DE819986C - Process for the extraction and extraction of overburden in opencast mining by means of a conveyor bridge - Google Patents

Process for the extraction and extraction of overburden in opencast mining by means of a conveyor bridge

Info

Publication number
DE819986C
DE819986C DEK1861A DEK0001861A DE819986C DE 819986 C DE819986 C DE 819986C DE K1861 A DEK1861 A DE K1861A DE K0001861 A DEK0001861 A DE K0001861A DE 819986 C DE819986 C DE 819986C
Authority
DE
Germany
Prior art keywords
overburden
extraction
excavator
grabs
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DEK1861A
Other languages
German (de)
Inventor
Hans Julius Klitzing
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DEK1861A priority Critical patent/DE819986C/en
Application granted granted Critical
Publication of DE819986C publication Critical patent/DE819986C/en
Expired legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G65/00Loading or unloading
    • B65G65/28Piling or unpiling loose materials in bulk, e.g. coal, manure, timber, not otherwise provided for

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Description

Verfahren zur Gewinnung und Förderung von Abraum im Tagebau mittels Förderbrücke Zusatz zum Patent 800 010 Die Erfindung betrifft eine weitere Ausbildung des Verfahrens zur Gewinnung und Förderung von Abraum im Tagebau von Braunkohle o. dgl. mittels den Tagebau üI,erspannender Förderbrücke, nach Patent 800 oil.Process for the extraction and promotion of overburden in open-cast mining by means of Conveyor bridge addition to patent 800 010 The invention relates to a further development the process for the extraction and extraction of overburden in open-cast lignite mining or the like. By means of the open pit mine, tensioning conveyor bridge, according to patent 800 oil.

Nach dem Hauptpatent sollen auf der Förderbrücke mehrere Baggergreifer längs verfahrbar sein, die hintereinander und nebeneinander angeordnet die gesamte Abbauböschung abbaggern und das Baggergut auf in der Förderbrücke befindliche Fördereinrichtungen aufgeben, die es zu den Ablagerungsstellen fördern. According to the main patent, several excavator grabs are to be placed on the conveyor bridge be longitudinally movable, arranged one behind the other and next to each other, the entire Dredge the excavation embankment and transfer the dredged material to the conveyor systems in the conveyor bridge give up that promote it to the deposition sites.

Gemäß diesem Verfahren besitzt die Abraumförderbrücke außer der Fahrbahn für die Baggergreifer noch die Fördereinrichtung zur Ablagerung der gewonnenen Klassen. Hierdurch wird das Brückengerüst erheblich belastet, was bei den großen Spannweiten, die bei einem tiefen Tagebau erforderlich sind, zu einem hohen Gesamtgewicht der Brücke führt. Hinzu kommt noch, daß beim Anheben der gefüllten Baggergreifer die Förderbrücke eine ruckartige Belastung erhält, was durch entsprechende Verstärkungen des Brückengerüstes berücksichtigt werden muß. According to this method, the overburden conveyor bridge has outside the carriageway for the excavator grab the conveyor for depositing the extracted classes. This puts considerable strain on the bridge structure, which is the case with the large spans, which are required in a deep open pit, result in a high total weight of the Bridge leads. In addition, when lifting the filled excavator grab, the Conveyor bridge receives a jerky load, which is achieved by appropriate reinforcements of the bridge framework must be taken into account.

Mit dem Verfahren nach der Erfindung sollen diese Nachteile dadurch vermieden werden, daß die Baggergreifer den Abraum ohne Umladung unmittelbar von der Gewinnungsstelle zur Halde fördern und dort verstürzen. Eine Erweiterung des Verfahrens besteht darin, daß zur Erzielung eines kontinuierlichen Betriebes der der Haldenkante zunächst angeordnete Baggergreifer die Haldenkrone beschickt, die nachfolgenden Baggergreifer im gleichen Abstand die Haldenböschung beschicken und der in,der Nähe der Deckgebirgsoberkante angeordnete Baggergreifer den Böschungsfuß anschüttet. With the method according to the invention, these disadvantages are thereby addressed it is avoided that the excavator grab the overburden without reloading directly from from the extraction point to the dump and topple over there. An extension of the The method is that to achieve continuous operation of the The excavator grabs arranged next to the edge of the dump create the top of the dump loaded, the following excavator grabs feed the slope embankment at the same distance and the excavator grab, which is arranged in the vicinity of the upper edge of the overburden, the base of the embankment pours.

Die Rückführung der entleerten Baggergreifer kann so erfolgen, daß sie von der Ausschüttstelle zu der in annähernd gleicher Höhe gelagerten Gewinnungsstelle des Deckgebirges fahren. Zur Aufrechterhaltung eines kontinuierlichen Betriebes sind die Fahrbahnen für die Hin- und Rückfahrt der Baggergreifer durch Spitzkehren miteinander verbunden.The return of the emptied excavator grab can be done so that it from the distribution point to the extraction point stored in approximately the same amount drive the overburden. To maintain continuous operation are the lanes for the outward and return journey of the excavator grabs through switchbacks connected with each other.

Mit der Erfindung soll eine wesentliche Entlastung des Brückengerüstes durch Wegfall der Fördereinrichtung erreicht werden. Ein weiterer Vorteil der Erfindung besteht darin, daß die zeitraubende Hubarbeit für die Baggergreifer in Wegfall kommt und daß der Abraum auf dem kürzesten Wege von der Gewinnungs- zur Ablagerungsstelle ohne Umladung gefördert wird. The invention is intended to significantly reduce the load on the bridge structure can be achieved by eliminating the conveyor. Another advantage of the invention is that the time-consuming lifting work for the excavator grabs is eliminated and that the overburden takes the shortest route from the extraction point to the depository is promoted without reloading.

Die Erfindung ist in der Zeichnung in einem Ausführungsbeispiel dargestellt. The invention is shown in the drawing in an exemplary embodiment.

Abb. I zeigt eine Abraumförderbrücke in einem tiefen Tagebau in Seitenansicht und Abb. 2 eine Draufsicht auf die Fahrbahn für die Baggergreifer. über dem Kohlenflöz a befindet sich das Deckgebirge b mit großer Mächtigkeit. Die Tagebaugrube c wird von der Förderbrücke d überbrückt, deren eines Fahrwerk dl auf der Deckgebirgsseite und deren anderes Fahrwerk d2 auf ,der Halde e verfahrbar ist. Fig. I shows an overburden conveyor bridge in a deep open pit in a side view and Fig. 2 is a plan view of the track for the excavator grabs. above the coal seam a is the overburden b with great thickness. The open pit c will bridged by the conveyor bridge d, one of which is undercarriage dl on the overburden side and the other chassis d2 on, the dump e can be moved.

Auf der Förderbrücke d sind mehrere Baggergreifer fl, 2, 3, 4, /5, f6 verfahrbar angeordnet. Sie dienen zur Abbaggerung des Deckgebirges b und sind erfindungsgemäß im Ausmaß der Tagebaugrube c auf den Fahrbahnen n und o verfahrbar, so daß sie die gebaggerten Massen unmittelbar von der Gewinnungsstelle zur Ablagerungsstelle auf die Halde e fördern können. Several excavator grabs fl, 2, 3, 4, / 5, f6 arranged to be movable. They are used to excavate the overburden b and are according to the invention movable to the extent of the open pit c on the lanes n and o, so that they can take the dredged masses directly from the extraction point to the deposition site can promote to the stockpile e.

Die Ablagerung der gewonnenen Massen geht erfindungsgemäß so vor sich, daß der am Böschungsfuß des Deckgebirges b arbeitende Baggergreifer fl entsprechend dem angedeuteten Förderweg die gebaggerten Massen auf der Haldenkrone verstürzt. According to the invention, this is how the masses obtained are deposited that the excavator grapple fl working at the base of the overburden b accordingly The excavated masses collapsed on the top of the dump along the indicated conveying path.

Der nachfolgende Baggergreifer 2 beschickt den darunterliegenden Abschnitt der Haldenböschung, desgleichen die Baggergreifer f3, 4 und 5, während der Baggergreifer /5 den Haldenfuß anschüttet. Die Laufkatzen m der Baggergreifer fl bis 6 verfahren hierbei auf der in der Brücke d angeordneten Fahrbahn n und werden mittels ,der Spitzkehren p auf die Fahrbahn o zur Rückfahrt geleitet. Auf der Gewinnungsseite befinden sich ebenfalls beide Fahrbahnen o, n verbindende Spitzkehren q, mittels deren die Laufkatzen m wieder zu der Fahrbahn n geleitet werden. Die hintereinander angeordneten einzelnen Baggergreifer fl bis 6 können auf diese Weise im kontinuierlichen Betrieb die Gewinnungs-, Förderungs- und Ablagerungsarbeit leisten.The following excavator grab 2 feeds the section below the dump embankment, as well as the excavator grabs f3, 4 and 5, while the excavator grabs / 5 fills the stockpile base. Move the trolleys m of the excavator grabs fl to 6 here on the lane n arranged in the bridge d and are by means of, the Switchbacks p on the lane o for the return trip. On the extraction side there are also both lanes o, n connecting switchbacks q, by means whose trolleys m are guided back to the lane n. The one behind the other arranged individual excavator grabs fl to 6 can in this way in continuous Operation to carry out the extraction, extraction and deposit work.

PATENTANSPROCHE: I. Verfahren zur Gewinnung und Förderung von Abraum im Tagebau von Braunkohle o. dgl. mittels dem Tagebau überspannender Förderbrücke, nach Patent 8oo 010, dadurch gekennzeichnet, daß die Baggergreifer (/l bis 6) den Abraum ohne Umladung unmittelbar von der Gewinnungsstelle zur Halde (e) fördern und dort verstürzen. PATENT CLAIM: I. Process for the extraction and extraction of overburden in opencast mining of lignite or the like by means of a conveyor bridge spanning opencast mining, according to patent 8oo 010, characterized in that the excavator grabs (/ l to 6) the Convey overburden directly from the extraction point to the heap (s) without reloading and fall there.

Claims (1)

2. Verfahren zur Gewinnung und Förderung von Abraum nach Anspruch I, dadurch gekennzeichnet, daß der der Halde (e) zunächst angeordnete Baggergreifer ( jl ) die Haldenkrone beschickt, die nachfolgenden Baggergreifer (j2 bis /5) in gleichen Abständen die Haldenböschung beschicken und der in puder Nähe der Deckgebirgsoberkante angeordnete Baggergreifer (6) den Böschungsfuß anschüttet. 2. A method for extracting and promoting overburden according to claim I, characterized in that the excavator grab initially arranged in the stockpile (s) (jl) the top of the stockpile is loaded, the following excavator grabs (j2 to / 5) in the slope embankment and the one powder near the top of the overburden arranged excavator grapple (6) fills the embankment base. 3. Verfahren zur Gewinnung und Förderung von Abraum nach Anspruch 2, dadurch gekennzeichnet, daß die entleerten Baggergreifer (fl bis f6) zu der in annähernd gleicher Höhe gelegenen Gewinnungsstelle des Deckgebirges (b) fahren. 3. A method for extracting and promoting overburden according to claim 2, characterized in that the emptied excavator grabs (fl to f6) to the in Drive the extraction point of the overburden (b) at approximately the same height. 4. Abraumförderbrücke zur Ausführung des Verfahrens nach Anspruch I, 2 oder 3, dadurch gekennzeichnet, daß die Fahrbahnen (n, o) für die Hin- und Rückfahrt der Baggergreifer (fl bis 6) durch Spitzkehren miteinander verbunden sind. 4. overburden conveyor bridge for performing the method according to claim I, 2 or 3, characterized in that the lanes (n, o) for the outward and Return of the excavator grabs (fl to 6) are connected to each other by hairpin bends. Angezogene Druckschriften: Deutsche Patentschrift Nr. 645 288; Zeitschrift des Vereins Deutscher Ingenieure, 1928, Seite 737 bis 742. Cited publications: German Patent No. 645 288; magazine of the Association of German Engineers, 1928, pages 737 to 742.
DEK1861A 1950-02-18 1950-02-18 Process for the extraction and extraction of overburden in opencast mining by means of a conveyor bridge Expired DE819986C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DEK1861A DE819986C (en) 1950-02-18 1950-02-18 Process for the extraction and extraction of overburden in opencast mining by means of a conveyor bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DEK1861A DE819986C (en) 1950-02-18 1950-02-18 Process for the extraction and extraction of overburden in opencast mining by means of a conveyor bridge

Publications (1)

Publication Number Publication Date
DE819986C true DE819986C (en) 1951-11-05

Family

ID=7209116

Family Applications (1)

Application Number Title Priority Date Filing Date
DEK1861A Expired DE819986C (en) 1950-02-18 1950-02-18 Process for the extraction and extraction of overburden in opencast mining by means of a conveyor bridge

Country Status (1)

Country Link
DE (1) DE819986C (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE645288C (en) * 1932-11-22 1937-05-26 Fritz Tresser Dipl Ing Cable excavator with towers that can be moved on the upper edge of the embankment of a mine

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE645288C (en) * 1932-11-22 1937-05-26 Fritz Tresser Dipl Ing Cable excavator with towers that can be moved on the upper edge of the embankment of a mine

Similar Documents

Publication Publication Date Title
DE10793425T1 (en) MAKING A SHEEP FOR A UNDERGROUND DAY
DE3246544C2 (en)
DE502034C (en) Equipment for the extraction, conveyance and relocation of overburden in opencast mines
DE819986C (en) Process for the extraction and extraction of overburden in opencast mining by means of a conveyor bridge
DE574718C (en) Overburden conveyor bridge spanning the opencast mining of lignite or the like
DE456347C (en) Bridge method with bucket wheel excavator for lignite mining
DE941362C (en) Extraction of lignite lozenges using cable excavators
DE562878C (en) Open pit mine for the extraction and relocation of mountain layers
DE693793C (en) Process and device for the removal of powerful rock layers
DE644444C (en) Plant for the extraction and conveyance of overburden in opencast mines
DE572012C (en) Settling system
DE800010C (en) Process and device for the operation of conveyor bridges for lignite opencast mines
DE944362C (en) Procedure for relocating the overburden, which has been extracted in stages, in open-cast lignite mining
DE348373C (en) Mining process for the extraction of lignite or the like in open-cast mining
DE504494C (en) Process for extracting coal in open-cast mines
DE419756C (en) Procedure for shoveling heaps
AT115754B (en) Plant for the deposition of the overburden obtained from opencast mines on the overburden side.
DE424943C (en) Process for depositing the excavated material by means of an excavation conveyor bridge
DE409460C (en) Method and device for material movement in opencast mines
DE719105C (en) Plant for the extraction and conveyance of overburden in opencast mines
DE371594C (en) Device for loosening, loading and conveying waste material
DD154352A5 (en) BOESCHUNGSBRUECKE
DE424926C (en) Procedure for clearing the overburden in lignite opencast mines
DE971749C (en) Trench bunker open on one side with movable emptying device assigned to the open side of the trench
DE611157C (en) Method for opening up opencast mines using a waste extraction and conveyor system