EP1972719B1 - Arrangement with a precast structural concrete slab and process for installing the same - Google Patents
Arrangement with a precast structural concrete slab and process for installing the same Download PDFInfo
- Publication number
- EP1972719B1 EP1972719B1 EP08005317.6A EP08005317A EP1972719B1 EP 1972719 B1 EP1972719 B1 EP 1972719B1 EP 08005317 A EP08005317 A EP 08005317A EP 1972719 B1 EP1972719 B1 EP 1972719B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- slab
- mortar
- boreholes
- layer
- structural arrangement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004567 concrete Substances 0.000 title claims description 35
- 238000000034 method Methods 0.000 title claims description 12
- 230000008569 process Effects 0.000 title claims description 12
- 239000004570 mortar (masonry) Substances 0.000 claims description 48
- 229920001971 elastomer Polymers 0.000 claims description 42
- 239000000806 elastomer Substances 0.000 claims description 37
- 239000000758 substrate Substances 0.000 claims description 33
- 210000002435 tendon Anatomy 0.000 claims description 9
- 239000007767 bonding agent Substances 0.000 claims description 3
- 238000010276 construction Methods 0.000 claims description 3
- 239000011248 coating agent Substances 0.000 claims description 2
- 238000000576 coating method Methods 0.000 claims description 2
- 239000013536 elastomeric material Substances 0.000 claims 1
- 239000000243 solution Substances 0.000 description 17
- 239000000463 material Substances 0.000 description 9
- 238000005452 bending Methods 0.000 description 5
- 238000002347 injection Methods 0.000 description 4
- 239000007924 injection Substances 0.000 description 4
- 239000011178 precast concrete Substances 0.000 description 4
- 230000001133 acceleration Effects 0.000 description 3
- 238000004873 anchoring Methods 0.000 description 3
- 239000010426 asphalt Substances 0.000 description 3
- 230000005540 biological transmission Effects 0.000 description 3
- 239000004568 cement Substances 0.000 description 3
- 239000003795 chemical substances by application Substances 0.000 description 3
- 238000005336 cracking Methods 0.000 description 3
- 239000002184 metal Substances 0.000 description 3
- 230000002093 peripheral effect Effects 0.000 description 3
- 230000002829 reductive effect Effects 0.000 description 3
- 230000036962 time dependent Effects 0.000 description 3
- 239000011398 Portland cement Substances 0.000 description 2
- 230000008901 benefit Effects 0.000 description 2
- 238000006073 displacement reaction Methods 0.000 description 2
- 238000009826 distribution Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 238000011900 installation process Methods 0.000 description 2
- 239000012188 paraffin wax Substances 0.000 description 2
- 239000011513 prestressed concrete Substances 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 238000010521 absorption reaction Methods 0.000 description 1
- 230000003213 activating effect Effects 0.000 description 1
- 230000006978 adaptation Effects 0.000 description 1
- 238000004458 analytical method Methods 0.000 description 1
- 230000003542 behavioural effect Effects 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 239000000835 fiber Substances 0.000 description 1
- 239000000945 filler Substances 0.000 description 1
- 238000009499 grossing Methods 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 230000000670 limiting effect Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000036961 partial effect Effects 0.000 description 1
- 229920002635 polyurethane Polymers 0.000 description 1
- 239000004814 polyurethane Substances 0.000 description 1
- 230000002441 reversible effect Effects 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 239000011800 void material Substances 0.000 description 1
- 239000001993 wax Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/002—Ballastless track, e.g. concrete slab trackway, or with asphalt layers
- E01B1/004—Ballastless track, e.g. concrete slab trackway, or with asphalt layers with prefabricated elements embedded in fresh concrete or asphalt
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B3/00—Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails
- E01B3/28—Transverse or longitudinal sleepers; Other means resting directly on the ballastway for supporting rails made from concrete or from natural or artificial stone
- E01B3/40—Slabs; Blocks; Pot sleepers; Fastening tie-rods to them
Definitions
- the present invention relates to a precast structural concrete slab and the process for installing same, said slab being of the type supporting the rails on which railway cars circulate and having on its face or lower surface an elastomer layer, preferably rubber agglomerate, which is fixed in a discontinuous manner to the slab, and the elastomer layer bonds to the substrate for supporting the slab, creating independent slabs.
- said slab being of the type supporting the rails on which railway cars circulate and having on its face or lower surface an elastomer layer, preferably rubber agglomerate, which is fixed in a discontinuous manner to the slab, and the elastomer layer bonds to the substrate for supporting the slab, creating independent slabs.
- Slab track systems are commonly formed by a reinforced or prestressed concrete slab on which the systems for fixing the rail on which railway cars circulate is arranged.
- precast slab track systems which have a precast slab independent from the adjacent slabs with a considerably prismatic shape and made from reinforced or prestressed concrete and a layer of material having low rigidity or an elastic layer (of elastomer, asphalt cement, etc.) located between the precast slab and the substrate of the track (normally concrete, as illustrated in EP 1 045 069 A2 , EP 0 516 612 A1 , DE 28 57 105 A1 or DE 100 18 112 A1 )
- Anchoring elements integral with the substrate and housed in geometrically identical cavities made in the slab are used for anchoring between the substrate and the precast slab.
- the purpose of the elastic layer is mainly to reduce the vertical rigidity of the assembly formed by the track, the fastening of the track slab and the substrate compared to the traditional track with sleepers and ballast. Another purpose is also to reduce the wear due to friction of the contact surface existing between the substrate, when it is made of concrete, and the precast concrete slab. Said wear is due to the transmission of forces to the substrate due to braking, longitudinal and centrifugal accelerations.
- stoppers In the first solution two cylindrical shaped stoppers are used and located outwardly from the longitudinal ends of the track slab, whereas in the second solution the stoppers are normally two in number and are located inwardly and have a rectangular shape, being internally lined by the elastomer which is a prolongation of the lower elastomer of the slab.
- the plan dimensions of these stoppers are always considerable (greater than 600 mm) and other boreholes with a small diameter are required for the installation, the function of which boreholes is to allow the injection of the asphalt cement or of the filler concrete in order to complete the access of these materials to the entire base of the slab.
- the contrast is the obligation of arranging considerable concrete elements or stoppers, normally surrounded by an elastic layer, connecting the precast track slab and the concrete of the substrate, allowing the absorption of the horizontal forces of breaking, acceleration, continuity of the rail, etc.
- the present invention consists of a precast structural arrangement having a concrete slab and a process for installing same, of the type supporting the rails on which railway cars circulate and having on its face or lower surface an elastomer layer, preferably rubber agglomerate, fixed to the slab without any intermediate adhering layer or admixture.
- Said structural concrete can be reinforced, prestressed or reinforced with fibers.
- the precast slab has several roughly cylindrical shaped boreholes, preferably two every two meters, with a diameter of between 10% and 16% of the width of the slab, which are internally lined or encased by an elastomer having a thickness greater than that of the elastomer or elastomeric layer arranged below the slab and which are filled by the self-compacting mortar in the final assembly situation.
- the reduced diameter of the boreholes allows the distribution of the prestressing of the slab to be even and therefore provides a solution for a structurally correct slab.
- a first object of the present invention is a structural arrangement having a slab and an elastomeric layer according to claim 1, i.e. a structural precast concrete slab, i.e. reinforced or prestressed and with a rectangular section.
- Said slab is preferably used in a slab track system on which train rails are fixed and has an elastomeric layer which is supported on a substrate through a mortar poured after placing the slab on the substrate, said slab and elastomeric layer having corresponding vertical holes or boreholes for pouring the mortar.
- the elastomeric layer is fixed in a discontinuous manner by one of its faces to the lower surface of the precast slab, only through certain points or areas partially covering said lower surface, and which never extend along the entire contact surface with the slab.
- Said elastomeric layer likewise bonds in a continuous manner to the subsequently poured mortar due to the natural bond existing between the mortar and the elastomer.
- the slab has at least four vertical holes for pouring the self-compacting mortar, and with a second elastomeric layer independent from the lower elastomeric layer, arranged therein by way of an inner lining.
- the process for installing the mentioned slab track system comprises the following steps:
- the rail would be installed on the structural precast concrete slab, said installation being able to be carried out previously or subsequently to pouring the concrete, i.e. before or after the previously described third step.
- a second object of the present invention is a process for installing a concrete slab according to claim 10.
- Both the slab and the installation process object of the present invention thus allow there to be no cohesion in the contact surface between the precast slab and the elastomer layer since there is no bonding agent, but there is friction between the concrete and the elastomer. There is likewise considerable bonding and friction in the contact surface between the elastomer layer and the self-compacting mortar upon the setting of the mortar in direct contact with said elastomer.
- Another feature object of the present invention and consequence of the simple geometry of the slab, of the boreholes with small diameter and of the possibility of varying the thicknesses of the elastic layer is the module character of the system, since it allows adapting to that end the amount of the prestressing tendons, which is geometrically easily achieved.
- the continuous elastomer layer with a peripheral elastomer band with boreholes covering the boreholes of the slab and a central area made of a material with very low rigidity, such as polyspan, and a thickness greater than the peripheral band.
- This alternative support form involves a modification of the stresses to which the system and particularly the slab is subjected and is solved by means of adapting the prestressing amount.
- the prestressed slab condition allows the modular nature of the solution, adapting the prestressing level in each case, due to the reversible character of this technology, i.e. the capacity of closing the cracks (remaining crack width less than 0.05 mm, implying an acceptable value in an aggressive environment) when overloads do not act, and due to the concrete element being compressed in the permanent weight situation.
- This prestressing property further involves a considerable strength capacity reserve in the case of localized cavities and settings of the supporting ground and high performance against fatigue and durability.
- the contiguous slabs are independent of one another, i.e. one slab is independent of the contiguous slab or slabs in the transmission of bending, even though the space existing between the precast slabs is filled or not filled by the self-compacting mortar, which does not transmit the bending moments between slabs.
- the slab 3 is prestressed both longitudinally and transversally with centered prestressing force provided preferably by two symmetrical layers of tendons.
- Said slab has planar and parallel faces, with dimensions between 5 and 6 meters in length, preferably 5.1m or 5.75m; between 2 and 2.8 meters in width, preferably 2.5 m; and between 0.15 and 0.25 meters thick, preferably 0.20 m; including at least four through boreholes 5, preferably six in number, evenly distributed in the base, two rows of three boreholes and with a considerably cylindrical longitudinal section and with a circular horizontal section with an average diameter of 0.3 m.
- the longitudinal section can also be frustum-conical and the horizontal section elliptical. This distribution of boreholes 5 and the reduced diameter thereof allows an optimized arrangement of the prestressing tendons inside the slab 3 in addition to enabling a reliable injection of the self-compacting mortar 2.
- the situation, dimensions and the use of either material for designing the slab have evidently been object of complex calculations and tests.
- the elastomer layer 4 is preferably formed by fine grain rubber agglomerate normally bonded or cemented with polyurethane and with a thickness of greater than 3 mm.
- the elastomer 6 coating the inside of the boreholes 5 useful as a lining therefor, has a thickness greater than that of the lower layer to regulate the horizontal rigidity of the lined stopper, which stopper results from the setting of the self-compacting mortar poured inside said boreholes, such that the horizontal stresses due to the trains are absorbed in large part by the lower surface of the slab supported on the elastomer layer 4 and in addition the restriction of the stoppers due to shrinkage, creep and thermal effects is very small.
- the self-compacting mortar layer 2 resulting from the pouring thereof through the boreholes 5 made in the slab 3, to have, due to construction conditions, an average thickness greater than 4 cm in order to thus absorb the irregularities of the substrate 1.
- Another embodiment (not covered by the claims) consists of substituting the mentioned continuous elastomer layer 4 with a peripheral elastomer band 8 with boreholes covering the boreholes 5 of the slab and a central area 9 made of a material having very low rigidity such as polyspan, and a thickness greater than the outer band 8.
- the precast slabs 3 are longitudinally and transversally stressed by means of prestressing tendons 11, the layout of said tendons 11 being geometrically compatible with the cylindrical holes or boreholes 5 crossing the slabs 3.
- the contiguous slabs 3 are independent of one another as can be observed in Figure 2 , i.e. slab 3 is independent of contiguous slab or slabs 3 in the transmission of bending, even though the space 10 existing between the precast slabs 3 is filled or not filled by the self-compacting mortar which does not transmit the bending moments between slabs.
- the completely planar geometry of the upper surface allows using SFC type fasteners by RAILTECH 12, in which the metal plate for supporting the fastener, providing the inclination of the rail 13, is fixed in the precast slab 3 by means of two threaded inserts, such that a multipurpose slab track is obtaining, arranging four inserts for support and forming pairs separated by a distance of 116.5 mm, and fixing the metal plate in either pair of inserts.
- This solution has the advantage of being able to use a normal, tested fastener, which has already been successfully used "in situ" concrete slab track, whereas this new application in the case of the precast slab involves considerable improvements both in construction and in final precision and reliability.
- a track is "multipurpose" if the fixing has two positions, one for international gauge (UIC) and the other for local gauge, for example Iberian gauge, such that it can initially work in this gauge and subsequently in an international gauge (UIC) by changing the position of the rails to this second position of the fastener.
- UICC international gauge
- Iberian gauge local gauge
- the process for installing the previously described precast slabs is carried out on a substrate and comprises the following steps:
- the slabs are installed separately from one another, being joined together only by the mortar poured inside each of the slabs.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
- Machines For Laying And Maintaining Railways (AREA)
Description
- The present invention relates to a precast structural concrete slab and the process for installing same, said slab being of the type supporting the rails on which railway cars circulate and having on its face or lower surface an elastomer layer, preferably rubber agglomerate, which is fixed in a discontinuous manner to the slab, and the elastomer layer bonds to the substrate for supporting the slab, creating independent slabs.
- Slab track systems are commonly formed by a reinforced or prestressed concrete slab on which the systems for fixing the rail on which railway cars circulate is arranged.
- In the state of the art there are different precast slab track systems known which have a precast slab independent from the adjacent slabs with a considerably prismatic shape and made from reinforced or prestressed concrete and a layer of material having low rigidity or an elastic layer (of elastomer, asphalt cement, etc.) located between the precast slab and the substrate of the track (normally concrete, as illustrated in
EP 1 045 069 A2 ,EP 0 516 612 A1DE 28 57 105 A1 orDE 100 18 112 A1 ) Anchoring elements integral with the substrate and housed in geometrically identical cavities made in the slab are used for anchoring between the substrate and the precast slab. - The purpose of the elastic layer is mainly to reduce the vertical rigidity of the assembly formed by the track, the fastening of the track slab and the substrate compared to the traditional track with sleepers and ballast. Another purpose is also to reduce the wear due to friction of the contact surface existing between the substrate, when it is made of concrete, and the precast concrete slab. Said wear is due to the transmission of forces to the substrate due to braking, longitudinal and centrifugal accelerations.
- The most important horizontal longitudinal forces or actions in these systems originate from, in addition to the previously indicated railway traffic, time-dependent deformations of the concrete (shrinkage and creep) as well as from the thermal changes overtime. Said deformations are different in the substrate and in the precast slab which causes stresses capable of cracking the concrete of the slab if, due to bonding, the substrate restricts the free shortening of the precast slab.
- There are two main solutions to prevent or limit this restriction.
- The first solution consists of placing by injection a layer of several centimeters of cement and asphalt mortar, or another type of flexible mortar, between the precast slab (already placed) and the substrate already set prior to placing the track slabs. This solution has considerable horizontal and vertical flexibility as well as a bonding limited to the two concretes which have been hardened long before their application, therefore the restriction of the horizontal deformation differences of both concretes is very small.
- The second solution, normally associated to using reinforced precast concrete slabs, uses a thin elastomer layer of around 5 mm adhered to a surface of the precast slab by one of the faces of the elastomer layer and the opposite face of said layer is put into contact with a concrete used for leveling-up that of the substrate, said face being provided with an anti-tack agent (wax or paraffin). This anti-tack agent cancels the bond which would otherwise occur between the elastomer and the leveling-up concrete which is incorporated on site and which, in the event that the anti-tack agent is not used, would set in contact with the elastomer. The latter is accentuated when elastic layers of rubber agglomerate with a coarse grain (2 to 4 mm) surface are used, for which purpose an anti-tack layer of paraffin with an impalpable aggregate is used further providing the property of smoothing the contact surface.
- In both solutions, especially in the second solution, there is virtually no bonding between the elastic layer and the concrete or lower mortar on which it is supported, concrete stoppers therefore being necessary which will be responsible for absorbing the horizontal forces due to the circulation of the trains on the slabs.
- In the first solution two cylindrical shaped stoppers are used and located outwardly from the longitudinal ends of the track slab, whereas in the second solution the stoppers are normally two in number and are located inwardly and have a rectangular shape, being internally lined by the elastomer which is a prolongation of the lower elastomer of the slab. The plan dimensions of these stoppers are always considerable (greater than 600 mm) and other boreholes with a small diameter are required for the installation, the function of which boreholes is to allow the injection of the asphalt cement or of the filler concrete in order to complete the access of these materials to the entire base of the slab.
- A numeric analysis of the stresses due to the shrinkage and creep of the concrete of the precast slab restricted with the concrete substrate, justifies the need to prevent the bonding between both concretes through the mentioned non-bonded elastomer layer. The obtained values indicate excessive cracking with normal amounts of reinforcement, and in the case of prestressed slabs, the loss over time of the total prestressing force in the case of bonding.
- The contrast is the obligation of arranging considerable concrete elements or stoppers, normally surrounded by an elastic layer, connecting the precast track slab and the concrete of the substrate, allowing the absorption of the horizontal forces of breaking, acceleration, continuity of the rail, etc.
- The present invention consists of a precast structural arrangement having a concrete slab and a process for installing same, of the type supporting the rails on which railway cars circulate and having on its face or lower surface an elastomer layer, preferably rubber agglomerate, fixed to the slab without any intermediate adhering layer or admixture. Said structural concrete can be reinforced, prestressed or reinforced with fibers.
- By means of the present slab, arrangement loads are transmitted to the substrate formed by compacted improved ground or concrete through a self-compacting rigid mortar or Portland cement mortar, and naturally joined together without any intermediate anti-tack material, both to the substrate and to the elastic layer. The precast slab has several roughly cylindrical shaped boreholes, preferably two every two meters, with a diameter of between 10% and 16% of the width of the slab, which are internally lined or encased by an elastomer having a thickness greater than that of the elastomer or elastomeric layer arranged below the slab and which are filled by the self-compacting mortar in the final assembly situation. The reduced diameter of the boreholes allows the distribution of the prestressing of the slab to be even and therefore provides a solution for a structurally correct slab.
- A first object of the present invention is a structural arrangement having a slab and an elastomeric layer according to claim 1, i.e. a structural precast concrete slab, i.e. reinforced or prestressed and with a rectangular section. Said slab is preferably used in a slab track system on which train rails are fixed and has an elastomeric layer which is supported on a substrate through a mortar poured after placing the slab on the substrate, said slab and elastomeric layer having corresponding vertical holes or boreholes for pouring the mortar. The elastomeric layer is fixed in a discontinuous manner by one of its faces to the lower surface of the precast slab, only through certain points or areas partially covering said lower surface, and which never extend along the entire contact surface with the slab. Said elastomeric layer likewise bonds in a continuous manner to the subsequently poured mortar due to the natural bond existing between the mortar and the elastomer. The slab has at least four vertical holes for pouring the self-compacting mortar, and with a second elastomeric layer independent from the lower elastomeric layer, arranged therein by way of an inner lining.
- The process for installing the mentioned slab track system comprises the following steps:
- 1 - Precasting the structural concrete slabs, preferably comprising inserts on the upper surface for fixing the rails, known as spikes or screws, for subsequently fixing the rail, preferably cylindrical boreholes with their elastomer lining or sleeve, an elastomer layer weakly and/or provisionally fixed at a series of specific points to the lower surface of the slab, but not fully adhered or bonded to all of said surface of the slab. Said elastomer layer is placed on the lower surface of the slab once the concrete thereof has set.
- 2 - After transporting the slab to its location, the on site positioning and vertical and horizontal plotting of the slabs in relation to the substrate is carried out. Metal frames or other provisional elements with hydraulic and mechanical elements can be used for this operation, which will allow the geometric adjustment of the slab and which will be supported in the substrate and be provisionally integral with the slab, the slab being in its definitive position and supported by the mentioned frames.
- 3 - Subsequently injecting the self-compacting bonding mortar, leveling and filling, carried out without vibration and which mortar is distributed though the preferably cylindrical boreholes or holes existing in the slab and evenly distributed in the base for allowing complete filling with said self-compacting mortar of the space existing between the slab and the substrate. As has been mentioned, this operation is carried out without any vibration as a result of using self-compacting mortars and concretes and of the pressure on the assembly produced by filling said boreholes.
- 4 - The last step of the installation process consists of the setting of the mortar, removal of the provisional fixings or pedestals and making the final geometric adjustments of the rail to be installed on the slab.
- In addition to the previous steps, the rail would be installed on the structural precast concrete slab, said installation being able to be carried out previously or subsequently to pouring the concrete, i.e. before or after the previously described third step.
- Therefore a second object of the present invention is a process for installing a concrete slab according to
claim 10. Both the slab and the installation process object of the present invention thus allow there to be no cohesion in the contact surface between the precast slab and the elastomer layer since there is no bonding agent, but there is friction between the concrete and the elastomer. There is likewise considerable bonding and friction in the contact surface between the elastomer layer and the self-compacting mortar upon the setting of the mortar in direct contact with said elastomer. - The performance of the installed precast slab given different stresses is detailed below:
- Given time-dependent deformations (shrinkage and creep) and thermal deformations of the precast slab.
These deformations occur over time without the presence of the weight of the trains, there being no restriction of the deformation by the elastomer layer in these conditions since the cohesion is virtually null and void and considerable vertical stresses do not exist in elastomer-slab contact; friction therefore does not act. This prevents cracking in reinforced slabs and the almost complete time-dependent losses of prestressing force in prestressed slabs. - Given longitudinal horizontal acceleration and braking actions and transverse actions.
These actions occur with the presence of the trains, causing the subsequent normal vertical stresses bringing about or activating friction between the slab and the upper face of the lower elastic layer. A large part of the horizontal forces, usually greater than 50% in normal cases, is transmitted to the substrate through this elastomer layer in a widely distributed manner and with very minor creep or displacements. This behavior together with the forces considerably less than 50% transmitted to the boreholes filled with mortar acting for this purpose as connectors, represent a clear advantage in displacements and stresses compared to other systems in which upon having an anti-tack substance on the contact surface between the elastomer and the filling concrete of the substrate, all the horizontal forces are transmitted in a concentrated manner through the rectangular connection or anchoring elements the dimensions of which must be considerable. - Given vertical loads as a composite section.
Friction causes the integral behavior of the slab and the elastomer layer upon the passage of vehicles, which together with the permanent bonding of the self-compacting mortar with the elastomer and with the substrate causes continuous deformations throughout the assembly and stresses in the materials, mainly in the slab, which are much lower than those corresponding to a behavior with sliding on the contact surfaces between different materials appearing in the solutions used in the state of the art using an anti-tack layer. - Another feature object of the present invention and consequence of the simple geometry of the slab, of the boreholes with small diameter and of the possibility of varying the thicknesses of the elastic layer is the module character of the system, since it allows adapting to that end the amount of the prestressing tendons, which is geometrically easily achieved.
- This modular adaptation quality has two important practical consequences:
- 1 - Using the system with substrates or with lower surfaces within a wide range of rigidities. To that end, the rigidity and thickness of the elastic layer is adapted, which allows responding to the range of corresponding bending moments and also to the amount of active reinforcement of the prestressing.
- 2 - Obtaining typical frequencies of the precast slab-non-cushioned mass assembly of the rolling stock, i.e. the train assembly sliding on the rails, within a predetermined range, particularly applicable for demanding environmental conditions with precise control of the vibrations transmitted to the supporting ground or structure, such as bridges for example. To that end considerable thicknesses (several cms of elastic layer) are necessary and obtaining greater flexibility further forces reducing the surface of the elastic layer.
- In order to solve the foregoing or for the purpose of saving in costs, it is possible to substitute the continuous elastomer layer with a peripheral elastomer band with boreholes covering the boreholes of the slab and a central area made of a material with very low rigidity, such as polyspan, and a thickness greater than the peripheral band.
- This solution maintains the behavioral philosophy of the previously detailed embodiment with a continuous elastomer layer as regards the behavior under horizontal loads and the implementation simplicity with the joint injection of the rigid self-compacting Portland cement mortar layer.
- This alternative support form involves a modification of the stresses to which the system and particularly the slab is subjected and is solved by means of adapting the prestressing amount.
- The prestressed slab condition allows the modular nature of the solution, adapting the prestressing level in each case, due to the reversible character of this technology, i.e. the capacity of closing the cracks (remaining crack width less than 0.05 mm, implying an acceptable value in an aggressive environment) when overloads do not act, and due to the concrete element being compressed in the permanent weight situation. This prestressing property further involves a considerable strength capacity reserve in the case of localized cavities and settings of the supporting ground and high performance against fatigue and durability.
- In the two proposed solutions, the contiguous slabs are independent of one another, i.e. one slab is independent of the contiguous slab or slabs in the transmission of bending, even though the space existing between the precast slabs is filled or not filled by the self-compacting mortar, which does not transmit the bending moments between slabs.
- Reference has been made below to the following figures attached to the description in a non-limiting manner for the purpose of facilitating the understanding of the invention.
-
Figure 1 shows an exploded view of the components of the precast slab. -
Figure 2 shows an upper plan view of the slab track system object of the present invention. -
Figure 3 shows a cross-sectional view according to the AB plane ofFigure 2 . -
Figure 4 shows a section of a second solution of the slab track system. -
Figure 5 shows a partial lower view of the base of the slab track system ofFigure 4 . -
Figure 6 shows a plan view of the precast slab according to the present invention in which an arrangement of theprestressing tendons 11 can be observed therein. -
Figure 7 shows an upper plan view of the precast slab with the rails installed. - In the first solution of the
precast slab 3 object of the present invention, which is observed infigures 1 ,2 ,3 and6 , theslab 3 is prestressed both longitudinally and transversally with centered prestressing force provided preferably by two symmetrical layers of tendons. Said slab has planar and parallel faces, with dimensions between 5 and 6 meters in length, preferably 5.1m or 5.75m; between 2 and 2.8 meters in width, preferably 2.5 m; and between 0.15 and 0.25 meters thick, preferably 0.20 m; including at least four throughboreholes 5, preferably six in number, evenly distributed in the base, two rows of three boreholes and with a considerably cylindrical longitudinal section and with a circular horizontal section with an average diameter of 0.3 m. The longitudinal section can also be frustum-conical and the horizontal section elliptical. This distribution ofboreholes 5 and the reduced diameter thereof allows an optimized arrangement of the prestressing tendons inside theslab 3 in addition to enabling a reliable injection of the self-compactingmortar 2. The situation, dimensions and the use of either material for designing the slab have evidently been object of complex calculations and tests. - The
elastomer layer 4 is preferably formed by fine grain rubber agglomerate normally bonded or cemented with polyurethane and with a thickness of greater than 3 mm. Theelastomer 6 coating the inside of theboreholes 5 useful as a lining therefor, has a thickness greater than that of the lower layer to regulate the horizontal rigidity of the lined stopper, which stopper results from the setting of the self-compacting mortar poured inside said boreholes, such that the horizontal stresses due to the trains are absorbed in large part by the lower surface of the slab supported on theelastomer layer 4 and in addition the restriction of the stoppers due to shrinkage, creep and thermal effects is very small. It is also appropriate for the self-compactingmortar layer 2, resulting from the pouring thereof through theboreholes 5 made in theslab 3, to have, due to construction conditions, an average thickness greater than 4 cm in order to thus absorb the irregularities of the substrate 1. - Another embodiment (not covered by the claims) consists of substituting the mentioned
continuous elastomer layer 4 with aperipheral elastomer band 8 with boreholes covering theboreholes 5 of the slab and acentral area 9 made of a material having very low rigidity such as polyspan, and a thickness greater than theouter band 8. - The
precast slabs 3 are longitudinally and transversally stressed by means of prestressingtendons 11, the layout of saidtendons 11 being geometrically compatible with the cylindrical holes orboreholes 5 crossing theslabs 3. - In the two proposed solutions, the
contiguous slabs 3 are independent of one another as can be observed inFigure 2 , i.e.slab 3 is independent of contiguous slab orslabs 3 in the transmission of bending, even though thespace 10 existing between theprecast slabs 3 is filled or not filled by the self-compacting mortar which does not transmit the bending moments between slabs. - Recently available materials such as self-compacting mortar, which allows using reduced thicknesses, as well as injecting without vibration through the preferably six
boreholes 5, the transversally non-bonding post-stressing and recently developed rubber agglomerates, which allow using very fine grains, self-cementing and obtaining custom-made superficial and elastic qualities, have been used for installing the precast slab. - The completely planar geometry of the upper surface allows using SFC type fasteners by
RAILTECH 12, in which the metal plate for supporting the fastener, providing the inclination of therail 13, is fixed in theprecast slab 3 by means of two threaded inserts, such that a multipurpose slab track is obtaining, arranging four inserts for support and forming pairs separated by a distance of 116.5 mm, and fixing the metal plate in either pair of inserts. This solution has the advantage of being able to use a normal, tested fastener, which has already been successfully used "in situ" concrete slab track, whereas this new application in the case of the precast slab involves considerable improvements both in construction and in final precision and reliability. As is known, a track is "multipurpose" if the fixing has two positions, one for international gauge (UIC) and the other for local gauge, for example Iberian gauge, such that it can initially work in this gauge and subsequently in an international gauge (UIC) by changing the position of the rails to this second position of the fastener. - The process for installing the previously described precast slabs is carried out on a substrate and comprises the following steps:
- Precasting of the structural concrete slabs with a rectangular section with at least four boreholes, an elastomer layer fixed at a series of specific points, or not fully bonded by fitting the elastic layer to the partially settled concrete precast slab without any bonding agent, to the lower surface of the slab,
- Transporting to the slab location site,
- On site positioning and vertical and horizontal plotting of the slabs in relation to the substrate by means of provisional fixings,
- Injecting the self-compacting bonding, leveling and filling mortar, which mortar is distributed through the boreholes or holes existing in the slab for allowing a complete filling of the space existing between the slab and the substrate with said self-compacting mortar without the need of vibration,
- Setting of the mortar, and
- Removing the provisional fixings for plotting.
- It is also possible to install the rail fasteners in the slab either before injecting the mortar or after the setting thereof, said self-compacting mortar preferably being rigid.
- The slabs are installed separately from one another, being joined together only by the mortar poured inside each of the slabs.
Claims (15)
- A reinforced or prestressed precast structural arrangement comprising a concrete slab (3) having a rectangular section, to be used in a slab track system on which rails are to be fixed, and a first elastomeric material layer (4), the slab (3) and elastomeric layer (4) having corresponding vertical holes or boreholes (5) for pouring through them a self compacting mortar (2) for the layer (4) to be supported on a substrate through said mortar (2) and the layer (4) to be naturally bonded to said mortar (2) in a continuous manner, characterized in that:- said first elastomeric layer (4) is fixed in a discontinuous manner by one of its faces to the lower surface of the precast slab (3) and only through certain points or areas partially covering said lower surface, never being extended along the entire contact surface with the slab (3), - so that first elastomeric layer (4) bonds in a continuous manner to the self-compacting bonding mortar (2) with the substrate due to the natural bonding existing between said mortar and the elastomer after pouring said mortar,- it has at least four vertical holes (5) that have therein a second elastomeric layer (6) coating the inside of the boreholes (5) as an inner lining, independent from the previous first elastomeric layer (4).
- A structural arrangement according to claim 1, characterized in that said first elastomeric layer (4) is arranged along the entire lower surface of the slab (3).
- A structural arrangement according to claim 1, characterized in that the vertical holes or boreholes (5) have a diameter of between 10% and 16% of the width of the slab.
- A structural arrangement according to the previous claims, characterized in that the slab is longitudinally and transversely prestressed by means of prestressing tendons (11), the layout of said tendons (11) being geometrically compatible with the cylindrical holes or boreholes crossing the slab.
- A structural arrangement according to claim 4, characterized in that said prestressing tendons (11) are placed in two symmetrical layers.
- A structural arrangement according to claim 1, characterized in that in its upper surface it simultaneously has inserts or threaded spikes in two positions, one position for the Iberian railway gauge and the other position one for the international railway gauge (UIC).
- A structural arrangement according to claim 1, characterized in that its upper surface and its lower surface are planar and parallel.
- A structural arrangement according to claim 1, characterized in that the holes or boreholes (5) have a frustum-conical or cylindrical longitudinal section.
- A structural arrangement according to claim 1, characterized in that the holes or boreholes (5) have an elliptical or circular horizontal section.
- A process for installing the precast slab according to claim 1 on a substrate, of the type used for slab track construction, characterized in that it comprises the following steps:- Precasting of the structural concrete slabs with a rectangular section with at least four boreholes (5), a first elastomeric layer (4) fixed at a series of specific points to the lower surface of the slab and a second elastomeric layer (6) fixed in the boreholes (5) as an inner lining,- Transporting to the slab location site,- On site positioning and vertical and horizontal plotting of the slabs in relation to the substrate by means of provisional fixings,- Injecting the self-compacting bonding, leveling and filling mortar (2), which mortar is distributed through the boreholes or holes (5) existing in the slab for allowing a complete filling of the space existing between the slab and the substrate with said self-compacting mortar, without the need of vibration,- Setting of the mortar, and- Removing the provisional fixings for plotting.
- A process according to claim 10, characterized in that the rail fasteners are installed before transporting the slab.
- A process according to claim 11, characterized in that it has an additional step to be carried out before the step of injecting the mortar or after the setting thereof consisting of fixing the rail to the fasteners thereof.
- A process according to claim 10, characterized in that the poured mortar is rigid self-compacting mortar.
- A process according to claim 10, characterized in that the slabs are installed separated from one another and are joined together only by the poured mortar inside the slabs.
- A process according to claim 10, characterized in that the first elastomer layer (4) is not fully bonded to the lower surface of the slab by fitting said layer to the partially settled concrete precast slab without any bonding agent.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
ES200700780A ES2334413B1 (en) | 2007-03-23 | 2007-03-23 | PREFABRICATED STRUCTURAL CONCRETE Slab FOR PLATE VIA AND SAME INSTALLATION PROCEDURE. |
Publications (2)
Publication Number | Publication Date |
---|---|
EP1972719A1 EP1972719A1 (en) | 2008-09-24 |
EP1972719B1 true EP1972719B1 (en) | 2017-08-30 |
Family
ID=39575539
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP08005317.6A Active EP1972719B1 (en) | 2007-03-23 | 2008-03-20 | Arrangement with a precast structural concrete slab and process for installing the same |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP1972719B1 (en) |
ES (2) | ES2334413B1 (en) |
PT (1) | PT1972719T (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2755804C1 (en) * | 2020-11-10 | 2021-09-21 | Акционерное общество "РЖДстрой" | Ballast-free railway track for cargo and passenger high-speed traffic and method for construction thereof |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107217550A (en) * | 2017-07-10 | 2017-09-29 | 中铁第四勘察设计院集团有限公司 | A kind of truss bars concrete folding plate, non-fragment orbit and construction method |
IT202000006484A1 (en) * | 2020-03-27 | 2021-09-27 | Wegh Group S P A | Method for the renewal of an existing railway line with the elimination of a ballast |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2857105C2 (en) * | 1978-04-20 | 1983-12-22 | Diether 4300 Essen Uderstädt | Sound-absorbing rail pad |
AT404037B (en) * | 1991-05-31 | 1998-07-27 | Porr Allg Bauges | Ballastless superstructure with rails |
AT409641B (en) * | 1999-04-13 | 2002-09-25 | Porr Allg Bauges | Ballastless superstructure with prefabricated concrete support plates as well as a procedure for the replacement of the same |
DE10018112A1 (en) * | 2000-04-12 | 2001-10-25 | Zueblin Ag | Construction method for vibration-dampened permanent ways for tunnels, bridges, etc. erects concrete base with bollards coated with elastic material, and projecting into site-mixed concrete supporting plate |
-
2007
- 2007-03-23 ES ES200700780A patent/ES2334413B1/en active Active
-
2008
- 2008-03-20 ES ES08005317.6T patent/ES2647939T3/en active Active
- 2008-03-20 EP EP08005317.6A patent/EP1972719B1/en active Active
- 2008-03-20 PT PT80053176T patent/PT1972719T/en unknown
Non-Patent Citations (1)
Title |
---|
None * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2755804C1 (en) * | 2020-11-10 | 2021-09-21 | Акционерное общество "РЖДстрой" | Ballast-free railway track for cargo and passenger high-speed traffic and method for construction thereof |
Also Published As
Publication number | Publication date |
---|---|
ES2647939T3 (en) | 2017-12-27 |
EP1972719A1 (en) | 2008-09-24 |
ES2334413A1 (en) | 2010-03-09 |
ES2334413B1 (en) | 2010-12-02 |
PT1972719T (en) | 2017-11-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0170631A2 (en) | Components for railway lines on pre-fabricated reinforced concrete slabs without ballast | |
KR101293285B1 (en) | Fixed running track on a bridge structure | |
US9758932B2 (en) | Ballastless track system | |
US6694690B2 (en) | Concrete constructions employing the use of a ductile strip | |
CN108755405B (en) | Assembly type steel plate bridge deck continuous structure and construction method | |
CN106368115A (en) | Novel shock insulation system suitable for medium and small-span beam bridges | |
JP5852353B2 (en) | Telescopic device used for bridge and method for manufacturing the same | |
WO2016135512A1 (en) | Steel-concrete composite structure | |
EP1972719B1 (en) | Arrangement with a precast structural concrete slab and process for installing the same | |
Tayabji et al. | Concrete slab track state of the practice | |
RU2755804C1 (en) | Ballast-free railway track for cargo and passenger high-speed traffic and method for construction thereof | |
CN210636309U (en) | Novel concrete bridge deck continuous structure applied to beam bridge | |
Roschke et al. | Overload and ultimate load behavior of posttensioned slab bridge | |
CN116835920A (en) | Ductile material, preparation method and expansion-preventing method of longitudinal connecting plate | |
KR102413972B1 (en) | Interlocking precast concrete rail track | |
KR101861968B1 (en) | Rigid-frame bridge | |
HU221891B1 (en) | Railway superstructure withouth rubblework and with prefabricated concrete slabs supporting rails and procedure for replacement thereof | |
Freudenstein et al. | Ballastless tracks | |
JP5620687B2 (en) | Telescopic device used for bridge and method for manufacturing the same | |
CN109024271B (en) | Construction method of built-in concrete beam bridge steel-concrete anchor capable of limiting local cracking | |
KR100895650B1 (en) | A method of making the simple bridge composed of girders with concrete slab deck continuous | |
SU1395723A1 (en) | Method of constructing ballast-free railway track | |
Carnahan et al. | Development of Alternative Bridge Superstructures for South Dakota Local Roads | |
Zobel et al. | Repair of impact damaged prestressed bridge girder using a variety of materials and placement methods | |
CN115387163A (en) | Novel assembled track structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR |
|
AX | Request for extension of the european patent |
Extension state: AL BA MK RS |
|
17P | Request for examination filed |
Effective date: 20090320 |
|
AKX | Designation fees paid |
Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR |
|
17Q | First examination report despatched |
Effective date: 20091214 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20170517 |
|
RIN1 | Information on inventor provided before grant (corrected) |
Inventor name: ALBAJAR MOLERA, LUIS |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 923681 Country of ref document: AT Kind code of ref document: T Effective date: 20170915 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602008051853 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: PT Ref legal event code: SC4A Ref document number: 1972719 Country of ref document: PT Date of ref document: 20171121 Kind code of ref document: T Free format text: AVAILABILITY OF NATIONAL TRANSLATION Effective date: 20171114 |
|
REG | Reference to a national code |
Ref country code: SE Ref legal event code: TRGR |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FG2A Ref document number: 2647939 Country of ref document: ES Kind code of ref document: T3 Effective date: 20171227 |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20170830 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG4D |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 923681 Country of ref document: AT Kind code of ref document: T Effective date: 20170830 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171130 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171130 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20171230 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: PLFP Year of fee payment: 11 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602008051853 Country of ref document: DE |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed |
Effective date: 20180531 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 |
|
REG | Reference to a national code |
Ref country code: BE Ref legal event code: MM Effective date: 20180331 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180320 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180320 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180331 Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180331 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180331 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20180320 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO Effective date: 20080320 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20170830 |
|
P01 | Opt-out of the competence of the unified patent court (upc) registered |
Effective date: 20230530 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20240327 Year of fee payment: 17 Ref country code: PT Payment date: 20240312 Year of fee payment: 17 Ref country code: GB Payment date: 20240327 Year of fee payment: 17 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: SE Payment date: 20240327 Year of fee payment: 17 Ref country code: FR Payment date: 20240325 Year of fee payment: 17 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: ES Payment date: 20240409 Year of fee payment: 17 |