according to claim 1, wherein the brick is substantially block-shaped and the side surface is substantially quadrangular.
  3. A brick according to claim 2, wherein the upstanding edge extends along three sides of the side surface.
  4. A brick according to any one of the preceding claims, wherein the upstanding edge is formed integrally with the brick.
  5. A brick according to any one of the preceding claims, wherein a side surface of the brick located opposite the upstanding edge is provided with bonding enhancing means.
  6. A brick according to any one of the preceding claims, wherein the brick is manufactured in a moulding tray.
  7. Brickwork of bricks according to any one of the preceding claims, wherein the bricks are positioned such that the at least partly interrupted edges are all located on a first side of the brickwork and the completely closed edges are all located on a second, opposite side of the brickwork.
  8. A method for effecting brickwork with bricks according to any one of claims 1 - 6, wherein an amount of mortar is applied in the space surrounded by the upstanding edge and the side surface of a first brick, whereupon a second brick is placed against this first brick, so that this second brick abuts against at least a part of the upstanding edge of the first brick, and the mortar extending within this upstanding edge.
  9. A method according to claim 8, wherein the second brick is placed on the upstanding edge in a somewhat tilted initial position, at the completely closed side, and is then tilted downwards so that mortar located under the second brick is pressed outwards, on the at least partly interrupted side of the upstanding edge.
  10. A method according to claim 8 or 9, wherein a bricklayer places the bricks with the at least partly interrupted edge facing him.
  11. A method according to any one of claims 8 - 10, wherein the bricks are placed dry next to one another.
EP08154539A 2007-04-16 2008-04-15 Brick with upright edge, and method and brickwork effected therewith Withdrawn EP1983122A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
NL1033697A NL1033697C2 (en) 2007-04-16 2007-04-16 Brick with raised edge, as well as working method and brickwork created with it.

Publications (1)

Publication Number Publication Date
EP1983122A1 true EP1983122A1 (en) 2008-10-22

Family

ID=38824954

Family Applications (1)

Application Number Title Priority Date Filing Date
EP08154539A Withdrawn EP1983122A1 (en) 2007-04-16 2008-04-15 Brick with upright edge, and method and brickwork effected therewith

Country Status (2)

Country Link
EP (1) EP1983122A1 (en)
NL (1) NL1033697C2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE1018592A3 (en) * 2009-12-08 2011-04-05 Saegher Jozef Serafin Julia De BRICK, WALL MANUFACTURED FROM SUCH BRICK AND METHOD FOR MANUFACTURING SUCH WALL.
WO2011092634A1 (en) 2010-01-26 2011-08-04 Vandersanden Steenfabrieken N.V. Building brick and method for effecting brickwork therewith
BE1019506A3 (en) * 2010-09-16 2012-08-07 Wienerberger Nv Bricklayer.
BE1020829A5 (en) * 2013-02-20 2014-05-06 Vandersanden Steenfabrieken BUILDING BLOCK FOR MASONRY, THEMSELF BUILT-IN MASONRY AND METHOD FOR MASONING WITH THIS BUILDING BLOCK.

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB332294A (en) 1930-01-13 1930-07-24 Caleb Arlidge A building brick for facing work
US3290849A (en) * 1964-09-02 1966-12-13 Universal Building Products Co Block with spacing legs and facing section
US5159801A (en) 1991-12-13 1992-11-03 Karl Schmidt Mortar securing building brick
GB2264311A (en) 1992-02-14 1993-08-25 London Brick Co Brickwork
BE1011516A3 (en) * 1997-10-28 1999-10-05 Heirbaut Paul Construction element

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB332294A (en) 1930-01-13 1930-07-24 Caleb Arlidge A building brick for facing work
US3290849A (en) * 1964-09-02 1966-12-13 Universal Building Products Co Block with spacing legs and facing section
US5159801A (en) 1991-12-13 1992-11-03 Karl Schmidt Mortar securing building brick
GB2264311A (en) 1992-02-14 1993-08-25 London Brick Co Brickwork
BE1011516A3 (en) * 1997-10-28 1999-10-05 Heirbaut Paul Construction element

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
"Draft BS 5628 - Code of practice for the use of masonry Part 3: materials and components, design and workmanship", BSI BRITISH STANDARDS, 19 April 2005 (2005-04-19), pages A,15,127, XP003026144
HAMMET M. ET AL: "Terms used for describing bricks", BRICKS NOTES ON THEIR PROPERTIES, July 1999 (1999-07-01), pages 2 - 6, XP003026143

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE1018592A3 (en) * 2009-12-08 2011-04-05 Saegher Jozef Serafin Julia De BRICK, WALL MANUFACTURED FROM SUCH BRICK AND METHOD FOR MANUFACTURING SUCH WALL.
WO2011092634A1 (en) 2010-01-26 2011-08-04 Vandersanden Steenfabrieken N.V. Building brick and method for effecting brickwork therewith
BE1019506A3 (en) * 2010-09-16 2012-08-07 Wienerberger Nv Bricklayer.
BE1020829A5 (en) * 2013-02-20 2014-05-06 Vandersanden Steenfabrieken BUILDING BLOCK FOR MASONRY, THEMSELF BUILT-IN MASONRY AND METHOD FOR MASONING WITH THIS BUILDING BLOCK.

Also Published As

Publication number Publication date
NL1033697C2 (en) 2008-10-20

Similar Documents

Publication Publication Date Title
US2209283A (en) Building unit
EP0175014A1 (en) Apparatus for laying tile
US8166726B2 (en) Tile leveling process and apparatus
US20020121027A1 (en) Apparatus and method for spacing tiles
EP1983122A1 (en) Brick with upright edge, and method and brickwork effected therewith
AU2002302249A1 (en) Panel, kit and method for forming a masonry wall
EP1395720A1 (en) Panel, kit and method for forming a masonry wall
US20100212256A1 (en) Tile installation method and devices
US20100095619A1 (en) Tile
CA3041317A1 (en) Shower tray
US7017308B2 (en) Bricklaying tool
US20220010548A1 (en) Expansion Joint Profile System
US6843034B2 (en) Masonry block locking device
EP2758614A1 (en) Ceramic tiled floor and its laying method
US3427774A (en) Grooved brick construction and composite thereof
WO1992014012A2 (en) A device for laying rigid flooring modules
GB2323394A (en) Mortarless brick walls
CA2511008A1 (en) Masonry brick
US4093172A (en) Tool for bricklaying
WO2011092634A1 (en) Building brick and method for effecting brickwork therewith
US20050238850A1 (en) System for laying and substituting facing overlays, a method for laying and removing facing overlays, and a flexible support means
NL1018993C2 (en) Brick for building wall using adhesive, has profiled edges designed to form horizontal and vertical grooves when bricks are stacked
EP2944743B1 (en) Mortar joint spacer
US295067A (en) George e
WO2005058568A1 (en) Method for manufacturing a tile, tile, and methods for laying and removing a tile floor

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA MK RS

17P Request for examination filed

Effective date: 20081013

17Q First examination report despatched

Effective date: 20081223

AKX Designation fees paid

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR

TPAC Observations filed by third parties

Free format text: ORIGINAL CODE: EPIDOSNTIPA

RAP1 Party data changed (applicant data changed or rights of an application transferred)

Owner name: VANDERSANDEN STEENFABRIEKEN N.V.

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20120821