DE893052C - Arrangement for cooling flue gas heated intermediate superheaters during start-up - Google Patents
Arrangement for cooling flue gas heated intermediate superheaters during start-upInfo
- Publication number
- DE893052C DE893052C DEH3514D DEH0003514D DE893052C DE 893052 C DE893052 C DE 893052C DE H3514 D DEH3514 D DE H3514D DE H0003514 D DEH0003514 D DE H0003514D DE 893052 C DE893052 C DE 893052C
- Authority
- DE
- Germany
- Prior art keywords
- steam
- pressure
- arrangement
- flue gas
- cooling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F22—STEAM GENERATION
- F22G—SUPERHEATING OF STEAM
- F22G1/00—Steam superheating characterised by heating method
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Engine Equipment That Uses Special Cycles (AREA)
Description
Anordnung zur Kühlung von rauchgasbeheizten Zwischenüberhitzern während des Aasfahrens Beim Anheizen von, Hochdruck dampferzeugern mit Zwischen.überh-itzern, welche die Wiederüberhitzung des in einer Hochdruckturbinenstufe verarbeiteten. Dampfes vornehmen,, ist eine zusätzliche Kühlung der Rohrwände des Zwischenüberhitzers erforderlich, da beim Anheizen in der Regel noch kein Abdampf aus der Hochdruckturbinenstufe zur Verfügung steht.Arrangement for cooling flue gas heated reheaters during when heating up, high-pressure steam generators with intermediate overheaters, which the re-superheating of the processed in a high pressure turbine stage. Making steam, is an additional cooling of the pipe walls of the reheater required, since there is usually no exhaust steam from the high-pressure turbine stage when heating up is available.
Eine so-Ich.e Kühlung wurde bisher schon mittels aus einem Niederdruckdampfnetz zugeführten Fremddampfes vorgenommen. Wegen des Druckabfalls im Zwischenüberhi.tzer kann jedoch aus diesem der Dampf nicht -,nieder in das gleiche Nie.derdrucknetz eingeführt werden. Eine Arbeitsleistung in den nachgeschalteten Niederdruckturbinen ist daher bei einer solchen Anordnung nicht möglich.So-ich.e cooling has already been done by means of a low-pressure steam network external steam supplied. Because of the pressure drop in the interim heater but the steam cannot come out of this - down into the same pressure network to be introduced. A job in the downstream low-pressure turbines is therefore not possible with such an arrangement.
Bekannt i,st es ferner, den Zwischenüberhitzer durch eine Wasserfüllung oder durch Wasserumwälzung zu kühlen.. Während der Entleerung ist hierbei aber eine Kühlung des Zwischenüberh.itzers nicht vorhanden, so. daB dieser zeitweilig gefährdet ist. Zudem werden umfangreiche Umschaft- und Absperrorgane erforderlich.It is also known to fill the reheater with water or to cool it by circulating water There is no cooling of the intermediate superheater, see above. that this is temporarily endangered is. In addition, extensive surrounding and shut-off devices are required.
Bei einer anderen bekannten. Anordnung werden während der Aasfahrzeit des Kessels Haupt- und Zwischenüberhitzer ,durch Fremddampf gekühlt, der einer besonderen Dampfquelle entnommen und durch eine Umwälzpumpe durch die Überh-itzungsrohrstränge gefördert wird. Die bekannte Anordnun - sieht jedoch vor, d-aß der Zwischenüberhitzer bei der Inbetriebnahme des Kessels und in Betriebspausen von Dampf durchströmt wird, der unter dem vollen Kesseldruck steht. Während nun der Zwisch:enüberhitzer beim normalen Betrieb nur niedrigeren Dampfspannungen ausgesetzt ist und in seinem Aufbau diesen geringeren Beanspruchungen entsprechend ausgeführt sein könnte, stellt die bekannte Anordnung erhöhte Anford°-rungen, da bei ihr auch der Zw ischenüberhitzer dem vollen Kesseldruck entsprechend bemessen sein muß, wodurch erhöhte Herstellurngsko:sten. bedingt werden.With another well-known. Arrangement will be made during carrion time of the boiler main and reheater, cooled by external steam, that of a special one Steam source is taken and by a circulation pump through the superheating pipe runs is promoted. The familiar arrangement - stipulates, however, that the Reheater when the boiler is started up and during breaks in operation Steam flows through, which is under full boiler pressure. While now the Intermediate superheater only exposed to lower steam voltages during normal operation and its structure is designed to meet these lower stresses could be, the well-known arrangement makes increased demands, as with her too the intermediate superheater must be dimensioned according to the full boiler pressure, which means increased manufacturing costs. be conditioned.
Nach der Erfindung werden die Mängel der bekannten Anordnungen sowie ein im Aufbau teuerer Zwischenüberhitzer dadurch vermieden, daß der einer besonderen Dampfquelle entnommene Kühldampf niederen Druckes vermittels einer Um-wälzpumpe bzw. eines Umwälzverdichters durch die während des Anfahr:ens vom Hochdruckdampferzeuger abgeschalteten Zwischenüberhitzer in die von der Fremddampfquelle kommende Leitung zurückgeführt bzw. einer Niederdruckturbine oder wieder der Umwälzpumpe zugeführt wird, wobei die aufgenommenen Wärmemengen durch einen Dampfkühler entzogen werden. Mit Vorteil wird als Umwälzpumpe ein Turbov-"rdichter verwendet, dessen Antriebsturbine aus dem gleichen Niederdrucknetz wie der Verdichter selbst gespeist wird. Der Druckabfall im Zwischenüberhitzer wird somit bei der erfindungsgemäßen Anordnung durch die Vorverdi,chtung des Kühldampfes überbrückt.According to the invention, the shortcomings of the known arrangements as well a reheater, which is expensive in construction, is avoided by using a special one Cooling steam at low pressure taken from the steam source by means of a circulating pump or a circulation compressor by the high pressure steam generator during start-up disconnected reheater in the pipe coming from the external steam source fed back or fed back to a low-pressure turbine or to the circulating pump is, the absorbed amounts of heat are extracted by a steam cooler. A turbo-compressor and its drive turbine are advantageously used as the circulating pump is fed from the same low-pressure network as the compressor itself. The pressure drop in the reheater is thus in the arrangement according to the invention by the Vorverdi, rect of the cooling steam bridged.
In der Zeichnung ist die Anordnung nach der Erfindung in einer schematischen Darstellung veranschaulicht.In the drawing, the arrangement according to the invention is in a schematic Illustration illustrated.
Hierin sind -i die Hochdruckdampferzcuger, 2 .die Hochdruckdampfsammelleitung, 3 eine Hochdruckvorschaltturbi.ne mit Stromerzeuger 4, 5 die Zwischendrucksammelleitung, 6 die Zwischenüberhitzer, .die im Rauchgasstrom :der Hochdruckdampferzeuge:r liegen. Die Mitteldrucksammelleitung ist mit 7 bezeichnet. In diese liefern. die Mitteldruckkesse114 ebenfalls Dampf, der zusammen mit dem zwischenüberhitzten. Dampf aus der Hochdruclcvo:rschaltturbine 3 die Nieder:druckturbine 8 mit ihrem Stromerzeuger g und Turbinenkondensator io- betreibt.Here are -i the high-pressure steam generators, 2. The high-pressure steam manifold, 3 a high pressure upstream turbine with power generator 4, 5 the intermediate pressure manifold, 6 the reheater, .which are in the flue gas flow: the high pressure steam generator: r. The medium pressure manifold is denoted by 7. Deliver in this. the medium pressure boiler 114 also steam, which together with the reheated. Steam from the high-pressure switch turbine 3 the low pressure turbine 8 with its power generator g and turbine condenser io- operates.
Um den feuergasbeheizten Zwischenüberhitzer 6 beim Anfahren der Hochdruck dampferzeuger i zu kühlen, solange die Hochdruckturbine 3 nicht in Betrieb ist und dementsprechend. Kühldampf aus dieser nicht zur Verfügung steht, wird aus der Sammelleitung 7 Heißdampf den Mitteldruckkesseln 14 entnommen. Dieser Dampf wird durch den Dampfkühler 13 gekühlt und dem Vard.ichter i i zugeführt. Dieser Verdichter kann beispielsweise von einer Turbine 12 angetrieben werden, die ihren Antriebsdampf aus dem gleichen M.itbeldrucknetz 7 erhält. Der im Verdichter i i verdichtete Dampf wird dem Netz, 5 zugeführt und :strömt über die Zwischenüberhitzer 6 teils der Niederdruckturb'in.e 8 zu, teils erneut dem Kühler 13 und dem Verdichter i i. Die im Zwischenüberhitzer 6 aus den Rauchgasen während des Anfahrene der Hochdruckkessel üb"rno:mmen,eÜb-e:rhitzungswärme wird während des Umnwälzens im Kühler 13 wieder hcrabgekühlt, so daß die Wandungstemperatur der Zwischenüberhitzer den zulässigen Wert nicht überschreiten kann.Around the fuel gas heated reheater 6 when starting high pressure To cool steam generator i as long as the high pressure turbine 3 is not in operation and accordingly. Cooling steam from this is not available, is from the collecting line 7 Superheated steam taken from the medium pressure boilers 14. This steam is passed through the steam cooler 13 cooled and fed to the Vard.ichter i i. This compressor can, for example are driven by a turbine 12, which gets its drive steam from the same M.itbeldrucknetz 7 receives. The steam compressed in the compressor i i is fed into the network, 5 is supplied and: flows through the reheater 6 in part to the low-pressure turbine 8 to, partly again to the cooler 13 and the compressor i i. The one in the reheater 6 from the flue gases during the start-up of the high-pressure boiler transfer no: mmen, eÜb-e: heating is cooled down again during circulation in the cooler 13, so that the wall temperature the reheater cannot exceed the permissible value.
Da es sich bei dem Verdichter i i und seiner Antriebsturbine 12 um eine Maschinengruppe handelt, die nur ganz kurzzeitig gebraucht wird, kann diese sehr ein@fach und,* billig gestaltet werden. Eine solche Gruppe kann erfahrungsgemäß inwenigen Sekunden auf höchste Drehzahlen gebracht werden, wenn sie entsprechend gebaut ist.Since the compressor i i and its drive turbine 12 are a machine group that is only needed for a very short time can do so can be designed very simply and, * cheaply. Experience shows that such a group can can be brought to the highest speed in a few seconds if it is appropriate is built.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DEH3514D DE893052C (en) | 1942-07-18 | 1942-07-18 | Arrangement for cooling flue gas heated intermediate superheaters during start-up |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DEH3514D DE893052C (en) | 1942-07-18 | 1942-07-18 | Arrangement for cooling flue gas heated intermediate superheaters during start-up |
Publications (1)
Publication Number | Publication Date |
---|---|
DE893052C true DE893052C (en) | 1953-10-12 |
Family
ID=7143614
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DEH3514D Expired DE893052C (en) | 1942-07-18 | 1942-07-18 | Arrangement for cooling flue gas heated intermediate superheaters during start-up |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE893052C (en) |
-
1942
- 1942-07-18 DE DEH3514D patent/DE893052C/en not_active Expired
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE19645322B4 (en) | Combined power plant with a forced once-through steam generator as a gas turbine cooling air cooler | |
DE60034423T2 (en) | Apparatus and method for reheating gas turbine cooling steam and high pressure steam turbine exhaust steam in a gas and steam turbine power generation system | |
DE19544226B4 (en) | Combined plant with multi-pressure boiler | |
DE102011000644A1 (en) | Systems and methods for preheating the pipe system of a heat recovery steam generator | |
DE3047008A1 (en) | "STEAM FLOW DEVICE FOR A STEAM TURBINE WITH INTERMEDIATE HEATING AND METHOD FOR OPERATING THE SAME" | |
EP0981681B1 (en) | Gas and steam turbine system, and refrigeration of the coolant intended for the gas turbine in such a system | |
DE893052C (en) | Arrangement for cooling flue gas heated intermediate superheaters during start-up | |
DE821733C (en) | Steam and gas turbine plant | |
EP0158629A2 (en) | Steam cycle for a steam power plant | |
DE4117191C2 (en) | Combined gas-steam power plant to generate energy | |
DE3331153A1 (en) | Gas turbine system for open process | |
DE1200326B (en) | Procedure for starting up a steam power plant | |
DE971815C (en) | Process for the operation of a steam power plant with temporary disconnection of the generator from the network and the steam power plant to carry out this process | |
CH621186A5 (en) | Steam-generator installation heated by waste gas | |
DE736611C (en) | Forced-through steam generator with a superheater connected directly to the evaporation heating surface | |
DE19944920A1 (en) | Combination power generation system has injection device for injecting water into fresh steam, and injection water is pre-heated by arrangement in line feeding injection device | |
DE1001286B (en) | Steam power plant with once-through steam generator | |
DE1050609B (en) | A thermal power plant comprising a gas turbine and a steam turbine plant | |
DE546779C (en) | Operating procedures for internal combustion turbine systems | |
DE19542917A1 (en) | Combined turbine generating set | |
CH334780A (en) | Steam power plant with once-through steam generator | |
EP2801759A1 (en) | Steam bypass in a waste heat steam generator | |
DE522718C (en) | Deflagration combustion power turbine, on whose impeller, which is acted upon by the combustion gases, at the same time, steam generated from the turbine waste heat is conducted | |
CH318983A (en) | Procedure for starting up a steam power plant | |
DE1011899B (en) | Method for heating a multi-stage turbine system |