EP0229460B1 - Bausystem für mehrstöckige Gebäude - Google Patents
Bausystem für mehrstöckige Gebäude Download PDFInfo
- Publication number
- EP0229460B1 EP0229460B1 EP19860308616 EP86308616A EP0229460B1 EP 0229460 B1 EP0229460 B1 EP 0229460B1 EP 19860308616 EP19860308616 EP 19860308616 EP 86308616 A EP86308616 A EP 86308616A EP 0229460 B1 EP0229460 B1 EP 0229460B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- module
- floor
- building
- building system
- attachment means
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
Definitions
- This invention relates to improvements relating to building systems, and more particularly to multi-storey building having a core unit of the wet area of the building.
- the core unit or module is fitted out with all the items desired or chosen by the owner and found in a site built home within the applicable area.
- the kitchens contain all cupboards, pantry, sink, cooker, tiles, flashbacks and fittings.
- Laundries contain the laundry tub, ceramic tile floors and skirtings and all fittings while the toilets are fitted out with a toilet suite, ceramic tile floors and skirtings and fittings.
- the bathrooms have the bath, shower recess and the basin and cabinet, ceramic tile floors and the whole core has all its electrical components and wirings fitted and wired to a sub-fuse box ready for connection.
- the plumbing is complete and also ready for interconnection at site.
- the module is transported to site, and utilises beam or truss members to allow the module to be crane lifted and placed on site.
- the foundation on which the module is placed can either be a wooden foundation, or can be a concrete slab.
- Multi-storey buildings utilising the module have been constructed. However, if a first module is placed in position and a concrete slab is provided for the floor above covering the first module, difficulties arise in positioning the second module and providing plumbing and other connections through the concrete slab floor.
- a building system for multi-storey buildings comprising at least two self-contained load-bearing building modules mounted one upon the other and each comprising a wet area, characterized in that each module comprise at each lower corner thereof base attachment means and at each upper corner thereof upper attachment means, the base attachment means of the upper module engaging the upper atachment means of the lower module to locate the upper module on the lower module, the upper attachment means of each module forming lifting points for transporting and placing the module, and each module comprising a false ceiling spaced below the upper portion thereof so as to form a space above the false ceiling providing access for the connection of plumbing and electrical supply services.
- each module at its upper perimeter incorporates a perimeter beam attached to the upper perimeter of the core unit, the perimeter beam forming the formwork for a surrounding concrete slab floor and interlocking therewith so that a further module may be positioned on the perimeter beam and thus supported thereon by the concrete slab floor.
- FIG. 1 a lower module 1 on which is supported a second module 1 (a) in turn supporting a further module 1 (b).
- the module has a floor 2 and a false ceiling 3.
- the ceiling being positioned to allow a ceiling cavity 4 for the plumbing and drainage with ventilation for the module 1 (b).
- the module has a floor 2 and a false ceiling 3.
- the ceiling being positioned to allow a ceiling cavity 4 for the plumbing and drainage with ventilation for the module 1 (b), and also the electrical services for module 1 (b).
- a similar arrangement is provided for all modules, where a false ceiling provides access and space for the plumbing and drainage of the module immediately thereabove.
- each module can comprise a bath 5 with a metal safe tray 6 therebeneath, cistern 7 and pan 8, vanity unit 9, light 10 and mirror 11, and a shower recess or alcove (not shown), and an entry door 12 providing access to the bathroom.
- Each module has an upper frame 13 and lower frame 14, these frames being joined together to unite one module to the next, the frame 14 of module 1 being mounted to a floor or the like of the building on the ground floor.
- module 1 and module 1 (b) are shown in broken form, these showing the outer construction of the modules.
- the floors for the adjoining rooms of the building are shown as concrete floors 15.
- the modules are manufactured at a central location and transported to the site for erection. As noted above each module is produced fully equipped, with all the plumbing, electrical and internal fittings included so that on erection the plumbing and electrical services have merely to be connected.
- the modules 1 are manufactured on a stand 16 (FIGS. 4 and 5) the stand having a shackle 17 and chain 18 to hold the module down onto a transport stand 19.
- the modules have base attachment means 20 at each corner (one only being shown in FIG. 2) formed by a cylindrical reducer 21 having a nut 22 welded thereto, the reducer being welded to a base angle 23 on the module.
- a bolt 24 attaches the module to the construction stand 16.
- Each module has an upper attachment means and lifting point 25 at each corner (one only being shown in FIG 3) this comprising a nut 26 welded to a plate 27 in the corner stud 28 of each module.
- FIG. 6 shows the interface along one side, the upper frame 29 of the lower module being in abutting arrangement with the frame 30 of the upper module.
- the concrete floor 31 of the upper module is supported on profiled steel decking 32 supported by the frame 30, fire proof boards 33 being underneath the decking 32 and also fire rated material 34 being positioned on the outer side of the frames 29 and 30 and inside frame 29.
- On the uipper surface of the concrete floor 31 are positioned tiles 35 on grouting 36.
- Stud 28 is attached by a cleat 37, skirting material 38 being positioned on each side of stud 28.
- the floor 39 of the adjoining floor of the building carpet 40 being positioned thereon.
- the modules are joined together by positioning the base attachment means 20 of the upper module into the upper attachment of the lower module and bolting the two together.
- FIG. 7 shows another view of one way of attaching the floor system to the wall frame.
- the floor of each module comprising compressed fibro sheeting 41 bolted to the base of stud 28, mortar 36 being layed on the fibro sheeting to support the tiles 35.
- the fibro sheeting 41 is bolted by bolts 42 to base plate 43 of stud 28.
- the floor is supported by grout 44 on concrete floor 45.
- FIG. 8 shows the position of the lowermost module on the concrete base floor 45 of the base building.
- the figure also shows further details of the stud 28 which comprises an aluminium column with a base plate 46 filloed with fire rated material 34, this being positioned on a plate 47, the fibro sheeting 41 being bolted thereto as shown in FIG. 7.
- a levelling pad 48 is positioned in the recess in the concrete base floor 45. the floor of the module being grouted to the base floor 45 as desired.
- this shows the w.c. pan waste drainage through the floor comprising the fibro sheets 41, mortar 36 and tiles 35.
- a pipe 49 is embedded by an epoxy seal 50 into the opening in the floor, a fitting 51 being situated over the pipe 49.
- the pan outlet 52 is retained by a clamping collar 53 and flexible collar 54 to the fitting 51.
- the flexible coupling 55 and pipe 55' is supplied and fitted by the plumber on site. This is an example of the drainage of an upper module, the connections being made by the plumber in the false ceiling space described above.
- FIG. 10 shows a vanity unit waste drainage for the lowermost module situated on the insitu concrete floor 45 of the building.
- the vanity unit coupling pipe 56 passes down through the cupboard floor 57 and is attached to a coupling unit 58 embedded in the fibro floor 41 resting on mortar bed 44 on concrete floor 45.
- a slab seal 59 is fitted into the slab floor 45, the outlet pipe 60 being fitted thereto by the plumber after the module has been positioned
- bath waste drainage for the base module is also shown, the bath 61 having a plugway 62 screwed to a fitting 63 passing through the bath safe tray 64 and connected to a socket extension 65 with collar 66 connected to socket 67 in the floor of the module.
- a PVC slab seal 68 for pipe 69 is formed in the slab, the pipe 69 being fitted by the plumber on site.
- FIG. 12 shows a floor waste drainage with the removal grating 70 resting in fitting 71 to which is adhered a PVC collar 72 adhered to fibro sheeting 41.
- a slab seal 73 is fitted to the slab to receive the waste pipe 74, the pipe 74 being fitted by the plumber on site.
- FIGS. 10 to 12 which described the connection through the base concrete floor, also can be applied to the upper modules.
- the outlet pipes are fitted into the ceiling space above the false ceiling, suitable elbows and traps being provided as desired in the ceiling space.
- FIG. 13 shows an alternative construction for mounting the modules on each other with modules being tied into the surrounding floor of the building.
- FIG. 13 there is shown a first module 80 with a second module 81 placed vertically thereabove and is supported thereto by a surrounding concrete floor slab 82.
- each module On the top of the wall plate 83 of the wall 84 of each unit, there is attached for example by welding, bolting or the like a perimeter beam 85, this passing completely around the upper perimeter of the wall 84 of the module. Also each module has, extending from the bottom plate 86 of each wall 84 an angle perimeter beam 87 to support the floor panel 88 and floor finishing material 89 and tiles 90 of the floor of the module.
- perimeter beam 85 and angled perimeter beam 87, floor 88, 89 and 90 of each unit as well as all the plumbing fittings, water supply services, sinks, basins, tubs and the like are completed in each module before placement.
- the perimeter beam 85 can be used to assist in supporting the insitu plywood formwork 91 surrounding the module for the pouring of the concrete floor slab 82 incorporating suitable reinforcement (not shown).
- the top When a module is positioned, the top may be covered with a platform or decking to provide access for the workmen pouring the concrete floor slab which surrounds the module, which slab is locked thereto by the perimeter beam which also forms the formwork for the opening in the floor slab above the module.
- the next module can be positioned, the bottom plate 86 resting on the perimeter beam 85 of the lower unit. Access is thus available under the floor of the unit 1 (a). On removing the ceiling panels 92 connection of the plumbing services and the like are made after which the ceiling panels 92 of the lower unit can be replaced.
- the reinforcing of the floor slab is designed to provide a void in the slab over most of the core area.
- the core unit for that floor is placed on the perimeter beam which has been strengthened by the addition of the concrete.
- a further advantage of using this system is that once the lower floor core is placed in position the concrete workers are relieved of the responsibility of providing accurate nesting in the concrete slab as required with previous systems.
- a further advantage is that sleeves for drainage and pipe work do not have to be provided in the concrete slab. All pipe work connections are made at some convenient time after the cores are placed in position and this is simplified by providing a normal suspended panel ceiling in the lower unit which can be sound rated and fire rated as desired.
- each module supports the next module above in a vertical stacking procedure.
- This method allows the concrete floors to be poured at any convenient time after the initial two or more modules are placed on top of each other. This method gives the site builder more flexibility in choosing concrete pour times.
- the modules are structurally designed to support a number of modules placed one on top of another, but will not structurally support the building. However, once each concrete floor slab is poured and cured the effect of the concrete keying into the perimeter beam of each module provides positive locking of the module into the surrounding floor structure. Thus the long term structural support for each module is provided by the pouring and curing of each successive floor as they progress upwards.
- a further advantage of stacking at least one module above the level where concrete is being poured is that greater protection for workmen is provided by not relying on the strength of the temporary platform or decking to support the weight of undetermined numbers of workmen and materials and equipment
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Floor Finish (AREA)
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AT86308616T ATE54977T1 (de) | 1985-11-15 | 1986-11-05 | Bausystem fuer mehrstoeckige gebaeude. |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AU3419/85 | 1985-11-15 | ||
AUPH341985 | 1985-11-15 | ||
AU65192/86A AU593037B2 (en) | 1985-11-15 | 1986-11-14 | Improved building system for multi-storey buildings |
Publications (2)
Publication Number | Publication Date |
---|---|
EP0229460A1 EP0229460A1 (de) | 1987-07-22 |
EP0229460B1 true EP0229460B1 (de) | 1990-07-25 |
Family
ID=25634630
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP19860308616 Expired EP0229460B1 (de) | 1985-11-15 | 1986-11-05 | Bausystem für mehrstöckige Gebäude |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP0229460B1 (de) |
ES (1) | ES2017632B3 (de) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2362659A (en) * | 2000-05-19 | 2001-11-28 | Madison Consult Serv Ltd | Self-contained bathroom unit construction method |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3800493A (en) * | 1972-03-01 | 1974-04-02 | Marcor Housing Systems | Dwelling construction system |
US4513545A (en) * | 1982-09-20 | 1985-04-30 | Hopkins Jr George D | Apparatus for and method of constructing, transporting and erecting a structure of two or more stories comprised of a plurality of prefabricated core modules and panelized room elements |
-
1986
- 1986-11-05 EP EP19860308616 patent/EP0229460B1/de not_active Expired
- 1986-11-05 ES ES86308616T patent/ES2017632B3/es not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
ES2017632B3 (es) | 1991-03-01 |
EP0229460A1 (de) | 1987-07-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4745712A (en) | Building system for multi-storey buildings | |
US20050108957A1 (en) | Pre-fabricated building modules and method of installation | |
TW293857B (de) | ||
IL37086A (en) | Modular building construction and erection method utilizing selectively oriented modules | |
KR20110079882A (ko) | 유니트 빌딩 시스템 | |
SG187296A1 (en) | A multi-storey building with prefabricated members and a semi-prefabricating construction method thereof | |
WO2018174825A1 (en) | Pre-fabricated pre-finished volumetric construction of a building | |
WO2003018934A1 (en) | A method of forming a tiled floor | |
SG184609A1 (en) | Prefabricated bathroom and method for constructing and installing the same | |
GB2623167A (en) | Kit of parts and method | |
GB2428434A (en) | Modular floor units | |
EP0229460B1 (de) | Bausystem für mehrstöckige Gebäude | |
RU2418926C2 (ru) | Способ ремонта санитарных узлов многоквартирного жилого дома | |
WO2013114271A2 (en) | Building method and system | |
AU593037B2 (en) | Improved building system for multi-storey buildings | |
WO2019051532A1 (en) | BUILDING UNITS AND DRAINAGE OF WASTEWATER | |
WO1992006251A1 (en) | A modular slab on ground building system | |
AU2018101022B4 (en) | Incorporation of pods in multi-storey constuctions | |
AU2011201797B2 (en) | Prefabricated Room Assembly | |
AU2018232911A1 (en) | Lifting Device | |
CN210507974U (zh) | 一种用于卫生间同层排水的装配式预制折板 | |
CN218990425U (zh) | 一种全装配式楼梯间 | |
JP3062810B2 (ja) | 建物における水回りユニットの組付方法およびその水回りユニット | |
CZ19995A3 (en) | Living unit, process of its production and a floor frame for such living unit | |
JPH0579778B2 (de) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE CH DE ES FR GB GR IT LI LU NL SE |
|
17P | Request for examination filed |
Effective date: 19880122 |
|
17Q | First examination report despatched |
Effective date: 19890209 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE CH DE ES FR GB GR IT LI LU NL SE |
|
REF | Corresponds to: |
Ref document number: 54977 Country of ref document: AT Date of ref document: 19900815 Kind code of ref document: T |
|
ITF | It: translation for a ep patent filed |
Owner name: NOTARBARTOLO & GERVASI S.R.L. |
|
REF | Corresponds to: |
Ref document number: 3672989 Country of ref document: DE Date of ref document: 19900830 |
|
ET | Fr: translation filed | ||
REG | Reference to a national code |
Ref country code: GR Ref legal event code: FG4A Free format text: 3000679 |
|
ITTA | It: last paid annual fee | ||
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed | ||
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AT Payment date: 19931112 Year of fee payment: 8 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CH Payment date: 19931115 Year of fee payment: 8 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 19931130 Year of fee payment: 8 Ref country code: GR Payment date: 19931130 Year of fee payment: 8 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: LU Payment date: 19931201 Year of fee payment: 8 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: BE Payment date: 19931222 Year of fee payment: 8 |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: 732E |
|
EPTA | Lu: last paid annual fee | ||
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19941105 Ref country code: AT Effective date: 19941105 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Effective date: 19941130 Ref country code: CH Effective date: 19941130 Ref country code: BE Effective date: 19941130 |
|
EAL | Se: european patent in force in sweden |
Ref document number: 86308616.1 |
|
BERE | Be: lapsed |
Owner name: AUSTRALIAN STRATACORE HOLDINGS LTD Effective date: 19941130 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: THE PATENT HAS BEEN ANNULLED BY A DECISION OF A NATIONAL AUTHORITY Effective date: 19950531 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Effective date: 19950601 |
|
NLV4 | Nl: lapsed or anulled due to non-payment of the annual fee | ||
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL Ref country code: GR Ref legal event code: MM2A Free format text: 3000679 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 19961105 Year of fee payment: 11 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 19961108 Year of fee payment: 11 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 19961111 Year of fee payment: 11 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: SE Payment date: 19961118 Year of fee payment: 11 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: ES Payment date: 19961122 Year of fee payment: 11 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19971105 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19971106 Ref country code: ES Free format text: LAPSE BECAUSE OF THE APPLICANT RENOUNCES Effective date: 19971106 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: THE PATENT HAS BEEN ANNULLED BY A DECISION OF A NATIONAL AUTHORITY Effective date: 19971130 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 19971105 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19980801 |
|
EUG | Se: european patent has lapsed |
Ref document number: 86308616.1 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FD2A Effective date: 20010402 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED. Effective date: 20051105 |