DE3242968A1 - Feed water control and vaporiser protection - Google Patents
Feed water control and vaporiser protectionInfo
- Publication number
- DE3242968A1 DE3242968A1 DE19823242968 DE3242968A DE3242968A1 DE 3242968 A1 DE3242968 A1 DE 3242968A1 DE 19823242968 DE19823242968 DE 19823242968 DE 3242968 A DE3242968 A DE 3242968A DE 3242968 A1 DE3242968 A1 DE 3242968A1
- Authority
- DE
- Germany
- Prior art keywords
- feed water
- water supply
- combustion chamber
- regulating
- supply
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F22—STEAM GENERATION
- F22D—PREHEATING, OR ACCUMULATING PREHEATED, FEED-WATER FOR STEAM GENERATION; FEED-WATER SUPPLY FOR STEAM GENERATION; CONTROLLING WATER LEVEL FOR STEAM GENERATION; AUXILIARY DEVICES FOR PROMOTING WATER CIRCULATION WITHIN STEAM BOILERS
- F22D5/00—Controlling water feed or water level; Automatic water feeding or water-level regulators
- F22D5/26—Automatic feed-control systems
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Control Of Steam Boilers And Waste-Gas Boilers (AREA)
Abstract
Description
SPEISEWASSERREGELUNG UND VERDAMPFERSCHUTZFEED WATER CONTROL AND EVAPORATOR PROTECTION
Die Erfindung betrifft ein Verfahren zur Regelung der Speisewasserzufuhr von Dampferzeugern bzw. zu deren Notabschaltung.The invention relates to a method for regulating the feed water supply of steam generators or their emergency shutdown.
Bei den bisher bekannten Zwangdurchlaufdampferzeugern wurde die Durchströmung der arbeitsmittelführenden- Teile nicht automatisch, sondern durch das Betriebspersonal, unter Benutzung von optischen oder akustischen Signalen zur Feststellung einer Überschreitung zulässiger Temperaturen nach den Verdampferwänden, überwacht. Örtliche Übertemperaturen werden in den Verdampferwänden nicht erfaßt und auch nicht Übertemperaturen beim Ans taue des Druckes wegen Strömungsstagnation.In the previously known once-through steam generators, the flow through the work equipment-carrying parts not automatically, but by the operating staff, using optical or acoustic signals to determine if the limit has been exceeded permissible temperatures after the evaporator walls, monitored. Local excess temperatures are not detected in the evaporator walls and neither are excess temperatures during The pressure was thawed because of flow stagnation.
Nachteilig ist es bei einer derartigen Überwachung, daß zwischen der Feststellung einer Störung und der Einleitung von behebenden bzw. schützenden Maßnahmen viel Zeit verloren geht bzw. die Störung nicht erkannt wird und dadurch erhebliche Schäden an den Dampferzeugern verursacht werden können.It is disadvantageous in such a monitoring that between the Detection of a malfunction and the initiation of corrective or protective measures a lot of time is lost or the fault is not recognized and therefore considerable Damage to the steam generator can be caused.
Bei Naturumlauf-Dampferzeugern erfolgt zwar im allgemeinen eine Notabschaltung bei Unterschreiten eines minimalen Wasserstandes. Kritische Übertemperaturen, wie sie im Festdruckbetrieb bei Laststeigerungen durch Druckabsenkung und dadurch vermindertem Umlauf und eventuelle Filmverdampfung bei gleichzeitig überhöhter Feuerleistung auftreten können, werden dadurch nicht vermieden. Ähnliches gilt für Dampferzeuger mit Umwälzung.In the case of natural circulation steam generators, there is generally an emergency shutdown when the water level falls below a minimum. Critical overtemperature, such as it in fixed pressure operation with load increases due to pressure reduction and thereby reduced Circulation and possible film evaporation with simultaneously excessive fire output can occur are not avoided. The same applies to steam generators with upheaval.
Der Erfindung liegt die Aufgabe zugrunde, ein Verfahren zu schaffen, bei dem das Auftreten von Betriebsstörungen schnellstmöglich erfaßt und Sofortmaßnahmen zu ihrer Beseitigung bzw. zum Schutz des Dampferzeugers eingeleitet werden können.The invention is based on the object of creating a method in which the occurrence of operational disruptions is recorded as quickly as possible and immediate measures are taken can be initiated to eliminate them or to protect the steam generator.
Diese Aufgabe wird dadurch gelöst, daß man a) an mehreren strömungsseitig hintereinanderliegenden Stellen die Wandtemperatur der Brennkammerrohre mißtv die Meßwerte mit einem vorgegebenen Temperaturprofil vergleicht und bei einem Abweichen der Temperaturen von dem vorgegebenen Temperaturprofil die Speisewasserzufuhr verändert bzw. bei Überschreiten vorgegebener Maximaltemperaturen den Dampferzeuger abschaltet, b) Wandtemperaturdifferenzen, die ein Maß für die Wärmestromdichte darstellen, zur Regelung der Speisewasserzufuhr verwendet, c) aus den Temperaturdifferenzmessungen die Wärmestromdichte an verschiedenen Stellen der Brennkammer ermittelt, daraus die gesamte Wärmezufuhr zur Brennkammer und mit der Enthalpie des Speisewassers vor bzw. nach dem Economizer den Sollwert für den Speisewasserstrom berechnet, d) die Wärmezufuhr zur Brennkammer aus der Brennstoffzufuhr errechnet.This object is achieved by a) at several on the flow side one behind the other, the wall temperature of the combustion chamber tubes measures the Compares measured values with a given temperature profile and if they deviate the temperatures of the predetermined temperature profile changes the feed water supply or switches off the steam generator when the specified maximum temperatures are exceeded, b) Wall temperature differences, which represent a measure of the heat flux density, for Control of the feed water supply used, c) from the temperature difference measurements the heat flux density at various points in the combustion chamber is determined from this the entire heat supply to the combustion chamber and with the enthalpy of the feed water the setpoint for the feed water flow is calculated before or after the economizer, d) the heat supply to the combustion chamber is calculated from the fuel supply.
Die erfindungsgemäßen Maßnahmen haben gegenüber dem bekannten Stand der Technik den Vorteil, daß auftretende Störungen ohne Zeitverlust erfaßt werden und ihnen entgegengewirkt werden kann und dadurch das Risiko eines Schadens am Dampferzeuger weitgehend verringert wird.The measures according to the invention have compared to the known prior art technology has the advantage that occurring faults can be detected without loss of time and they can be counteracted and thereby the risk of damage to the steam generator is largely reduced.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19823242968 DE3242968C2 (en) | 1982-11-20 | 1982-11-20 | Procedure for regulating the feed water supply to steam generators |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19823242968 DE3242968C2 (en) | 1982-11-20 | 1982-11-20 | Procedure for regulating the feed water supply to steam generators |
Publications (2)
Publication Number | Publication Date |
---|---|
DE3242968A1 true DE3242968A1 (en) | 1984-01-12 |
DE3242968C2 DE3242968C2 (en) | 1985-11-14 |
Family
ID=6178587
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19823242968 Expired DE3242968C2 (en) | 1982-11-20 | 1982-11-20 | Procedure for regulating the feed water supply to steam generators |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE3242968C2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0439765A1 (en) * | 1990-01-31 | 1991-08-07 | Siemens Aktiengesellschaft | Steam generator |
WO1993022599A1 (en) * | 1992-05-04 | 1993-11-11 | Siemens Aktiengesellschaft | Forced-flow steam generator |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB926949A (en) * | 1961-02-15 | 1963-05-22 | Sulzer Ag | Regulation of forced-flow once-through steam generators |
-
1982
- 1982-11-20 DE DE19823242968 patent/DE3242968C2/en not_active Expired
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB926949A (en) * | 1961-02-15 | 1963-05-22 | Sulzer Ag | Regulation of forced-flow once-through steam generators |
Non-Patent Citations (1)
Title |
---|
DE-Z.: BWK, 1974, Nr.5, S.202-207 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0439765A1 (en) * | 1990-01-31 | 1991-08-07 | Siemens Aktiengesellschaft | Steam generator |
US5056468A (en) * | 1990-01-31 | 1991-10-15 | Siemens Aktiengesellschaft | Steam generator |
WO1993022599A1 (en) * | 1992-05-04 | 1993-11-11 | Siemens Aktiengesellschaft | Forced-flow steam generator |
US5529021A (en) * | 1992-05-04 | 1996-06-25 | Siemens Aktiengesellschaft | Forced once-through steam generator |
Also Published As
Publication number | Publication date |
---|---|
DE3242968C2 (en) | 1985-11-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2359058B1 (en) | Method of operating a waste heat steam generator | |
EP2700075A1 (en) | Method for conditioning a power-generating circulatory system of a power plant | |
DE102011076968A1 (en) | Method for operating a circulation heat recovery steam generator | |
WO2006005708A1 (en) | Process for operating a continuous steam generator | |
DE3523147A1 (en) | METHOD AND ARRANGEMENT FOR PROTECTING PUMP SYSTEMS | |
DE3333907A1 (en) | METHOD AND DEVICE FOR DEFROSTING HEAT PUMPS | |
DE3242968A1 (en) | Feed water control and vaporiser protection | |
WO2016071204A1 (en) | Control method for operating a heat recovery steam generator | |
EP2360545A1 (en) | Method for regulating a valve | |
EP0180093B1 (en) | Thermal power plant | |
EP0843075B1 (en) | Method and apparatus for controlling turbomachinery | |
DE1297624B (en) | Steam power plant | |
DE2700168C3 (en) | Device for the removal of decay heat in a steam power plant heated with nuclear energy | |
EP1365110A1 (en) | Process and apparatus for operating a steam power plant, especially in a partial load range | |
DE2621340B2 (en) | Heat recovery steam generator | |
DE3303548C3 (en) | Method for operating a once-through steam generator | |
DE3401948C2 (en) | Procedure for operating steam generators | |
DE3243578C2 (en) | ||
EP3467378B1 (en) | Waste heat installation for hot water generation and method for operating same | |
EP2772686A1 (en) | Method and device for operating a steam generator in a combustion plant | |
DE2360293A1 (en) | Emergency cooling system - for nuclear reactor based on shunt permanently across secondary coolant circuit | |
EP1492222A2 (en) | A method and apparatus for detecting the decoupling of the load between an electric energy generating rotary machine and a supply network coupled to the rotary machine to supply current | |
DE3301895A1 (en) | Method for operating steam generators | |
DE10312667A1 (en) | Method for monitoring a boiler system for water and device for carrying out the method | |
DE2434528C3 (en) | Nuclear power plant |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
OAV | Applicant agreed to the publication of the unexamined application as to paragraph 31 lit. 2 z1 | ||
OP8 | Request for examination as to paragraph 44 patent law | ||
D2 | Grant after examination | ||
8364 | No opposition during term of opposition | ||
8327 | Change in the person/name/address of the patent owner |
Owner name: LEITHNER, REINHARD, PROF. DR.TECHN., 3300 BRAUNSCH |
|
8339 | Ceased/non-payment of the annual fee |