DE29702719U1 - Device for erecting dams - Google Patents

Device for erecting dams

Info

Publication number
DE29702719U1
DE29702719U1 DE29702719U DE29702719U DE29702719U1 DE 29702719 U1 DE29702719 U1 DE 29702719U1 DE 29702719 U DE29702719 U DE 29702719U DE 29702719 U DE29702719 U DE 29702719U DE 29702719 U1 DE29702719 U1 DE 29702719U1
Authority
DE
Germany
Prior art keywords
wall elements
sleepers
rails
rail
transport
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
DE29702719U
Other languages
German (de)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DE29702719U priority Critical patent/DE29702719U1/en
Publication of DE29702719U1 publication Critical patent/DE29702719U1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B37/00Making, maintaining, renewing, or taking-up the ballastway or the track, not provided for in a single one of groups E01B27/00 - E01B35/00
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Cylinder Crankcases Of Internal Combustion Engines (AREA)

Description

• · · I· · I

Vorrichtung zum Errichten von DämmenDevice for building dams

, Die Erfindung betrifft eine Vorrichtung zur Errichtung von, The invention relates to a device for the construction of

Dämmen und findet insbesondere beim Bau von Bahnkörpern oder Trassen Anwendung.Dams and is particularly used in the construction of railway tracks or routes.

Es sind Verfahren und Vorrichtungen zum Errichten von Dämmen bekannt. So wird in der RU 20 22 105 ein Verfahren zum Bau von Dämmen beschrieben, bei dem in einem ersten Verfahrensschritt ein Transportgleis verlegt wird, das Gleisbett in einem zweiten Verfahrensschritt mit Dammbauboden {Sand, Schotter) aufgefüllt wird, danach das Transportgleis aufgenommen und der Damm planiert wird. Diese Verfahrensschritte werden solange wiederholt, bis die notwendige Höhe des Dammes erreicht ist.Methods and devices for building dams are known. For example, RU 20 22 105 describes a method for building dams in which a transport track is laid in a first step, the track bed is filled with dam construction soil (sand, gravel) in a second step, then the transport track is removed and the dam is leveled. These steps are repeated until the required height of the dam is reached.

Der Nachteil dieser Lösung besteht darin, daß die Menge und damit die Höhe des auszubringenden Dammbaubodens begrenzt ist, denn die Schienen dürfen nicht mit Dammbauboden bedeckt werden. Sie müssen weiter befahrbar bleiben.The disadvantage of this solution is that the amount and therefore the height of the dam construction soil that can be applied is limited, because the rails must not be covered with dam construction soil. They must remain passable.

Aufgabe der Erfindung ist es, eine Möglichkeit zu schaffen, die Schienen vor aus Schienenfahrzeugen ausgebrachten größeren Mengen Dammbaubodens zu schützen.The object of the invention is to create a possibility to protect the rails from large quantities of embankment soil discharged from rail vehicles.

Diese erfindungsgemäSe Aufgabe wird mit den kennzeichnenden Merkmalen des ersten Anspruchs gelöst. Vorteilhafte Ausgestaltungen sind Gegenstand der Unteransprüche.This object according to the invention is achieved with the characterizing features of the first claim. Advantageous embodiments are the subject of the subclaims.

In dem bei verlegten Transportgleisen rechts und links von jeder Schiene im wesentlichen senkrecht stehende Wandelemente angeordnet werden, und der Dammbauboden zwischen den inneren Wändelementen der ein Gleis bildenden Schienen und außerhalb der äußeren Wandelemente ausgebracht wird, wird verhindert, daß bei größeren Mengen ausgebrachten Dammbaubodens dieser auf die Schienen fällt.When transport tracks are laid, essentially vertical wall elements are arranged to the right and left of each rail, and the dam construction soil is placed between the inner wall elements of the rails forming a track and outside the outer wall elements, this prevents large quantities of dam construction soil from falling onto the rails.

1" ' 'IaI1JiP11: &igr;" I im h'" ' 1Jf " '' I' '«'!!''"''!'!i'lto "'' ' if " ! ■ ■ 1I &Igr;"1'1 &Iacgr; ' ■ '11I1 "ff *"!''!f ' |l '"Ti1V '■ '"* &Igr;1!!111 &eeacgr;' " ' '■ i ' 1 "''IaI 1 JiP 11: &igr;" I im h'"' 1 Jf "''I''«'!!''"''!'!i'lto"''' if " ! ■ ■ 1 I &Igr;" 1 ' 1 &Iacgr;' ■ ' 11 I 1 "ff *"!''!f ' |l '"Ti 1 V '■ '"* &Igr; 1 !! 111 &eeacgr;'"''■ i '

Die Wandelemente werden vorteilhafterweise auf den Schwellen angeordnet, wobei sie in der im wesentlichen senkrecht stehenden Position auf diesen arretierbar sind. Weiterhin sieht die Erfindung in einer Ausführungsform vor, daß die Wandelemente vorzugsweise im Bereich zwischen den Schwellen Ausschnitte aufweisen, deren Höhe so bemessen ist, daß durch die Ausschnitte dringender Dammbauboden bis an den jeweiligen Schienenfuß gelangt, deren Kopf jedoch nicht verdeckt.The wall elements are advantageously arranged on the sleepers, whereby they can be locked in the essentially vertical position. Furthermore, in one embodiment, the invention provides that the wall elements preferably have cutouts in the area between the sleepers, the height of which is such that dam construction soil that penetrates through the cutouts reaches the respective rail foot, but does not cover the head.

Die Wandelemente sind mit den Schwellen entweder lösbar verbunden oder sie sind seitlich von der jeweiligen Schiene abklappbar angeordnet. Dadurch wird der Vorteil des Stapeltransportes der Transportgleise zur Baustelle und von der Baustelle weg weiterhin gewährleistet.The wall elements are either detachably connected to the sleepers or they are arranged so that they can be folded down to the side of the respective rail. This ensures that the advantage of stacking the transport tracks to and from the construction site is still guaranteed.

1515

Die Höhe der Wandelemente innerhalb des Transportgleises ist so bemessen, daß es zu keiner Kollision mit den Achsen und dem Wagenunterbau kommt. Die mögliche Höhe der äußeren Wandelemente wird von deren Anordnung auf den Schwellen bestimmt. Bei einer Anordnung im Bereich unterhalb des Wagens ist die Höhe durch die Bodenfreiheit des Wagens begrenzt, bei einer Anordnung seitlich vom Wagen kann sie größer gewählt werden.The height of the wall elements within the transport track is dimensioned so that there is no collision with the axles and the wagon substructure. The possible height of the outer wall elements is determined by their arrangement on the sleepers. If arranged in the area below the wagon, the height is limited by the ground clearance of the wagon; if arranged to the side of the wagon, it can be chosen to be higher.

Die Erfindung wird anhand der Zeichnung näher erläutert. Es zeigenThe invention is explained in more detail with reference to the drawing.

Fig. 1 eine Schwellenanordnung mit darauf befindlichenFig. 1 shows a sleeper arrangement with

Wandelementen und
30
Wall elements and
30

Fig. 2 einen Querschnitt des Transportgleises.Fig. 2 a cross section of the transport track.

In Fig. 1 ist ein Transportgleis bestehend aus Schwellen und Schienen 2 dargestellt bei dem beidseitig jeder Schiene 2 nahezu senkrecht und in dieser Position arretierbare Wandelemente 3 angeordnet sind. Diese Wandelemente 3 sind im Bereich zwischen den Schwellen 1In Fig. 1, a transport track consisting of sleepers and rails 2 is shown, in which wall elements 3 are arranged almost vertically on both sides of each rail 2 and can be locked in this position. These wall elements 3 are in the area between the sleepers 1

il - -il - -

&idiagr;&iacgr;&idiagr;&idiagr;&Igr;&Mgr; &ohacgr;&iacgr;&igr;&igr;^&Lgr;^&Agr;&iacgr;&idiagr;&Agr;'/^^,^,.,; ■-: ,*««.«&idiagr;&iacgr;&idiagr;&Igr;&Mgr;&ohacgr;&iacgr;&igr;&igr;^&Lgr;^&Agr;&iacgr;&idiagr;&Agr;'/^^,^,.,; ■-: ,*««.«

mit Ausschnitten 4 versehen, die so bemessen sind, daß der zwischen den inneren Wandelementen 3.1 der ein Gleis bildenden Schienen 2 und außerhalb der äußeren Wandelemente 3.2 ausgebrachte Dammbauboden bis an den jeweiligen Schienenfuß gelangt, den Schienenkopf jedoch nicht bedecken kann.provided with cutouts 4 which are dimensioned such that the embankment soil placed between the inner wall elements 3.1 of the rails 2 forming a track and outside the outer wall elements 3.2 reaches the respective rail foot, but cannot cover the rail head.

In Fig. 2 ist rechts die erfindungsgemäße Vorrichtung mit Wandelementen 3.1 und 3.2 dargestellt, auf der linken Seite das Ausbringen von Dammbauboden in herkömmlicher Art und Weise. Der rechte Teil der Fig. 2 zeigt deutlich, daß mit der erfindungsgemäßen Vorrichtung wesentlich mehr Dammbauboden in einem Arbeitsgang ausgebracht werden kann, ohne daß die Befahrbarkeit der Schienen eingeschränkt wird.In Fig. 2, the device according to the invention is shown on the right with wall elements 3.1 and 3.2, and on the left the application of dam construction soil in the conventional manner. The right part of Fig. 2 clearly shows that with the device according to the invention, significantly more dam construction soil can be applied in one operation without restricting the ability of the rails to be driven on.

Die Höhe der Wandelemente 3.1 innerhalb des Transportgleises ist so bemessen, daß es zu keiner Kollision mit den Achsen und dem Wagenunterbau kommt. Die mögliche Höhe der äußeren Wandelemente 3.2 wird von deren Anordnung auf den Schwellen bestimmt. Bei einer Anordnung im Bereich unterhalb des Wagens ist die Höhe durch die Bodenfreiheit des Wagens begrenzt, bei einer Anordnung seitlich vom Wagen kann sie größer gewählt werden.The height of the wall elements 3.1 within the transport track is dimensioned so that there is no collision with the axles and the wagon substructure. The possible height of the outer wall elements 3.2 is determined by their arrangement on the sleepers. If arranged in the area below the wagon, the height is limited by the ground clearance of the wagon; if arranged to the side of the wagon, it can be chosen to be higher.

2525

Um zu gewährleisten, daß die Transportgleise nach dem Abbau stapelbar bleiben, sieht die Erfindung vor, daß die Wandelemente 3 seitlich von der jeweiligen Schiene 2 abklappbar oder lösbar mit den Schwellen verbunden sind.In order to ensure that the transport tracks remain stackable after dismantling, the invention provides that the wall elements 3 can be folded down laterally from the respective rail 2 or are detachably connected to the sleepers.

Das Abklappen oder Lösen der Wandelemente 3 erfolgt beim Aufnehmen des Transportgleises.The wall elements 3 are folded down or released when the transport track is picked up.

&igr; &Ggr; &iacgr;|1· ;'&pgr;,",&igr;·« .,i.f'iui &igr;&Ggr;&iacgr;|1·;'&pgr;,"&igr;·« .,i.f'iui

Claims (4)

SchutzansprücheProtection claims 1. Vorrichtung zum Errichten von Dämmen bestehend aus einem Transportgleis, von dem aus Transportwagen Dammbauboden ausgebracht wird, dadurch gekennzeichnet, daß1. Device for building dams consisting of a transport track from which dam construction soil is spread from transport wagons, characterized in that bei verlegten Transportgleisen rechts und links von jeder Schiene (2) im wesentlichen senkrecht stehende Wandelemente (3) angeordnet sind, die verhindern, daß der zwischen den inneren Wandelementen 3.1 der ein Gleis bildenden Schienen 2 und außerhalb der äußeren Wandelemente 3.2 ausgebrachte Dammbauboden auf die Schienen (2) fällt.When transport tracks are laid, essentially vertical wall elements (3) are arranged to the right and left of each rail (2), which prevent the dam construction soil laid out between the inner wall elements 3.1 of the rails 2 forming a track and outside the outer wall elements 3.2 from falling onto the rails (2). 2. Vorrichtung nach Anspruch 1, dadurch gekennzeichnet, daß2. Device according to claim 1, characterized in that die Wandelemente (3) im Bereich zwischen den Schwellen (1) Ausschnitte (4) aufweisen, die so bemessen sind, daß durch die Ausschnitte (4) dringender Dammbauboden bis an den jeweiligen Schienenfuß gelangt, den Schienenkopf jedoch nicht verdecken kann.the wall elements (3) in the area between the sleepers (1) have cutouts (4) which are dimensioned such that penetrating embankment soil can reach the respective rail foot through the cutouts (4) but cannot cover the rail head. 3. Vorrichtung nach Anspruch 1, dadurch gekennzeichnet, daß die Wandelemente {3) in die Schwellen (1) einsteckbar sind.3. Device according to claim 1, characterized in that the wall elements (3) can be inserted into the sleepers (1). 4. Vorrichtung nach Anspruch 1,4. Device according to claim 1, dadurch gekennzeichnet, daßcharacterized in that 3030 die Wandelemente {3} derart mit den Schwellen (1) verbunden sind, daß sie in nahezu senkrechter Position arretierbar, ansonsten jeweils seitlich von der jeweiligen Schiene (2) abklappbar sind.the wall elements {3} are connected to the sleepers (1) in such a way that they can be locked in an almost vertical position, otherwise they can be folded down to the side from the respective rail (2). 3535
DE29702719U 1996-12-05 1997-02-06 Device for erecting dams Expired - Lifetime DE29702719U1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE29702719U DE29702719U1 (en) 1996-12-05 1997-02-06 Device for erecting dams

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE29621866 1996-12-05
DE29702719U DE29702719U1 (en) 1996-12-05 1997-02-06 Device for erecting dams

Publications (1)

Publication Number Publication Date
DE29702719U1 true DE29702719U1 (en) 1997-04-30

Family

ID=8033396

Family Applications (1)

Application Number Title Priority Date Filing Date
DE29702719U Expired - Lifetime DE29702719U1 (en) 1996-12-05 1997-02-06 Device for erecting dams

Country Status (1)

Country Link
DE (1) DE29702719U1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19724785A1 (en) * 1997-06-05 1998-12-17 Felix Kunzewitsch Method for laying transport rail tracks on compressed bed of sand and gravel
DE10005677C2 (en) * 2000-02-07 2003-08-14 Felix Kunzewitsch Method and device for building routes and dams

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19724785A1 (en) * 1997-06-05 1998-12-17 Felix Kunzewitsch Method for laying transport rail tracks on compressed bed of sand and gravel
DE19724785C2 (en) * 1997-06-05 1999-10-21 Felix Kunzewitsch Method and device for building dams and routes
DE10005677C2 (en) * 2000-02-07 2003-08-14 Felix Kunzewitsch Method and device for building routes and dams

Similar Documents

Publication Publication Date Title
DE2731228C2 (en) Concrete shaped stone for the production of a retaining wall and retaining wall made of such shaped stones
CH618226A5 (en)
DE2945767C2 (en)
DE8129931U1 (en) KIT FOR THE PRODUCTION OF NOISE AND VISUAL PROTECTION WALLS FROM PRE-FABRICATED COMPONENTS
DE29702719U1 (en) Device for erecting dams
DE19706033C2 (en) Device for erecting dams
DE102007029928A1 (en) Filled or fillable vehicle restraint system for limiting roadways
DE102012009284B4 (en) Process for the rehabilitation of a solid road / solidified gravel railway
DE4439937A1 (en) Earth reinforcement honeycomb plate
CH641861A5 (en) Arrangement for re-constructing a boundary path next to the ballast bed of a railway embankment
DE202018004358U1 (en) Segment of an amphibious protection device
DE2308957A1 (en) CONCRETE SLEEPER BLOCK FOR A MOVABLE CRANE SECTION
DE19724785C2 (en) Method and device for building dams and routes
DE19706032C2 (en) Process for the construction of paved routes and device for this process
DE1970492U (en) EMBOSSING MAT FOR SECURING EARTH STRUCTURES.
DE19649985C2 (en) Procedure for the construction of dams
DE202023002316U1 (en) Concrete paving stone
DE19915751C2 (en) Mobile track tamping machine
DE9419755U1 (en) Angular post for a rail security fence
DE2231694A1 (en) RAMP OR BRIDGE CONSTRUCTION WITH GRID PLATES
DE1534522A1 (en) Railing for the barrier of roads, bridges and the like.
DE202021100592U9 (en) Drive-over locking device
DE1935531C (en) Track support plate
DE9115098U1 (en) Traffic island
DD260724A1 (en) DEVICE FOR IMPROVING STEEL PLATES

Legal Events

Date Code Title Description
R207 Utility model specification

Effective date: 19970612

R156 Lapse of ip right after 3 years

Effective date: 20010901