EP0083138B1 - Converter vessel for steel preparation - Google Patents

Converter vessel for steel preparation Download PDF

Info

Publication number
EP0083138B1
EP0083138B1 EP19820201643 EP82201643A EP0083138B1 EP 0083138 B1 EP0083138 B1 EP 0083138B1 EP 19820201643 EP19820201643 EP 19820201643 EP 82201643 A EP82201643 A EP 82201643A EP 0083138 B1 EP0083138 B1 EP 0083138B1
Authority
EP
European Patent Office
Prior art keywords
vessel
wall
flange
steel
layers
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
EP19820201643
Other languages
German (de)
French (fr)
Other versions
EP0083138A1 (en
Inventor
Dick C. J. Zuyderduyn
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tata Steel Ijmuiden BV
Original Assignee
Hoogovens Groep BV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hoogovens Groep BV filed Critical Hoogovens Groep BV
Publication of EP0083138A1 publication Critical patent/EP0083138A1/en
Application granted granted Critical
Publication of EP0083138B1 publication Critical patent/EP0083138B1/en
Expired legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C5/00Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
    • C21C5/28Manufacture of steel in the converter
    • C21C5/42Constructional features of converters
    • C21C5/44Refractory linings

Definitions

  • the invention relates to a converter vessel for steel preparation, having a vessel wall and refractory permanent and working linings.
  • permanent lining is meant the layer(s) of the brickwork which is (are) applied very securely to the vessel wall and which is (are) in principle maintained unchanged in a repair to the lining.
  • the working lining is subjected to wear and attack during the steel making, and must therefore be replaced from time to time.
  • the vessel wall has an outwardly convex bottom and a side wall, as seen in the vertical position of the converter.
  • the brickwork of the linings is applied in horizontal layers, and on the bottom the linings are installed in layers which generally follow the shape of the bottom.
  • a flange or horizontal ring secured to the vessel wall, which supports the permanent lining of the side wall.
  • the permanent lining of the vessel bottom exerts high pressures on the specially shaped connecting bricks, so that the latter are crushed and lose their supporting function. Furthermore, this high expansion pressure may also continue as far as the welded-on steel ring, which is pushed upwards as a result. This in turn pushes up the permanent lining of the side wall, so that cohension in the permanent lining is lost.
  • the object of the invention is to provide a vessel in which these difficulties are avoided or mitigated.
  • the invention consists in that the said horizontal flange secured to the vessel wall forms part of a rigid hollow tubular steel structure which also includes a support wall extending obliquely relative to the adjacent vessel wall and transversely to the adjacent parts of the layers of the permanent lining on the vessel bottom.
  • This tubular steel structure can provide very great rigidity so that it cannot be pushed upwards by expansions in the bottom lining.
  • the expansion pressure is thus completely absorbed by the vessel wall and is therefore no longer exerted on the permanent lining of the vessel wall.
  • this construction can avoid the use of the expensive specially shaped bricks at the transition region, which represents a considerable saving in the costs of the vessel lining.
  • the hollow steel tubular structure is filled with refractory concrete. Suitable openings can be provided in the structure for this purpose.
  • the layers of brickwork of the permanent lining in the vessel bottom cannot all extend right up to the said support wall of the tubuluar structure, due to the curvature of the transition region from the bottom towards the side wall.
  • the lowest layer is terminated before it reaches this support wall, and the space thereby formed, between the subsequent layers and the support wall of the tubular structure may be filled with concrete.
  • the lowest layer now expands, for whatever reason, then its expansion pressure will be transmitted to this concrete region which may be crushed as a result.
  • an additional peripheral steel flange is provided extending transversely to the vessel bottom adjacent to the peripheral edge lowest layer of the permanent lining of the bottom, this flange having about the same height as this layer, and that the space between this flange and the hollow tubular structure is filled with refractory concrete, which is preferably anchored. Compressive forces in the lowest layer, resulting from its expansion, are not absorbed by the concrete, but are absorbed by the steel flange which in itself is a continuous ring.
  • the compressive forces transmitted by the different layers of brickwork in the vessel bottom to the said additional steel flange, and to the hollow tubular structure can be further reduced by ending these layers at a distance from the hollow tubular structure and/or the flange on the vessel bottom and by filling the spaces thus left free with a refractory ramming mass. Since the layers of brickwork consist of individual bricks, a free space will generally be left at the edges of these layers in any case. Refractory ramming masses are generally fairly compressible, so that by their use the compressive forces acting on the steel tubular structure and on the flange can be limited.
  • a steel outer shell 1 comprising the vessel side wall, the transition region and the outwardly convex vessel bottom which are denoted as regions I, II and III respectively.
  • a permanent lining 2 and a working lining 3 are located against the side wall, inside the steel outer shell 1 of the vessel, both being constructed from bricks which are arranged in horizontal layers (courses).
  • the lining of the vessel bottom comprises three layers of permanent brickwork 4, 5 and 6 forming the permanent lining, together with a working lining 7.
  • the bricks of the bottom brickwork are laid in layers which follow the shape of the vessel bottom.
  • a horizontal steel ring 9 is welded to the outer shell 1, to form a peripherally extending flange extending inwardly to the width of the permanent lining of the side wall at the location of the transition between vessel wall I and transition region II.
  • the permanent lining 2 of the side wall I is constructed on this ring 9.
  • FIG. 2 shows the portion of the structure at the transition region II, on a larger scale.
  • a support wall 8 extends inwards obliquely from the outer shell 1 to the inner edge of the ring 9.
  • the wall 8 is welded securely to the ring 9 and the shell 1.
  • the portion of the shell 1 between the outer edges of the ring 9 and the wall 8, the wall 8 and the ring 9 thus form a rigid annular steel tubular structure.
  • the ring 9 is drilled at various points (not shown) to provide holes through which the space inside this tubular structure has been injected with refractory concrete 14.
  • This tubular structure extends peripherally around the vessel and provides a very strong structure capable of absorbing and resisting the forces exerted on expansion of the permanent lining layers 5, 6 of the bottom.
  • a peripheral steel flange 10 is welded to the bottom so as to extend transversely thereto as seen in Fig. 2, at the location of the transition from the vessel bottom III to the transition piece II.
  • This flange has a height which corresponds to the thickness of the lowest layer 4 of the bottom lining, and thus serves to absorb the forces arising on expansion of the layer 4.
  • the space thus left between the layer 5, the steel shell 1 of the vessel, the flange 10 and the support wall 8 is filled with concrete 11.

Description

  • The invention relates to a converter vessel for steel preparation, having a vessel wall and refractory permanent and working linings.
  • Where reference is made to this description and claims to a converter vessel, no distinction is made between the different types of vessels which are used for various methods of steel preparation, such as the method in which oxygen is blown into the vessel by a lance from above, or the method in which oxygen and/or inert gases are blown through the vessel bottom, or a combination of these two methods. Such methods may be further combined with the supply of lime, carbon or other solids to the molten metal.
  • By the term "permanent lining" is meant the layer(s) of the brickwork which is (are) applied very securely to the vessel wall and which is (are) in principle maintained unchanged in a repair to the lining. The working lining, on the other hand, is subjected to wear and attack during the steel making, and must therefore be replaced from time to time.
  • Typically, in such a converter, the vessel wall has an outwardly convex bottom and a side wall, as seen in the vertical position of the converter. On the side wall, the brickwork of the linings is applied in horizontal layers, and on the bottom the linings are installed in layers which generally follow the shape of the bottom. At a transition region of the wall between the bottom and the side wall there is a flange or horizontal ring secured to the vessel wall, which supports the permanent lining of the side wall.
  • It is known that the transition region between the, for example, almost cylindrical, vessel side wall and the bottom gives rise to problems in practice. At this point the bricks on the vessel bottom are usually connected to the permanent lining of the vessel wall by high quality special shaped bricks. These shaped bricks must provide a consistently good connection between the two parts of the lining in the different positions of the converter vessel. As mentioned above, in most cases a horizontal steel ring or flange is secured to the vessel side wall, between these connecting' specially shaped bricks and the permanent lining of the vessel side wall.
  • In practice however, due to variations in the temperature of the vessel bottom and/or the penetration of dust and slag particles into the bottom brickwork, the permanent lining of the vessel bottom exerts high pressures on the specially shaped connecting bricks, so that the latter are crushed and lose their supporting function. Furthermore, this high expansion pressure may also continue as far as the welded-on steel ring, which is pushed upwards as a result. This in turn pushes up the permanent lining of the side wall, so that cohension in the permanent lining is lost.
  • The object of the invention is to provide a vessel in which these difficulties are avoided or mitigated.
  • The invention consists in that the said horizontal flange secured to the vessel wall forms part of a rigid hollow tubular steel structure which also includes a support wall extending obliquely relative to the adjacent vessel wall and transversely to the adjacent parts of the layers of the permanent lining on the vessel bottom.
  • This tubular steel structure can provide very great rigidity so that it cannot be pushed upwards by expansions in the bottom lining. The expansion pressure is thus completely absorbed by the vessel wall and is therefore no longer exerted on the permanent lining of the vessel wall. At the same time, this construction can avoid the use of the expensive specially shaped bricks at the transition region, which represents a considerable saving in the costs of the vessel lining.
  • In order to increase the rigidity of the tube, and also in order to limit the flow of heat through the tube, it is preferred that the hollow steel tubular structure is filled with refractory concrete. Suitable openings can be provided in the structure for this purpose.
  • The layers of brickwork of the permanent lining in the vessel bottom cannot all extend right up to the said support wall of the tubuluar structure, due to the curvature of the transition region from the bottom towards the side wall. In practice the lowest layer is terminated before it reaches this support wall, and the space thereby formed, between the subsequent layers and the support wall of the tubular structure may be filled with concrete. However, if the lowest layer now expands, for whatever reason, then its expansion pressure will be transmitted to this concrete region which may be crushed as a result. It is preferred therefore, in the practice of the invention, that an additional peripheral steel flange is provided extending transversely to the vessel bottom adjacent to the peripheral edge lowest layer of the permanent lining of the bottom, this flange having about the same height as this layer, and that the space between this flange and the hollow tubular structure is filled with refractory concrete, which is preferably anchored. Compressive forces in the lowest layer, resulting from its expansion, are not absorbed by the concrete, but are absorbed by the steel flange which in itself is a continuous ring.
  • The compressive forces transmitted by the different layers of brickwork in the vessel bottom to the said additional steel flange, and to the hollow tubular structure can be further reduced by ending these layers at a distance from the hollow tubular structure and/or the flange on the vessel bottom and by filling the spaces thus left free with a refractory ramming mass. Since the layers of brickwork consist of individual bricks, a free space will generally be left at the edges of these layers in any case. Refractory ramming masses are generally fairly compressible, so that by their use the compressive forces acting on the steel tubular structure and on the flange can be limited.
  • The preferred embodiment of the invention is illustrated below by way of non-limitative example and with reference to the accompanying drawings, in which
    • Fig. 1 shows in section half of the bottom end of a steel converter embodying the invention; and
    • Fig. 2 shows a detail of Fig. 1 at the transition region on a larger scale.
  • In the part of a converter vessel shown in Fig. 1 there is a steel outer shell 1 comprising the vessel side wall, the transition region and the outwardly convex vessel bottom which are denoted as regions I, II and III respectively. A permanent lining 2 and a working lining 3 are located against the side wall, inside the steel outer shell 1 of the vessel, both being constructed from bricks which are arranged in horizontal layers (courses).
  • The lining of the vessel bottom comprises three layers of permanent brickwork 4, 5 and 6 forming the permanent lining, together with a working lining 7. The bricks of the bottom brickwork are laid in layers which follow the shape of the vessel bottom.
  • At the lower end of the side wall I, a horizontal steel ring 9 is welded to the outer shell 1, to form a peripherally extending flange extending inwardly to the width of the permanent lining of the side wall at the location of the transition between vessel wall I and transition region II. The permanent lining 2 of the side wall I is constructed on this ring 9.
  • Fig. 2 shows the portion of the structure at the transition region II, on a larger scale. A support wall 8 extends inwards obliquely from the outer shell 1 to the inner edge of the ring 9. The wall 8 is welded securely to the ring 9 and the shell 1. The portion of the shell 1 between the outer edges of the ring 9 and the wall 8, the wall 8 and the ring 9 thus form a rigid annular steel tubular structure. The ring 9 is drilled at various points (not shown) to provide holes through which the space inside this tubular structure has been injected with refractory concrete 14. This tubular structure extends peripherally around the vessel and provides a very strong structure capable of absorbing and resisting the forces exerted on expansion of the permanent lining layers 5, 6 of the bottom.
  • A peripheral steel flange 10 is welded to the bottom so as to extend transversely thereto as seen in Fig. 2, at the location of the transition from the vessel bottom III to the transition piece II. This flange has a height which corresponds to the thickness of the lowest layer 4 of the bottom lining, and thus serves to absorb the forces arising on expansion of the layer 4. The space thus left between the layer 5, the steel shell 1 of the vessel, the flange 10 and the support wall 8 is filled with concrete 11.
  • The spaces left between the flange 10 and the layer 4, and the spaces between the support wall 8 and the layers 5 and 6, are filled with refractory ramming mass 12, 13. Furthermore, all free spaces around the bottom bricks of the working lining 3 are filled with refractory ramming mass 15.

Claims (5)

1. Converter vessel for steel preparation, having (as seen in the vertical position of the vessel) a vessel wall comprising an outwardly convex bottom and a side wall and refractory permanent and working linings which are applied on the side wall in horizontal layers and on the bottom in layers which generally follow the shape of the bottom, there being a transition region of the vessel wall between the bottom and the side wall where an inwardly projecting pheripheral steel flange, which supports the permanent lining of the side wall, is secured to the vessel wall characterised in that said flange forms part of a rigid hollow tubular steel structure which also includes a peripheral support wall extending inwardly obliquely relative to the adjacent part of the vessel wall and transversely to the adjacent parts of the layers of the permanent lining of the bottom.
2. Converter vessel according to claim 1 wherein said rigid hollow tubular structure is comprised of said flange, said support wall and a portion of said vessel wall which extends between the respective outer ends of said flange and said support wall.
3. Converter vessel according to claim 1 or claim 2 wherein said hollow tubular structure is filled with refractory concrete.
4. Converter vessel according to any one of claims 1 to 3 having a further peripheral steel flange extending inwardly from the bottom transversely thereto adjacent the peripheral edge of the lowest layer of the permanent lining of the bottom, the height of said further steel flange corresponding to the thickness of said lowest layer and the space between said further steel flange and the said hollow tubular structure is filled with refractory concrete forming an extension of said lowest layer.
5. Converter vessel according to any one of claims 1 to 4 wherein spaces between on the one hand the layers of the permanent lining of the bottom and on the other hand the said hollow tubular structure and said further steel flange are filled with refractory ramming mass.
EP19820201643 1981-12-29 1982-12-21 Converter vessel for steel preparation Expired EP0083138B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NL8105877A NL8105877A (en) 1981-12-29 1981-12-29 CONVERTER VESSEL FOR STEEL PREPARATION.
NL8105877 1981-12-29

Publications (2)

Publication Number Publication Date
EP0083138A1 EP0083138A1 (en) 1983-07-06
EP0083138B1 true EP0083138B1 (en) 1985-05-29

Family

ID=19838623

Family Applications (1)

Application Number Title Priority Date Filing Date
EP19820201643 Expired EP0083138B1 (en) 1981-12-29 1982-12-21 Converter vessel for steel preparation

Country Status (3)

Country Link
EP (1) EP0083138B1 (en)
DE (1) DE3263945D1 (en)
NL (1) NL8105877A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104962682A (en) * 2015-05-25 2015-10-07 丹东播磨耐火材料有限公司 Converter spherical rounded-corner elbow furnace-lining structure
RU2758600C1 (en) * 2021-01-17 2021-11-01 Акционерное общество «ЕВРАЗ Нижнетагильский металлургический комбинат» (АО «ЕВРАЗ НТМК») Method for lining oxygen converter

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL277037A (en) * 1962-04-10 1900-01-01
DE1282043B (en) * 1963-03-14 1968-11-07 Demag Ag Work platform for lining metallurgical vessels
BE653159A (en) * 1963-09-26 1965-03-16
US3370840A (en) * 1965-07-30 1968-02-27 Harbison Walker Refractories Basic oxygen furnace construction
DE1807322A1 (en) * 1968-11-06 1972-02-24 Fried Krupp Huettenwerk Ag Lining for metallurgical vessels, especially for electric arc furnaces

Also Published As

Publication number Publication date
NL8105877A (en) 1983-07-18
EP0083138A1 (en) 1983-07-06
DE3263945D1 (en) 1985-07-04

Similar Documents

Publication Publication Date Title
JP2583301B2 (en) Container for processing heated material and method for cooling the same
US5348275A (en) Tundish nozzle assembly block
US3431691A (en) Apparatus and method for supporting vessels
EP0083138B1 (en) Converter vessel for steel preparation
US2486348A (en) Blast furnace wall structure
US3053237A (en) Furnace lining
US4649867A (en) Coal gasification reactor of the type employing a bath of liquid metal
US3623717A (en) Self-supporting blast furnace shell and metallic lining for blast furnace
CN215162867U (en) Blast furnace taphole and blast furnace with same
US4673167A (en) Method for installing a converter bottom
SU1554780A3 (en) Converter with bottom blasting
US3586304A (en) Furnace cooling system
US4343459A (en) Basic oxygen furnace construction
RU2210599C2 (en) Iron making blast furnace and method of its functioning
EP0319068B1 (en) Repair of the refractory lining of the wall of a shaft furnace and a repaired shaft furnace
JPS6138760Y2 (en)
US5562880A (en) Refractory brick design for open end of refractory lined vessel
US4595178A (en) Leg for vacuum tank for refining molten steel
US1937940A (en) Bottom for boiler furnaces
USRE32205E (en) Basic oxygen furnace construction
US3559972A (en) Furnace apparatus
US3370840A (en) Basic oxygen furnace construction
CN218080388U (en) Furnace cover structure of torpedo hot metal mixer car
US4852859A (en) Gastight bottom construction for a shaft furnace
US2597501A (en) Blast furnace support

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 19821221

AK Designated contracting states

Designated state(s): DE

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Designated state(s): DE

REF Corresponds to:

Ref document number: 3263945

Country of ref document: DE

Date of ref document: 19850704

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed
PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 19891130

Year of fee payment: 8

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Effective date: 19910903